Upload
gavin-brown
View
223
Download
5
Tags:
Embed Size (px)
Citation preview
Status of CMS CSC upgrade in LS1
Present CSC Status
ME 4/2 project
ME 1/1 project
04/18/23 Petr Levchenko NEC 2013, Varna 1
CSC Upgrade
04/18/23 2Petr Levchenko NEC 2013, Varna
04/18/23 Petr Levchenko NEC 2013, Varna 3
Total weight : 12,500 tOverall diameter : 15 mOverall length : 21.6 mMagnetic field : 4 Tesla
6 layer multi-wire proportional chambers
Cathode Strip Chambers
Resistive Plate Chambers
MUONENDCAPS
Main goals of CSC Upgrade
Build , install and commossion72 ME4/2 chambers to complete the 4th station. For the moment YE3 disk uncompleted due to missing outer (1.2<η<1.8) ME4/2
Remove, refurbish, reinstall and commission 72 ME1/1 chambers (1.6<||<2.4)
Introduce into the DAQ optical readout electronics and increase number of readout channels (SLink)
Largely extent the LV and HV systems
04/18/23 Petr Levchenko NEC 2013, Varna 4
5
Schedule driven by YE+4 disk construction with all other activities requiring crane in the shadow (ME1/1 PP)
Present Status (Sep 04-Oct 11)
04/18/23 Petr Levchenko NEC 2013, Varna
Recent CMS View
04/18/23 Petr Levchenko NEC 2013, Varna 6
pa
ne
l s
tora
ge
Incoming parts
5m
Loadingarea20
m
Gas
Panel cleaning/gluing
Str
ip g
luin
g
25m
hand soldering Kit preparation
10m
10mL
on
g t
erm
gas
&
HVElectronics
assemblyFast site testing
10m 10m15m 15m
7m
6m
7mPacking
Chamber storage
area6m
C
ham
ber
rac
k
clean Lab 1 clean Lab 2 platform
• Incoming parts
• Kit preparation
• Panel bar gluing
• Wire wiring, gluing, soldering (Lab 1)
• Electrical components hand soldering
• Chamber assembly & test (Lab 2)
• Long term gas, HV tests
• Electronics assembly & Fast site test
• Final inspection packing, storing
Chamber production workflow
04/18/23 7Petr Levchenko NEC 2013, Varna
04/18/23Petr Levchenko NEC 2013, Varna 8
FR4 bar bonding
wire winding wire soldering
Wire pitch and tension HV testing
chamber testing chamber integration
components soldering
chamber assembly
chamber installation
ME4/2 schedule (original plan)
Production schedule A production rate of 1 chamber/week (7 working days) is our target
By February/March 2013 we hope to have built 31 chambers (5 already
on YE+3 disk, 2 more ready and 6 in the workflow at b904). The additional 36 chambers will be ready by March of 2014.
Note: plan to re-use on-chamber electronics from ME1/1 Our aim is to complete the project on time for installation during LS1,
assuming schedule for LS1 will not slip (starting on Nov 17).
1st endcap 2nd endcap
04/18/23 9Petr Levchenko NEC 2013, Varna
Achieved chamber production 1st
endcap (30 chambers)
10
Xm
as
brea
k
assuming a rate of 3.3 CSC/month
DONE
!
Not considering time for chamber long term HV training (8 weeks), electronics integration (2 days) and final testing (3-4 days)
04/18/23 Petr Levchenko NEC 2013, Varna
Chamber production chart 2nd endcap (36 chambers)
11
Rate = 4 CSC/month
ME4/2 chamber factory status: 89% of chambers now assembled
04/18/23 Petr Levchenko NEC 2013, Varna
ME4/2 Electronics Update
CSC
CFEBCFEBCFEB CFEB
ALCT1 of 24
CFEB
1 of 2
LVDBLV Distribution Board
FED Crate in USC551 of 5
1 of 5
Anode Front-end Board
Cathode Front-end Board
Anode LCT Board
MPC
DMB
TMB
DMB
TMB
DMB
TMB
DMB
TMB
DMB
TMB
DMB
TMB
DMB
TMB
DMB
TMB
DMB
TMB
CCBC
ONTROLLER
Peripheral Crate on iron disk
Slow Control
Trigger-Timing-Control
Muon Sector ReceiverLev-1 Trigger
Trig Motherboard
DAQ Motherboard
Clock Control Board DDU Board
Readout Data
RAT aux card (behind)
System Layout04/18/23 12Petr Levchenko NEC 2013, Varna
CSC ME4/2 project final remarks
The ME4/2 on-chamber and DAQ electronics partially come from the ME1/1 system after refurbishment
All board stay unchanged except (UCLA- J. Hauser) ALCT mezzanine boards Small Spartan-6 FPGA cards
Radiation tested, 100% compatible firmware, passes STEP testing Originally for ME4/2 only, but low cost replace on ME1/1 as well
LV system enriched by four Maraton power supplies and LV delivery system (Junction Box) partially recuperated from ME1/1 system
HV system now is the paste copy of station 2.3 with power capacity to supply 72 chambers
Spartan-6 vs Virtex-E features:•10x logic•2x speed•Low power ~same•SEU mitigation options•TMB-compatible
04/18/23 13Petr Levchenko NEC 2013, Varna
ME1/1 Refurbishment and Testing of Boards
All ME-1/1 Chambers have been removed from the Muon Endcap and taken to the SX5 area at the CMS Center
17 chambers have been refurbished and two have been installed on +YE1 disk
The old electronics already used for the ME-4/2 system
Each refurbished chamber undergoes STEP tests with upgraded readout electronics
14
ME-1/1
ME1/1 SX5 area
04/18/23 Petr Levchenko NEC 2013, Varna
LTT
Many new items Electronics designs are fully
validated DCFEB, ALCT S6, LVDB7,
LVMB7 and PPIB production is complete
>300 of 550 cathode boards (DCFEB) received at CERN
Off-chamber electronics OTMB are in production ODMB design is finished, awaiting
a Production Readiness Review
ME1/1 electronics
04/18/23 15Petr Levchenko NEC 2013, Varna
ME-1/1 On-Chamber Electronics Upgrade_1
Remove triple-strip-ganging in ME1/1a region (57 CFEB) Suppress low-pT mis-measured muons Reduces ambiguities due to combinatorics
ALCT ALCT(S6): Anode readout board FPGA Virtex E Spartan 6 New, faster FPGA to handle rates
Low Voltage Distribution Board to supply low voltage to on-chamber electronics and Low Voltage Mezzanine Board is the interface between the LVDB and the readout board ODMB, which we use for monitoring and control
CSC
CFEBCFEBCFEB
CFEB
ALCT1 of 24
CFEB
LVDB
Anode Front-end Board
Cathode Front-end Board
Anode LCT Board
UpgradedCurrent
04/18/23 16Petr Levchenko NEC 2013, Varna
ME-1/1 On-Chamber Electronics Upgrade_2
CLK,L1A,JTAG...TMB Path copperData Path copper
Virtex I
Trig brd2brd
Comparator ASIC
6 Wilkinson ADCs
Switch Capacitor ASIC
Buckeye Amp/shaperASIC
Coupling/Protection
Cathode Front End Boards Digital Cathode Front End Boards (All OSU design – S.Durkin, B. Bylsma)•Virtex 1 Virtex 6•Replace the current analog CFEB with SCA and 16:1 multiplexing ADC by digital design with flash ADC for each channel and digital pipeline storage•Optical Data and Trigger Path CLK,L1A,JTAG...
TMB Path opticalData Path optical
Virtex 6
Trig brd2brd
Comparator ASIC
Flash ADCs
Fully Diff Amps
Buckeye Amp/shaperASIC
Coupling/Protection
CFEB DCFEB
04/18/23 17Petr Levchenko NEC 2013, Varna
Low Voltage Distribution Board (LVDB7)
RDMS design (V.Y. Karjavin) Reviewed in February Fabrication and assembly in Russia
PCB fabrication complete Assembly and test have been completed
72 production boards + spares currently at CERN
Terminal block Fixation of LV cable
04/18/23 18Petr Levchenko NEC 2013, Varna
Low Voltage Mezzanine (Monitor) Board (LVMB7)
UC Davis design (Ray Gerhard)
Performs same functions as previous LVMB but with increased number of channels
interface between ODMB and LVDB boards
Control and monitoring of LVDB power channels
Underwent mini (internal) PRR in May
One FET replaced for rad hardness
Buffer added for temperature monitoring
All PCB’s have been fabricated
36 assembled production boards at CERN
Production LVMB7 with skew clear cable
19 Petr Levchenko NEC 2013, Varna04/18/23
Patch Panel Interconnect Board (PPIB)
PPIB: active interface board in patch panel to take 2 skew clear cables from OTMB and distribute signals to 7 DCFEBs
Designed by Mike Matveev (Rice)
Prototype arrived in April; production completed and all board delivered to CERN
Uses existing skew clear cables to connect to ODMB
Uses new cables to connect PPIB to DCFEBs
2 skew clear cables to ODMB
7 new cables to DCFEBs
04/18/23 20Petr Levchenko NEC 2013, Varna
ME-1/1 Readout Electronics Upgrade
Optical Trigger Mother Board (OTMB). UCLA – J. Hauser
Replaced Mezzanine card. TAMU – J Gilmor
Virtex 6 FPGA enhances our capabilities
memory & speed for improved trigger logic
Use 7 multi-gigabit serial links for data from DCFEBs
New Base Board A new front panel to make room
for optical links Modification specifically targets
improvement in power distribution
Full backwards compatibility is maintained
04/18/23 21Petr Levchenko NEC 2013, Varna
ME-1/1 Readout Electronics Upgrade
Optical Data acquisition Mother Board (ODMB) UCSB, NE Optical Transceivers New Virtex-6 to handle the fiber optic data and optical
transmission for 7 DCFEBs
04/18/23 22Petr Levchenko NEC 2013, Varna
System Test of Endcap Peripheral Crate and Chamber Electronics (STEP Tests)
A comprehensive tests of the chambers which can help detect problems with connectivity, noise, and electronics firmware
Set of tests below are performed on all me-1/1 chambers being refurbished All CSC chambers installed on the muon endcap have undergone these tests
STEP testsSlow Control
Anode Front End Board Threshold and Analog Noise test
Anode Front End Board Noise test
Anode Front End Board Time-delay verification
Pipeline Depth test
Digital Cathode Front End Board Noise test
Digital Cathode Front End Board Connectivity test
Digital Cathode Front End Board DAQ-Path Calibration: Pulse Response and Cross Talks
Digital Cathode Front End Board DAQ-Path Calibration: Amplifier Gain
Digital Cathode Front End Board Comparator Thresholds and Analog Noise
Digital Cathode Front End Board Left/right Comparator Logic test
ALCT self-trigger on cosmic test
High-statistics cosmic test
Chamber gain map
04/18/23 23Petr Levchenko NEC 2013, Varna
Some items… ME1/1 electronics upgrade invoke deep changes in LV system LV system enriched by eight Maraton power supplies and LV delivery system (Junction Box) was
completely redesigned by S.Lusin and produced by Wisconsin and now in CERN In order to prove high reliability new CSC electronics special Low Voltage Test stand (LTT)has been built
in SX5 test area. It has capacity to run six chambers in the same time
* CSC DAQ hardware in USC- number of readout channels (SLink) increased from 8 to 36 to better cope with higher rates and new chambers- chamber grouping modified for better load balancing
* CSC computers- upgrading to more powerful server PCs for detector control and VME communication- new interface cards for VME communication
* CSC software- adapting to the new electronics on the innermost 72 chambers. configuration. control and monitoring (+DCS). data format- updating operating system to SLC 6 or 7 (based on Red Hat EL 6 or 7)- updating to latest CMS online software framework- expanding the scope of expert system- exploiting parallel processing- consolidating applications
04/18/23 Petr Levchenko NEC 2013, Varna 24
Very intense in Oct-Nov for + side endcap: ME4/2 starts Oct. 7, want 24/7 operation for commissioning ME1/1 starts Oct. 17
Installation schedule
04/18/23 25Petr Levchenko NEC 2013, Varna
Summary
CSC Upgrade on it straight way, but still lot of work to do….
ME4/12 project is close to final stage.
ME1/1 refurbishing goes well.
In spite of some delay CSC installation going to happened soon
04/18/23 26Petr Levchenko NEC 2013, Varna