  • MT. SAN ANTONIO COMMUNITY COLLEGE DISTRICT

    Addendum No. 1

    August 25, 2017

    Purchase of Triple-Wide Trailer Unit, SIM Lab

    Bid No. 3167

    To All Bidders: All bidders shall acknowledge receipt of this Addendum on the bid form.

    Acknowledgement of receipt of this Addendum shall be taken as prime facie evidence that, prior to submission of this bid, the bidder was fully cognizant of all provisions of the Addendum and of all work and conditions affected thereby.

    FAILURE TO ACKNOWLEDGE RECEIPT OF THIS ADDENDUM MAY BE CAUSE TO REJECT BID AS BEING NON-RESPONSIVE.

    In case of conflict among Bid Documents, Contract Documents and this Addendum, this Addendum shall govern.

    This Addendum forms a part of the Bid Documents and modifies the original bid documents for the above-referenced project. The following changes, additions, or deletes shall be made. All other terms and conditions remain the same.

    Changes & Additions Item #1: Attached are the cut sheets and the three additional drawings with a drawing

    list. Attachments Zurn EZ Flush Sensor Unit Sloan VBF-72 A Vacuum Breaker Trap Sloan Royal Flushmeter Projector and Screen Mounts Pro 750 Food Waste Disposers Olsonite Toilet Seat Mitsubishi Electric P-Series Legrand Projector Mount an Ceiling Box Lectern Location Drawing FSR-PWB 253 Elkay Sink Drawing Log – SIM Lab Trailer Dahl Mini-ball Valves Chicago Faucets Chicabo Faucets Sink Faucet with Side

  • Bid No. 3156 Addendum No. 1

    Page 2 of 2 American Electric Water Heaters SIM Lab Trailer Spec Chart Floor Plan Site Plan Topo Plan Revised Drawing List Rev 1 General Conditions

    END OF ADDENDUM

  • Mt. SAC PROJECT

    GENERAL CONDITION LIST

    PROJECT: DRAFT

    SIM LAB PROJECT 8/24/2017 REV 1

    GENERAL CONDITIONS 3,600 sf

    No. Description Responsible Contractor Notes

    1.0

    Trash pick up and site clean up. The trailer vendor will be responsible to

    pick up their trash daily. The general contractor will provide a dumpster

    located outside. All

    1.1 Contractor will provide the following: All

    3 - 33 gallon (or larger) Trash Cans -

    We prefer that trash be separated from recyclables

    2 - Brooms and Dust Pans

    These items to be given to owner at end of project.

    2.0 Communication All

    2.1

    There will be a weekly tailgate (in the building) meeting to coordinate the

    work and discuss any issues.

    2.2

    Weekly Safety meetings are to be held with your staff and notes from this

    meeting are to be given to Mt SAC Field Manager.

    2.3 All communications are to go through the Mt SAC Field Manager

    3.0 Behavior All

    3.1

    This project is in an busy parking lot and near an operational building

    where there will be students and staff during the construction timeframe.

    As such there will be no fraternization with the students or other faculty

    members.

    3.2

    Due to the nearby classes and offices no radios will be allowed and no

    inappropriate or lewd language will be allowed.

    3.3

    Appropriate clothing will be worn at all times: Shirts, pants / shorts,

    sturdy shoes will be required. Personal Protective Equipment will be

    required - hard hats, safety glasses and vests will be required.

    4.0

    Parking - Parking Permits will be issued by the Project Manager and Site

    staff. Please put it on the dashboard for your vehicle(s) at all times. We

    are not responsible for any parking citations or fees that may be charged

    due to a failure of this protocol. All

    5.0

    The trailer vendor is responsible for electrical power during their work.

    He is to coordinate with the Mt SAC Field Manager for the following: All

    power shut-downs

    equipment electrical tie-ins

    Power, data, sewer and water to the SIM Lab will be provided by a

    General Contractor working directly for the Owner. General Contractor

    6.0 The Modular Vendor will be responsible to provide the following: Trailer Vendor

    Ventilation of the work areas if required.

    Secured site.

    7.0

    Flooring - will be provided by Owner for all areas EXCEPT the three

    restrooms. The floor of the restrooms will be Dal Tile ceramic tile with

    cove base by Trailer Vendor.

    Flooring Contractor - by

    owner

    7.1

    Flooring Contractor - Will provide floor protection for the use of all

    contractors once the flooring has been laid. Any contractor not using the

    floor protection will be responsible for the cost of the repair of the

    damaged material.

    Flooring Contractor - by

    owner

    8.0

    Caulking and Trim -The Trailer vendor is responsible for caulking and

    trimm for their work, and for fire blocking, water proofing, and making

    openings water tight. Trailer Vendor

    9.0

    Daily lock up - Will be the responsibility of the Trailer Vendor. If the

    Trailer vendor is not on site, any workers must advise the Mt SAC field

    rep to check all openings and doors to make sure the site is locked every

    night. All

    10.0

    Work Schedule - The normal working hours will be 7:00 am to 7:00 pm,

    but extended work hours on Monday thru Friday and on weekends can

    be coordinated with the Mt. SAC site rep. Excessive noise will also need

    to be coordinated with the site rep to avoid impact to the daily operations. All

    11.0 Demo and new site work General Contractor

    11.1

    The General Contractor will pull back all utilities prior to the demolition for

    the modular General Contractor

    11.2

    The contractor must protect the site and their work area from student

    traffic and vehicular traffic with a construction fence. All

    11.3

    All contractors must removal all of their own trash. It cannot be disposed

    of on the Mt SAC campus. All

    11.4

    Coordination with the Mt. SAC IT department and Public Safety

    Department will be necessary. All

    11.5

    Fence - Install the 48: tall chain link fence per the drawings. Install the

    Owner provided 3 K-rail per the drawings. Owner's K-rail is located near

    the entrance to the Wild Life Sanctuary and will require a large fork lift to

    move it. General Contractor

    The following General conditions will apply to all contracts issued for this project. The designated contractor who is to supply or be

    responsible for the item is noted in the column to the right.

  • cj/mtsac/B41A/ BIDs/ Rondell/ 8-24-17 REV 1 General conditions List - SIM LAB TRAILER.

  • Facilities Planning & Management 1100 North Grand Avenue Walnut, CA 91789

    909-274-4850 www.mtsac.edu

    Project Name: SIM LAB TRAILER

    Drawing No. Drawing Name Date Addendum

    No. Notes

    0.1 Topo Plan 8/24/2017 1 0.2 Site Plan 8/24/2017 1 0.3 Floor Plan 8/24/2017 1

    E-0.1 Legend and Sheet Index 6/21/2017 E-0.2 General Notes 6/21/2017 E-1.0 Electrical Site Plan 6/21/2017 E-2.0 SIM Lab Electrical Plan 6/21/2017 E-2.1 SIM Lab Lighting Plan 6/21/2017 E-6.1 Details 6/21/2017 E-6.2 Details 6/21/2017 E-6.3 Details 6/21/2017

    7 8 9

    11

    REVISED DRAWING LIST

    1

    10

    6 5 4

    2

    Number

    3

    BID No. 3167

    8/24/2017

  • mpenaloza1 Text Box Simulation Lab Trailer

    mpenaloza1 Text Box TOPO Site Plan

    mpenaloza1 Text Box 1 of 3

    mpenaloza1 Text Box 08/24/17

  • SIM LAB TRAILER SPECIFICATION CHART 8/24/2017 REV 2 DRAFT

    Confirm in

    design Audio Visual Information

    Technology Size 36' x 60' sf 2,160

    Item

    # Item Quantity

    Included

    in

    contract

    Not

    included in

    contract Total Fee $

    Work by

    Trailer

    Vendor

    Contractor

    by Mt. SAC

    Facilities

    Work by Mt.

    SAC IT

    Work by

    MT. SAC

    AV

    contractor

    Work by

    General

    Contractor

    / Electrical

    CONTRACT PART 1

    1 Design & Engineering X X

    2 Exterior Elevations X X

    3 Sections each direction X X

    4 Standard Delivery & Installation X X

    5 Standard craning & rigging X X

    6

    Fire extinguisher cabinets with

    extinguishers per code X X

    7

    CONTRACT PART 2

    FABRICATION

    8

    SWPPP program, dust control and

    erosion control N/A

    9

    Single Story Trailer building, Type

    V construction X X

    10

    20 lb. roof - 3-GNC built-up roof

    with gutters and downspouts -

    center ridge X X

    11

    Connection of downspouts to

    storm drain system N/A

    12 85 mph exposure X X

    13 Type V non- rated, 2013 CBC X X

    14 65 lb. floor load X X

    15 FOB Walnut, CA X X

    16 36' X 60' X X

    17 Stiffened wood subfloor X X

    18

    Site Utility Connections by Mt SAC

    contractor X X

    19

    TOTAL FEE (including all of

    items below)

    20

    21

    Features - Included in base

    Scope

    22

    Mounting blocks with seismic tie-

    downs and skirt painted to match

    the sidin