32
Sardar Sarovar Project Environment Safeguard Measures in Maharashtra Report of Field Visit – 10 th to 13 th June 2013 Environment Department Government of Maharashtra

Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

  • Upload
    others

  • View
    8

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

Sardar Sarovar Project

Environment Safeguard Measures in Maharashtra

Report of Field Visit – 10th to 13th June 2013

Environment Department

Government of Maharashtra

Page 2: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

Report Preparation:

Ms. Kirti Amritkar-Wani, Project Officer, SSP Monitoring Cell, Environment

Department, GoM

Valuable Inputs:

Dr. Pawan Kumar, Director (Environment), Narmada Control Authority, Indore

Mr. A. M. Pimparkar, Scientist I, Environment Department, GoM

Mr. Anish Parshurame, Scientist II & Under Secretary, Environment Department, GoM

Ms. Archana shirke, Scientist II, Environment Department, GoM

Support:

Mr. Sudhir Shetty, Assistant, Environment Department, GoM

Mr. Dinesh Banate, Data Entry Operator, Environment Department, GoM

Page 3: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

Table of Contents

Sr No Description Page No.

1 Introduction & Field Visit Schedule 1

2 Catchment Area Treatment 3

3 Compensatory Afforestation 7

4 Health Aspects 14

5 Meeting with Field Agencies 19

6 Summary of Work to be done 22

7 Annexure I – Participants of Field Visit 25

Page 4: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra
Page 5: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

1

Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

during 10th to 13th June 2013

Introduction:

The Sardar Sarovar Project is an inter-state multidisciplinary project with a terminal dam

on river Narmada at Kevadia in Gujarat. It is meant to benefit the 4 states of Gujarat, Madhya

Pradesh, Maharashtra and Rajasthan. It is a multipurpose project with irrigation, power and

drinking water benefits. The Sardar Sarovar dam is presently at a height of 121.92 meters.

Although entirely rain fed, the Narmada has a fairly heavy discharge because of

moderately heavy annual average rainfall in the basin, particularly in the upper catchment area.

The total basin area of the river Narmada is 97,410 square kilometer comprising 85,858 square

kilometer in Madhya Pradesh, 1658 square kilometer in Maharashtra and 9894 square kilometer

in Gujarat. Its Catchment area is about 98000 Sq.Kms which is spread to the states of Madhya-

Pradesh, Maharashtra and Gujarat. The Mean annual rainfall in its basin is 1180mm (46.45

inches). Average annual runoff is 41000 MCuM (Million Cubic Meter) (33.21 Million Acre

Feet).

Through this dam Gujarat & Rajasthan have proposed to utilize their share of allocated

water. An annual irrigation of 17.92 lakh ha in Gujarat, 2.46 lakh ha in Rajasthan and hydel

power generation of 1450 MW are proposed through SSP.

Environmental Clearance for the Sardar Sarovar Project by Govt. of India:

Ministry of Water Resources had developed detailed guidelines framed during October,

1980 for project formulations and for assessment of environmental impact of the project and

planning for Environmental Safeguard Measures.

In accordance with the requirement of the Department of Environment, project authorities

submitted the detailed project report (DPR) along with environmental issues during February to

October 1980. Environmental Appraisal Committee of the Ministry of Environment and Forests

approved the project in principle during its 12th

meeting held in 1983. The studies, action and

data were considered at levels and the Sardar Sarovar Project in Gujarat was formally cleared

Page 6: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

2

from environmental angle on 24th

June 1987 by the Ministry of Environment and Forests, Govt.

of India.

The four conditions of the clearance were:

The Narmada Control Authority will ensure that the environmental safeguard measures are

planned and implemented pari passu with the progress of the work on the Project.

The detailed surveys / studies would be done

Catchment Area Treatment (CAT) and rehabilitation programs would be completed ahead of

the reservoir filling.

The Ministry of Environment & Forests would be kept informed of the progress periodically.

Narmada Control Authority:

The Narmada Control Authority (NCA) has been setup following the decision of the

Narmada Water Disputes Tribunal (NWDT) as machinery for implementation of its directions

and decision. The authority started functioning from 20th December, 1980. The authority is a

body corporate with representatives of the four States of Madhya Pradesh, Gujarat, Maharashtra,

Rajasthan and representatives of Govt. of India. Secretary (Water Resources), Govt. of India is

the ex-officio Chairman of the Authority, whereas the routine administration is the responsibility

of Executive Member of the Authority. NCA presently has six subgroups; the Environment

Subgroup is one of them.

SSP Monitoring Cell in Maharashtra:

Environment Sub Group of NCA directed constitution of an Environment Monitoring

Cell for effective implementation and coordination of the SSP work. In pursuance thereof

Government of Maharashtra established Environment Monitoring Cell in the year 2007 to

coordinate and monitor the physical and financial progress of Environmental Safeguard

Measures of SSP.

Field Visit by SSP Monitoring Cell:

A field visit to review the environment safeguard measures in SSP area of Maharashtra was

organized by SSP Environment Monitoring Cell, Environment Department, Government of

Maharashtra during 10th

to 13th

June 2013. Mr. R.K.Suryawanshi, Member (E & R), Narmada

Page 7: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

3

Control Authority; Dr. Pawan Kumar, Director (Environment), Narmada Control Authority and

representatives of SSP Monitoring Cell, Environment Department, Government of Maharashtra

also participated. The list of participants is attached at Annexure I.

The Visit was undertaken as per following schedule:

Date Place of

Visit

Work details

10/6/2013 Nandurbar Meeting with Health officers, Nandurbar

Visit to Valheri PHC

11/6/2013 Shahada

&

Toranmal

Visit to seismic monitoring station at Sawalde, Shahada

Visit to toranmal watershed area – Na 8p

Visit to Toranmal PHC & Rural Hospital (under

construction)

12/6/2013 Dhadgaon Visit to Kakadada PHC & Subcentre

Visit to Mandavi PHC

Visit to Dhadgaon rural hospital

Visit to Compensatory Afforestation area

Meeting with fisheries officers

13/6/2013 Kevadia

Colony,

Gujarat

Visit to see SSP dam site

Following parameters which could be verified in the field were inspected towards review of the

progress.

Catchment Area Treatment (CAT)

As per the guidelines given by Ministry of water Resources, Govt. of India, New Delhi,

only ‘very high priority (VHP)’ and ‘high priority (HP)’ sub-watersheds were decided to be

treated for catchment area treatment.

Government of Maharashtra appointed “All India Soil and Land Use Survey

Organization (AISLUS), Nagpur” for identification and classification of Watersheds in project

area of the State. AISLUS identified total 83 watersheds on the basis of ‘Silt Yield Index’.

Page 8: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

4

Among 83 watersheds in SSP area of Maharashtra, only 52 very high priority and high priority

watersheds were identified for treatment by AISLUS, Nagpur.

The 52 VHP and HP watersheds were divided in two phases for carrying out the CAT

work-

Phase I covering 17 Directly Draining and Critically Degraded Watersheds

Phase II covering 35 Indirectly Draining Watersheds

CAT plan for the 17 directly draining sub-watersheds (Phase I) was prepared using

remotely sensed data by Space Application Centre (ISRO), Ahmedabad and the Maharashtra

State Forest Department, Dhule in September 1993. The CAT plan for 35 indirectly draining

sub-watersheds (Phase II) was prepared by the Maharashtra State Forest Department, Dhule

using remotely sensed data in November 1994.

The Catchment Area Treatment includes following measures:

Mechanical measures involving construction of weirs, gully plugs, nalla bunds, check dams,

contour trenches, etc.

Biological measures such as intensive Afforestation, rehabilitation of degraded forests, pasture

development, improved farming practices, etc. It also involves creation of nurseries of suitable

plant species.

The work is carried out by Chief Conservator of Forests (CCF), Dhule Circle and

Director, Soil Conservation, Commissionerate of Agriculture, Pune. The summary of the work is

given below-

Phase I: Directly draining sub- watersheds

Work was started in 1992 involving treatment of 17 directly draining watersheds.

By the end of September 1998, an area of 20283.48 ha (forest area) was treated by Forest

Department and 3011.52 ha (non forest area) was treated by Commissionerate of

Agriculture.

Thus an area of 23,295 ha was treated in the phase I, against a target of 24,298 ha.

Balance areas (1003 ha) were not available for treatment on account of being rocky / steep

slope etc., hence treatment of phase I area was considered complete.

Page 9: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

5

Phase II: Indirectly draining sub-watersheds

Phase II of CAT works in 35 indirectly draining Watersheds was started by

Commissionerate of Agriculture and Forest Department from 1994-95.

A macro-watershed plan for 77,568 ha in 35 sub watersheds was prepared by

Government of Maharashtra. These sub watersheds covers 43,125 ha of treatable areas.

Details of Phase II CAT Work

Watersheds Target Area (ha) Work status

26 sub watersheds 21,659 Work Completed by

Commissionerate of

Agriculture and is

ongoing in 4

watersheds by Forest

Department

5 Sub watersheds

(Forest area)

13,336 Work ongoing

4 Sub watersheds

(Agricultural area)

8,130

Total no of

Watersheds: 35

Total treatable

area : 43,125

Assessment of the Efficacy of CAT work

Assessment of efficacy of Catchment Area Treatment includes

Forest Cover Assessment

Silt Monitoring

1. The Forest cover assessment for phase I was carried out by Forest Survey of India in

October 2004.

2. Silt Monitoring Stations (SMS) were established in both Forest and agriculture area. For

Phase I CAT Work, two SMS in Forest area and 3 SMS in Agriculture area were

established.

Site Visit to Subwatershed Na 8p in Toranamal-

The team inspected sub-watershed Na 8p of the category "indirectly draining" (Phase-II)

at Toranmal to review Catchment Area Treatment (CAT) works. The works were accomplished

during the year 2012-13 by Forest and Water Conservation Department.

Page 10: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

6

Loose Boulder Structure

Water Harvesting Structure

Area of Sub-Watershed Na8p

Observations:

1. Work done by Water Conservation Department – The work includes loose boulder

structures (LBS) earthen bund and water harvesting structures. From this LBS (48 cu.m.)

and water harvesting structure were seen. The officers reported that, currently there is

availability of Rs 7440 per ha for the treatment and the actual need is Rs 12000 to 18000

per ha.

2. 2. Work done by Forest Department - A series of nala bunds on stream were observed.

The officers stated that currently the plantation area under CAT is kept minimal as per

Page 11: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

7

Nala Bund

fund availability and there is need to increase plantation area. The officers were directed

to submit a note on Compartment history of CAT area.

3. Both the Departments were advised to refer the Silt Yield Index (SYI) analysis for earlier

CAT works. With that justification accordingly prepare a Need based action plan for 9

indirectly draining watersheds

from Phase II. The objective

should be of obtaining the SYI

of 900.

4. It was also directed to do the

Reassessment of earlier CAT

work by Forest survey of India

(FSI)

The garden of medicinal Plants/ trees at Toranamal was also inspected by the team. Dr.

Pawan Kumar, Director (Environment), NCA suggested that nursery of indigenous medicinal

plants could be developed in adjacent area.

It was also observed that barren hills in the identified catchment were covered initially with

native grass species for reducing erosion of soil. The indigenous species of trees found in the

Toranamal region can be used for plantation in Catchment Area Treatment works also. The tree

planting could be taken-up simultaneously. Fencing the work area with vegetation (like Nirgudi

– Vitex negundo etc.) can also serve the purpose as it will reduce the interference on land & help

in natural regeneration of grasses & herbs.

Compensatory Afforestation

Compensatory Afforestation is required to be done against any forestland diverted for the

non-forest purpose. For Sardar Sarovar Project (SSP), Compensatory Afforestation is carried out

to compensate the area submerged under dam water, area used for construction & rehabilitation

purpose. For SSP the total forestland diverted was 13,386 ha (Gujarat 4165.91 ha, Madhya

Pradesh 2731.00 ha and Maharashtra 6488.54 ha). In addition to this, an area of 4200 ha from

Page 12: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

8

Maharashtra was also diverted for Resettlement & Rehabilitation (R&R) of people displaced by

SSP.

As per the provisions of the Forest Conservation Act (1980), Compensatory Afforestation

(CA) be undertaken on an area of land equivalent to the area of forest submerged. One of the

stipulations given by MoEF while permitting the diversion of forestland includes that, ‘for every

hectar of forestland submerged or diverted for construction of the project, there should be

compensatory afforestation on 1 ha of non forest land plus reforestation on 2 ha of degraded

forest land’.

Where non-forest land is afforested, it is also required to declare it as a reserved or

protected forest, under the Indian Forest Act 1927, and to hand over the control and management

of this area to the state forest department.

In Maharashtra, Compensatory afforestation was undertaken & monitored by the Chief

Conservator of Forests, Dhule Circle, who is designated as ‘nodal officer’ for project works.

Maharashtra state has prepared an Action Plan for Compensatory Afforestation areas within

its boundaries. The action plan entitled ‘Compensatory Afforestation scheme in lieu of Sardar

Sarovar Project in Dhule district, Maharashtra State’ was submitted to MoEF in 1989.

The important elements of CA Action plan includes identification of areas for CA,

description of selected areas, justification of selection of areas, identification of responsible

agency, description of staffing & material requirements, estimate of costs, identification of tree

species, description of preparatory work needed, description of planting techniques, provision for

aftercare, yearly planting target, yearly budget and provision made for monitoring

implementation.

To compensate for the forestland taken for the project, Compensatory Afforestation

involving a programme of tree planting in both non-forest and degraded forest areas was

proposed by the State, the summary of which is given in following table-

Area for Compensatory Afforestation in Maharashtra -

Area of

forestland

diverted for

SSP ( ha)

Area of Degraded

forest to be replanted

( ha)

Area of Non-Forest

land to be Afforested

( ha)

Total area for CA

( ha)

10688* 12976 10688 23664

* 10688 ha area includes 6488 ha of forestland diverted for submergence of SSP and

4200 ha of forestland diverted for R&R works.

Page 13: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

9

Implementation of the CA action plan was started in 1992 by the Forest Department. Out of

the total proposed 23664 ha. area, CA over an area of 23576.29 ha has been done by the Forest

Department and Forest Development Corporation of Maharashtra (FDCM) Ltd. up to 1998.

During the CA programme, species of Bamboo, Chinch, Vilayati chinch, Sitafal, Awala,

Kaju, Bor, Charoli, Tembhur, Behda, Hirda, Kawath, Shivan, Moha, Jambhul, Bel, Khair etc.

have been planted.

Compensatory Afforestation Details:

A. Compensatory Afforestation in lieu of Submergence-

Details Physical

Target ha.

Physical

Achievement ha. Remarks

Compensatory Afforestation on degraded forestland

Dhule Circle (1992) 1572.00 1572.00 Target completed

Dhule Circle (1994) 22.08 22.08 Target completed

FDCM 11383.00 11383.00 Target completed

Total 12977.08 12977.08 100 % Target

completed

Compensatory Afforestation on non forestland

Dhule Circle (1992) 84.00 84.00 Target completed

Dhule Circle (1993) 897.71 897.71 Target completed

Dhule Circle (1994) 835.00 835.00 Target completed

Dhule Circle (1998) 85.00 85.00 Target completed

Dhule Circle 86.83 0.00 Area found to be

unworkable for plantation.

Aurangabad 4500.00 4500.00 Target completed

Total 6488.54 6401.71

98.66 % completed

86.83 ha –

unworkable area

B. Compensatory Afforestation in lieu of Rehabilitation-

Details Physical

Target ha.

Physical

Achievement ha. Remarks

Compensatory Afforestation on non forestland

Dhule Circle (1992) 1019.44 1016.94 Target nearly completed

Yeotmal 765.56 765.56 Target completed

Nashik 381.00 381.00 Target completed

Amravati 534.00 534.00 Target completed

Aurangabad 1500.00 1500.00 Target completed

Page 14: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

10

Total 4200.00 4197.50 99.94 % completed

2.50 ha - unworkable area

Grand Total of Table A & B:

Physical

Target ha.

Physical

Achievement ha. Balance area

Grand Total 23665.62 23576.29 89.33 ha*

* The balance area of 89. 33 ha is unfit for plantation and have been informed to NCA in

December 2007. Alternate non-forest land for balance area is being sought from Collector,

Nandurbar.

Declaration of Compensatory Afforestation as ‘Protected Forests’ - After compensatory

afforestation on non forestland is done, it is mandatory to declare the said land as a ‘Protected

Forest’ under the Forest Act of 1927. In this project, the process is under advanced stage. Over

99.80 % areas are already declared as Protected Forest

The CA plantation is monitored for 10 years from the initial year of plantation. The Survey

of Survival Count and Species Composition in CA area was done by the office of Chief

Conservator of Forests, Dhule Circle. The survival count was carried out to check the survival

rate of the plants that were planted during the CA programme.

Area-wise survival percentage of Compensatory Afforestation as on 31.05.2007

Year of

Plantation

Name of

Circle

Name of Division Area in ha. No. of

plants

Planted

No. of

plants

survived

Average

Survival

% as on

31.5.2007

1991 FDCM FDCM Nandurbar 360.40 640868 288012 45 %

1991 FDCM FDCM Nagpur 300.00 750000 229208 31 %

1991 FDCM FDCM Bhandara 250.00 625000 44854 15 %

1991 FDCM FDCM Gondia 64.00 155000 48546 31 %

1991 FDCM FDCM Thane 830.00 1677973 456664 27 %

1991 FDCM FDCM Dahanu 560.00 1207346 237705 20 %

1992 CCF, Dhule Dy CF West

Dhule 500.00 1099581 479911 44 %

1992 CCF, Dhule Dy CF North

Dhule 546.00 1364680 501824 37 %

1992 CCF, Dhule Dy CF Mewasi 526.00 1314882 470385 36 %

1992 CCF, Dhule Dy CF West

Dhule 269.85 570300 307554 54 %

1992 CCF, Dhule Dy CF

NorthDhule 42.00 81200 48996 60 %

Page 15: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

11

Year of

Plantation

Name of

Circle

Name of Division Area in ha. No. of

plants

Planted

No. of

plants

survived

Average

Survival

% as on

31.5.2007

1992 CCF, Dhule Dy CF Jalgaon 705.09 1457237 750684 51 %

1992 CCF, Dhule Dy CF North

Dhule 86.46 162305 52201 32 %

1992 CCF,

Amaravati DCF Paratwada 375.00 765602 171025 22 %

1992 CCF,

Amaravati DCF Buldhana 84.00 210000 79517 38 %

1992 FDCM FDCM Nandurbar 2162.15 4171575 1544158 37 %

1992 CCF, Nasik DCF A’Nagar 363.00 619734 259631 42 %

1993 CCF, Dhule Dy CF North

Dhule 897.00 2245499 990359 44 %

1993 CCF, A’bad Parbhani 150.00 375000 44900 12 %

1993 CCF, A’bad Nanded 800.00 1895552 772215 41 %

1993 CCF, A’bad Beed 220.00 0 0 46 %

1993 CCF, A’bad Osmanabad 601.00 1354307 954228 70 %

1994 CCF, Dhule Dy CF North

Dhule 22.08 0 0 47 %

1994 CCF, Dhule Dy CF North

Dhule 833.00 0 0 44 %

1994 CCF, A’bad Osmanabad 358.00 945928 631496 67 %

1994 CCF, A’bad Parbhani 28.43 60605 6285 10 %

1994 CCF, A’bad Beed 380.00 0 0 49 %

1994 CCF, A’bad Nanded 608.00 1529569 516450 34 %

1994 CCF, Nasik DCF A’Nagar 18.00 32400 15888 49 %

1994 CCF,

Amaravati DCF Paratwada 159.52 286200 136231 48 %

1995 CCF, Nasik DCF A’Nagar 4.00 7200 3996 55 %

1995 CCF, A’bad DCF Nanded 493.00 1135291 366692 32 %

1995 CCF, A’bad DCF Osmanabad 293.75 716718 478150 67 %

1996 CCF, A’bad DCF Osmanabad 101.00 181800 127908 70 %

1996 CCF, A’bad DCF Nanded 298.00 591354 199940 34 %

1997 CCF, A’bad DCF Nanded 9.00 15700 4682 30 %

1998 CCF, Dhule Dy. CF North

Dhule 85.25 0 0 63 %

2001 FDCM FDCM N.

Chandrapur 300.00 525974 234729 45 %

Grand Total 14682.98 28772380 11455024 41.55 %

Page 16: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

12

Site Visit to Compensatory Afforestation Work in Dhadgaon -

Compensatory afforestation work at two adjoining sites in Dhadgaon (gut no 28) was

inspected. Areas of the plantation were 50 ha and 20ha respectively. The work on 50 ha was

carried out during 1993 and that on 20 ha was carried out during 1994 rains.

50 ha CAF area – 150 Nalla bunds with

310 cu.m. area and 1,25,000 pits along with

trenches of 4056.80 running meter were taken up.

The species planted included Australian babhul,

Khair, Bamboo, Ketaki, Prosopis, Neem, Shisoo,

Teak stumps, Shivan, Babhul. About 1,25,000

saplings were planted. The Survival percentage is

55 %.

20 ha CAF area – Nalla bunds with

489 cu.m. area and pits along with trenches

of 15333 running meter were taken up. The

species planted included Prosopis, Acacia

tortalis, Acacia, Kashid, Ber, Bakam, Neem,

Shivan, Kavath, Moh, Kanchan, Shisam,

Teak, Ramkathi Babhul, Parkinsonia. About

50,250 saplings were planted. The Survival

percentage is 52 %. It was also reported that

there is presence of 20 -25 peacocks in afforestation area. It was suggested to plan for gap filling

to enrich the plantations.

The afforestation area with good growth of Agave at trenches was observed. It was

suggested by Director (Environment), NCA that a yardstick to be set for survival percentage as

per plantation success on adjoining forest land.

Page 17: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

13

Seismic Monitoring Station at Sawalade, Shahada

Out of the 9 seismic monitoring stations set for SSP, one is in Maharashtra at Sawalade,

Shahada. The upgraded sensor and seismograph instrument were installed and were functioning.

It was reported that the seismographs are regularly send to SSNNL, Gujarat, online. It was

observed that during rains the roof was leaking and needed repairs.

It was suggested that the seismic monitoring data and its analysis should be taken from

the seismic monitoring centre in Maharashtra, as it will be useful in future for designing

structures on the periphery of the reservoir to withstand tremors and for Research &

Development works besides input for disaster management plan.

Page 18: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

14

Health Aspects

The construction of dams and water projects leads to alteration of water distribution

patterns which brings a lot of environmental change impacting health of the people who live

around. Water borne diseases like diarrhea, cholera & water related disease like Malaria spread

in these areas. The adverse health effects need to be prevented, controlled and treated by

effective monitoring, before they become uncontrollable. Creation of facilities for prevention of

the water borne diseases and screening of migrant workers and immigrant influx has been key

concern of SSP project. Plans and proper implementation is needed to control disease vectors

and to provide health facilities for migrant construction workers and the resettled population.

As a consequence of the SSP, 33 villages from Akkalkuva and Dhadgaon Taluka from

Nandurbar District, Maharashtra are being submerged and are being rehabilitated in Taloda

Taluka of Nandurbar District. These 33 villages are discretely situated on the riverside with their

150 padas.

GoM submitted an initial Work Plan for Public Health Sector in 1987, which was

modified and resubmitted for consideration in 1991 and further updated in 1992 & 1993. The

initial work plan was based on the State Health Department survey of Dhule District. The

principal objectives of the plan were as follows:

Provisions for strengthening of State and District health facilities in existing villages and

in resettlement areas.

Establishment of a monitoring and laboratory cell at the Rural hospital.

Strengthening of the existing Primary Health centres.

To monitor closely health conditions in Dhule district

To provide facilities for carrying out this monitoring

To adopt precautionary measures against the spread of diseases.

To be prepared to combat epidemics that might arise.

This plan contained full description of the likely costs and manforce requirement for

these measures. Epidemiological surveillance report for phase I has been submitted by Topiwala

national medical college, Mumbai. Phase II studies were conducted by Medical College, Dhule.

Page 19: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

15

The above plan was then revised as plan of 2007-08. According to the revised plan, total

number of families residing in 33 villages was 4,163 out of which 3,083 families were to be

rehabilitated. A total of 9 rehabilitation sites were identified for resettlement in Taloda, Akkalkua

and Shahada Taluka. According to the information received 2331 families were resettled in these

locations. Action plan provided arrangements for health facilities:

1. For residents of peripheral villages

2. For residents at the rehabilitation sites

The modified disease management measures required additional financial support.

Similarly a plan for providing health facilities at the 9 rehabilitation sites required additional

manpower and funds.

Health Facilities in SSP impact area and peripheral area*:

Sr

no

Health

Institution

Akkalkuva Dhadgaon Total

1 Rural Hospital 3 1 4

2 Primary Health

Center

13 13 26

3 Sub center 61 50 111

4 Rescue point 13 12 25

5 Floating

Dispensaries

1 1 2

*All these health facilities are working, but construction is not completed for all.

Disease surveillance, malaria control programme, IEC activities etc are carried out under

routine health programmes.

Site Visit to Health Facilities –

The team inspected Rural Hospital (RH), Primary Health Centres (PHC) and Subcentre

from impact & surrounding area and inspected the facilities, held discussion with Medical

Officers to ascertain the ground realities.

Page 20: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

16

Water Testing Laboratory

Biomedical Waste Disposal Pit

Rural Hospital at Dhadgaon

1. The Medical Superintendent at RH

gave brief information about facilities

at the hospital. The hospital had good

infrastructure with all necessary

facilities.

2. The hospital has capacity of 30 bed

with separate gynecologist,

pediatrician and anesthetist appointed.

Along with the delivery room and

operation theater the hospital has

facility of NICU. A blood storage unit

is also proposed.

3. Special training to the PHC staff is

given for safe delivery practices.

4. It was informed that snakebites cases

are within normal limits.

5. Medicine storage, OPD, wards,

laboratory & water testing laboratory

was also inspected. The drinking water

analysis and its reporting to respective

area is done regularly at the water

testing laboratory.

6. Medical officer (BAMS) from Bilgaon

PHC had come for discussion. She

mentioned that 700 to 800 patients

visit the PHC per month and the

number increases to 1700 in rainy

season. Mostly the patients show

symptoms of fever, diarrhea, and

dehydration. In rainy season 40 to 60 patients of Malaria are treated. She informed that

Page 21: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

17

Biomedical Waste Disposal Pit

the medicine stock is not enough for waterborne diseases. Though the PHC is disposing

its biomedical waste in pit there is no proper system followed by the private practitioners

in the area. She also stated the need of permanent staff and residential facility for medical

officers.

7. The NBA activists mentioned about the problem of river pollution in submergence area

due to waste from Dhadgaon going downstream from hill to streams joining the river.

Primary Health Centre (PHC) at Valheri, Nandurbar

1. The population catered by the PHC is about 10,000. The PHC has staff of 14 people

including 2 medical officers (MBBS & BAMS).

2. The PHC had laboratory facility, Operation Theater, indoor capacity of 4 beds, maternity

room, injection room, medicine storage room and 1 ambulance. Mostly the NSV

operations are carried out in the PHC. Daily 15 to 20 patients visit the PHC.

3. Registers maintained for OPD, Malaria and blood sample analysis, medicine stock were

seen. It showed updated record. For

Malaria testing, positive records need

to maintained separately.

4. Hatchery for Guppy Fishes was

observed in the PHC premises.

5. Facility for Biomedical Waste

Disposal was observed. An

underground pit is used for disposing

the biomedical waste. The pit is not

protected from rainwater entering in to

it. Hence the present facility needs improvement. It was informed that the waste is

disinfected before disposing.

Primary Health Centre (PHC) at Toranmal

1. The PHC has staff of 10 people including 2 medical officers (Radiologist & BAMS).

Page 22: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

18

Medicine Storage at

Toranmal PHC

Maleria Testing Record

2. The PHC had laboratory facility, indoor capacity of 4 beds, maternity room, medicine

storage room. Daily 15 to 20 patients visit the PHC.

3. Records maintained for OPD, Malaria and

blood sample analysis, medicine stock were

seen.

4. As the construction of Rural Hospital (30

bed capacity) is ongoing in Toranmal, the

PHC will be soon shifted to other area.

Camp based treatment will be provided in

this rural hospital. It was directed to take

consent for biomedical waste disposal.

Primary Health Centre (PHC) & Subcentre

at Kakadada (Taluka Dhadgaon)

1. The PHC has 2 medical officers (BAMS).

2. The PHC had laboratory facility, indoor

capacity of 4 beds, medicine storage room. Daily 30 to 40 patients visit the PHC.

3. Registers maintained for OPD, Malaria and blood sample analysis, medicine stock were

seen.

4. The biomedical waste from PHC is disposed off in a pit.

5. The sub-centre has the facility of vaccination and delivery. It also had a solar energy

backup needed in emergency.

Primary Health Centre (PHC) at

Mandavi

1. The population catered by the PHC

is about 11,000. The PHC has staff

of 12 people including 2 medical

officers.

2. The PHC had laboratory facility,

Operation Theater, delivery room,

Page 23: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

19

indoor capacity of 4 beds, maternity room, injection room, medicine storage room and 1

ambulance. Daily 15 to 20 patients visit the PHC.

3. Registers maintained for OPD, Malaria and blood sample analysis, medicine stock were

seen. It showed updated record.

4. Hatchery for Guppy Fishes was observed in the PHC premises.

5. Facility for Biomedical Waste Disposal was observed. An underground pit is used for

disposing the biomedical waste. The pit was found in good condition.

6. For power backup, the PHC have a solar photovoltaic inverter (3 day power backup).

Meeting with Field Agencies

Recommendations – Health Aspects

1. Director Environment, NCA suggested to improve the Health Action Plan prepared for

impact area with focus on reinforcement for optimum health infrastructure & disease

surveillance. The action plan should be prepared with holistic view for impact area with

capacity to address any disease outbreak in impact area after full reservoir level is

achieved.

2. Disease surveillance before & after the project is necessary to analyze the project impact.

3. Problem of open defecation, pollution of drinking water sources and increase of

dysentery cases were mentioned by the Taluka Health Officers (THOs).

4. While revising the action plan, Phase I & Phase II studies on Health aspects and Health

action plan 1986-88 should be referred. Training for data collection, focus on water

related diseases, provision for sanitary latrines / toilets , analysis of disease pattern in

impact and surrounding area, drinking water quality checking, IEC activities should be

part of the action plan.

5. Analysis of MIS reports from impact area health facilities should be submitted.

6. Yearly action plan with physical / financial activities should be made available.

7. Registration of PHCs and RH for Biomedical waste disposal should be done. It was

informed to submit list of PHCs along with their status of consent for disposal of

biomedical waste.

Page 24: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

20

8. Progress on implementation of earlier health action plan should be submitted.

9. Impact area data analysis, possibilities of outbreak, measures, density of disease

mapping, thematic mapping should be done.

10. It was suggested to keep adequate stock of water disinfecting agents in all PHCs and shall

be supplied regularly to villages. Increase in Medicine & medichlor supply, providing it

throughout the year.

11. Submit the solar dual pump proposal (drinking water – lift, storage & purification) for

experimental area. First approve it from Water Supply Department.

12. It was also suggested to hire/consult institute like NIMR (National Institute of Malaria

Research) for analyzing impact area disease surveillance data. And that there should be a

computerized central monitoring cell for coordinating and monitoring of disease pattern

and data being collected through health surveillance system by an expert in the area of

health issues. This sub cell may be integrated with Environment Department’s monitoring

cell.

Recommendations - Aquatic Ecosystem , Fisheries

Stocking of Indian Major Carp, cold storage facility for fishes can also be added to

Action Plan. It was requested to send a copy of ‘letter sent to CIFRI about endangered

fish species stocking’.

Director Environment, NCA suggested that villagers can be involved in ‘fish hatcheries’

and then the fingerlings can be purchased from them by Fisheries Department.

The officers were directed to refer earlier surveys about sociology of impact area, and

then prepare a phase wise plan for forming fisheries cooperative society. It was informed

that 5 proposals were received on fisheries cooperative society through Gramsabha. It

was suggested that the progress on formation of cooperative societies should be made

available to Environment Department, GoM.

Improvement in Fisheries Action Plan, should taken up as per suggestion of HLEG.

Issues for SSP Environment Monitoring cell

Director Environment NCA suggested appointing a Separate Consultant, a medico (on

contract / rtd personal) as is being the case in Gujarat and Madhya Pradesh for looking

Page 25: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

21

after all tasks related to Health and water quality for better coordination and continuous

updates in real time, while other activities like seismicity rim stability , CAF and CAT

fisheries archeology/ anthropology etc work may continued to be monitored by the

existing formations.

For undertaking comprehensive compilation and preparation of data bank on suggested

parameters, the expenditure incurred on the SSP works in Maharashtra since beginning

including the Study, and implementation of environment safeguard measures, the cell

should be strengthened as it will be playing important role in representing Maharashtra

state with all necessary data during the review of the award of the Tribunal scheduled to

be undertaken during 2025.

Data collection, data analysis, GIS based representation etc be displayed and updated

regularly on web site also.

Participants of Field Visit

Page 26: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

22

Summary of Work to be done

Sr

No

Area of Work Implementing Agency /

Concerned Department

1 Catchment Area treatment

Refer the Silt Yield Index (SYI) analysis for earlier

CAT works. With that justification accordingly

prepare a Need based action plan for 9 indirectly

draining watersheds in Phase II.

It was also directed to do Reassessment of earlier

CAT work by Forest survey of India (FSI)

CCF, Dhule

&

Directorate of Agriculture,

Pune

2 Compensatory Afforestation

Reassessment of CAF work by Forest survey of

India (FSI)

Status of declaration of CAF area as protected

forest.

Submit report on Gap filling work.

CCF, Dhule

3 Aquatic Ecosystem – Fisheries

Improvement in Fisheries Action Plan, should

taken up as per suggestion of HLEG.

Stocking of Indian Major Carp, cold storage facility

for fishes can also be added to Action Plan.

Send a copy of ‘letter sent to CIFRI about

endangered fish species stocking’, report prepared

in 2004, & ‘Proforma of Fisheries cooperative

society formation’ to Environment Department,

GoM

The officers were directed to refer earlier surveys

about sociology of impact area, and then prepare a

phase wise plan for forming fisheries cooperative

society.

The progress on formation of cooperative societies

should be made available to Environment

Department, GoM.

Fisheries Commissionorate

4 Health Aspects

Improve the Health Action Plan prepared for

impact area with focus on reinforcement for

Directorate of Health

Page 27: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

23

optimum health infrastructure & disease

surveillance. The action plan should be prepared

with holistic view for impact area with capacity to

address any disease outbreak in impact area after

full reservoir level is achieved.

While revising the action plan, Phase I & Phase II

studies on Health aspects and Health action plan

1986-88 should be referred. Training for data

collection, focus on water related diseases,

provision for sanitary latrines / toilets, analysis of

disease pattern in impact and surrounding area,

drinking water quality checking, IEC activities

should be part of the action plan.

Analysis of MIS reports from impact area health

facilities should be submitted.

Analysis about Disease surveillance before & after

the project to analyze the project impact.

Yearly action plan with physical / financial

activities should be made available.

Registration of PHCs and RH for Biomedical waste

disposal should be done & reported. It was

informed to submit list of PHCs along with their

status of consent for disposal of biomedical waste.

Progress on implementation of earlier health action

plan should be submitted.

Impact area data analysis, possibilities of outbreak,

measures, density of disease mapping, thematic

mapping should be done.

Increase in Medicine & medichlor supply,

providing it throughout the year

Submit the solar dual pump proposal (drinking

water – lift, storage & purification) for

experimental area after approval from Water

Supply Department.

Hire/consult institute like NIMR (National Institute

of Malaria Research) for analyzing impact area

disease surveillance data.

& DHO Nandurbar

5 SSP Monitoring Cell

Appointing a Separate Consultant, a medico (on

contract / rtd personal) as is being the case in

Gujarat and Madhya Pradesh for looking after all

tasks related to Health and water quality for better

Directorate of Health

&

SSP Monitoring Cell,

Environment Department,

GoM

Page 28: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

24

coordination and continuous updates in real time.

There should be a computerized central monitoring

cell for coordinating and monitoring of disease

pattern and data being collected through health

surveillance system by an expert in the area of

health issues. This sub cell may be integrated with

Environment Department’s monitoring cell.

The seismic monitoring data and its analysis should

be taken from the seismic monitoring centre in

Maharashtra,

For undertaking comprehensive compilation and

preparation of data bank on suggested parameters,

the expenditure incurred on the SSP works in

Maharashtra since beginning including the Study,

and implementation of environment safeguard

measures, the cell should be strengthened as it will

be playing important role in representing

Maharashtra state with all necessary data during the

review of the award of the Tribunal scheduled to be

undertaken during 2025.

Data collection, data analysis, GIS based

representation etc be displayed and updated

regularly on web site also.

SSP Monitoring Cell,

Environment Department,

GoM

Page 29: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

25

Annexure I

Participants of the field visit & Meeting

Narmada Control Authority, Indore

1. Mr. R.K.Suryawanshi, Member (E & R)

2. Dr. Pawan Kumar, Director (Environment)

Environment Department (Sardar Sarovar Project Monitoring Cell)

3. Mr. A.M. Pimparkar, Scientist I

4. Ms. Archana Shirke, Scientist II

5. Ms Kirti Amritkar-Wani, Project Officer

6. Mr. Dinesh Banate, Data Entry Operator

Collector office, Nandurbar

1. Mr. A. S. Ranga Naik, Chief Executive Officer, Nandurbar

Forest Department

1. Mr. S.T.Jagtap, Deputy Conservator of Forests, Shahada

2. Mr.N.G.Patale, Assistant Conservator of Forests, Nandurbar Forest Division

3. Mr.Dharamveer Salvitthal, Assistant Conservator of Forests, Mewasi Forest Division,

Taloda.

4. Mr. P.S.Wagh, Assistant Conservator of Forests, Taloda Forest Division

5. Mr. Suryavanshi, Range Forest Officer, Toranamal

6. Mr. Chandel, Range Forest Officer, Akrani

7. Mr. R.D.Pawar, Range Forest Officer, Kathi

8. Mr. K.B.Rajput, Range Forest Officer, Khapar

Page 30: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

26

Fisheries Department

1. Mr.U.K.Bansode, Regional Deputy Commissioner of Fisheries, Nashik

2. Mr.S.K.Chiplunkar, Assistant Commissioner of Fisheries, Nandurbar

3. Mr.P.D.Khairnar, Fisheries Devlopment Officer, Nashik

4. Mr.K.G.Padavi, Assistant Fisheries Development Officer, Nandurbar

Health Department

1. Dr.P.M.Padvi, District Health Officer, Nandurbar

2. Dr.Kothari.A.R, Taluka Health Officer, Nandurbar

3. Dr.S.N.Parmar, Taluka Health Officer, Nandurbar

Water Conservation Department

1. Mr.A.M.Kamble, District Superintend Agriculture Officer, Nandurbar

2. Mr.R.M.Pawar, Taluka Agriculture Officer,Akrani

3. Mr.J.C.Padvi, Circle Agriculture Officer,Dhadgaon

4. Mr.M.A.Borate, Agriculture Assistant

5. Mr.S.S.Bhalerao, Agriculture Assistant

6. Mr.R.B.Kokani, Agriculture Assistant

Page 31: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra
Page 32: Sardar Sarovar Project - NCAnca.gov.in/field-visit-env/visit_report_Maharashtra.pdf · 2018. 2. 16. · 1 Report of the Field Visit to the Sardar Sarovar Project (SSP) Areas in Maharashtra

Narmada Main Canal SSP Dam Backwater

SSP Dam Backwater