Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Quantifying the Full Value of Hydropower in the y pTransmission Grid
Tom KeyP j t MProject ManagerIndustry Review at NHA Annual MeetingApril 6, 2011
Quantifying the Full Value of Hydropower in the Transmission Grid
Industry Review Meeting Wednesday April 6, 2011, 1-4 PM New York Roomdust y e e eet g ed esday p 6, 0 , e o oo
Time Topic Presenter
1:00 p.m. Welcome, Meeting Objectives Introductions
Tom Key, EPRI
1:10 p.m. Project Update Progress in year 1 Deliverable status Plans for year 2
Lindsey Rogers, EPRI
Plans for year 2
1:30 p.m. Defining the Value of Hydropower Strategy for defining hydropower value Modeling overview and insights so far
Tom Key, EPRIDaniel Brooks, EPRI
Insights from case studies so far Input on Hydro in US Markets Input on Hydro in European Markets
Pat March, HPPiBrendan Kirby, Kirby ConsultingDick Fisher, Consultant/Voith
3:00 p.m. Industry Round Table: Defining Value Getting beyond a “cost-basis” approach. Reconciling power market differences. Affecting choices for capacity expansion.
All
2© 2011 Electric Power Research Institute, Inc. All rights reserved.
Others..
4:00 p.m. Adjourn
Industry Cost Share and Case Study Commitmentsy
3© 2011 Electric Power Research Institute, Inc. All rights reserved.
Project Team
DOE Contracts ManagerDOE Technical Program Manager
Alejandro Moreno
EPRI Contracts Manager
David Morrisony
EPRI Project Manager
Thomas Key
Principal Investigator
Patrick March, HPPi
G id M d li d St di
Principal Investigator
Daniel Brooks, EPRI
DOE FFRDC Support
ORNL – Hydrologic Constraints
Grid Modeling and Studies
LCG Consulting
Sidart Deb
S i i J i
Hydropower Operation, Cost and Markets
HDR|DTA
Dr. Brennan Smith
Dr. Michael R. Starke
SNLA – Grids and MarketsSrinivas Jampani
Cascade Consulting
Charlie Clark, Tom Guardino
EPRI
Robert Rittase
Steve Brown
Brendan Kirby, Consultant
Markets
Dr. Abraham Ellis
Dr. Verne Loose
Dr Mark Ehlen
4© 2011 Electric Power Research Institute, Inc. All rights reserved.
EPRI
Aidan Tuohy
Matt Rylander
Consultant Dr. Mark Ehlen
Project Update
2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1
Month 13 - 24Month 1 - 12PROJECT GANTT CHART
CONTRACT START
Confidential Studies
TASK 3 E l t N ti l H d P ti i ti i A ill S i M k t
TASK 2: Establish Wide-Area Modeling Approach and Policy Scenarios
CONTRACT START
TASK 1: Prepare Industry Case Studies
2a
1a 1b 1c
2b
3a 3b 3cTASK 3: Evaluate National Hydropower Participation in Ancillary Services Markets
TASK 5: Develop Data Base of Cost Elements for Development Options
TASK 4: Analyze Systemic Operating Constraints on Hydropower Resources
TASK 6: Develop and Compute Scenario Simulations for WECC Projects
4b
5b
3a 3b
4a 4c
6b
5a 5c
6a
3c
5d
TASK 7: Determine Effects of Alternative Policy Scenarios on Value of Hydropower
TASK 6: Develop and Compute Scenario Simulations for WECC Projects
TASK 8: Define Strategies for Planning and Applying Hydropower Assets
TASK 9: Documentation and Dissemination of Results (See Project Milestones/Deliverables)
7b
8a
7a
ES Final
PROJECT MILESTONES/DELIVERABLESProject Review MeetingsIndustry Review Meetings
Internal Report Industry Review/Public Report
5© 2011 Electric Power Research Institute, Inc. All rights reserved.
Internal Report Industry Review/Public Report
Progress so far
Public Reports– Task 3a- Role of Hydropower in Existing Markets (11/30/2010) y p g ( )
http://prod.sandia.gov/techlib/access-control.cgi/2011/111009.pdf– Task 2b- Modeling Approach and Base Case Scenario (12/30/2010)
Internal ReportsIndustry Review Task Report on plan for documenting scheduling and operating– Industry Review Task Report on plan for documenting scheduling and operating practices- LCG (10/31/2010)
– Detailed plan for the scope and content of the hydropower cost database-HDR|DTA (12/31/2010)I l T k R h i d l ORNL (3/14/2011)– Internal Task Report on the water operations model- ORNL (3/14/2011)
– Industry Review Task Report on description of technologies and preliminary cost elements for team review and input - HDR|DTA (3/31/2011)
– Industry Review Task Report providing detailed definition and modeling plans for all y p p g g pscenarios including specifications of inputs and expected outputs- LCG (3/31/2011)
Other Milestones First Quarter 2011– Site Visits & Plant Case Studies (TVA, Ameren, NYPA, Exelon)
M h 14 & 15 M d li W k h f WECC
6© 2011 Electric Power Research Institute, Inc. All rights reserved.
– March 14 & 15 Modeling Workshop for WECC– NHA Industry Review Meeting
Project Update
2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1
Month 13 - 24Month 1 - 12PROJECT GANTT CHART
CONTRACT START
Confidential Studies
TASK 3 E l t N ti l H d P ti i ti i A ill S i M k t
TASK 2: Establish Wide-Area Modeling Approach and Policy Scenarios
CONTRACT START
TASK 1: Prepare Industry Case Studies
2a
1a 1b 1c
2b
3a 3b 3cTASK 3: Evaluate National Hydropower Participation in Ancillary Services Markets
TASK 5: Develop Data Base of Cost Elements for Development Options
TASK 4: Analyze Systemic Operating Constraints on Hydropower Resources
TASK 6: Develop and Compute Scenario Simulations for WECC Projects
4b
5b
3a 3b
4a 4c
6b
5a 5c
6a
3c
5d
TASK 7: Determine Effects of Alternative Policy Scenarios on Value of Hydropower
p p j
TASK 8: Define Strategies for Planning and Applying Hydropower Assets
TASK 9: Documentation and Dissemination of Results (See Project Milestones/Deliverables)
7b
8a
7a
ES Final
PROJECT MILESTONES/DELIVERABLESProject Review MeetingsIndustry Review Meetings
Internal Report Industry Review/Public Report
7© 2011 Electric Power Research Institute, Inc. All rights reserved.
Internal Report Industry Review/Public Report
Year 2 Reports & Project Milestone
Public Reports– Task 5c- Plant Cost Elements (5/30/2011)– Task 3b- Opportunities in Future Markets (6/30/2011)– Task 4c- Systemic Plant Operating Constraints (9/30/2011) – Task 6b- Modeling Results for Future Scenarios (9/30/2011)
Task 1c Case Studies on Plant Operations and Utilization (9/30/2011)– Task 1c- Case Studies on Plant Operations and Utilization (9/30/2011)– Task 8a- Planning and Operating Strategies (executive summary) (11/30/2011)– Task 9- Quantifying the Value of Hydropower in the Electric Grid: Final Report
(1/31/2012)I t l R tInternal Reports
– Internal Task Report with plant owners on Columbia (WECC) water operations model and verification of UPLAN hydro model- ORNL (6/30/2011)
– Internal Reports summarizing results after conducting site visits, completing data l i d i b k h d d li d kanalysis and reporting back to operators to support hydro modeling and market
participation reports- HPPi (8/31/2011)Other Milestones
– July 18: Industry Review meeting in conjunction with Hydrovision 2011- Sacramento, CA
8© 2011 Electric Power Research Institute, Inc. All rights reserved.
– September-October: East Hydropower Modeling Workshop- Review hydro participation eastern interconnect- Date and Location TBD
9© 2011 Electric Power Research Institute, Inc. All rights reserved.
Project Approach/Strategy for Defining Hydropower Valuey p
Year One:• Conduct specific plant studies to determine operation (HPPi)Conduct specific plant studies to determine operation (HPPi)• Model WECC electric sector to determine value of (LCG):
– Energy arbitrage value with LMP– Ancillary ServicesAncillary Services – Consider CO2, RPS, and future generation mix
• Determine cost of future hydro technology/assets (HDR|DTA)• Evaluate today’s market rules (Sandia)• Evaluate today s market rules (Sandia)
Year Two:• Run scenarios to determine future value (LCG)• Consider other values e g freq regulation reliability energy security (All)• Consider other values e.g. freq. regulation, reliability energy security (All)• Factor in systemic constraints and ways to minimize (ORNL)• Synthesis into valuing/methods report comparing alternatives (All)
10© 2011 Electric Power Research Institute, Inc. All rights reserved.
Challenges Ahead….Identified at WECC Workshop March 14-15, 2011p ,
• Define metrics/methods that will best quantify value of hydropowerhydropower
• Address questions about “cost-based” modeling and consider exogenous or other societal value basisg
• Better engage WECC, plant owners and balancing authorities to confirm plant modeling assumptionsC id th f t t f t d li• Consider other factors to energy futures modeling– Include potential limits on gas transmission– Define higher future NG cost scenarios– Define higher future NG cost scenarios – Adjust reserve requirements for future wind and solar
variability/uncertainty
11© 2011 Electric Power Research Institute, Inc. All rights reserved.
– Consider higher RPS…..and look out to 2030
Capacity Expansion Modeling to Define Future Generation Mix in WECC
• The Business As Usual scenario, with reference values and trends (e.g. moderate demand growth, existing renewable Reference Case ( g g genergy mandates)
Reference Case
• This scenario will model a fast, high growth recovery in demand from the economic downturn
High Demand/Energy* from the economic downturnDemand/Energy
• Requires 20% renewable energy for entire WECC• 33% RPS in CaliforniaFederal RPS*
• Models a cap on future CO2 emissions• Waxman-Markey bill for guidance
Carbon Constrained*Constrained
• Combine the impact of two future policy scenarios into one future
• Federal RPS + Carbon ConstrainedCombined Policy*
12© 2011 Electric Power Research Institute, Inc. All rights reserved.
* EPRI's NESSIE model shall be used to develop the expansion plan for these scenarios.
Scenario Planning Energy Futures
Reference Case High Demand/Energy Federal RPS Carbon Constrained Combined Policy
LCG PLATO Reference Values
Variable Unit Low (L) Mid (M) High (H)
Existing state Renewable Penetration as a Percentage of Total Energy Delivered*
Proposed Futures
• California RPS: 33% of energy
• WECC Mandate: 15% of energy
California RPS % - requirements in California - 33% RPS
-
WECC Mandate %Existing state requirements
20% by 2020 -
energy
• Average natural gas price: $7.1/MMBtu
Natural Gas ($/MMBtu)LCG PLATO Ref. -
20%LCG PLATO Ref.
LCG PLATO Ref. + 20%
Coal ($/MMBtu)LCG PLATO Ref. -
20%LCG PLATO Ref.
LCG PLATO Ref. + 20%
Fuel Cost
• Emissions• CO2 price: $0/ton• SO2 price: $58/ton• NOx price:
$3,000/ton (NOx season)$1 500/ton (Non NOx
Uranium ($/MMBtu)LCG PLATO Ref. -
20%LCG PLATO Ref.
LCG PLATO Ref. + 20%
SO2 ($/ton) LCG PLATO Ref.NOx ($/ton) LCG PLATO Ref.
Emissions Costs
13© 2011 Electric Power Research Institute, Inc. All rights reserved.
$1,500/ton (Non-NOxseason)
($ )CO2 ($/ton) 0 34
LCG PLATO - Plants, Loads, Assets, Transmission and Operations
EIA (AEO) Natural Gas Price Estimates
14© 2011 Electric Power Research Institute, Inc. All rights reserved.
NG Infrastructure
15© 2011 Electric Power Research Institute, Inc. All rights reserved.
Reference Case Inputs: Commodity Prices
Our intention is to determine “non controversial” commodity prices for the reference case and then investigate different prices in Task 6.
• 2020 Commodity Prices ($/MMBtu)
12 0
Natural Gas Prices $/MMBtu (2008‐2020)
– Natural Gas = 7.1
– Light Oil = 10
– Heavy Oil = 8
10.3
8.2
5 5 5.9 6.2 6.5 6.8 7.1
6 0
8.0
10.0
12.0
/MMBtu
– Heavy Oil = 8
– Coal = 1.5
– Uranium = 0.6
4.7 4.54.9 5.1 5.3 5.5
2.0
4.0
6.0$/
• CO2 emission allowances = $0/ton (reference case)
0.0
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
16© 2011 Electric Power Research Institute, Inc. All rights reserved.
( )
• Sources: EIA, NYMEX Futures
EIA Data on WECC PS Utilization
W E C C P u m p in g
5000000
6000000
W addellG ianelli
3000000
4000000
Pum
ped
Therm alitoO neillM t E lbertM orm on F latE as twood
2000000
3000000
Annu
al M
Wh Hors e M es a
Helm sG rand CouleeF lat ironE dward Hy att
0
1000000
1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009
Cas taicCabin Creek
17© 2011 Electric Power Research Institute, Inc. All rights reserved.
1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009
Ye a r
Capacity Additons by Decade Thru 2007
300,000 120%
250,000 100%
150,000
200,000
60%
80%
100,000 40%
‐
50,000
0%
20%
1890 1900 1910 1920 1930 1940 1950 1960 1970 1980 1990 2000
Coal Oil
Gas NuclearHydro Bio
18© 2011 Electric Power Research Institute, Inc. All rights reserved.
Geo WindSolar Percent capacity built since year
Hydro-related databases and data (Verne Loose, Sandia), )
Operational data and databases
•2010 ISO/RTO Metrics Report - hydro use by ISOs for all ISOs
•Bureau of Reclamation website @ http://www.usbr.gov/power/data/data.html
•1995-2007 capacity, gross generation, net generation; service records all facilitiesp y g g g
•Facility generation by Month (rolling for last 10 years)
•2007 Reclamation Data book has operational data on all facilities (might be new?)
•Power performance data sliced by size of unit and region•Power performance data sliced by size of unit and region
•WECC TEPPC website @ www.wecc.biz detailed navigation and credentials required
•USACE website @ http://www.nwd-wc.usace.army.mil/perl/dataquery.pl?k=id:GCL
•Has some operational data including hourly generation, pumped water, power produced, etc. however access to data is awkward and would be tedious
•Chelan and Grant Counties sites have bid data but only in aggregate terms
19© 2011 Electric Power Research Institute, Inc. All rights reserved.
•http://www.chelanpud.org/power-auction-product-description.html
Hydro data and databases, cont’d.
Operational data and databases
•EIA http://www.eia.doe.gov/cneaf/electricity/epm/table1_1.html
•aggregate hydro data that can be broken down by state, sector, type of owner
Other data and databases
•http://www.nwd-wc.usace.army.mil/tmt/
•stream flow and water quality for Columbia River.
•http://www nwrfc noaa gov/http://www.nwrfc.noaa.gov/
•contains detailed hydrological data
•http://www.nwd-wc.usace.army.mil/report/total.html
•mostly water quality
•http://waterwatch.usgs.gov/new/index.php?r=17&id=real
•stream flow data
20© 2011 Electric Power Research Institute, Inc. All rights reserved.
Synthesizing Results
Task 7 - Determine Effects of Alternative Policy, Market Rules & Scenarios on Value of Hydropower OutlineRules & Scenarios on Value of Hydropower Outline
• Market treatment of ancillary services– Current treatment and potential changes in ancillaryCurrent treatment and potential changes in ancillary
services- Kirby Consulting– Enhancements in plant utilization and optimization-
HPPiHPPi– Gaps in regulatory, market and scheduling structures-
Sandia• Future Scenario analysis of energy policy- LCG• Constraints on water usage- ORNL
21© 2011 Electric Power Research Institute, Inc. All rights reserved.
Synthesizing Results to Define Value
Current operations and optimizing plant performance (HPPi)
Modeling of current role of hydro (LCG)
p ( )
Recommendations Modeling Future
Scenarios of hydro Valuebased on gaps in reg, market and scheduling
structures (Sandia)
(LCG)
Today’s Market treatment oftreatment of
ancillary services (Kirby)
22© 2011 Electric Power Research Institute, Inc. All rights reserved.
Also considering future hydro costs (HDR|DTA) & water constraints (ORNL)
WECC Production Cost Model
Necessary Model Components• Transmission network
Detailed WECC Grid Simulation Model Needed to Quantify Hydro ValueTransmission network
– Associated physical constraints
• Conventional generation– Physical & economic characteristics
Needed to Quantify Hydro Value
– Fuel Prices– Participation in A/S
• Conventional & Pumped Storage Model– Conventional parameters
Markets&
TransmissionGeneration
– Conventional parameters– Water availability– Non-power constraints
• Wind and PV
&Physics
Temporal– Spatial and temporal characteristics
• Energy and A/S Markets– Relative economics and market rules
TemporalConstraints
23© 2011 Electric Power Research Institute, Inc. All rights reserved.
– A/S Requirements
LCG UPLAN Network Power Model (NPM)
• LCG’s UPLAN NPM platform– Security Constrained Unit Commit &Security Constrained Unit Commit &
Econ Dispatch (SCUC/SCED)– Co-optimized Energy & A/S Markets– Hourly Resolution
• A/S Provision– Reg Up/Dn, Spin, Non-Spin,
Replacement• Hydro ModelHydro Model
– Plant constraints– Schedules to accommodate variable
generation– Respond to price signals
• Pumped Storage Model– Price-driven logic
C id ffi i t
24© 2011 Electric Power Research Institute, Inc. All rights reserved.
– Considers energy efficiency, storage limits, and transmission limitations
Study Footprint and BA Interaction
• Model spans all of WECC– 37 BAs individual BAs37 BAs individual BAs– Modeled as 12 coordinated sub-
regions
• Day-Ahead Unit Commitment– Commits generation to meet
area load – UC without regard to cost of– UC without regard to cost of
neighboring generation
• Real-Time Dispatchp– Available generation transferred to
surrounding BAs if economic – Transmission losses and hurdle rates
respected
25© 2011 Electric Power Research Institute, Inc. All rights reserved.
respected
Study Year(s) and Scenarios/Sensitivities
• 2010 Reference CaseU d f d l lid ti / fid– Used for model validation/confidence
• 2020 Reference Case– 2019 WECC TEPPC transmission network– Generator characteristic data from LCG PLATO database
• EIA FERC 714 WECC et al• EIA, FERC 714, WECC, et. al.– Wind/PV build out to meet existing state RES for 2020– Existing plus Planned New Pumped Storage Plants
• Water Availability from EIA data
• 2020 Sensitivity Cases
26© 2011 Electric Power Research Institute, Inc. All rights reserved.
• 2020 Sensitivity Cases
2010 Generation Resource Mix
WECC has a diverse mix of resources in 2010. Gas and Hydro provide much of the capacity followed by coal.
40,000
45,000
50,000
Others
Oil PetroleumHydro29%
Nuclear4%
WECC Capacity by Fuel Type : 2010
Hydro29%
Nuclear4%
WECC Capacity by Fuel Type : 2010 Generation 2,437 Units
D t il d t
25 000
30,000
35,000
,
Gas Based
Wind
l
29%
Oil Petroleum0%
Others2%
Solar1%
29%
Oil Petroleum0%
Others2%
Solar1%
Detailed parameters Economic Operational
Loads Historical BA loads scaled to the
15,000
20,000
25,000 Solar
Hydro
Nuclear
Coal Based17%
Gas Based41%
Wind6%
Coal Based17%
Gas Based41%
Wind6%
Historical BA loads scaled to the study years
Distributed to nodal level using load flow cases
‐
5,000
10,000 Coal Based
Annual Peak Demand (MW)
27© 2011 Electric Power Research Institute, Inc. All rights reserved.
Comparison of 2010 & 2020 Installed Capacity
CC and CT technology additions to compensate for increasing demand and renewables
Category Diff (MW) Diff %Biomass 579 50%C l 460 1%
WECC Total100,000
120,000
Hydro
Solar
Wi d Coal 460 1%Combined Cycle 4,430 9%CT 5,131 25%CT Oil 2 0%Geothermal 2,253 76%Hydro 741 1%40,000
60,000
80,000 Wind
Pumped Storage
Geothermal
Biomass
NuclearMW
Hydro 741 1%IC ‐ 0%Nuclear ‐ 0%Pumped Storage ‐ 0%Solar 11,799 2469%Steam (1 812) ‐9%
‐
20,000
,Steam
IC
CT Oil
CT
Combined Cycle Steam (1,812) 9%Wind 11,860 105%
Figure: Installed Capacity in 2010 and 2020 by WECC sub‐region (MW)
2010 2020 2010 2020 2010 2020 2010 2020
AZ‐NM‐SNV CA‐MX US NWPP RMPA
Coal
WECC sub‐region
28© 2011 Electric Power Research Institute, Inc. All rights reserved.
gu e: sta ed Capac ty 0 0 a d 0 0 by CC sub eg o ( )
2020 Reference Case Renewable Additions
2020 RPS Targets for WECC States and ProvincesAs a Percent of Energy Sales Subject to RPS
IdahoColoradoCalifornia
British ColumbiaArizona
Texas EPEOregon
New MexicoNevada
MontanaMexico (CFE)
0 5 10 15 20 25 30 35
AlbertaWyoming
WashingtonUtah
Texas‐EPE
% Breakdown of Renewables by Type ‐ WECC wide
0 5 10 15 20 25 30 35
29© 2011 Electric Power Research Institute, Inc. All rights reserved.
Wind Solar Geothermal Biomass Small HydroBy Capacity 55.3% 25.7% 10.4% 4.3% 4.3%By Energy 43.7% 19.6% 22.7% 8.9% 5.1%
Characterization of Hydropower
• Conventional Hydro2006 EIA hi t i l thl it f t– 2006 EIA historical monthly capacity factors
– A/S capability Regulation, Spin, Non-Spin– Ramp rate (MW/Hr) – full load in 10 minutes
• Pumped Storage– Storage capacity (GWh): Weekly– Average Pumping size (MW)/Generating size = 0.8– Efficiency: 75%– A/S capability Regulation (only Gen mode existing; PlantA/S capability Regulation (only Gen mode existing; Plant
specific for expansion), Spin, Non-Spin– Ramp rate (MW/Hr) – full load in 10 minutes
30© 2011 Electric Power Research Institute, Inc. All rights reserved.
• Non-power constraints incorporated only to extent reflected in monthly EIA data
UPLAN NPM Temporal Resolution
• Hourly-resolution simulation
• Intra-hour flexibility represented by including intra-hour A/S requirements procured through DA marketA/S requirements procured through DA market– Reg Up & Reg Dn– Spin & Non-Spin
• Model does not represent individual unit efficiency (heat rate or water efficiency) impacts of intra-hr variabilityrate or water efficiency) impacts of intra hr variability
31© 2011 Electric Power Research Institute, Inc. All rights reserved.
Short-term Wind Forecast Error
• Used for fast schedulingscheduling
• Based on 10 minute wind data
• Forecast is 10• Forecast is 10 minute persistence
• Need to cover variability betweenvariability between the forecast and actual
32© 2011 Electric Power Research Institute, Inc. All rights reserved.
Hour-ahead wind forecast error
• For intra-hour scheduling– Can effect reserves by non-optimum unit commitment when the forecast isCan effect reserves by non optimum unit commitment when the forecast is
high– A way to insure enough capacity is committed– Using the same procedure as the short-term forecast error calculationg p
• For hourly scheduling – Predicts additional regulation required for the hour
33© 2011 Electric Power Research Institute, Inc. All rights reserved.
Incremental Operating Reserves for Wind
• Method for requiring additional operating reserves to maintain CPS1/CPS2 at similar pre wind levelsmaintain CPS1/CPS2 at similar pre-wind levels– regulating reserve based on short-term forecast error– regulating, spin, & supplemental reserve based onregulating, spin, & supplemental reserve based on
hour-ahead forecast error
• NREL Western Interconnect wind and wind forecast 10-min data
• 8760 reserve requirement time series developed for each sub-region incorporating additional reserve requirements
34© 2011 Electric Power Research Institute, Inc. All rights reserved.
for variability and uncertainty of VG in sub-region
Remaining Modeling Improvements/Questions
• Validation of 2010 reference case against historical hydro data
• Include incremental intra-hr reserve requirements to cover variability/uncertainty of wind/PV
• 2020 Transmission Upgrades beyond TEPPC to allow utilization of existing and future pumped storage plants
• Review treatment of existing hydro plants– Non-Power constraints– Availability
• Gas prices and impact of limited gas line flexibility
35© 2011 Electric Power Research Institute, Inc. All rights reserved.
Gas prices and impact of limited gas line flexibility
INSIGHTS FROM CASE STUDIESPat MarchPat MarchHPPi
36© 2011 Electric Power Research Institute, Inc. All rights reserved.
Case Studies Task: Purpose and Project Integration
Knowledge gaps that this task addresses:● Understanding market-related and non-market operational
patterns● Quantifying suboptimization due to these operational patterns● Quantifying suboptimization due to these operational patterns● Comparing near-real-time operations with hourly averages
Integration of task results into overall HGS Project:Integration of task results into overall HGS Project:● Assisting the verification of the UPLAN model for WECC● Providing “rules of thumb” for market-related suboptimization to
inform model assumptions for future scenarios● Providing recommendations for further investigation
37© 2011 Electric Power Research Institute, Inc. All rights reserved.
Technical Approach for Case Studies
Procedure:N ti t tilit ti i ti d d t fid ti lit t● Negotiate utility participation and data confidentiality agreements
● Conduct site visits, collect operational data, collect market data
● Conduct detailed performance analyses for each plant p y p
● Segregate data by operational pattern, conduct performance analyses
● Prepare confidential reports to utilities and HGS summary report using non-confidential resultsU i tUnique aspects:
● Utilization of optimization engine and automated data analysis engine to perform quantitative performance analyses
● Comparison of one-minute results with hourly averages
● Evaluation of multiple owner/operators, multiple market regions (and non-market regions), and multiple plant and unit types
38© 2011 Electric Power Research Institute, Inc. All rights reserved.
multiple plant and unit types
Case Study Locations for Hydro Grid Services Project
New York Power Auth.Blenheim-Gilboa
NYISO
New York Power Auth.Blenheim-Gilboa
NYISO
New York Power Auth.Blenheim-Gilboa
NYISO
New York Power Auth.Blenheim-Gilboa
NYISO
USACE
SWPA MISO
USACEHarry S. Truman
AmerenUEOsageMISO
AmerenUEOsageMISO
AmerenUETaum Sauk
MISO
AmerenUETaum Sauk
MISO
Chelan County PUDRocky Reach
WECC
Chelan County PUDRocky Reach
WECC
Chelan County PUDRocky Reach
WECC
Chelan County PUDRocky Reach
WECC
AmerenUEOsageMISO
AmerenUEOsageMISO
AmerenUETaum Sauk
MISO
AmerenUETaum Sauk
MISO
New York Power Auth.Bl h i Gilb
New York Power Auth.Blenheim-GilboaNew York Power Auth.
Bl h i GilbExelon Generation
Muddy Run-SWPA, MISO Blenheim-GilboaNYISO
Blenheim-GilboaNYISOBlenheim-Gilboa
NYISOMuddy Run-
PJM
Chelan County PUDRocky Reach
WECC
Chelan County PUDRocky Reach
WECC
Chelan County PUDRocky Reach
WECC
Exelon GenerationConowingo
PJM
Pacific Gas & ElectricHelms
CAISO, WECC
Pacific Gas & ElectricHelms
CAISO, WECC
Duke EnergyBad CreekSoutheast
Duke EnergyBad CreekSoutheast
Duke EnergyBad CreekSoutheast
Duke EnergyBad CreekSoutheast
New York Power Auth.New York Power Auth.BlenheimGilboaNew York Power Auth.TVARaccoon Mountain
39© 2011 Electric Power Research Institute, Inc. All rights reserved.
Blenheim-GilboaNYISO
Blenheim-GilboaNYISOBlenheim-Gilboa
NYISORaccoon Mountain-
SoutheastConventional HydroPumped-Storage
Example of Market Effects on Plant Operation
40© 2011 Electric Power Research Institute, Inc. All rights reserved.
Typical Operational Patterns for Generation and Pumping
Generation Energy vs Hour of Day
9,000
10,000Jan-Hourly Generation EnergyFeb Hourly Generation Energy
5,000
6,000
7,000
8,000
9,000
rgy
(MW
h)
Feb-Hourly Generation EnergyMar-Hourly Generation EnergyApr-Hourly Generation EnergyMay-Hourly Generation EnergyJun-Hourly Generation EnergyJul-Hourly Generation EnergyAug-Hourly Generation EnergySep-Hourly Generation Energy
0
1,000
2,000
3,000
4,000
0 5 10 15 20 25
Ener Oct-Hourly Generation Energy
Nov-Hourly Generation EnergyDec-Hourly Generation Energy
0 5 10 15 20 25
HourScroll Data '
Show AllSelect Series 'X-Axis Scale 'Pump Energy vs Hour of Day
20,000
25,000Jan-Hourly Pump Energy
Feb-Hourly Pump Energy
Mar-Hourly Pump Energy
10,000
15,000
Ener
gy (M
Wh)
Apr-Hourly Pump Energy
May-Hourly Pump Energy
Jun-Hourly Pump Energy
Jul-Hourly Pump Energy
Aug-Hourly Pump Energy
Sep-Hourly Pump Energy
41© 2011 Electric Power Research Institute, Inc. All rights reserved.
0
5,000
0 5 10 15 20 25
Hour
Oct-Hourly Pump Energy
Nov-Hourly Pump Energy
Dec-Hourly Pump Energy
Sc oll Data ' Select Se ies 'X A is Scale '
Process for Performance Analyses
OHPI Data Analysis ScriptOHPI Data Analysis ScriptOHPI Data Analysis ScriptOHPI Data Analysis ScriptOHPI Data Analysis ScriptOHPI Data Analysis ScriptOHPI Data Analysis Script
Archival Data (WaterView)
Time, Flow, Power, Gate, Blade, Head
OHPI Data Analysis Script
Archival Data (WaterView)
Time, Flow, Power, Gate, Blade, Head
OHPI Data Analysis Script
Archival Data (WaterView)
Time, Flow, Power, Gate, Blade, Head
OHPI Data Analysis Script
Archival Data (WaterView)
Time, Flow, Power, Gate, Blade, Head
OHPI Data Analysis Script
Archival Data (WaterView)
Time, Flow, Power, Gate, Blade, Head
OHPI Data Analysis Script
Archival Data (WaterView)
Time, Flow, Power, Gate, Blade, Head
DataWolff (Automated Data A l i S t )
Unit Characteristics File (WaterView)
Expected Flow, Power for Given HeadDataWolff
(Automated Data A l i S t )
Unit Characteristics File (WaterView)
Expected Flow, Power for Given HeadDataWolff
(Automated Data A l i S t )
Unit Characteristics File (WaterView)
Expected Flow, Power for Given HeadDataWolff
(Automated Data A l i S t )
Unit Characteristics File (WaterView)
Expected Flow, Power for Given HeadDataWolff
(Automated Data A l i S t )
Unit Characteristics File (WaterView)
Expected Flow, Power for Given HeadDataWolff
(Automated Data A l i S t )
Unit Characteristics File (WaterView)
Expected Flow, Power for Given Head
Analysis System)
Calculation Libraries
•Optimization Module (WaterView)•Averaging, Segmenting, Integration Routines
Analysis System)
Calculation Libraries
•Optimization Module (WaterView)•Averaging, Segmenting, Integration Routines
Analysis System)
Calculation Libraries
•Optimization Module (WaterView)•Averaging, Segmenting, Integration Routines
Analysis System)
Calculation Libraries
•Optimization Module (WaterView)•Averaging, Segmenting, Integration Routines
Analysis System)
Calculation Libraries
•Optimization Module (WaterView)•Averaging, Segmenting, Integration Routines
Analysis System)
Calculation Libraries
•Optimization Module (WaterView)•Averaging, Segmenting, Integration Routines g g, g g, g(DataWolff)
Analysis Results
Indicators - LEO, LRO, WCO for l d i id if i
g g, g g, g(DataWolff)
Analysis Results
Indicators - LEO, LRO, WCO for l d i id if i
Note:LEO = Lost Energy OpportunityLRO = Lost Revenue Opportunity
g g, g g, g(DataWolff)
Analysis Results
Indicators - LEO, LRO, WCO for l d i id if i
g g, g g, g(DataWolff)
Analysis Results
Indicators - LEO, LRO, WCO for l d i id if i
g g, g g, g(DataWolff)
Analysis Results
Indicators - LEO, LRO, WCO for l d i id if i
g g, g g, g(DataWolff)
Analysis Results
Indicators - LEO, LRO, WCO for l d i id if i
Note:LEO = Lost Energy OpportunityLRO = Lost Revenue Opportunity
42© 2011 Electric Power Research Institute, Inc. All rights reserved.
system, plants, and units, identifying major energy losses within system.system, plants, and units, identifying major energy losses within system.
LRO = Lost Revenue OpportunityWCO = Water Conservation Opportunity
system, plants, and units, identifying major energy losses within system.system, plants, and units, identifying major energy losses within system.system, plants, and units, identifying major energy losses within system.system, plants, and units, identifying major energy losses within system.
LRO = Lost Revenue OpportunityWCO = Water Conservation Opportunity
Typical Plant CharacteristicsOverall Plant Efficiency versus Head and Power
Efficiency vs. Power100
95
1140 ft
1200 ft
1260 ft
90
95
ency
(%)
85
90
Effic
ie
85
43© 2011 Electric Power Research Institute, Inc. All rights reserved.
800 500 1,000 1,500 2,000 2,500 3,000 3,500
Power (MW)
Example of Sampling Interval Analyses
Calculated Improvement versus Sampling Interval3.5
P t I t P t Ch i I t
2
2.5
3
)
Percent Improvement Percent Change in Improvement
0.5
1
1.5(%
-0.5
01 Min Snapshot 5 Min Snapshot 15 Min Snapshot 30 Min Snapshot Hourly Snapshot Hourly Avg
44© 2011 Electric Power Research Institute, Inc. All rights reserved.
Non-Market Example 1 ( Scheduling Analysis)
Actual vs Optimized Energy, Head 1175
7000 100
5000
6000
7000
d 11
75
94
96
98
100
ency
(%)
3000
4000
2010
-Ene
rgy
Hea
d
86
88
90
92
miz
ed P
lant
Effi
cie
0
1000
2000
0 200 400 600 800 1000 1200 1400 1600 1800
Apr
il
80
82
84
86
Opt
im
0 200 400 600 800 1000 1200 1400 1600 1800
Power (MW)
Scroll Data 'Show A
Select Series 'X-Axis Scale '
45© 2011 Electric Power Research Institute, Inc. All rights reserved.
Non-Market Example 2 (Operational Efficiency Analysis)
Load and Eff Improvement vs Time
500.0
600.0
4.00
4.50
5.00
200.0
300.0
400.0
Uni
t Pow
er (M
W)
1.50
2.00
2.50
3.00
3.50
ency
Impr
ovem
ent (
%)
0.0
100.0
04/03/09 09:09 04/03/09 10:21 04/03/09 11:33 04/03/09 12:45 04/03/09 13:57 04/03/09 15:09 04/03/09 16:21 04/03/09 17:33 04/03/09 18:45 04/03/09 19:57
Time
U
0.00
0.50
1.00 Effic
ie
Scroll Data ' Select Series 'X Axis Scale ' TimeScroll Data Show All
Select Series X-Axis Scale
46© 2011 Electric Power Research Institute, Inc. All rights reserved.
Market Example 1 ( Scheduling Analysis)
Actual vs Optimized Energy8000 95
6000
7000
8000
90
95
)
4000
5000
nerg
y H
ead
860
85
ant E
ffici
ency
(%)
2000
3000
July
2010
-E
80 Opt
imiz
ed P
la
0
1000
-100 0 100 200 300 400 500 600 700
P (MW)
75
47© 2011 Electric Power Research Institute, Inc. All rights reserved.
Power (MW)Scroll Data '
Show AlSelect Series '
Example Showing Volumetrically Derived Unit Characteristics
Flow vs Power6,000
Corrected Flow
2,000
3,000
4,000
5,000
Flow
(cfs
)
Expected FlowFlow - Curve Fit (cfs)
0
1,000
,
100 120 140 160 180 200 220 240 260 280 300
Power (MW)
Efficiency vs Power
85
90
95
100Volumetric Efficiency (cfs)Expected EfficiencyEfficiency-Curve Fit
60
65
70
75
80
Eff (
%)
48© 2011 Electric Power Research Institute, Inc. All rights reserved.
60100 120 140 160 180 200 220 240 260 280 300
Power (MW)
Market Example 2 (Scheduling Analysis)
Actual vs Optimized Energy
4000
4500
ad
95
cy
2000
2500
3000
3500
010-
Ener
gy H
ea11
00 85
90
d Pl
ant E
ffici
enc
(%)
500
1000
1500
Sept
embe
r2
80
Opt
imiz
ed
0-200 0 200 400 600 800 1000 1200 1400 1600
Power (MW)
75
Scroll Data 'Show All
Select Series 'X-Axis Scale '
49© 2011 Electric Power Research Institute, Inc. All rights reserved.
Market Example 2 (Operational Efficiency Analysis)
Load and Eff Improvement vs Time
300
350
400
16.0
18.0
20.0
%)
150
200
250
nit1
-Act
Uni
tPow
er
8.0
10.0
12.0
14.0
ency
Impr
ovem
ent (
%
0
50
100
11/10/08 07:37 11/10/08 08:49 11/10/08 10:01 11/10/08 11:13 11/10/08 12:25
U
0.0
2.0
4.0
6.0
Effic
ie
TimeScroll Data '
Show AllSelect Series 'X-Axis Scale '
50© 2011 Electric Power Research Institute, Inc. All rights reserved.
Market Example 3 (Scheduling Analysis, 95 ft GH, Non-aerating Operation in May)Non aerating Operation in May)
9516000
Actual vs Optimized Energy
9012000
14000
Non-aerating Operation
858000
10000
ant E
ffici
ency
(%)
Hea
d 95
804000
6000
Opt
imiz
ed P
la
May
2010
-Ene
rgy
H
75
80
0
2000
4000
51© 2011 Electric Power Research Institute, Inc. All rights reserved.
750-50 0 50 100 150 200 250 300 350 400
Power (MW)
Market Example 3 (Scheduling Analysis, 95 ft GH, Aerating Operation in July)g p y)
9516000
Actual vs Optimized Energy
Aerating Operation
9012000
14000
Aerating Operation
858000
10000
Plan
t Effi
cien
cy (%
)
gy H
ead
95
804000
6000
Opt
imiz
ed
July
2010
-Ene
r g
750
2000
-50 0 50 100 150 200 250 300 350 400
52© 2011 Electric Power Research Institute, Inc. All rights reserved.
50 0 50 100 150 200 250 300 350 400
Power (MW)
Preliminary Results from Case Studies
● Markets (particularly ancillary services markets) can lead to significant energy suboptimization of hydro assets at the unit level and the plant level suboptimization of hydro assets at the unit level and the plant level
● Profitability increases, but
● Quantitative maintenance cost increases are unknown
● Environmental operations can lead to significant energy suboptimization of hydro assets at the unit and plant levels
● Markets can lead to significant suboptimization of multiple hydro projects sharing a water resource
● “Smart” markets sho ld better address energ limited reso rces incl ding ● “Smart” markets should better address energy limited resources, including pumped-storage
● Opportunities for low-cost production improvement exist in both market and
53© 2011 Electric Power Research Institute, Inc. All rights reserved.
pp p pnon-market environments
OPERATIONS IN US MARKETS
Brendan KirbyBrendan KirbyKirby Consulting
54© 2011 Electric Power Research Institute, Inc. All rights reserved.
Power Systems Economics & Markets Define The “Need” For Energy Storage
• Pumped storage is an ideal power system resource– Flexible in both directions
gy g
– Fast and accurate• Wind and solar add variability and uncertainty to the power
system• Storage can help mitigate both variability and uncertaintyThe “need” for storage is an economic choice among
competing alternatives– Demand response– Transmission– Flexible generation– Improved operational practices
• Storage should (almost) always be used as a system resource rather than balancing wind or solar
55© 2011 Electric Power Research Institute, Inc. All rights reserved.
Changed System Conditions
• Energy arbitrage less attractive than in 1980s– Dramatic drop in gas price– Increased efficiency of CCGTs and CTs
Reduced capital cost for CCGTs and CTs– Reduced capital cost for CCGTs and CTs• (Increased capital cost of pumped storage)
– Gas is often on the margin at nightGas is often on the margin at night• Wind and solar increase variability• Response valued through ancillary services and
hourly/sub-hourly energy markets• Markets/reliability rules may not appropriately consider
inter-temporal storage constraints
56© 2011 Electric Power Research Institute, Inc. All rights reserved.
inter-temporal storage constraints
Power System Values Response to Variability and Uncertainty
• Ancillary services– Regulation: minute-to-minute AGC response
y
Regulation: minute to minute AGC response– Spinning reserve: On line, full response in 10 min– Non-spin: Full response in 10 min– Supplemental: Full response in 30 min
• Energy markets– Bilateral– Day-ahead hourly
Markets provide transparencyWholesale energy and ancillary
– Hour-ahead hourly– Subhourly
• Other servicesCapacity
service markets cover >½ of the U.S. load
Same needs exist in non-– Capacity– Blackstart– Voltage support and dynamic reactive– T&D deferral
Same needs exist in nonmarket areas
57© 2011 Electric Power Research Institute, Inc. All rights reserved.
– T&D deferral
Maximize Pumped Storage Profits With Energy & Ancillary Service Markets
• Power system values flexibility
Energy & Ancillary Service Markets
Power system values flexibility– Hour-ahead energy markets are more volatile than day-
ahead• 5 minute markets are even more volatile
– Regulation costs more than spinning reserve which costs more than non spincosts more than non-spin
– Prices change hourly• Maximize profits by selling the most profitable mix each p y g p
hour
58© 2011 Electric Power Research Institute, Inc. All rights reserved.
2002 2003 2004 2005 2006 2007 2008 2009 2010
Ancillary Services Show a
Annual Average $/MW-hr California (Reg = up + dn)
Regulation 26.9 35.5 28.7 35.2 38.5 26.1 33.4 12.6 10.6 Spin 4.3 6.4 7.9 9.9 8.4 4.5 6.0 3.9 4.1
Non Spin 1 8 3 6 4 7 3 2 2 5 2 8 1 3 1 4 0 6Show a Consistent
Pattern
Non-Spin 1.8 3.6 4.7 3.2 2.5 2.8 1.3 1.4 0.6 Replacement 0.90 2.9 2.5 1.9 1.5 2.0 1.4
ERCOT (Reg = up + dn) Regulation 16.9 22.6 38.6 25.2 21.4 43.1 17.0 18.1 Responsive 7.3 8.3 16.6 14.6 12.6 27.2 10.0 9.1
Year to Year R i t
Non-Spin 3.2 1.9 6.1 4.2 3.0 4.4 2.3 4.3 New York (east)
Regulation 18.6 28.3 22.6 39.6 55.7 56.3 59.5 37.2 28.8 Spin 3.0 4.3 2.4 7.6 8.4 6.8 10.1 5.1 6.2
Non Spin 1.5 1.0 0.3 1.5 2.3 2.7 3.1 2.5 2.3– Region to Region
Non Spin 1.5 1.0 0.3 1.5 2.3 2.7 3.1 2.5 2.3 30 Minute 1.2 1.0 0.3 0.4 0.6 0.9 1.1 0.5 0.1
MISO (day ahead) Regulation 12.3 12.2
Spin 4.0 4.0 N S i 0 3 1 5
Quicker Pays More
Non Spin 0.3 1.5 New England (Reg +”mileage”)
Regulation 54.64 30.22 22.26 12.65 13.75 9.26 7.07 Spin 0.27 0.41 1.67 0.71 1.75
10 Minute 0.13 0.34 1.21 0.47 1.15
59© 2011 Electric Power Research Institute, Inc. All rights reserved.
30 Minute 0.01 0.09 0.06 0.08 0.42
Energy Only PS Net Income & CyclingEnergy Only PS Net Income & Cycling
60© 2011 Electric Power Research Institute, Inc. All rights reserved.
MISO 2009
Power System Values Flexibility
61© 2011 Electric Power Research Institute, Inc. All rights reserved.
Preliminary Energy & Ancillary Service Results:
$/KW/Yr Total Energy Regulation Spin
MISO 2009 $40.63 $40.63
Energy & AS$49.89122%
$28.6672%
$9.4222%
$11.8129%122% 72% 22% 29%
NYISO 2009 $26.73 $26.73
Energy & AS$60.25 $10.27 $33.80 $16.18
Energy & AS 225% 38% 126% 61%
NYISO 2008 $49.39 $49.39
$97 15 $19 56 $54 30 $23 29Energy & AS
$97.15197%
$19.5640%
$54.30110%
$23.2947%
•Ancillary Services during generation only
62© 2011 Electric Power Research Institute, Inc. All rights reserved.
•$5/MWH minimum spread – 80% round trip efficiency
•16 hr storage
5 Minute Energy Markets May Offer Additional Profit Potential
• 2010 NYISO annual average energy prices:$ /– $42.05/MWH Day-ahead
– $42.82/MWH Hour-ahead$41 81/MWH 5 minute– $41.81/MWH 5-minute
• Average within-hour price range for 5-minute energy: $39.99/MWH
• NYISO settles on 5 minute prices– Other markets settle on hourly average
63© 2011 Electric Power Research Institute, Inc. All rights reserved.
Hydropower inHydropower in European M k tMarketsRICHARD FISHER & JIRI KOUTNIKVOITH HYDROVOITH HYDRO
64© 2011 Electric Power Research Institute, Inc. All rights reserved.
Comparisons, Europe to US
CanadaCanada
US
65© 2011 Electric Power Research Institute, Inc. All rights reserved.
Comparisons, Europe to US
Wind Power Production in the EU – TWH
Share of consumption according to the NREAPS
66© 2011 Electric Power Research Institute, Inc. All rights reserved.
IEWA:EU Energy Policy To 2050
Comparisons, Europe to US
67© 2011 Electric Power Research Institute, Inc. All rights reserved.
Comparisons, Europe to US ?
68© 2011 Electric Power Research Institute, Inc. All rights reserved.
Source: US Department of Energy
Total Generation Comparisons, Europe to US
US % Europe %
Carbon awareness Low HighFeed in Tariff Policy Some Yes
% renewabes 2000 9.4 13.9% renewables 2010 10.0 19.0% renewables 2020 13.7 32.0
% wind 2000 0 2 0 7% wind 2000 0.2 0.7% wind 2010 2.2 5.0% wind 2020 3.5 14.0
% Hydro 2000 7.0 10.6% Hydro 2010 6.0 10.2% Hydro 2020 5.9 10.0
69© 2011 Electric Power Research Institute, Inc. All rights reserved.
IEWA:EU Energy Policy To 2050
EIA: International Energy Outlook 2010, 2011
Volatility of wind & solar generation - 2010
70© 2011 Electric Power Research Institute, Inc. All rights reserved.
Source: REW: New Technologies 10-26-2010
Forecast wind power – next hours
Wind power
put i
n M
WO
utp
71© 2011 Electric Power Research Institute, Inc. All rights reserved.
Source: RWTH, Prof. Sauer
Feb 3 Mar 2
Grid requirements – grid code 2000 in Europe
• UCPTE (DVG) requirements– Primary control (second reserve (Power Quality) ) – ensures stable powerPrimary control (second reserve (Power Quality) ) ensures stable power
supply; (5% power increase in 30 s / 2,5% power increase in 5s)– Secondary control (minutes reserve (Bridging Power) ) – frequency error
compensation– Tertiary control (Energy Management) – covering of large power
differences (seasonal changes)
• 5-step-plan– step 1 49,8Hz Alarm, Usage of existing power, pump shut-off– step 2 49,0Hz 15-20% load rejection of the system load– step 3 48,7Hz the next 15-20% load rejection of the system load– step 4 48,4Hz the next 15-20% load rejection of the system load– step 5 47,5Hz Disconnection of the power plants from the grid
72© 2011 Electric Power Research Institute, Inc. All rights reserved.
4696e
Speed of Response of Different Conventional Solutions
Minimum Load Ramp Rate Type Minimum Load
Generating [% power per minute]
CCGT ~50% 2.5%
Gas Turbines >25% 4%
Coal >25% 1%
Nuclear ~50% 1.5%
Pumped Storage(conventional hydro) > 40% 100%
N t S i i t t diti f P d St H t t t diti f th
73© 2011 Electric Power Research Institute, Inc. All rights reserved.
Notes: Spinning reserve start condition for Pumped Storage, Hot start condition for others
Grid power control needs and pumped storage solutionsp p g
5% power increase
European i tms s minµs hours days
Power Quality Bridging Power Energy Management
requirement
Renewables - intermittency
Scheduling / economics / emissions
Transmission bottlenecks
Grid harmonics
Grid faults / stability
Conventional PS Units
Variable Speed & Ternary PS Units
Advanced Conventional PS Units
time scale
74© 2011 Electric Power Research Institute, Inc. All rights reserved.
time scale
Possible PS Unit Configurations Depending on Regulation Responsiveness and Grid Needsg p
– Conventional reversible unit & f
SlowerLess Flexible– Fast & frequent response reversible unit
– Conventional units in short circuit arrangementVariable Speed reversible unit
Less Flexible
– Variable Speed reversible unit– Ternary unit arrangement (Francis or Pelton) Faster
More Flexible
75© 2011 Electric Power Research Institute, Inc. All rights reserved.
Conventional Reversible Unit
– Typical of older fleet in world todaytoday
– Regulating in turbine modeRegulating in turbine mode only
– Load range for generation: • 50-100% power.
– Proven technology
76© 2011 Electric Power Research Institute, Inc. All rights reserved.
Advanced Conventional Reversible Unit
– Typical of new fixed speed conventional units todaytoday
– Designed for faster & more frequent responseP t k t l t• Penstocks, surge control systems
• Valves• Mode change & control systems• Materials
– Fast & frequent response duty leads to moreFast & frequent response duty leads to more stringent maintenance requirements
77© 2011 Electric Power Research Institute, Inc. All rights reserved.
Variable Speed Reversible Units
– Power regulation in the pump modemode
– Improved part-load efficiency inImproved part load efficiency in turbine mode
– Wider and more stable operation range in turbine mode
78© 2011 Electric Power Research Institute, Inc. All rights reserved.
4707e
Example of the Power Regulation Band in Pump Mode for a Variable Speed Machinep p
110
120
Max. Power limit
100
tput
[%]
80
90Ou
7080 85 90 95 100 105 110 115 120
Net Head [%]
79© 2011 Electric Power Research Institute, Inc. All rights reserved.
Net Head [%]
Ternary Arrangement
– Turbine + Generator +Torque Converter + Multistage pumpConverter Multistage pump
– Regulating in turbine and pump modes with hydraulic “short
Upper reservoir
modes with hydraulic short circuit”
Project Kops (Austria) recently– Project Kops (Austria) recently commissioned is latest version of this flexible arrangement.• No change of rotation direction Lo
wer
es
ervo
ir
• No change of rotation direction • Enables steepest load ramp• Quickest mode changes
r
80© 2011 Electric Power Research Institute, Inc. All rights reserved.
• Lowest losses4708e
Mode change times for various Unit concepts -“Flexibility”y
Pump Turbine time [seconds]T Mode change A B C D ET Mode change A B C D E
1 90 75 90 90 652 340 160 230 85 80
Standstill TU-Mode
Standstill PU-Mode
5 70 20 60 40 206 70 50 70 30 258 420 470 45 259 190 90 280 60 25
TU-Mode
PU-Mode
PU-Mode
SC-Mode
SC-Mode
PU M d
TU-Mode
9 190 90 280 60 25TU-ModePU-Mode
Reversible PTA – advanced conventional B – extra fast response conventionalp
C – VarSpeed,
Ternary setD – with hydraulic torque converter + hydr. short circuit, horiz, with Francis Turbine
81© 2011 Electric Power Research Institute, Inc. All rights reserved.
D with hydraulic torque converter hydr. short circuit, horiz, with Francis Turbine
E – same as E but vertical with Pelton Turbine
Revenue optimization - Feedback EoN
Reference: Dr Klaus Engels, Michael Brfuckner, Michaela Harasta and
Dr Tobias MirbachDr. Tobias Mirbach
Energy-Economic Evaluation of Pumped-Storage Plants
82© 2011 Electric Power Research Institute, Inc. All rights reserved.
Revenue optimization - Feedback Kops II
– Number of mode changes:t 500 th & it– up to 500 per month & unit
– Number of operating hours per unit per month:p g p p– Turbine mode - ~ 200 - 500– Pump mode - ~ 10 - 50– Sync. condens. - ~ 10– Hydraulic circuit - ~ 150 - 400
83© 2011 Electric Power Research Institute, Inc. All rights reserved.
Pumped storageNumber of NEW projects per Areap j p
• Projects with DoA 2000 – 2011O• Only NEW projects, total 31 projects
84© 2011 Electric Power Research Institute, Inc. All rights reserved.
Pumped storageNumber of NEW projects per Areap j p
• Projects with DoA 2011 – 2015O• Only NEW projects, total 31 projects
85© 2011 Electric Power Research Institute, Inc. All rights reserved.
Selected pumped storage projects in bidding / planning stage in Europe and North America todayp g g p y
Niederwartha
Vetaux R h
Atdorf
Kuethai II
Salamonde II
Waldeck 2+
Vetaux Hongrin
Rosshag
Kuethai IIWaldeck 2+????????
Green marked plants are reversible PS
86© 2011 Electric Power Research Institute, Inc. All rights reserved.
Yellow marked plants are ternary sets
Conclusion
• Renaissance of pumped storage in Europe due to increased wind power installation; load regimes are changedpower installation; load regimes are changed
• often, new pumped storage plants are using existing reservoirs, thus, full load hours of those reservoirs are reducedfull load hours of those reservoirs are reduced
• ternary sets provide more flexibility (faster mode switch times, regulation of pumping power)regulation of pumping power)
• trend with an increase of variable speed units
• waterways are to be designed depending on unit type selection
87© 2011 Electric Power Research Institute, Inc. All rights reserved.
Europe (Germany) plans
• 30% renewables by 2020%• 80% renewables by 2050
• long time storage necessary• 20 40 TWh might be needed (0 04 TWh available in• 20 – 40 TWh might be needed (0.04 TWh available in
Germany today)
88© 2011 Electric Power Research Institute, Inc. All rights reserved.
89© 2011 Electric Power Research Institute, Inc. All rights reserved.
90© 2011 Electric Power Research Institute, Inc. All rights reserved.
HydroPeak concept
Norway providing storage for Europe with:
Conventional Hydro
Pumped storage
91© 2011 Electric Power Research Institute, Inc. All rights reserved.
Industry Roundtable: Defining Value
• Getting beyond a “cost-basis” approachff• Reconciling power market differences
• Affecting choices for capacity expansion• Others• Others
92© 2011 Electric Power Research Institute, Inc. All rights reserved.
Synthesizing Results
Task 7 - Determine Effects of Alternative Policy, Market Rules & Scenarios on Value of Hydropower OutlineRules & Scenarios on Value of Hydropower Outline
• Market treatment of ancillary services– Current treatment and potential changes in ancillaryCurrent treatment and potential changes in ancillary
services- Kirby Consulting– Enhancements in plant utilization and optimization-
HPPiHPPi– Gaps in regulatory, market and scheduling structures-
Sandia• Future Scenario analysis of energy policy- LCG• Constraints on water usage- ORNL
93© 2011 Electric Power Research Institute, Inc. All rights reserved.
Synthesizing Results to Define Value
Current operations and optimizing plant performance (HPPi)
Modeling of current role of hydro (LCG)
p ( )
Recommendations Modeling Future
Scenarios of hydro ValueEnergy Security?
based on gaps in reg, market and scheduling
structures (Sandia)
(LCG)
Today’s Market treatment oftreatment of
ancillary services (Kirby)
Societal?
94© 2011 Electric Power Research Institute, Inc. All rights reserved.
Also considering future hydro costs (HDR|DTA) & water constraints (ORNL)
Action Items
• Look into why Europeans are building new PS plants and how they are operating and paying for them. What is driving it? (Dick Fisher,are operating and paying for them. What is driving it? (Dick Fisher, Brennan Smith, Rick Miller)– Understand compensation streams & market structure (Rick
Miller))– Determine if 2.5/30s reserve requirement is the driver in Europe
(Daniel Brooks, LCG, Brendan Kirby)• Follow up with ORNL to review the LCG hydro plant modelingFollow up with ORNL to review the LCG hydro plant modeling
parameters in WECC• Better cost information (Brennan Smith, HDR|DTA)• How do you monetize benefits (Brennan Smith)• How do you monetize benefits (Brennan Smith)
– How do you monetize benefits compared to others• Look into possibility of validating model with WAPA website SCADA
information (http://www wapa gov/crsp/opsmaintcrsp/scada htm)
95© 2011 Electric Power Research Institute, Inc. All rights reserved.
information (http://www.wapa.gov/crsp/opsmaintcrsp/scada.htm)
Together Shaping the Future of ElectricityTogether…Shaping the Future of Electricity
96© 2011 Electric Power Research Institute, Inc. All rights reserved.