No 03/1203 Edition: AIRAC 1203
Monitoring Report: AIRAC 1208 26 July 2012 - 22 August 2012
E UROCONTROL
EUROPEAN ORGANISATION FOR SAFETY OF AIR NAVIGATION
European Route Network Improvement Plan
(ERNP) Implementation Monitoring
Monitoring Report: AIRAC 1208 26 July 2012 - 22 August 2012
DIRECTORATE NETWORK MANAGEMENT
Left blank intentionally
European Route Network Improvement Plan (ERNIP) – Implementation Monitoring Monitoring Report AIRAC 1208 (26 July 2012 – 22 August 2012)
- 1 -
TABLE OF CONTENT TABLE OF CONTENT...................................................................................................................... 1 1. INTRODUCTION................................................................................................................. 3
1.1 SUMMARY...........................................................................................................................3 1.2 EVOLUTIONS TOWARDS THE ACHIEVEMENT OF THE EUROPEAN TARGET ............3 1.3 AIRSPACE DESIGN DEVELOPMENT AND IMPLEMENTATION MONITORING ..............3 1.4 EXTERNAL DOCUMENT RELEASE...................................................................................4
2. LIST OF PROPOSALS IMPLEMENTED AIRAC 1208 (26 JULY 2012)............................ 5 2.1 SUMMARY OF MAJOR PROJECTS IMPLEMENTED ON 26 JULY 2012..........................5
3. AIRSPACE DESIGN INDICATOR...................................................................................... 6 3.1 FLIGHT EFFICIENCY INDICATORS EVOLUTION .............................................................6 3.2 FLIGHT EFFICIENCY EVOLUTION PER AIRAC CYCLE...................................................6 3.3 EVOLUTION OF INDICATORS ...........................................................................................7 3.4 BENEFITS............................................................................................................................7
ANNEX A: DETAILED LIST OF PROJECTS IMPLEMENTED 26 JULY 2012 ............................... 9 ANNEX B: ACRONYMS AND ABBREVIATIONS ......................................................................... 12
European Route Network Improvement Plan (ERNIP) – Implementation Monitoring Monitoring Report AIRAC 1208 (26 July 2012 – 22 August 2012)
- 2 -
Left blank intentionally
European Route Network Improvement Plan (ERNIP) – Implementation Monitoring Monitoring Report AIRAC 1208 (26 July 2012 – 22 August 2012)
- 3 -
1. INTRODUCTION
1.1 SUMMARY This Report informs on the progress achieved to further improve the airspace design and utilisation flight efficiency based on the improvement proposals implemented during the relevant AIRAC cycle. The methodology used for assessing flight efficiency is included in the WP9 of RNDSG/64. This document can be consulted on: http://myorbite.eurocontrol.int/http://beid.eurocontrol.be:8980/Members/irc/eurocontrol/rndsg/home. This edition focuses on AIRAC 1208 (26 July 2012).
1.2 EVOLUTIONS TOWARDS THE ACHIEVEMENT OF THE EUROPEAN TARGET
The Performance Scheme for air navigation services and network functions includes an environment/ flight efficiency Key Performance area: Average horizontal en-route flight efficiency: o the average horizontal en-route flight efficiency indicator is the difference between the length of
the “en-route” part of the trajectory and the optimum trajectory which, in average, is the great circle.
o “en-route” is defined as the distance flown outside a circle of 40 NM around the airport. o the flights considered for the purpose of this indicator are:
- all commercial IFR flights within European airspace; - where a flight departs or arrives outside the European airspace, only that part inside the
European airspace is considered; - circular flights and flights with a great circle distance shorter than 80NM between terminal
areas are excluded. For the performance reference period starting on 1st January 2012 and ending on 31st December 2014, the European Union-wide and EUROCONTROL performance targets will be as follows: Environment target: an improvement by 0,75 percentage points of the average horizontal en-route flight efficiency indicator in 2014 as compared to the situation in 2009.
1.3 AIRSPACE DESIGN DEVELOPMENT AND IMPLEMENTATION MONITORING The Network Manager coordinates the following activities to achieve the required improvement in flight efficiency:
Enhancing European enroute airspace design through annual improvements of European ATS route network, high priority being given to: o Implementation of a coherent package of annual improvements and shorter routes; o Improving efficiency for the most penalised city pairs; o Implementation of additional Conditional Routes for main traffic flows; o Supporting initial implementation of free route airspace.
Improving airspace utilisation and route network availability through: o Actively supporting and involving aircraft operators and the computer flight plan service
providers in flight plan quality improvements; o Gradually applying route availability restrictions only where and when required; o Improving the use and availability of civil/military airspace structures.
Efficient Terminal Manoeuvring Area (TMA) design and utilisation through: o Implementing advanced navigation capabilities; o Implementing Continuous Descent Operations (CDO), improved arrival/departure routes,
optimised departure profiles, etc. Improving awareness of performance.
European Route Network Improvement Plan (ERNIP) – Implementation Monitoring Monitoring Report AIRAC 1208 (26 July 2012 – 22 August 2012)
- 4 -
1.4 EXTERNAL DOCUMENT RELEASE A copy of the AIRAC Report of the European Route Network Improvement Plan is also available via the restricted OneSky Online websites for access by other interested members of the RNDSG, ASMSG and NETOPS (see ref sub-sections under main section "LIBRARY"). EUROCONTROL OneSky Teams NETOPS, RNDSG and ASMSG Library: http://myorbite.eurocontrol.int/http://beid.eurocontrol.be:8980/Members/irc/eurocontrol/ant/home http://myorbite.eurocontrol.int/http://beid.eurocontrol.be:8980/Members/irc/eurocontrol/rndsg/home http://myorbite.eurocontrol.int/http://beid.eurocontrol.be:8980/Members/irc/eurocontrol/asm-sg/home EUROCONTROL Airspace, Network Planning & Navigation activities website http://www.eurocontrol.int/airspace/public/subsite_homepage/homepage.html Furthermore, it is planned to upload the AIRAC Report of the European Route Network Improvement Plan as well on: NOP Network Operations Portal / Post-Operations https://www.public.cfmu.eurocontrol.int/PUBPORTAL/gateway/spec/index.html ERNIP database: http://prisme-web.hq.corp.eurocontrol.int/ernip-database/Index.action
European Route Network Improvement Plan (ERNIP) – Implementation Monitoring Monitoring Report AIRAC 1208 (26 July 2012 – 22 August 2012)
- 5 -
2. LIST OF PROPOSALS IMPLEMENTED AIRAC 1208 (26 JULY 2012)
2.1 SUMMARY OF MAJOR PROJECTS IMPLEMENTED ON 26 JULY 2012 During the AIRAC cycle 6 packages of airspace improvements coordinated at network level have been implemented. The list below provides an overview of the major improvement projects implemented on 26 July 2012:
Egypt: - Cairo FIR new Night ATS route.
Germany / Austria:
- ATS route network improvements.
Germany / France: - ATS route network improvement (shorter route option city pair EDDM - LFPG).
Italy:
- Milano FIR ATS route network improvements.
Spain: - Madrid FIR ATS route network improvements.
Turkey:
- Ankara FIR Lower ATS route network improvements (for new Igdir/LTCT airport).
A detailed list of all improvement measures implemented on 26 July 2012 is attached in Annex A. The list is an extract of the European Route Network Improvement Plan database accessible via: https://extranet.eurocontrol.int/http://prisme-web.hq.corp.eurocontrol.int/ernip_database/Index.action A description of the airspace improvements together with orientation maps due for implementation on the relevant AIRAC cycle is provided in the RNDSG Airspace Improvements Synopsis (RAIS).
European Route Network Improvement Plan (ERNIP) – Implementation Monitoring Monitoring Report AIRAC 1208 (26 July 2012 – 22 August 2012)
- 6 -
3. AIRSPACE DESIGN INDICATOR
3.1 FLIGHT EFFICIENCY INDICATORS EVOLUTION The graphs below show the evolution of the airspace design flight efficiency (RTE-DES) and of the last filed flight plan indicator (RTE-FPL) between 2007 and 22 August 2012.
RTE-DES
3.53% 3.54% 3.45% 3.22% 3.04% 2.97%
2%
3%
4%
5%
6%
2007 2008 2009 2010 2011 2012
RTE-FPL
4.91% 5.03% 4.90% 4.91% 4.73% 4.65%
2%
3%
4%
5%
6%
2007 2008 2009 2010 2011 2012
3.2 FLIGHT EFFICIENCY EVOLUTION PER AIRAC CYCLE The graph below shows the evolution per AIRAC cycle of the flight efficiency indicators between 2007 and 22 August 2012.
Route Efficiency KPI per AIRAC cycle
2010
2008
2007
2009
2011
2.5%
3.0%
3.5%
4.0%
4.5%
5.0%
5.5%
713
801
802
803
804
805
806
807
808
809
810
811
812
813
901
902
903
904
905
906
907
908
909
910
911
912
913
1001
1002
1003
1004
1005
1006
1007
1008
1009
1010
1011
1012
1013
1101
1102
1103
1104
1105
1106
1107
1108
1109
1110
1111
1112
1113
1201
1202
1203
1204
1205
1206
1207
1208
AIRAC
Rou
te E
xten
sion
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
RTE-DESRTE-FPL
Note: FPL: Flight Plan data provided by CFMU, SAAM analysis performed by DNM/COO/NOM/OPL. DES:Ttraffic demand provided by CFMU, airspace environment data, profile calculations and SAAM analysis provided by DNM/COO/NOM/OPL.
European Route Network Improvement Plan (ERNIP) – Implementation Monitoring Monitoring Report AIRAC 1208 (26 July 2012 – 22 August 2012)
- 7 -
3.3 EVOLUTION OF INDICATORS The current data indicates that, the route extension due to airspace design reduced between 2009 and 2012 by 0.48 percentage points. The evolution of the airspace design indicator is on the right trend and the contributions of the airspace design projects are key for improving flight efficiency. The current data indicates that, the route extension based on the last filed flight plan reduced between 2009 and 2012 by 0.25 percentage points. The difference between the airspace design indicator and the last filed flight plan indicator was 1.45 percentage points in 2009 and is 1.68 percentage points in August 2012, recording a slight decrease compared to the previous AIRAC cycle. The route extension due to airspace design reached in August 2012 a historically low level, at 2.93%. The evolution of the airspace design indicator is on the right trend and the contributions of the airspace design projects are key for improving flight efficiency. The route extension based on the last filed flight plan went down to the lowest levels ever at 4.53% in August 2012. The differences shown above clearly indicate that more efforts must be made to improve the efficiency of the airspace utilisation and to ensure that the indicator based on the latest filed flight plan follows a similar trend like the airspace design indicator.
3.4 BENEFITS Due to the airspace design improvements, the savings achieved during the AIRAC cycle 1208 amount to 121 114 NMs flown less compared to the equivalent AIRAC cycle in 2011. This translates into approximately 727 tons of fuel, or 2400 tons of CO2, or 605 000 Euros. Based on the last filed flight plan indicator, the savings achieved during the AIRAC cycle 1208 amount to 241 000 NMs flown less compared to the equivalent AIRAC cycle in 2011. This translates into approximately 1400 tons of fuel, or 4800 tons of CO2, or 1 205 000 Euros.
FLIGHT EFFICIENCY SAVINGS COMPARED TO EQUIVALENT AIRAC CYCLE IN THE PREVIOUS YEAR
(In Nautical Miles)
-300000
-200000
-100000
0
100000
200000
300000
400000
AIRAC CYCLE
NM NM DES
NM FPL
NM DES 230000 62000 6000 157000 96100 236000 169000 121114
NM FPL 242000 45000 -200000 139000 82400 331000 150854 241141
1201 1202 1203 1204 1205 1206 1207 1208
FLIGHT EFFICIENCY SAVINGS COMPARED TO EQUIVALENT AIRAC CYCLE IN THE PREVIOUS YEAR
(In CO2)
-6000
-4000
-2000
02000
4000
6000
8000
AIRAC CYCLE
TON
S O
F C
O2
TONS CO2 DES
TONS CO2 FPL
TONS CO2 DES 4600 1240 120 3140 1922 4720 3380 2422
TONS CO2 FPL 4840 900 -4000 2780 1648 6620 3017 4823
1201 1202 1203 1204 1205 1206 1207 1208
FLIGHT EFFICIENCY SAVINGS COMPARED TO EQUIVALENT AIRAC CYCLE IN THE PREVIOUS YEAR
(In Tons of Fuel)
-1500-1000-500
0500
1000150020002500
AIRAC CYCLE
TON
S O
F FU
EL
TONS FUEL DES
TONS FUEL FPL
TONS FUEL DES 1380 372 36 942 577 1416 1014 727
TONS FUEL FPL 1452 270 -1200 834 494 1986 905 1447
1201 1202 1203 1204 1205 1206 1207 1208
FLIGHT EFFICIENCY SAVINGS COMPARED TO EQUIVALENT AIRAC CYCLE IN THE PREVIOUS YEAR
(In EURO)
-1500000
-1000000
-500000
0
500000
1000000
1500000
2000000
AIRAC CYCLE
EUR
O EURO DESEURO FPL
EURO DES 1150000 310000 30000 785000 480500 1180000 845000 605570
EURO FPL 1210000 225000 -1000000 695000 412000 1655000 754270 1205705
1201 1202 1203 1204 1205 1206 1207 1208
European Route Network Improvement Plan (ERNIP) – Implementation Monitoring Monitoring Report AIRAC 1208 (26 July 2012 – 22 August 2012)
- 8 -
Left blank intentionally
European Route Network Improvement Plan (ERNIP) – Implementation Monitoring Monitoring Report AIRAC 1208 (26 July 2012 – 22 August 2012)
- 9 -
ANNEX A: DETAILED LIST OF PROJECTS IMPLEMENTED 26 JULY 2012 The following table presents detailed information about each of the improvement proposals developed within the RNDSG and implemented 26 July 2012. The description of the proposals is based on the information available from different sources (e.g. AOs, ANSPs and EUROCONTROL). For the correctness and verification of the relevant aeronautical information consult official State AIP publication. The data from this document should not be used for operational purposes. The table includes:
Proposal number: A reference number to identify each proposal allowing to trace at which RNDSG it was
initiated.
Description: A detailed description of the planned improvement proposal.
Objective: A brief description of the purpose of the enhancement measure.
Status: The implementation status defined as Proposed, Planned, Confirmed or Implemented.
Project Group: The Functional Airspace Block Group (FAB), Regional Focus Group (RFG), Sub-Group (SG) or any other Project Group(s) involved directly or indirectly by the proposed enhancement measure.
Project Category: The nature of the proposed enhancement measure defined through Project Categories referring to:
o Airspace Structure; o ATC Sectors; o ATS Routes; o CDRs: o Civil/Military Airspace; o DCTs; o Free Route Airspace; o Night Routes; o RAD; o Route Redesignation; o TMA.
States and Organisations: The States and/or Organisations involved directly or indirectly by the proposed enhancement measure.
Originator(s): The States, Organisations who have originated the proposal.
Comments: The conditions and/or pre-requisites which have to be met in order to implement the proposal or any other relevant comment(s).
Note: The list of implemented changes for this AIRAC cycle does not claim to be complete.
European Route Network Improvement Plan (ERNIP) – Implementation Monitoring Monitoring Report AIRAC 1208 (26 July 2012 – 22 August 2012)
- 10 -
Proposal : 69.221 Status: State(s) & Org. Comments:
1.
To implement a shorter route option for city pair EDDM - LFPG as follows: 1. new ATS routes and/or route segments:
T107 LUPEN - KUNOD eastbound (ODD) [CDR 1/2] only for ARR EDDM; UM164 PELOG - UTABA westbound (EVEN) [CDR 1] only for DEP EDDM; Z714 OLASO - LUPOL westbound (EVEN) [extension];
2. realignment of existing ATS route UM164 as LUPEN - UTABA and change it from eatbound to bidirectional (westbound only for DEP EDDM).
Objective: To reach the requirement of major AOs.
Implemented 26 JUL 2012 Project Group: FAB EC 50 MPCPEs Project Category: ATS Routes
DEU FRA Originator(s): DEU
Germany stated that new SID OLASO will allow proper connection to UM164 via LUPEN.
Proposal : 76.010 Status: State(s) & Org. Comments:
2.
To implement bidirectional ATS route UM191 NVS - PDT. Objective: To further improve ATS route network within Spain.
Implemented 26 JUL 2012 Project Category: ATS Routes
ESP Originator(s): ESP
Extension of existing RD. Currently UM191 exists as RIVRO - BARDI
- RIDAV - DIPOL - NVS.
Proposal : 76.043 Status: State(s) & Org. Comments:
3.
To implement the following eastbound ATS route segments: 1. Y11 LAPRI - KUMIN, vertical limits FL145/195, MNM FL150, 2. M730 NITAM - KUMIN, vertical limits FL155/195, MNM FL170; 3. M730 KUMIN - KODOK, vertical limits FL135/195, MNM FL150; 4. M730 KODOK - TOP, vertical limits FL095/195, MNM FL110. Objective: To further improve the ATS route network within Milano FIR.
Implemented 26 JUL 2012 Project Category: ATS Routes
ITA Originator(s): ITA
Proposal : 76.065 Status: State(s) & Org. Comments:
4.
To implement the following new low level ATS routes for traffic to/from new Igdir (LTCT) airport: 1. W138 YAVUZ - PEXES - GDR bidirectional; 2. W159 ARI - GDR bidirectional. Objective: To further improve ATS route network within Ankara FIR.
Implemented 26 JUL 2012 Project Group: RFG SE Project Category: ATS Routes
TUR Originator(s): TUR
Proposal : 76.060 Status: State(s) & Org. Comments:
European Route Network Improvement Plan (ERNIP) – Implementation Monitoring Monitoring Report AIRAC 1208 (26 July 2012 – 22 August 2012)
- 11 -
5.
To implement northbound Night ATS route T55 NABED - GINDI - KATAB. Objective: To further improve the ATS route network within Cairo FIR while providing a shorter option for HEGN and HEMA departures to Germany, Switzerland and Austria.
Implemented 26 JUL 2012 Project Category: Night Routes ATS Routes
EGY Originator(s): EGY
Hours of operation 2200-0500. Estimated savings ~34NM per flight.
Proposal : 76.064 Status: State(s) & Org. Comments:
6.
a. To implement the following new ATS routes and/or route segments: i. T168 KERAX - EBIPA - INBOS - PSA - PEKIG - ASBAB
bidirectional; ii. Y168 UTOPO - GEKPI - KNG eastbound (ODD) [DEP EDFE
only]; iii. Y169 UTOPO - RID southbound (ODD) [DEP EDFE only];
b. To realign the following existing ATS routes (new waypoint): L605, UL605, M/UM852, N/UN871, Q104, Q118, UQ305, T700, Z113.
c. To raise the upper vertical limit of ATS route Z714 LUPOL - PELOG from FL90 to FL660.
d. To permanently withdraw existing waypoint BAGED. e. To introduce changes to utilisation remarks on the following ATS
routes or route segments: N850, Q230, Q800, UL986, UN851, UZ36, UZ131, Z850.
Objective: To further improve ATS route network between Germany and Austria.
Implemented 26 JUL 2012 Project Category: ATS Routes
DEU AUT Originator(s): DEU AUT
European Route Network Improvement Plan (ERNIP) – Implementation Monitoring Monitoring Report AIRAC 1208 (26 July 2012 – 22 August 2012)
- 12 -
ANNEX B: ACRONYMS AND ABBREVIATIONS
1. The following ISO-3 coding of States is used in the column States and Organisation: ALB Albania IRQ Iraq ARM Armenia ITA Italy AUT Austria LBY Libyan Arab Jamahiriya AZE Azerbaijan LTU Lithuania BEL Belgium LUX Luxembourg BGR Bulgaria LVA Latvia BIH Bosnia and Herzegovina MAR Morocco BLR Belarus MDA Moldova, Republic of CHE Switzerland MKD The former Yugoslav Republic of Macedonia CYP Cyprus MLT Malta CZE Czech Republic MNE Montenegro DEU Germany NLD Netherlands DNK Denmark NOR Norway DZA Algeria POL Poland EGY Egypt PRT Portugal ESP Spain ROU Romania EST Estonia RUS Russian Federation FIN Finland SRB Serbia FRA France SVK Slovakia GBR United Kingdom SVN Slovenia GEO Georgia SWE Sweden GRC Greece SYR Syrian Arab Republic HRV Croatia TUN Tunisia HUN Hungary TUR Turkey IRL Ireland UKR Ukraine IRN Iran, Islamic Republic of
MUAC Maastricht UAC
European Route Network Improvement Plan (ERNIP) – Implementation Monitoring Monitoring Report AIRAC 1208 (26 July 2012 – 22 August 2012)
- 13 -
2. BLUMED FAB, DANUBE FAB and FAB CE proposals referenced in proposal number box are coded with a unique identification number abbreviated as BM or DN or CE, respectively, following by four digits (XXXX) (example BM0001 or DN0001 or CE0001).
3. Content of each proposal is an indication of State’s intention to implement the relevant airspace improvement but don't represent a copy of any official publication. For the correctness and verification of the relevant aeronautical information consult official State AIP publication. The data from this document should not be used for operational purposes.