Nick Johnson, PE Senior Project Manager CARSON CITY FREEWAY PHASE 2B October 1, 2012

Nick Johnson, PE Senior Project Manager October 1, 2012

Embed Size (px)

Citation preview

Carson City Freeway Phase 2B

Nick Johnson, PESenior Project ManagerCARSON CITY FREEWAY PHASE 2B

October 1, 2012

Presentation OverviewCarson Freeway ProjectsCarson Freeway Phase 2B overviewProject ElementsProject PhasingScheduleQuestions

Project History

CC Freeway Phase 2BApproximately 4 MilesFairview Drive to South Carson StreetOverall Cost: $100 -$110 M

Approximately $100 - $110 Million4 Lanes access controlled Freeway Fairview Dr. to S. Carson St.South Carson Street InterchangeCompletion of Fairview Drive InterchangeSnyder Avenue BridgeClearview Drive BridgeKoontz Avenue BridgeSound walls 5 miles Earthwork 1.4 million cubic yards of excavationDrainage FacilitiesConcrete Lined Channels, Box Culverts and Offsite Conveyance SystemDetention BasinsLandscaping and Aesthetic TreatmentsUtility Relocation of:Carson City Sanitary Sewer, Water and Reclaimed WaterSouthwest Gas, NV Energy, Charter Cable, Frontier, and AT&TCC Freeway Phase 2B

Fairview Drive Interchange

Koontz and Cleaview Structures

Snyder Ave. Structure

S. Carson St. Interchange

VOLTAIRE DETENTION BASINPONDEROSA DETENTION BASINBENNET DETENTION BASINPhase 2B Drainage

Sound WallsPhase 2B Sound Walls

Sound Wall Aesthetic Treatments

Sound Wall Aesthetic Treatments

Stewart Community Sound Wall PatternLandscape & Aesthetics

FAIRVIEW DRIVE CLEARVIEW DRIVESNYDER AVE.KOONTZ DRIVESOUTH CARSONSTREETPhase 2B to be constructed in 4 phasesPhasing ConsiderationsLocal Access and ConnectivityConstructabilityFunding Availability Design ConstraintsUtility RelocationsStructures DrainageEarthworkSound Walls Phasing PlanCarson City Freeway Phase 2B-1

Scope: Construct Koontz & Clearview Structures, Edmonds Channel, and Utility RelocationsCosts: $9 MillionAwarded to Q&D in Early 2010Completed Construction in October 2011

Scope: Construct Snyder Avenue Structure, Grading, Drainage, and Utility RelocationsCosts: $9.5 MillionAwarded to Granite in Early 2013Anticipated Completion in Summer 2014Carson City Freeway Phase 2B-2

Carson City Freeway Phase 2B-2Scope: Interim Connection to the US 50/S. Carson Street Signal, Earthwork, Sound Walls, L&A, and Paving, Signs, and Lighting.Costs: $40 - $43 MillionProject Advertisement: 2014 - 2015

Carson City Freeway Phase 2B-3Carson City Freeway Phase 2B-3

Scope: S. Carson Street Interchange and Final Freeway ConfigurationCosts: $27 - $30 MillionProject Advertisement: 2020 or later

Carson City Freeway Phase 2B-4

CARSON CITY FREEWAY Phase 2B SchedulePhase 2B is anticipated to be constructed in 4 packages.Phase 2B-1: Completed Oct. 2011Phase 2B-2: Anticipated Completion Mid 2014Phase 2B-3: Anticipated Start of Construction Mid 2015Phase 2B-4: To Be Determined; Pending Funding Availability

20122013201420152016201720182019202020212022Phase 2B-3**Dates subject to available fundingPhase 2B-2Phase 2B-4*CARSON CITY FREEWAY Phase 2B

Nick Johnson, PE Senior Project ManagerQUESTIONS