21
CRAIG EDWARD GUENETTE SUPERVISOR: CHRISTOPHER “SCOTT” JAMES BUDDY #1: RYAN ADAMS BUDDY #2: SEAN DOREY No Diamonds YetCollege: Wentworth Institute of Tech. Major: Mechanical Engineering Tech. Current Year: Junior Current GPA: 3.648 Exp. YOG: August 2010 Sub-Division: Missiles and Fire Control Location: Camden, AR Program: THAAD (Terminal High Altitude Area Defense) Position: Co-op Mechanical Engineer Start/End Date: January 12, 2009/May 8, 2009 1 Table of Contents

Final Presentation

Embed Size (px)

Citation preview

Page 1: Final Presentation

1

CRAIG EDWARD GUENETTE

SUPERVISOR: CHRISTOPHER “SCOTT” JAMES BUDDY #1: RYAN ADAMS BUDDY #2: SEAN DOREY

No Diamonds Yet…

College: Wentworth Institute of Tech.Major: Mechanical Engineering Tech.Current Year: JuniorCurrent GPA: 3.648Exp. YOG: August 2010

Sub-Division: Missiles and Fire ControlLocation: Camden, ARProgram: THAAD (Terminal High Altitude Area Defense)

Position: Co-op Mechanical EngineerStart/End Date: January 12, 2009/May 8, 2009

Table of Contents

Page 2: Final Presentation

2

TABLE OF CONTENTSHISTORIC MILESTONESTHAADWEEK 1WEEK 2WEEK 3WEEK 4WEEK 5WEEK 6WEEK 7WEEK 8WEEK 9

WEEK 10WEEK 11WEEK 12WEEK 13WEEK 14WEEKS 15 - 17VALUED EXPERIENCESTHANK YOU!

Page 3: Final Presentation

3

HISTORIC MILESTONESBorn and Raised: Acushnet, MA

Home life: Loving Family of six

Age 5: Exposure to Mechanical and Electrical Systems

Age 7-18: Continuous involvement in Athletics/Sports

Age 8: Identified my career choice – ME

Age 15: Entered the Workforce

Age 18: Secured my first job as a ME Co-op –

Age 19: Optional Co-op –

Age 20: First (of Two) mandatory Co-op –

Age 21: “Here I Stand!”

Table of Contents

Page 4: Final Presentation

4

THAAD 5 Major Components

Launcher Missiles Radar Fire Control Ground Support

Endo and Exo-atmospheric

Enlarges Battle Space

Rapid Deployment

Hit-To-Kill Lethality

Missile Defense

Table of Contents

Page 5: Final Presentation

5

WEEK 1 Extensive Lockheed Martin Corporation Training

Courses Taken: 35 Courses Failed: 0

Grand Tour of the CLIC Building and my workstation

First design assignment – MRP Flip-Right “Cart”

01/12/09 – 01/18/09

Nomenclature:- Completed- In-Progress

Table of Contents

Flip-Right

Page 6: Final Presentation

6

WEEK 2 Designed MRP Flip-Right “High Mobility Caster Assembly”

Calculated, Researched, and Submitted a PR for HMCA materials

Second Design Project – MRP Hydraulic Lift “Safety Stop”

01/19/09 – 01/25/09

Table of Contents

MRP

Page 7: Final Presentation

7

WEEK 301/26/09 – 02/01/09

Designed MRP Hydraulic Lift “Height Adjustment Safety Blocks”

Located In-Stock Domex material for HASB to be delivered to CLIC

Received HMCA materials and submitted a WO for fabrication

Designed Launcher Oil Drain Protection Cover

Table of Contents

Page 8: Final Presentation

8

WEEK 402/02/09 – 02/08/09

Built MRP HASB and submitted a WO for paint

HASB tested and incorporated into MRP build-up process

HMCA fabricated, tested, and reside under the MRP Flip-Right

Supervised Launcher Integration – CAB Cable Installations (2 employees)

Table of Contents

Flip-Right

Page 9: Final Presentation

9

WEEK 502/09/09 – 02/15/09

Supervised Launcher Integration – Battery Box Installation (3 employees)

Designed MRP Gusset Location Tools – Two Options

Built Launcher Oil Drain Protection Cover

Table of Contents

Before After

Page 10: Final Presentation

10

WEEK 602/16/09 – 02/22/09

Ordered, received, and assembled suitable cart for MRP Borescope

Redesigned MRP Cart Supports (previous co-op’s design)

Designed MRP Cross Member Location Tool Supervised Launcher Integration – MUJB (3 employees)

Table of Contents

Page 11: Final Presentation

11

WEEK 702/23/09 – 03/01/09

Studied engineering/planning for TFCC SSG (ASV and CSV) integration

Designed TFCC ACU Installation Support Deck

Fabrication of MRP Cross Member Location Tool

Table of Contents

Page 12: Final Presentation

12

WEEK 803/02/09 – 03/08/09

Developed Parallel Processing for ASV Work Instructions – Pending Work Order

Fabrication of MRP Cross Member Location Tool

Fabrication of TFCC ACU Installation Support Deck

Table of Contents

Page 13: Final Presentation

13

WEEK 903/09/09 – 03/15/09

Designed Launcher CEM Drill Fixture Stands – Two Options

Selected and Built CEM Drill Fixture Stands – Option 2 (top right)

Supervised FUF 1 ASV integration (2 employees)

12’- 8”5’- 2”

Table of Contents

Before After

Page 14: Final Presentation

14

WEEK 1003/16/09 – 03/22/09

Designed Riv-nut Nose Piece Modification

Tested and Incorporated Modified Nose Piece into SSG integration

Supervised FUF 1 ASV integration (2-3 employees)

Table of Contents

Page 15: Final Presentation

15

WEEK 1103/23/09 – 03/29/09

Incorporated cumulative redlines into planning

Designed 33/64” and 12.5 mm Drill Guides for SSG construction

Supervised FUF 1 ASV integration (2-4 employees)

Table of Contents

Page 16: Final Presentation

16

WEEK 1203/30/09 – 04/05/09

Order of operations changed on the SSG integration process

Successfully supervised FUF 1 ASV integration (3-5 employees)

Table of Contents

Page 17: Final Presentation

17

WEEK 1304/06/09 – 04/12/09

Created Engineering Drawing of MRP Riv-Nut Alignment Template

Successfully Supervised FUF 1 CSV integration (3-5 employees)

Cleaned, Organized, and Prepared for THAAD Roll Out 2009

Table of Contents

Page 18: Final Presentation

18

WEEK 1404/13/09 – 04/19/09

THAAD Roll Out Ceremony

Ordered tooling for FUF 2 SSG Integration

Drastically updated ASV and CSV Planning

Table of Contents

MY BUDDY!!

Page 19: Final Presentation

19

WEEKS 15 - 1704/20/09 – 05/08/09

Table of Contents

Toured Lockheed Martin’s MFC Dallas, TX Facility

Successfully supervised FUF 2 ASV integration (3 employees)

Supervised FUF 2 CSV integration (3 employees)

Page 20: Final Presentation

20

VALUED EXPERIENCES Personally Fabricated Design Projects: 5

Personally Design Projects: 13

Average Hours Worked/Week: 58.3

Networking Opportunities: Endless

Table of Contents

+One Unforgettable Experience

My Career

Page 21: Final Presentation

21

THANK YOU!

RESERVED

FOR

APPRECIATION

Although it has been an enjoyable, rewarding, and truly paramount experience, the time has arrived where this particular southern escapade has unfortunately come to an end…

…However, I will look forward to the period in time when another extraordinary opportunity, such as this, is presented.

Table of Contents