19
7 May 09 1 Environmental Energy Technologies Division Data Center Control with Wireless Sensor Technology and Airflow Management Demonstration at the California Franchise Tax Board August 2008 - April 2009

Data Center Control with Wireless Sensor Technology and ... · Data Center Control with Wireless Sensor Technology and Airflow Management. Demonstration at the California Franchise

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

7 May 09 1Environmental Energy Technologies Division

Data Center Control with

Wireless Sensor Technology and

Airflow Management

Demonstration at the California Franchise Tax Board

August 2008 - April 2009

7 May 09 2Environmental Energy Technologies Division

Opening Remarks: Welcome & thank you for attending… In August 2008, FTB partnered with California’s

Department of General Services and the California Energy Commission to install a Data Automation Software and Hardware (DASH™) system from Federspiel Controls.

The DASH system uses wireless sensors and web based software to control computer room air handling (CRAH) units.

The project also included installing variable frequency fan drives and fusible-link curtains.

7 May 09 3Environmental Energy Technologies Division

Opening Remarks: Thanks to our supporters!

7 May 09 4Environmental Energy Technologies Division

Project Overview: Significant Results…

Reduces fan energy by 66%

Lowers total energy by 21.3%

Saves 475,000 kWh/yr Eliminates >400 tons

CO2/yr Payback in 3.1 years Bottom-line: $42,722 per

year saved

7 May 09 5Environmental Energy Technologies Division

Demonstration Support: Primary Goals…Demonstrate wireless, mesh-network technology to

directly control air handlers.Analyze supervisory software and hardware.Eliminate over-cooling caused by contending controls.Examine air management best-practices.Ensure CRAH unit operational redundancy.

LBNL mission:Perform independent “white-paper” review of project.Provide knowledgeable support to all parties involved.Share project findings with data center community.Satisfy PIER and CEC resource needs…

7 May 09 6Environmental Energy Technologies Division

Executive Summary:FTB Data Center

Description:• 10,000 Sq Ft • 12 CRAH cooling units • 135 kW load

Challenges:• Over-provisioned • History of fighting • Manual shutoff not successful

Solution:• Intelligent supervisory control software with inlet air sensing

7 May 09 7Environmental Energy Technologies Division

Project Tasks:

• Establish baseline

• Adjust floor tiles

• Install Variable Frequency Drives (VFDs)

• Install supervisory control software

• Isolate hot-aisles

• Blank racks

7 May 09 8Environmental Energy Technologies Division

DASH: • 50 wireless temperature sensors

(Dust Networks radios)• Intelligent control software

7 May 09 9Environmental Energy Technologies Division

89 °F (31.7 °C)

63 °F (17 °C)

Airflow Solution

7 May 09 10Environmental Energy Technologies Division

Smart software: learns about curtains

CRAH 3 influence at start CRAH 3 influence after curtains

CRAH-03

7 May 09 11Environmental Energy Technologies Division

Effect on cold aisle temperatures:

50

55

60

65

70

75

80

85

90

A B C D E FTime Interval

degF

floor

tile

cha

nges

VFD

s

cont

rol s

oftw

are

hot a

isle

isol

atio

n

rack

bla

nks

lower limit of ASHRAE recommended range

upper limit of ASHRAE recommended range

7 May 09 12Environmental Energy Technologies Division

DASH = Dramatic Reduction…

0

10

20

30

40

50

60

1/31 2/5 2/10 2/15date/time

Mai

n br

eake

r, kW

BEFORE

AFTER

DASH™ software started

7 May 09 13Environmental Energy Technologies Division

CRAH Power reduction:

0

10

20

30

40

50

60

A B C D E FTime Interval

mai

n br

eake

r kW flo

or ti

le c

hang

es

VFD

s

cont

rol s

oftw

are

hot a

isle

isol

atio

n

rack

bla

nks

7 May 09 14Environmental Energy Technologies Division

Cost-Benefit analysis:

• Total project cost-benefit• Cost: $134,057• Savings: $42,772• Payback: 3.1 years

• DASH cost-benefit (sensors and software)• Cost: $56,824• Savings: $30,564• Payback: 1.9 years

7 May 09 15Environmental Energy Technologies Division

Lessons learned:

• Controls and software eliminated 59.6% of fan energy and 13.6% of chilled-water use from baseline.

• Re-arranging floor tiles reduced chilled water use and made cold-aisle temperatures more uniform.

• VFDs reduced CRAH electrical energy use and further reduced chilled water use.

• Isolation enabled higher return air temperatures, increasing CRAH capacity.

• Wireless reliability was 99.999% (only 81 packets lost out of nearly 10 million sent).

7 May 09 16Environmental Energy Technologies Division

Closing Remarks:Suggested next steps… Continue optimization of control and sensor

installations.

Scrutinize floor tile re-arrangement benefits.

Evaluate higher chilled-water temperature to save energy.

Consider introducing outside air to cool data centers.

Turn Off Lights in your data center!

7 May 09 17Environmental Energy Technologies Division

Real improvements; No waiting; Let’s do it!

Readily available…

Applicable throughout California…

Short payback periods; 3 to 5 years...

Creates jobs…

Saves energy and the environment…

7 May 09 18Environmental Energy Technologies Division

Questions?

7 May 09 19Environmental Energy Technologies Division

For More Information

Bill Tschudi, [email protected]

http://hightech.lbl.gov/datacenters.html

Geoffrey C. Bell, [email protected]

Cliff Federspiel, Ph.D., [email protected]