Final Presentation CEM2 6

Embed Size (px)

DESCRIPTION

Roads

Citation preview

  • 5/26/2018 Final Presentation CEM2 6

    1/50

    DESIGN OF A MODERN HIGH-RISE BUILDING

    IN ABU-DHABI

    United Arab Emirates University

    Faculty of Engineering

    Department of Civil and Environmental Engineering

    Graduation Project II

    Fall 2010

    Thursday 13 January 2010

    Student Name ID Number

    Abdulrahman Abdulla Alili 200409918

    Mohammed Amer Al-Ameri 200416269

    Wadah Abdulla Ahmed 200540613

    Amr Ezzat Abdel-Havez 200540677

    Advisor : Dr. Aman Mwafy

    Examination Committee:

    Dr. Hany Maximos (Faculty)

    Dr. Amr Sweedan (Dept.)

    Dr. Bilal El-Ariss (Dept.)

  • 5/26/2018 Final Presentation CEM2 6

    2/50

    Objectives

    The Graduation Project is divided into two main phases, namelyGPI and GPII. The three-dimensional (3D) analytical modeling of

    the 60-story building, load calculations and verifications of the

    analytical model were performed in GPI. Tasks and results of this

    phase are briefly presented in this report.

    The second phase of the project focus on designing different

    structural members of the high-rise building such as floor slabs,

    beams, columns, shear walls and foundations using latest analysis

    software and modern design codes.

  • 5/26/2018 Final Presentation CEM2 6

    3/50

    Original Building

  • 5/26/2018 Final Presentation CEM2 6

    4/50

    Building After Modifications

  • 5/26/2018 Final Presentation CEM2 6

    5/50

    Design process

    Requirements SpecificationsConseptual

    Design

    EmbodimentDesign

    (SimulationModel)

    DetailedDesign

    Specification:Building should be design according to:

    ACI 318-05 Code.

    IBC 2009/ASCE 7-05 for calculating the wind loads.

    Structural Analysis programs:

    CSI ETABSCSI SAFE

    PROKON

    Requirement:

    Plan area: 1750.2 m2

    Total number of stories: 60

    Typical Story height: 3.5 m

    Use of the building: residential building

    Used materials: normal and high strength

    material and reinforcing steel

  • 5/26/2018 Final Presentation CEM2 6

    6/50

    Summary of GPI

    Geometric and Load Modeling

    Structural elements modeling (beams, slabs etc..)

    Load modeling

    Hand Calculations

    Actions and deformations

    Preliminary Cost Estimate

  • 5/26/2018 Final Presentation CEM2 6

    7/50

    Summary of GPI

    0

    5000

    10000

    15000

    20000

    25000

    30000

    EarthquakeLoadWind LoadE-W

    Hand Calculation ETABS Results

    0

    200000

    400000

    600000

    800000

    1000000

    1200000

    Dead Load

    Live Load

    Hand ETABS Results

  • 5/26/2018 Final Presentation CEM2 6

    8/50

    GPII Tasks

    Verified three dimensional analytical model of a typical 60-story building,

    representing the modern tall buildings in the UAE.

    Design different structural elements, including the complete design of suitable

    floor slab systems, such as solid slabs and flat slabs, at different story levels of

    the high-rise building using the SAFE and PROKON programs.

    Optimized design of shear walls using the latest version of the ETABS program

    with different load combinations and different cross section sizes and

    reinforcement ratios to arrive at the most cost-effective design.

    Design of columns and different types of beams.

    Design of stairs and the piles foundation system.

    Final Cost Estimates.

  • 5/26/2018 Final Presentation CEM2 6

    9/50

    Design of slab systems

    Flat Slab

    Hollow Block Slab Solid Slab

    Diaphragms and slabs can be defined as a structural system that resist, collect and

    distribute the lateral forces, either earthquake or wind, in the horizontal planes of a structure

    then transmit them to the vertical bearing elements (shear walls, frames) then to the

    foundation and the ground.

    In GPII we have designed three types of slab systems

    1- Flat Slab

    2- Hollow Block Slab

    3- Solid Slab

  • 5/26/2018 Final Presentation CEM2 6

    10/50

    Design of Hollow Block slabs

    Design as a T-

    Section

  • 5/26/2018 Final Presentation CEM2 6

    11/50

    Hollow Block slabs

    Different alternatives of the slab dimensions are considered.We started with a depth equals to 250 mm, which led to a deflection that

    exceeds the

    maximum allowed value.

    To overcome this issue, we increased the depth of the slab to 350 mm by having

    two

    layers of blocks each has 150 mm height, which produced safe deflection

    Increasing the width of ribs

    Increasing the depth & number of blocks

    Increasing of the reinforcement

  • 5/26/2018 Final Presentation CEM2 6

    12/50

  • 5/26/2018 Final Presentation CEM2 6

    13/50

    Solid Slabs

    Wu=1.2WD+ 1.6WL== 16.98 kN/m2

    Mu= 13.262 kN.m/m

    Rn=[Mu/ ( = 2.62 = 0.0065

    As= bd=487.5 mm2 use 7 bars #10

  • 5/26/2018 Final Presentation CEM2 6

    14/50

    Flat slabsExporting three slabs:

    The following three slabs are exported from ETABS to SAFE:

    Ground story slab.

    17th story slab.

    37th story slab.

    Two critical load combinations are selected to extract results from SAFE,

    1.4 SDL+1.4 O.W+ L.L+ 1.4 EQX) a

    1.4 SDL+1.4 O.W+ L.L+ 1.4 EQY).

    The design process of flat slabs is started by

    determining the most optimum thickness of the slab.

    The optimum thickness can be determined by

    selecting the slab thickness and verifying the

    deflection

  • 5/26/2018 Final Presentation CEM2 6

    15/50

    Slab Optimum thicknessL < L/360

    L + add < L/360add = * D

    = / 1+ 50

    ` = As`/ bd

    Safe Unsafe

    Increase the ts

    and check

    Ground story slab thickness equals to 200mm:

    L/360 = 22.2 mm

    L/240 = 33.33 mm

    d = 20025 = 175 mm

    ` = As`/bd = 0.003686

    = / 1+ 50 ` = 1.6887

    where = 2

    L < L/360 5.22 < 22.22O.K

    D = 13.5 + 13 = 26.5

    add =

    * D

    = 44.71

    L+ add < L/36049.93 > 33.33

    unsafe, we have to increase the thickness.

  • 5/26/2018 Final Presentation CEM2 6

    16/50

    Design of flat slabs

    Strip # Direction Strip width (m) Strip type

    S1 x X direction 1 Column strip

    S2 y Y direction 4 Middle strip

    S3 y Y direction 4 Middle strip

    Three strips are defined for each slab, two middle strips and one columnstrip, as shown below.

    The defined strips are used to calculate the maximum bending moment, as

    shown in Figures

  • 5/26/2018 Final Presentation CEM2 6

    17/50

    Design of flat slabs Example :Ground story

    After extracting the maximum positive and negative moment, each is divided by the stripwidth to get the bending moment per unit length and calculate the correspondingreinforcement

    Strip No. +M -M +M/width -M/width

    S1x 123.3 240.9 123.3 240.9

    S2y 229.13 600.3 57.28 150.1

    S3y 298.78 196.9 74.695 49.2

    Strip No. +M/width As = bd Mesh top & bot.

    S1x 123.3 0.00457 1188.2 616

    Strip No. -M/width As = bd Amesh As - Amesh Additional Reinf.

    S1x 240.9 2410 1188.2 1221.8 616

    S2y 150.1 1457.64 1188.2 269.44 412

    S3y 49.2 463.46 1188.2 ---- ----

  • 5/26/2018 Final Presentation CEM2 6

    18/50

    Strip No. -M/width As = bd Amesh

    As -

    Amesh Additional Reinf.

    S1x 240.9 2410 1188.2 1221.8 616

    S2y 150.1 1457.64 1188.2 269.44 412

    S3y 49.2 463.46 1188.2 ---- ----

  • 5/26/2018 Final Presentation CEM2 6

    19/50

    Check of Punching Shear

    12

    ')2(

    fc

    b

    d

    o

    s

    bod

    3

    'fc bod

    6

    ')

    21(

    fc

    c bodVc1 =

    Vc2 =

    Vc3 =

    Vu

    = Vc

    + Vs

    Element Vc (KN) f Vc (KN) Vu (KN) fVu (KN) Decision

    Col-1 595.9 446 161.88 242.82 Safe

    Col-2 1115.94 836.96 275.08 357.6 Safe

    Col-3 2147.66 1610.745 151.8 197.34 Safe

  • 5/26/2018 Final Presentation CEM2 6

    20/50

    Best Alternative

    FlatSlabs

    HollowBlockSlabs

    DecisionBased

    on

    Efficiency/

    Construction

    Cost

    0.00

    10.00

    20.00

    30.00

    40.00

    50.00

    60.00

    Floor slabs cost Hollow block slab

    CostinMillions

    AED

    - The choice of the slab system for the 60-

    stor building is based on the cost and

    performance

    - The hollow block slab system is more

    expensive than flat slabs. Moreover, flat

    slabs are much easier in construction, and

    therefore the flat slabs are selected.

  • 5/26/2018 Final Presentation CEM2 6

    21/50

    Stairs

    Wu= 16.08kN/m

    2

    WuX 0.3 load of each stair = 16.08 X 0.3 = 4.824 kN/m

    (M max)=(Wux L2)/2= (4.824 x 1.452) /2 = 5.07 kN.m

    .

    STEP 1: Determine steel ratio ()

    Rn= [Mu/ (= (5.07*106)/ (0.9*300*(195)2) = 0.49

    = (1- ) = 0.00117

    min= 0.003521

    STEP 2: Determine As

    As= bd = 0.003521*300*195= 206 mm2

    [use 3 bars#10]

    Stairs

    Design of stairs using hand calculations

  • 5/26/2018 Final Presentation CEM2 6

    22/50

    Stairs

    Reinforcement details of stairs

    3#10 /step

    3#10 /step

    Reinforcement distribution

  • 5/26/2018 Final Presentation CEM2 6

    23/50

    BeamsDesign of hidden beam

    Design of edge beam

    Design of connecting beamB1

    Connecting beams

  • 5/26/2018 Final Presentation CEM2 6

    24/50

    Beams

    (M max) = (Wux L2)/8 =168.44 (KN.m)

    STEP 1: Determine steel ratio ()

    Rn= = = 0.975

    = (1- ) = 0.002361

    min= 0.003521 from Eqn. 13

    max= 0.0216 from

    Then min max use min

    STEP 2: Determine As

    d= Beam heightcover = 450 -50= 400 mm

    As= b d = 0.003521 1200 400= 1690.1 mm2

    From Ref [11] , Table B.4 use 9 bars # 16

    From Ref [11], Table B.5One layer

    Beam cross section

    Design of hidden beam using hand calculations

    B

  • 5/26/2018 Final Presentation CEM2 6

    25/50

    Beams

    Bending moment diagram of the hidden beam

    Beam deflection

    Design of hidden beam using Prokon

  • 5/26/2018 Final Presentation CEM2 6

    26/50

    Beams

    Slab Load:

    Dead load from slab = 48.03 kN/m

    Live load from slab = 8.5 kN/m

    Beam own weight

    hb= 620 mmO.W Beam= bwhb c= ((0.250.24) + (0.81 0.38)) (25) = 9.195 kN/m)

    Wall own weight

    O.W wall= bwhw= 0.25 2.88 10 = 7.2 (KN/m)

    Effective Length

    bw+ 6t= 0.25+ (60.38)=2.53

    Effective width (bE)= Smaller of bw+L / 12=0.25 +(6.7/12)=0.81m

    bw+ b0= 0.25+ 4= 4.25 m

    Then, Effective length (bE)= 0.81 m = 810 mm

    Edge beam cross section

    Design of edge beam using hand calculations

  • 5/26/2018 Final Presentation CEM2 6

    27/50

    Beams

    Long-term deflection

    Moment x-x

    Design of edge beam using Prokon

  • 5/26/2018 Final Presentation CEM2 6

    28/50

    Reinforcement distribution

    BeamsReinforcement distribution

  • 5/26/2018 Final Presentation CEM2 6

    29/50

    Beams

    Check if its coupling or conventional beams:

    Design of connecting beams

    Lengthdivided by

    height

    Greaterthan 2

    From ACIcode

    Conventionalbeams

    [3/1]= 3 greater than 2 .ok

  • 5/26/2018 Final Presentation CEM2 6

    30/50

    Beams

    Input data in prokon

    Design of connecting beams using ETABs &Prokon

  • 5/26/2018 Final Presentation CEM2 6

    31/50

    Beams

    Level Beams No. Flange Width Bending Moment Shear Force

    ground

    story levels

    B1_1 750mmM=1270.42 KN.m V=865.2 (KN)

    Reinforcement 8 T 25 4 T 8@ 120 mm

    B1_2 625mm M=1660.9 KN.m V= 1047.6 (KN)

    Reinforcement10 T 25 4 T 10 @ 150 mm

    B1_3 625mm

    M=1537.34 KN.m V= 1072.71 (KN)Reinforcement 9 T 25 4 T 10@ 120 mm

    17thstory

    levels

    B2_1 750mm M=763.82 KN.m V= 620.4 (KN)

    Reinforcement 5 T 25 4 T 8@ 150 mm

    B2_2 625mm M=895.1 KN.m V= 716.71 (KN)

    Reinforcement 6 T 25 4 T 8@ 120 mm

    B2_3 625mm M=767.92 KN.m V= 619.9 (KN)

    Reinforcement 5 T 25 4 T 8@ 150 mm

    36thstory

    levels

    B3_1 750mm M=760.1 KN.m V= 630.37 (KN)

    Reinforcement 5 T 25 4 T 8@ 150 mm

    B3_2 625mm M=820.9 KN.m V= 637.1 (KN)

    Reinforcement 5 T 25 4 T 8@ 150 mm

    B3_3 625mm M=679.5 KN.m V= 564.4 (KN)

    Reinforcement 4 T 25 4 T 8@ 200 mm

    Data outcome form Prokon & ETABS

    Design of connecting beams using ETABs &Prokon

  • 5/26/2018 Final Presentation CEM2 6

    32/50

    Shear Walls

    Design shear walls using ETABs

    Selected shear walls

  • 5/26/2018 Final Presentation CEM2 6

    33/50

    Shear Walls

    o Define pier section.

    o Pier section data.

    o Section designer.

    o Assign pier section.

    o Assign general Reinforcing pier section.o Start design of section.

    Design process

  • 5/26/2018 Final Presentation CEM2 6

    34/50

    Shear Walls

    The D/C ratio indicates the demand over capacity:

    D/C Ratio less than 1section is safe in flexure

    D/C Ratio greater than 1Section is unsafe

    General reinforcing Pier Section

  • 5/26/2018 Final Presentation CEM2 6

    35/50

    Shear Walls

    As(min)= (0.25/100) Ag

    Optimization

    Level Wall Reinforcement

    Layout (1,2 and3)

    P3S mm167@12#6

    P2SS mm167@12#6

    P1SS mm167@12#6

    P4S mm167@12#6

    P5 mm167@12#6

    P6 mm200@12#5P7 mm167@16#6

    mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:5mailto:5mailto:5mailto:5mailto:5mailto:5mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:5mailto:5mailto:5mailto:5mailto:5mailto:5mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6
  • 5/26/2018 Final Presentation CEM2 6

    36/50

    Columns

    Columns name Col(1-20) Col(2-20) Col(2-40)

    No. of columns 8 4 4

    Columns dimension (1000x300) (1500x400) (1500x300)

    Design columns using ETABs

  • 5/26/2018 Final Presentation CEM2 6

    37/50

    Columns

    Columns reinforcement detail

  • 5/26/2018 Final Presentation CEM2 6

    38/50

    Columns

    If columns un-safe:

    Check safety of columns

    Increase columnsdimension

    Increase concretestrength

  • 5/26/2018 Final Presentation CEM2 6

    39/50

    Design of Foundation

    Using Safe program 709 piles have been distributedamong the raft area.

  • 5/26/2018 Final Presentation CEM2 6

    40/50

    Foundation Results

    Point loads representation due to applied loads.

  • 5/26/2018 Final Presentation CEM2 6

    41/50

    Foundation Results

    Deformed shape.

  • 5/26/2018 Final Presentation CEM2 6

    42/50

    Foundation Results

    Strip # 1 in X-direction Strip # 2 in Y-direction Strip # 3 in Y-direction

  • 5/26/2018 Final Presentation CEM2 6

    43/50

    Foundation Reinforcement

    Reinforcement detailing for the raft foundation

  • 5/26/2018 Final Presentation CEM2 6

    44/50

    BeamsBeams (cost) = width length depth number of stories cost of one m3

    ColumnsColumns (cost) = width length height number of stories cost of one m3

    Cost Estimate

  • 5/26/2018 Final Presentation CEM2 6

    45/50

    Cost Estimate

    Shear WallsShear walls (cost) = thickness length height number of stories cost of one m3

    Floor slab

    Flat slab (cost) =thickness net area cost of one m3number of stories

  • 5/26/2018 Final Presentation CEM2 6

    46/50

    Stairs

    Stairs (cost) = Area Stairs thickness Factor (1.2)number of stories cost of one

    m3

    = [(3 m 7 m)0.23 m1.260 stories 2500 (Dhs/ m3)]2= 1,738,800 AED

    Cost Estimate

    Excavation

    Excavations (cost) = Depth Area Raft cost of one m3= 11 m 1750.2 m2 50 (Dhs/m3) = 962,610 AED

    Plain ConcreteConcrete Plan(cost)= Area Raft Thickness Cost of one m3

    = (1750.2) m2 0.4 m 700 (Dhs/ m3)= 490,056 AED

    Raft FoundationRaft foundation(cost)= Area Raft Thickness Cost of one m3

    = (1750.2) m2 3.2 m2200 (Dhs/m3) = 12,321,408AED

    Pile Foundation

    Piles foundation (cost)= Number of piles length of pile Cost of one meter= 709 piles 25 m 2800 (Dhs/m) = 49,630,000 AED

    Foundations

    170,969,819

    AED

  • 5/26/2018 Final Presentation CEM2 6

    47/50

    Cost Estimate

    0

    10

    20

    30

    40

    50

    60

    70

    CostinMillion(AED)

    Final cost estimate of structural system

  • 5/26/2018 Final Presentation CEM2 6

    48/50

    Project Management

    O d li bl

  • 5/26/2018 Final Presentation CEM2 6

    49/50

    Outcomes and Deliverable

    Verified three dimensional analytical model for a typical

    60-story building, representing the modern tall buildings in

    Dubai and Abu Dhabi.

    Design different structural elements and establish full

    design of suitable floor slab systems, such as solid slabs and

    flat slabs, at different story levels of the high-rise building

    using SAFE and PROKON programs.

    Design of columns and different types of beams such as

    conventional.

  • 5/26/2018 Final Presentation CEM2 6

    50/50

    Conclusion

    The analytical model and modern design provisions

    have been employed in the second phase of the project

    (GPII) to fully design different structural members of the

    60-story high-rise building.

    Work in a group and write technical reports.