Deposit of high toxic waste in underground storages and underground reutilisations of the K+S AG. Belgrade, Serbia, 24.11.2011. The K+S Group | Facts and figures. A world wide leader in the sectors of: Special and standard fertilisers Plant care products Salt products - PowerPoint PPT Presentation
Citation preview
K+S Group
K+S Entsorgung GmbH
Deposit of high toxic waste in underground storages and underground reutilisations of the K+S AG
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHThe K+S Group | Facts and figures
Sites in 25 countries
A world wide leader in the sectors of:
• Special and standard fertilisers
• Plant care products
• Salt products
• More than 15,200 employees
• Revenue 2010: 4.99 billion €
• Since September 2008: listed in the DAX – Germany‘s most important stock index
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHThe K+S Group | Corporate structure
K+S Group
Core Business Sector FertilizersCore Business
Sector SaltComplementary
Business Sectors
NitrogenFertilizers
Salt
Waste Mgmt. &RecyclingPotash and
Magnesium Products Animal hygieneproducts
Kali-TransportGmbH (KTG)
Trading business (CFK)
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHK+S Entsorgung | Profile
• A K+S Group business segment since 1991
• Disposal activities are centrally managed from Kassel
• Internationally active, with representatives in eight countries
• Pioneer of underground waste disposal;first facility worldwide: Herfa-Neurode (1972)
• Revenue 2010: 73.8 m. €
Europe‘s leading company in the field of underground waste disposal
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHK+S Entsorgung | Areas of activity
Recycling
K+S Entsorgung
Underground waste management
Disposal(UTD)
Reutilisation(UTV)
Salt slag(REKAL)
Buildingmaterial
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHK+S Entsorgung | Areas of activity
Underground disposalSolution for highly contaminated materialsLong-term removal from the biosphere
Underground reutilisation
Solution for less contaminated materialsUtilisation of the material properties by:• Stacking backfill• High-consistency slurry backfill• Tipping backfill
Building material recycling
Recycling of construction materialsUtilisation as cover material for greening a potash tailings pile
Secondary aluminium
System solutions • Distribution of salt fluxes• Recycling of salt slag• Raw materials recovery• Disposal of filter dusts
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHDisposal facilities | Germany
1 Underground waste disposal plant Zielitz
2 Underground waste disposal plant Herfa-Neurode
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbH
1 Underground waste disposal plant Zielitz
2 Underground waste disposal plantHerfa-Neurode
3 Underground reutilisation facility Zielitz
4 Underground reutilisation facility Bernburg
5 Underground reutilisation facility Wintershall
6 Underground reutilisation facility Hattorf
7 Underground reutilisation facility Unterbreizbach
Disposal facilities | Germany
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbH
1 Underground waste disposal plant Zielitz
2 Underground waste disposal plant Herfa-Neurode
3 Underground reutilisation facility Zielitz
4 Underground reutilisation facility Bernburg
5 Underground reutilisation facility Wintershall
6 Underground reutilisation facility Hattorf
7 Underground reutilisation facility Unterbreizbach
8 Aluminium salt slag recyclingSigmundshall
9 Building material recycling Sehnde
Disposal facilities | Germany
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbH
• Focal point: underground waste disposal
• Disposal at own facilities
• Largest number of facilities on the market
• Largest range of procedures
• Ideal conditions for long-term safe disposal of wastes
Solutions | Underground waste disposal
Basic principle: Safety
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbH
Formation of the salt layers 250 million years ago
Evaporation caused by solar heat
Barrier
Salt deposit
Potash deposit
Semi-enclosed sea
Salted sea water
Geology | Formation of the salt and potash deposits
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHGeology | Werk Werra
Deposit thickness up to 500 metres | Gastight
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHMining | Map of mine
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHMining | Preparation for blasting
2 | Blast hole drilling
1 | Large hole drilling
3 | Filling with explosives
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHMining | Underground transport of salt
4 | Transport of ore 5 | Transport via conveyor to the shaft
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHMining | Preparation of the cavities
1 | Scaling of the roof 2 | Installation of roof bolts
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHMining | Construction of roadways
1 | Filling up with salt 2 | Levelling, humidification, compacting
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbH
Objective: long-term-safe removal of hazardous wastes from the biosphere
UTD | Disposal of wastes
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbH
• Ideal geological conditions and technical safety systems
• Deposit at depths of 500 to 800 m, way below the ground water
• Traceability of all deposits due to detailed documentation
• Retrievability of all wastes for recycling
Objective: long-term-safe removal of hazardous wastes from the biosphere
UTD | Disposal of Wastes
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHUTD Herfa-Neurode | Prerequisites
Safest solution for the disposal of hazardous waste
Prerequisites for underground waste disposal:
• Disused, excavated area of the mine
• Remote from extraction area with possibility to be sealed off
• Galleries remain open and have no backfill obligation
• Galleries have to be stable and must remain accessible even after a longer time
• Mine has to be dry and free of water
• Storage area has to be sealed off from biosphere by geological barriers
• Maintenance-free
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbH
Examples of waste types
• arsenic-containing wastes
• mercury-containing wastes
• contaminated construction and demolition waste
(e.g. heavy metal, dioxin, mercury, PCB)
• hardening salt residues
• cyanide-containing wastes
• filter dusts
UTD Herfa-Neurode | Waste types
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbH
Natural barriers
• Salt (gastight) 300 m
• Clay (watertight) 100 m
• Bunter stone 500 m
Artificial barriers
• Waste packaging
• Brick walls
• Field dams
• Disposal field dams
• Watertight sealing of the shafts
UTD Herfa-Neurode | Multi-barrier-system
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHUTV | Underground Reutilisation
Objective: safeguarding former mining chambers
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbH
• Utilisation of the wastes‘ material properties
• Deployment of certain, non-mining mineral wastes
• Support of pillars by backfill material, prevention of deformations
• Disposal option for less contaminated materials
• Backfill obligation valid only for certain mine sectors
UTV | Underground Reutilisation
Objective: safeguarding former mining chambers
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHUTV | Backfill Procedures
Backfill procedure depends on waste properties & site conditions
• Deposited by dump trucks
• Dumping and compacting
• Marginally contaminated materials
Tipping backfill Stacking backfill Slurry backfill
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHUTV | Backfill Procedures
• Deposited by dump trucks
• Dumping and compacting
• Marginally contaminated materials
Tipping backfill Slurry backfillStacking backfill
• Conditioning and packaging
• Stacking of big-bags
• Filling of the gapswith rock salt
Backfill procedure depends on waste properties & site conditions
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHUTV | Backfill Procedures
• Deposited by dump trucks
• Dumping and compacting
• Marginally contaminated materials
Tipping backfill Stacking backfill Slurry backfill
• Material pneumatically transportable
• Mixing with salt brine
• Sludge production
• Pumping into caverns
• Conditioning and packaging
• Stacking of big-bags
• Filling of the gapswith rock salt
Backfill procedure depends on waste properties & site conditions
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbH
• Solution for uncontaminated or marginally contaminated soil,construction and demolition waste
• Processing of material
• Depositing on potash tailings pile
• Basis for plant growth
Recycling | Building Material Recycling
Pilot project: greening of potash tailings pile
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbH
• Provision of high-grade salt fluxes
• Salt slag processing
• Reutilisation of all components
Recycling | REKAL
Complete solution for the secondary aluminium industry
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbHK+S Entsorgung | Long-term-safety
• Agencies in different countries
• International team
• Experienced in project management
• Experienced in managing notificationprocedures
• Large number of sites
• Technical diversity
• Longest experience in underground disposal
• Maintenance-free
Belgrade, Serbia, 24.11.2011
K+S Group
K+S Entsorgung GmbH
T h a n k y o u f o r y o u r a t t e n t i o n !
Belgrade, Serbia, 24.11.2011