I-91 Viaduct Public Information Briefing
Agenda
Welcome and Presenter Introductions
Update on Construction and Demolition Activities
(Stage 1B)
Next: Stage 2 Starts in Early Winter 2016
Traffic Management & Mitigation
Public Involvement and Outreach
7/25/2019 I-91 Update
2/23
6/27
Project Purpose
To replace the bridge deck of the I-91 Viaduct in
Springfield, due to its poor condition. The result will be a
more reliable and dependable highway.
Project Limits
7/25/2019 I-91 Update
3/23
6/27
Project Scope Rehabilitation includes the following:
Complete deck replacement
Painting of structural steel, replacement of bearings,structural steel repairs, concrete substructure repairs
Improved bridge drainage and highway lighting (on thehighway, surface streets under the viaduct, upper levels ofthe north and south garage, and the Columbus Avenuerailroad underpass)
Other safety improvements, such as at the I-291/I-91 merge
Comprehensive Traffic Management
Fast Facts Viaduct length is approximately mile
15,000 cubic yards of concrete for bridge deck and barriers1,500 cubic yards placed to date
Over 7 million pounds of reinforcing steel710,000 pounds placed to date
Over 450 bearing replacementsover 63 replaced to date
23 subcontractors to date
Approximately 100 workers per day of which over 20 are from Springfieldand over 80 are from the Greater Springfield area and Western Mass.
7/25/2019 I-91 Update
4/23
6/27
J.F. White Contracting Co. A General Contractorperforming heavy civil work in Massachusetts for over90 years.
Schiavone Construction Co. A General Contractorperforming heavy civil work in the northeast regionfor over 50 years.
The Joint Venture Constructing the Project
Construction Schedule
Milestone ContractorForecasted
Date
ContractRequired
Date
Stage 1A Complete N/A
Stage1B Ongoing N/A
Stage2Start EarlyWinter2016 N/A
Full
Beneficial
Use Late
Fall
2017 August
6, 2018
Substantial Completion LateFall2018 November 6,2018
FieldCompletion January2019 February 4,2019
7/25/2019 I-91 Update
5/23
6/27
Definition of Full Beneficial UseI-91, I-291 & Assoc. Ramps
Themajorityofthecontractworkhasbeencompletedand
theasset(s)hasbeenopenedforfullmultimodal
transportationuse,exceptforlimitedcontractworkitems
thatdonotmateriallyimpairorhindertheintendedpublic
useofthetransportationfacility.Allanticipatedlanetakings
havebeencompleted. Thisincludescompletionof
superstructurework,bridgebarrier,permanentguardrail,
removalof
temporary
concrete
barriers, final
paving,
permanenttrafficmarkingsandsignage, permanentlighting.
Definition of Substantial Completion
Themajoritytheroadwayandutilityworkiscompleteonthe
municipalstreetsandtheremainingworknotdirectly
requiringlanestakenontheI91,I291,andtheassociated
lanesiscomplete.Completedworkincludesallstructural
steelrepairs,
painting
of
structural
steel,
bearing
replacements,installationofmunicipalstreetlighting,final
pavingandtrafficmarkingsatthemunicipalstreetlevel,
Restorationofalldisturbedareas.
7/25/2019 I-91 Update
6/23
6/27
Definition of Field Completion
AllphysicalcontractWorkiscompleteincludingpunchlist.
TheContractorhasfullydemobilizedfromfieldoperations.
Now: Stage 1B Construction
Inner lanes and median closed for construction of new median and high-speed lanes
Traffic moved to right/outer lanes
Reconstruction of I-291 westbound on-ramp to I-91 South
Ramp closures and detours (maps and directions handout available):
On-ramp from Birnie Ave/Rte.20 Connector to I-91 South
Exits 6 and 7 on I-91 South (detour to temporary ramp north of Exit 8)
On-ramps to I-91 North from State St and Union St (detour to East ColumbusAve)
Closure of north entrance to North Parking Garage, exit remains open
7/25/2019 I-91 Update
7/23
6/27
Now: Deck Demolition and Reconstruction Began in February
Northbound Stage 1Bdemolition complete
Southbound to begin nextmonth
Two shifts: (7:00 AM to 5:00 PM)and (3:30 PM to midnight)
Noise mitigation: noise controlcurtains, special back-up alarms
for equipment
Hotel area: no demo workFriday-Sunday, delayed start time(8:00 AM)
Traffic - Traffic Management (Stage 1B)
*OnsectionsnorthofI291,NBandSBareseparatedbygrade.
*
7/25/2019 I-91 Update
8/23
6/27
Stage 1B Progress Photos
Stage 1B Progress Photos
7/25/2019 I-91 Update
9/23
6/27
Stage 1B Progress Photos
7/25/2019 I-91 Update
10/23
6/27
7/25/2019 I-91 Update
11/23
7/25/2019 I-91 Update
12/23
6/27
Stage 1B Progress Photos
Stage 1B Progress Photos
7/25/2019 I-91 Update
13/23
6/27
Remaining Stage 1B Work Continuing demolition of all Stage 1B decks
Clean, prime & paint beam top flanges
Install stay-in-place (SIP) forms & rebar
Replace bridge bearings and pin & hanger connections
Pour new concrete decks & barriers (45 spans in eachdirection)
Install membrane waterproofing & pave deck
Install new signage
Install Stage 2 traffic pattern and prepare for Stage 2.
Traffic Management To maximize work space, safety and limit confusion, there will
be two major phases of work. Each phase will result in areduction of one lane from the existing configuration.
The project maintains access to/from I-291.
Designated on/off ramps remain closed until late fall of 2017 for
operational/safety reasons and to expedite construction. Access to downtown and local businesses will be maintained
using East and West Columbus and Hall of Fame Avenues.
Continuing analysis of traffic conditions and response to issuesas they arise.
7/25/2019 I-91 Update
14/23
6/27
Traffic Management (Stage 1B)
Traffic Mitigation Initial testing of detours took place to observe and make adjustments,
if needed.
Repairs to signals at State St/Columbus and Boland Way/Columbus.
Police details are provided at critical intersections during peak periods,if needed.
Comprehensive monitoring program of key corridors/intersections
traffic plan is updated when needed, based on impacts. Monitoring cameras are tied into the City of Springfield.
Real Time Traffic Management System (RTTM) continuously updatedmessage boards to deliver information in real-time.
Incident Response Operations (IRO)
7/25/2019 I-91 Update
15/23
6/27
Next: Stage 2
Traffic Management Approach (Stage 2)
7/25/2019 I-91 Update
16/23
6/27
Traffic Management Approach (Stage 2)
Improvementstomergeareas
Traffic Mitigation - RTTM
7/25/2019 I-91 Update
17/23
6/27
Traffic Mitigation - RTTM Message boards w/ live traffic updates
Traffic alerts to key personnel
Aid Emergency Responders for efficient response
Highway Advisory Radio 530 AM
Traffic Mitigation RTTM Screen
7/25/2019 I-91 Update
18/23
6/27
Traffic Mitigation RTTM Screen
Detour signs for Downtown and attractions
7/25/2019 I-91 Update
19/23
6/27
Speed Limits
Speed reduced from 50 to45 MPH approaching thework zone, with 40 mphlimit in the zone
Double fines in the workzone
State Police enforcementfor driver andconstruction team safety
Travel Without LimitsTaylor Rock
7/25/2019 I-91 Update
20/23
6/27
MassRIDES Programs
Online Ride Matching
Commuter Incentives
Emergency Ride Home NuRide.com/MassRIDES
Encouraging Mode Shift
Carpool, vanpool, transit, bike, walk, telework
Reduce traffic congestion
Reduce emissions Employers - outreach and worksite services
Commuters - ridematching, incentives, promotions andmarketing
MassRIDES = Statewide Travel Options Program
7/25/2019 I-91 Update
21/23
6/27
MassRIDES Outreach 325+ partner organizations, including:
MassMutual, Baystate Medical Center, American InternationalCollege, City of Springfield, Peter Pan Bus Company, PioneerValley Planning Commission, Pioneer Valley Transit Authority,Springfield Technical Community College, United Personnel-Springfield, Western New England University, Westfield StateUniversity
465,000+ commuters
Worksite focus commute travel
Taylor Rock
www.commute.com
7/25/2019 I-91 Update
22/23
6/27
Public Involvement Quarterly update meetings
Regularly updated project website:www.mass.gov/massdot/I91ViaductRehab
Project fact sheets & community briefings
Notices and e-blasts on traffic changes during construction andresponses to inquiries
Project updates on social media
English and translated materials and interpreters available uponrequest
How to Contact Us
Sign up on the project website for email information
and updates:
www.mass.gov/massdot/I91ViaductRehab
Send questions or concerns to:
7/25/2019 I-91 Update
23/23
6/27
THANK YOU!
Questions?