24
Future Development of HKIA Planning of the Three-Runway System Presentation to Hong Kong Air Cargo Forum 19 June 2013 1

Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

Future Development of HKIA

Planning of the Three-Runway System

Presentation to Hong Kong Air Cargo Forum

19 June 2013

1

Page 2: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

Three-runway System: A Three-phase Process

Land formation Detailed designs Construction of related facilities

Implementation

About 8 years*

Environmental permit Foreshore and

seabed gazettal Financial

arrangement

Approval

About 1 year*

Environmental Impact Assessment studies Associated

design details Funding options

Planning

About 2 years*

2

*Indicative timeline that is subject to changes

Page 3: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

EIA & Planning Study Team

EIA Lead Consultant Mott MacDonald

AAHK

Air Quality Consultant Arup

Aircraft Noise Consultant

URS

Chinese White Dolphin Experts Bernd Wursig &

Tom Jefferson

EIA Review Consultant ERM

3rd Runway Reclamation Scheme

Design Consultant Atkins

Terminal 2 Expansion

Scheme Design Consultant

AECOM

3rd Runway Infrastructure &

Concourse Scheme Design Consultant Mott MacDonald

3

Page 4: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

EIA Calendar

Submit EIA Report to EPD

end 2013

EPD to review and approve

EIA 2Q 2014

Obtain Environmental

Permit 2Q 2014

4

Page 5: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

1st EIA for a Transport Infrastructure Project to require consideration of health impacts (aircraft noise/ emissions)

Covering 12 environmental aspects:

Three-Runway System EIA Study Brief

Air Quality Land Contamination Noise Chinese White Dolphins Hazard to Life (Fuel System) Marine Ecology & Fisheries Water Quality Landscape and Visual Sewerage and Sewage Treatment

Cultural Heritage

Waste Management Health Impact (Aircraft noise/Emission)

Air Quality Land Contamination Noise Chinese White Dolphins Hazard to Life (Fuel System) Marine Ecology & Fisheries Water Quality Landscape and Visual Sewerage and Sewage Treatment

Cultural Heritage

Waste Management Health Impact (Aircraft Noise/Emission)

5

Page 6: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

1. Reclamation

2. Terminal 2 Expansion

3. 3rd Runway Infrastructure/Concourse

6

Scheme Designs to Complete in 2Q 2014

Completed

In progress

In progress

Detailed Designs to follow (planned to take 2 years)

6

Page 7: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

Airside Fire Station

Future 3rd Runway to be in operation by Q3 2021 (existing North Runway closed)

7

Reclamation Works

Page 8: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

Key Technical Challenges & Constraints

8

Existing Airport 3RS

Environment Related

Not subject to EIA

Reclamation on Contaminated Mud Pits; No dredging committed

Fill Source Locally available Need to secure marine sand from the Mainland

Land Formed Some superstructure built on rock platform

Construction on reclaimed land

Airport Operation

Built on green field site Works subject to airport height/operational restrictions

Integration of Facilities

No planning on site needed

Need for closure of North Runway

Page 9: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

Soft marine clay outside CMPs

Implications -> Require Special Ground Improvement

Key Challenges & Constraints – Non-dredge Seawall Foundation

9

Seawall

Page 10: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

10

West of Po Toi

Brothers Borrow Area East Sha Chau

Main Sources for Existing Airport Quantity

Original CLK Island, Lam Chau & Brothers Islands

~120 Mm3

Brothers Borrow Area ~30 Mm3

East Sha Chau ~15 Mm3

West of Po Toi ~15 Mm3

South of Tsing Yi ~10 Mm3

South of Tsing Yi

Key Challenges & Constraints - No Locally Available Fill Sources

Implication -> Require to search for fill sources outside HK

Page 11: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

Key Challenges & Constraint - Construction on reclaimed land

11

Footprint of Reclamation

Existing Airport 3RS

Existing Airport 3RS

~983 ha Reclamation Area ~644 ha

~11 km Length of Seawall ~13 km

~190 Mm3 Total Volume of Fill Required ~130 Mm3

~70/0/120 Mm3 Sand Fill/Public Fill/Rock Fill ~110/10/10 Mm3

Existing Reclamation 983 Ha

Original CLK Island

258 Ha

Lam Chau 7 Ha

Page 12: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

12

53

Key Challenges & Constraints – Airport Height Restriction

AHR due to Sha Chau Radar

Implications of radar removal -> Remove constraints on the size of marine construction plant over most of the reclamation area

Page 13: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

13

Key Challenges & Constraints – Need for closure of North Runway

New Taxiways

New Airfield Tunnels

3rd Runway and Taxiways (2021)

Re-open of North Runway (2023)

Closure of North Runway (2021)

New Concourse

Page 14: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

14

Ground Improvement

Low-headroom DCM

Deep Cement Mixing (DCM)

Low Headroom DCM

Steel Cells

Stone Columns

Prefabricated Vertical Drains (PVD)

Deep Cement Mixing(DCM)

Page 15: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

Seawall Zone

Formation Zone with PVD

Formation Zone with DCM

Contaminated Mud Pit / Marine Deposit

Sand Blanket Marine Fill

Land Fill

Surcharge

N.T.S

DCM DCM PVD

Sea Water Level

Sea wall

15

Reclamation Works Construction Sequence

Page 16: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

AHR-adapted Installation Approach for Steel Cells Cofferdam

16

Installation Approach for HZMB Islands in PRC waters (No AHR Constraint)

16

Seawalls: Steel Cells

Page 17: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

17

Target Baseline Programme

2 Years (24 Months)

4 Year Reclamation Programme

2.5 Years (30 Months)

3 Years (36 Months)

3.5 Years (42 Months)

4 Years (48 Months)

Page 18: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

18

Design Goals

• What is the most sustainable, long-term approach to the providing an expanded Terminal 2, as part of a 3-runway system?

• How do we match the very high standard set by Terminal 1 to ensure HKIA provides a consistent Level of Service?

Scheme Design – T2 Expansion

Page 19: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

Scheme Design – T2 Expansion

19

Page 20: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

Evaluation of Differentiators

Scheme Design – T2 Expansion

Level of Service/ Pax Experience

Walking distance, level changes, wayfinding, special features

Operational Efficiency

Capacity, impact on existing operations, economy of resources, flexibility

Commercial Retail, advertising, commercial development (including NCD)

Environmental Energy efficiency, BEAM + rating, “green” perception

Quality/Image Architecture, spatial quality, quality of building systems

20

Page 21: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

21

Key Planning Parameters being Studied

Scheme Design - 3rd Runway Infrastructure and Concourse

• Strategy for Automated People Mover

• Strategy for Baggage Handling System

• Concourse and Apron Layouts

Page 22: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

22

Master Plan 2030

Estimated Project Cost

86.2 bn

2010 $

136.2 bn MOD

Page 23: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

3RS Programme Update

Obtain Environmental

Permit 2Q 2014

Obtain ExCo’s project

approval 3Q 2014

Complete statutory processes 1Q 2015

Complete detailed

design and obtain LegCo’s funding

approval By end 2015

Start reclamation

1Q 2016

23

Page 24: Future Development of HKIA Planning of the Three- Runway ... · EIA Calendar Submit EIA Report to EPD . end 2013 . EPD to review and approve EIA 2Q 2014 Obtain ... wall 15 Reclamation

Thank You

24