NW Cornelius Pass Rd.
Project Update
ODOT Mobility
November 20st, 2018
Multnomah County Transportation
NW CORNELIUS PASS ROAD // Project Overview
Project Description
● Safety improvements are
needed to Cornelius Pass
Rd between Highway 30
and NW Kaiser Rd
● The Oregon Legislature
allocated funding to
Multnomah County for the
enhancements
● Landslides on alternate
routes delayed project
2
NW CORNELIUS PASS ROAD // Project Overview
3
NW CORNELIUS PASS ROAD // Project Details and Locations
3
NW CORNELIUS PASS ROAD // Traffic Plan
3
● Reviewed many options with consultant:○ In-water work:
■ 11-weeks (July 15-September 30) in water-work window.
■ Full closure required to do in one summer.
○ Flagging two-way traffic around one lane closure:
■ Traffic backups to Hwy. 26 and 30.
■ Large trucks may be banned due to narrow work zone.
○ One-way traffic:
■ Building culvert in 2 sections stretches schedule to 2 years
and very costly.
■ Large trucks may be banned due to narrow work zone.
○ Full Closure:
■ Large trucks have long detours, but fastest schedule
(4 months).
■ Cars and small trucks have nearby alternate routes.
NW CORNELIUS PASS ROAD // 2019 Construction Stages and Timelines
3
NW CORNELIUS PASS ROAD // Stage 1 Traffic Plan
3
NW CORNELIUS PASS ROAD // Stage 2 Traffic Plan
3
NW CORNELIUS PASS ROAD // Freight Detour Route
1
Truck alternate route
Hazardous material
truck alternate route
NW CORNELIUS PASS ROAD // Safety
1
NW CORNELIUS PASS ROAD // Next Steps
Detour Plan
● Bicycle and Pedestrian Outreach: October 2018
● Outreach to freight: November 2018
● Coordination with Washington and Columbia Counties
● Pre-construction public meeting: Spring 2019
● Other issues/actions needed?
1
NW Cornelius Pass
Questions
For more information:Web: multco.us/cornpass
Twitter: @MultCoRoads