Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
1
Quantifying the Impact of Hydropower Operations on Shoreline Erosion throughout the
Turners Falls Impoundment (Connecticut River)
By Timothy Sullivan, Regulatory Specialist, Gomez and Sullivan Engineers, Henniker, NH;
Dr. Andrew Simon, P.E., Fluvial Geomorphologist, Cardno, Oxford, MS; and
Dr. Robert Simons, P.E., Fluvial Geomorphologist, Simons & Associates, Midway, UT
ABSTRACT
As part of the Federal Energy Regulatory Commission relicensing of the Turners Falls
Hydroelectric Project and the Northfield Mountain Pumped Storage Project, a multi-year study
was conducted to identify, evaluate, and quantify the causes of erosion throughout the Turners
Falls Impoundment (Connecticut River, which serves as the lower reservoir for the pumped
storage project) and determine the extent to which erosion was related to hydropower operations.
To achieve the goals of the study a wide variety of field data collection efforts, data analyses, and
computational modeling were conducted. HEC-RAS and River2D hydraulic models were
developed to analyze the complex hydrologic and hydraulic characteristics of the Turners Falls
Impoundment as well as the location, duration, and magnitude of hydraulic forces associated with
erosion. The results of the HEC-RAS model, combined with a wide array of field collected data,
were then used as input parameters for the Bank Stability and Toe Erosion Model (BSTEM).
Site-specific BSTEM results from twenty-five detailed study sites along the Turner Falls
Impoundment riverbank were then extrapolated throughout the entire Impoundment to identify the
dominant and contributing causes of erosion at each riverbank segment and to determine the
impact hydropower operations have on erosion, if any. The results of the study found that naturally
occurring high flows were the dominant cause of erosion at almost all riverbank segments with
boat waves also having an impact in the lower portion of the study area.
INTRODUCTION
The Northfield Mountain Pumped Storage Project (Northfield Mountain) (FERC No. 2485) and
the Turners Falls Hydroelectric Project (Turners Falls) (FERC No. 1889), collectively referred to
as the Project, are located on the Connecticut River in the towns of Montague and Erving, MA,
respectively. The Turners Falls Dam creates the approximately twenty-mile-long Turners Falls
Impoundment (Impoundment), which also serves as the lower reservoir and tailrace for Northfield
Mountain. The Turners Falls Dam includes two hydroelectric projects operating from a canal
including Station No. 1 and Cabot Station. The Vernon Dam, which is part of the Vernon
Hydroelectric Project (Vernon) (FERC No. 1904) and located in Vernon, VT, is located at the
upstream extent of the Impoundment. The Turners Falls and Northfield Mountain Projects are
owned and operated by FirstLight Hydro Generating Company (FirstLight) and are currently
licensed with the Federal Energy Regulatory Commission (FERC or the Commission). The
licenses for Turners Falls and Northfield Mountain were issued on May 14, 1968 and May 5, 1980,
respectively, with both set to expire on April 30, 2018. FirstLight has initiated the process of
relicensing the Project with the Commission using FERC’s Integrated Licensing Process. The
figure found on page 2 depicts the Impoundment from the Turners Falls Dam to Vernon Dam.
2
Streambank erosion throughout the Impoundment has been a contentious issue for decades. Since
operation of the Northfield Mountain Project commenced in 1972, local stakeholders have
contended that water level
fluctuations associated with
the Project’s pumping and
generation cycles have been
the cause of erosion
throughout the
Impoundment. Under the
current license, FirstLight is
responsible for remediating
all erosion in the
Impoundment, regardless of
cause. Due to the history of
this resource issue, Simons &
Associates, Cardno, and
Gomez and Sullivan
Engineers, DPC1
(collectively referred to as the
Study Team), conducted the
multi-year Northfield
Mountain/Turners Falls
Operations Impact on
Existing Erosion and
Potential Bank Instability
relicensing study (the study).
The results from this study
were used to identify,
evaluate, and quantify the
causes of erosion throughout
the Impoundment and to determine the extent to which hydropower operations impact erosion, if
at all.
METHODOLOGY
To achieve the study goals a wide variety of field data collection efforts, data analyses, and
computational modeling were conducted throughout the study area. The study area included the
entire Impoundment from Vernon Dam to Turners Falls Dam; the study period encompassed 2000-
2014. Five potential primary causes of erosion were examined in-depth including: (1) hydraulic
shear stress due to flowing water; (2) water level fluctuations due to hydropower operations; (3)
boat waves; (4) land management practices; and (5) ice. Secondary causes of erosion such as
1 Additional study partners included The National Center for Computational Hydroscience at the University of
Mississippi, New England Environmental, and Dr. Kit Choi, P.E.
3
animal activity; freeze-thaw; wind waves; and seepage and piping were thought to have minimal
to no influence on erosion in the Impoundment except in specific, localized areas where they may
occur. As such, these potential secondary causes were not examined in-depth.
An extensive combination of historic data from the 1990s and 2000s combined with newly
collected field data provided the foundation from which all analyses and modeling were conducted.
Datasets for this study included
hydraulic and hydrologic data;
geomorphic and riverbank
geotechnical data; Project
operations data; and cross-
sectional and bathymetric
survey data. Given the vast
study area (i.e., over forty miles
of riverbank), twenty-five
detailed riverbank study sites
were established throughout
the Impoundment with in-
depth field data collection,
investigation, and modeling
occurring at each site. The
detailed study sites (shown in
the adjacent figure) spanned
the geographic extent of the
Impoundment, included a
representative range of
riverbank features,
characteristics, hydraulic, and
erosion conditions, included
both non-restored and restored
sites, and were located at a
combination of existing
transects (surveyed annually
since the late 1990s) and newly
identified sites. Detailed study sites located at existing transects provided an opportunity to
calibrate the Bank Stability and Toe Erosion Model (BSTEM) with actual erosion amounts or
changes in bank geometry as it occurred over time.
Prior to evaluating the causes of erosion, a 1-dimensional unsteady HEC-RAS model and 2-
dimensional River2D hydraulic model were developed to analyze the complex hydraulic and
hydrologic characteristics of the Impoundment as well as their associated impact on erosion
processes. The hydraulic model results provided valuable insight into the hydraulic forces
associated with erosion and were used for several analyses including delineation of hydraulic
reaches as well as shear stress, water level duration, stage-discharge, and flow exceedance
4
analyses. The outputs from the HEC-RAS model (specifically hourly Energy Grade Line Slope
(EGL slope) and water surface elevation), combined with field collected data, were used as input
parameters for BSTEM. BSTEM was run on an hourly timestep at each of the twenty-five discrete
detailed riverbank study sites located throughout the Impoundment over the period 2000-2014. In
the event that a study site had been previously restored, BSTEM was run for both the pre-
restoration and post-restoration condition.
The site-specific BSTEM results, combined with the results of the hydraulic models and other
supplemental analyses, were used to quantify the dominant and contributing causes of erosion at
each detailed study site. Once the causes of erosion were determined for each site, an
extrapoloation approach was utilized to assign the cause(s) of erosion for each riverbank segment2
throughout the Impoundment.
RESULTS
Although a wide array of data analyses and computational modeling were conducted for this study,
discussion presented in this section focuses primarily on the results of the hydraulic and BSTEM
modeling. The results of the hydraulic modeling provided valuable insight into the hydraulic
forces associated with erosion and the influence that hydropower operations have on the complex
hydraulics in the study area. Site-specific BSTEM results quantified the amount of bank erosion
which occurred over the course of the study period and identified dominant and contributing causes
of erosion at each site. Results from the hydraulic model analyses and BSTEM are discussed in
greater detail below.
Hydraulic Modeling Results
The results of the hydraulic modeling were used for several analyses to better understand the
complex hydrologic and hydraulic characteristics of the study area and to determine the extent to
which hydropower operations impact the hydraulic forces associated with erosion. Analyses
pertaining to flow, water level, and shear stress as well as delineation of hydraulic reaches were
conducted. An overview of each of these analyses is presented below.
Delineation of hydraulic reaches: Review of the hydraulic model results, and more specifically
the EGL slope, revealed four distinct hydraulic reaches within the Impoundment including: the
Upper (Reach 4), Middle (Reach 3), Northfield Mountain (Reach 2), and Lower (Reach 1) reaches
(figures page 5 and 10). The delineation of hydraulic reaches was significant in that the results of
the hydraulic and BSTEM models indicated that hydropower operations can only potentially
impact erosion processes within the hydraulic reach where a given project is located due to the
varying hydraulic characteristics of the Impoundment. In other words, the models showed that
Vernon operations can only potentially impact erosion processes at riverbank segments in Reach
4, Northfield Mountain operations can only potentially impact erosion processes in Reach 2, and
Turners Falls operations can only potentially impact erosion processes in Reach 1. Hydropower
operations do not impact erosion processes at all in Reach 3. Although hydropower operations
can impact flows and water levels beyond their given hydraulic reach, the impacts at flows which
2 Riverbank segments were delineated during an earlier FERC relicensing study (i.e., the 2013 Full River
Reconnaissance survey).
5
cause erosion (as determined by BSTEM) are minor enough that they do not alter the EGL slope,
and therefore the velocity or shear stress, outside of their reach.
Flow Analysis: The models assessed the erosive impacts of flows within thresholds established
by the hydraulic characteristics of each reach. Through further analysis of the various modeling
results two flow thresholds were established in the Upper reach of the Impoundment (Reach 4):
(1) <17,130 cubic feet per second (cfs), and (2) >17,130 cfs. This threshold value was identified
as it corresponds with the total turbine hydraulic capacity of the Vernon Hydroelectric Project and
is consistent with the hydraulic characteristics of this more riverine reach of the Impoundment.
In the remaining three hydraulic reaches, three flow thresholds were established, including: (1)
Low Flow (<17,130 cfs), during these periods flows and water levels are controlled by
hydroelectric operations; (2) Moderate Flow (17,130 to 37,000 cfs), during these periods several
hydraulic influences are observed including hydropower operations, Turners Falls Dam water level
management, and a natural hydraulic control (i.e., the French King Gorge3 at flows greater than
30,000 cfs); and (3) High Flow (>37,000 cfs). 37,000 cfs was chosen as the high flow threshold
as it represents the combined hydraulic capacity of Vernon and Northfield Mountain, is at a flow
above which the French King Gorge becomes the hydraulic control for the mid and upper portions
of the Impoundment (see figure on page 3), and represents periods when Northfield Mountain
operates less frequently. Flows greater than 37,000 cfs are considered naturally occurring.
The establishment of flow thresholds was vital when determining the impact Project operations
may have on erosion processes. Given that BSTEM was run on an hourly timestep for the full
study period, the site-specific BSTEM results quantified the amount of erosion which occurred at
every flow and determined the flow at which the majority of erosion occurred at a given site. Flow
analyses were run using the BSTEM results to determine the erosion flow threshold at which 50%
and 95% of all erosion occurred at a given site. Based on the results of this analysis, and the
established flow thresholds, a determination was made as to the sites where natural moderate or
3 The French King Gorge is located in Reach 2; the river width narrows considerably here causing backwatering to
occur in Reaches 2, 3, and 4 at flows greater than approximately 30,000 cfs.
6
high flows were found to be a dominant or contributing cause of erosion. The results of the HEC-
RAS model were then used to determine the percent of time flows at which the majority of erosion
occurred. By delineating hydraulic reaches and establishing flow thresholds, the Study Team
could determine erosion caused by natural flows versus erosion caused by hydropower operations.
Water Level Analysis: Hydraulic erosion processes associated with hydraulic shear stress due to
flowing water; water level fluctuations due to hydropower operations; boat waves; and ice occur
at or below the water surface. As such, it is vital to understand where on the riverbank the water
surface rests and for what duration.
Impoundment riverbanks are typically
characterized by a clearly defined lower
and upper bank (see adjacent figures). The
lower bank is typically a relatively flat,
beach-like feature that is submerged or
experiences daily water level fluctuations
during low to moderate flows because of
hydropower peaking operations. As one
moves up-gradient from the normal edge-
of-water, the lower bank transitions to an
upper bank; the toe of which is clearly
identifiable. The upper bank is typically
steep, has some degree of vegetation, and is
usually above the water surface except
during high flows. The distinction between
the upper and lower bank is important as
the vast majority of erosion in the
Impoundment occurs when the water
surface reaches the upper bank.
To determine the amount of time the water
surface rests on the upper bank, and
therefore the amount of time the vast
majority of erosion occurs, a water level
duration analysis was conducted at a representative subset of the twenty-five detailed study sites.
The water level duration analysis entailed using the HEC-RAS results to develop stage-discharge
relationships at the representative sites to determine the flow at which the water level exceeds the
toe of the upper bank (toe-of-bank elevations were derived from cross-section survey data). Flow
duration curves were then developed and examined to determine the percent of time flows which
resulted in a water surface elevation which exceeded the toe of the upper bank could have occurred.
The results of the stage-discharge analysis were then compared against the results of the BSTEM
flow analysis which examined the flows at which 50% and 95% of all erosion occurred at a given
site.
7
The results of this analysis found that the water level rested on the lower bank, where minimal to
no erosion occurs, the vast majority of the time (i.e., 78-90% of the time during the study period).
The flow required for the water surface to exceed the toe of the upper bank was generally found
to be within the moderate flow range (i.e., 17,130 cfs to 37,000 cfs); however, the flows at which
95% of all erosion occurred were found to be close to, or greater than, the natural high flow
threshold (37,000 cfs) at almost all sites. The percent of time which the 95% erosion flow
threshold occurred at these sites ranged from 3%-7%, with the corresponding water surface
elevations well above the toe of the upper bank. In other words, as observed from the models,
minimal to no erosion occurred during low flow periods when river flows are less than the
hydraulic capacity of the hydroelectric projects. It was not until the water surface reached the
upper bank during naturally occurring moderate to high flows that the vast majority of erosion
occurred.
The results of this analysis demonstrated the minimal impact which hydropower operations have
on erosion in the Impoundment by determining the location, duration, and magnitude of the
hydraulic forces associated with erosion processes.
Shear Stress: The results of the River2D hydraulic model were used to evaluate velocity and shear
stress in the near-bank area at each of the detailed study sites as well as other areas of interest (i.e.,
areas with unique hydraulic conditions such as eddies). Given that BSTEM determines the
boundary shear stress along each node of the wetted perimeter, the River2D analysis was
conducted as a supplemental analysis to verify and confirm the BSTEM findings.
The River2D analysis utilized the results of six steady-state simulations which examined a range
of conditions, including normal operating conditions, commonly occurring flows that might occur
every few years, and more extreme events including the 100-year flood. Boundary shear stress
values derived from the River2D model were compared against the critical shear stress at each site
which was derived from field collected data. The results of this analysis found that the hydraulic
shear stress is only sufficient to cause erosion when flows at Turners Falls Dam exceed
approximately 30,000 to 65,000 cfs, and may be insufficient to cause erosion at approximately half
of the detailed study sites under a 100-year return period event (i.e., 157,700 cfs).
BSTEM Results
BSTEM is a state-of-the-science deterministic model that simulates hydraulic and geotechnical
erosion processes responsible for bank erosion, including the effects of vegetation, pore-water
pressure, and the confining forces due to flow in the channel. BSTEM was the principal tool used
to evaluate the potential primary causes of erosion including hydraulic shear stress due to flowing
water, water level fluctuations, and boat waves. The remaining potential primary causes of erosion
(i.e., ice and land management practices) were evaluated through separate, supplemental analyses.
Multiple hourly BSTEM runs for the full study period (2000-2014) were executed at each detailed
study site and included the Baseline Condition, which represented observed conditions during the
model period, and Scenario 1, which modeled Northfield Mountain as being idle (no pumping or
generation) for the full model period. In addition, model runs for both the Baseline Condition and
Scenario 1 were run with the boat wave module “turned on” and “turned off” to determine the
impact of boat waves. If a detailed study site had previously been restored, BSTEM was run for
8
both the pre-restoration and post-restoration condition. BSTEM outputs quantified the total
erosion under the Baseline Condition in terms of ft3/ft/yr and determined the erosion flow
thresholds at which 50% and 95% of all erosion occurred at each detailed study site. Site specific
BSTEM results are presented in the figures below. The top figure depicts the average annual rate
of erosion at each detailed study site, while the bottom figure depicts the discharge at which 95%
of erosion occurs.
To determine the impact hydropower operations had on erosion and bank instability, the potential
primary causes of erosion were further broken down into the following categories: (1) natural
moderate or high flows; (2) boat waves; (3) Vernon operations; (4) Northfield Mountain
operations; and (5) Turners Falls operations. Table 1 provides an overview of how each primary
cause of erosion was determined. Based on these classifications dominant and contributing causes
of erosion were identified at each detailed study site. For a cause to be considered Dominant, it
needed to be responsible for at least 50% of the erosion at a given site, as determined by the
modeling results. Conversely, for a cause to be considered Contributing, it must be responsible
for at least 5% but less than 50% of the bank erosion at a given site. Causes responsible for less
9
than 5% of the erosion at a given site were considered immeasurable and were within the accuracy
of the analysis. The site-specific BSTEM results identified the bank erosion rate, dominant cause,
contributing cause(s), contributing factors, and contributing processes for each detailed study.
Table 1 - Determination of the Primary Causes of Erosion in the Turners Falls Impoundment
Primary
Cause Description
Moderate or
High Flows
Hydraulic shear stress due to flowing water. A flow analysis was conducted
which resulted in identification of the erosion flow threshold at which 50% and
95% of all erosion occurred at a given site. Based on the results of this analysis,
and the flow thresholds discussed earlier, a determination was then made as to
the sites where natural moderate or high flows were found to be a dominant or
contributing cause of erosion.
Boat waves
BSTEM was enhanced with a built-in boat wave module for this study. Two
BSTEM runs were executed utilizing this module, one with boat waves “turned
on” and the other with boat waves “turned off”. The difference in observed
erosion between the two model runs determined the sites where boat waves were
a cause of erosion.
Vernon
operations
Hydraulic shear stress due to flowing water, water level fluctuations associated
with hydropower operations. The results of the flow analysis were used to
identify areas within the Upper hydraulic reach where erosion was observed at
flows below 17,130 cfs.
Northfield
Mountain
operations
Hydraulic shear stress due to flowing water, water level fluctuations associated
with hydropower operations. Two BSTEM runs were executed, one
representing Baseline Conditions and one representing Northfield Mountain as
idle. The difference in observed erosion between the two model runs determined
the sites where Northfield Mountain operations were a cause of erosion.
Turners
Falls
operations
Hydraulic shear stress due to flowing water, water level fluctuations associated
with hydropower operations. Due to the hydraulic characteristics of the Lower
hydraulic reach (i.e., lake-like downstream portion (Barton Cove) and a riverine
upstream portion), a combination of site-specific BSTEM results, geomorphic
assessment, and hydraulic model analysis were used to determine the causes of
erosion in the Lower hydraulic reach and the impact, if any, of Turners Falls
operations.
SUMMARY EVALUATION OF THE CAUSES OF EROSION
After determining the dominant and contributing causes of erosion at each detailed study site, the
BSTEM results, combined with the results of the supplemental analyses conducted for this study,
were extrapolated across the Impoundment to over 593 riverbank segments. The extrapolation
process was a multi-step process that included analysis of the riverbank features, characteristics,
10
and erosion conditions at each segment, the variability of hydraulic forces throughout the
Impoundment, and the adjacent land-use. The result of this task was the quantification, based on
relative percentages, of the dominant and contributing causes of erosion at each detailed study site
and the Impoundment overall.
The results of the extrapolation process found that naturally occurring high flows were the
dominant cause of erosion in the Impoundment at 78% of the riverbank segments (~33 miles)
followed by boat waves at 13%
(~6 miles). Northfield
Mountain or Turners Falls
operations were not found to
be a dominant cause of erosion
at any riverbank segment in the
Impoundment. Analysis of the
contributing causes of erosion,
found that the majority of
riverbank segments in the
Impoundment did not have a
contributing cause of erosion
(68% of the riverbank
segments or ~29 miles) given
that natural high flows were
such a dominant factor in
erosion processes. At
riverbank segments that did
have contributing causes of
erosion, boat waves were
found to be the most common
(16% or ~7 miles) followed by
naturally occurring moderate
flows (10% or ~4 miles),
natural high flows (9% or ~4
miles), and Northfield
Mountain operations (4% or
~1.5 miles)4. Turners Falls or
Vernon operations were not found to be a contributing cause of erosion at any riverbank segment
in the Impoundment. The spatial distribution of the causes of erosion are presented in the adjacent
figure.
4 Note that since moderate flows and boat waves are contributing causes of erosion at a number of the same riverbank
segments, the total percentage for contributing causes does not equal 100%. In other words, given that a riverbank
segment can have more than one contributing cause of erosion, the percentages do not add to 100%.
11
CONCLUSIONS
The Northfield Mountain/Turners Falls Operations Impact on Existing Erosion and Potential
Bank Instability Study successfully utilized state-of-the-science technology and a wide array of
existing and newly collected data, data analyses, and computational modeling to identify and
quantify the causes of erosion at 593 riverbank segments spanning over forty miles of shoreline.
In addition, the study successfully quantified and identified the locations where hydropower
operations are a dominant or contributing cause of erosion.
The two primary tools used to conduct this study (1-dimensional unsteady HEC-RAS model and
BSTEM) provided a comprehensive analysis of the causes of erosion, and forces associated with
them, in the study area. Results of the hydraulic model analyses were vital in identifying the
hydraulic reaches where a given hydroelectric project could or could not potentially impact erosion
processes; identifying flow thresholds that were vital in determining the causes of erosion and the
impact of hydropower operations; and determining the location, duration, and magnitude of
hydraulic forces associated with erosion. Site-specific BSTEM results determined bank erosion
rates and erosion flow thresholds as well as dominant and contributing causes of erosion,
contributing factors, and contributing processes at each detailed study site.
The successful execution of the study provides a template from which other erosion causation
studies can follow to evaluate and identify the causes of erosion and determine the extent to which
hydropower operations impact erosion processes.
AUTHORS
Timothy Sullivan, GISP
Mr. Sullivan is a regulatory specialist with Gomez and Sullivan Engineers, DPC with experience
related to both traditional and pumped storage hydroelectric projects. He has served as the Project
Manager or technical lead for several erosion and sediment transport studies in the Northeast and
Mid-Atlantic United States and has experience in geomorphology; sediment transport; shoreline
erosion; hydrology; and hydraulics, including HEC-RAS modeling.
Andrew Simon, PhD, PE
Dr. Andrew Simon is an internationally recognized geomorphologist at Cardno in Oxford, MS.
He has 35 years of research experience which includes 16 years with the U.S. Geological Survey
and 16 years at the USDA-Agricultural Research Service, National Sedimentation Laboratory. He
is the author of more than 100 technical publications, has edited several books and journals and is
the senior developer of BSTEM.
Robert Simons, PhD, PE
Dr. R. K. Simons of Simons & Associates has extensive experience on hundreds of projects
covering various aspects of civil engineering focusing on the interaction and effect of projects on
watersheds, rivers, and estuaries related to changing hydrology, hydraulics, fluvial
geomorphology, sediment transport, erosion and sedimentation, flooding, and channel
stabilization.