Sep 23 1999 Nick Hadley DØ Prague Workshop 1
Overview Organization Status (brief) Conclusion
Run II Computing and Run II Computing and SoftwareSoftware
Sep 23 1999 Nick Hadley DØ Prague Workshop 2
ComputingComputing
Lehman Baseline
Trigger Systems
DAQ System
$6.0 M
$0.6 M
50 - 100 Hz
Reconstruction Farms $1.6 M, 20 - 40 Hz DC
Central AnalysisSystems $2.8 M
MassStorage
$2.9 M
Workgroup Server
WorkgroupServer
Desktops
RemoteComputing
Monte Carlo, ...
$0.8 M *
Sep 23 1999 Nick Hadley DØ Prague Workshop 3
SoftwareSoftware
Trigger Controls
Trigger Algorithms
Controls & MonitoringRun Control, Data Logging
Subdetector TasksAccelerator Interface
Calibration and Hardware Databases
Farm Control Software
Offline Reconstruction
Production DatabasesAnalysis Tools
Analysis Software
MSS ControlPersistency Tools
Remote Systems
Monte Carlos
DevelopmentEnvironment
Physicists’Analyses
Sep 23 1999 Nick Hadley DØ Prague Workshop 4
HistoryHistory
Run I Computing at DØ
Data collection @ 2 Hz with very high efficiency Reconstruction kept up with collection
time lag of ~ 2 weeks for calibration
Successes: Robustness and timeliness of reconstruction Easy access to microDST data set of all events
Problems/Bottlenecks: Tape access (8mm drives, no significant HSM system) Network access
Reconstruction system difficult to test and verify
Sep 23 1999 Nick Hadley DØ Prague Workshop 5
DØ Run II Data SetDØ Run II Data Set
Run II Parameters for DØ:
Trigger rate 50 Hz (LHC / 2)
Raw data event size 250 kB (LHC / 4)
Data collection 600 M evts/ yr (LHC / 2)
Summary event size 150 kB (LHC x 2)
Physics sum’ry evt siz 10 kB (LHC ??)
Total dataset size 300 TB/yr (LHC / 3)
Bottom line: Computing project
~ O (Run I x 20), ~ O (LHC / 3-4)
Must be accomplished w/ resources avail in 2000, not 2005!
Sep 23 1999 Nick Hadley DØ Prague Workshop 6
Run II Computing and Run II Computing and Software PlanSoftware Plan
Original Plan January 1997 Update to Plan January 1999
See DøatworkComputingReviews & Documentation
Key goals: Maintainability, Separately testable modules Flexibility
• Replaceable packages (e.g., the implementation of persistency, the graphics package, etc.)
Key decisions: OOAD/ C++
Interface to persistency mechanism (first implementations: DSPACK, EVPACK )
Sep 23 1999 Nick Hadley DØ Prague Workshop 7
R2CSP Organization R2CSP Organization
Co-LeadersHadley, Merritt
InfrastructureGreenlee,Li,Prosper
AlgorithmsProtopopescu,Womersley
Monte CarloKlima
Production/Data AccessDiesburg,Lueking
OnlineFuess,Slattery
Computing PlanningBoard
Tightly connected to Joint Projects
SoftwareTools
edm
dØom
framework
RCP
Config Man
Graphics
Subdetectors
Calib/AlignLevel 3Global Tracking
VertexingEM IDMuon IDTau IDJets/Missing Et
Generators Geant sim C++ wrapper Param MC
Procurements Farms Mass Storage Analysis SysSoftware Farms ENSTORE LSF, etc.Data basesData handling SAM
Hardware controls DAQ - primary & secondary Event monitoring Control room applications
Sep 23 1999 Nick Hadley DØ Prague Workshop 8
Joint Offline ProjectsJoint Offline Projects
ZOOM - C++ Class Libraries RIP - Reconstruction Input Pipeline (writes
data into robot in FCC) Support Databases
Using ORACLE, license negotiated through CD
Configuration Management Using SoftRelTools with DØ interface (ctest)
Hardware Projects Mass storage - new robot purchased Networking - new single mode fiber to DØ Farms - in progress (prototype purchase) Physics analysis - 1/3 purchased, online soon, 5TB
disk Note: So far, costed at or under DMNAG ests.
Sep 23 1999 Nick Hadley DØ Prague Workshop 9
Joint Offline Projects cont’dJoint Offline Projects cont’d
Visualization Making use of Open Inventor licenses
Physics Analysis ROOT chosen Evaluations of products
Storage Management Decision to use ENSTORE, linked to SAM
Data Access SAM Working Group - charged with producing a
proof - of - principle demonstration Oct. 98 - done!
Sep 23 1999 Nick Hadley DØ Prague Workshop 10
Computing and Software Plan: Computing and Software Plan: Decision TimelineDecision Timeline
1995 Use C++ ; write data using DSPACK
1996 Begin project; CPB structure, Begin to understand large C++ system
Use DØOM : isolate I/O from usr code
1997 (Jan) 60-page plan submitted
(Jul) Use KAI & VC++ compilers
(Oct) Use SAM
(Dec) Use ZOOM products
1998 (Jan) Use ORACLE for DB needs
(Mar - DAM review) Use modified exclusive streaming
(May) Use ENSTORE instead of HPSS; use Open Inventor graphics
(Aug - GCM review) Use tri-level analysis system; PC’s on desktop
(Sept.) Physics analysis software -Root
Sep 23 1999 Nick Hadley DØ Prague Workshop 11
Status in a NutshellStatus in a Nutshell
SAM Data Handling:Version 0 released in KITSUsed on farm prototypeReady for general users ond02ka
Reconstruction Program:Works from MC digi hits to producecentral tracks, cal & PS clusters,muon system hits, first versions ofphysics objects
Online System:Prototype DAQ working --Able to log data, Cal, muonInterface to control HV, etc.Framework for data monitoringLevel 3 readout software
Monte Carlo:Full GEANT3.21 sim of detectorMultiple interaction capability~90K events available (bkg, sig)Fast MC under development
Analysis Program:HBOOK Ntuples from MCC1available, MCC2 by 1/00ROOT - new Run II tool(can analyze old & new format)
Level 3 Filters:Tools & Filters under development; excellent tutorial on web
Databases:Oracle Event/File DB inproduction; used by SAMOther DBs under devel
Event DispFull det duein OctDisplaysfor alg devavailable now
Sep 23 1999 Nick Hadley DØ Prague Workshop 12
Status in a NutshellStatus in a Nutshell
ADIC tape robotOperational750 TB capacityIn use for SAM &ENSTORE tests;MCC99-1
Central Analysis SystemNow:d02ka + ~ 500 GB diskComing: 1/3 of final system Available to users by 22-Sep64 SGI R12000’s 1923 Gigabit Ethernet Interfaces5 TB disk 30 TB
Online SystemsDecAlpha hostsLevel 3 farmLinux & NT PCs forcontrols & monitoringEXAMINE farm
Networking UpgradesFC rewiring of DAB & PKs100 Mb to desktopsGb uplinks to main switchDone by Sept
Desktops at DØNT or Linux PCsLinux support person hiredOperations strategybeing worked out
Project Servers?NT, LINUXPossible rolesModel for offsite?SpecificationTax ??
Database Servers2 Suns here In use for Evt/File DB
Farms Prototype (4 nodes) for MCC -1Fermilab purchase this yr - 50nodesOffsite proposals for MC
Sep 23 1999 Nick Hadley DØ Prague Workshop 13
Status:Status: Infrastructure Infrastructure
Packages to support batch reconstruction are
in place and in use edm - stable, a few changes coord. with dØom rcp - flat file version stable dØom - DSPACK, EVPACK done, DB design work framework - batch, single threaded interactive have event displays for many detectors still to do: multi-threaded Interactive Framework,
DB version of RCP, integrated event display
Sep 23 1999 Nick Hadley DØ Prague Workshop 14
Status:Status: Infrastructure Infrastructure
Configuration management status Golden releases ~ every three weeks Latest release to IRIX and Linux (~200
packages)• OSF1, NT (40 packages now)• Switching to CTB2, SRT2. Needed for NT
Still with KAI compiler & VC++
• Debugger - TotalView a big improvement
Releases - set a new goal of one week releases
Still Working on t59 Established subsystem coordinators t60 will use SRT2 (and this will be the only
change!)
Sep 23 1999 Nick Hadley DØ Prague Workshop 15
Status:Status: Monte Carlo Monte Carlo
Full GEANT simulation Phase 1 of MCC 99 generated 87K events multiple interactions, better secondary tracing
now implemented
Production release of DØGSTAR/simpp certified for MCC99-2
Monte Carlo presentations to Run II Physics meeting: hope for additional users/feedback/help
Fast MC, trigger simulation in progress
Sep 23 1999 Nick Hadley DØ Prague Workshop 16
Status: AlgorithmsStatus: Algorithms
RECO program including first versions of all particle ID exists
First production version March 99 Algorithms group proceeding toward
Oct. 30 production release
Level 3 reviewed in April 99 software infrastructure in good shape, more
effort needed on releases all basic tools being designed and coded number of people increasing
Sep 23 1999 Nick Hadley DØ Prague Workshop 17
Status:Status: Production and Data Production and Data AccessAccess
SAM and ENSTORE prototypes exist and have been used to access MCC data with production RECO.
Solved numerous problems
Good progress on framework integration for Oct.1 SAM release
first 1/3 of central analysis server has arrived, available for users soon
final system 90K MIPS, 30 TB of disk
New DØ tape robot (750 GB) installed and in use
Serial Media choice by early fall
Sep 23 1999 Nick Hadley DØ Prague Workshop 18
Status:Status: Online Online
Version 0 of COOR, other infrastructure in place
Two DEC Alpha hosts + some PCs
Beginning to use system for commissioning tasks
Milestones driven by users’ needs
Muons and calorimeter successfully readout through the complete chain
Sep 23 1999 Nick Hadley DØ Prague Workshop 19
Von Rüden V Closeout Von Rüden V Closeout June99June99
Joint ProjectsProcurement Spending on track; well under controlManagement & Organization Move into understanding support
phaseInfrastructure Going wellData Access
Networking Continue good collaboration with CDRIP Stick to scheduleSerial Media Work out a backup strategy for Mammoth II’sENSTORE (DØ) Very pleased with excellent management
SAM (DØ) Pleased with further SAM progress; develop plans to further exercise the system with users
Production System Procurements(Robot Well done at the last review)Central Analysis System Well doneFarms Another success
Sep 23 1999 Nick Hadley DØ Prague Workshop 20
Von Rüden V CloseoutVon Rüden V CloseoutDØEnsure further attention to Level 3Global Tracking should work to recruit more people,
especially with prior experience in trackingStart working on calibration & alignment
OverallWe are “very much on track”The committee feels “rather confident” of a successful
completion (And they request us not to embarrass them by
proving them wrong)
Sep 23 1999 Nick Hadley DØ Prague Workshop 21
ScheduleSchedule The Schedule
MCC99-2 Monte Carlo Production release 9/01/99
Monte Carlo evt gen complete 11/15/99
RECO 3rd Production release 10/31/99 Farm production for MCC99-2 11/30/99
Level 3 many skeleton phys tools 7/31/99 1st prod rel. working physics tools 10/31/99 physics tools with raw data 2/28/00
Online System data logging rate test to FCC 9/01/99 integrated DAQ run 11/22/99
MCC99-2 analysis (SAM, DB, ROOT) 12/31/99 MCC99-2 Workshop for results ~2/28/00
Detector Ready for data 1/23/00 We still have a great deal to do. More time but no
extra people. Set priorities and keep focus.
Sep 23 1999 Nick Hadley DØ Prague Workshop 22
Summary of Computing Summary of Computing and Softwareand Software
Integration of systems is beginning!
Good reviews for software infrastructure and hardware purchasing plans
Reconstruction and Monte Carlo moving to V2.
We are well positioned but still need manpower.Hardware needs may make it difficult to add people at FNAL. Contributions of those based elsewhere very important.