40
GOVERNMENT OF MONTENEGRO MINISTRY OF SUSTAINABLE DEVELOPMENT & TOURISM PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES BOOK 5 – WASTE WATER TREATMENT PLANT Volume 5.2 – Hydraulic Design MAY 2013.

Hydrotechnical Project Cetinje

Embed Size (px)

DESCRIPTION

Hidrotehnicki projekat

Citation preview

  • GOVERNMENT OF MONTENEGRO MINISTRY OF SUSTAINABLE DEVELOPMENT & TOURISM

    PPRREELLIIMMIINNAARRYY DDEESSIIGGNN FFOORR WWWWTTPP CCEETTIINNJJEE && SSEEWWEERRAAGGEE NNEETTWWOORRKK WWIITTHH FFAACCIILLIITTIIEESS

    BBOOOOKK 55 WWAASSTTEE WWAATTEERR TTRREEAATTMMEENNTT PPLLAANNTT

    VVoolluummee 55..22 HHyyddrraauulliicc DDeessiiggnn

    MAY 2013.

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012

    GENERAL PROJECT CONTENT

    No. NAME OF PROJECT PART

    GEOTECHNICAL STUDY

    HYDROLOGICAL STUDY ON RAINFALL AND FLOW

    BOOK 1 GENERAL BOOK

    BOOK 2 SEWAGE NETWORK

    BOOK 3 ATMOSPHERIC NETWORK

    BOOK 4 HYDRAULIC TUNNEL BELVEDER

    BOOK 5 WASTE WATER TREATMENT PLANT (WWTP)

    Volume 5.1 Process design

    Volume 5.2 Hydraulic design

    Volume 5.3 Architectural design

    Volume 5.4 Mechanical design

    Volume 5.5.1 Electrical design new TS

    Volume 5.5.2 Electrical design electrical equipment for the treatment process and SCADA

    Volume 5.5.3 Electrical design additional installations

    Volume 5.6 Previous expropriation study

    Note: All general documentation of project is located in Book 1 General book.

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012

    TERMS OF REFERENCE

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 1

    TABLE OF CONTENT

    1. LOCATION WWTP CETINJE ............................................................................................................. 2

    2. HYDROTECHNICAL SOLUTION ....................................................................................................... 4 2.1. WASTE WATER LINE TREATMENT ....................................................................................................................4 2.2. PROTECTION LINE OF OVERFLOW WATER........................................................................................................4

    3. HYDRAULIC CALCULATIONS.......................................................................................................... 5

    4. EXTERNAL PIPELINES ................................................................................................................... 13

    5. EXTERNAL AND INTERNAL WATER AND SEWAGE SYSTEM..................................................... 14 5.1. EXTERNAL WATER SYSTEM...........................................................................................................................14 5.2. EXTERNAL SEWAGE SYSTEM.........................................................................................................................14 5.3. INTERNAL WATER AND SEWAGE SYSTEM.......................................................................................................15

    6. RAIN WATER SYSTEM.................................................................................................................... 17 6.1. CHANNEL DESCRIPTION ................................................................................................................................17 6.2. HYDRAULIC CALCULATIONS..........................................................................................................................17

    7. SYSTEM OF FIRE PROTECTION .................................................................................................... 19 7.1. EXTERNAL AND INTERNAL HYDRANT NETWORK.............................................................................................19 7.2. HYDRAULIC CALCULATION............................................................................................................................20

    8. BILL OF QUANTITIES...................................................................................................................... 22 8.1. EXTERNAL PIPELINES ...................................................................................................................................22 8.2. EXTERNAL WATER, HYDRANTS AND SEWAGE NETWORK................................................................................23 8.3. INTERNAL WATER AND SEWAGE NETWORK ...................................................................................................28 8.4. RAIN WATER DRAINAGE SYSTEM...................................................................................................................35 8.5. SUMMARY RECAPITULATION .........................................................................................................................36

    9. LIST OF GRAPHICAL DOCUMENTATION...................................................................................... 37

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 2

    1. LOCATION WWTP CETINJE

    According to the adopted regulations plans, location of the future waste water treatment plant for the Royal Capital Cetinje is located on a site near the village Dobrsko selo. WWTP occupies a rectangular shape of the total area 7.944,0 m, and enclosed area 6.600 m (or 66 acres). This area will be located at ground level, leveled approximately 530,00 masl, while the current field is in a range of small slope between elevation 542,00 to 526,60 masl. To WWTP location can be reached by turning from the highway Podgorica-Cetinje, which leads next to Belveder restaurant and come down on the macadam road which will be reconstructed for the needs of the plant. This road would later serve as a service road to serving this plant.

    Location of the future WWTP extends on a total of 12 land parcels, some of them are fully engaged and some of them are partially engaged, which is shown in detail in previous expropriation study.

    PICTURE 1 LOCATION OF THE FUTURE WWTP

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 3

    PICTURE 2 ACCESS ROAD

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 4

    2. HYDROTECHNICAL SOLUTION

    Waste water gravity comes to the location of the WWTP by fecal sewer 400. Because of the difference in altitude from exit of collector of the future tunnel Belveder to location of the plant, we provide larger number of manholes with cascades so that water leads to manhole with flow meter at low pressure from a few meters, so that this flow meter can work with full profile. After leaving this manhole, the water enters in the separating chamber from where water distributed on two lines with 50% capacity (55 l/sec) to a screens and grit and grease chamber. Also, lateral is designed safety overflow, which also represents the by-pass through whole plant. The dimension of this pipeline is 500 and through him all water amount leads to collecting manhole. In this manhole water is combined with purified water and that mix leads to manhole with exit flow meter, and then gravity, with free fall, goes to trapezoidal channel for large atmospherically water which goes to river Rijeka Crnojevia.

    2.1. WASTE WATER LINE TREATMENT

    From grit and grease chamber, water through pressure pipeline goes to equalization tanks where it is the accumulation done for equal supply to the SBR units. This unit works discontinuous, i.e. it has a period of charging and discharging, that difference in continuous flow and operating mode of SBR accepts equalization tanks. In the first phase is provide to be completed one units SBR, while in the final phase is provide two more.

    Water supply to the SBR is done through the inlet pipeline 500, by which the water is distributed into one of six units of SBR (two units were merged into one building units). The entry in each unit is providing via penstock gate.

    After water treatment in SBR, the water is collected in the collecting pipeline and then to a collecting manhole, from where water gravity goes to pumping station within command building. These pumps provide enough pressure for water filtration through sand filters (chosen filter type is one who work normally under pressure), after filters the water leads into the manhole with reducing-valve pressure and goes to manhole with exit flow meter. Situation with routes of external pipe connection have been given in the hydro-technical part of the project and in the appendix is given hydraulic profile of water and sludge line through the plant.

    On the sludge line, from the SBR through pipeline 100 leads to thickener and filter presses.

    2.2. PROTECTION LINE OF OVERFLOW WATER

    Security overflow, by the separating chamber overflow which leads to by pass, is provided from the collecting basin.

    Especially are given discharge for drainage water from certain object through special manhole discharged into treated waste water.

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 5

    3. HYDRAULIC CALCULATIONS Water supply from the tunnel to the plant

    D= 250 mm 0.25 m Qmax,hour = 102.8 l/s 0.1028 m3/s

    i= 39 % 0.39 L= 250 m

    h= 0.16 m

    Kv= 525.16 masl ADOPTED

    Kv= 529.00 masl From entry flow meter to separating chamber

    L= 9 m Qmax,hour = 102.8 l/s 0.1028 m3/s

    D= 400 mm 0.4 m v= 0.81806 m/s k= 0.15 mm = 0.01600

    ul= 0.5 zat= 0.1 iz= 1

    h= 0.07027 m Kv= 528.93 masl

    From separating chamber through Hubers packet do equalization tanks Entrance in Hubers packet is 300, which means that we must have reduced from 400. For adopted packet, manufacturer was prescribed losses:

    h= 0.14 m Kv= 528.79 masl

    Outlet from Hubers packet is 350.

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 6

    Revision manhole Equalization tanks Qmax,hour/2 = 51.4 l/s 0.0514 m3/s

    D= 350 mm 0.35 m v= 0.53424 m/s

    ul= 0.5 zat= 0.1 iz= 1

    h= 0.02328 m Kv= 528.77 masl

    Equalization tank

    Qmax,day = 60.4 l/s 0.0604 m3/s A= 160 m2 v= 0.00038 m/s

    ul= 0.5 iz= 1

    h= 1.09E-08 m Kv= 528.77 masl

    In equalization tanks are given two pumps (1+1) which, by pipeline 300, pump water in manhole in front of equalization tanks, from there water goes by gravity to SBR pipeline 300. Water elevation on which the pumps push water in manhole in front of SBR is:

    Kv= 528.55 masl Losses in Equalization tanks are small, so they will be ignored.

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 7

    Equalization tank SBR FIRST

    Qmax,day = 60.4 l/s 0.0604 m3/s D= 350 mm 0.35 m L= 26 m v= 0.62779 m/s k= 0.15 mm = 0.01655

    ul= 0.5 zat= 0.1 iz= 1

    rac= 1.5 kol= 0.1

    h= 0.08696 m

    max Kv= 528.44 masl min Kv= 526.94 masl

    SECOND

    Qmax,day = 60.4 l/s 0.0604 m3/s D= 350 mm 0.35 m L= 15.5 m v= 0.62779 m/s k= 0.15 mm = 0.01655

    ul= 0.5 zat= 0.1 iz= 1

    rac= 1.5 kol= 0.1

    h= 0.07900 m

    max Kv= 528.45 masl min Kv= 526.95 masl

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 8

    THIRD

    Qmax,day = 60.4 l/s 0.0604 m3/s D= 350 mm 0.35 m L= 8.5 m v= 0.62779 m/s k= 0.15 mm = 0.01655

    ul= 0.5 zat= 0.1 iz= 1

    rac= 1.5 kol= 0.1

    h= 0.07436 m

    max Kv= 528.46 masl min Kv= 526.96 masl

    FOURTH

    Qmax,day = 60.4 l/s 0.0604 m3/s D= 350 mm 0.35 m L= 19 m v= 0.62779 m/s k= 0.15 mm = 0.01655

    ul= 0.5 zat= 0.1 iz= 1

    rac= 1.5 kol= 0.1

    h= 0.08634 m

    max Kv= 528.44 masl min Kv= 526.94 masl

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 9

    FIFTH

    Qmax,day = 60.4 l/s 0.0604 m3/s D= 350 mm 0.35 m L= 30.5 m v= 0.62779 m/s k= 0.15 mm = 0.01655

    ul= 0.5 zat= 0.1 iz= 1

    rac= 1.5 kol= 0.1

    h= 0.09927 m

    max Kv= 528.43 masl min Kv= 526.93 masl

    SIXTH

    Qmax,day = 60.4 l/s 0.0604 m3/s D= 350 mm 0.35 m L= 44 m v= 0.62779 m/s k= 0.15 mm = 0.01655

    ul= 0.5 zat= 0.1 iz= 1

    rac= 1.5 kol= 0.1

    h= 0.11410 m

    max Kv= 528.42 masl min Kv= 526.92 masl

    SBR

    Qmax,day = 60.4 l/s 0.0604 m3/s A= 900.00 m2 v= 6.71E-05 m/s

    ul= 0.5 iz= 1

    h= 6.89E-10 m

    Losses through SBR are small, so they will be ignored.

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 10

    As authoritative value will be adopted the biggest loss, and that is loss which is made to six SBR basin and is 1.61 m, so authoritative water elevation is Kv = 526.92 masl. SBR - Collecting basin FIRST AND SECOND

    V = 300 m3 t = 30 min 1800 s

    Q = 166.667 l/s 0.16667 m3/s D = 500 mm 0.5 m L = 93.5 m Manhole between v = 0.84883 m/s k = 0.15 mm L= 68 m = 0.01513 h= 0.57135 m

    ul = 0.5 Kv= 526.37 masl FIRST iz = 1 Kv= 526.38 masl SECOND

    h= 0.65478 m Kv= 526.29 masl FIRST Kv= 526.30 masl SECOND

    THIRD AND FOURTH

    V = 300 m3 t = 30 min 1800 s

    Q = 166.6667 l/s 0.166667 m3/s D= 500 mm 0.5 m L= 70.5 m v= 0.84883 m/s Manhole between k= 0.15 mm = 0.01513 L= 46 m

    ul= 0.5 h= 0.43673 m iz= 1 Kv= 526.52 masl THIRD

    Kv= 526.51 masl FOURTH h= 0.51904 m Kv= 526.44 masl THIRD Kv= 526.42 masl FOURTH

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 11

    FIFTH AND SIXTH

    V = 300 m3 t = 30 min 1800 s

    Q = 166.6667 l/s 0.166667 m3/s D= 500 mm 0.5 m L= 46.5 m v= 0.84883 m/s Manhole between k= 0.15 mm = 0.01513 L= 24 m

    ul= 0.5 h= 0.30210 m iz= 1 Kv= 526.63 masl FIFTH

    Kv= 526.61 masl SIXTH h= 0.38220 m Kv= 526.55 masl FIFTH Kv= 526.53 masl SIXTH

    As authoritative value will be adopted the biggest loss which gave us the lowest water elevation, so authoritative water elevation is: Kv = 526.29 masl. Collecting basin - Filters Pressure flow Line losses are ignored, so we have only local. Pressure at the outlet of the pump is 5 bars.

    D= 100 mm 0.1 m Q = 13 l/s 0.013 m3/s v= 1.65521 m/s

    ul= 0.5 zat= 0.1 iz= 1

    rac= 1.5 kol= 0.5 kl= 1.5

    h= 0.85180 m 0.09 bars

    Pressure at the inlet in filters is 4.91 bars. Losses through filters are 0.8 bars, so pressure at outlet of the filters is 4.11 bars.

    h= 8.00 m

    UV disinfection

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 12

    Adopted loss through UV disinfection is 20 cm, i.e. after UV disinfection pressure is 4.09 bars.

    h= 0.20 m 0.02 bars From UV to exit flow meter

    Qpump = 39 l/s 0.039 m3/s D= 250 mm 0.25 m L= 24 m v= 0.79450 m/s k= 0.15 mm = 0.01800

    ul= 0.5 zat= 0.1 iz= 1

    kol= 0.5

    h= 0.12315 m 0.012 bars From here the water goes to exit flow meter, which is under pressure. A detail description of the flow meter is located in the mechanical part of the project.

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 13

    4. EXTERNAL PIPELINES

    With external pipelines are covered pipes which connect object from input to output flow meter.

    Provided pipes are from HDPE or PE, which is mostly, used because of the technical benefits and economic costs.

    In the line of water treatment are connected the following facilities:

    Section from - to

    Diameter (mm)

    Length (m) Note

    Flow meter manhole separating chamber 400 18.0 Equalization tanks manhole in front of SBR 300 8.6 pressure pipeline Manhole in front of SBR - SBR 350 55.3 SBR collecting basin 500 92.8 Collecting basin - filters 100 3.3 pressure pipeline

    Filters UV disinfection 100 7.0 pressure pipeline

    UV disinfection by pass 250 4.2 By pass (from exit flow meter) 100 6.0

    In the line of sludge treatment are connected the following facilities:

    Section from - to

    Diameter (mm)

    Length (m) Note

    SBR thickener 100 98.2 pressure pipeline

    Thickener command building 100 9.9 pressure pipeline

    In addition to these pipelines are especially given independent systems, external water network with hydrants and external sewage network, and for drainage atmospheric water is provided open channel system. These entire projects are given independently in this book.

    Bill of Quantities of outside pipeline works is given in section 8 Bill of Quantities of this book.

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 14

    5. EXTERNAL AND INTERNAL WATER AND SEWAGE SYSTEM

    5.1. EXTERNAL WATER SYSTEM

    In the external water supply network are included the following facilities: guard house, command building, grit and grease chamber.

    External water supply network is connected to a city water supply network of city Cetinje with sump 150 at junction in which is located internal flow meter. Available pressure at the connection is here 4.0 bars.

    Water needs:

    In this plant from external water supply network is provided following purposes: Fire protection needs Sanitation needs Washing facilities (basin)

    5.2. EXTERNAL SEWAGE SYSTEM

    External sewage network is used for evacuation of waste water from sanitary facilities located in buildings WWTP Cetinje. There is no city sewage system in the location of the plant, because of that provided the sewage and drainage collected from beginning of process of purification.

    To the external sewage drains system is connected following customers: Sanitary facilities from guard house (object 3) Sanitary facilities from command building (object 12)

    Considering the small amount of wastewater, the network is dimensioned according to technical regulations.

    All pipelines are gravity.

    All pipes are made of PE or PVC of various diameters. These materials are selected because of the sewerage pipes have the following advantages over other types of materials:

    They are easy to install; They have more bandwidth for the same diameter pipeline; They are easy to transport and They are easy to make new connections.

    The network is dimensioned so that the adopted slopes, fulfillments of cross section are not exceeding 50%.

    All sewage water collects and drains to a separating chamber (object 5) and leads to a process of purification.

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 15

    In the following table is given diameter pipes and slopes by sections:

    Section Kuzv L I Kniz From - to (masl) (m) (%) (masl) Junction

    a1 RS1 527.40 1.30 2 527.37 RS1 RS1 RS2 527.37 19.40 2 526.99 RS2 RS2 RS3 526.99 36.30 2 526.26 RS3 a2 RS3 527.30 0.80 2 527.28 RS3

    RS3 RS4 526.26 2.80 1 526.23 RS4 a3 RS4 527.30 0.80 2 527.28 RS4

    RS4 RS5 526.23 39.80 1 525.83 RS5

    5.3. INTERNAL WATER AND SEWAGE SYSTEM

    Guard house is located on leveled plateau at a level +528.80 masl, near the entrance gate, from which it is direct, visual and physical access control or exit from the area of plants on the access road.

    The facility is on ground level, square in shape, dimensions 4.20 x 4.20 m and consists of office (for one or two persons), entrance hall and bathroom. Ground floor elevation of the building is raised to 0.15m in relation to the elevation of the plateau at the site of construction.

    Water supply system is designed to be made of galvanized water pipes with diameter from 15 to 25 mm. Water supply is connected to the existing external system within the waste water treatment plant with pipes 25 and connects to an external distribution network 100.

    Sewage will be constructed of PVC sewer pipe with diameters from 75 to 160 mm. Provided is one sewer vertical in the object. Waste water is drained with pipe 160 to the manhole RS-1.

    Command building is multi-level building, (Po + P +1) rectangular shape, overall dimensions 17:44 x 11.54 m, 9.25 m height. Object is accessed from the plateau on the north and northwest sides. Ground floor elevation of the building is raised by 0.15m relative to level of plateau at the site of construction. Under ground elevation is on the absolute elevation of 528.95 mals.

    In the basement is provided: Space to house compressors, filters and UV disinfection and stairs.

    The ground floor contains the following facilities: Hallway and stairs to first floor and basement; Office; Two toilets with sink; Warehouse; Workshop; Room for sludge treatment; Mounting hole for the basement.

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 16

    All rooms are accessible through the central hall, and for workshop, room for sludge treatment and mounting hole are provided and direct access from the outside.

    First floor contains the following facilities: Control room; Manager office; Two working office; Two toilets with sink Living room with kitchen for workers; Physical and chemistry laboratory; Microbiological laboratory; Hallway with stairs.

    Water supply network is designed to be made of galvanized water pipes with diameter from 15 to 50 mm. Water network is connected to the existing system within external water in the plant pipes 50, which is connected to the external distribution system and two 100 and 25 pipe from which the divorce connected to the pipe 50. Sewage will be constructed of PVC sewer pipe with diameters from 75 to 160 mm. Two sewage verticals are planned in the object. Part of the wastewater is discharged with pipe 160 to the manhole RS-3, and other waste water through a pipe 160 to the manhole RS-4.

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 17

    6. RAIN WATER SYSTEM

    For drainage of storm water from the plant, is provided the system of open channel, which are placed parallel with internal road. It is planed that channel leads rain water from plant to river Rijeka Crnojevia. Authoritative rain for territory of the Municipality of Cetinje which are adopted during calculation are twenty minutes rains, t = 20 min, with return period of five years, T = 5 y, and amount i = 22.4 l/m2/20 min, or i = 0.01867 l/m2/s.

    During the calculation are adopted basic parameters, such as runoff coefficient, which is for green areas = 0.35, and for roads and roofs of building is = 1.

    6.1. CHANNEL DESCRIPTION

    These channels installed at the plant for waste water treatment, used for collecting water from the roofs of buildings and land under roads and green areas.

    The channels are placed at the edge of the plant and between object following the internal road, and they serve to protect WWTP from atmospheric water and evacuation of water from impermeable surfaces.

    Channels are designed as a concrete channels, rectangular cross section, width and depth of 30cm or 40cm, depending of the amount of water which they should receive.

    In section 1 4, the channel passes through internal road, so it is planed that on this part of road channel should be covered by grid resistant on heavy traffic.

    6.2. HYDRAULIC CALCULATIONS

    During the calculation are adopted the following values: Mannings coefficient n = 0.013 m-1/3/s Runoff coefficient from green areas = 0.35 Runoff coefficient from impermeable surfaces = 1 Intensity of rainfall i = 0.01867 l/m2/s

    Detailed hydraulic calculation is shown below.

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 18

    CHANNEL 1

    Section Ground

    elevation upstream

    Bottom elevation upstream

    Ground elevation

    downstream

    Bottom elevation

    downstream

    Length L

    Slope I

    Area (road + object)

    Runoff coefficient

    Green area

    Runoff coefficient

    Intensity Flow Q

    Total flow Q

    Water depth in channel

    h

    Velocity v

    Channel width

    masl masl masl masl m % m2 - m2 - l/m2/s l/s l/s m m/s m 1 - 2 529.00 528.70 528.70 528.40 56.30 0.53 373.56 1 638.30 0.35 0.01867 11.14 11.14 0.06 0.66 0.30 2 - 3 528.70 528.40 528.30 528.00 89.30 0.45 267.90 1 774.00 0.35 0.01867 10.06 21.20 0.09 0.77 0.30 CHANNEL 2

    Section Ground

    elevation upstream

    Bottom elevation upstream

    Ground elevation

    downstream

    Bottom elevation

    downstream

    Length L

    Slope I

    Area (road + object)

    Runoff coefficient

    Green area

    Runoff coefficient

    Intensity Flow Q

    Total flow Q

    Water depth in channel

    h

    Velocity v

    Channel width

    masl masl masl masl m % m2 - m2 - l/m2/s l/s l/s m m/s m 1 - 4 529.00 528.70 528.60 528.30 89.30 0.45 785.10 1 918.05 0.35 0.01867 20.65 20.65 0.09 0.76 0.30 4 - 3 528.60 528.30 528.30 528.00 56.30 0.53 267.24 1 806.62 0.35 0.01867 10.26 30.91 0.11 0.90 0.30 CHANNEL 3

    Section Ground

    elevation upstream

    Bottom elevation upstream

    Ground elevation

    downstream

    Bottom elevation

    downstream

    Length L

    Slope I

    Area (road + object)

    Runoff coefficient

    Green area

    Runoff coefficient

    Intensity Flow Q

    Total flow Q

    Water depth in channel

    h

    Velocity v

    Channel width

    masl masl masl masl m % m2 - m2 - l/m2/s l/s l/s m m/s m 3 - 5 528.30 527.90 528.20 527.80 14.30 0.70 143.00 0.35 0.01867 0.93 53.05 0.12 1.13 0.40

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 19

    7. SYSTEM OF FIRE PROTECTION

    7.1. EXTERNAL AND INTERNAL HYDRANT NETWORK

    For fire fighting of any fire on the building is provided the external and internal hydrant network. The external network is placed around the plant in a ring, pipe diameter 100, for operating pressures up to 10 bars, while for the internal of command building is designed hydrant, pipe diameter 50.

    Fire fight hydrant network is connected to a city water supply network of city Cetinje, where is provided amount of 12 l/sec and minimum pressure of 4 bar.

    The total amount of water needed for firefighting in the building, depending on the degree of resistance to fire and building categories according to the technological process of fire risk are given in the table.

    TABLE 7.1

    The degree of resistance to fire in building

    Category technological process according to fire risk

    The amount of water in liters per second needed for a fire, depending on the volume in cubic meters building which will be protected

    up to

    3000

    3001 to

    5000

    5001 to

    20000

    20001 to

    50000

    50001 to

    200000

    200001 to

    400000

    over

    400000

    V and IV K4, K5 10 10 10 10 15 20 25

    V and IV K1, K2, K3 10 10 15 20 30 35 -

    III K4, K5 10 10 15 25 - - -

    I and II K4 and K5 10 15 20 30 - - -

    I and II K3 15 20 25 - - - -

    Considering that the category of technological process in the facility K5, and the volume of the largest facility of up to 2.000 m3, and the fact that the degree of resistance to the fire building II, the amount of water needed for effective firefighting is 10 l/sec.

    In our case, for turning off the fire, must be provide a minimum amount of water of 10 l/sec, which is required for simultaneous operation of external (5 l/sec) and internal (2 x 2,5 = 5 l/sec) hydrants network, or with two external hydrants.

    7.1.1. EXTERNAL HYDRANT NETWORKS

    External hydrant network is providing in the form of a ring system of pipelines.

    The largest distance between the external hydrants is 80 m, with a fact that the fire in a building can be put out with the outer two hydrants simultaneously.

    The distance from hydrants to building wall is at minimum 5 m.

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 20

    Around the building are placed underground hydrants.

    Hydrants diameter is 80.

    Pipe of distribution pipelines in network of pipes and hydrants for each hydrant have a diameter not less than 100.

    Minimum work pressure at external hydrant should be 2.5 bars.

    7.1.2. INTERNAL HYDRANT NETWORKS

    For fire fighting in enclosed building, areas over 150 m2, is planed internal hydrant network, which are powered by external hydrant network.

    Pressure at the most unfavorable hydrant is no less than 2.5 bars.

    For inside hydrant network is provide minimum inner pipe diameter 52mm, and hydrant connector smallest inner diameter 52mm, type C, according to JUS M.B6. 673.

    Distance between hydrants is such that the entire aria which will be protected by covering with jet water, with certain allowances for the fact that length of hose is 15m, and length of compact jet is 5m.

    In fire cabinets set is putted a fire hose with normal diameter of 52mm, with a nozzle diameter of 12mm.

    Internal hydrant network in the building is set up so that it is possible to protect all areas of fire.

    7.2. HYDRAULIC CALCULATION

    Hydraulic calculation of hydrants network are done for the case when two farthest external hydrants works, and in this case there are hydrants PH2 and PH3. Pressure which will be provided from city network of Cetinje on inlet 150 in junction where located flow meter at the entrance on the plant is is 4.0 bars. Considering that the minimum pressure at external hydrant is 2.5 bars, that losses in network should not exceed 1.5 bars.

    From the hydraulic calculation (given in table 7.2) that show that the losses in the ring hydrant networks are almost negligible, so it can be concluded from the fact that the hydrants will work smoothly.

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 21

    PICTURE 7.1 DESIGN OF HYDRANTS NETWORK AT WWTP CETINJE

    TABLE 7.2 HYDRAULIC CALCULATIONS OF LOSSES IN HYDRANTS NETWORK

    Section from - to

    Length (m)

    Diameter (mm)

    Flow (l/s)

    Velocity (m/s)

    Loss (m/m)

    Pressure loss (bar)

    Tv1 Tv3 29.09 100 3.97 0.51 0.003 0.008 Tv3 t1 3.05 100 3.97 0.51 0.003 0.001 t1 PH2 0.65 80 5 0.99 0.012 0.001 Tv4 t1 3.89 100 1.03 0.13 0 0 Tv4 Tv5 11.01 100 1.92 0.25 0.001 0.001 Tv5 t2 5.95 100 1.92 0.25 0.001 0 t2 PH3 0.65 80 5 0.99 0.012 0.001 Tv6 t2 23.09 100 3.08 0.39 0.002 0.004 Tv7 Tv6 11.01 100 3.08 0.39 0.002 0.002 Tv7 Tv4 29.09 100 2.95 0.38 0.002 0.004 Tv1 Tv7 6.94 100 6.03 0.77 0.006 0.004 M Tv1 4.24 150 10 0.57 0.002 0.001

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 22

    8. BILL OF QUANTITIES

    8.1. EXTERNAL PIPELINES

    No. DESCRIPTION OF Unit Quantity Unit price PRICE WORKS Euro Euro

    A. External pipe connections (I PHASE)

    I Earth works

    1 Excavation of trenches for laying pipes and manholes in the soil category III. Calculation per m3 m3 583.0 5.0 2,915.0

    2 Procurement, delivery and filling of pipes beneath the sand, d = 10 cm and filling 30cm above the pipe. Calculation per m3. m3 175.0 11.0 1,925.0

    3 Backfilling of the trench dug into the layers of 20cm, with compacting. Backfill to be made to the technical regulations for this type of work.

    Calculation per m3. m3 373.0 3.0 1,119.04

    Planning surplus excavated material on the site. Calculation per m3. m3 210.0 2.0 420.0

    I Earth work

    Total

    6,379.0

    IV Installation works

    1

    Procurement, transport and installation HDPE100 pipe with fittings and fittings, complete. Calculation per m1

    315/23.2 3.0 68.0 204.0 355/26.1 24.0 88.0 2,112.0 400/29.4 28.0 115.0 3,220.0 500/36.8

    m1

    157.0 135.0 21,195.0

    IV Installation works Total 26,731.0

    1 HIDRAULIC TESTING Hydraulic testing of the placed supply on the test pressure in accordance with instructions of the relevant community organizations and the technical requirements of this project, with the obligatory presence of the supervisor. Calculation per meter tested supply. m 212 3.0 636.0

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 23

    2 DESINFECTION Disinfection and cleaning of pipelines as directed by the relevant community organizations and the competent supervisory authority with the presence of mandatory supervisory authority. Calculation of the m1 cleaned pipeline m1 212 3.0 636.0

    V Other works Total 1,272.0

    RECAPITULATION FOR COSTRUCTION WORKS for external water network

    I Earth works 6,379.0 IV Mounting works 26,731.0 V Other works 1,272.0 TOTAL 34,382.0 Euro

    8.2. EXTERNAL WATER, HYDRANTS AND SEWAGE NETWORK

    No. DESCRIPTION OF Unit. Quantity Unit price PRICE

    WORKS Euro Euro

    A. External water and hydrant network

    I Earth works

    1 Excavation of trenches for laying pipes and manholes in the soil category III Calculation per m3 m3 395.4 5.0 1,977.0

    2 Procurement, delivery and filling of pipes beneath the sand, d = 10 cm and filling 30cm above the pipe. Calculation per m3. m3 148.7 11.0 1,635.7

    3 Backfilling of the trench dug into the layers of 20cm, with compacting. Backfill to be made to the technical regulations for this type of work.

    Calculation per m3. m3 243.3 3.0 729.9Procurement, transport and placing pebbles in a layer of 20cm below the buffer layer. Calculation per m3.

    4

    m3 2.60 11.0 28.65 Planning surplus excavated material on the

    site. Calculation per m3. m3 153.5 2.0 307.0 I Earth works Total 4,678.2

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 24

    II Concrete and reinforced concrete for water meter manhole

    Unreinforced concrete

    1 Concreting of the buffer layer reinforced concrete manhole below MB15 thickness d = 10 cm.1.9X1.9X2 +2 X3 = 13.2 Calculation per m2. m2 9.6 8.0 76.8

    4 Procurement, transport and installation r the concrete bearing under the water meter. Calculation per m3. m3 0.16 140.0 22.4

    Reinforced concrete

    1 Construction of reinforced concrete manhole of the reinforced concrete MB30, VDP8 in all the drawings and regulations for this kind of works together with the formwork. ((1.9X1.9X0.25)+(1.9X1.9X0.15)+(2.2X1.5X0.2X4)) x 2 + (2x3x0.25+2x3x0.1+2.21x0.25x9.5) = 15.50

    Calculation per m3. m3 11.5 180.0 2,070.0

    II Concrete and reinforced concrete for water meter manhole Total 2,169.2

    III Reinforcement work

    1

    Procurement, transport, unloading, straightening, cleaning, cutting, bending and placing of concrete iron to static calculation. Calculation per kg.

    RA 400/500 - 2 kg 1,035.0 1.2 1,242.0 III Reinforcement work

    Total 1,242.0

    IV Installation works

    1 Procurement, transport and installation HDPE100 pipe with fittings and fittings, complete. Calculation per m1

    PE100110 415.0 24.0 9,960.0 PE10090 8.0 22.0 176.0 PE10063 28.0 20.0 560.0 PE10025

    m1

    3.0 10.0 30.02 Procurement, transport and installation of built

    furniture, kit. The calculation per unit. 110/25 1 120.0 120.0 110/80

    unit 4 175.0 700.0

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 25

    3 Procurement, transport and installation of water

    fittings, together with connecting and sealing material, a set of certificate, operating instructions and maintenance. Calculation per unit

    Combined water meter 100 mm, 1 230.0 230.0 The cap NP 10 bars 100mm 3 140.0 420.0 50mm

    unit

    1 70.0 70.0

    4

    Procurement and installation of underground hydrant DN80/PN10 unit 4 250.0 1,000.0

    5 Procurement and installation of cast iron cover for heavy traffic. Calculation per unit

    625mm unit 1 180.0 180.0

    6 Procurement and installation of cast iron cover for heavy traffic. Calculation per unit

    600X600mm unit 1 180.0 180.0

    Procurement and installation of cast iron cover for heavy traffic. Calculation per unit 700X700 mm unit 1 200.0 200.0

    6 E-PE-HD compound DN80/PN10 unit 16 30.0 480.0

    7 The arched piece with the foot, N90 , cast iron DN80/PN10 unit 4 30.0 120.0

    8

    Procurement and installation of hydrant cabinets for Internal hydrants with water valve with connection 2 ", l = 15m hose and full brass door unit 1 190.0 190.0

    9

    Procurement and installation of oval DN80/PN10 valve with built-capped and street furniture unit 4 180.0 720.0

    10 Procurement and installation of cast iron creepers. Calculation per unit unit 14 5.0 70.0

    IV Installation works Total 15,406.0

    V Other works

    1 HIDRAULIC TESTING Hydraulic testing of the placed supply on the test pressure in accordance with instructions of the relevant community organizations and the technical requirements of this project, with the obligatory presence of the supervisor. Calculation per meter tested supply. m1 454 3.0 1,362.0

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 26

    RECAPITULATION FOR CONSTRUCTION WORKS for external water network

    I Earth works 4,678.2 II Concrete and reinforced concrete for water meter manhole 2,169.2 III Reinforcement works 1,242.0 IV Installation works 15,406.0 V Other works 2,724.0 TOTAL 26,219.4 Euro

    No. DESCRIPTION OF Unit. Quantity Unit price PRICE WORKS Euro Euro

    B External sewage

    I Earth works

    1 Excavation of trenches for laying pipes and manholes in the soil category III, bottom plan, groundwater pumping, and all other costs charged to this position

    Calculation per m3. m3 172.0 5.0 860.02 Procurement, delivery and filling of pipes

    beneath the sand, d = 10 cm and filling 30cm above the pipe. Calculation per m3.

    m3 55.1 11.0 606.13

    Backfilling of the trench dug into the layers of 20cm, with compacting. Backfill to be made to the technical regulations for this type of work (172-60)=112

    Calculation per m3. m3 112.0 3.0 336.04 Planning surplus excavated material on the site

    (172-112) = 60. Calculation per m3. m3 60.0 2.0 120.0

    I Earth works Total 1,922.1

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 27

    II Concrete and reinforced concrete works

    Unreinforced concrete 1 Concreting of the buffer layer reinforced concrete

    below manholes thickness MB15 d=10 cm. (0.65xx5)=6.63

    Calculation per m2. m2 6.63 8.0 53.04 Reinforced concrete 2 Construction of reinforced concrete standard

    manholes of the reinforced concrete MB30 Calculation per m. m 14.20 140.0 1,988.0

    II Concrete and reinforced concrete works Total 2,041.04

    III Installation works

    1 Procurement, transport and installation of PVC sewer pipe with fittings and fittings, set. Calculation per m1.

    160 m 65.0 14.0 910.0 200 m 41.0 18.0 738.0

    III Installation works Total 1,648.0

    IV Other works

    1 Hydraulic testing of laid sewerage system at test pressure and water resistance. Calculation per meter tested network.

    m 106 3.0 318.02 Procurement and installation of cast iron

    creepers. Calculation per unit. unit 48 5.0 240.03 Procurement and installation of cast iron covers

    for heavy traffic 625. Calculation per unit unit 5 180.0 900.0

    IV Other works Total 1,458.0

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 28

    RECAPITULATION FOR CONSTRUCTION WORKS

    for external sewage network

    I Earth works 1,922.10 II Concrete and reinforced concrete works 2,041.04 III Installation works 1,648.00 IV Other works 1,458.00 TOTAL 7,069.14 Euro

    SUMMARY RECAPITULATION FOR External water and sewage network

    I Water supply and hydrant network 26,219.4 II External sewage 7,069.1 TOTAL 33,288.5 Euro

    8.3. INTERNAL WATER AND SEWAGE NETWORK

    POS. DESCRIPTION OF WORKS UNIT. QUANTITY U PRICE() PRICE()

    0BJECT: Guard house

    1. Sewage

    1 Plastic PVC pipes

    Procurement, transport and setting PVC sewage pipes with necessary parts, connecting and midfield material to create sewage. Unit price includes the examination to be carried waterproofing in the presence of supervisory. Unit price entered all the necessary work and connecting and bonding material.

    Calculation per m'.

    160 mm mI 1.00 11.00 11.00

    110 mm mI 10.00 10.00 100.00

    75 mm mI 6.00 5.00 30.00

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 29

    2 Sand

    Procurement, transport and installation of sand below and above the water and sewage pipes in the layer below 10 cm and 10 cm above the pipe, the lower layer in the direction of the projected decline.

    Calculation per m3 Sewage m3 5.00 13.00 65.00

    3 Ventilation

    Procurement, transport and installation of air hole. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per unit. unit 1 15.00 15.00

    4 Testing sewage

    Testing and flushing mounted sewerage system on the waterproofing.

    The calculation of the m. mI 17.00 2.00 34.00 Total sewage: 255.00

    2. Water supply 1 Water pipeline

    Procurement, transport and installation of galvanized steel water pipes with fittings, for working pressures to 10 bars for water distribution in the house. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per m 25 mm mI 3.00 6.00 18.00 15 mm mI 2.00 4.80 9.602 Pass valves

    Procurement, transport and incorporation of porous nickel valve cap and rosette. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per unit. 25 mm unit 1 10.00 10.003 Angle Valves

    Procurement, transport and angular neckline valve diameter 15 mm. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per unit. unit 1 8.00 8.00

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 30

    4 Testing of the pressure

    Testing mounted on the water distribution test pressure of 12 bars, all in accordance with technical regulations and standards for this type of work. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per m'. mI 5.00 2.00 10.005 Disinfection

    Disinfection of water distribution in all the technical regulations and standards for this type of work. Disinfection must be performed by an authorized institution. Upon completion of disinfection rinse water supply.

    Calculation per m'. mI 5.00 4.00 20.00 Total water supply: 75.60

    3. Sanitation

    1 Toilet

    Procurement, transport and installation of toilet type "Simplon", complete with low-enameled water tank assembly with plastic pipes merge, toilet seats made of hard PVC, rubber sleeves, rubber gasket and screws. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per unit. unit 1 172.00 172.002 Basins

    Procurement, transport and installation of sinks white faience, domestic production, and class, complete with pole, standing mixer battery for hot and cold water, a siphon with a nickel-plated plugs, chains and rosettes and the "Diana" screws. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per unit. -large basin unit 1 115.00 115.003 Container for liquid soap

    Procurement, transport and montage containers for liquid soap. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per unit. unit 1 12.00 12.004 Container for liquid towel

    Procurement, transport and montage containers for liquid towel. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per unit. unit 1 8.00 8.00

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 31

    5 Toilet towels

    Procurement, transport and installation of bathroom towel holders, position the unit cost of entering all the necessary work and connecting and bonding material.

    Calculation per unit unit 1 6.00 6.006 Shelf and Mirror

    Procurement, transport and montage shelf and mirror above the sink. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per unit unit 1 25.00 25.007 Floor drains

    Procurement, transport and installation of floor drains LG 70 mm, with chrome Rostom (20/20 cm), for installation in bathrooms. The unit cost position entering all the necessary work and connecting and bonding material.

    The calculation of per unit. - Horizontal drain 70 mm unit 1 28.00 28.008 Electric Water Heater

    Procurement, transport and installation of electric water heaters.

    Calculation per unit 8 lit electric water heater unit 1 100.00 100.00 Total sanitation: 466.00

    RECAPITULATION

    1. Sewage 255.00

    2. Water supply 75.60

    3. Sanitation 466.00

    TOTAL: 796.60

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 32

    POS. DESCRIPTION OF WORKS UNIT QUANTITY U.PRICE

    () PRICE ()

    0BJECT Command building

    1. Sewage

    1 Plastic PVC pipes

    Procurement, transport and setting PVC sewage pipes with necessary parts, connecting and midfield material to create sewage. Unit price includes the examination to be carried waterproofing in the presence of supervisory unit price entered all the necessary work and connecting and bonding material.

    Calculation per m'.

    160 mm mI 2.00 11.00 22.00

    110 mm mI 25.00 10.00 250.00

    75 mm mI 21.50 5.00 107.50

    2 Ventilation

    Procurement, transport and installation of air hole. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per unit. kom 2 15.00 30.00

    3 Testing sewage

    Testing and flushing mounted sewerage system on the waterproofing.

    The calculation of the m. mI 48.50 2.00 97.00 Total sewage: 506.50

    2. Water supply

    1 Water pipeline

    Procurement, transport and installation of galvanized steel water pipes with fittings, for working pressures to 10 bar for water distribution in the house. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per m 50 mm mI 9.50 10.00 95.00 25 mm mI 42.00 6.00 252.00 20 mm mI 7.00 5.00 35.00 15 mm mI 13.50 4.80 64.80

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 33

    2 Pass valves

    Procurement, transport and incorporation of porous nickel valve cap and rosette. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per unit. 50 mm unit 2 25.00 50.00 25 mm unit 6 10.00 60.00

    3 Angle Valves

    Procurement, transport and angular neckline valve diameter 15 mm. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per unit. unit 8 8.00 64.00

    4 Hose connection

    Procurement, transport and installation connection hose 50. The unit price position entering all needed work, and connecting and bonding material.

    Calculation per unit. unit 1 20.00 20.00

    5 Testing of the pressure

    Testing mounted on the water distribution test pressure of 12 bars, all in accordance with technical regulations and standards for this type of work. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per m'. mI 72.00 2.00 144.00

    6 Disinfection

    Disinfection of water distribution in all the technical regulations and standards for this type of work. Disinfection must be performed by an authorized institution. Upon completion of disinfection rinse water supply.

    Calculation per m'. mI 72.00 4.00 288.00

    Total water supply: 1,072.803. Sanitation

    1 Toilet

    Procurement, transport and installation of toilet type "Simplon", complete with low-enameled water tank assembly with plastic pipes merge, toilet seats made of hard PVC, rubber sleeves, rubber gasket and screws. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per unit. unit 4 172.00 688.00

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 34

    2 Basins

    Procurement, transport and installation of sinks white faience, domestic production, and class, complete with pole, standing mixer battery for hot and cold water, a siphon with a nickel-plated plugs, chains and rosettes and the "Diana" screws. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per unit. -large basin unit 4 115.00 460.003 Container for liquid soap

    Procurement, transport and montage containers for liquid soap. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per unit. unit 4 12.00 48.004 Container for liquid towel

    Procurement, transport and montage containers for liquid towel. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per unit. unit 4 8.00 32.005 Toilet towels

    Procurement, transport and installation of bathroom towel holders, position the unit cost of entering all the necessary work and connecting and bonding material.

    Calculation per unit unit 4 6.00 24.006 Shelf and Mirror

    Procurement, transport and montage shelf and mirror above the sink. The unit cost position entering all the necessary work and connecting and bonding material.

    Calculation per unit unit 4 25.00 100.007 Floor drains

    Procurement, transport and installation of floor drains LG 70 mm, with chrome Rostom (20/20 cm), for installation in bathrooms. The unit cost position entering all the necessary work and connecting and bonding material.

    The calculation of per unit. unit 4 28.00 112.008 Electric Water Heater

    Procurement, transport and installation of electric water heaters.

    Calculation per unit 80 lit electric water heater unit 1 172.00 172.00 8 lit electric water heater unit 4 100.00 400.00 Total sanitation: 2,036.00

    RECAPITULATION

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 35

    1. Sewage 506.50

    2. Water supply 1,072.80

    3. Sanitation 2,036.00

    TOTAL 3,615.30

    8.4. RAIN WATER DRAINAGE SYSTEM

    No. DESCRIPTION OF Unit. Quantity U.price PRICE

    WORKS Euro Euro

    Drainage channels for rain water

    I Preparatory works

    Route marking channels. 1 Calculation per m m 305.5 1.0 305.5

    I Preparatory works Total 305.5

    II Earth works

    Excavation for concrete channel in the soil category III, and the planning. Channel bottom. 1

    Calculation per m3 m3 101.0 8.0 807.6Taking the excess land at a location designated by the supervisory authority 3 Calculation per m3 m3 101.0 2.5 252.4

    II Earth works Total 1,060.0

    III Concrete works

    1 Concrete of canal with MB30 (or prefabricated elements). Calculation per m3 m3 55.6 140.0 7,788.7

    III Concrete works Total 7,788.7

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 36

    IV Other works

    1

    Supply and installation of cast iron manhole grate width 38cm, together with the frame for the traffic load of 400KN Calculation per m' m 15.1 26.0 392.6

    IV Other works Total 392.6

    SUMARY OF COSTRUCTION WORKS for rain water drainage system

    I Preparatory works 305.5 II Earth works 1,060.0 III Concrete works 7,788.7 IV Other works 392.6 TOTAL 9,546.8 Euro

    8.5. SUMMARY RECAPITULATION

    Position Price (EUR) 1. External pipelines 34,382.0

    2. External water, hydrant and sewage network 33,288.5 3. Internal water and sewage network 4,411.9 4. Rain water drainage system 9,546.8

    TOTAL 81,629.3

  • PRELIMINARY DESIGN FOR WWTP CETINJE & SEWERAGE NETWORK WITH FACILITIES MUNICIPALITY OF CETINJE / MONTENEGRO

    BOOK 5 WASTE WATER TREATMENT PLANT VOLUME 5.2 HYDRAULIC DESIGN

    IOV10-17 IK CONSULTING ENGINEERS APRIL 2012 PAGE 37

    9. LIST OF GRAPHICAL DOCUMENTATION

    No. drawing

    Name of drawings

    001 GENERAL SITUATION (and external pipelines)

    002 Hydraulic profile

    003 GENERAL SITUATION, Water, sewage and hydrant network

    004 Longitudinal profile of sewage

    005 GUARD HOUSE, Ground floor plan water supply and sewage, Profiles sewage, Axonometric chart water supply and air holes

    006 COMMAND BUILDING, Basement plan water supply

    007 COMMAND BUILDING, Ground plan water supply

    008 COMMAND BUILDING, First floor plan water supply

    009 COMMAND BUILDING, Axonometric chart water supply

    010 COMMAND BUILDING, Ground plan sewage

    011 COMMAND BUILDING, First floor plan sewage

    012 COMMAND BUILDING, Roof plan air holes, Profiles sewage

    013 GENERAL SITUATION, Rain water drainage system