ISOLATED FOOTINGMANHOUR DERIVATION
LENGTH ( m ) WIDTH ( m ) THICKNESS ( m ) DEPTH FROM NGL Footing 1.5 1.5 0.525 1.525 pedestal 0.4 0.4 1.000
Volume of Concrete 1.34 m3
NGL
1000mm 400mm 1500mm
525mm
1500mm
1500mm
OPTION 1 - MANUAL
Item Qty Unit Unit Mhr Total Mhr REMARKS
excavation 6.73 m3 8.00 53.80 Manual backfill 5.38 m3 1.89 10.18 Manual disposal 1.34 m3 0.06 0.08 lean concrete 0.11 m3 5.50 0.62 pedestal concrete 0.16 m3 12.00 1.92 Bagger mixedfooting concrete 1.18 m3 12.00 14.18 Bagger mixedrebars 110.00 kgs 0.07 7.70 Manual Cut & bendforms 4.75 m2 3.30 15.68 Wooden formsTotal 104.16 mhrs
Average Mhr / 77.66 mhrs / m3 Volume of Concrete
OPTION 2 - MECHANIZED
Item Qty Unit Unit Mhr Total Mhr REMARKS
excavation 6.73 m3 0.16 1.08 Mechanizedbackfill 5.38 m3 0.46 2.48 Mechanizeddisposal 1.34 m3 0.06 0.08 lean concrete 0.11 m3 5.50 0.62 pedestal concrete 0.16 m3 4.10 0.66 Batch Plant / transit mixedconcrete 1.18 m3 4.10 4.84 Batch Plant / transit mixedrebars 110.00 kgs 0.06 6.60 Machine Cut & Bendforms 4.75 m2 2.70 12.83 Steel forms / Pre fabTotal 29.19 mhrs
Average Mhr / 21.76 mhrs / m3 Volume of Concrete