MICE WBS rebuild/extract: • Top level: http://mice.iit.edu/tb/MICE-Schedule/ – PM: (Long acting) • Level 2: – MICE Muon Beam, MICE Hall and infrastructure • MMB, MH&I: Nichols • S/w, cntrls, instrumentation: Apsimon – MICE Instrumentation: • Bross – MICE Cooling Channel • Zisman To be expanded to next levels asap. S/w to be included in tasks as Appropriate (c.f,trackergroup) S/w infrastructure (fibre to ATLAS centre forexpam ple)in infrastructure

MICE WBS rebuild/extract: Top level: –//mice.iit.edu/tb/MICE-Schedule/ –PM: (Long acting) Level 2: –MICE Muon

  • View
    217

  • Download
    0

Embed Size (px)

Citation preview

MICE WBS rebuild/extract:• Top level:

– http://mice.iit.edu/tb/MICE-Schedule/– PM: (Long acting)

• Level 2:– MICE Muon Beam, MICE Hall and infrastructure

• MMB, MH&I: Nichols• S/w, cntrls, instrumentation: Apsimon

– MICE Instrumentation:• Bross

– MICE Cooling Channel• Zisman

To be expanded to next levelsasap.

S/w to be included in tasks asAppropriate (c.f, tracker group)

S/w infrastructure (fibre to ATLAScentre for expample) in infrastructure

2.0 MICE Muon Beam, MICE Hall, infrastructure

• MICE Muon Beam, MICE Hall, infrastructure:– Nichols

• Software, controls, instrumentation:– Apsimon

2.0 MMB, MH&I

2.0.1 MICE Muon Beam: Long

2.0.2 MICE Hall and infrastructure: Nelson

2.0.3 Christmas 2007 shutdown: Hayler

2.0.1 MICE Muon Beam

• Long

2.0.1.1 Target• Booth

• Removal of old target:• Discussion with RPA:

• Require revised method statement quantifying doses, isotopes etc.

• Suggestion using MMPX to evaluate activation

• Revision goal: 13Sep07• 18: Jacking motor controls:

• Working with G.Charnley, to be updated, goal 13Sep07.• 23: Cable installation: working with A.Nobbs, to be updated, goal

13Sep07• 33: Development of bearings: working S.Payne

• Require to prepare document for CM19. Document to:• Propose operation scheme to be presented to ISIS

(Findlay) for running from January ’08;• Propose development plan for final target bearing

scheme

• 37: Installation of the PSU:• Location defined, working with A.Nobbs

• 40: Installation of target controls:• Location defined, working DL on controls, S.Britnell on

cabling in Hall and MLCR• Revision of schedule promised for 13Sep07

2.0.1.2 Q35 refurbishment• Long

• Refurbishment scheme needs to be reviewed in light of experience

• Review to be carried out as soon as E.Cappozi and C.Locket are both avaulable.

• Testing scheme to be developed in consultation with M.Hughes and K.Tilley

2.0.1.3 Linde refridgerator

• Courthold

• Noted pressure on schedule:

• First priority: must not be allowed to slip:

• Implies potential call on additional resources

• Require to ensure adequate number of people trained for working at height:

• MC has organisation of training course in hand

• ~8 places available.

• Agreed: first call on places for:

• Spensley (if not already trained), Jamdagni (+second Hall Foreman), Capozzi, Lockett, Courthold, Nelson, Jones

2.0.1.4 PSI solenoid• Courthold

• To be reviewed for next week (13Sep07)

• Noted from discussion:

• Require to add electrical testing schedule

• Swagelock adaptor, which is on order, is required before vac test can begin.

• Question added ‘in proof’:

• Does this need to be chased with Swagelock?

2.0.1.5 Q4—9 installation

• Nelson

• To be reviewed for next week (13Sep07)

• Noted from discussion:

• Presently only delivery schedule

• Installation schedule needs to be developed

2.0.2 MICE Hall

• Nelson• Tasks identified (with person responsible) below. [Caution, may not be complete list:]

• Magnetic shield walls Nelson

• MICE Hall Floor: Nelson

• Plinth (concrete infill in ‘pit’)

• False floor (levelling sloping floor)

• Rolling platforms Nelson

• Water Govens

• Air conditioning Govens

• Power Griffiths

• Liquid-hydrogen system Ivanyushenkov

• MLCR Kyberd

• Networking Brandwood

• Cabling: Griffiths

• Linde

• Test positions Courthold

• Final positions Courthold

• Cable trays/cable layout etc.

2.0.2.1 MICE Local Control Room• Kyberd

• P.Kyberd not at meeting so noted:

• Revision requested for 13Sep07

• Personnel responsible for sub-systems:

• Civil work: Houseman in absence of Pyke

• PPS Alexander

• Networking Brandwood

• Racks ‘DL’

• Rack installation PK

• Cabling Britnell

2.0.3 XMas2007-shutdown

• Hayler

• Discussion of resources (availability, etc.) starts 06Sep07

• Priority 1:

• Implies planning of tasks Sep—Dec done to preserve/advance Christmas schedule