18
Potential for Tram in the City of Skopje, Project Introduction Gjorgjievski Kristijan | 13 October 2011

Potential for Tram in the City of Skopje, Project Introduction

  • Upload
    mckile

  • View
    34

  • Download
    0

Embed Size (px)

DESCRIPTION

Potential for Tram in the City of Skopje, Project Introduction. Gjorgjievski Kristijan | 13 October 2011. Developments in the past year. December 2010 – The City of Skopje engaged Vialto Consulting and EC Harris as consultants to do the following tasks: - PowerPoint PPT Presentation

Citation preview

Page 1: Potential for Tram  in the City of Skopje,  Project Introduction

Potential for Tram in the City of Skopje,

Project Introduction

Gjorgjievski Kristijan | 13 October 2011

Page 2: Potential for Tram  in the City of Skopje,  Project Introduction

Developments in the past year■ December 2010 – The City of Skopje engaged Vialto Consulting and EC

Harris as consultants to do the following tasks:

– Phase I - Preparation of a Study for a concession project for development and introduction of light railway system for passenger transport in the area of the City of Skopje. The study includes:

• Traffic - technical analysis

• Economic and financial analysis

• Legal analysis

• Possibilities for development

– Phase II - Preparation of Tender Documentation and model contract, evaluation criteria and animation of potential investors;

– Phase III – Advisory in the selection process and contracting negotiations

2

Page 3: Potential for Tram  in the City of Skopje,  Project Introduction

3

Planned Tram Network(Feasibility Study 2007)

Line 1Line 1 alternativesLine 2Line 3Line 4

Page 4: Potential for Tram  in the City of Skopje,  Project Introduction

4

Estimated Passenger Flow(Peak Hour)

Page 5: Potential for Tram  in the City of Skopje,  Project Introduction

5

Estimated Tram Passenger Flow

■ „Corridor” approach (change to tram)

– 80% of bus passengers (80 pax per bus)

– 20% of car passengers (1,5 pax per car)

■ Daily passengers assumptions

– w = 15% (peak hour factor)

– growth factor: 1% per year

– diameter shaped lines have two branches

■ Yearly passengers assumptions

– 250 workdays, 115 holidays

– holiday = 0.5 × workday

Page 6: Potential for Tram  in the City of Skopje,  Project Introduction

6

Other Analysed Technical Issues

■ Modification of tram stop allocation

■ Track alignment (side or central)

■ Tariff system

■ Bus reorganization

Page 7: Potential for Tram  in the City of Skopje,  Project Introduction

7

Proposed Versions

Bulit Service Journey approx

Version Service track length time peak off-peak evening service

name name length one dir. 6-8;13-17 5-6;8-13;17-20 20-23 per day

[km] [min] [min] [min] [min] [pcs]

A B C D E F G H I J

V1 Tram 1 Novo Lisice - Centar 5,7 5,7 16 6 10 10 132

V2a Tram 1 Gjorche Petrov - Novo Lisice 12,1 12,1 33 4 6 10 198

V2b Tram 1 Gjorche Petrov - Novo Lisice 12,1 12,1 33 6 6 10 168

V3 Tram 1 Gjorche Petrov - Novo Lisice 12,1 12,1 33 8 10 15 111

Tram 2 [Gjorche Petrov] - Sever 5,6 12,8 32 8 10 15 111

17,7

V4 Tram 1 Gjorche Petrov - Novo Lisice 12,1 12,1 33 4 6 10 198

Tram 2 Staklarna - Sever 9,6 10,2 25 8 10 15 111

21,7

V5 Tram 1 Gjorche Petrov - Novo Lisice 12,1 12,1 33 8 10 15 111

Tram 3 [Gjorche Petrov] - Agroservice 4,4 12,7 32 8 10 15 111

Tram 2 Staklarna - Sever 9,6 10,2 25 8 10 15 111

26,1

Tram lines ServicesFollow-up time

Page 8: Potential for Tram  in the City of Skopje,  Project Introduction

8

Investments and Operational CostVersion 2a - Novo Lisice - Centar - Gjorce Petrov

Page 9: Potential for Tram  in the City of Skopje,  Project Introduction

9

Investments and Operational CostVersion 2a - Novo Lisice - Centar - Gjorce Petrov

No. Item Unit QuantityCost

per unitTotal cost

A B C D E F1

2 Track infrastructure track km 24,2 2 000 48 4003 Catenary track km 24,2 500 12 1004 Depot (only at Novo Lisice) each 1 15 000 15 0005 Vehicles each 22 1 900 41 8006 Subtotal 1000EUR 117 3007 Technical reserve 1000EUR 10% 11 7308 Provision for inflation 1000EUR 5% 5 8659 Provision for exchange rate 1000EUR 5% 5 865

10 Total 1000EUR 140 76011

12 Vehicles running (O&M) cost* km 1 665 444 0,004 6 66213 Infrastructure maintenance track km 24,2 50 1 21014 Total per year 1000EUR 7 872

*228 runs on workdays (250 day/year), 168 runs on other days

[1000 EUR]

Investment cost

Operational cost ( per year )

Page 10: Potential for Tram  in the City of Skopje,  Project Introduction

Financial analysis of a possible version■ Optimum operative subsidy, with 10% initial investment

– 10 % initial investment granting

– optimum operative subsidy (to reach at least 11 % interest rate on equity and not to have negative cumulative cash-flow)

– no ticket price reduction (except for students and pensioner)

13 october 2011 |Kristijan Gjorgjievski| 10

Financial Indicators

Net present value 68.26 M Eur

Benefit – Cost Ratio(BCR) 1.217

Net discounted profit (NPV – PV of equity investment) 54.19 M Eur

Interest rate on equity 11.00 %

Total Subsidy PV 68.58 M Eur

Page 11: Potential for Tram  in the City of Skopje,  Project Introduction

The Study - Conclusions■ It is financially feasible to introduce the Tram as an environmentaly friendly high

capacity transport mode in the City of Skopje;

■ Among line options investigated, nr 1 proved to be most beneficial and financially feasible (12km long trunk line);

■ Later further development is possible (line 2, 3);

■ Sustainable public financing is needed

• 10 % initial investment granting

• optimal operative subsidy

■ Risks to be mitigated (cost overrun, time overrun, policy failure, car invasion).

■ Need for changes in legislation, due to a new way of transport

■ Additional measures:

1. Modification of local transport strategy.

2. Reorganisation of JSP

11

Page 12: Potential for Tram  in the City of Skopje,  Project Introduction

Next steps

■ The city of Skopje decided to proceed with the next phase, i.e into project preparatory phase

■ Animation of possible investors and organizing round table (end of November 2011)

■ Expected tender announcement – End of January 2012

13 october 2011 |Kristijan Gjorgjievski| 12

Page 13: Potential for Tram  in the City of Skopje,  Project Introduction

Questions ?

Page 14: Potential for Tram  in the City of Skopje,  Project Introduction

Thank You for Your Attention!

[email protected]

The study was prepared by

Dr. Csaba Orosz,

Dr. Janos BERÉNYI

Dr. Tibor Princz-Jakovics

Dr. Peter Bocz,

Page 15: Potential for Tram  in the City of Skopje,  Project Introduction

Backup slides

13 october 2011 |Kristijan Gjorgjievski| 15

Page 16: Potential for Tram  in the City of Skopje,  Project Introduction

16

PPP (DBFM) Structure

Page 17: Potential for Tram  in the City of Skopje,  Project Introduction

27th of June 2011 1717

Present traffic flow to the centre (morning peak hour)Тековен проток на сообраќајот во центарот car

bus

Page 18: Potential for Tram  in the City of Skopje,  Project Introduction

Public subsidy, Version 2a/4

15th of April 2011 18