Upload
faheem2005raja
View
17
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Roads
Citation preview
5/26/2018 Final Presentation CEM2 6
1/50
DESIGN OF A MODERN HIGH-RISE BUILDING
IN ABU-DHABI
United Arab Emirates University
Faculty of Engineering
Department of Civil and Environmental Engineering
Graduation Project II
Fall 2010
Thursday 13 January 2010
Student Name ID Number
Abdulrahman Abdulla Alili 200409918
Mohammed Amer Al-Ameri 200416269
Wadah Abdulla Ahmed 200540613
Amr Ezzat Abdel-Havez 200540677
Advisor : Dr. Aman Mwafy
Examination Committee:
Dr. Hany Maximos (Faculty)
Dr. Amr Sweedan (Dept.)
Dr. Bilal El-Ariss (Dept.)
5/26/2018 Final Presentation CEM2 6
2/50
Objectives
The Graduation Project is divided into two main phases, namelyGPI and GPII. The three-dimensional (3D) analytical modeling of
the 60-story building, load calculations and verifications of the
analytical model were performed in GPI. Tasks and results of this
phase are briefly presented in this report.
The second phase of the project focus on designing different
structural members of the high-rise building such as floor slabs,
beams, columns, shear walls and foundations using latest analysis
software and modern design codes.
5/26/2018 Final Presentation CEM2 6
3/50
Original Building
5/26/2018 Final Presentation CEM2 6
4/50
Building After Modifications
5/26/2018 Final Presentation CEM2 6
5/50
Design process
Requirements SpecificationsConseptual
Design
EmbodimentDesign
(SimulationModel)
DetailedDesign
Specification:Building should be design according to:
ACI 318-05 Code.
IBC 2009/ASCE 7-05 for calculating the wind loads.
Structural Analysis programs:
CSI ETABSCSI SAFE
PROKON
Requirement:
Plan area: 1750.2 m2
Total number of stories: 60
Typical Story height: 3.5 m
Use of the building: residential building
Used materials: normal and high strength
material and reinforcing steel
5/26/2018 Final Presentation CEM2 6
6/50
Summary of GPI
Geometric and Load Modeling
Structural elements modeling (beams, slabs etc..)
Load modeling
Hand Calculations
Actions and deformations
Preliminary Cost Estimate
5/26/2018 Final Presentation CEM2 6
7/50
Summary of GPI
0
5000
10000
15000
20000
25000
30000
EarthquakeLoadWind LoadE-W
Hand Calculation ETABS Results
0
200000
400000
600000
800000
1000000
1200000
Dead Load
Live Load
Hand ETABS Results
5/26/2018 Final Presentation CEM2 6
8/50
GPII Tasks
Verified three dimensional analytical model of a typical 60-story building,
representing the modern tall buildings in the UAE.
Design different structural elements, including the complete design of suitable
floor slab systems, such as solid slabs and flat slabs, at different story levels of
the high-rise building using the SAFE and PROKON programs.
Optimized design of shear walls using the latest version of the ETABS program
with different load combinations and different cross section sizes and
reinforcement ratios to arrive at the most cost-effective design.
Design of columns and different types of beams.
Design of stairs and the piles foundation system.
Final Cost Estimates.
5/26/2018 Final Presentation CEM2 6
9/50
Design of slab systems
Flat Slab
Hollow Block Slab Solid Slab
Diaphragms and slabs can be defined as a structural system that resist, collect and
distribute the lateral forces, either earthquake or wind, in the horizontal planes of a structure
then transmit them to the vertical bearing elements (shear walls, frames) then to the
foundation and the ground.
In GPII we have designed three types of slab systems
1- Flat Slab
2- Hollow Block Slab
3- Solid Slab
5/26/2018 Final Presentation CEM2 6
10/50
Design of Hollow Block slabs
Design as a T-
Section
5/26/2018 Final Presentation CEM2 6
11/50
Hollow Block slabs
Different alternatives of the slab dimensions are considered.We started with a depth equals to 250 mm, which led to a deflection that
exceeds the
maximum allowed value.
To overcome this issue, we increased the depth of the slab to 350 mm by having
two
layers of blocks each has 150 mm height, which produced safe deflection
Increasing the width of ribs
Increasing the depth & number of blocks
Increasing of the reinforcement
5/26/2018 Final Presentation CEM2 6
12/50
5/26/2018 Final Presentation CEM2 6
13/50
Solid Slabs
Wu=1.2WD+ 1.6WL== 16.98 kN/m2
Mu= 13.262 kN.m/m
Rn=[Mu/ ( = 2.62 = 0.0065
As= bd=487.5 mm2 use 7 bars #10
5/26/2018 Final Presentation CEM2 6
14/50
Flat slabsExporting three slabs:
The following three slabs are exported from ETABS to SAFE:
Ground story slab.
17th story slab.
37th story slab.
Two critical load combinations are selected to extract results from SAFE,
1.4 SDL+1.4 O.W+ L.L+ 1.4 EQX) a
1.4 SDL+1.4 O.W+ L.L+ 1.4 EQY).
The design process of flat slabs is started by
determining the most optimum thickness of the slab.
The optimum thickness can be determined by
selecting the slab thickness and verifying the
deflection
5/26/2018 Final Presentation CEM2 6
15/50
Slab Optimum thicknessL < L/360
L + add < L/360add = * D
= / 1+ 50
` = As`/ bd
Safe Unsafe
Increase the ts
and check
Ground story slab thickness equals to 200mm:
L/360 = 22.2 mm
L/240 = 33.33 mm
d = 20025 = 175 mm
` = As`/bd = 0.003686
= / 1+ 50 ` = 1.6887
where = 2
L < L/360 5.22 < 22.22O.K
D = 13.5 + 13 = 26.5
add =
* D
= 44.71
L+ add < L/36049.93 > 33.33
unsafe, we have to increase the thickness.
5/26/2018 Final Presentation CEM2 6
16/50
Design of flat slabs
Strip # Direction Strip width (m) Strip type
S1 x X direction 1 Column strip
S2 y Y direction 4 Middle strip
S3 y Y direction 4 Middle strip
Three strips are defined for each slab, two middle strips and one columnstrip, as shown below.
The defined strips are used to calculate the maximum bending moment, as
shown in Figures
5/26/2018 Final Presentation CEM2 6
17/50
Design of flat slabs Example :Ground story
After extracting the maximum positive and negative moment, each is divided by the stripwidth to get the bending moment per unit length and calculate the correspondingreinforcement
Strip No. +M -M +M/width -M/width
S1x 123.3 240.9 123.3 240.9
S2y 229.13 600.3 57.28 150.1
S3y 298.78 196.9 74.695 49.2
Strip No. +M/width As = bd Mesh top & bot.
S1x 123.3 0.00457 1188.2 616
Strip No. -M/width As = bd Amesh As - Amesh Additional Reinf.
S1x 240.9 2410 1188.2 1221.8 616
S2y 150.1 1457.64 1188.2 269.44 412
S3y 49.2 463.46 1188.2 ---- ----
5/26/2018 Final Presentation CEM2 6
18/50
Strip No. -M/width As = bd Amesh
As -
Amesh Additional Reinf.
S1x 240.9 2410 1188.2 1221.8 616
S2y 150.1 1457.64 1188.2 269.44 412
S3y 49.2 463.46 1188.2 ---- ----
5/26/2018 Final Presentation CEM2 6
19/50
Check of Punching Shear
12
')2(
fc
b
d
o
s
bod
3
'fc bod
6
')
21(
fc
c bodVc1 =
Vc2 =
Vc3 =
Vu
= Vc
+ Vs
Element Vc (KN) f Vc (KN) Vu (KN) fVu (KN) Decision
Col-1 595.9 446 161.88 242.82 Safe
Col-2 1115.94 836.96 275.08 357.6 Safe
Col-3 2147.66 1610.745 151.8 197.34 Safe
5/26/2018 Final Presentation CEM2 6
20/50
Best Alternative
FlatSlabs
HollowBlockSlabs
DecisionBased
on
Efficiency/
Construction
Cost
0.00
10.00
20.00
30.00
40.00
50.00
60.00
Floor slabs cost Hollow block slab
CostinMillions
AED
- The choice of the slab system for the 60-
stor building is based on the cost and
performance
- The hollow block slab system is more
expensive than flat slabs. Moreover, flat
slabs are much easier in construction, and
therefore the flat slabs are selected.
5/26/2018 Final Presentation CEM2 6
21/50
Stairs
Wu= 16.08kN/m
2
WuX 0.3 load of each stair = 16.08 X 0.3 = 4.824 kN/m
(M max)=(Wux L2)/2= (4.824 x 1.452) /2 = 5.07 kN.m
.
STEP 1: Determine steel ratio ()
Rn= [Mu/ (= (5.07*106)/ (0.9*300*(195)2) = 0.49
= (1- ) = 0.00117
min= 0.003521
STEP 2: Determine As
As= bd = 0.003521*300*195= 206 mm2
[use 3 bars#10]
Stairs
Design of stairs using hand calculations
5/26/2018 Final Presentation CEM2 6
22/50
Stairs
Reinforcement details of stairs
3#10 /step
3#10 /step
Reinforcement distribution
5/26/2018 Final Presentation CEM2 6
23/50
BeamsDesign of hidden beam
Design of edge beam
Design of connecting beamB1
Connecting beams
5/26/2018 Final Presentation CEM2 6
24/50
Beams
(M max) = (Wux L2)/8 =168.44 (KN.m)
STEP 1: Determine steel ratio ()
Rn= = = 0.975
= (1- ) = 0.002361
min= 0.003521 from Eqn. 13
max= 0.0216 from
Then min max use min
STEP 2: Determine As
d= Beam heightcover = 450 -50= 400 mm
As= b d = 0.003521 1200 400= 1690.1 mm2
From Ref [11] , Table B.4 use 9 bars # 16
From Ref [11], Table B.5One layer
Beam cross section
Design of hidden beam using hand calculations
B
5/26/2018 Final Presentation CEM2 6
25/50
Beams
Bending moment diagram of the hidden beam
Beam deflection
Design of hidden beam using Prokon
5/26/2018 Final Presentation CEM2 6
26/50
Beams
Slab Load:
Dead load from slab = 48.03 kN/m
Live load from slab = 8.5 kN/m
Beam own weight
hb= 620 mmO.W Beam= bwhb c= ((0.250.24) + (0.81 0.38)) (25) = 9.195 kN/m)
Wall own weight
O.W wall= bwhw= 0.25 2.88 10 = 7.2 (KN/m)
Effective Length
bw+ 6t= 0.25+ (60.38)=2.53
Effective width (bE)= Smaller of bw+L / 12=0.25 +(6.7/12)=0.81m
bw+ b0= 0.25+ 4= 4.25 m
Then, Effective length (bE)= 0.81 m = 810 mm
Edge beam cross section
Design of edge beam using hand calculations
5/26/2018 Final Presentation CEM2 6
27/50
Beams
Long-term deflection
Moment x-x
Design of edge beam using Prokon
5/26/2018 Final Presentation CEM2 6
28/50
Reinforcement distribution
BeamsReinforcement distribution
5/26/2018 Final Presentation CEM2 6
29/50
Beams
Check if its coupling or conventional beams:
Design of connecting beams
Lengthdivided by
height
Greaterthan 2
From ACIcode
Conventionalbeams
[3/1]= 3 greater than 2 .ok
5/26/2018 Final Presentation CEM2 6
30/50
Beams
Input data in prokon
Design of connecting beams using ETABs &Prokon
5/26/2018 Final Presentation CEM2 6
31/50
Beams
Level Beams No. Flange Width Bending Moment Shear Force
ground
story levels
B1_1 750mmM=1270.42 KN.m V=865.2 (KN)
Reinforcement 8 T 25 4 T 8@ 120 mm
B1_2 625mm M=1660.9 KN.m V= 1047.6 (KN)
Reinforcement10 T 25 4 T 10 @ 150 mm
B1_3 625mm
M=1537.34 KN.m V= 1072.71 (KN)Reinforcement 9 T 25 4 T 10@ 120 mm
17thstory
levels
B2_1 750mm M=763.82 KN.m V= 620.4 (KN)
Reinforcement 5 T 25 4 T 8@ 150 mm
B2_2 625mm M=895.1 KN.m V= 716.71 (KN)
Reinforcement 6 T 25 4 T 8@ 120 mm
B2_3 625mm M=767.92 KN.m V= 619.9 (KN)
Reinforcement 5 T 25 4 T 8@ 150 mm
36thstory
levels
B3_1 750mm M=760.1 KN.m V= 630.37 (KN)
Reinforcement 5 T 25 4 T 8@ 150 mm
B3_2 625mm M=820.9 KN.m V= 637.1 (KN)
Reinforcement 5 T 25 4 T 8@ 150 mm
B3_3 625mm M=679.5 KN.m V= 564.4 (KN)
Reinforcement 4 T 25 4 T 8@ 200 mm
Data outcome form Prokon & ETABS
Design of connecting beams using ETABs &Prokon
5/26/2018 Final Presentation CEM2 6
32/50
Shear Walls
Design shear walls using ETABs
Selected shear walls
5/26/2018 Final Presentation CEM2 6
33/50
Shear Walls
o Define pier section.
o Pier section data.
o Section designer.
o Assign pier section.
o Assign general Reinforcing pier section.o Start design of section.
Design process
5/26/2018 Final Presentation CEM2 6
34/50
Shear Walls
The D/C ratio indicates the demand over capacity:
D/C Ratio less than 1section is safe in flexure
D/C Ratio greater than 1Section is unsafe
General reinforcing Pier Section
5/26/2018 Final Presentation CEM2 6
35/50
Shear Walls
As(min)= (0.25/100) Ag
Optimization
Level Wall Reinforcement
Layout (1,2 and3)
P3S mm167@12#6
P2SS mm167@12#6
P1SS mm167@12#6
P4S mm167@12#6
P5 mm167@12#6
P6 mm200@12#5P7 mm167@16#6
mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:5mailto:5mailto:5mailto:5mailto:5mailto:5mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:5mailto:5mailto:5mailto:5mailto:5mailto:5mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:6mailto:65/26/2018 Final Presentation CEM2 6
36/50
Columns
Columns name Col(1-20) Col(2-20) Col(2-40)
No. of columns 8 4 4
Columns dimension (1000x300) (1500x400) (1500x300)
Design columns using ETABs
5/26/2018 Final Presentation CEM2 6
37/50
Columns
Columns reinforcement detail
5/26/2018 Final Presentation CEM2 6
38/50
Columns
If columns un-safe:
Check safety of columns
Increase columnsdimension
Increase concretestrength
5/26/2018 Final Presentation CEM2 6
39/50
Design of Foundation
Using Safe program 709 piles have been distributedamong the raft area.
5/26/2018 Final Presentation CEM2 6
40/50
Foundation Results
Point loads representation due to applied loads.
5/26/2018 Final Presentation CEM2 6
41/50
Foundation Results
Deformed shape.
5/26/2018 Final Presentation CEM2 6
42/50
Foundation Results
Strip # 1 in X-direction Strip # 2 in Y-direction Strip # 3 in Y-direction
5/26/2018 Final Presentation CEM2 6
43/50
Foundation Reinforcement
Reinforcement detailing for the raft foundation
5/26/2018 Final Presentation CEM2 6
44/50
BeamsBeams (cost) = width length depth number of stories cost of one m3
ColumnsColumns (cost) = width length height number of stories cost of one m3
Cost Estimate
5/26/2018 Final Presentation CEM2 6
45/50
Cost Estimate
Shear WallsShear walls (cost) = thickness length height number of stories cost of one m3
Floor slab
Flat slab (cost) =thickness net area cost of one m3number of stories
5/26/2018 Final Presentation CEM2 6
46/50
Stairs
Stairs (cost) = Area Stairs thickness Factor (1.2)number of stories cost of one
m3
= [(3 m 7 m)0.23 m1.260 stories 2500 (Dhs/ m3)]2= 1,738,800 AED
Cost Estimate
Excavation
Excavations (cost) = Depth Area Raft cost of one m3= 11 m 1750.2 m2 50 (Dhs/m3) = 962,610 AED
Plain ConcreteConcrete Plan(cost)= Area Raft Thickness Cost of one m3
= (1750.2) m2 0.4 m 700 (Dhs/ m3)= 490,056 AED
Raft FoundationRaft foundation(cost)= Area Raft Thickness Cost of one m3
= (1750.2) m2 3.2 m2200 (Dhs/m3) = 12,321,408AED
Pile Foundation
Piles foundation (cost)= Number of piles length of pile Cost of one meter= 709 piles 25 m 2800 (Dhs/m) = 49,630,000 AED
Foundations
170,969,819
AED
5/26/2018 Final Presentation CEM2 6
47/50
Cost Estimate
0
10
20
30
40
50
60
70
CostinMillion(AED)
Final cost estimate of structural system
5/26/2018 Final Presentation CEM2 6
48/50
Project Management
O d li bl
5/26/2018 Final Presentation CEM2 6
49/50
Outcomes and Deliverable
Verified three dimensional analytical model for a typical
60-story building, representing the modern tall buildings in
Dubai and Abu Dhabi.
Design different structural elements and establish full
design of suitable floor slab systems, such as solid slabs and
flat slabs, at different story levels of the high-rise building
using SAFE and PROKON programs.
Design of columns and different types of beams such as
conventional.
5/26/2018 Final Presentation CEM2 6
50/50
Conclusion
The analytical model and modern design provisions
have been employed in the second phase of the project
(GPII) to fully design different structural members of the
60-story high-rise building.
Work in a group and write technical reports.