Provisional Bills of Quantities Item Quantity Rate Amount No SECTION NO. 1 BILL NO. 1 PRELIMINARIES MEANING OF TERMS "TENDER / TENDERER" Any reference to the words "Tender" or "Tenderer" herein and/or in any other documentation shall be construed to have the same meaning as the words "Bid" or "Bidder" PRELIMINARIES The JBCC Preliminaries Code 2103, May 2005 edition for use with JBCC Principal Building Agreement Edition 4.1 Code 2101, March 2005 is taken to be incorporate herein. The tenderer is deemed to have referred to these documents for the full intent and meaning of each clause. These clauses are referred to by number and heading only. Where standard clauses or options are not applicable to the contract such modifications or corrections as are necessary are given under each relevant clause. Where an item is not relevant to this specific contract such item is marked "N/A" signifying "Not Applicable". PRICING OF PRELIMINARIES Should Option A, as set out in clause B10.3.1 hereinafter be used for the adjustment of preliminaries then each item priced is to be allocated to one or more of the three categories Fixed, Value Related or Time Related and the respective amounts entered in the space provided under each item Items not priced in these Preliminaries shall be deemed to be included elsewhere in these Bills of Quantities. SECTION A: JBCC PRINCIPAL BUILDING AGREEMENT DEFINITIONS A1.0 - DEFINITIONS AND INTERPRETATION Clause 1.0 Clause 1.1 Definition of "Commencement Date" is added: Carried to Collection R Section No. 1 Bill No. 1 PRELIMINARIES PROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOL LCAbn08-01 -55-

Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

  • Upload
    lecong

  • View
    227

  • Download
    10

Embed Size (px)

Citation preview

Page 1: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

SECTION NO. 1

BILL NO. 1

PRELIMINARIES

MEANING OF TERMS "TENDER / TENDERER"

Any reference to the words "Tender" or "Tenderer" herein and/or inany other documentation shall be construed to have the same meaningas the words "Bid" or "Bidder"

PRELIMINARIES

The JBCC Preliminaries Code 2103, May 2005 edition for use withJBCC Principal Building Agreement Edition 4.1 Code 2101, March2005 is taken to be incorporate herein. The tenderer is deemed tohave referred to these documents for the full intent and meaning ofeach clause. These clauses are referred to by number and headingonly. Where standard clauses or options are not applicable to thecontract such modifications or corrections as are necessary are givenunder each relevant clause. Where an item is not relevant to thisspecific contract such item is marked "N/A" signifying "NotApplicable".

PRICING OF PRELIMINARIES

Should Option A, as set out in clause B10.3.1 hereinafter be used forthe adjustment of preliminaries then each item priced is to beallocated to one or more of the three categories Fixed, Value Relatedor Time Related and the respective amounts entered in the spaceprovided under each item

Items not priced in these Preliminaries shall be deemed to be includedelsewhere in these Bills of Quantities.

SECTION A: JBCC PRINCIPAL BUILDING AGREEMENT

DEFINITIONS

A1.0 - DEFINITIONS AND INTERPRETATION

Clause 1.0

Clause 1.1 Definition of "Commencement Date" is added:

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 5 5 -

Page 2: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

"COMMENCEMENT DATE" means the date that the agreement,made in terms of the Form of Offer and Acceptance, comes into effect

Clause 1.1 Definition of "Construction Guarantee" is amended byreplacing it with the following:

"CONSTRUCTION GUARANTEE" means a guarantee at callobtained by the contractor from an institution approved by theemployer in terms of the employer's construction guarantee form asselected in the schedule

Clause 1.1 Definition of "Construction Period" is amended byreplacing it with the following:

"CONSTRUCTION PERIOD" means the period commencing onthe commencement date and ending on the date of practicalcompletion

Clause 1.1 Definition of "Corrupt Practice" is added:

"CORRUPT PRACTICE" means the offering, giving, receiving orsoliciting of anything of value to influence the action of a publicofficial in the procurement process or in contract execution.

Clause 1.1 Definition of "Fraudulent Practice" is added:

"FRAUDULENT PRACTICE" means a misrepresentation of factsin order to influence a procurement process or the execution of acontract to the detriment of any tenderer and includes collusivepractice among tenderers (prior to or after the tender submission)designed to establish tender prices at artificial non-competitive levelsand to deprive the tenderer of the benefits of free open competition.

Clause 1.1 Definition of "Interest" is amended by replacing it withthe following:

"INTEREST" means the interest rates applicable on this contract,whether specifically indicated in the relevant clauses or not, will bethe rate as determined by the Minister of Finance, from time to time,in terms of section 80(1)(b) of the Public Finance Management Act,1999 (Act No. 1 of 1999).

Clause 1.1 Definition of "Principal Agent" is amended by replacingit with the following:

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 5 6 -

Page 3: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

"PRINCIPAL AGENT" means the person or entity appointed by theemployer and named in the schedule. In the event of a principalagent not being appointed, then all the duties and obligations of aprincipal agent as detailed in the agreement shall be fulfilled by arepresentative of the employer as named in the schedule

Clause 1.1 Definition of "Security" is amended by replacing it withthe following:

"Security" means the form of security provided by the employer orcontractor, as stated in the schedule, from which the contractor o remployer may receiver expense or loss

Clause 1.6 is amended by replacing the words"prepaid registered post,telefax or e-mail" with "prepaid registered post or telefax"

No clause

A Fixed:.......... Values related:..........Time related:..........Item

OBJECTIVE AND PREPARATION

A2.0 - OFFER, ACCEPTANCE AND PERFORMANCE

Clause 2.0

B Fixed:.......... Value related:.......... Time related:.......... Item

A3.0 - DOCUMENTS

Clause 3.0

Clause 3.2.1 is amended by replacing"14.1" with "14.0"

Clause 3.7 is amended by the addition of the following:

The contractor shall supply and keep a copy of the JBCC Series2000 Principal Building Agreement and Preliminaries applicable tothis contract on the site, to which the employer, principal agent a n dagents shall have access at all times

Clause 3.10 is amended by replacing the second reference to "principal agent" with the word "employer"

C Fixed:.......... Value related:.......... Time related:.......... Item

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 5 7 -

Page 4: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

A4.0 - DESIGN RESPONSIBILITY

Clause 4.0

Clause 4.3 is amended by replacing it with the following:

No clause

A Fixed:........... Value related:..........Time related:.......... Item

A5.0 - EMPLOYER'S AGENTS

Clause 5.0

Clause 5.1.2 is amended to include clauses 32.6.3, 34.3, 34.4 and38.5.8

B Fixed:.......... Value related:........... Time related:.......... Item

A6.0 - SITE REPRESENTATIVE

Clause 6.0

C Fixed:.......... Value related:........... Time related:.......... Item

A7.0 - COMPLIANCE WITH REGULATIONS

Clause 7.0

Note: A separate clause has been included in Section C : SpecificPreliminaries of bills of quantities / lump sum document for thecontractor to have the opportunity to price for all the requirements ofthe Occupational Health and safety Act, Construction Regulations andHealth and Safety specification

D Fixed:.......... Value related:.......... Time related:......... Item

A8.0 - WORKS RISK

Clause 8.0

E Fixed:.......... Value related:........... Time related:.......... Item

A9.0 - INDEMNITIES

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 5 8 -

Page 5: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

Clause 9.0

A Fixed:.......... Value related:.......... Time related:.......... Item

A10.0 - WORKS INSURANCES

Clause 10.0

Clause 10.0 is amended by the addition of the following clauses:

10.5 Damage to the works

(a) Without in any way limiting the contractor's obligations in terms of the contract, the contractor shall bear the full risk ofdamage to and/or destruction of the works by whatever cause duringconstruction of the works and hereby indemnifies and holds harmlessemployer against any such damage. The c o n t r a c t o r shall take suchprecautions and security measures and other steps for the protectionand security of the works as the contractor may deem necessary

(b) The contractor shall at all times proceed immediately to removeor dispose of any debris arising from damage to or destruction of thworks and to rebuild, restore, replace and/or repair of the works

(c) The employer shall carry the risk of damage to or destruction ofthe works and materials paid for by the employer that is the result ofthe expected risks as set out in 10.6

(d) Where the employer bears the risk in terms of this contract, thecontractor shall, if requested to do so, reinstate any damage ordestroyed portions of the works and the costs of such reinstatementshall be measured and valued in terms of 32.0 hereof

Injury to Persons or loss of or damage to Properties

(a) The contractor shall be liable for and hereby indemnifies the theemployer against any liability, loss, claim or proceeding whetherarising in common law or statute, consequent upon personal injuriesto or death of any person whomsoever arising out of or in the courseof or caused by the execution of the works unless due to any act ornegligence of any person for whose actions the employer is legallyliable

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 5 9 -

Page 6: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

(b) The contractor shall be liable for and hereby indemnifies theemployer against any liability, loss, claim or proceeding consequentupon loss of or damage to any moveable or immovable or personalproperty or property contiguous to the site, whether belonging to orunder the control of the employer or any other body or person, arisingout of or in the course of or by reason of the execution of the worksunless due to any act or negligence of any person for whose actionsthe employer is legally liable

(c) The contractor shall, upon receiving a contract instruction f r o mthe principal agent, cause the same to be made good in a perfect andworkmanlike manner at his own cost and in default thereof theemployer shall be entitled to cause it to be made good and to recoverthe cost thereof from the contractor or to deduct the same fromamounts due to the contractor

(d) The contractor shall be responsible for the protection and safetyof such portions of the premises placed under his control by theemployer for the purpose of executing the works until the issue of thecertificate of practical completion

(e) Where the execution of the works involves the risk of removal oror interference with support to adjoining properties including land orstructures to be altered or added to, the contractor shall obtainadequate insurance and will remain adequately insured or insured tothe specific limit stated in the contract against the death of injury topersons or damage to such property consequent on such removal orinterference with the support until such portion of the works has beencompleted

(f) The contractor shall at all times proceed immediately at his owncost to remove or dispose of any debris and to rebuild, restore, replaceand/or repair such property and to execute the works

10.7 High risk insurance

In the event of the project being executed in a geological areaclassified as a "High Risk Area", that is an area which is subject tohighly unstable subsurface conditions that might result in catastrophicground movement evident by sinkhole or doline formation thefollowing will apply:

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 6 0 -

Page 7: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

10.7.1 Damage to the works

The contractor shall, from the commencement date of the worksuntil the date of the certificate of practical completion bear the fullrisk of and hereby indemnifies and holds harmless the employeragainst any damage to and/or destruction of the works consequentupon a catastrophic ground movement as mentioned above. Thecontractor shall take such precautions and security measures andother steps for the protection of the works as he may deem necessary

When so instructed to do so by the principal agent, the contractorshall proceed immediately to remove and/or dispose of any debrisarising from damage to or destruction of the works and to rebuild,restore, replace and/or repair the works, at the contractor's o w ncosts

10.7.2 Injury to persons or loss of or damage to property

The contractor shall be liable for and hereby indemnifies and holdsharmless the employer against any liability, loss, claim or proceedingarising at any time during the period of the contract whether arising incommon law or by statute, consequent upon personal injuries to or thedeath of any person whomsoever resulting from, arising out of orcaused by a catastrophic ground movement as mentioned above

The contractor shall be liable for and hereby indemnifies theemployer against any liability, loss, claim or proceeding consequentupon loss of or damage to any moveable or immovable or personalproperty or property contiguous to the site, whether belonging to orunder the control of the employer or any other body or personwhomsoever arising out of or caused by a catastrophic groundmovement , as mentioned above, which occurred during the period ofthe contract

10.7.3 It is the responsibility of the contractor to ensure that he hasadequate insurance to cover his risk and liability as mentioned in10.7.1 and 10.7.2. Without limiting the contractor's obligations interms of the contract, the contractor shall, within twenty one(21)calendar days of the commencement date but beforecommencement of the works, submit to the employer proof of suchinsurance policy, if requested to do so

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 6 1 -

Page 8: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

10.7.4 The employer shall be entitled to recover any and all lossesand/or damages of whatever nature suffered or incurred consequentupon the contractor's default of his obligations as set out in 10.7.1;10.7.2 and 10.7.3. Such losses or damages may be recovered from thecontractor or by deducting the same from any amounts still dueunder this contract or under any other contract presently or hereafterexisting between the employer and the contractor and for thispurpose all these be considered one indivisible whole

A Fixed:.......... Value related:.......... Time related:.......... Item

A11.0 - LIABILITY INSURANCES

Clause 11.0

B Fixed:.......... Value related:.......... Time related:.......... Item

A12.0 - EFFECTING INSURANCES

Clause 12.0

C Fixed:.......... Value related:.......... Time related:.......... Item

A13.0 - No Clause

A14.0 - SECURITY

Clause 14.0

Clause 14.1 - 14.8 are amended by replacing them with the following:

14.1 In respect of contracts with a contract sum up to R1 million, thesecurity to be provided by the contractor to the employer will bepayment reduction of five percent (5%) of the value certified in thepayment certificate (excluding VAT)

14.1.1 The payment reduction to the value certified in a paymentcertificate shall be mutatis mutandi in terms of 31.8(A)

14.1.2 The employer shall be entitled to recover expense and lossfrom the payment reduction in terms of 33.0 provided that theemployer complies with the provisions of 33.4 in which event theemployer's entitlement shall take precedence over his obligations torefund the payment reduction security or portions thereof to thecontract

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 6 2 -

Page 9: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

14.2 In respect of contracts with a contract sum above R1 million,the contractor shall have the right to select the security to beprovided in terms of 14.3, 14.4, 14.5, 14.6 or 14.7 as stated in theschedule. Such security shall be provided to the employer w i t h i ntwenty one (21) calender days from commencement date. Shouldthe contractor fail to select the security to be provided or should thecontractor fail to provide the employer with the selected securitywithin twenty one (21) calendar days f r o m commencement date, thesecurity in terms of 14.7 shall be deemed to have been selected

14.3 Where security as cash deposit of ten percent (10%) of thecontract sum (excluding VAT) has been selected:

14.3.1 The contractor shall furnish the employer with a cash depositequal in value to ten percent (10%) of the contract sum ( e x c l u d i n gVAT) within twenty one (21) calendar days f r o m commencementdate

14.3.2 Within twenty one (21) calendar days of the date of practicalcompletion of the works t h e employer shall reduce the cash depositto an amount equal to three percent (3%) of the contract value(excluding VAT), and refund the balance to the contractor

14.3.3 Within twenty one (21) calendar days of the date of finalcompletion of the works t h e employer shall reduce the cash depositto an amount equal to one percent (1%) of the contract value(excluding VAT), and refund the balance to the contractor

14.3.4 On the date of payment, of the amount in the final paymentcertificate, the employer shall refund the remainder of the cashdeposit to the contractor

14.3.5 The employer shall be entitled to recover expense and lossfrom the cash deposit in terms of 33.0 provided that the employercomplies with the provisions of 33.4 in which event the employer'sentitlement shall take precedence over his obligations to refund thecash deposit security or portions thereof to the contractor

14.3.6 The parties expressly agree that neither the employer nor thecontractor shall be entitled to cede the rights to the deposit to anythird party

14.4 Where security is a variable construction guarantee of tenpercent (10%) of the contract sum (excluding VAT)has been selected:

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 6 3 -

Page 10: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

14.4.1 The contractor shall furnish the employer with an acceptablevariable construction guarantee equal in value to ten percent (10%)of the contract sum (excluding VAT) within twenty one (21)calendar days from commencement date

14.4.2 The variable construction guarantee shall reduce and expirein terms of the Variable Construction Guarantee form included inthe invitation to tender

14.4.3 The employer shall return the variable constructionguarantee to the contractor within fourteen (14) calendar days of itexpiring

14.4.4 Where the employer has a right of recovery against thecontractor in terms of 33.0, the employer shall issue a writtendemand in terms of the variable construction guarantee

14.5 Where security as a fixed construction guarantee of fivepercent (5%) of the contract sum (excluding VAT) and a five percent(5%) payment reduction of the value certified in the paymentcertificate (excluding VAT) has been selected:

14.5.1 The contractor shall furnish a fixed construction guaranteeto the employer equal in value to five percent (5%) of the contractsum (excluding VAT)

14.5.2 The fixed construction guarantee shall come into force on thedate of issue and shall expire on the date of the last certificate ofpractical completion

14.5.3 The employer shall return the fixed construction guaranteeto the contractor within fourteen (14) calendar days of it expiring

14.5.4 The payment reduction of the value certified in a paymentcertificate shall be in terms of 31.8(A) and 34.8

14.5.5 Where the employer has a right of recovery against thecontractor in terms of 33.0, the employer shall be entitled to issue awritten demand in terms of the fixed construction guarantee or mayrecover from the payment reduction or may do both

14.6 Where security as a cash deposit of five percent (5%) of thecontract sum (excluding VAT) and a payment reduction of fivepercent (5%) of the value certified in the payment certificate(excluding VAT) has been selected:

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 6 4 -

Page 11: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

14.6.1 The contractor shall furnish the employer with a cash depositequal in value to five percent (5%) of the contract sum ( e x c l u d i n gVAT) within twenty one (21) calendar days f r o m commencementdate

14.6.2 Within twenty one (21) calendar days of the date of practicalcompletion of the works t h e employer shall refund the cash depositin total to the contractor

14.6.3 The payment reduction of the amount certified in a paymentcertificate shall be mutatis mutandi in terms of 31.8(A)

14.6.4 Where the employer has a right of recovery against thecontractor in terms of 33.0, the employer may issue a written noticein terms of 33.4 or may recover from the payment reduction or maydo both

14.7 Where security as a payment reduction of ten percent (10%) ofthe value certified in the payment certificate (excluding VAT) hasbeen selected:

14.7.1 The payment reduction of the value certified in a paymentcertificate shall be mutatis mutandi in terms of 31.8(B)

14.7.2 The employer shall be entitled to recover expense and lossfrom the payment reduction in terms of 33.0 provided that theemployer complies with the provisions of 33.4 in which event theemployer's entitlement shall take precedence over his obligations torefund the payment reduction or portions thereof to the contractor

14.8 Payments made by the guarantor to the employer in terms of thefixed or variable construction guarantee shall not prejudice therights of the employer or contractor in terms of this agreement

14.9 Should the contractor fail to furnish the security in terms of14.2, the employer, in his sole discretion and without notification tothe contractor, is entitled to change the contractor's selected form ofsecurity to that of a ten percent (10%) payment reduction of the valuecertified in the payment certificate (excluding VAT), whereafter14.7 shall be applicable

A Fixed:.......... Value related:.......... Time related:.......... Item

EXECUTION

A15.0 - PREPARATION AND EXECUTION OF THE WORKS

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 6 5 -

Page 12: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

Clause 15.0

Clause 15.1.1 is amended by replacing it with:

No clause

Clause 15.1.2 is amended by replacing it with:

The security selected in terms of 14.0

Clause 15.1 is amended by the addition of the following clause:

15.1.4 An acceptable health and safety plan, required in terms of theOccupational Health and Safety Act, 1993 (Act 85 of 1993), withintwenty one (21) calender days of commencement date

Clause 15.2.1 is amended by replacing it with the following clause:

Give the contractor possession of the site within ten (10) workingdays of the contractor complying with the terms of 15.1.4

A Fixed:.......... Value related:.......... Time related:.......... Item

A16.0 - ACCESS TO THE WORKS

Clause 16.0

B Fixed:.......... Value related:.......... Time related:.......... Item

A17.0 - CONTRACT INSTRUCTIONS

Clause 17.0

Clause 17.1.11 is amended by deleting the words "and theappointment of nominated and selected subcontractors"

C Fixed:.......... Value related:.......... Time related:.......... Item

A18.0 - SETTING OUT OF THE WORKS

Clause 18.0

D Fixed:.......... Value related:.......... Time related:.......... Item

A19.0 - ASSIGNMENT

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 6 6 -

Page 13: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

Clause 19.0

A Fixed:.......... Value related:.......... Time related:.......... Item

A20.0 - NOMINATED SUBCONTRACTORS

Clause 20.0

Clause 20.1.3 is amended by replacing it with the following:

No clause

Note: See item B9.1 hereinafter for adjustment of attendance onnominated subcontractors executing work allowed for underprovisional sums

B Fixed:.......... Value related:.......... Time related:.......... Item

A21.0 - SELECTED SUBCONTRACTORS

Clause 21.0

Clause 21 is amended by replacing it with:

No clause

C Fixed:.......... Value related:.......... Time related:.......... Item

A22.0 - EMPLOYER'S DIRECT CONTRACTORS

Clause 22.0

D Fixed:.......... Value related:.......... Time related:.......... Item

A23.0 - CONTRACTOR'S DOMESTIC SUBCONTRACTORS

Clause 23.0

E Fixed:.......... Value related:.......... Time related:.......... Item

COMPLETION

A24.0 - PRACTICAL COMPLETION

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 6 7 -

Page 14: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

Clause 24.0

A Fixed:.......... Value related:.......... Time related:.......... Item

A25.0 - WORKS COMPLETION

Clause 25.0

B Fixed:.......... Value related:.......... Time related:.......... Item

A26.0 - FINAL COMPLETION

Clause 26.0

Clause 26.1 is amended by inserting "#" next to 26.1.2

C Fixed:.......... Value related:.......... Time related:.......... Item

A27.0 - LATENT DEFECTS LIABILITY PERIOD

Clause 27.0

D Fixed:.......... Value related:.......... Time related:.......... Item

A28.0 - SECTIONAL COMPLETION

Clause 28.0

E Fixed:.......... Value related:.......... Time related:.......... Item

A29.0 - REVISION OF DATE FOR PRACTICALCOMPLETION

Clause 29.0

Clause 29.2.5 is amended by replacing it with:

No clause

F Fixed:.......... Value related:.......... Time related:.......... Item

A30.0 - PENALTY FOR NON-COMPLETION

Clause 30.0

G Fixed:.......... Value related:.......... Time related:.......... Item

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 6 8 -

Page 15: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

PAYMENT

A31.0 - INTERIM PAYMENT TO THE CONTRACTOR

Clause 31.0

Clause 31.5.2 is amended by replacing 14.7.1 with 14.0:

Clause 31.8 is amended by replacing it with the following twoalternative clauses:

Alternative A

318(A) Where a security is selected in terms of 14 .1; 14.5 or 14.6,the value of the works in terms of 31.4.1 and materials and goods interms of 31.4.2 shall be certified in full. The value certified shall besubject to the following percentage adjustments:

31.8(A).1 Ninety five percent (95%) of such value in interimpayment certificates issued up to the date of practical completion

31.8(A).2 Ninety seven percent (97%) of such value in interimpayment certificates issued on the date of practical completion a n dup to but excluding the date of final completion

31.8(A).3 Ninety nine percent (99%) of such value in interimpayment certificates issued on the date of final completion and upto but excluding the final payment certificate in terms of 34.6

31.8(A).4 One hundred percent (100%) of such value in the finalpayment certificate in terms of 34.6 except where the amountcertified is in favour of the employer. In such an event the paymentreduction shall remain at the adjustment level applicable to the finalpayment certificate

Alternative B

31.8(B) Where security as a payment reduction in terms of 14.7 hasbeen selected, the value of the works in terms of 31.4.1 and materialsand goods in terms of 31.4.2 shall be certified in full. The valuecertified shall be subject to the following percentage adjustments:

31.8(A).1 Ninety percent (90%) of such value in interim paymentcertificates issued up to the date of practical completion

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 6 9 -

Page 16: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

31.8(A).2 Ninety seven percent (97%) of such value in interimpayment certificates issued on the date of practical completion a n dup to but excluding the date of final completion

31.8(A).3 Ninety nine percent (99%) of such value in interimpayment certificates issued on the date of final completion and upto but excluding the final payment certificate in terms of 34.6

31.8(A).4 One hundred percent (100%) of such value in the finalpayment certificate in terms of 34.6 except where the amountcertified is in favour of the employer. In such an event the paymentreduction shall remain at the adjustment level applicable to the finalpayment certificate

Clause 31.12 is amended by deleting the following:

Payment shall be subject to the employer giving the contractor a taxinvoice for the amount due

A Fixed:.......... Value related:.......... Time related:.......... Item

A32.0 - ADJUSTMENT TO THE CONTRACT VALUE

Clause 32.0

Clause 32.5.1, 32.5.4 and 32.5.7 are amended by the addition of thefollowing at the end of the sentence:

"due to no fault of the contractor"

B Fixed:.......... Value related:.......... Time related:.......... Item

A33.0 - RECOVERY OF EXPENSE AND LOSS

C Fixed:.......... Value related:.......... Time related:.......... Item

A34.0 - FINAL ACCOUNT AND FINAL PAYMENT

Clause 34.0

Clause 34.1 is amended by removing "#" next to 34.1

Clause 34.2 is amended by inserting "#" next to 34.2

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 7 0 -

Page 17: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

Clause 34.8 is amended by deleting the words "where security as afixed construction guarantee in terms of 14.4 has been selected orwhere payment reduction has been applied in terms of 14.7.1"

Clause 34.13 is amended by replacing "seven (7) calendar days"with "twenty one (21) calendar days" and deleting the words "subjectto the employer giving the contractor a tax invoice for the amountdue"

A Fixed:.......... Value related:.......... Time related:.......... Item

A35.0 - PAYMENT TO OTHER PARTIES

Clause 35.0

B Fixed:.......... Value related:.......... Time related:.......... Item

CANCELLATION

A36.0 - CANCELLATION BY EMPLOYER - CONTRACTOR'SDEFAULT

Clause 36.0

Clause 36.1 is amended by the addition of the following clauses:

36.1.3 refuses or neglects to comply strictly with any of the conditionsof contract

36.1.4 estate being sequestrated, liquidated or surrendered in terms ofthe insolvency laws in force within the Republic of South Africa

36.1.5 in the judgement of the employer, has engaged in corrupt o rfraudulent practices in competing for or in executing the contract

Clause 36.3 is amended by removing the reference to "No clause" andreplacing the words"principal agent" with "employer"

Clause 36.0 is amended by the addition of the following clause:

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 7 1 -

Page 18: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

36.7 Notwithstanding any clause to the contrary, on cancellation ofthis agreement either by the employer or the contractor; or for anyreason whatsoever, the contractor shall on written instruction,discontinue with the works on a date stated and withdraw himselffrom the site. The contractor shall not be entitled to refuse towithdraw from the works on the grounds of any lien or right ofretention or on the grounds of any other right whatsoever

A Fixed:.......... Value related:.......... Time related:.......... Item

A37.0 - CANCELLATION BY EMPLOYER - LOSS ANDDAMAGE

Clause 37.0

Clause 37.3.5 is amended by replacing "ninety (90)" with "onehundred and twenty (120)"

Clause 37.0 is amended by the addition of the following clause:

37.5 Notwithstanding any clause to the contrary, on cancellation ofthis agreement either by the employer or the contractor; or for anyreason whatsoever, the contractor shall on written instruction,discontinue with the works on a date stated and withdraw himselffrom the site. The contractor shall not be entitled to refuse towithdraw from the works on the grounds of any lien or right ofretention or on the grounds of any other right whatsoever

B Fixed:.......... Value related:.......... Time related:.......... Item

A38.0 - CANCELLATION BY CONTRACTOR - EMPLOYER'SDEFAULT

Clause 38.0

Clause 38.5.4 is amended by replacing "ninety (90)" with "onehundred and twenty (120)"

Clause 38.5.4 is amended by the addition of the following clause:

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 7 2 -

Page 19: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

38.7 Notwithstanding any clause to the contrary, on cancellation ofthis agreement either by the employer or the contractor; or for anyreason whatsoever, the contractor shall on written instruction,discontinue with the works on a date stated and withdraw himselffrom the site. The contractor shall not be entitled to refuse towithdraw from the works on the grounds of any lien or right ofretention or on the grounds of any other right whatsoever

A Fixed:.......... Value related:.......... Time related:.......... Item

A39.0 - CANCELLATION - CESSATION OF THE WORKS

Clause 39.0

Clause 39.3.5 is amended by the addition of the following sentence:"within one hundred and twenty (120) working days of completion ofsuch a report"

B Fixed:.......... Value related:.......... Time related:.......... Item

DISPUTE

A40.0 - DISPUTE SETTLEMENT

Clause 40.0

Clause 40.2.2 is amended by replacing "one (1) year" with "three (3)years"

Clause 40.6 is amended by removing the reference to:

No clause

Clause 40.7.1 is amended by replacing "(10)" with "(15)" and by theaddition of the following:

Whether or not mediation resolves the dispute, the parties shall beartheir own costs concerning the meditation and equally share the costsof the mediator and related costs

C Fixed:.......... Value related:.......... Time related:.......... Item

SUBSTITUTE PROVISIONS

A41.0 - STATE CLAUSES

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 7 3 -

Page 20: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

Clause 41.0

A Fixed:.......... Value related:.......... Time related:.......... Item

CONTRACT VARIABLES

A42.0 - THE SCHEDULE (DPW-04EC)

Clause 42.0

Tenderers are referred to the Contract Data DPW-04(EC) forvariables pertaining to this contract

B Fixed:.......... Value related:.......... Time related:.......... Item

SECTION B: JBCC PRELIMINARIES

B1.0 - DEFINITIONS AND INTERPRETATION

B1.1 Definitions and interpretation

See also clause A1.0 of Section A for additional and/or amendeddefinitions which shall apply equally to this Section

C Fixed:.......... Value related:.......... Time related:.......... Item

B2.O - DOCUMENTS

B2.1 Checking of documents

D Fixed:.......... Value related:.......... Time related:.......... Item

B2.2 Provisional bills of quantities

E Fixed:.......... Value related:.......... Time related:.......... Item

B2.3 Availability of construction documentation

F Fixed:.......... Value related:.......... Time related:.......... Item

B2.4 Interests of agents

G Fixed:.......... Value related:.......... Time related:.......... Item

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 7 4 -

Page 21: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

B2.5 Priced documents

A Fixed:.......... Value related:.......... Time related:.......... Item

B2.6 Tender submission

Clause 2.6 is amended by replacing "JBCC Form of Tender" with"Form of offer and Acceptance DPW-07(EC)"

B Fixed:.......... Value related:.......... Time related:.......... Item

B3.0 - THE SITE

B3.1 Defined works area

C Fixed:.......... Values related:..........Time related:..........Item

B3.2 Geotechnical investigation

D Fixed:.......... Value related:.......... Time related:.......... Item

B3.3 Inspection of the site

Tenderers shall complete the Site Inspection Certificate (DPW16 EC)included in the tender documents and return the same with the tendersubmission

E Fixed:.......... Value related:.......... Time related:.......... Item

B3.4 Existing premises occupied

F Fixed:........... Value related:..........Time related:.......... Item

B3.5 Previous work - dimensional accuracy

G Fixed:.......... Value related:........... Time related:.......... Item

B3.6 Previous work - defects

H Fixed:.......... Value related:........... Time related:.......... Item

B3.7 Services - known

J Fixed:.......... Value related:.......... Time related:......... Item

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 7 5 -

Page 22: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

B3.8 Services - unknown

A Fixed:.......... Value related:........... Time related:.......... Item

B3.9 Protection of trees

B Fixed:.......... Value related:.......... Time related:.......... Item

B3.10 Articles of value

C Fixed:.......... Value related:.......... Time related:.......... Item

B3.11 Inspection of adjoining properties

D Fixed:.......... Value related:.......... Time related:.......... Item

B4.0 - MANAGEMENT OF CONTRACT

B4.1 Management of the works

E Fixed:.......... Values related:..........Time related:..........Item

B4.2 Programme of the works

F Fixed:.......... Value related:.......... Time related:.......... Item

B4.3 Progress meetings

G Fixed:.......... Value related:.......... Time related:.......... Item

B4.4 Technical meetings

H Fixed:........... Value related:..........Time related:.......... Item

B4.5 Labour and plant records

J Fixed:.......... Value related:........... Time related:.......... Item

B5.0 - SAMPLES, SHOP DRAWINGS ANDMANUFACTURER'S INSTRUCTIONS

B5.1 Samples of materials

K Fixed:.......... Values related:..........Time related:..........Item

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 7 6 -

Page 23: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

B5.2 Workmanship samples

A Fixed:.......... Value related:.......... Time related:.......... Item

B5.3 Shop drawings

B Fixed:.......... Value related:.......... Time related:.......... Item

B5.4 Compliance with manufacturer's instructions

C Fixed:........... Value related:..........Time related:.......... Item

B6.0 - TEMPORARY WORKS AND PLANT

B6.1 Deposits and fees

D Fixed:.......... Values related:..........Time related:..........Item

B6.2 Enclosure of the works

E Fixed:.......... Value related:.......... Time related:.......... Item

B6.3 Advertising

F Fixed:.......... Value related:.......... Time related:.......... Item

B6.4 Plant, equipment, sheds and offices

G Fixed:........... Value related:..........Time related:.......... Item

B6.5 Main notice board

H Fixed:.......... Value related:........... Time related:.......... Item

B6.6 Subcontractor's notice board

J Fixed:........... Value related:..........Time related:.......... Item

B7.0 - TEMPORARY SERVICES

B7.1 Location

K Fixed:.......... Values related:..........Time related:..........Item

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 7 7 -

Page 24: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

B7.2 Water

A Fixed:.......... Value related:.......... Time related:.......... Item

B7.3 Electricity

B Fixed:.......... Value related:.......... Time related:.......... Item

B7.4 Telecommunication facilities

C Fixed:........... Value related:..........Time related:.......... Item

B7.5 Ablution facilities

D Fixed:.......... Value related:........... Time related:.......... Item

B8.0 - PRIME COST AMOUNTS

B8.1 Responsibility for prime cost amounts

E Fixed:.......... Values related:..........Time related:..........Item

B9.0 - ATTENDANCE ON N/S SUBCONTRACTORS

B9.1 General attendance

F Fixed:.......... Values related:..........Time related:..........Item

B9.2 Special attendance

G Fixed:.......... Value related:.......... Time related:.......... Item

B9.3 Commissioning - fuel, water and electricity

H Fixed:.......... Value related:.......... Time related:.......... Item

B10.0 - FINANCIAL ASPECTS

B10.1 Statutory taxes, duties and levies

J Fixed:.......... Value related:.......... Time related:.......... Item

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 7 8 -

Page 25: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

B10.2 Payment of preliminaries

A Fixed:.......... Value related:.......... Time related:.......... Item

B10.3 Adjustment of preliminaries

Clauses B10.3.1 and B10.3.2 are amended by replacing "withinfifteen (15) working days of taking possession of the site" with "inhis priced bills of quantities / lump sum document submitted withhis tender offer"

B Fixed:.......... Value related:.......... Time related:.......... Item

B10.4 Payment certificate cash flow

C Fixed:.......... Value related:.......... Time related:.......... Item

B11.0 - GENERAL

B11.1 Protection of the works

D Fixed:.......... Value related:.......... Time related:.......... Item

B11.2 Protection / isolation of existing / sectionally occupiedworks

E Fixed:.......... Value related:.......... Time related:.......... Item

B11.3 Security of the works

F Fixed:.......... Value related:.......... Time related:.......... Item

B11.4 Notice before covering work

G Fixed:.......... Value related:.......... Time related:.......... Item

B11.5 Disturbance

H Fixed:.......... Value related:.......... Time related:.......... Item

B11.6 Environmental disturbance

J Fixed:.......... Value related:.......... Time related:.......... Item

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 7 9 -

Page 26: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

B11.7 Works cleaning and clearing

A Fixed:.......... Values related:..........Time related:..........Item

B11.8 Vermin

B Fixed:.......... Values related:..........Time related:..........Item

B11.9 Overhand work

C Fixed:.......... Value related:........... Time related:.......... Item

B11.10 Instruction manuals and guarantees

D Fixed:.......... Value related:.......... Time related:.......... Item

B11.11 As built information

E Fixed:........... Value related:..........Time related:.......... Item

B11.12 Tenant installations

F Fixed:.......... Values related:..........Time related:..........Item

B12.0 - SCHEDULE OF VARIABLES

B12.1 - Schedule of variables

G Fixed:.......... Value related:.......... Time related:.......... Item

This schedule contains all variables referred to in this document andis divided into pre-tender and post tender categories. The pre-tendercategory must be completed in full and included in the tenderdocuments. Both the pre-tender and post tender categories form partof these Preliminaries

Spaces requiring information must be filled in, shown as "notapplicable" or deleted and not left blank. Where choices are offered,the non-applicable items are to be deleted. Where insufficient space isprovided the information should be annexed hereto andcross-referenced to the applicable clause of the schedule. Key crossreference clauses are italicised in [] brackets

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 8 0 -

Page 27: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

12.1 PRE-TENDER INFORMATION

12.1.1 Provisional bills of quantities

[2.2] The quantities are provisional (yes)_____

12.1.2 Availability of construction documentation

[2.3] Construction documentation is complete (yes/no)_____

12.1.3 Interests of agents

[2.4] Details:

Not applicable

12.1.4 Defined works area

[3.1] Details:

Not applicable

12.1.5 Geotechnical investigation

[3.2] Details:

Not applicable

12.1.6 Existing premises occupied

[3.4] Specific Requirements:

The premises are occupied. Requirements of clauseapplicable

12.1.7 Previous work - dimensional accuracy

[3.5] Details:

The Works are new structures. Requirements of clauseare not applicable

12.1.8 Previous work - defects

[3.6] Details:

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 8 1 -

Page 28: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

Not applicable

12.1.9 Services - known

[3.7] Details:

Should the contractor encounter any existing services suchas underground cables, pipes or sewer during theexecution of the works he shall notify the principal agentimmediately and suspend all affected work in theimmediate vicinity until instruction to proceed has beengiven by the principal agent.

12.1.10 Protection of trees

[3.9] Details:

Not applicable

12.1.11 Inspection of adjoining properties

[3.11] Details:

Not applicable

12.1.12 Enclosure of the works

[6.2] Details:

Not applicable

12.1.13 Enclosure of the works

[6.4.3] Details:

Applicable

12.1.14 Offices

[6.5] Details:

Applicable

12.1.14 Main notice board

[6.5] Details:

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 8 2 -

Page 29: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

Applicable

12.1.15 Subcontractor's notice board

[6.6] A notice board is required (yes/no)_____

12.1.16 Water

[7.2] Option B (by Contractor ) (yes/no)_____

12.1.17 Electricity

[7.3] Option B (by Contractor) (yes/no)_____

12.1.18 Telecommunications

[7.4] Telephone (yes/no)_____

Facsimile (yes/no)_____

E - mail (yes/no)_____

12.1.19 Ablution facilities

[7.5] Option A (by contractor) (yes/no)_____

12.1.20 Protection of existing/sectionally occupied works

[11.2] Protection is required (yes/no)_____

12.1.21 Special attendance

[9.2] Subcontractor (1) details:

Subcontractor (2) details:

Subcontractor (3) details:

Subcontractor (4) details:

12.1.22 Protection of the works

[11.1] Specific requirements:

12.1.23 Disturbance

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 8 3 -

Page 30: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

[11.5] Specific requirements:

The contractor shall keep the site, structures, etc wellwatered during operations to prevent dust and shallprovide and erect and remove on completion of the worksall necessary temporary dust screens all to the satisfactionof the principal agent

12.1.24 Environmental disturbance

[11.6] Specific requirements:

B12.2 - POST-TENDER INFORMATION

12.2.1 - Payment of preliminaries

[10.2] Option A (prorated) (yes/no)_____

Option B (calculated) (yes/no)_____

12.2.2 - Adjustment of preliminaries

[10.3] Option A (three categories) (yes/no)_____

Option B (detailed breakdown) (yes/no)_____

12.2.3 - Additional agreed preliminaries items

Details:

Not applicable

SECTION C: SPECIFIC PRELIMINARIES

Section C contains specific preliminary items which apply to thiscontract except where N/A (Not Applicable) appears against an item

C1 CONTRACT DRAWINGS

The drawings issued with the tender documents do not comprise thecomplete set but serve as a guide only for tendering purposes and forindicating the scope of the work to enable the tenderer to acquainthimself with the nature and extent of the works and the manner inwhich they are to be executed

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 8 4 -

Page 31: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

Should any part of the drawings not be clearly understood by thetenderer he shall, before submitting his tender, obtain clarification inwriting from the principal agent

A Fixed:.......... Value related:.......... Time related:.......... Item

C2 GENERAL PREAMBLES

The document "Specification of Materials and Methods to be used(PW371)" is obtainable on request from the head office and allregional offices of the Department, and shall be read in conjunctionwith the bills of quantities and be referred to for the full descriptionsof work to be done and materials to be used

B Fixed:.......... Value related:.......... Time related:.......... Item

C3 TRADE NAMES

Wherever a trade name for any product has been described in the billsof quantities, the tenderer's attention is is drawn to the fact that anyother product of equal quality may be used subject to the writtenapproval of the principal agent being obtained prior to the closingdate for submission of tenders

If prior written approval for an alternative product is not obtained, theproduct described shall be deemed to have been tendered for

C Fixed:.......... Value related:.......... Time related:.......... Item

C4 IMPORTED MATERIALS AND EQUIPMENT

Where imported items are listed in the tender documents, the tenderershall provide all the information called for, failing which the price ofany such item, materials or equipment shall be excluded fromcurrency fluctuations. (refer to Schedule of Imported Materials andEquipment DPW-23(EC) to be completed by tender)

Notwithstanding any provisions elsewhere regarding the adjustment ofcontract prices, the price of any item, materials or equipment listed interms of this clause shall be executed from the Contract PriceAdjustment Provisions (if applicable)

D Fixed:.......... Value related:.......... Time related:.......... Item

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 8 5 -

Page 32: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

C5 VIEWING THE SITE IN SECURITY AREAS

The site is situated in a security area and the tender must arrange withthe unit commander or other responsible officer to obtain permissionto enter the site for tendering purposes

A Fixed:.......... Value related:.......... Time related:.......... Item

C6 COMMENCEMENT OF WORKS IN SECURITY AREAS

As the works falls within a security area the contractor must give theunit commander or other responsible officer notice beforecommencement of the works. Should the contractor fail to makesuch arrangements, admission to the site may be refused and anyadditional costs will be for the contractor's account

B Fixed:.......... Value related:.......... Time related:.......... Item

C7 ENTRANCE PERMITS TO SECURITY AREAS

As the works falls within a security area the contractor shall obtainentrance permits for his personnel and workmen entering the area andshall comply with all regulations and instructions which may be usedfrom time to time regarding the protection of persons and propertyunder the control of the Defence Force

C Fixed:.......... Value related:.......... Time related:.......... Item

C8 SECURITY CHECK OF PERSONNEL

The principal agent may require the contractor to have hispersonnel and workmen, or a certain number of them, securityclassified

In the event of the principal agent requesting the removal of a personor persons from the works for security reasons, the contractor shalldo so forthwith and shall thereafter ensure that such person or personsare denied access to the works and the site and/or to any document orinformation relating to the works

D Fixed:.......... Value related:.......... Time related:.......... Item

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 8 6 -

Page 33: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

C9 PROHIBITION OF TAKING PHOTOGRAPHS

In terms if article 119 of the Defence Act, 44 of 1957, it is prohibitedto sketch or to take photographs of any military site or installation orany building or civil works thereon or to be in possession of a cameraor other apparatus used for taking of photographs except whenauthorised thereto by or on behalf of the Minister

The same prohibition is also applicable to all correctional institutionsin terms of article 44.1(e) of the Correctional Services Act 8 of 1959

A Fixed:.......... Value related:.......... Time related:.......... Item

C10 HIV/AIDS AWARENESS

It is required of the contractor to thoroughly study the HIV/AIDSSpecification (PW 1544) of the Department that must be read togetherwith and is deemed to be incorporated under this Section of bills ofquantities / lump sum document. Provision for pricing ofHIV/AIDS awareness is made under items C10.1 to C10.5 hereafterand it is explicitly pointed out that all requirements of theaforementioned specification are deemed to be priced hereunder, asthe said items represent the only method of measurement and noadditional items or extras to the contract in this regard shall beentertained

The contractor must take note that compliance with the HIV/AIDSSpecification is compulsory. In the event of partial or totalnon-compliance, the principal agent, not withstanding the provisionsof clause A 31.0 of Section A or any other clause to the contrary,reserves the right to delay issuing any progress payment certificateuntil the contractor provides satisfactory proof of compliance. Thecontractor shall not be entitled to any compensation of whatsoevernature, including interest, due to such delay of payment

B Fixed:.......... Value related:.......... Time related:.......... Item

C10.1 AWARENESS CAMPAIGN

Selection, appointment, briefing and making available of AwarenessCampaign including provision of all relevant services, all inaccordance with the HIV/AIDS specification

C Fixed:.......... Value related:.......... Time related:.......... Item

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 8 7 -

Page 34: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

C10.2 AWARENESS WORKSH0PS

Selection and appointment of a competent Service Provider approvedby the principal agent, provision of a Service Provider WorkshopPlan and a suitable venue, conducting of awareness workshops bymeans of traditional and/or modern multi-media techniques, includingfollow-up courses, making available all tuition material andperforming assessment procedures, all in accordance with theHIV/AIDS Specification

A Fixed:.......... Value related:.......... Time related:.......... Item

C10.3 POSTERS, BOOKLETS, VIDEOS, ETC

Provision, displaying, maintaining and replacing when necessary offour plastic laminated posters, booklets and educational videos, etcfor the duration of the construction period, all in accordance with theHIV/AIDS Specification

B Fixed:.......... Value related:.......... Time related:.......... Item

C10.4 ACCESS TO CONDOMS

Provision and maintenance of condom dispensers fixed in position,including male and female condoms, replenishing male and femalecondoms on a daily basis as required for the duration of theconstruction period, all in accordance with the HIV/AIDSSpecification

C Fixed:.......... Value related:.......... Time related:.......... Item

C10.5 MONITORING

Monitoring HIV/AIDS awareness of workers, providing the principalagent with access to information including making available allreports, thoroughly completed and reflecting the correct information,for the duration of the construction period and close out, all inaccordance with the HIV/AIDS Specification

D Fixed:.......... Value related:.......... Time related:.......... Item

C11 OCCUPATIONAL HEALTH AND SAFETY ACT

The contractor shall comply with all the requirements set out in theConstruction Regulations, 2003 issued under the Occupational Healthand Safety Act, 1993 (Act No 85 of 1993).

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 8 8 -

Page 35: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

It is required of the contractor to thoroughly study the Health andSafety Specification that must be read together with and is deemed tobe incorporated under this Section of the bills of quantities/ lumpsum document.

The contractor must take note that compliance with the OccupationalHealth and Safety Act, Construction Regulations and Health andSafety Specification is compulsory. In the event of partial or totalnon-compliance, the principal agent, notwithstanding the provisionsof clause A31.0 of Section A or any other clause to the contrary,reserves the right to delay issuing any progress payment c e r t i f i c a t euntil the contractor provides satisfactory proof of compliance. Thecontractor shall not be entitled to any compensation of whatsoevernature, including interest, due to such delay of payment.

Provision for pricing of the Occupational Health and Safety Act,Construction Regulations and Health and Safety Specification is madeunder this clause and it is explicitly pointed out that all requirementsof the aforementioned are deemed to be priced hereunder and noadditional claims in this regard shall be entertained.

A Fixed:.......... Value related:.......... Time related:.......... Item

Carried to Collection R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 8 9 -

Page 36: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 1

Preliminaries

Bill No. 1

PRELIMINARIES

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -55-

-56-

-57-

-58-

-59-

-60-

-61-

-62-

-63-

-64-

-65-

-66-

-67-

-68-

-69-

-70-

-71-

-72-

Carried Forward R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 9 0 -

Page 37: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 1

Preliminaries

Bill No. 1

PRELIMINARIES

COLLECTION

Page AmountNo

Brought Forward R

Total Brought Forward from Page No. -73-

-74-

-75-

-76-

-77-

-78-

-79-

-80-

-81-

-82-

-83-

-84-

-85-

-86-

-87-

-88-

Carried Forward R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 9 1 -

Page 38: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 1

Preliminaries

Bill No. 1

PRELIMINARIES

COLLECTION

Page AmountNo

Brought Forward R

Total Brought Forward from Page No. -89-

Carried to Final Summary R Section No. 1Bill No. 1PRELIMINARIESPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 9 2 -

Page 39: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

SECTION NO. 2

BILL NO. 1

EARTHWORKS

NOTE: The contractor is advised to study the Model Preambles forTrades before pricing this bill

NOTE: All unit rates must take into account and will be assumed toinclude all applicable taxes including Value Added Tax Act. Noadditional claims relating to taxes will be entertained

NOTE: The contactor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies between thebill and the drawings the contractor must notify the Principal Agent

N O T E : Unless otherwise stated herein, all items in this bill shall bedeemed to fall into Work Group No.104 for CPAP formula purposes

N O T E : Unless otherwise stated herein, all work in this trade shall beexecuted in accordance with the guidelines of the Expanded PublicWorks Programme second edition of July 2005

SUPPLEMENTARY PREAMBLES

Nature of ground

A soils investigation test has been carried out on site by the engineerand the report is available on request at the offices of the engineer.Descriptions of excavations shall be deemed to include all groundconditions classifiable as "Earth" described in the above report andwhere conditions of a more difficult character are indicated these areseparately measured

Carting away of excavated material

Descriptions of carting away of excavated material shall be deemed toinclude loading excavated material onto trucks directly from theexcavations or, alternatively, from stock piles situated on the buildingsite and dumping on areas to be indicated by the Principal Agent

EXCAVATION, FILLING, ETC

Carried to Collection R Section No. 2Bill No. 1EARTHWORKSPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 9 3 -

Page 40: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

Excavation in earth not exceeding 2m deep

A Trenches m3 2

Extra over trench and hole excavations in earth for excavation in

B Soft rock m3 0,2

C Hard rock m3 0,1

Extra over all excavations for carting away

D Surplus material from excavations and/or stock piles on site to adumping site to be located by the contractor m3 1

Risk of collapse of excavations

E Sides of trench and hole excavations not exceeding 1,5m deep m2 4

Keeping excavations free of water

F Keeping excavations free of water other than subterranean water Item

FILLING ETC

Earth filling obtained from the excavations and/or prescribedstock piles on site, compacted to 90% Mod AASHTO density

G Under floors, steps, pavings, etc m3 1

Coarse river sand filling supplied by the contractor

H Under floors, etc m3 0,3

Compaction of surfaces

J Compaction of ground surface under floors, etc m2 5

SOIL POISONING

Soil insecticide

K Under floors etc including forming and poisoning shallow furrowsagainst foundation walls etc, filling in furrows and ramming m2 5

L To bottoms and sides of trenches, holes, etc m2 4

Carried to Collection R Section No. 2Bill No. 1EARTHWORKSPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 9 4 -

Page 41: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

Bill No. 1

EARTHWORKS

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -93-

-94-

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 1EARTHWORKSPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 9 5 -

Page 42: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

SECTION NO. 3

BILL NO. 2

CONCRETE, FORMWORK AND REINFORCEMENT

NOTE: The contractor is advised to study the Model Preamblesfor Trades before pricing this bill

NOTE: All unit rates must take into account and will be assumedto include all applicable taxes including Value Added Tax Act.No additional claims relating to taxes will be entertained

NOTE: The contractor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrapencies betweenthe bill and the drawings the contractor is must notify the PrincipalAgent

N O T E : Unless otherwise stated herein, all items in this bill shallbe deemed to fall into Work Group No.110 for CPAP formulapurposes

N O T E : Unless otherwise stated herein, all work in this trade shallbe executed in accordance with the guidelines of the ExpandedPublic Works Programme second edition of July 2005

SUPPLEMENTARY PREAMBLES

"Foamcement" lightweight concrete

"Foamcement" lightweight concrete is to have a density of600kg/m3 for the top 50mm and 400kg/m3 for the remainingthickness. The minimum thickness at outlets, channels, etc shallbe 50mm

Concrete batching

Unless otherwise agreed in writing by the Engineer all cement andaggregate shall be batched by weight using an acceptable concretebatching' plant. Details of the proposed type of batching plantmust be submitted with the tender

Carried to Collection R Section No. 2Bill No. 2CONCRETE, FORMWORK AND REINFORCEMENTPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 9 6 -

Page 43: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Cost of tests

The costs of making, storing and testing of concrete test cubes asrequired under clause 7 "Tests" of SABS 1200 G shall include thecost of providing cube moulds necessary for the purpose, fortesting costs and for submitting reports on the tests to the architect. The testing shall be undertaken by an independent firm orinstitution nominated by the contractor to the approval of thearchitect. (Test cubes are measured separately)

Formwork

Descriptions of formwork shall be deemed to include use andwaste only (except where described as "left in" or "permanent"),for fitting together in the required forms, wedging, plumbing andfixing to true angles and surfaces as necessary to ensure easyrelease during stripping and for reconditioning as necessary beforere-use. The vertical strutting shall be carried down to suchconstruction as is sufficiently strong to afford the required supportwithout damage and shall remain in position until the newlyconstructed work is able to support itself

Formwork to soffits of solid slabs etc shall be deemed to be toslabs not exceeding 250mm thick unless otherwise described

Formwork to sides of bases, pile caps, ground beams, etc will onlybe measured where it is prescribed by the engineer for designreasons. Formwork necessitated by irregularity or collapse ofexcavated faces will not be measured and the cost thereof shall bedeemed to be included in the allowance for taking the risk ofcollapse of the sides of the excavations, provision for which ismade in "Earthworks"

---------------

UNREINFORCED CONCRETE CAST AGAINSTEXCAVATED SURFACES

15MPa/19mm Concrete

A Surface blinding under footingsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 0 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m3 0,3

Carried to Collection R Section No. 2Bill No. 2CONCRETE, FORMWORK AND REINFORCEMENTPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 9 7 -

Page 44: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

25MPa/19mm Concrete

A Strip footingsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m3 1

B RampsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 7 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m3 7

C Surface beds on waterproofingA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 6 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m3 6

TEST BLOCK

D Making and testing 150 x 150 x 150mm concrete strength testcube

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 6 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 6

CONCRETE SUNDRIES

Finishing top surfaces of concrete smooth with a wood float

E Surface beds, slabs, etcA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1384 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 1 384

F Surface beds, slabs, etc to fallsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 109 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 109

NOTE: All items in this section shall be deemed to fall intoWork Group No.111 for CPAP formula purposes.

Carried to Collection R Section No. 2Bill No. 2CONCRETE, FORMWORK AND REINFORCEMENTPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 9 8 -

Page 45: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

ROUGH FORMWORK (DEGREE OF ACCURACY II)

Rough formwork to sides

A Strip footingsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 5 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 5

MOVEMENT JOINTS ETC

Expansion joints with "Flexcell" joint filler between verticalconcrete and brick surfaces

B 10mm Joints not exceeding 300mm highA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 29 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 29

Expansion joints with "Flexcell" joint filler vertical betweenconcrete surfaces

C 10mm Joints exceeding 300mm wideA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 4 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 4

Isolation joints with 10mm softboard between horizontalconcrete and brick surfaces

D 10mm Joints not exceeding 300mm highA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 51 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 51

Saw cut joints

E 3 x 40mm Saw cut joints in top of concreteA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 517 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 517

REINFORCEMENT

NOTE: All items in this section shall be deemed to fall intoWork Group No.114 for CPAP formula purposes

Carried to Collection R Section No. 2Bill No. 2CONCRETE, FORMWORK AND REINFORCEMENTPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 9 9 -

Page 46: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

High tensile steel reinforcement to structural concrete work

A 10mm Diameter barsA1: 0,00 AW: 0,00 B1: 0,00 BW: 0,00

C1: 0,00 CW: 0,00 D1: 0,14 DW: 0,00

E1: 0,00 EW: 0,00 F1: 0,00 FW: 0,00 t 0,14

B 12mm Diameter barsA1: 0,00 AW: 0,00 B1: 0,00 BW: 0,00

C1: 0,00 CW: 0,00 D1: 0,12 DW: 0,00

E1: 0,00 EW: 0,00 F1: 0,00 FW: 0,00 t 0,12

Fabric reinforcement

C Type A193 fabric reinforcement in concrete surface beds, slabs,etc

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 109 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 109

Carried to Collection R Section No. 2Bill No. 2CONCRETE, FORMWORK AND REINFORCEMENTPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 0 0 -

Page 47: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

Bill No. 2

CONCRETE, FORMWORK AND REINFORCEMENT

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -96-

-97-

-98-

-99-

-100-

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 2CONCRETE, FORMWORK AND REINFORCEMENTPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 0 1 -

Page 48: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

SECTION NO. 2

BILL NO. 3

PRECAST CONCRETE

NOTE: The contractor is advised to study the Model Preamblesfor Trades before pricing this bill

NOTE: All unit rates must take into account and will be assumedto include all applicable taxes including Value Added Tax Act.No additional claims relating to taxes will be entertained

NOTE: The contractor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies betweenthe bill and the drawings the contractor must notify the PrincipalAgent

N O T E : Unless otherwise stated herein, all items in this bill shallbe deemed to fall into Work Group No.112 for CPAP formulapurposes

N O T E : Unless otherwise stated herein, all work in this trade shallbe executed in accordance with the guidelines of the ExpandedPublic Works Programme second edition of July 2005

SUPPLEMENTARY PREAMBLES

Sizes:

Blocks, sills, etc measured linear shall be made in suitable lengths. Large size setting out drawings shall be prepared wherenecessary and submitted to the architect for approval beforemoulds are made

General:

Where kerbstones, blocks, etc are laid in ground descriptions shallbe deemed to include necessary excavation, filling in and ramming

Carried to Collection R Section No. 2Bill No. 3PRECAST CONCRETEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 0 2 -

Page 49: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

PRECAST CONCRETE WINDOWS

PRECAST CONCRETE WINDOW SURROUNDS

General

Window surrounds are to be checked at delivery for squareness.Surrounds out of square will be rejected

NOTE: Prices only for aluminium and glazing as Windbloks arealready installed on exists structure.

WiNblok window surroundings with rebate placed to theoutside of the wall including aluminium window insert withclear toughned glass (code:WGB66T)

A Window surrounds (code:WB66), size 600 x 600 x 260mm deepglazed with 6mm toughened clear float glass(WT15)

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 120 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 120

WiNblok window surroundings with rebate placed to theoutside of the wall including aluminium window insert withclear toughned glass (code:WGB66T) and burglar barwindow accessory fitted to rebate of surround usingnon-ascetic silicone sealant

B Window surrounds (code:WB44), size 800 x 400 x 260mm deepglazed with 6mm toughened clear float glass, 8mm square burglarbars in grid perttern fitted to rebate of surrounds usingnon-ascentic silicone sealant (WT18)

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 3 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 3

Carried to Collection R Section No. 2Bill No. 3PRECAST CONCRETEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 0 3 -

Page 50: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

WiNblok window surroundings (code: WB66), size 600 x600mm x 260mm deep with rebate placed to the outside of thewall, including aluminium window insert with clear glass(codes:WGB66T) with burglar bar window accessory fitted torebate of surround using non-ascetic silicone sealant

A Window overal size 2400 x 3000mm high glazed with 6mmtoughened clear float glass, 8mm square burglar bars in gridperttern (WT22)

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 4 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 4

WiNblok window surroundings (code:WB44), size 400 x 400 x260mm deep and (code: WB88), size 800 x 800mm x 260mmdeep with rebate placed to the outside of the wall, includingaluminium window insert with clear glass (codes:WGB66Tand WGB88T) with burglar bar window accessory fitted torebate of surround using non-ascetic silicone sealant

B Window overal size 4400 x 2400mm high glazed with 6mmtoughened clear float glass, 8mm square burglar bars in gridperttern (WT2)

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 6 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 6

WiNblok window surroundings (code:WB44), size 400 x 400 x260mm deep with rebate placed to the outside of the wall,including aluminium window insert with clear glass(code:WGB44T) and burglar bar window accessory fitted torebate of surround using non-ascetic silicone sealant

C Window overal size 4400 x 2400 glazed with 6mm toughenedclear float glass, 8mm square burglar bars in grid perttern fitted torebate of surrounds using non-ascentic silicone sealant (WT3)

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 3 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 3

Carried to Collection R Section No. 2Bill No. 3PRECAST CONCRETEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 0 4 -

Page 51: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

WiNblok modular window of high density, low permeability,unreinforced 30MPa smooth finish pre-cast concreteconsisting square window surrounds (code:WB44), size 400 x400 x 260mm deep with rebate placed to the outside of thewall, including aluminium window insert with clear glass(code:WGB44T) and burglar bar window accessory fitted torebate of surround using non-ascetic silicone sealant

A Window overal size 4400 x 2400 glazed with 6mm toughenedclear float glass, 8mm square burglar bars in grid perttern fitted torebate of surrounds using non-ascentic silicone sealant (WT4)

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

WiNblok window surroundings (code:WB44), size 400 x 400 x260mm deep and (code: WB88), size 800 x 800mm x 260mmdeep with rebate placed to the outside of the wall, includingaluminium window insert with clear glass (codes:WGB66Tand WGB88T) with burglar bar window accessory fitted torebate of surround using non-ascetic silicone sealant

B Window overal size 1600 x 800mm high glazed with 6mmtoughened clear float glass, 8mm square burglar bars in gridperttern fitted to rebate of surrounds using non-ascentic siliconesealant (WT13)

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 6 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 6

C Window overal size 1600 x 1200mm high glazed with 6mmtoughened clear float glass, 8mm square burglar bars in gridperttern fitted to rebate of surrounds using non-ascentic siliconesealant (WT5)

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

D Window overal size 1600 x 1600mm high glazed with 6mmtoughened clear float glass, 8mm square burglar bars in gridperttern (WT8)

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 4 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 4

Carried to Collection R Section No. 2Bill No. 3PRECAST CONCRETEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 0 5 -

Page 52: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A Window overal size1600 x 1600mm glazed with 6mm toughenedclear float glass, 8mm square burglar bars in grid perttern fitted torebate of surrounds using non-ascentic silicone sealant (WT12)

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

B Window overal size1600 x 1600mm glazed with 6mm toughenedclear float glass, 8mm square burglar bars in grid perttern fitted torebate of surrounds using non-ascentic silicone sealant (WT14)

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

WiNblok window surroundings (code:WB44), size 400 x 400 x260mm deep and (code: WB66), size 600 x 600mm x 260mmdeep with rebate placed to the outside of the wall, includingaluminium window insert with clear glass (codes: WGB44Tand WGB66T) with burglar bar window accessory fitted torebate of surround using non-ascetic silicone sealant

C Window overal size 2000 x 1600mm high glazed with 6mmtoughened clear float glass, 8mm square burglar bars in gridperttern fitted to rebate of surrounds using non-ascentic siliconesealant (WT6)

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

(LABOUR RATE ONLY ON EXISTING MATERIAL ONSITE)

WiNblok window of high density, low permeability,unreinforced 30MPa smooth finish pre-cast concrete

D Window surrounds (code:WB66), size 600 x 600 x 260mm deep (WT15)

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 8 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 8

Carried to Collection R Section No. 2Bill No. 3PRECAST CONCRETEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 0 6 -

Page 53: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

Bill No. 3

PRECAST CONCRETE

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -102-

-103-

-104-

-105-

-106-

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 3PRECAST CONCRETEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 0 7 -

Page 54: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

SECTION NO. 2

BILL NO. 4

MASONRY

NOTE: The contractor is advised to study the Model Preamblesfor Trades before pricing this bill

NOTE: All unit rates must take into account and will be assumedto include all applicable taxes including Value Added Tax Act.No additional claims relating to taxes will be entertained

NOTE: The contractor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies betweenthe bill and the drawings the contractor must notify the PrincipalAgent

N O T E : Unless otherwise stated herein, all items in this bill shallbe deemed to fall into Work Group No.118 for CPAP formulapurposes

N O T E : Unless otherwise stated herein, all work in this trade shallbe executed in accordance with the guidelines of the ExpandedPublic Works Programme second edition of July 2005

SUPPLEMENTARY PREAMBLES

BRICKWORK

Sizes in descriptions

Where sizes in descriptions are given in brick units, "one brick"shall represent the length and "half brick" the width of a brick

Hollow walls, etc

Descriptions of hollow walls shall be deemed to include leavingevery fifth perpend of the bottom course of the external skin openas a weep hole

Carried to Collection R Section No. 2Bill No. 4MASONRYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 0 8 -

Page 55: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Wall ties

Wall ties shall be "Joluka Posi-ties Type PTT 4 Ref: 8312" orsimilar approved. Ties for hollow walls shall be of sufficientlength to allow not less than 75mm of each end to be built into thebrickwork. Ties are to be spaced at intervals of not more than 1min the horizontal direction and not more than 400mm staggered inthe vertical direction except at openings, vertical joints or ends ofwalls where they are to be placed vertically above each other

Face bricks

Bricks shall be ordered timeously to obtain uniformity in size andcolour

Pointing

Descriptions of recessed pointing to fair face brickwork and facebrickwork shall be deemed to include square recessed, hollowrecessed, weathered pointing, etc

BLOCKWORK

Concrete masonry units

Blocks are to be either solid or hollow modular dense concretemasonry units having a compressive strength of 7 MPa

Wall ties for blockwork

Wall ties shall be "Joluka Posi-ties Type PTT 4 Ref: 8312" orsimilar approved. Ties for hollow walls shall be of sufficientlength to allow not less than 75mm of each end to be built into theblockwork. Ties are to be spaced at intervals of not more than 1min the horizontal direction and not more than 400mm staggered inthe vertical direction except at openings, vertical joints or ends ofwalls where they are to be placed vertically above each other

Blockwork

Blockwork shall comply with SABS 0145 "Concrete MasonryConstruction"

Carried to Collection R Section No. 2Bill No. 4MASONRYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 0 9 -

Page 56: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Surfaces to be plastered shall have joints raked out to a depth of atleast 10mm to provide a key. Cavities of hollow walls shall bekept free of mortar droppings or other undesirable matter. Everysecond perpend of the bottom course of the external skin ofhollow walls shall be left open as a weep hole

Standard complementary blocks

Descriptions of blockwork shall be deemed to include standardcomplementary blocks such as corner, three-quarter, half andquarter blocks required in the construction of corners, reveals,jambs, ends, etc to solid and hollow walls and for bonding asnecessary

BRICKWORK SUPPLIED BY COROBRICK AS ACESSION

SUPERSTRUCTURE (LABOUR RATE ONLYAPPLICABLE)

Brickwork of NFX bricks (14 MPa nominal compressivestrength) in class II mortar

A PiersA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 3 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m3 3

B Half brick wallsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 90 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 90

C Half brick walls in beamfillingA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 32 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 32

D One brick wallsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 338 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 338

Carried to Collection R Section No. 2Bill No. 4MASONRYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 1 0 -

Page 57: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A One brick walls circular on planA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 27 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 27

B One brick walls in beamfillingA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 26 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 26

Brickwork of NFX bricks (14 MPa nominal compressivestrength) in class I mortar in loadbearing walls etc

BRICKWORK SUNDRIES

Brickwork reinforcement

C 75mm Wide reinforcement built in horizontallyA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 124 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 124

D 150mm Wide reinforcement built in horizontallyA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 933 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 933

E 150mm Wide reinforcement built in horizontally circular on planA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 79 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 79

Prestressed fabricated lintels

F 100 x 70mm Lintels in lengths not exceeding 3mA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 47 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 47

Turning pieces

G 90mm Wide turning piece to lintels etcA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 9 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 9

Carried to Collection R Section No. 2Bill No. 4MASONRYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 1 1 -

Page 58: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A 150mm Wide turning piece to lintels etcA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 34 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 34

FACE BRICKWORK

Corobrik® 25-35MPa Roan Satin Imperial FBX or similarapproved clay face brick, size 222 x 106 x 73mm pointed withrecessed horizontal and vertical joints

B Extra over brickwork for face brickworkA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 396 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 396

C Extra over brickwork for brick-on-edge header course lintelA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 51 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 51

Carried to Collection R Section No. 2Bill No. 4MASONRYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 1 2 -

Page 59: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

Bill No. 4

MASONRY

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -108-

-109-

-110-

-111-

-112-

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 4MASONRYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 1 3 -

Page 60: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

SECTION NO. 2

BILL NO. 5

ROOF COVERINGS ETC

NOTE: The contractor is advised to study the Model Preamblesfor Trades before pricing this bill

NOTE: All unit rates must take into account and will be assumedto include all applicable taxes including Value Added Tax Act.No additional claims relating to taxes will be entertained

NOTE: The contractor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies betweenthe bill and the drawings the contractor must notify the PrincipalAgent

N O T E : Unless otherwise stated herein, all items in this bill shallbe deemed to fall into Work Group No.122 for CPAP formulapurposes

N O T E : Unless otherwise stated herein, all work in this trade shallbe executed in accordance with the guidelines of the ExpandedPublic Works Programme second edition of July 2005

PROFILED METAL SHEETING AND ACCESSORIES

Arona Roofing 0,58mm thick Novotexi 440® profile 440mmcover Z275 spelter ISQ300 or similar approved galvanisedsteel roof sheeting in single lengths with Gemsbok SandChromadek top coat and grey backing coat

A Roof covering with pitch not exceeding 50 degrees withCompriband sealant at all laps

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1808 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 1 808

B Ridge cappings 650mm girthA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 64 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 64

Carried to Collection R Section No. 2Bill No. 5ROOF COVERINGS, ETCPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 1 4 -

Page 61: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A Side wall flashing 408mm girth two times bent along girthA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 26 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 26

B Narrow and broad flute closers 650mm girthA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 128 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 128

ROOF AND WALL INSULATION

Roof insulation to be 50mm Thick Isover Factorylite flexible,non-combustible lightweight industrial fibreglass insulationmaterial (nominal density12kg per m3), with Reinforced KraftAluminium foil faced finish laid taut over purlins at 1000centres fixed concurrent with the roof covering withgalvanised steel straining wires at 300mm centres, and tieddown top and bottom after tensioning with galvanized hoopiron ties.

C Insulation laid taut over purlins (at approximately 1200mmcentres) and fixed concurrent with roof covering including chickenwire mesh

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1808 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 1 808

Carried to Collection R Section No. 2Bill No. 5ROOF COVERINGS, ETCPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 1 5 -

Page 62: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

Bill No. 5

ROOF COVERINGS, ETC

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -114-

-115-

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 5ROOF COVERINGS, ETCPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 1 6 -

Page 63: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

SECTION NO. 2

BILL NO. 6

CARPENTRY AND JOINERY

NOTE: The contractor is advised to study the Model Preamblesfor Trades before pricing this bill

NOTE: All unit rates must take into account and will be assumedto include all applicable taxes including Value Added Tax Act.No additional claims relating to taxes will be entertained

NOTE: The contractor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies betweenthe bill and the drawings the contractor must notify the PrincipalAgent

N O T E : Unless otherwise stated herein, all items in this bill shallbe deemed to fall into Work Group No.126 for CPAP formulapurposes

N O T E : Unless otherwise stated herein, all work in this trade shallbe executed in accordance with the guidelines of the ExpandedPublic Works Programme second edition of July 2005

SUPPLEMENTARY PREAMBLES

Particle board

Particle board shall comply with the following specifications:

a) SABS 1300 Particle board: exterior and flooring type

b) SABS 1301 Particle board: interior type

Descriptions of frames shall be deemed to include frames,transomes, mullions, rails, etc

Carried to Collection R Section No. 2Bill No. 6CARPENTRY AND JOINERYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 1 7 -

Page 64: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Joinery

Descriptions of hardwood joinery shall be deemed to includepelleting of bolt holes

Descriptions of hardwood joinery shall be deemed to includepelleting of bolt holes

Fixing

Items described as "nailed" shall be deemed to be fixed withhardened steel nails or shot pins to brickwork or concrete

Decorative laminate finish

Laminate finish shall be glued under pressure. Edge strips shall bebutt jointed at junctions with adjacent similar finish

ROOFS ETC

Plate nailed timber roof truss construction

Sawn softwood

A 38 x 114mm Wall platesA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 213 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 213

Prefabricated timber roof trusses

The following is applicable in respect of roof trusses:

Carried to Collection R Section No. 2Bill No. 6CARPENTRY AND JOINERYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 1 8 -

Page 65: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Timber roof structure shall be fully designed, constructed of SouthAfrican pine and certified on completion by a firm of SpecialistTimber Roof Designers and Manufacturers

The Tenderers are referred to the Architect's roof plan annexed tothese bills of quantities/accompanying these bills of quantities fortender purposes

The dimensions in the descriptions of the trusses are nominal andactual measurements are to be obtained from the Architect and/orthe site before design or fabrication commences

Prices shall include designs and certification on completion. Thedesigns shall be availed to the Structural Engineer on award of thecontract

A Fully designed timber roof structure to Block D complete withtrusses, jack rafters, permanent bracing and purlins/battens asnecessary all in accordance with the Architect's roof planincluding provision of an Engineer's Approval Certificate oncompletion (area measured on plan over the roof line as per theArchitect's drawings) "EXISTING ON SITE"

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 395 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 395

Sundries

B 30 x 1,6mm Galvanised hoop iron roof tie 900mm girth with eachend fixed to timber

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 178 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 178

EAVES, VERGES, BARGE BOARDS ETC

Carried to Collection R Section No. 2Bill No. 6CARPENTRY AND JOINERYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 1 9 -

Page 66: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Medium density plain fascia boards, size 225 x 10mm thick,fixed to 38 x 38mm tilter batten and 38 x 38mm supportbattens between rafters twice screwed with 12 x 40mmcountersunk brass screws at 900mm centres to supportbattens with aluminium H-profile fascia joiner betweenboards and aluminium H-profile fascia corner joiners atboard ends

A 300 x 15mm thick Fascias and barge boardsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 258 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 258

Everite medium density plain Nutec fascia boards, fixed to 38x 38mm tilter batten and 38 x 38mm support battens betweenrafters twice screwed with 12 x 40mm countersunk brassscrews at 900mm centres to support battens with aluminiumH-profile fascia joiner between boards and aluminiumH-profile fascia corner joiners at board ends

B Verge soffit coverings 300mm wide of 4mm thick sheets,including 38 x 38mm sawn softwood brandering along edges andat 1,20m centres across sheets

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 32 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 32

C Eaves soffit coverings 500mm wide of 4mm thick sheets,including 38 x 38mm sawn softwood brandering along edges,along centre and at 1,20m centres across sheets

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 236 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 236

SKIRTINGS

Skirtings with 19mm quater ref no. WSK 2 in solid Meranti,plugged and countersunk screwed and pellated to walls.

D 19 x 76mm Skirting including 19mm quadrant bead nailedA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 240 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 240

Carried to Collection R Section No. 2Bill No. 6CARPENTRY AND JOINERYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 2 0 -

Page 67: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A 19 x 76mm Skirting including 19mm quadrant bead nailed circularon plan

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 99 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 99

DOORS ETC

THE FOLLOWING IN BLOCK D

Horizontal hardwood entrance door. Sand down timbersurface to a fine smooth surface and apply quality timbersealant prior to installation, all in accordance withManufacturer's recommendations with and including powdercoated aluminium louvre size 600mm x 400mm high

B 44mm Door size 813 x 2032mm (T3)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 8 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 8

Semi-solid medium weight 813mm timber door trimmed150mm above floor level

C 44mm Door size 813 x 2032mm (T4)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 10 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 10

Swartland Gold 10 year guarantee, sealed with a linseed oilbased transit stabilizing sealer. with 700 x 350 mm powdercoateted aluminium louvre. Sand down timber surface to afine smooth finish and apply three coats Swartland Maxicarequality timber sealant prior to installation, all in accordancewith the Manufacturer's recommendations

D 44mm Door, size 1359 x 2032mm (T7)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

Carried to Collection R Section No. 2Bill No. 6CARPENTRY AND JOINERYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 2 1 -

Page 68: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Swartland Gold 10 year guarantee , SD10/1612 small panedouble hardwood patio door with 105mm stiles, sealed with alinseed oil based transit stabilizing sealer with 2 x 400 x 400 x6mm safety glass panel. Sand down timber surface to a finesmooth finish and apply three coats Swartland Maxicarequality timber sealant prior to installation, all in accordancewith the manufacturer's recommendations

A 44mm Door, size 1613 x 2032mm (T8)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 4 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 4

Carried to Collection R Section No. 2Bill No. 6CARPENTRY AND JOINERYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 2 2 -

Page 69: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

Bill No. 6

CARPENTRY AND JOINERY

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -117-

-118-

-119-

-120-

-121-

-122-

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 6CARPENTRY AND JOINERYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 2 3 -

Page 70: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

SECTION NO. 2

BILL NO. 7

CEILINGS, PARTITIONS, ACCESS FLOORING

NOTE: The contractor is advised to study the Model Preamblesfor Trades before pricing this bill

NOTE: All unit rates must take into account and will be assumedto include all applicable taxes including Value Added Tax Act.No additional claims relating to taxes will be entertained

NOTE: The contractor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies betweenthe bill and the drawings the contractor must notify the PrincipalAgent

NOTE: All items in this section shall be deemed to fall intoWork Group No.129 for CPAP formula purposes

N O T E : Unless otherwise stated herein, all work in this trade shallbe executed in accordance with the guidelines of the ExpandedPublic Works Programme second edition of July 2005

SUPPLEMENTARY PREAMBLES

Descriptions

Items described as "nailed" shall be deemed to be fixed withhardened steel nails or pins or shot pinned to brickwork orconcrete

Items described as "plugged" shall be deemed to include screwingto fibre, plastic or metal plugs at not exceeding 600mm centres,and where described as "bolted" the bolts have been givenelsewhere

Carried to Collection R Section No. 2Bill No. 7CEILINGS, PARTITIONS, ACCESS FLOORINGPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 2 4 -

Page 71: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

CEILING TIMBERS, BEADS, INSULATION, ETC

"Fibreglass" insulation

A 75mm Insulation closely fitted and laid on top of branderingbetween roof timbers etc

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 448 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 448

NAILED UP CEILINGS

Gyproc 6,4mm RhinoCeil Standard M-Strip or similarapproved ceiling with square edged Rhinoboard fixed printside up, at right angles to brandering using 25mm streakerscrews at 150mm centres to Donn Steel brandering at 400mmcentres in one direction only with Aluzinc M-Strip cover stripsover joints with all nail or screw heads stopped and sandedlevel when dry all fixed to trusses at centres exceeding1000mm, not exceeding 1200mm

B Ceilings including 38 x 38mm sawn softwood brandering at450mm centres

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 448 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 448

C Extra over ceiling for 600 x 600mm trap door including framewith ceiling board and fitted flush in opening

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 5 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 5

FD1 gypsum cornice, fixed to wall and ceiling with Rhinobedadhesive

D Cornice 70 x 75mm highA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 725 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 725

SUSPENDED CEILINGS

Carried to Collection R Section No. 2Bill No. 7CEILINGS, PARTITIONS, ACCESS FLOORINGPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 2 5 -

Page 72: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Proprietary suspended ceilings

Note: Electrical light fittings, diffusers, panels, etc generally are"lay in" units of the same dimensions as the suspension griddescribed and allowance must be made accordingly for theirsupport inclusive of any flexibility in setting out that may berequired (ceiling panels have not been deducted and pricing is totake cognisance thereof)

---------------

"DONNCEIL"

Gyproc DonnCeil Gyprex Porcelain vinyl finished gypsumceiling tiles size 1200 x 600mm x 12,5mm thick laid on andincluding SQ/T38 White powder coated main tees, cross tees,hold-down clips, wedges, etc., all suspended with galvanised19mm strap suspension hangers at hanger centres notexceeding 1200mm

A Ceilings suspended not exceeding 1m below steel roof trussesA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 937 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 937

B Extra over ceiling for opening for 100mm diameter downlighterA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 88 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 88

C Extra over ceiling for opening for 1200 x 600mm light fittingA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 11 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 11

D Extra over ceiling for 600 x 600mm Trap door including framewith ceiling board and fitted flush in opening

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

Carried to Collection R Section No. 2Bill No. 7CEILINGS, PARTITIONS, ACCESS FLOORINGPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 2 6 -

Page 73: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

Bill No. 7

CEILINGS, PARTITIONS, ACCESS FLOORING

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -124-

-125-

-126-

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 7CEILINGS, PARTITIONS, ACCESS FLOORINGPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 2 7 -

Page 74: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

SECTION NO. 2

BILL NO. 8

FLOOR COVERINGS, WALL LININGS, ETC

NOTE: The contractor is advised to study the Model Preambles forTrades before pricing this bill

NOTE: All unit rates must take into account and will be assumed toinclude all applicable taxes including Value Added Tax Act. Noadditional claims relating to taxes will be entertained

NOTE: The contractor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies between thebill and the drawings The contractor must notify the Principal Agent

N O T E : Unless otherwise stated herein, all items in this bill shall bedeemed to fall into Work Group No.130 for CPAP formula purposes

N O T E : Unless otherwise stated herein, all work in this trade shall beexecuted in accordance with the guidelines of the Expanded PublicWorks Programme second edition of July 2005

FLOOR COVERINGS, PLASTIC LININGS, ETC

FLOOR COVERINGS

Polyflex Plus (Border grey 7110) or similar approved SemiFlexible vinyl floor tiles, size 300 x 300 x 2,5mm thick

A On floors m2 751

2mm "POLYSAFE" Astral safety or similar approved flooringcontaining silicone carbide and aluminium oxide granules withstabilising crinette interlayer with Dupont Supratec

B On floors m2 205

C On treads and risers of stairs m2 4

D Margins and borders not exceeding 500mm wide m 113

E Turn-ups over coves and up against walls not exceeding 500mm girth m 113

Carried to Collection R Section No. 2Bill No. 8FLOOR COVERING, WALL LININGS, ETCPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 2 8 -

Page 75: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

A Turn-ups over coves and up against walls not exceeding 500mm girthcircular on plan m 99

B Circular cutting m 99

Sundries to vinyl sheeting

C 40mm "Polycap" CS48 vinyl capping strip m 188

D 20 x 20mm "Polycove" PC20 cove former to receive vinyl sheeting m 188

E 400mm Wide "Classic Mystique PuR" edge strip laid 200mm on floorwith 200mm turn-ups over coves and up against walls m 188

POLISH, SEALERS, ETC

F Three coats wax polish on vinyl flooring m2 955

G Three coats wax polish on turn-ups over coves and up against wallsnot exceeding 500mm girth m 188

Carried to Collection R Section No. 2Bill No. 8FLOOR COVERING, WALL LININGS, ETCPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 2 9 -

Page 76: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

Bill No. 8

FLOOR COVERING, WALL LININGS, ETC

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -128-

-129-

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 8FLOOR COVERING, WALL LININGS, ETCPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 3 0 -

Page 77: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

SECTION NO. 2

BILL NO. 9

IRONMONGERY

NOTE: The contractor is advised to study the Model Preamblesfor Trades before pricing this bill

NOTE: All unit rates must take into account and will be assumedto include all applicable taxes including Value Added Tax Act.No additional claims relating to taxes will be entertained.

NOTE: The contractor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies betweenthe bill and the drawings the contractor must notify the PrincipalAgent.

N O T E : Unless otherwise stated herein, all items in this bill shallbe deemed to fall into Work Group No.132 for CPAP formulapurposes.

N O T E : Unless otherwise stated herein, all work in this trade shallbe executed in accordance with the guidelines of the ExpandedPublic Works Programme second edition of July 2005.

SUPPLEMENTARY PREAMBLES

Carried to Collection R Section No. 2Bill No. 9IRONMONGERYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 3 1 -

Page 78: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Finishes to ironmongery

Where applicable finishes to ironmongery are indicated bysuffixes in accordance with the following list:

BS - Satin bronze lacquered CH Chromium platedSC - Satin chromium platedSE - Silver enamelledGE - Grey enamelledAS - Anodised silverAB - Anodised bronzeAG - Anodised goldABL - Anodised blackPB - Polished brassPL - Polished and lacqueredPT - Epoxy coatedSD - Sanded

HINGES, BOLTS, ETC

A Double panic bolt complete sliver (HA2950SR)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

B S/CHROME flush bolt 150 x 20mm (120/150)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

CATCHES, CABIN HOOKS, ETC

"DCLSA" or similar approved

C S/S Hat and Coat hook rubber buffer (154/69)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 10 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 10

D CABIN HOOK 150mm POL SAT/CH (106-150/76)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 4 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 4

Carried to Collection R Section No. 2Bill No. 9IRONMONGERYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 3 2 -

Page 79: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

LOCKS

"DCLSA" or similar approved

A Marseilles set on rose C/W CYL ESC (DC113AC69)A1: 0,0 AW: 0,0 B1: 0,0 BW: 0,0

C1: 0,0 CW: 0,0 D1: 7,5 DW: 0,0

E1: 0,0 EW: 0,0 F1: 0,0 FW: 0,0 Pairs 7,5

B Rabate conv. set 76mm lock NP (130/81)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

C Prof CYL D/LOCK R/BOLT latch SS (662/35)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

D 5 PIN MK D/CYL 60mm 3K N.PL (850-60/78)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 4 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 4

E Thumb turn and lock TT001SS (194/01)A1: 0,0 AW: 0,0 B1: 0,0 BW: 0,0

C1: 0,0 CW: 0,0 D1: 10,0 DW: 0,0

E1: 0,0 EW: 0,0 F1: 0,0 FW: 0,0 Sets 10,0

F 76mm Prof CYL Sashlock 22mm CP (325/51)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 8 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 8

G 5 Pin PIN MK K/CYL 66mm 3K N.PL (855-66/78)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

H 5 Pin PIN MK D/CYL 66mm 3K N.PL (850-66/78)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 4 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 4

HANDLES

Carried to Collection R Section No. 2Bill No. 9IRONMONGERYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 3 3 -

Page 80: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

"DCLSA" or similar approved

A BTB S.S O/set 400 x 350 x 25mm (JS206OS/350BTB)A1: 0,0 AW: 0,0 B1: 0,0 BW: 0,0

C1: 0,0 CW: 0,0 D1: 7,5 DW: 0,0

E1: 0,0 EW: 0,0 F1: 0,0 FW: 0,0 Pairs 7,5

B S/ST P/PL 160 x 160 x 0.9mm E/T/CUP (079/160E/T/Cup)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

DOOR CLOSERS

"Union" or similar approved

C TS 1500GF D/Closer C/W Mech HO G/Rail SR (AZ1504SR)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 8 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 8

LETTERS, NAMEPLATES, ETC

"Union" or similar approved

D S/ST P/PL 160 x 160 x 0.9mm E/Male (079/160E/Male)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 3 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 3

E S/ST P/PL 160 x 160 x 0.9mm E/FEM. (079/160E/F)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 3 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 3

F Ref. E15 anodised aluminium plate with fire exit, fireextinguisher, fire hose reel or fire hydrant symbol

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 12 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 12

BATHROOM FITTINGS

Carried to Collection R Section No. 2Bill No. 9IRONMONGERYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 3 4 -

Page 81: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

"Kimberley-Clark" or similar approved

A Kimberly-Clark® Professional MR2 Satin finish Stainless Steeltoilet tissue dispenser (code: SA426130), overall size 130 x 135 x256mm high, installed by a Kimberly Clark® installation team

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 11 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 11

B Kimberly-Clark® Professional Disposer Plus Stainless Steel wallmounted waste bin (code: SA426135), overall size 300 x 250 x500mm high, installed by a Kimberly Clark® installationteam

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 8 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 8

C Kimberly-Clark® Professional Reflex® MK2 Stainless Steel handtowel dispenser (Code: SA426125), overall size 310 x 280 x400mm high, installed by a Kimberly Clark® installationteam

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 7 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 7

D Kimberly-Clark® Professional Series I Twinpak Skincare soapdispenser colour Black (code: SA921940), overall size 184 x 110x 264mm high, installed by a Kimberly Clark® installation team

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 5 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 5

"Franke" or similar approved

E Franke Chronos BS 611 V Grade 304 18/10 satin stainless steelsanitary towel disposal bins (product code: 359830), size 304 x205 x 134mm deep, capacity of 6 litres, plugged and screwed tothe wall with stainless steel screws.

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 7 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 7

Carried to Collection R Section No. 2Bill No. 9IRONMONGERYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 3 5 -

Page 82: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A 32mm Stainless steel Paraplegic back grab rail 800mm longplugged

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 8 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 8

B 32mm Stainless steel Paraplegic side grab rail 900mm longplugged

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 8 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 8

"Buchel" or similar approved

C "Buchel" Cat. No. BM 9400 or similar approved paraplegic toilethandrail sets comrising 32mm stainless steel side grab rail (CodeDL2), 32mm stainless steel rear grab rail around cistern (CodeSR2) and 32mm stainless steel rear grab rail around flush valve(Code SR1) including all necessary fixing, etc.

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 8 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 Sets 8

JOINERY FITTINGS IRONMONGERY

SUNDRIES

'Union' or similar approved

D SLIMLINE DOUBLE PANIC BOLT SET by (HZ595)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 4 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 4

'Solid' or similar approved

E S/Steel F/MNT Doorstop by DCLSA (140/69)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 13 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 13

Carried to Collection R Section No. 2Bill No. 9IRONMONGERYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 3 6 -

Page 83: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

Bill No. 9

IRONMONGERY

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -131-

-132-

-133-

-134-

-135-

-136-

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 9IRONMONGERYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 3 7 -

Page 84: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

SECTION NO. 2

BILL NO. 10

METALWORK

NOTE: The contractor is advised to study the Model Preamblesfor Trades before pricing this bill

NOTE: All unit rates must take into account and will be assumedto include all applicable taxes including Value Added Tax Act.No additional claims relating to taxes will be entertained

NOTE: The contractor advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies betweenthe bill and the drawings the contractor must notify the PrincipalAgent

N O T E : Unless otherwise stated herein, all items in this bill shallbe deemed to fall into Work Group No.136 for CPAP formulapurposes

N O T E : Unless otherwise stated herein, all work in this trade shallbe executed in accordance with the guidelines of the ExpandedPublic Works Programme second edition of July 2005

WELDED SCREENS, GATES, ETC

Purpose made burglar proofing in 50 x 50mm welded squaretube steel frame and 25 x 25mm square tube studs welded at100mm centres in herringbone pattern all primed and painted(paint elsewhere) including fixing to steel window frames

A Purpose made double swing gate made from mild steel to fitopening size 2360 x 2100mm high comprising 60 x 40 x 2mm and75 x 50 x 3mm rectangular gate frame, 19mm diameter steel rodsinfill at 110mm centres, galvanised steel safety top track withbracket, bottom roller bearing with 15mm diameter steel barwelded to 5mm thick steel plate cast into concrete includingupright five lever mortice deadlock in steel plate housing. BLOCKD T2

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

Carried to Collection R Section No. 2Bill No. 10METALWORKPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 3 8 -

Page 85: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A Purpose made single swing gate made from mild steel to fitopening size 900 x 2100mm high comprising 60 x 40 x 2mm and75 x 50 x 3mm rectangular gate frame, 19mm diameter steel rodsinfill at 110mm centres, galvanised steel safety top track withbracket, bottom roller bearing with 15mm diameter steel barwelded to 5mm thick steel plate cast into concrete includingupright five lever mortice deadlock in steel plate housing. BLOCKD T3

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 0 DW: 2

E1: 0 EW: 0 F1: 0 FW: 0 No 2

Double Sash Valudor® fabricated from Burgundy powdercoated hot dipped galvanised mild steel in two equal widthgrilles comprising uprights at maximum 115mm centres withfour flights of trelliswork, top track, with two anchor jambs,with one lock stile, with one strike stile, and hot dippedgalvanised steel with matching powder coating removable sillwith Trellidor Slam-lock with 5 pin full cylinder lock en suiteto master key, with perimeter framing plugged and screwed atmaximum 300mm centres to concrete or brickwork usingTrellidor tamper-proof coach screws and plastic wall plugs

B Overall size 2500 x 2400mm high ( Block D T1)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 4 DW: 2

E1: 0 EW: 0 F1: 0 FW: 0 No 6

PRESSED STEEL DOOR FRAMES

1,2mm Rebated standard frames suitable for one brick wallscomplete with hinges, striking plate, rubber buffers and fixinglugs welded to frame

C Frame for door 813 x 2032mm high with fanlight 302mm highA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

D Frame for door 1524 x 2032mm high with fanlight 302mm highand two side fanlights 288mm wide

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 4 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 4

Carried to Collection R Section No. 2Bill No. 10METALWORKPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 3 9 -

Page 86: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A Frame for door 1359 x 2032mm high with fanlight 302mm highand two side fanlights 288mm wide

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

Durowin internally glazed industrial hot dip galvanised

B Window size 533 x 359mm high (NG1)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 6 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 6

C Window size 533 x 359mm high (NG5)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 14 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 14

D Window size 673 x 511mm high (MG1)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

E Window size 673 x 511mm high (SS21)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 14 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 14

F Window size 1616 x 978mm high (SS52)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 4 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 4

G Window size 1616 x 1445mm high (SS53)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 4 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 4

THE FOLLOWING IN BLOCK D

Carried to Collection R Section No. 2Bill No. 10METALWORKPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 4 0 -

Page 87: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

KAL Maxima coupled unit comprising polyester powdercoated (50 - 100µ thick) aluminium side hung double entrancedoor, each leaf in two panes with horizontal glazing bar hungon two stainless steel washered aluminium butts, one leaffitted with two aluminium concealed lever action flush boltsand the other with lock and set of lever furniture, coupled totwo fixed sidelights with panes to match, and all with fixedlights over, all glazed with Africa Glass Tempershield tintedtoughened safety glass with clip-on glazing beads withneoprene seals, plugged to brickwork orconcrete.Non-Standard powder coating or anodising colour:Bronze

A Door size 2400 x 2400mm high (T1)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 4 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 4

B Door size 2200 x 2400mm high (T2)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

Steel french doors including sidelights

C Door size overal size 2471 x 2449mm high (T6)A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

SHOWER CUBICLE DOORS, ETC.

"Clearway" or similar approved white powder coatedanodized aluminium shower doors glazed as described,including frames cleats, stops, etc., plugged and screwed totiled walls and floor

D Shower door size 920 x 1750mm high as Bi slider code BS 900,glazed with obscure toughened safety glass.

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

Carried to Collection R Section No. 2Bill No. 10METALWORKPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 4 1 -

Page 88: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A Shower door size 1200 x 1820mm high as Trimatic code TM1318, glazed with obscure toughened safety glass.

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

SUNDRY STAINLESS STEEL WORK

Corner protectors

B 80 x 80 x 6mm Angle section corner protector to horizontalcorners, plugged on both sides

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 64 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 64

GALVANISED STEEL FLOORS

Floor grating, fixed to steel standard fixing clips

C Floor grating of 300 x 1000mmA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 15 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 15

Carried to Collection R Section No. 2Bill No. 10METALWORKPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 4 2 -

Page 89: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

Bill No. 10

METALWORK

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -138-

-139-

-140-

-141-

-142-

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 10METALWORKPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 4 3 -

Page 90: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

SECTION NO. 2

BILL NO. 11

PLASTERING

NOTE: The contractor is advised to study the Model Preamblesfor Trades before pricing this bill

NOTE: All unit rates must take into account and will be assumedto include all applicable taxes including Value Added Tax Act.No additional claims relating to taxes will be entertained

NOTE: The contractor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies betweenthe bill and the drawings the contractor must notify the PrincipalAgent

N O T E : Unless otherwise stated herein, all items in this bill shallbe deemed to fall into Work Group No.142 for CPAP formulapurposes

N O T E : Unless otherwise stated herein, all work in this trade shallbe executed in accordance with the guidelines of the ExpandedPublic Works Programme second edition of July 2005

SCREEDS

Screeds on concrete

A 75mm Thick wearing screed on floor to fall with ABE Duraproofadditive

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1391 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 1 391

INTERNAL PLASTER

Two coat plaster with gypsum finish on brickwork

B On wallsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 359 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 359

Carried to Collection R Section No. 2Bill No. 11PLASTERINGPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 4 4 -

Page 91: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A On narrow widthsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 22 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 22

One coat cement plaster on brickwork

B On wallsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 171 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 171

WALL AND CORNER PROTECTORS, DIVIDING STRIPS,ETC

Dividing strips, etc

C 3 x 25mm Flat section brass weather barsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 14 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 14

D 3 x 25mm Flat section brass dividing strips between different floorfinishes

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 7 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 7

Carried to Collection R Section No. 2Bill No. 11PLASTERINGPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 4 5 -

Page 92: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

Bill No. 11

PLASTERING

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -144-

-145-

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 11PLASTERINGPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 4 6 -

Page 93: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

SECTION NO. 2

BILL NO. 12

TILING

NOTE: The contractor advised to study the Model Preambles forTrades before pricing this bill

NOTE: All unit rates must take into account and will be assumedto include all applicable taxes including Value Added Tax Act.No additional claims relating to taxes will be entertained.

NOTE: The contractor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies betweenthe bill and the drawings the contractor must notify the PrincipalAgent

N O T E : Unless otherwise stated herein, all items in this bill shallbe deemed to fall into Work Group No.144 for CPAP formulapurposes

N O T E : Unless otherwise stated herein, all work in this trade shallbe executed in accordance with the guidelines of the ExpandedPublic Works Programme second edition of July 2005

WALL TILING

Glazed ceramic wall tiles size 200 x 200 x 6,5mm thick, fixed towood floated Class II mortar plaster backings with Tal tileadhesive (elsewhere specified) with 3mm joints continuous inboth directions and flush pointed with Tal tile grout(elsewhere specified) with minimum 5mm expansion joints atperimeter, all structural expansion and construction jointsand at maximum 5m centres internally and 4m centresexternally, in both directions

A On wallsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 171 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 171

Carried to Collection R Section No. 2Bill No. 12TILINGPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 4 7 -

Page 94: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A On walls in isolated panels, splashbacks, etcA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 7 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 7

B Fair exposed cutting and fitting around pipe not exceeding 100mminternal diameter

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 24 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 24

C Fair exposed cutting and fitting around pipe exceeding 100mmand not exceeding 150mm internal diameter

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 24 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 24

FLOOR TILING

"Kenzan Piombo" or similar approved full bodied porcelainunrectified tiles (code: PIOMBO) with 4 PEI rating, size 300x 600mm

D On floors and landingsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 95 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 95

E Skirting 100mm high of Code AW036 floor tiles circular on planA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 139 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 139

F Extra for external corner tileA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 5 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 5

G Extra for internal corner tileA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 4 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 4

Carried to Collection R Section No. 2Bill No. 12TILINGPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 4 8 -

Page 95: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A Extra for end tileA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

"Tile Africa Africa" Desert or similar approved porcelainfloor tiles (Code: AF-069) with 4 PEI Rating, size 400 x 400 x8mm thick

B On floors and landingsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 84 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 84

C Skirting 100mm high of Code AW036 floor tilesA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 50 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 50

D Extra for external corner tileA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 4 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 4

E Extra for internal corner tileA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 3 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 3

F Extra for end tileA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

EXTERNAL FLOOR TILING

Carried to Collection R Section No. 2Bill No. 12TILINGPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 4 9 -

Page 96: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

"Union" or similar approved non skid terrazzo tiles (colour tobe selected) tiles, size 300 x 300 x 25mm thick, bedded on30-40mm thick 1:5 semi dry screed with cement slurry pouredunder each tile and tile gently tapped using rubber mallet with15-20mm wide joints jointed and pointed with 1:3 semi drymortar laid in custom design. Tiles and bedding laid outdoorson levelled concrete surface bed to minimum 1:50 falls. Theexpansion joints are to be provided against walls andobstacles. The tiles to confirm to CKS208 as regards cement,colour, aggregate, finish, pigments , shape, warpagetransverse strength and water. The tiles to be sealed withUnion Terrazzo sealer for non skid range.

A On floors and landingsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 351 DW: 177

E1: 0 EW: 0 F1: 0 FW: 0 m2 528

TOILET PAPER HOLDERS, ETC

B 152 x 152mm Glazed ceramic toilet paper holder built into brickwall and pointed all round to match wall tiling

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 8 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 8

C 152 x 152mm Glazed ceramic soap holder built into brick walland pointed all round to match wall tiling

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 15 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 15

VANITY TOPS

Vanity top granite slab with all exposed edges pencil edged,fixed to supports using 100% clear silicone adhesive at 200 to300mm centres along all supports with all joints and mitrescut at 45°, all joints, mitres and seams filled with matchingpolyester resin glue

D Type 210 40mm thickA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 12 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 12

Carried to Collection R Section No. 2Bill No. 12TILINGPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 5 0 -

Page 97: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A Type 590 40mm thickA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 2

SUNDRIES

Aluminium corner protectors, stair nosings, expansion jointstrips, etc

B "Union" or similar approved M-Trim aluminium straight edge trimA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 189 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 189

Carried to Collection R Section No. 2Bill No. 12TILINGPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 5 1 -

Page 98: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

Bill No. 12

TILING

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -147-

-148-

-149-

-150-

-151-

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 12TILINGPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 5 2 -

Page 99: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

SECTION NO. 2

BILL NO. 13

PLUMBING AND DRAINAGE

ITEMS IN THIS TRADE ARE SUBJECT TOCOMFIRMATION ON SITE

NOTE: The contractor advised to study the Model Preambles forTrades before pricing this bill

NOTE: All unit rates must take into account and will be assumedto include all applicable taxes including Value Added Tax Act.No additional claims relating to taxes will be entertained

NOTE: The contractor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies betweenthe bill and the drawings The contractor must notify the PrincipalAgent

NOTE: All items in this section shall be deemed to fall intoWork Group No.146 for CPAP formula purposes

N O T E : Unless otherwise stated herein, all work in this trade shallbe executed in accordance with the guidelines of the ExpandedPublic Works Programme second edition of July 2005

SUPPLEMENTARY PREAMBLES

Concrete pipes

Pipes shall be jointed with ogee joints with rubber collars orsocket and spigot joints with rubber rings

Vitrified clay pipes etc

Pipes shall rest on solid ground and, where necessary, pockets ofsufficient size shall be cut around joints to enable the jointing tobe properly performed or, alternatively, pipes shall be bedded fulllength on and including unreinforced concrete laid in a semi-drystate immediately before pipes are laid

Carried to Collection R Section No. 2Bill No. 13PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 5 3 -

Page 100: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

uPVC pipes and fittings

Sewer and drainage pipes and fittings shall be jointed and sealedwith butyl rubber rings

Soil, waste and vent pipes and fittings shall be solvent weldjointed

uPVC pressure pipes and fittings

Pipes for water supply shall be of the class stated

Pipes of 40mm diameter and smaller shall be plain ended withsolvent welded uPVC loose sockets and fittings

Pipes of 50mm diameter and greater shall have sockets and spigotswith push-in type integral rubber ring joints. Bends shall be uPVCand all other fittings shall be cast iron, all with similar push-intype joints

Copper pipes

Pipes shall be hard drawn and half-hard pipes of the class stated.Class 0 (thin walled hard drawn) pipes shall not be bent. Class 1(thin walled half-hard), class 2 (half-hard) and class 3 (heavywalled half-hard) pipes shall only be bent with benders with innerand outer formers. Fittings to copper waste, vent and anti-syphonpipes, capillary solder fittings and compression fittings shall be"Cobra Watertech" type. Capillary solder fittings shall complywith ISO 2016. Only compression fittings shall be used in wallsor in ground

Lead pipes and traps

All soldered joints shall be wiped and brass unions shall be usedfor jointing lead to steel

Carried to Collection R Section No. 2Bill No. 13PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 5 4 -

Page 101: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Reducing fittings

Where fittings have reducing ends or branches they are describedas "reducing". In the case of pipes with diameters not exceeding60mm only the largest end or branch size is given. Should thecontractor wish to use other fittings and bushes or reducers he maydo so on the understanding that no claim in this regard will beentertained. In the case of pipes with diameters exceeding 60mmall sizes are given and no claim for extra bushes, reducers, etc willbe entertained

Wire gratings

Descriptions of gutter outlets etc shall be deemed to include wireballoon gratings

Reducing fittings

Where fittings have reducing ends or branches they are describedas "reducing". In the case of pipes with diameters not exceeding60mm only the largest end or branch size is given. Should thecontractor wish to use other fittings and bushes or reducers he maydo so on the understanding that no claim in this regard will beentertained. In the case of pipes with diameters exceeding 60mmall sizes are given and no claim for extra bushes, reducers, etc willbe entertained

Exposed concrete surfaces

Exposed surfaces of concrete stormwater channels, cover slabs,inspection eye marker slabs, gulley tops, cleaning eye tops,catchpits, inspection chambers, etc shall be finished smooth withplaster

Carried to Collection R Section No. 2Bill No. 13PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 5 5 -

Page 102: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Excavations

No claim for rock excavation will be entertained unless thecontractor has timeously notified the quantity surveyor thereofprior to backfilling

"Soft rock" and "hard rock" shall be as defined in "Earthworks"

Laying, backfilling, bedding, etc of pipes

Pipes shall be laid and bedded and trenches shall be carefullybackfilled in accordance with manufacturers' instructions

Laying, backfilling, bedding, etc of pipes

Pipes shall be laid and bedded and trenches shall be carefullybackfilled in accordance with manufacturers' instructions

Where no manufacturers' instructions exist pipes shall be laid inaccordance with clauses 5.1 and 5.2 of each of the following:SABS 1200 L : Medium-pressure pipelinesLD : SewersLE : Stormwater drainagePipe trenches etc shall be backfilled in accordance with clauses 3,5.5, 5.6, 5.7 and 7 of SABS 1200 DB : Earthworks (Pipe trenches)

Pipes shall be bedded in accordance with clauses 3.1 to 3.4.1, 5.1to 5.3 and 7 of SABS 1200 LB : Bedding (Pipes).Unless otherwise described bedding of rigid pipes shall be class Bbedding

Flush pans

Flush pans shall have straight or side outlets and "P" or "S" trapsas necessary

Waste unions

Descriptions of waste unions shall be deemed to include rubber orvulcanite plugs and chains fixed to fittings

Carried to Collection R Section No. 2Bill No. 13PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 5 6 -

Page 103: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Steel sectional water tanks

Tanks shall comply with SABS CKS 114

---------------

PLUMBING

NOTE: All items in this section shall be deemed to fall intoWork Group No.148 for CPAP formula purposes

_____________________________

SANITARY FITTINGS

"Citimetal" or similar approved stainless steel

A 1500mm "Citimental" Ref: DT150C Double bowl stainless steelor similar approved sink in accordance with Architect'sspecification complete with mounting brackets, stopper and chainby Citimetal or similarly approved

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

"Franke" or similar approved stainless steel

"Vaal" or similar approved

B Vaal Sanitaryware Weaver vitreous china lavatory basin colourWhite(code: 700303), size 510 x 440mm with one tapholeincludingintegrated overflow and chainstay hole, fitted onto vanitytop (elsewhere specified)

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 13 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 13

C "Protea" close coupled 90 degrees Paraplegic floor mountedwashdown WC set Cat. No. 750200 comprising double flap heavyduty plastic seat and lid, matching 9 litre cistern Cat. No. 710631,purpose made chromium plated side flush lever and intergral "P"trap

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 8 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 8

Carried to Collection R Section No. 2Bill No. 13PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 5 7 -

Page 104: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A 610 x 385mm "Lavatera" vitreous china wall mounted "Flatback"urinal Cat. No. 705426 with top inlet, comprising 38mmchromium plated bottle trap Cat. No. 340, 1 1/4" chromium platedwaste Cat. No. 301-32, 38mm chromium plated domical gratingCat. No. 8787Z0, chromium plated spreader Cat. No. 7054Z1 and2No. hanger brackets Cat. No. 8127Z0 with division pieces Cat.No. 7052 fitted with flushmaster valve Cat. No. FJ6.000 includingFJT5.4CP tailpipe

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 6 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 6

WASTE UNIONS ETC

"Cobra Watertech"

B 32mm Basin waste unionA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 15 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 15

C 32mm Bath or sink waste unionA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

TRAPS ETC

uPVC

D 38mm Deep seal "P" or "S" trapA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 14 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 14

Cast iron

E 38mm Urinal trapA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 6 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 6

Carried to Collection R Section No. 2Bill No. 13PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 5 8 -

Page 105: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

"Cobra Watertech" or similar approved

A 32mm 345/50 CP deep bottle trapA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 23 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 23

B 75mm VA3.113 CP hinged urinal domical gratingA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 6 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 6

TAPS, VALVES, ETC

"Cobra Watertech" or similar approved

C Cobra Watertech 15mm chrome plated elbow action pillar-typemixer with overarm swivel outlet (Code: 521-21), manufactured inaccordance with SANS 226:2004 Type 2 (BS 5412).All pipes to be fitted with Cobra Watertech 15mm ball type anglevalve with 350mm flexible hose connector (Code: 32/350F) andall drains behind the Universal Half pedestal to have a CobraWatertech 40mm rough brass shallow seal bath P trap with FIoutlet and two cleaning eyes (Code: 370) or approved equivalent

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 14 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 14

D 15mm Ref: 136CP stopcockA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 46 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 46

E 22mm Ref: 1003-125 cast brass heavy duty fullway gate valvewith non-blowout, non rising spindle, non-asbestos gland packing,guided wedge and red pressed steel hand wheel

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

F 15mm Chrome plated 3396/ST wall type sink mixer includingoverarm swivel spout

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

Carried to Collection R Section No. 2Bill No. 13PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 5 9 -

Page 106: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A 15mm CP 521-21 elbow action pillar-type mixer with overarmswivel outlet

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

B 15mm Ref: 710-15 low pressure MOH pattern float valve with286mm long arm, 32mm side inlet, brass piston, backnut and3,2mm diameter I.D. nylon seat including M12 Ref: 756-12 brasssolder stud for copper float valves

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

C 20mm Ref: 1025-20 cast brass spring loaded automatic checkvalve

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

D 15mm Ref: 1050-15 Cast brass in-line strainer with stainless steelstrainer basket

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 42 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 42

E 25mm Ref: 1050-25 Cast brass in-line strainer with stainless steelstrainer basket

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 5 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 5

F 22mm Ref: 550-22 copper to copper geyser draincock with 22mminlet and outlet and 20mm drainage hose tail

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

G 22mm Ref: PB1.10CX "Vacubreak I" vacuum breaker (doublejumper) with 22mm copper to copper inlet

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

Carried to Collection R Section No. 2Bill No. 13PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 6 0 -

Page 107: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A 20mm Ref: PA1.1 "Kwikflo" combined pressure control valvewith integral expansion relief valve, stainless steel seat, stainlesssteel strainer, 20mm FI inlet and outlet and 15mm FI expansionoutlet, system pressure 400 kPa

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

"Walcro" or similar approved

B "Walcro" 103 (LHS) HT Flushing ValveA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 8 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 8

SANITARY PLUMBING

uPVC plastic pipes

C 50mm PipesA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 46 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 46

D 110mm PipesA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 4 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 4

Extra over uPVC pipes for fittings

E 50mm AdaptorA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 17 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 17

F 50mm BendA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 5 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 5

G 50mm IE bendA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 12 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 12

Carried to Collection R Section No. 2Bill No. 13PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 6 1 -

Page 108: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A 50mm JunctionA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 6 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 6

B 50mm IE junctionA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 5 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 5

C 110mm BendA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

D 110mm IE bendA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

E 110mm Pan connectorA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 8 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 8

F 110mm Reducing junctionA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 6 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 6

G 110mm Reducing IE junctionA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 6 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 6

H 110mm IE bend with hornA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 8 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 8

Sundries

WATER SUPPLY

Carried to Collection R Section No. 2Bill No. 13PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 6 2 -

Page 109: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

"Ctando" or similar approved polypropylene plastic twin wallpipe

A 15mm PipesA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 122 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 122

B 22mm PipesA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 114 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 114

C 35mm PipesA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 72 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 72

Extra over "Ctando"or similar approved polypropyleneplastic twin wall pipe for capillary fittings

D 15mm FittingsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 118 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 118

E 22mm FittingsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 228 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 228

F 35mm BendA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 28 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 28

G 35mm TeeA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 50 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 50

H 35mm ReducerA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 28 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 28

Carried to Collection R Section No. 2Bill No. 13PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 6 3 -

Page 110: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A 35mm Reducing teeA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 6 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 6

"Ctando" or similar approved polypropylene plastic twinwall pipe overflow and service pipes

B 15mm Overflow pipe 500mm girth twice bentA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

DRIP TRAYS, TANKS, ETC

0,6mm Galvanised sheet steel

C 1800 x 800mm Drip tray for water heater, with 100mm highupstand all round with top edge bent over and with 20mmthreaded outlet union

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

FIRE APPLIANCES ETC

"Chubb" or similar approved

D " Everyway" hose reel complete with 30m rubber hose, chromiumplated stopcock, shut off nozzle and wall bracket

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 2 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 2

E 7.5kg Carbon dioxide fire extinguisherA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 12 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 12

LAGGING

Carried to Collection R Section No. 2Bill No. 13PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 6 4 -

Page 111: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

"Gundle" or similar approved Plastics Group

A Aluminium foil faced geyser insualtion blanket, size 1250 x1530mm including end and pipe strips, wrapped around geyserand pipes, all installed in accordance with manufacturer'srecommendations

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 1 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 1

Carried to Collection R Section No. 2Bill No. 13PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 6 5 -

Page 112: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

Bill No. 13

PLUMBING AND DRAINAGE

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -153-

-154-

-155-

-156-

-157-

-158-

-159-

-160-

-161-

-162-

-163-

-164-

-165-

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 13PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 6 6 -

Page 113: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

BILL NO. 14

ELECTRICAL INSTALLATION

NOTE: The contractor is advised to study the Model Preambles forTrades before pricing this bill

NOTE: All unit rates must take into account and will be assumed toinclude all applicable taxes including Value Added Tax Act. Noadditional claims relating to taxes will be entertained

NOTE: The contractor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies between thebill and the drawings the contractor must notify the Principal Agent.

The Electrical Bills of Quantities is contained in a separatedocument titled PART II, ELECTRICAL INSTALLATION,which is to be priced in full by the Contractor in terms of theAgreement and Schedule of Conditions of Building Contract andall other supplementary documentation contained in theabovementioned PART II and in these Bills of Quantities. Theamount obtained from the Summary of the abovementionedPART II is to be fully inclusive of all necessary allowances, exceptfor Value Added Tax which will be added in the Final Summaryof these Bills of Quantities, and is to be entered as a SUM in theprovided column herein

A Electrical Installation Brought Forward from the Summary of Part II,ELECTRICAL INSTALLATION, excluding Value Added Tax SUM

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 14ELECTRICAL INSTALLATIONPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 6 7 -

Page 114: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

SECTION NO. 2

BILL NO. 15

GLAZING

NOTE:The contractor is advised to study the Model Preambles forTrades before pricing this bill

NOTE: All unit rates must take into account and will be assumedto include all applicable taxes including Value Added Tax Act.No additional claims relating to taxes will be entertained

NOTE: The contractor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies betweenthe bill and the drawings the contractor must notify the PrincipalAgent

N O T E : Unless otherwise stated herein, all items in this bill shallbe deemed to fall into Work Group No.150 for CPAP formulapurposes

N O T E : Unless otherwise stated herein, all work in this trade shallbe executed in accordance with the guidelines of the ExpandedPublic Works Programme second edition of July 2005

GLAZING TO STEEL WITH PUTTY

6mm Clear float safety glass

A Panes exceeding 0,5m2 and not exceeding 2m2A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 22 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 22

TOPS, SHELVES, DOORS, MIRRORS, ETC

Carried to Collection R Section No. 2Bill No. 15GLAZINGPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 6 8 -

Page 115: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Franke M 600 HD Grade 304 13mm 18/10 or similarapproved stainless steel mirrors (product code: 359922),concealed thief resistant fixings, plugged and screwed to thewall with stainless steel screws

A 500 x 600mmA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 14 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 14

Wall mirror with stainless steel trim to lower edge code41210800 steel

B Mirror 450 x 600mm highA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 15 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 No 15

Carried to Collection R Section No. 2Bill No. 15GLAZINGPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 6 9 -

Page 116: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

Bill No. 15

GLAZING

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -168-

-169-

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 15GLAZINGPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 7 0 -

Page 117: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

SECTION NO. 2

BILL NO 16

STRUCTURAL STEELWORK

User note

Consideration is to be given in specific applications (eg where"heavy" steel structures such as in industrial plants, towers for mineshafts, etc are dominant) to implement the principles laid down by the"Measurement for Structural Steelwork" as prepared andrecommended by the South African Institute of Steel Construction

This bill however is based on the Standard System of MeasuringBuilding Work Sixth Edition (Revised)

SUPPLEMENTARY PREAMBLES

Descriptions

Descriptions of bolts shall be deemed to include nuts and washers

Descriptions of L-shaped and U-shaped anchor bolts shall be deemedto include bending, threading, nuts and washers and embedding inconcrete

Descriptions of expansion anchors and bolts and chemical anchorsand bolts shall be deemed to include nuts, washers and mortices inbrickwork or concrete

STRUCTURAL STEEL ROOF STRUCTURE

THE FOLLOWING IN BLOCK D (HALL):

10 No. Trusses in taper flange I - Section spanning 24126mm andheight to apex 2170mm high including tie beam, rafter, struts,braces, cleats welded to steel

A 120 x 120 x 15mm I - Section tie beam t 5,27

B 150 x 150 x 15mm I - Section rafter t 10,30

C 70 x 70 x 6mm I - Section struts t 2,73

D 60 x 60 x 6mm I - Section bracing t 1,79

Carried to Collection R Section No. 2Bill No. 16STRUCTURAL STEELPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 7 1 -

Page 118: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

A 50 x 50 x 6mm angle iron bracing fixed under tie beam on plan notexceeding 2000mm long t 0,196

B 60 x 60 x 6mm angle iron bracing fixed under tie beam on plan notexceeding 2350mm long

t 0,28

C 70 x 70 x 6mm angle iron bracing fixed under tie beam on plan notexceeding 2750mm long

t 0,386

D 80 x 80 x 6mm angle iron bracing fixed under tie beam on plan notexceeding 3150mm long

t 0,58

E 90 x 90 x 6mm angle iron bracing fixed under tie beam on plan notexceeding 3500mm long

t 0,638

Purlin and angle iron, welded and bolted

F 175 x 50 x 20 x 3.5mm Lipped channel purlin t 6,59

G 125 x 75 x 8mm Angle iron t 0,465

Base plate, gusset plate, fork plate, end plate and etc fixed toconcrete column

H 114.3 x 6mm CHS welded all round to end of rafterNo 20

J 345 x 345 x 12mm Thick gusset plate notched, cut to shape andwelded to tie beam on either side of joint

No 10

K 345 x 345 x 12mm Thick gusset plate notched, cut to shape andwelded to strut on either side of joint

No 10

L 345 x 345 x 12mm Thick base plate fixed to column No 20

M 70 x 70 x 12mm Thick base plate No 80

Carried to Collection R Section No. 2Bill No. 16STRUCTURAL STEELPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 7 2 -

Page 119: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

BOLTS, FASTENERS, ETC

A M8 nut and bolt No 80

B M12 HSL heavy duty anchor drilled into concrete column No 80

C M12 Holding down bolts cast into concrete column with 150mmembedment No 80

D M16 bolts covered/coated with bituminous materIal as protectionagainst oxidation No 120

E M20 holding down bolts 560mm long cast in concrete columns with75mm diameter x 150mm pockets No 80

F 16mm Diameter bolt with a nut locking the lipped channel No 440

G 70 x 70mm Washer plate No 80

Carried to Collection R Section No. 2Bill No. 16STRUCTURAL STEELPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 7 3 -

Page 120: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

Bill No. 16

STRUCTURAL STEEL

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -171-

-172-

-173-

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 16STRUCTURAL STEELPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 7 4 -

Page 121: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

SECTION NO. 2

BILL NO. 17

PAINTWORK

NOTE:The contractor is advised to study the Model Preambles forTrades before pricing this bill

NOTE: All unit rates must take into account and will be assumedto include all applicable taxes including Value Added Tax Act.No additional claims relating to taxes will be entertained

NOTE: The contractor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies betweenthe bill and the drawings the contractor must notify the PrincipalAgent

N O T E : Unless otherwise stated herein, all items in this bill shallbe deemed to fall into Work Group No.152 for CPAP formulapurposes

N O T E : Unless otherwise stated herein, all work in this trade shallbe executed in accordance with the guidelines of the ExpandedPublic Works Programme second edition of July 2005

PAINTWORK ETC TO NEW WORK

ON INTERNAL FLOATED PLASTER SURFACES

Plascon Cashmere to interior new cement plaster (NW 202).Surface to be dry, sound and clean and cured for a minimumof 14 days, with a moisture content measured with a DoserHygrometer (or equivalent), of BD 2 scale - 8% or less. Primewith one coat of Plascon Plaster Primer (UC 56) with anovercoating time of 16 hours and finish with two coats ofCashmere (CAS) with 2 hours drying time between coats, fora maintenance cycle of 7 years in a C1 - inland environment

A On internal wallsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 359 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 359

Carried to Collection R Section No. 2Bill No. 17PAINTWORKPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 7 5 -

Page 122: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Plascon Wall & All to interior new cement plaster (NW 201).Surface to be dry, sound and clean and cured for a minimumof 14 days, with a moisture content measured with a DoserHygrometer (or equivalent), of BD 2 scale - 8% or less. Primewith one coat of Plascon Plaster Primer (UC 56) with anovercoating time of 16 hours and finish with two coats of Wall& All (WAA) with 2 hours drying time between coats, for amaintenance cycle of 7 years in a C1 - inland environment

A On internal wallsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 18 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 18

ON INTERNAL GYPSUM PLASTER SURFACES

One coat undercoat and two coats Plascon Wall and All(NW-201)

B On internal wallsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 66 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 66

ON PLASTERBOARD SURFACES

One coat primer, one undercoat and two coats PlasconProfessional Eggshell Enamel paint

C On ceilings and cornicesA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 158 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 158

ON FIBRE-CEMENT BOARD SURFACES

Apply one coat Plascon Wall & All Pure Acrylic thinned 20%and one coat Plascon Wall & All Pure Acrylic paint all toManufacture's specifications

D On ceilings and cornicesA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 268 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 268

Carried to Collection R Section No. 2Bill No. 17PAINTWORKPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 7 6 -

Page 123: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A On fascias and barge boardsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 72 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 72

One coat primer, one undercoat and two coats PlasconVelvaglo paint

B On ceilings and beamsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 448 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 448

C On internal sills not exceeding 300mm girthA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 70 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 70

ON METAL SURFACES

One coat of plascon universal undercoat and two coats ofplascon velvaglo polyurethane enamel paint

D On door framesA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 27 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 27

One coat red oxide, one coat epoxy primer and two coatsSuper Acrylic paint on steel

E WindowsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 22 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 22

F Columns and beamsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 15 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 15

Carried to Collection R Section No. 2Bill No. 17PAINTWORKPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 7 7 -

Page 124: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Spot priming defects in pre-primed surfaces with zincchromate primer and applying one undercoat and two coatsPlascon Velvaglo paint on steel

A On gates, grilles, burglar screens, balustrades, etc (both sidesmeasured over the full flat area)

A1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 71 DW: 8

E1: 0 EW: 0 F1: 0 FW: 0 m2 78

ON WOOD SURFACES

One coat plascon wood primer and one coat Plascon universalundercoat and two coats plascon velvaglo polyutheraneenamel paint

B On doorsA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 112 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m2 112

One coat wood primer and two coats Plascon varnish

C On skirtings, rails, etc not exceeding 300mm girthA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 240 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 240

D On skirtings, rails, etc not exceeding 300mm girth circular on planA1: 0 AW: 0 B1: 0 BW: 0

C1: 0 CW: 0 D1: 99 DW: 0

E1: 0 EW: 0 F1: 0 FW: 0 m 99

Carried to Collection R Section No. 2Bill No. 17PAINTWORKPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 7 8 -

Page 125: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

Bill No. 17

PAINTWORK

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -175-

-176-

-177-

-178-

Carried Forward to Summary of Section No. 2 R Section No. 2Bill No. 17PAINTWORKPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 7 9 -

Page 126: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 2

Building Works

SECTION SUMMARY - Building Works

Bill Page AmountNo No

1 -95-EARTHWORKS

2 -101-CONCRETE, FORMWORK AND REINFORCEMENT

3 -107-PRECAST CONCRETE

4 -113-MASONRY

5 -116-ROOF COVERINGS, ETC

6 -123-CARPENTRY AND JOINERY

7 -127-CEILINGS, PARTITIONS, ACCESS FLOORING

8 -130-FLOOR COVERING, WALL LININGS, ETC

9 -137-IRONMONGERY

10 -143-METALWORK

11 -146-PLASTERING

12 -152-TILING

13 -166-PLUMBING AND DRAINAGE

14 -167-ELECTRICAL INSTALLATION

15 -170-GLAZING

16 -174-STRUCTURAL STEEL

17 -179-PAINTWORK

Carried to Final Summary R Section No. 2PROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 8 0 -

Page 127: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

SECTION NO. 3

BILL NO. 1

EXTERNAL PLUMBING AND DRAINAGE

ITEMS IN THIS TRADE ARE SUBJECT TOCOMFIRMATION ON SITE

NOTE: The contractor is advised to study the Model Preamblesfor Trades before pricing this bill

NOTE: All unit rates must take into account and will be assumedto include all applicable taxes including Value Added Tax Act.No additional claims relating to taxes will be entertained

NOTE: The contactor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies betweenthe bill and the drawings the contractor must notify the PrincipalAgent

N O T E : Unless otherwise stated herein, all items in this bill shallbe deemed to fall into Work Group No.104 for CPAP formulapurposes

N O T E : Unless otherwise stated herein, all work in this trade shallbe executed in accordance with the guidelines of the ExpandedPublic Works Programme second edition of July 2005

CONCRETE STORMWATER AND SURFACE WATERCHANNELS, ETC

A Concrete channel size 500 x 300mm deep including allexcavations, concreting, brickwork, reinforcement, formwork,plastering, etc m 120

Precast concrete channel finished smooth on exposed surfacesincluding bedding, jointing, and pointing

B Channel (Type C7) 590 x 175mm deep including all excavations,etc m 67

WATER SUPPLIES

Carried to Collection R Section No. 3Bill No. 1EXTERNAL PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 8 1 -

Page 128: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Excavations

A Excavation in earth not exceeding 1m deep for pipe trenches m3 27

B Backfilling to pipe trenches compacted to 95% Mod AASHTOdensity m3 27

C Selected granular filling in bedding under and filling around pipes m3 1

D 19mm Crushed stone bedding under pipes m3 0,3

"Ctando" or similar approved polypropylene plastic twin wallpipe

E 22mm Pipes m 270

Extra over "Ctando"or similar approved polypropyleneplastic twin wall pipe for capillary fittings

F 22mm Bend No 90

TESTING

G Testing water pipe system Item

FIRE APPLIANCES ETC

"Chubb"

H 100mm Diameter 2500 kPa pressure gauge syphon and stopcockincluding tapped hole in steel pipe No 2

J 80 x 65mm Brass hydrant booster connection with cap and chain No 1

K 80 x 65mm Brass right angle hydrant valve with cap and chain No 2

L 80 x 65mm Brass double booster pump connection with caps andchains No 1

Fire Hydrant Pedestal

M Unreinforced concrete hydrant pedestal 900mm high cast aroundvertical pipe with bottom 300mm below ground, 300 x 300mmsquare at base and tapering to octagonal shaped top 200 x 200mmoverall including all necessary excavation, formwork and twocoats of paint to exposed surfaces No 1

Carried to Collection R Section No. 3Bill No. 1EXTERNAL PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 8 2 -

Page 129: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

A Standpipe hydrants, including valves, seals etc. No 1

WATER SUPPLIES TO FIRE APPLIANCES

Excavations

B Excavation in earth not exceeding 1m deep for pipe trenches m3 35

C Backfilling to pipe trenches m3 35

D Backfilling to pipe trenches compacted to 95% Mod AASHTOdensity m3 1

E Selected granular filling in bedding under and filling around pipes m3 1

Class 16 uPVC pressure pipes with rubber ring joints

F 80mm Pipes laid in trenches (trenches elsewhere) m 351

Extra over class 16 uPVC pressure pipes for uPVC pressurefittings with rubber rings

G 80mm End cap No 12

H 80mm Bend No 6

J 80mm Tee No 12

K 80mm Reducing tee No 6

L 80mm Hydrant tee No 12

M 80mm BSP adaptor No 12

Sundries

N Testing fire water pipe system Item

MANHOLES, INSPECTION CHAMBERS, DRAINAGESUMPS, ETC

Carried to Collection R Section No. 3Bill No. 1EXTERNAL PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 8 3 -

Page 130: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Manholes

A Manhole size 1000 x 1000 x 750mm deep internally including allnecessary excavation, carting away, etc, 230mm thick 20Mpaconcrete walls and base slab and 230mm thick concrete roof slabreinforced with 12mm diameter high tensile steel rods at 150mmcentres in both directions and cast iron manhole cover and frametype 8B and step irons cast into concrete in two staggered rows at300mm centres. Prices shall include for all necessary formwork,holing of walls, sleeves, etc No 3

Inspection chambers, drainage sumps, etc

B "Saint Gobain Pipelines" or similar approved medium duty Type 7stopcock box Ref: 02680, size 115mm Ø x 102mm x 4,3kgincluding brick chamber below not exceeding 750mm deep No 1

C "Saint Gobain Pipelines" or similar approved medium duty Type 5hydrant box Ref: 02690, size 375 x 300 x 150mm x 45kgincluding brick chamber below not exceeding 750mm deep No 1

D "Saint Gobain Pipelines" or similar approved heavy duty Type 3Bvalve box Ref: 02630, size 100 x 230 x 300mm x 25,2kgincluding brick chamber below not exceeding 750mm deep No 1

E "Saint Gobain Pipelines" or similar approved heavy duty vandalproof meter box Ref: 02604, size 220 x 125 x 170mm x 8kgincluding brick chamber below not exceeding 750mm deep No 1

F 500 x 500mm Valve chamber not exceeding 750mm deepinternally (cover and frame elsewhere) No 1

G One brick junction box 450 x 450 x 300mm deep internally withconcrete base No 1

Sundries

H "Saint Gobain Pipelines" or similar approved light duty squaredished grating Ref: 02946, size 450 x 450mm x 27,4kg No 1

J 265 x 265mm x 9kg Cast iron single seal manhole cover andframe No 2

THE FOLLOWING TO WATER STORAGE TANK

EXCAVATION, FILLING, ETC

Carried to Collection R Section No. 3Bill No. 1EXTERNAL PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 8 4 -

Page 131: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Excavation in earth not exceeding 2m deep

A Trenches m3 39

Extra over trench and hole excavations in earth for excavationin

B Soft rock m3 4

C Hard rock m3 2

Extra over all excavations for carting away

D Surplus material from excavations and/or stock piles on site to adumping site to be located by the contractor m3 39

Risk of collapse of excavations

E Sides of trench and hole excavations not exceeding 1,5m deep m2 22

Keeping excavations free of water

F Keeping excavations free of water other than subterranean water Item

SOIL POISONING

Soil insecticide

G To bottoms and sides of trenches, holes, etc m2 72

UNREINFORCED CONCRETE CAST AGAINSTEXCAVATED SURFACES

15MPa/19mm Concrete

H Surface blinding under footings and bases m3 3

REINFORCED CONCRETE

25MPa/19mm Concrete

J Bases m3 9

REINFORCEMENT

Carried to Collection R Section No. 3Bill No. 1EXTERNAL PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 8 5 -

Page 132: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Mild steel reinforcement to structural concrete work

A 10mm Diameter bars t 1,00

B 8mm Diameter bars t 0,01

C 12mm Diameter bars t 0,03

D 20mm Diameter bars t 2,84

Bolts to steel

E M20 bolts No 16

WATER STORAGE TANK

F Booster Pump Item

G Water Tank Item

H Water Pipework Item

Carried to Collection R Section No. 3Bill No. 1EXTERNAL PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 8 6 -

Page 133: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 3

Site Works

Bill No. 1

EXTERNAL PLUMBING AND DRAINAGE

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -181-

-182-

-183-

-184-

-185-

-186-

Carried Forward to Summary of Section No. 3 R Section No. 3Bill No. 1EXTERNAL PLUMBING AND DRAINAGEPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 8 7 -

Page 134: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

SECTION NO. 3

BILL NO. 2

ROAD WORKS, PAVINGS, APRONS, ETC.

NOTE: The contractor is advised to study the Model Preamblesfor Trades before pricing this bill

NOTE: All unit rates must take into account and will be assumedto include all applicable taxes including Value Added Tax Act.No additional claims relating to taxes will be entertained

NOTE: The contactor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies betweenthe bill and the drawings the contractor must notify the PrincipalAgent

N O T E : Unless otherwise stated herein, all items in this bill shallbe deemed to fall into Work Group No.104 for CPAP formulapurposes

N O T E : Unless otherwise stated herein, all work in this trade shallbe executed in accordance with the guidelines of the ExpandedPublic Works Programme second edition of July 2005

THE FOLLOWING TO CONCRETE APRONS, STEPS ANDRAMPS

Site clearance

A Digging up and removing rubbish, debris, vegetation, hedges,shrubs and trees not exceeding 200mm girth, bush, etc m2 225

Earth filling supplied by the contractor compacted to 95%Mod AASHTO density

B Under floors, steps, paving, etc. m3 34

Compaction of surfaces

C Compaction of ground surface under floors etc m2 225

Carried to Collection R Section No. 3Bill No. 2ROAD WORKS, PAVINGS, APRONS, ETC.PROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 8 8 -

Page 135: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Soil insecticide

A Under floors, etc m2 225

25MPa/19mm concrete

B Aprons m3 18

Non-skid wood float finish to concrete

C Pavings, etc to falls m2 225

Test block

D Making and testing 150 x 150 x 150mm concrete strength testcube No 5

Rough formwork to sides

E Edges, risers, ends, etc. not exceeding 300mm high or wide m 188

Saw cut joints

F 15 x 30mm Saw cut joints on top of concrete m 75

Fabric reinforcement

G Type A193 fabric reinforcement in concrete surface beds, slabs,etc m2 225

THE FOLLOWING IN PAVING ( UNCOVEREDWALKWAYS)

Site clearance

H Stripping average 150mm thick layer of top soil and stockpillingon site m2 166

Extra over all excavations for carting away

J Surplus material from excavations and/or stock piles on site to adumping site to be located by the contractor m3 25

Coarse river sand filling supplied by the contractor

K Under paving, etc m3 42

Carried to Collection R Section No. 3Bill No. 2ROAD WORKS, PAVINGS, APRONS, ETC.PROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 8 9 -

Page 136: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Unit Quantity Rate AmountNo

Selected earth filling obtained from stock piles on site,compacted to 93% Mod AASHTO density

A Sub-base course under paving m3 25

Earth filling supplied by the contractor compacted to 95%Mod AASHTO density

B Over site (G5) m3 25

Compaction of surfaces

C Compaction of ground surface under paving etc m2 166

Soil insecticide

D Under floors, etc m2 166

Prescribed density tests on filling

E "Modified AASHTO Density" test No 3

60mm Std grey Zig Zag double interlocking precast conretepaving blocks laid to pattern on river sand bedding with sandswept into joints

F 60mm Standard "Concor Double Zig Zag" interlocking roadstonepaving m2 166

Combined barrier kerb and channel consisting 250 x 125mmthick 25MPa cast in-situ channel with joints at maximum 2mcentre and precast concrete kerb (SABS 927fig 4) 150 x300mm high, with 150 x 150 x 300mm unreiforced concretehaunching at back of each joint including finishing smooth onall exposed surfaces, excavation, backfilling, jointing,pointing, bedding in cement mortar, etc

G Straight kerbing and channelling m 89

Carried to Collection R Section No. 3Bill No. 2ROAD WORKS, PAVINGS, APRONS, ETC.PROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 9 0 -

Page 137: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 3

Site Works

Bill No. 2

ROAD WORKS, PAVINGS, APRONS, ETC.

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -188-

-189-

-190-

Carried Forward to Summary of Section No. 3 R Section No. 3Bill No. 2ROAD WORKS, PAVINGS, APRONS, ETC.PROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 9 1 -

Page 138: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 3

Site Works

SECTION SUMMARY - Site Works

Bill Page AmountNo No

1 -187-EXTERNAL PLUMBING AND DRAINAGE

2 -191-ROAD WORKS, PAVINGS, APRONS, ETC.

Carried to Final Summary R Section No. 3PROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 9 2 -

Page 139: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

SECTION NO. 4

BILL NO. 1

PROVISIONAL AMOUNTS

NOTE: The contractor advised to study the Model Preambles forTrades before pricing this bill

NOTE: All unit rates must take into account and will be assumed toinclude all applicable taxes including Value Added Tax Act. Noadditional claims relating to taxes will be entertained

NOTE: The contractor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepencies between thebill and the drawings the contractor must notify the Principal Agent

N O T E : Items in this section shall be deemed to fall into relevantWork Groups for CPAP formula purposes, each as describedpreviously herein

N O T E : Unless otherwise stated herein, all work in this trade shall beexecuted in accordance with the guidelines of the Expanded PublicWorks Programme second edition of July 2005

SELECTED SUBCONTRACTORS

The following Provisional Amounts are for specialist work to beexecuted by a selected sub-contractor who upon appointment in termsof the Conditions of Contract shall be deemed to be a selectedsub-contractor

A selected sub-contractor shall be a contractor executing work forwhich a sum of money is provided for in the bills of quantities or asub-contractor executing additional work specialist work which arisesas a result of an instruction by the representative/agent

Tender documents for such work shall be prepared by therepresentative/agent in consultation with and to the approval of thecontractor. Tenders shall be called for from a list of tenderers agreedbetween the contractor and the Principal Agent. Tenders shall besubmitted to the representative/agent for adjudication

Carried to Collection R Section No. 4Bill No. 1PROVISIONAL AMOUNTSPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 9 3 -

Page 140: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

The selected sub-contractor shall be chosen by therepresentative/agent and the contractor, and the contractor shallsatisfy himself that such selected sub-contractor can meet therequirements of the sub-contract agreement and the contractor shallinform the representative/agent accordingly. The contractor shallappoint such selected sub-contractor and inform the principal agentaccordingly

The procedure relating to the method of selection, obtaining oftenders, adjudication thereof and the appointment of the selectedsub-contractor shall not create any contractual relationship betweenthe Department and the selected sub-contractor

All provisional amounts cover supply of material and equipment andinstallation where applicable by firms of specialists. Provisionalamounts are nett and do not include builder's discount, but thetenderer may allow under "Profit" items for profit he considersnecessary

PROVISIONAL SUMS FOR NOMINATED/SELECTEDSUBCONTRACT WORKS

MAIN GATE

A Allow the Provisional Amount of R 12 000.00 (Twelve ThousandRand) NET for Main Gate to be executed by a sub-contractor Item 12 000 00

B Add for profit Item

C Allow for general attendance on sub-contractor Item

FLAG POLES

D Allow the Provisional Amount of R 4 000.00 (Four Thousand Rand)NET for Flag Pole to be executed by a sub-contractor Item 4 000 00

E Add for profit Item

F Allow for general attendance on sub-contractor Item

DRINKING WATER FOUNTAIN

G Allow the Provisional Amount of R 1 500.00 (One Thousand FiveRand) NET for Drink Water Fountain to be executed by asub-contractor Item 1 500 00

Carried to Collection R Section No. 4Bill No. 1PROVISIONAL AMOUNTSPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 9 4 -

Page 141: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

A Add for profit Item

B Allow for general attendance on sub-contractor Item

SOFT LANDSCAPING

C Allow the Provisional Amount of R 25 000.00 (Tweenty FiveThousand Rand) NET for Soft Landscaping to be executed by asub-contractor Item 25 000 00

D Add for profit Item

E Allow for general attendance on sub-contractor Item

GAS CYLINDER AND AIR CONDITIONING UNITS CAGE

F Allow the Provisional Amount of R 55 000.00 (Fifty Five ThousandRand) NET for Gas Cyliner Cage to be executed by a sub-contractor Item 55 000 00

G Add for profit Item

H Allow for general attendance on sub-contractor Item

HALL STAGE CURTAIN

J Allow the Provisional Amount of R 85 000.00 (Eighty five ThousandRand) NET for Hall Stage Curtain to be executed by a sub-contractor Item 85 000 00

K Add for profit Item

L Allow for general attendance on sub-contractor Item

WHITE EDUCATIONAL BOARDS

M Allow the Provisional Amount of R 16 000 (Sixteen Thousand Rand)NET for White Educational Boards, etc. to be executed by asub-contractor Item 16 000 00

N Add for profit Item

P Allow for general attendance on sub-contractor Item

Carried to Collection R Section No. 4Bill No. 1PROVISIONAL AMOUNTSPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 9 5 -

Page 142: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

BALUSTRADING AND HANDRAILING

A Allow the Provisional Amount of R 80 000 ( Eighty Thousand Rand)NET for Balustrading and Handrailing to be executed by asub-contractor Item 80 000 00

B Add for profit Item

C Allow for general attendance on sub-contractor Item

SIGNAGE

D Allow the Provisional Amount of R 15 000.00 (Fifteen ThousandRand) NET for Signage to be executed by a sub-contractor Item 15 000 00

E Add for profit Item

F Allow for general attendance on sub-contractor Item

PROJECT STREERING COMMITTEE

G Allow the Provisional Amount of R 6 600.00 (Six Thousand SixHundred Rand) NET for Project Steering Committee Item 6 600 00

H Add for profit Item

J Allow for general attendance on sub-contractor Item

COMMUNITY LIAISON OFFICER

K Allow the Provisional Amount of R 21 000.00 (Twenty OneThousand Rand) NET for community liaison officer Item 21 000 00

L Add for profit Item

M Allow for general attendance on sub-contractor Item

STORAGE OF VINYL SHEETING

N Allow the Provisional Amount of R 40 000.00 Forty Thousand Rand)NET for storage charges by the supplier Item 40 000 00

P Allow for general attendance on sub-contractor Item

Carried to Collection R Section No. 4Bill No. 1PROVISIONAL AMOUNTSPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 9 6 -

Page 143: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

BUDGETARY ALLOWANCES

A Allow the Provisional Amount of R 60 000.00 (Sixty ThousandRand) NET for leakage on Administration Block sanitary fittings. Item 60 000 00

B Allow for general attendance on sub-contractor Item

Carried to Collection R Section No. 4Bill No. 1PROVISIONAL AMOUNTSPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 9 7 -

Page 144: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Section No. 4

Provisional Amounts

Bill No. 1

PROVISIONAL AMOUNTS

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -193-

-194-

-195-

-196-

-197-

Carried to Final Summary R Section No. 4Bill No. 1PROVISIONAL AMOUNTSPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 9 8 -

Page 145: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

Item Quantity Rate AmountNo

SECTION NO. 5

HEALTH AND SAFETY AND HIV/AIDS PROGRAMMEIMPLEMENTATION

NOTE: The contractor is advised to study the Model Preambles forTrades before pricing this bill

NOTE: All unit rates must take into account and will be assumed toinclude all applicable taxes including Value Added Tax Act. Noadditional claims relating to taxes will be entertained

NOTE: The contractor is advised to study the Architect's drawingsbefore pricing this bill. In the case of any discrepancies between thebill and the drawings the contractor must notify the Principal Agent

The Health and Safety Bills of Quantities is contained in aseparate document titled PART IV, OCCUPATIONAL HEALTHAND SAFETY, which is to be priced in full by the Contractor interms of the Agreement and Schedule of Conditions of BuildingContract and all other supplementary documentation containedin the abovementioned PART IV and in these Bills of Quantities.The amount obtained from the Summary of the abovementionedPART IV is to be fully inclusive of all necessary allowances,except for Value Added Tax which will be added in the FinalSummary of these Bills of Quantities, and is to be entered as aSUM in the provided column herein

A Occupational Health and Safety Brought Forward from the Summaryof Part IV, OCCUPATIONAL HEALTH AND SAFETY, excludingValue Added Tax SUM

Carried to Final Summary R Section No. 5Bill No. 1HEALTH AND SAFETYPROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 1 9 9 -

Page 146: Provisional Bills of Quantities SECTION NO. 1 BILL NO. 1 ... OF...Provisional Bills of Quantities Item Quantity Rate Amount No "COMMENCEMENT DATE" means the date that the agreement,

Provisional Bills of Quantities

FINAL SUMMARY

Section Page AmountNo No

1 -92-Preliminaries

2 -180-Building Works

3 -192-Site Works

4 -198-Provisional Amounts

5 -199-Health and safety

SUB-TOTAL R

Contingencies

Allow the sum of R 200 000.00 (Two Hundered Thousand Rand) forthe Contingencies to be used as directed by the Principal Agent anddeducted in part or in whole if not required R 200 000 00

SUB-TOTAL R

ADD: VALUE ADDED TAX AT 14% R

Carried to Form of Tender R

PROPOSED ADDITIONAL FACILITIES TO MATLA PRIMARY SCHOOLLCAbn08-01

- 2 0 0 -