Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Future Development of HKIA
Planning of the Three-Runway System
Presentation to Hong Kong Air Cargo Forum
19 June 2013
1
Three-runway System: A Three-phase Process
Land formation Detailed designs Construction of related facilities
Implementation
About 8 years*
Environmental permit Foreshore and
seabed gazettal Financial
arrangement
Approval
About 1 year*
Environmental Impact Assessment studies Associated
design details Funding options
Planning
About 2 years*
2
*Indicative timeline that is subject to changes
EIA & Planning Study Team
EIA Lead Consultant Mott MacDonald
AAHK
Air Quality Consultant Arup
Aircraft Noise Consultant
URS
Chinese White Dolphin Experts Bernd Wursig &
Tom Jefferson
EIA Review Consultant ERM
3rd Runway Reclamation Scheme
Design Consultant Atkins
Terminal 2 Expansion
Scheme Design Consultant
AECOM
3rd Runway Infrastructure &
Concourse Scheme Design Consultant Mott MacDonald
3
EIA Calendar
Submit EIA Report to EPD
end 2013
EPD to review and approve
EIA 2Q 2014
Obtain Environmental
Permit 2Q 2014
4
1st EIA for a Transport Infrastructure Project to require consideration of health impacts (aircraft noise/ emissions)
Covering 12 environmental aspects:
Three-Runway System EIA Study Brief
Air Quality Land Contamination Noise Chinese White Dolphins Hazard to Life (Fuel System) Marine Ecology & Fisheries Water Quality Landscape and Visual Sewerage and Sewage Treatment
Cultural Heritage
Waste Management Health Impact (Aircraft noise/Emission)
Air Quality Land Contamination Noise Chinese White Dolphins Hazard to Life (Fuel System) Marine Ecology & Fisheries Water Quality Landscape and Visual Sewerage and Sewage Treatment
Cultural Heritage
Waste Management Health Impact (Aircraft Noise/Emission)
5
1. Reclamation
2. Terminal 2 Expansion
3. 3rd Runway Infrastructure/Concourse
6
Scheme Designs to Complete in 2Q 2014
Completed
In progress
In progress
Detailed Designs to follow (planned to take 2 years)
6
Airside Fire Station
Future 3rd Runway to be in operation by Q3 2021 (existing North Runway closed)
7
Reclamation Works
Key Technical Challenges & Constraints
8
Existing Airport 3RS
Environment Related
Not subject to EIA
Reclamation on Contaminated Mud Pits; No dredging committed
Fill Source Locally available Need to secure marine sand from the Mainland
Land Formed Some superstructure built on rock platform
Construction on reclaimed land
Airport Operation
Built on green field site Works subject to airport height/operational restrictions
Integration of Facilities
No planning on site needed
Need for closure of North Runway
Soft marine clay outside CMPs
Implications -> Require Special Ground Improvement
Key Challenges & Constraints – Non-dredge Seawall Foundation
9
Seawall
10
West of Po Toi
Brothers Borrow Area East Sha Chau
Main Sources for Existing Airport Quantity
Original CLK Island, Lam Chau & Brothers Islands
~120 Mm3
Brothers Borrow Area ~30 Mm3
East Sha Chau ~15 Mm3
West of Po Toi ~15 Mm3
South of Tsing Yi ~10 Mm3
South of Tsing Yi
Key Challenges & Constraints - No Locally Available Fill Sources
Implication -> Require to search for fill sources outside HK
Key Challenges & Constraint - Construction on reclaimed land
11
Footprint of Reclamation
Existing Airport 3RS
Existing Airport 3RS
~983 ha Reclamation Area ~644 ha
~11 km Length of Seawall ~13 km
~190 Mm3 Total Volume of Fill Required ~130 Mm3
~70/0/120 Mm3 Sand Fill/Public Fill/Rock Fill ~110/10/10 Mm3
Existing Reclamation 983 Ha
Original CLK Island
258 Ha
Lam Chau 7 Ha
12
53
Key Challenges & Constraints – Airport Height Restriction
AHR due to Sha Chau Radar
Implications of radar removal -> Remove constraints on the size of marine construction plant over most of the reclamation area
13
Key Challenges & Constraints – Need for closure of North Runway
New Taxiways
New Airfield Tunnels
3rd Runway and Taxiways (2021)
Re-open of North Runway (2023)
Closure of North Runway (2021)
New Concourse
14
Ground Improvement
Low-headroom DCM
Deep Cement Mixing (DCM)
Low Headroom DCM
Steel Cells
Stone Columns
Prefabricated Vertical Drains (PVD)
Deep Cement Mixing(DCM)
Seawall Zone
Formation Zone with PVD
Formation Zone with DCM
Contaminated Mud Pit / Marine Deposit
Sand Blanket Marine Fill
Land Fill
Surcharge
N.T.S
DCM DCM PVD
Sea Water Level
Sea wall
15
Reclamation Works Construction Sequence
AHR-adapted Installation Approach for Steel Cells Cofferdam
16
Installation Approach for HZMB Islands in PRC waters (No AHR Constraint)
16
Seawalls: Steel Cells
17
Target Baseline Programme
2 Years (24 Months)
4 Year Reclamation Programme
2.5 Years (30 Months)
3 Years (36 Months)
3.5 Years (42 Months)
4 Years (48 Months)
18
Design Goals
• What is the most sustainable, long-term approach to the providing an expanded Terminal 2, as part of a 3-runway system?
• How do we match the very high standard set by Terminal 1 to ensure HKIA provides a consistent Level of Service?
Scheme Design – T2 Expansion
Scheme Design – T2 Expansion
19
Evaluation of Differentiators
Scheme Design – T2 Expansion
Level of Service/ Pax Experience
Walking distance, level changes, wayfinding, special features
Operational Efficiency
Capacity, impact on existing operations, economy of resources, flexibility
Commercial Retail, advertising, commercial development (including NCD)
Environmental Energy efficiency, BEAM + rating, “green” perception
Quality/Image Architecture, spatial quality, quality of building systems
20
21
Key Planning Parameters being Studied
Scheme Design - 3rd Runway Infrastructure and Concourse
• Strategy for Automated People Mover
• Strategy for Baggage Handling System
• Concourse and Apron Layouts
22
Master Plan 2030
Estimated Project Cost
86.2 bn
2010 $
136.2 bn MOD
3RS Programme Update
Obtain Environmental
Permit 2Q 2014
Obtain ExCo’s project
approval 3Q 2014
Complete statutory processes 1Q 2015
Complete detailed
design and obtain LegCo’s funding
approval By end 2015
Start reclamation
1Q 2016
23
Thank You
24