Upload
truongtruc
View
280
Download
3
Embed Size (px)
Citation preview
Chapter 6
Transmission System Analysis
Chapter 6. Transmission System Analysis
6-1
Chapter 6. Transmission System Analysis
6.1. Purpose of the System Analysis The capacity of a power system to transmit electricity has limitations depending on the design of equipment and system condition. If the implementation of an electrification project, with the maximum power load at local level exceeds the system capacity of that area, then reinforcement of transmission system is inevitable and its cost should be added to the cost of the electrification project. This is why the analysis of the capacity of local network systems, i.e. the capacity of each substation, needs to be carried out for an electrification study.
In this section, the capacity of the transmission system and possible bottlenecks are studied.
6.2. Current Status of the Power Transmission System in Zambia The main characteristics of ZESCO’s power transmission system are as follows.
ZESCO’s transmission system has various voltage levels, namely 330kV, 220kV, 132kV, 88kV and 66kV. These voltage levels are stepped-down to 33kV and 11kV for distribution at substations.
ZESCO’s power system is interconnected to that of neighbouring countries as part of the Southern African Power Pool (SAPP). SAPP consists of power systems in southern African countries, namely Angola, Botswana, Democratic Republic of Congo, Lesotho, Malawi, Mozambique, Namibia, Republic of South Africa, Swaziland, Tanzania, Zambia and Zimbabwe, though actually some of these countries are not interconnected yet.
The main 330kV transmission lines are running north to south in the middle of the country because the copper mines, the largest load centre, are located in the north and the main generation stations are located in the south. The electricity generation mostly comes from three hydro power plants located in southern area of Zambia, thus the main power flow is streaming from south to north.
Copperbelt Energy Corporation (CEC) has some transmission lines, substations and generators to supply electricity to the copper mines. CEC’s transmission system also has interconnection with DR Congo to wheel power export from DR Congo to Zimbabwe and South Africa.
66kV transmission lines are used for local supply. In North-Eastern and Western areas, the span of 66kV lines is in general very long.
Figure 6-1 illustrates the diagram of transmission system in Zambia as of 2006, most of which is owned and operated by ZESCO. The list of 330kV – 88kV transmission lines and that of 66kV line are shown in Table 6-1 and Table 6-2 respectively. According to the statistic data of ZESCO, total circuit length of 330kV transmission lines is 2,241km, total 220kV lines 348km, total 132kV lines 202km, total 88kV lines 754km and total 66kV lines 3,033km as at the end of March 2006. In addition, CEC also has transmission lines whose total length is 808km. Transmission system of ZESCO, as part of SAPP, has interconnection with DR Congo, Zimbabwe and Namibia in the south, and is also used for international power trade.
Chapter 6. Transmission System Analysis
6-2
Figure 6-1 Transmission System Diagram of Zambia as of 2006
Chapter 6. Transmission System Analysis
6-3
Table 6-1 Transmission Lines of ZESCO as of June 2006 (330kV – 88kV)
Voltage (kV) Line (from – to) Conductor No. of
Circuits Route Length
(km)
330 Kabwe – Pensulo 2xACSR381, Bison 1 300 Kabwe – Luano 2xACSR381, Bison 2 252
Kabwe – Kitwe 2xACSR381, Bison 2 212
Kariba North – Leopards Hill 2xACSR381, Bison 2 123
Leopards Hill – Kabwe 2xACSR381, Bison 3 97
Kafue West – Lusaka West 2xACSR381, Bison 1 42
Leopards Hill – Kafue West 2xACSR381, Bison 1 53
Kafue Gorge – Leopards Hill 2xACSR381, Bison 2 47
Kafue Gorge – Kafue West 2xACSR381, Bison 1 42
Kitwe – Luano 2xACSR381, Bison 1 40
Kafue Town – Kafue West 2xACSR381, Bison 1 3
Kariba North – Zimbabwe Border 2xACSR381, Bison 2 1
220 Muzuma – Kafue Town 1xACSR381, Bison 1 189
Victoria Falls – Muzuma 1xACSR381, Bison 1 159
132 Lusiwasi – Msoro 1xACSR158, Wolf 1 115
Leopards Hill – Coventry 1xACSR100, Dog 1 29
Lusaka West – Roma 1xACSR158, Wolf 1 20
Roma – Leopards Hill 1xACSR158, Wolf 1 26
Lusaka West – Coventry 1xACSR158, Wolf 1 11
88 Leopards Hill – Kafue Town 1xACSR158, Wolf 1 62
Kapiri – Mpongwe 1xACSR158, Wolf 1 96
Figtree – Kabwe 1xACSR158, Wolf 1 56
Leopards Hill – Figtree 1xACSR158, Wolf 1 55
Leopards Hill – Chirundu 1xACSR100, Dog 1 80
Napundwe – Mumbwa 1xACSR100, Dog 1 90
Kafue Town – Napundwe 1xACSR100, Dog 1 46
Leopards Hill – Water Works 1xACSR100, Dog 1 22
Kafue Town – Mazabuka 1xACSR100, Dog 1 40
Muzuma – Maamba 1xACSR100, Dog 1 30
Kabwe Step Down – Kapiri Mposhi 1xACSR100, Dog 1 98
Leopards Hill – Mapepe 1xACSR158, Wolf 1 29
Leopards Hill – Coventry 1xACSR100, Dog 1 28
Kabwe Step Down – Kabwe Town 1xACSR100, Dog 1 24
Kafue Town – Mapepe 1xACSR158, Wolf 1 33
Source: ZESCO Statistic Data 2005/06
Chapter 6. Transmission System Analysis
6-4
Table 6-2 Transmission lines of ZESCO as of June 2006 (66kV)
Voltage (kV) Line (from – to) Conductor No. of
Circuits Route Length
(km)
66 Katima Mulilo – Senanga 1xACSR100, Dog 1 212 Kasama – Mpika 1xACSR158, Wolf 1 211
Luano – Solwezi 1xACSR131, Tiger 1 189
Chinsali – Mpika 1xACSR158, Wolf 1 179
Kasama – Mbala 1xACSR158, Wolf 1 161
Kawambwa – Mporokoso 1xACSR158, Wolf 1 142
Chabasitu tee – Luwingu 1xACSR158, Wolf 1 123
Lusiwasi – Msoro 1xACSR158, Wolf 1 115
Kazungula – Sesheke 1xACSR100, Dog 1 108
Isoka – Nakonde 1xACSR158, Wolf 1 107
Mongu – Senanga 1xACSR100, Dog 1 105
Lubushi – Luwingu 1xACSR158, Wolf 1 100
Chilonga – Mununga 1xACSR158, Wolf 1 100
Lusiwasi – Pensulo 1xACSR158, Wolf 1 90
Chinsali – Isoka 1xACSR158, Wolf 1 82
Chipata – Msoro 1xACSR100, Dog 1 80
Victoria Falls – Kazungula 1xACSR100, Dog 1 80
Pensulo – Mununga 1xACSR158, Wolf 1 75
Chambasitu Tee – Kawambwa 1xACSR158, Wolf 1 71
Kasama – Lubushi 1xACSR158, Wolf 1 70
Kalabo – Mongu 1xACSR100, Dog 1 66
Msoro – Mfuwe 1xACSR100, Dog 1 65
Msoro – Azele 1xACSR100, Dog 1 55
Lusiwasi – Kaombe 1xACSR158, Wolf 1 50
Pensulo – Serenje 1xACSR158, Wolf 1 43
Musonda Falls – Chambasitu Tee 1xACSR158, Wolf 1 40
Chishimba Falls – Kasama 1xACSR100, Dog 1 30
Mpika – Chilonga 1xACSR158, Wolf 1 22
Kanona – Kaombe 1xACSR158, Wolf 1 21
Kanona – Chinese Rd 1xACSR158, Wolf 1 19
Sesheke – Katima Mulilo 1xACSR100, Dog 1 8
Pensulo – Chinese Rd 1xACSR158, Wolf 1 1
Mongu – Kaoma 1xACSR158, Wolf 1 195
Source: ZESCO Statistics data 2005/06
Chapter 6. Transmission System Analysis
6-5
Table 6-3 Transformers of ZESCO Substations as of 2006
Substation Transformer Capacity [MVA] Voltages [kV]
Leopards Hill 2 x125 330/132 2 x 90 330/ 88
Kafue Town 1 x 60 330/ 88
2 x 60 220/ 88
Kabwe 2 x 60 330/ 88
Kitwe 6 x120 330/220
6 x 60 220/ 66
Luano 4 x120 330/220
Pensulo 2 x 60 330/ 66
Source: ZESCO Statistics Data 2005/06
6.3. Reinforcement Plan of Transmission System in Zambia Transmission System Development Plan, which was provided by the Transmission System Planning Department of ZESCO, is listed in Table 6-4 . Diagrams of projected transmission system in 2010, 2015, 2020 and 2030 respectively are shown in Figures from Figure 6-2 to Figure 6-5
Chapter 6. Transmission System Analysis
6-6
Table 6-4 ZESCO’s Existing Transmission Development Plan
Voltage From-To Commissioning year No. of circuits Notes
330 Kansanshi – Lumwana 2007 1 New installation
Pensulo – Kasama 2009 2 New installation
Kasama – (Tanzania) 2009 2 New installation
Kafue Town – Muzuma 2010 1 Upgrade
Muzuma – Victoria Falls 2010 1 Upgrade
Victoria Falls – Katimamulilo 2010 1 Upgrade
Katimamulilo – (Namibia) 2010 1 Upgrade
Muzuma – Itezhi-Tezhi 2010 1 Upgrade
Victoria Falls – (Zimbabwe) 2010 1 New installation
Lumwana – (DR Congo) 2010 1 New installation
Kabwe – Pensulo 2011 1 2nd circuit
Pensulo – Lusiwasi 2020 1 New installation
Lusiwasi – Msoro 2020 1 New installation
Msoro – (Malawi) 2030 1 New installation
220 Victoria Falls – Katima Mulilo 2006 1 New installation
Katima Mulilo – (Namibia) 2006 1 New installation
Luano – Michelo 2008 1 2nd circuit
Michelo – (DR Congo) 2008 1 2nd circuit
Muzuma – Itezhi-Tezhi 2009 1 New installation
132 Katima Mulilo – Senanga 2008 1 Upgrade
Senanga – Mongu 2008 1 Upgrade
Leopards Hill – Chirundu 2030 1 New installation
66 Serenje – Mkushi 2007 1 New installation
Kasempa – Mufumbwe 2008 1 New installation
Mongu – Lukulu 2020 1 New installation
Lukulu – Kabonpo 2020 1 New installation
Lukulu – Zambezi 2020 1 New installation
Zambezi – Chavuma 2020 1 New installation
Lumwana - Mwinilunga 2030 1 New installation
Source: ZESCO
Chapter 6. Transmission System Analysis
6-7
Figure 6-2 Transmission System Diagram of Zambia as of 2010
Chapter 6. Transmission System Analysis
6-8
Figure 6-3 Transmission System Diagram of Zambia as of 2015
Chapter 6. Transmission System Analysis
6-9
Figure 6-4 Transmission System Diagram of Zambia as of 2020
Chapter 6. Transmission System Analysis
6-10
Figure 6-5 Transmission System Diagram of Zambia as of 2030
Chapter 6. Transmission System Analysis
6-11
6.4. Analysis of the Capacity of Transmission System There are two options of rural electrification, i.e. national grid extension and off-grid electrification, and regarding the first option, which is the topic of this section, it is necessary to take into account the effect of an electrification project on the capacity of power system such as substations and transmission lines. As already explained in Section 6.1. , if the maximum power load at local level is expected to exceed the facilities’ capacity, reinforcement of the system should be considered as a part of the electrification project.
In this section, the capacity of the transmission system is analysed by using a simulation model. The main objective of this analysis is to identify the capacity of transmission system, especially regarding substations, which can be specified as follows, and the bottlenecks in the system, taking into account the demand growth and the system development plan.
Remaining capacity of source substations that can be used for the local supply system from bulk power transmission system (blue coloured circle in image diagram)
Remaining capacity of end substation that can be used for local supply system (red coloured circle in image diagram)
Figure 6-6 is the image diagram of remaining availability for electrification projects.
6.4.1. Assumptions of the Analysis
(1) Methodology
The methodology to grasp the system’s capacity takes the following steps. First, the base scenario of the power system in the future is considered based on the business as usual (BAU) case power demand projection (that is, additional rural electrification projects are not considered) and the system reinforcement already planned by ZESCO. Then, the power flow and the voltage in the system are simulated repeatedly by gradually increasing the local load of a particular area. And finally each substation’s remaining availability for electrification projects is determined at the level just below the point where the calculation cannot be converged due to the system’s overload or voltage instability. When we find that some system reinforcement is necessary even in the base scenario but that no information regarding the reinforcement has been given by ZESCO, we assume that an appropriate reinforcement shall be done, which is included additionally in the base scenario. This simulation model also assumes that the installation of capacitors, which is necessary for keeping the system voltage stable to meet the demand growth, shall be done properly. Although it is said that 88kV is not standard voltage level in Zambia, 88kV existing and planning facilities are took into consideration in system analysis. And the necessary reinforcement in the base scenario of each simulation period is the same as existing one even 88kV system, which is the simplest method. The details should be considered in transmission system master plan.
(2) Simulation periods
Year 2010, 2015, 2020, and 2030
(3) Power demand
The simulation model uses the projection of annual peak demand that is supposed to be possibly the highest so that the tight supply-demand balance is assumed even without electrification projects. The peak demand up to 2013 is based on ZESCO’s forecast. Peak demand beyond 2013, i.e. between 2014 and 2030, is projected by the Study Team, assuming that 3% p.a. growth rate for the last five years in ZESCO’s projection (from 2008 to 2013) continues. The annual peak demand used for this analysis is summarized in Table 6-5 . Generation development plan, shown in Table 6-6, is also included in the base scenario.
Chapter 6. Transmission System Analysis
6-12
Table 6-5 Projection of Peak Demand in Zambia
Year 2006 2010 2015 2020 2030
Peak demand [MW] 1,404 1,818 2,108 2,448 3,295 Average annual growth rate – 6.7% 3.0% 3.0% 3.0%
Table 6-6 Generation Development Plan of ZESCO
Power Station Unit No. Capacity [MW] Commissioning Year Notes
Kafue Gorge 1,2 150 165 2007 Rehabilitation Kafue Gorge 3,4 150 165 2006 Rehabilitation Kafue Gorge 5,6 150 165 2008 Rehabilitation Kariba North 1,2 150 180 2006 Rehabilitation Kariba North 3,4 150 180 2009 Rehabilitation Itezhi-Tezhi 1 120 2009 New installation Kariba North 5 360 2009 Extension Kafue Gorge Lower 1 750 2011 New installation Kalungwishi 1 220 2015 New installation Lusiwasi 1,2,3,4 3 15.5 2015 Rehabilitation Musonda Falls 1 5 7.5 2015 Rehabilitation Chishimba Falls 1 6 9.6 2015 Rehabilitation Lunzua 1 0.75 4.4 2015 Rehabilitation Source: ZESCO
(4) Power trade with neighbouring countries through interconnection line
The following Table 6-7 is the assumption of power export/import through interconnection lines. These numbers are provided to the Study Team by ZESCO.
Table 6-7 Trading Power of Interconnection Line with Neighboring Countries
Country Voltage Substation in Zambia Commissioning Year Target Power Flow
D.R.Congo 220 Michelo Existing (reinforced in 2008) 200MW inflow
D.R.Congo 330 Lumwana 2010 500MW inflow Tanzania 330 Kasama 2009 200MW outflow Zimbabwe 330 Kariba north Existing 200MW outflow Zimbabwe 330 Victoria Falls 2010 100MW outflow Namibia 330 (220) Katima Mulilo 2010 (2006) 200MW outflow Malawi 330 Msoro 2030 100MW outflow
(5) Power system analysis software
PSS/E is employed for the study, which is also the software that ZESCO uses for system planning and analysis.
Chapter 6 Transmission System Analysis
6-13
Figure 6-6 Image Diagram of Remaining Availability for Electrification Projects
: Electrification area from source substation of 88,66kV system (Image) : Electrification area from end substation of 88,66kV system (Image)
Chapter 6. Transmission System Analysis
6-14
6.4.2. Transmission System as of 2010
Transmission system diagram as of 2010 is shown in Figure 6-2 . The list of reinforcement of substations necessary to be done by 2010 is shown in Table 6-8 and that of transmission lines are shown in Table 6-9 These reinforcements are considered in the base scenario in addition to the reinforcement projects already planned by ZESCO (refer to Table 6-4 The demand growth and power development plan up to 2010 are considered as explained in “(1) Assumptions of the Analysis”. This simulation model assumes that the installation of capacitors is done properly to keep the system voltage stable.
Power flow diagram of the base scenario as of 2010 is shown in Figure 6-7 Table 6-10 shows the remaining availability that can be used for electrification projects, as well as the maximum capacity of each local substation in the base scenario, which is shown in Figure 6-8 as image diagram.
Table 6-8 Additional Necessary Reinforcement of Substations by 2010
Substation Reinforcement (Objective)
Lusaka West Install one more unit of 330/132kV Transformer (Overload prevention) Michelo Install one more unit of 220/66kV Transformer (Overload prevention) Kabwe Install one more unit of 88/66kV Transformer (Overload prevention)
Table 6-9 Additional Necessary Reinforcement of Transmission Lines by 2010
Transmission Line Reinforcement (Objective)
132kV Leopards Hill – Coventry (Leopards Hill 132kV system) Install one more circuit (Overload prevention)
132kV Leopards Hill – Roma (Leopards Hill 132kV system) Install one more circuit (Overload prevention)
88kV Leopards Hill – Waterworks (Leopards Hill 88kV system) Install one more circuit (Overload prevention)
66kV Maposa - Dolahill (Maposa 66kV system) Install one more circuit (Overload prevention)
66kV Ndola - Dolahill (Maposa 66kV system) Install one more circuit (Overload prevention)
66kV Pensulo - Serenje (Pensulo 66kV system) Install one more circuit (Overload prevention)
Chapter 6. Transmission System Analysis
6-15
Table 6-10 Maximum Transmitting Capacity of each Substation as of 2010
Substation Peak
Demand [MW]
Remaining Availability
[MW]
Maximum Capacity
[MW] Bottlenecks
System source substations of 88kV and 66kV Kasama 66kV 16 65 81 Overload (Kasama 330/66kV Tr) Pensulo 66kV 58 60 118 Overload (Pensulo 330/66kV Tr) Michelo 66kV 96 60 156 Overload (Michelo 220/66kV Tr) Luano 66kV 245 40 285 Overload (66kV Michelo–Bancroft Line) Kansuswa 66kV 177 45 222 Overload (Kansuswa 330/66kV Tr) Kitwe 66kV 229 25 254 Overload (Kitwe 220/66kV Tr) Maposa 66kV 248 50 298 Overload (Maposa 330/66kV Tr) Kabwe 66kV 17 8 25 Overload (Kabwe 88/66kV Tr) Kabwe 88kV 64 35 99 Overload (Kabwe 330/88kV Tr) Leopards Hill 88kV 141 40 181 Overload (Leopards Hill 330/88kV Tr) Kafue Town 88kV 72 45 117 Overload (Kafue Town 330/88kV Tr) Muzuma 88kV 16 40 56 Overload (Muzuma 330/88kV Tr) Victoria Falls 33kV 0 75 75 Overload (330kV Muzuma–Victoria Falls Line)Victoria Falls 66kV 9 2 11 Overload (Victoria Falls 33/66kV Tr) Katimamulilo 66kV 1 50 * 51 Overload (Katimamulilo 330/66kV Tr) Mongu 66kV 6 40 * 46 Overload (Mongu 132/66kV Tr)
System end substations of 88kV and 66kV Mbala 66kV 5 20 25 Overload (66kV Kasama-Mbala Line) Mporokoso 66kV 1 5 6 Voltage instability Mansa 66kV 4 5 9 Voltage instability Nakonde 66kV 1 5 6 Voltage instability Mfuwe 66kV 1 15 16 Voltage instability Chipata 66kV 8 10 18 Voltage instability Azele 66kV 2 15 17 Voltage instability Mufumbwe 66kV 3 2 5 Voltage instability Kasempa 66kV 4 1 5 Voltage instability Mumbwa 88kV 0 25 25 Overload (88kV Nampundwe–Mumbwa Line) Kaoma 66kV 3 10 13 Voltage instability Kalabo 66kV 1 25 * 26 Overload (66kV Mongu–Kalabo Line)
Note: * These are calculated based on the assumption that Victoria Falls 33/66kV transformers, which are to be overloaded as a result of loop power flow balancing when the system load at 66kV level becomes high, shall be isolated.
Chapter 6. Transmission System Analysis
6-16
Figure 6-7 Power Flow Diagram of the Base Scenario as of 2010
Chapter 6 Transmission System Analysis
6-17
Figure 6-8 Image Diagram of Remaining Availability for Electrification Projects in 2010
: Electrification area from source substationof 88,66kV system (Image) : Electrification area from end substation of 88,66kV system (Image)
+65MW
+60MW
+60MW +40MW
+25MW
+50MW
+35MW
+40MW
+45MW
+40MW +75MW +50MW
+40MW
+20MW
+5MW
+5MW
+5MW
+15MW
+10MW
+15MW
+2MW
+1MW
+25MW +10MW +25MW
+10MW : Additional power that can be electrified
(5MW) : Base load in 2010
(58MW)
(16MW)
(96MW)
+45MW (245MW)
(177MW)
(229MW)
(248MW)
(64MW)
(141MW)
(72MW)
(16MW) (0MW) (1MW)
(6MW)
(1MW) (3MW) (0MW)
(4MW)
(3MW)
(2MW)
(8MW)
(1MW)
(1MW)
(1MW)
(5MW)
(4MW)
Chapter 6. Transmission System Analysis
6-18
6.4.3. Transmission System in 2015
Transmission system diagram in 2015 is shown in Figure 6-3 The list of reinforcement of substations necessary to be done by 2015 is shown in Table 6-11 and that of transmission lines are shown in Table 6-12 These reinforcements are considered in the base scenario in addition to the reinforcement projects already planned by ZESCO (refer to Table 6-4 The demand growth and power development plan up to 2015 are considered as explained in “(1) Assumptions of the Analysis”. This simulation model assumes that the installation of capacitors is done properly to keep the system voltage stable.
Power flow diagram of the base scenario as of 2015 is shown in Figure 6-9 Table 6-13 shows the remaining availability that can be used for electrification projects, as well as the maximum capacity of each local substation in the base scenario, which is shown in Figure 6-10 as image diagram.
Table 6-11 Additional Necessary Reinforcement of Substations by 2015
Substation Reinforcement (Objective)
Kitwe Install one more unit of 220/66kV Transformer (Overload prevention) Kansanshi Install one more unit of 330/33kV Transformer (Overload prevention)
Luano Install each one more unit of 330/33 & 220/66kV Transformers (Overload prevention)
Maposa Install one more unit of 220/66kV Transformer (Overload prevention)
Table 6-12 Additional Necessary Reinforcement of Transmission Lines by 2015
Transmission Line Reinforcement (Objective)
66kV Maposa - Ndola (Maposa 66kV system) Install one more circuit (Overload prevention)
66kV Stadium – Kabundi (Luano 66kV system) Install one more circuit (Overload prevention)
66kV Michelo – Bancroft (Michelo 66kV system) Install one more circuit (Overload prevention)
Chapter 6. Transmission System Analysis
6-19
Table 6-13 Maximum Transmitting Capacity of each Substation in 2015
Substation Peak
Demand [MW]
Remaining Availability
[MW]
Maximum Capacity
[MW] Bottlenecks
System source substations of 88kV and 66kV Kasama 66kV 16 60 76 Overload (Kasama 330/66kV Tr) Pensulo 66kV 49 65 114 Overload (Pensulo 330/66kV Tr) Michelo 66kV 109 30 139 Overload (Michelo 220/66kV Tr)
Luano 66kV 286 65 351 Overload (Luano 220/66kV Tr) [open BNCNT–BNCRF Line]
Kansuswa 66kV 206 35 241 Overload (Kansuswa 330/66kV Tr) Kitwe 66kV 308 30 338 Overload (Kitwe 220/66kV Tr) Maposa 66kV 414 60 474 Overload (Maposa 220/66kV Tr) Kabwe 66kV 19 5 24 Overload (Kabwe 88/66kV Tr) Kabwe 88kV 75 25 100 Overload (Kabwe 330/88kV Tr) Leopards Hill 88kV 161 15 176 Overload (Leopards Hill 330/88kV Tr) Kafue Town 88kV 85 30 115 Overload (Kafue Town 330/88kV Tr) Muzuma 88kV 19 35 54 Overload (Muzuma 330/88kV Tr) Victoria Falls 33kV 0 70 70 Overload (330kV Muzuma–Victoria Falls Line) Victoria Falls 66kV 10 1 11 Overload (Victoria Falls 33/66kV Tr) Katimamulilo 66kV 2 45 * 47 Overload (Katimamulilo 330/66kV Tr) Mongu 66kV 7 35 * 42 Overload (Mongu 132/66kV Tr)
System end substations of 88kV and 66kV Mbala 66kV 5 15 20 Voltage instability Mporokoso 66kV 1 5 6 Voltage instability Mansa 66kV 4 5 9 Voltage instability Nakonde 66kV 1 5 6 Voltage instability Mfuwe 66kV 1 15 16 Voltage instability Chipata 66kV 9 10 19 Voltage instability Azele 66kV 2 15 17 Voltage instability Mufumbwe 66kV 3 0 3 Voltage instability Kasempa 66kV 5 0 5 Voltage instability Mumbwa 88kV 0 20 20 Overload (Kafue Town 330/88kV Tr) Kaoma 66kV 3 5 8 Voltage instability Kalabo 66kV 1 20 * 21 Voltage instability
Note: * These are calculated based on the assumption that Victoria Falls 33/66kV transformers, which are to be overloaded as a result of loop power flow balancing when the system load at 66kV level becomes high, shall be isolated.
Chapter 6. Transmission System Analysis
6-20
Figure 6-9 Power Flow Diagram of the Base Scenario in 2015
Chapter 6 Transmission System Analysis
6-21
Figure 6-10 Image Diagram of Remaining Availability for Electrification Projects in 2015
: Electrification area from source substationof 88,66kV system (Image) : Electrification area from end substation of 88,66kV system (Image)
+10MW : Additional power that can be electrified
(5MW) : Base load in 2015
+60MW
+65MW
+30MW
+65MW +35MW
+30MW
+60MW
+25MW
+15MW
+30MW
+35MW +70MW +45MW
+35MW
+15MW
+5MW
+5MW
+5MW
+15MW
+10MW
+15MW
+0MW
+0MW
+20MW+5MW +20MW
(16MW)
(49MW)
(109MW)
(286MW)
(206MW)
(308MW)
(414MW)
(75MW)
(161MW)
(85MW)
(19MW) (0MW) (2MW)
(7MW)
(1MW) (3MW) (0MW)
(5MW)
(3MW)
(2MW)
(9MW)
(1MW)
(5MW)
(1MW)
(1MW)
(4MW)
Chapter 6. Transmission System Analysis
6-22
6.4.4. Transmission system in 2020
Transmission system diagram in 2020 is shown in Figure 6-4 The list of reinforcement of substations necessary to be done by 2020 is shown in Table 6-14 and that of transmission lines are shown in Table 6-15 These reinforcements are considered in the base scenario in addition to the reinforcement projects already planned by ZESCO (refer to Table 6-4 The demand growth and power development plan up to 2020 are considered as explained in “(1) Assumptions of the Analysis”. This simulation model assumes that the installation of capacitors is done properly to keep the system voltage stable.
Power flow diagram of the base scenario as of 2020 is shown in Figure 6-11 Table 6-16 shows the remaining availability that can be used for electrification projects, as well as the maximum capacity of each local substation in the base scenario, which is shown in Figure 6-12 as image diagram.
Table 6-14 Additional Necessary Reinforcement of Substations by 2020
Substation Reinforcement (Objective)
Kansanshi Install one more unit of 330/66kV transformer to connect between Solwezi 66kV system and Kansanshi 66kV system (Voltage instability prevention)
Leopards Hill Install one more unit of 330/132kV Transformer (Overload prevention)Leopards Hill Install one more unit of 330/88kV Transformer (Overload prevention) Kansuswa Install one more unit of 330/66kV Transformer (Overload prevention)
Table 6-15 Additional Necessary Reinforcement of Transmission Lines by 2020
Transmission Line Reinforcement (Objective)
66kV Kansanshi - Solwezi (Kansanshi 66kV system)
Connection of Kansanshi 66kV system and Solwezi 66kV system (Voltage instability prevention)
66kV Luano - Stadium (Luano 66kV system) Install one more circuit (Overload prevention)
66kV Serenje – Mkushi (Pensulo 66kV system) Install one more circuit (Voltage instability prevention)
66kV Kafue Town – Mazabuka (Kafue Town 88kV system) Install one more circuit (Overload prevention)
66kV Kansuswa – Kankoyo (Kansuswa 66kV system) Install one more circuit (Overload prevention)
66kV Maposa – Ndola (Maposa 66kV system) Install one more circuit (Overload prevention)
Chapter 6. Transmission System Analysis
6-23
Table 6-16 Maximum Transmitting Capacity of each Substation in 2020
Substation Peak
Demand [MW]
Remaining Availability
[MW]
Maximum Capacity
[MW] Bottlenecks
System source substations of 88kV and 66kV Kasama 66kV 21 55 76 Overload (Kasama 330/66kV Tr) Pensulo 66kV 50 75 125 Overload (Pensulo 330/66kV Tr) Msoro 66kV ** 4 50 54 Overload (Msoro 330/66kV Tr) Michelo 66kV 122 15 137 Overload (Michelo 220/66kV Tr)
Luano 66kV 308 45 353 Overload (Luano 220/66kV Tr) [open BNCNT–BNCRF Line]
Kansuswa 66kV 238 65 303 Overload (Kanauswa 330/66kV Tr) Kitwe 66kV 301 20 321 Overload (Kitwe 220/66kV Tr) Maposa 66kV 335 25 360 Overload (Maposa 220/66kV Tr) Kansanshi 66kV ** 25 35 60 Overload (Kansanshi 330/66kV Tr) Kabwe 66kV 23 1 24 Overload (Kabwe 88/66kV Tr) Kabwe 88kV 87 20 107 Overload (Kabwe 330/88kV Tr) Leopards Hill 88kV 192 60 252 Overload (Leopards Hill 330/88kV Tr) Kafue Town 88kV 90 20 110 Overload (Kafue Town 330/88kV Tr) Muzuma 88kV 22 30 52 Overload (Muzuma 330/88kV Tr) Victoria Falls 33kV 0 55 55 Overload (330kV Muzuma–Victoria Falls Line) Victoria Falls 66kV 10 0 10 Overload (Victoria Falls 33/66kV Tr) Katimamulilo 66kV 6 40 * 46 Overload (Katimamulilo 330/66kV Tr) Mongu 66kV 15 30 * 45 Overload (Mongu 132/66kV Tr)
System end substations of 88kV and 66kV Mbala 66kV 6 15 21 Voltage instability Mporokoso 66kV 1 5 6 Voltage instability Mansa 66kV 5 5 10 Voltage instability Nakonde 66kV 1 5 6 Voltage instability Mfuwe 66kV 1 20 21 Overload (66kV Msoro–Mfuwe Line) Chipata 66kV 11 10 21 Overload (66kV Msoro–Chipata Line) Azele 66kV 2 20 22 Overload (66kV Msoro–Azele Line) Mufumbwe 66kV 4 5 9 Voltage instability Kasempa 66kV 5 10 15 Voltage instability Mumbwa 88kV 0 15 15 Overload (Kafue Town 330/88kV Tr) Kaoma 66kV 4 5 9 Voltage instability Kalabo 66kV 1 15 * 16 Voltage instability Kabompo 66kV 1 5 6 Voltage instability Chavuma 66kV 1 5 6 Voltage instability
Note: * These are calculated based on the assumption that Victoria Falls 33/66kV transformers, which are apt to be overloaded as a result of loop power flow balancing when the system load at 66kV level becomes high, shall be isolated.
** Newly installed substations
Chapter 6. Transmission System Analysis
6-24
Figure 6-11 Power Flow Diagram of the Base Scenario in 2020
Chapter 6 Transmission System Analysis
6-25
Figure 6-12 Image Diagram of Remaining Availability for Electrification Projects in 2020
+55MW
+75MW
+65MW
+45MW
+20MW
+25MW
+20MW
+60MW
+20MW
+30MW +55MW +40MW
+30MW
+15MW
+15MW +5MW +15MW
+20MW
+10MW
+20MW
+50MW
+35MW
+5MW
+10MW +5MW +5MW
(21MW)
(4MW)
(50MW)
+15MW (122MW)
(238MW)
(308MW)
(301MW)
(335MW)
(25MW)
(87MW)
(192MW)
(90MW)
(22MW) (0MW)
(15MW)
(6MW)
(1MW) (4MW)
(1MW)
(4MW)
(1MW) (5MW)
(0MW)
(2MW)
(11MW)
(1MW)
(1MW)
(6MW) (1MW)
(5MW)
+5MW
+5MW
+5MW : Electrification area from source substation of 88,66kV system (Image) : Electrification area from end substation of 88,66kV system (Image)
+10MW : Additional power that can be electrified
(5MW) : Base load in 2020
Chapter 6. Transmission System Analysis
6-26
6.4.5. Transmission System in 2030
Transmission system diagram in 2030 is shown in Figure 6-5 The list of reinforcement of substations necessary to be done by 2030 is shown in Table 6-17 and that of transmission lines are shown in Table 6-18 These reinforcements are considered in the base scenario in addition to the reinforcement projects already planned by ZESCO (refer to Table 6-4 The demand growth and power development plan up to 2030 are considered as explained in “(1) Assumptions of the Analysis”. This simulation model assumes that the installation of capacitors is done properly to keep the system voltage stable.
Power flow diagram of the base scenario as of 2030 is shown in Figure 6-13 Table 6-19 shows the remaining availability that can be used for electrification projects, as well as the maximum capacity of each local substation in the base scenario, which is shown in Figure 6-14 as image diagram.
Table 6-17 Additional Necessary Reinforcement of Substations by 2030
Substation Reinforcement (Objective) Maposa Install one more unit of 220/66kV Transformer (Overload prevention) Kitwe Install three more units of 330/220kV Transformer (Overload prevention)Kitwe Install two more units of 220/66kV Transformer (Overload prevention) Kabwe Install one more unit of 330/88kV Transformer (Overload prevention) Kabwe Install one more unit of 88/66kV Transformer (Overload prevention) Kansanshi Install one more unit of 330/33kV Transformer (Overload prevention) Luano Install one more unit of 330/220kV Transformer (Overload prevention) Luano Install two more units of 220/66kV Transformer (Overload prevention) Maposa Install one more unit of 220/66kV Transformer (Overload prevention) Michelo Install one more unit of 220/66kV Transformer (Overload prevention) Kansuswa Install one more unit of 220/66kV Transformer (Overload prevention) Leopards Hill Install one more unit of 330/132kV Transformer (Overload prevention)
Table 6-18 Additional Necessary Reinforcement of Transmission Lines by 2030
Transmission line Reinforcement 66kV Maposa – Roan (Maposa 66kV system) Install one more circuit (Overload prevention) 66kV Irwin – Maclaren (Maposa 66kV system) Install one more circuit (Overload prevention) 66kV Maposa – Ndola (Maposa 66kV system) Install two more circuits (Overload prevention)66kV Skyways – Depot Road (Maposa 66kV system) Install one more circuit (Overload prevention) 66kV Dolahll – Pamodzi (Maposa 66kV system) Install one more circuit (Overload prevention) 66kV Maposa – Balub (Maposa 66kV system) Install one more circuit (Overload prevention) 66kV Skyways – Ndola (Maposa 66kV system) Install one more circuit (Overload prevention) 66kV Kitwe – Scaw Mill (Kitwe 66kV system) Install one more circuit (Overload prevention) 66kV Mindolo – Chibuluma (Kitwe 66kV system) Install one more circuit (Overload prevention) 132kV Lusaka West – Coventry (Leopards Hill 132kV system) Install one more circuit (Overload prevention) 132kV Leopards Hill – Roma (Leopards Hill 132kV system) Install one more circuit (Overload prevention) 88kV Leopards Hill – Waterworks (Leopards Hill 88kV system) Install one more circuit (Overload prevention) 66kV Luano – Kabundi (Luano 66kV system) Install one more circuit (Overload prevention) 66kV BNCNT – BNCRF (Michelo 66kV system) Install one more circuit (Overload prevention) 66kV Luano – Stadium (Luano Michelo 66kV system) Install one more circuit (Overload prevention) 66kV Kansuswa – Kankoyo (Kansuswa 66kV system) Install one more circuit (Overload prevention) 66kV Kankoyo – Mufulira (Kansuswa 66kV system) Install one more circuit (Overload prevention)
Chapter 6. Transmission System Analysis
6-27
Table 6-19 Maximum Transmitting Capacity of each Substation in 2030
Substation Peak
Demand [MW]
Remaining Availability
[MW]
Maximum Capacity
[MW] Bottlenecks
System source substations of 88kV and 66kV Kasama 66kV 33 45 78 Overload (Kasama 330/66kV Tr) Pensulo 66kV 67 60 127 Overload (Pensulo 330/66kV Tr) Msoro 66kV ** 8 55 63 Overload (Msoro 330/66kV Tr) Michelo 66kV 174 30 204 Overload (Michelo 220/66kV Tr) Luano 66kV 404 55 459 Overload (Luano 220/66kV Tr) Kansuswa 66kV 320 65 385 Overload (Kansuswa 330/66kV Tr) Kitwe 66kV 399 45 444 Overload (Kitwe 220/66kV Tr) Maposa 66kV 449 60 509 Overload (Maposa 220/66kV Tr) Kansanshi 66kV ** 32 20 52 Overload (Kansanshi 330/66kV Tr) Kabwe 66kV 20 4 24 Overload (Kabwe 88/66kV Tr) Kabwe 88kV 119 35 154 Overload (Kabwe 330/88kV Tr) Leopards Hill 88kV 243 20 263 Overload (Leopards Hill 330/88kV Tr) Kafue Town 88kV 135 35 170 Overload (Kafue Town 330/88kV Tr) Muzuma 88kV 29 20 49 Overload (Muzuma 330/88kV Tr) Victoria Falls 33kV 0 40 40 Overload (330kV Muzuma–Victoria Falls Line)Victoria Falls 66kV 12 4 16 Overload (Victoria Falls 33/66kV Tr) Katimamulilo 66kV 8 35 43 Overload (330kV Muzuma–Victoria Falls Line)Mongu 66kV 15 25 40 Overload (330kV Muzuma–Victoria Falls Line)
System end substations of 88kV and 66kV Mbala 66kV 8 15 23 Voltage instability Mporokoso 66kV 1 3 4 Voltage instability Mansa 66kV 6 5 11 Voltage instability Nakonde 66kV 2 4 6 Voltage instability Mfuwe 66kV 2 20 22 Overload (66kV Msoro–Mfuwe Line) Chipata 66kV 15 5 20 Overload (66kV Msoro–Chipata Line) Azele 66kV 3 20 23 Overload (66kV Msoro–Azele Line) Mufumbwe 66kV 5 4 9 Voltage instability Kasempa 66kV 7 5 12 Voltage instability Mwinilunga 66kV ** 0 15 15 Voltage instability Mumbwa 88kV 0 25 25 Overload (Kafue Town 330/88kV Tr) Chirundu 66kV ** 0 70 70 Overload (132kV Leopards Hill–Chirundu Line)Kaoma 66kV 5 5 10 Voltage instability Kalabo 66kV 1 15 16 Voltage instability Kabompo 66kV 1 5 6 Voltage instability Chavuma 66kV 2 3 5 Voltage instability
Note: ** Newly installed substations
Chapter 6. Transmission System Analysis
6-28
Figure 6-13 Power Flow Diagram of the Base Scenario in 2030
Chapter 6 Transmission System Analysis
6-29
Figure 6-14 Image Diagram of Remaining Availability for Electrification Projects asof 2030
: Electrification area from source substation of 88,66kV system (Image) : Electrification area from end substation of 88,66kV system (Image)
+10MW : Additional power that can be electrified
(5MW) : Base load in 2030
+45MW
+60MW
+55MW +65MW
+45MW
+60MW
+35MW
+20MW
+35MW
+20MW
+40MW
+35MW
+25MW
+15MW
+3MW
+5MW
+4MW
+25MW+5MW +15MW
+20MW
+5MW
+20MW
+55MW
+20MW
+4MW
+5MW +5MW +3MW
+30MW
+15MW
+70MW
(33MW)
(67MW)
(8MW)
(174MW)
(404MW)
(320MW)
(399MW)
(449MW)
(32MW)
(119MW)
(243MW)
(135MW)
(29MW)
(0MW)
(8MW)
(15MW)
(5MW)
(1MW)
(1MW)
(2MW)
(5MW)
(7MW)
(0MW)
(0MW) (0MW)
(3MW)
(15MW)
(2MW)
(6MW)
(1MW)
(8MW)
(2MW)
Chapter 6. Transmission System Analysis
6-30
6.4.6. Observations on the Simulation Results
In this section, the capacity of source substations and end substations in local network system at 88kV and 66kV, which are the main source of local power supply, was analysed. The capacity of substations that are placed between a source substation and an end substation is estimated to come in-between. The system’s remaining availability for electrification projects shall be referred to as basic data when considering electrification projects through grid extension.
The following features regarding Zambia’s transmission system are observed through the analysis.
Each source substation has in general around 20-70MW availability and each end substation has in general around 0-20MW availability for electrification projects.
The capacity of source substations in the local network system is in general determined by the restriction deriving from equipment capacity whereas the capacity of end substations is determined by the restriction deriving voltage instability.
Since the network system in the western region is underdeveloped and the transmission lines have a long span, the network system is vulnerable to voltage instability and its remaining availability is small. Implementation of large-scale electrification projects is not feasible without system reinforcement.
Since the network system in the northern region is also underdeveloped and the transmission lines have a long, implementation of large-scale electrification projects is not feasible without system reinforcement.
In general, the remaining availability for electrification projects becomes smaller as the power demand grows. However, this availability can be expanded with the implementation of the reinforcement of network system and the development of power stations. This possibility needs to be analysed in detail for each individual case.
Concerning the simulation model, the following issues should be paid attention to as important notice.
Since the simulation was executed on each individual case, the results may not be the same as what would happen in reality, where many electrification projects are implemented in parallel. The simulation with comprehensive analysis should be carried out after the list of candidate sites for electrification is finalized and the schedule of implementing electrification projects is determined.
If a candidate site for electrification is far from the existing grid, the availability of substations may be smaller than this simulation results due to the restriction of voltage instability. This effect should be analysed in detail after the list of candidate sites is finalized.
Chapter 7
Distribution System Planning
Chapter 7. Distribution System Planning
7-1
Chapter 7. Distribution System Planning
7.1. Current Status of Distribution System The distribution system in Zambia comprises the “interconnected system”, i.e. the main distribution network, which is connected to the national grid, and the “isolated system”, which is fed from stand-alone power stations (diesel or hydro) and is often called “off-grid” system. All the distribution system is owned and operated by ZESCO with some exceptions23. The distribution network reaches all of the 9 Provincial Centres and most of the 72 District Centres (BOMAs) countrywide, but the network is still too underdeveloped to cover the villages countrywide.
Distribution network is operated at 33kV and 11kV middle voltages and 400V/230 V low voltage. Total length of 33kV and 11kV lines is 2,245 km and 7,000 km respectively, and detailed facility data (type of support, type of conductor, location of facilities, etc) and operation data is not maintained. In addition, the statistics of 400V/230V lines are not available. Almost all the distribution lines are overhead wires, whereas underground cables are installed in some parts of town centres.
ZESCO has segmented the whole country in four (4) areas called “Divisions”, and Division Managers are responsible for the operation and maintenance of distribution lines in their respective area. Under the Divisions, there are 13 Regional Offices whose coverage area roughly corresponds to each Province24, and under Regional Offices are District Offices that are in charge of forefront operation and maintenance activities.
Table 7-1 ZESCO’s Operation and Maintenance Divisions
Headquarters Covering Area
Lusaka Division Lusaka • Lusaka province (except Luangwa District) • Mumbwa District of Central Province • Siavonga District of Southern Province
Copperbelt Division Kitwe • Luanshya, Kitwe, Kalulushi, Mufulira, Chingola & Chiliabombwe Districts of Copperbelt Province
Northern Division Ndola • Northern, Luapula & North-Western Provinces • Ndola, Lufwanyama, Masaiti & Mpongwe Districts25
of Copperbelt Province
Southern Division Lusaka • Southern Province (except Siavonga District) • Central Province (except Mumbwa District) • Western & Eastern Provinces
ZESCO has developed distribution network maps, some electronically and some manually, but since not all of them are complete and frequently updated, the JICA Study Team has prepared a map that
23 Small isolated power network with mini-hydro in remote area owned by private entities (refer to Section 3.3.2). 24 There are 4 Regional Offices in Lusaka Province and Copperbelt Province has Regional Offices in Kitwe and Ndola, which turns out to be “13 Regional Offices in 9 Provinces”. For technical reasons, the covering area of each Regional Office does not necessarily match the area of a Province (some Districts, where distribution lines are not extended from its Provincial centre but from another Province, are administrated by the Regional Office of that Province).
25 Lufwanyama, Masaiti & Mpongwe Districts used be a part of Ndola District (“Ndola-rural”). Some ZESCO documents still define “Ndola District” as including these four Districts.
Chapter 7. Distribution System Planning
7-2
covers the complete distribution network countrywide at 11kV and above, based on the information collected from ZESCO’s regional offices. GIS Software is used to compile the collected information electronically and to generate a map. The latest output of this GIS map is shown in Figure 13-2.
7.2. Data Collection The following sections discuss the data that have been collected so far from DoE, REA and ZESCO.
7.2.1. Specification of distribution system
Design standard of transmission and distribution system were developed in 1997, and consists of following items.
General Parameters Monitoring Trip Circuits Plant Control Multicore Cables in Substations System Earthing Instruments Control, & Relay Panel Wiring & Layout System Phasing & Switchgear Phase Marking Substation SLDs and Protection Schemes Design Philosophy Township Electrification
Allowable voltage and conductor sizes for overhead lines prescribed in this standard are as follows.
Table 7-2 ZESCO’s Standard on Overhead Distribution Lines
Allowable voltage: Between -5% to +5%
Conductor size: ACSR 100mm2, 200mm2 and 300mm2
7.2.2. Unit Cost of Equipment
The list of unit equipment cost provided by ZESCO was the one as of 2000 or 2003. For this Study, the Study Team shall adjust the costs taking into account the price escalation. The unit cost after adjustment is shown in Table 7-3.
Table 7-3 Unit Cost of Equipment
Item Unit Unit CostTransmission Line 66 kV Transmission Line US$/km 40,000
33 kV Distribution Line (including pole and accessories) US$/km 36,000Distribution Line 33/0.4kV Transformer on the pole (100kVA) US$/Unit 13,700
New substation (2.5MVA) US$/Unit 600,000New substation (5MVA) US$/Unit 800,000New substation (10MVA) US$/Unit 1,000,000New substation (15MVA) US$/Unit 1,300,000
66/33kV Substation
33 kV bay US$/Unit 99,300
Chapter 7. Distribution System Planning
7-3
7.2.3. Current Distribution Lines Extension Planning
The list of rural electrification projects to be executed in 2006 is shown in Table 3-2, which is publicized by Rural Electrification Authority (REA). All these projects, except for two micro-hydro projects in North-Western Province, deal with either distribution network extension or isolated network with diesel power plant, and are contracted ZESCO. The detailed scope of works of these projects is shown in Table 7-4.
Table 7-4 Rural Electrification Projects slated for 2006 and their Scope of Works
Project Scope of Works
Mungule’s Area-Mungule Clinic and Court and Mutakwa School, Chibombo (Phase I)
Constructing 13km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Installing 1 X 100kVA, 11/0.4kV pole mounted transformers substations. Installing 1 X 50kVA, 11/0.4kV pole mounted transformers substations. Constructing 1,630m of 50mm2 ACSR medium voltage overhead line. Providing 23 x standard single phase overhead service connections as follows:
a) One (1) for Chieftainess Mungule’s palace main house b) Three (3) Chieftainess Mungule’s palace, guest & families’ houses. c) One (1) Chieftainess Mungule’s Palace Courthouse. d) One (1) Chieftainess Mungule’s Retainer house. e) One (1) for Mungule’s court. f) Four (4) for Mungule’s courthouse. g) One (1) for Mungule’s clinic block. h) Six (6) for Mungule’s staff houses. i) Five (5) for Mutakwa school staff houses.
Providing 3 x standard single-phase underground service connections as follows. a) One (1) for Chieftainess Mungule’s palace borehole b) One (1) for Mungule Clinic borehole c) One (1) for Mutakwa School classroom blocks.
Carry out internal wiring of Chieftainess Mungule’s Palace, Mutakwa School and staff houses, Mungule clinic and staff houses and Mungule court and staff houses.
Mutombe Basic School, Mumbwa
Constructing 5km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Installing 1 X 50kVA, 11/0.4kV pole mounted transformers substations. Constructing 300m of 50mm2 ACSR medium voltage overhead line. Providing 8 x standard single-phase overhead service connections to staff houses. Providing 2 x standard three phase underground service connections to the classroom block and to the
school borehole. Nambala High School, Mumbwa
Constructing 15km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Installing 1 X 100kVA, 11/0.4kV pole mounted transformer substation. Constructing 800m of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Providing 16 X standard single-phase overhead service connections to staff houses for the school and
rural health centre. Providing 2 X standard three phase underground service connections for the school and rural health
centre.
Cen
tral P
rovi
nce
Serenje’s Area-Muzamene Basic School, Serenje
Tee-off through 20m of 66kV overhead line. Establishing a 100kVA, 66/0.4kV pole mounted transformer substation. Laying and connecting 30m of 70mm2 4core PVC medium voltage cable. Constructing 500m of medium voltage overhead line. Providing 1 x three-phase service connection to Chief Serenje’s palace. Carrying out internal wiring of Chief Serenje’s palace.
Lubendo Basic School, Masaiti
Constructing 4km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Installing 1 X 25kVA, 11/0.4kV pole mounted transformer substation. Laying & connecting 30m of 16mm2 4core PVC medium voltage cable. Providing 1 X standard three-phase underground service connection to Lubendo School. Providing 4 X standard single-phase overhead service connections to Lubendo school staff houses.
Cop
perb
elt P
rovi
nce
Mushili School, Masaiti
Constructing 8.1km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Installing 1 X 25kVA, 11/0.4kV pole mounted transformer. Providing eight standard single-phase overhead service connections.
Chapter 7. Distribution System Planning
7-4
Kabushi Township, Ndola (Phase I)
Reinforcing existing feeder by constructing 6km of 100mm2 ACSR 11kV overhead line from Mushili substation. Upgrading existing 1,110m of 25mm2 ACSR 11kV overhead line to 50mm2 ACSR three phase three-wire
11kV overhead lines. Upgrading existing 2 x 50kVA, 11/0.4kV and 3 X 100kVA to 200kVA, 11/0.4kV pole mounted transformer
substations. Constructing 6.5km additional total route length of 50mm2 ACSR three phase three-wire 11kV overhead
line within the township. Installing 25 X 200kVA, 11/0.4kV pole mounted transformer substations. Constructing 14.5km of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Laying and connecting a total of 540m of 120mm2 4-core PVC medium voltage cable. Providing 4500 X single-phase overhead services.
Kankoyo/Chibolya, Mufulira
Construction of 1.12km of 50mm2 ACSR, 11kV overhead line. Installation of 7 X 200kVA, 11/0.4kV pole mounted transformer substations. Laying and connecting a total of 320m of 185mm2 4-core PVC medium voltage cable. Construction of 7.6km of 100mm2 ACSR three phase four-wire medium voltage overhead lines. Providing 820 X standard single-phase services.
Mphamba Basic School, Lundazi
Construction of 1.2km of 50mm2 ACSR11kV overhead line. Installing a 50kVA, 11/0.4kV transformer. Constructing 600m of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Provision of 12 X single-phase overhead services. Laying and connecting a total of 320m of 185mm2 4-core PVC medium voltage cable.
Mtenguleni Areas-Katinta Basic School, Chipungu Rural Health Centre and Chankanga Basic School, Chipata
Constructing 8km of 100mm2 ACSR three phase three-wire 11kV overhead lines. Installing three sets of 11kV drop out fuses at the tee offs. Installing 2 X 100kVA, 11/0.4kV pole mounted transformers. Laying and connecting 120m of 70mm2 4-core PVC medium voltage cable from the pole mounted
transformers to the medium voltage lines (2 x 30m per transformer) Constructing a total of 2050m of 100mm2 ACSR three phase four-wire MV overhead lines. Providing 9 X standard single-phase overhead services as follows: 01 to the main arena, 01 school
block, 01 VCT building, 04 school staff houses and 02 Chief's structures. Ndake Area – Ndake Basic School, Ndake Court House and Ndake Rural Health Centre, Nyimba
Constructing 7.4km of 100mm2 ACSR three-phase, three wire, 11kV overhead line. Installing 100kVA, 11/0.4kV pole mounted transformer. Laying and connecting 30m of 70mm2 4core PVC medium voltage cable. Constructing 1220m of 100mm2 ACSR three-phase four-wire medium voltage overhead line. Providing 2 x standard underground services up to 15kVA to the palace and the school. Providing 13 x standard single-phase overhead services up to 15kVA to eleven (11) teachers' houses,
court building and court clerk's house.
Eas
tern
Pro
vinc
e
Lumezi, Lundazi Survey and pole peg of 35km, 33kV overhead line wayleave. Bush clear 35km of 33kV overhead line wayleave. Construct 35km of 50mm2 ACSR three phase three-wire 33kV overhead lines. Install 3 X sets 33kV drop out fuses. Lay and terminate 2 X 30m of 95mm2 3 core XLPE 33kV copper cables Install 2 X 500kVA, 33/0.4kV ground mounted transformers. Lay and terminate 2 X 40m of 185mm2 4Core PVC medium voltage cable. Install 1 X 6Way, 1200A feeder Pillar complete with earthing. Install 1 X 1500A kWh metering.
Lukwesa High School, Mwense
Constructing 700m of 50mm2 ACSR three phase three-wire 33kV overhead lines. Installing 1 X 25kVA, 33/0.4kV pole mounted transformer substation. Constructing 450m of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Providing 10 X standard single-phase overhead service connections to staff houses. Providing 1 X standard three-phase underground service connections to classroom block.
Bakashiwa Home Care, Kawambwa
Constructing 1.7km of 50mm2 ACSR three phase three-wire 33kV overhead lines. Installing 1 x 25kVA, 33/0.4kV pole mounted transformer substation. Laying and connecting 30m of 16mmsq 4-core PVC medium voltage cable. Providing 1 X standard single-phase underground service connection.
Luap
ula
Pro
vinc
e
Schools in Samfya (Nsengaila Basic School)
Constructing 50m of 50mm2 ACSR three phase three-wire 33kV overhead lines. Installing 1 X 25kVA, 33/0.4kV pole mounted transformer substation. Constructing 300m of 50mm2 three-phase four-wire medium voltage overhead line. Providing 6 X standard single-phase overhead service connections.
Chapter 7. Distribution System Planning
7-5
(Nshungu Basic School)
Constructing 400m of 50mm2 ACSR three phase three-wire 33kV overhead lines. Installing 1 X 25kVA, 33/0.4kV pole mounted transformer substation. Constructing 600m of 50mm2 three-phase four-wire medium voltage overhead line. Providing 5 X standard single-phase overhead service connections.
(Mashitolo Basic School)
Constructing 200m of 50mm2 ACSR three phase three-wire 33kV overhead lines. Installing 1 X 25kVA, 33/0.4kV pole mounted transformer. Constructing 400m of 50mm2 three-phase four-wire medium voltage overhead line. Providing 4 X standard single-phase overhead service connections.
(Mambilima Mwange Basic School)
Constructing 600m of 50mm2 ACSR three phase three-wire 33kV overhead lines. Installing 1 X 25kVA, 33/0.4kV pole mounted transformer substation. Constructing 400m of 50mm2 three-phase four-wire medium voltage overhead line. Providing 5 x standard single-phase overhead service connections. Constructing 200m of 50mm2 ACSR three phase three-wire 33kV overhead lines. Installing 1 X 25kVA, 33/0.4kV pole mounted transformer. Constructing 400m of 50mm2 three-phase four-wire medium voltage overhead line. Providing 4 X standard single-phase overhead service connections.
Schools in Kawambwa (Lubansa Basic School)
Constructing 400m of 50mm2 ACSR three phase three-wire 33kV overhead lines. Installing 1 X 25kVA, 33/0.4kV pole mounted transformers substations. Constructing 430m of 50mm2 three-phase four-wire medium voltage overhead line. Constructing 100m of 50mm2 single-phase two-wire low voltage overhead line. Providing 5 x standard single-phase overhead service connections. Providing 5 x ready boards.
(Kalasa Basic School)
Constructing 400m of 50mm2 ACSR three phase three-wire 11kV overhead lines. Constructing 150m of 50mm2 single-phase two-wire low voltage overhead line. Providing 8 x standard single-phase overhead service connections.
Chabilikila Middle Basic School, Nchelenge
Constructing 100m of 50mm2 ACSR three-phase three wire, 33kV overhead line. Installing 50kVA, 33/0.4kV pole mounted transformer. Laying and connecting 30m of 35mm2 4core PVC medium voltage cable. Constructing 400m of 50mm2 three-phase four-wire medium voltage overhead line. Providing 2 x standard single-phase overhead services up to the school.
Palabana Reinforcement of 24km of 50mm2 ACSR three phase three-wire 11kV line has been done in Palabana area. Material procurement is in progress for the remaining works.
Mupelekesi Area-Schools and Rural Health Centres
Constructing 48km of 50mm2 ACSR 3phase 3wire 11kV overhead line. Installing 5 X 50kVA, 11/0.4kV pole mounted transformer substations. Constructing 1380m of 50mm2 three-phase four-wire medium voltage overhead line. Providing a total of 5 X standard three phase overhead services to Mulola, Mpango, Mwapula and
Mupelekesi classroom blocks and Mpango clinic respectively. Providing a total of 24 x standard single-phase overhead services to Mulola, Mpango, Mwapula and
Mupelekesi schools and Mpango clinic staff houses.
Lusa
ka P
rovi
nce
Luangwa (Phase I)
Reinforcement and stabilization of power supply in Luangwa.
Schools in Solwezi (Kimiteto Primary School)
Constructing 600m of 50mm2 ACSR three phase three-wire 11kV overhead lines. Constructing 950m of 50mm22 ACSR three phase four-wire medium voltage overhead lines. Installing 1 X 25kVA, 11/0.4kV pole mounted transformer substation. Laying and connecting 30m of 35mm2 4core PVC medium voltage cable. Providing 11 X standard single-phase overhead services. Providing 1 X standard three phase overhead service. Carrying out internal wiring for Kimiteto Primary School and eleven (11) staff houses.
(Rodwell Mwepu Primary School)
Constructing 800m of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Providing 3 X standard single-phase overhead services. Providing 1 X standard three phase underground service. Carrying out internal wiring for Rodwell Mwepu Primary School and three (3) staff houses.
Nor
th- W
este
rn P
rovi
nce
(Kisalala Basic School)
Constructing 80m of 50mm2 ACSR three phase three-wire 11kV overhead lines. Constructing 1150m of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Installing 1 X 25kVA, 11/0.4kV pole mounted transformer substation. Laying and connecting 60m of 35mm2 4 core PVC medium voltage cable Providing 6 X standard single-phase overhead services. Providing 1 X standard three phase overhead service. Carrying out internal wiring for Kisalala School & six (6) staff houses.
Chapter 7. Distribution System Planning
7-6
(Tumvwana’nai Basic School)
Providing 1 standard single-phase overhead service. Carrying out internal wiring for Tumvwana’nai Basic School.
(Kapijimpanga Basic School)
Constructing 600m of 50mm2 ACSR three phase three-wire 11kV overhead lines. Constructing 500m of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Installing 1 X 25kVA, 11/0.4kV pole mounted transformer substation. Laying and connecting 30m of 35mm2 4core PVC medium voltage cable. Providing 9 X standard single-phase overhead services. Providing 1 X standard three phase overhead service. Carrying out internal wiring for Kapijimpanga Basic School and nine (9) staff houses.
(Kaimbwe School, Kasempa)
Constructing 12km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Establishing 1 X 50kVA, 11/0.4kV pole mounted transformer substation. Constructing 300m of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Providing 9 X single-phase overhead standard service connections. Providing 1 X three phase overhead standard service connection.
Chikwanda Basic School, Court House and Rural Health Centre, Mpika
Constructing 100m of 50mm2 ACSR three phase three-wire 11kV overhead lines. Establishing 1 X 25kVA, 11/0.4kV pole mounted transformer substation. Constructing 350m of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Providing 2 X single-phase overhead standard service connections to Chikwanda courthouse and Rural
Health Centre. Providing 2 X three phase underground standard service connection to Chikwanda’s palace and
Chikwanda Basic School. Carrying out internal wiring of the chief’s palace.
Luwingu High School Cooks Compound, Luwingu
Establishing 1 X 100kVA, 11/0.4kV pole mounted transformer substation. Construction of 950m of 50mm2 ACSR medium voltage overhead line. Providing 45 X single-phase service connections.
Saili Basic School, Luwingu
Construction of 600m of 50mm2 ACSR 11kV overhead line. Establishing 1 X 50kVA, 11/0.4kV pole mounted transformer substation. Construction of 500m of 50mm2 ACSR medium voltage overhead line. Providing 6 X single-phase service connections.
Connection of Kaputa District to the Grid (Phase I)
Construction of 125km of 100mm2 ACSR three phase wire 33kV overhead line from Mununga to Kaputa. Establishment of a 2.5MVA, 33/11kV substation at Kaputa and connecting to the existing 11kV network.
Waitwika’s Area, Nakonde
Constructing 8km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Establishing 1 X 25kVA, 11/0.4kV pole mounted transformer substation. Constructing 300m of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Providing 6 X single-phase overhead standard service connections to Chieftainess Waitwika’s palace. Providing 1 X three phase underground standard service connection to Chieftainess Waitwika’s palace. Carrying out internal wiring of six structures at chief Waitwika’s palace.
Mpumba Basic School And Court House, Mpika
Tee-off through 1.8km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Establishing 1 X 25kVA, 11/0.4kV pole mounted transformer substation. Constructing 700m of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Providing 7 X single-phase overhead standard service connections to Chief Mpumba, Mpumba Basic
School and courthouse. Carrying out internal wiring of six structures at Chief Mpumba’s palace.
Mulilansolo, Chinsali (Phase I)
Construction of 45km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Establishing 1 X 500kVA, 11/0.4kV ground mounted transformer substation. Construction of 1600m of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Providing 10 X single-phase service connections. Providing 1 X single-phase service connection.
Nor
ther
n P
rovi
nce
Chitimukulu Rural Health Centre, Police, Kapolyo Basic and Kanyanta Basic Schools, Kasama
Constructing 11.4km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Establishing 1 X 50kVA, 11/0.4kV pole mounted transformer substation. Constructing 400m of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Laying and connecting 60m of 35mm2 4-core PVC medium voltage cable. Providing 3 X single-phase overhead service connections to the Chiefs Chitimukulu’s palace. Providing 2 X single-phase overhead service connections to clinic staff houses. Providing 1 X three phase overhead service connection to the Clinic. Carrying out internal wiring for Chief Chitimukulu’s palace.
Chapter 7. Distribution System Planning
7-7
Kafwimbi Basic School and Rural Health Centre, Isoka
Constructing 15km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Establishing 1 X 50kVA, 11/0.4kV pole mounted transformer substation. Constructing 300m of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Laying and connecting 30m of 35mm2 4core PVC medium voltage cable. Providing 6 X single-phase overhead service connections to Chief Kafwimbi’s Palace, Basic school and
Rural Health Centre. Providing 2 X three phase overhead service connections to the Clinic and school. Carrying out internal wiring of six structures at the Chief’s palace.
Sianjalika Area–School and Rural Health Centre, Mazabuka
Construct 4.3km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Install 1X 25kVA, 11/0.4kV pole mounted transformer substation. Laying and connecting 16m of 35mm2 4core PVC medium voltage line. Providing 3 X three phase service connections to Chief Sianjalika’s Palace, school and Rural Health
Centre. Sikalongo Mission, Choma
Construct 21km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Install 1 X 25kVA, 11/0.4kV pole mounted transformer substation. Install 1 X 200kVA, 11/0.4kV pole mounted transformer substation. Construct 2450m of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Lay and connect 30m of 185mm2 PVC Medium voltage cable Lay and connect 60m of 35mm2 PVC Medium voltage cable. Providing 47 X service connections.
Mwanachingwala–School and Rural Health Centre, Mazabuka
Install 1 X 50kVA, 11/0.4kV pole mounted transformer substation. Laying and connecting 35m of 35mm2 4Core PVC medium voltage line. Constructing 430m of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Providing 3 X single-phase service connections to Chief Mwanachingwala’s palace. Providing 1 X three phase service connection to Chief Mwanachingwala’s Palace.
(Supply to Sianyolo’s Area, School and Rural Health Centre – Siavonga) Providing 16 X single-phase standard services & 1 X three phase standard service.
(Supply to Simamba’s Area and Rural Health Centre – Siavonga) Providing 12 X single-phase standard services.
(Supply to Sikongo’s Area and School – Siavonga) Providing 12 X single-phase standard services & 1 X three phase standard overhead service.
(Supply to Chipepo’s Area- Syakalyabanyama –Siavonga) Providing 16 X single-phase standard services & 1X three-phase standard overhead service.
Gwembe Tonga
(Supply to Chikanta’s Area And School – Kalomo) Providing 8 X standard single-phase overhead services& 1X three phase standard overhead service.
Schools in Mazabuka (Nansenga Basic School)
Constructing 100m of 50mm2 ACSR three phase three-wire 11kV overhead lines. Establishing 1X25kVA, 11/0.4kV pole mounted transformer substation. Constructing 250m of 50mm2 ACSR three phase three-wire medium voltage overhead lines. Providing 5 X single-phase overhead standard service connections.
(Mulawo Academic Production Unit (APU))
Constructing 2km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Establishing 1 X 25kVA, 11/0.4kV pole mounted transformer substation. Constructing 400m of 50mm2 ACSR three phase three-wire medium voltage overhead lines. Providing 5 X single-phase overhead standard service connections. Providing 1 X three phase overhead standard service connection
(Kaunga Basic School)
Constructing 2km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Establishing 1 X 25kVA, 11/0.4kV pole mounted transformer substation. Constructing 300m of 50mm2 ACSR three phase three-wire medium voltage overhead lines. Providing 5X single-phase overhead standard service connections. Providing 1 X three phase overhead standard service connection
(Malala Basic School)
Constructing 900m of 50mm2 ACSR three phase three-wire 11kV overhead lines. Establishing 1X25kVA, 11/0.4kV pole mounted transformer substation. Constructing 600m of 50mm2 ACSR three phase four-wire medium voltage overhead lines. Providing 9 X single-phase overhead standard service connections. Providing 1 X three phase overhead standard service connection
Sou
ther
n P
rovi
nce
Choongo’s Area –Ntema Basic School, Monze
Constructing 6.5 km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Installing 1 X 25kVA 11/0.4 kV pole mounted transformer substation. Constructing 1200m of 50mm2 three-phase four-wire medium voltage overhead line. Connecting 30m X 35mm2 4core PVC Medium voltage cable. Providing 2 X three phase standard overhead service connections to Chief Choongo’s area and Ntema
Basic School.
Chapter 7. Distribution System Planning
7-8
Shang’ombo District by Diesel Generators
Construction of the powerhouse building. Installation of 2 X 400kVA, 400V diesel generators. Establishing 2 X 400kVA, 0.4/11kV ground-mounted transformer substations. Construction of 4.6km of 50mm2 ACSR 3-phase 3-wire 11kV overhead line. Installing 2 X 100kVA, 11/0.4kV pole mounted transformer substations. Installing 3 X 50kVA, 11/0.4kV pole mounted transformer substations. Laying and connecting 4 X 30m of 70mm2 4core PVC medium voltage cable. Laying and connecting 4 X 30m of 35mm2 4core PVC medium voltage cable. Construction of 5,950m of 50mm2 ACSR medium voltage line. Provision of 102 X single-phase service connections. Provision of 6 X three phase service connections.
Luampa Mission Construction of part of 54km of 100mm2 ACSR 33kV overhead line. Kalabo Basic School & Kalabo Training Centre, Kalabo
Constructing 1.5km of 50mm2 ACSR three phase three-wire 11kV overhead lines. Installing 2 X 25kVA, 11/0.4kV pole mounted transformer substations. Constructing 800m of 50mm2 ACSR medium voltage overhead line. Providing 13 x standard single-phase overhead service connections to staff houses. Providing 2 X standard three phase underground service connections to classroom block at Kalabo Basic
School and Kalabo Farm Training Centre. Mwandi Basic School, Royal Court and Market, Sesheke
Installing 1 X 25kVA, 11/0.4kV pole mounted transformers substation. Constructing 700m of 50mm2 medium voltage overhead line. Providing 10 x standard single-phase overhead service connections to staff houses for school and court. Providing 1 x standard three phase underground service connections to classroom block at Mwandi
Basic School.
Wes
tern
Pro
vinc
e
Lukulu Refurbishment of generator set
Chapter 7. Distribution System Planning
7-9
7.3. Review of Existing Distribution Extension Plans As observed in Table 7-4, most of the on-going rural electrification projects are relatively small-scaled ones that simply consist of the construction of short-span distribution lines and the installation of on-site transformers, and the projects’ target of electrification is limited to public facilities such as schools, hospitals, as well as chief’s palaces in some projects. On top of that, not all the projects in the list literally deal with “rural electrification”, since two projects in Copperbelt Province, namely “Kabushi” and “Kankoyo”, obviously have their objective rather strengthening electricity supply in urban area. In short, clear and long-term aspects in planning rural electrification projects don’t appear to exist, though each individual project may have its reason to be implemented.
7.4. Preliminary Study for Planning Distribution Line Extension This section explains how to proceed with the planning of distribution line extension projects as preliminary deskwork before the field study.
7.4.1. Assumptions of Distribution System Expansion Planning
As existing distribution system is spreading dispersedly as observed in Figure 13-2, not many Rural Growth Centres (RGCs) in remote areas (e.g. Eastern, Northern, Luapula, North-Western and Western Provinces) are easily accessible from existing distribution lines while RGCs in Copperbelt, Lusaka, Central and Southern Provinces are relatively close to existing lines. Main scope of works of rural electrification projects is the extension of 33 kV and 11 kV overhead lines with 50 mm2 or 100 mm2 ACSR. Based on these preconditions, together with the information obtained through the interviews with ZESCO staff, the Study Team applies the following assumptions in planning distribution network expansion from existing substation including construction of bulky substation.
Applying 33kV and ACSR100mm2 lines shall be considered in this study, taking into account minimizing the voltage drop on long-span distribution lines.
Because of the demand increase in electrified RGC and capacity limitation of existing lines, T-off and/or Extension from existing lines shall not be considered.
In case the capacity of one circuit is not enough to cover the increasing power load, addition of one more circuit shall be constructed instead of increasing the conductor size of existing lines.
Distribution routes shall be constructed alongside the public roads taking into account the easiness of construction works and maintenance.
Step Voltage Regulator (SVR) shall not be applied in this study, because SVR has not been used so far in Zambia.
Demand growth up to the year 2030 shall be considered.
Transformer capacity of 100kVA shall be applied. In other words, the number of necessary transformers is calculated by dividing the demand of RGC by 100kVA. The 20% capacity margin shall be considered in determining transformer capacity.
When electrifying a candidate RGC with high priority, RGCs with lower priority that are positioned between the target RGC and the existing distribution line (or substation) shall be electrified as well.
Chapter 7. Distribution System Planning
7-10
7.4.2. Flowchart of the Study
Figure 7-1 shows the flowchart of the study that visualized the above-mentioned assumptions.
Figure 7-1 Flowchart of the Study
Chapter 7. Distribution System Planning
7-11
7.4.3. Result of the Study
(1) Data Collection
Demand and Priority of RGC is shown in Table 5-11. The position of RGC was input on the GIS map based on the data obtained from each district’s representative and REA. In addition, existing distribution facility data was also input confirming with ZESCO.
(2) Selection of Power Source and Result of Analysis
Comparing with the distance between each RGC and near substations, the nearest substation was selected as a power source. Below figure is example. Although the direct distance between a substation and RGC is shorter than the direct distance between B substation and RGC, actual distance between B substation and RGC is shorter. Therefore, the electric power for this RGC should be supplied from B substation.
As a result of selection of power source based on the above-mentioned rule, the total demand of some substations became very large. Therefore, it was necessary to arrange the demand and/or add the new substation.
Based on the above distribution system, power flow and voltage analysis of each distribution line was carried out. The condition and model for analysis was shown in Table 7-5 and Figure 7-2 respectively.
Table 7-5 Condition for Analysis Voltage 33 kV
Conductor size 100 mm2
Capacity of conductor 313 A
R 0.323
X 0.349
Specification of
Conductor
Y 3.147x10-6
Power factor 0.85
Chapter 7. Distribution System Planning
7-12
Figure 7-2 Model and Formula for Analysis
As a result of analysis, there were large voltage drop in some distribution lines, and it was necessary to add new substations. The total demand supplied from each substation, the number of RGC and the number of feeder is shown in Table 7-6-1 - 7-6-3.
The maps of each distribution line route are attached Appendix B, and the results of voltage analysis for each package of distribution line are attached Appendix C.
Chapter 7. Distribution System Planning
7-13
Table 7-6-1 Total Demand and Number of RGC (Existing SS)
Province Substation Total Demand
(kW) # of RGC # of feeder
Kabwe 7,257 15 2
Fig Tree 2,053 10 1
Kapiri Mposhi 12,703 10 2
Mkushi 3,502 12 1
Mkushi Farm Block 3,234 12 1
Mumbwa 8,583 18 3
Pensulo 520 1 1
Nampundwe 5,291 10 1
Central
Serenje 2,039 4 1
Kansunswa 10,115 9 1
Kitwe 8,555 28 3
Luano 5,063 12 2
Maposa 6,317 16 2
Mpongwe 5,970 29 3
Copperbelt
Ndola 4,180 6 1
Azele 10,573 4 2
Chipata 10,097 15 2
Lundazi 11,919 19 3 Eastern
Msoro 1,328 2 1
Chipili 3,878 12 2
Kawambwa Tea 3,702 9 1
Mansa 1,572 19 2
Mbereshi 6,835 13 2
Nchelenge 7,877 18 2
Luapula
Samfya 1,251 3 1
Chapter 7. Distribution System Planning
7-14
Province Substation Total Demand
(kW) # of RGC # of feeder
Coventry 1,678 8 1
Kafwe Town 936 3 1 Lusaka
Leopard's Hill 3,669 13 1
Kasempa 2,620 18 2 Northwestern
Solwezi 6,947 14 3
Chinsali 3,462 28 3
Isoka 8,837 11 3
Kasama 6,843 22 2
Luwingu 12,039 22 3
Mbala 7,557 26 2
Mfuwe 4,293 4 1
Mpika 5,679 11 3
Mporokoso 8,938 13 2
Northern
Nakonde 3,848 10 1
Chilundu 3,384 17 2
Maamba 2,021 14 1
Mazabuka 1,756 7 1
Muzuma 2,711 11 3
Sinazongwe 2,548 22 1
Southern
Victoria Falls 4,440 33 3
Kalabo 11,894 37 3
Kaoma 11,360 40 4
Mongu 9,754 14 2
Senanga 11,974 9 3
西部
Sesheke 3,808 6 1
Total 287,410 719 95
Chapter 7. Distribution System Planning
7-15
Table 7-6-2 Total Demand and Number of RGC (Proposed SS by ZESCO)
Province Substation Total Demand
(kW) # of RGC # of feeder
New SS at Chama 4,707 11 2 Eastern
New SS at Nyimba 1,120 14 1
Lusaka New SS at Chilundu 5,013 16 2
New SS at Chavuma 1,335 13 1
New SS at Kabompo 7,116 14 2
New SS at Mufumbwe 3,570 14 1
New SS at Mumbezi 1,333 4 1
New SS at Mwinilunga 6,323 16 3
Northwestern
New SS at Zambezi 6,686 17 2
Western New SS at Lukulu 7,631 17 2
Total 44,834 136 17
Chapter 7. Distribution System Planning
7-16
Table 7-6-3 Total Demand and Number of RGC (Proposed SS by Consultant)
Province Substation Total Demand
(kW) # of RGC # of feeder
Pensulo 1 6,522 10 2
Pensulo 2 8,247 15 2
Kabwe 1 4,226 3 1 Central
Kabwe 2 5,538 4 1
Luano 1 3,457 16 2
Luano 2 3,695 9 1 Copperbelt
Ndola 1 6,773 4 1
Azele 1 12,201 10 2
Azele 2 12,082 6 2
Azele 3 10,217 3 2
Azele 4 12,327 9 2
Azele 5 11,154 4 1
Azele 6 5,392 11 2
Lundazi 1 2,728 3 1
Eastern
Mfuwe 1 3,172 7 1
Mbereshi 1 9,933 17 2
Nchelenge 1 6,954 12 2
Samfya 1 5,742 10 2 Luapula
Samfya 2 6,110 8 2
Mwinilunga 1 3,530 5 1 Northwestern
Zambezi 1 2,891 6 1
Chapter 7. Distribution System Planning
7-17
Province Substation Total Demand
(kW) # of RGC # of feeder
Isoka 1 6,550 3 3
Kasama 1 6,531 4 1
Kasama 2 6,484 4 1
Luwingu 1 5,791 5 1
Luwingu 2 11,262 13 2
Luwingu 3 7,391 12 2
Mpika 1 7,201 8 2
Northern
Mpika 2 3,126 3 1
Mazabuka 1 7,348 31 3
Muzuma 1 8,996 19 3
Muzuma 2 7,578 9 2 Southern
Muzuma 3 6,250 10 2
Mongu 1 11,888 20 2
Mongu 2 13,149 10 2
Senanga 1 6,156 5 1
Senanga 2 4,038 6 2
Senanga 3 10,275 10 2
Sesheke 1 3,025 8 1
Western
Sesheke 2 3,010 9 1
Total 278,940 361 67
7.5. Cost Estimate for Distribution Line Extension
7.5.1. Condition
In case the distribution line is constructed from existing substation, following items should be considered to estimate the amount of equipment.
Actual distance of distribution line between existing substation and RGC
The number of transformer on the pole
The number of bay In case the distribution line is constructed from new substation, following items should be considered to estimate the amount of equipment.
Distance of transmission line between existing substation and new substation
Actual distance of distribution line between new substation and RGC
The number of transformer on the pole
New substation depending on the total demand of related RGCs The capacity of substation should be selected following the below table. (e.g. If total demand of substation is 4.5MW, 10MVA capacity should be selected.)
Chapter 7. Distribution System Planning
7-18
Capacity of Substation
(MVA)
Power Factor of Distribution Line
Capacity of Substation
(MW)
2.5 2.125
5 4.25
10 8.5
15
0.85
12.75
Cost estimation shall be carried out depending on the above-mentioned amount and unit cost obtained from ZESCO. Cost shall be divided into foreign currency (material cost) and local currency (material cost, transport cost, overhead cost, labour cost) based on the following table obtained from ZESCO.
Item Breakdown
F.C. Material Cost 80.166747 %
Material Cost, Transportation Cost, Overhead Cost 11.816629 %
Skilled Labour 3.20667 % L.C.
Unskilled Labour 4.810005 %
7.5.2. Result of Cost Estimation
Amount of facility and the result of cost estimation are shown in table 7-7-1 – 7-7-3. If all RGCs are electrified by distribution lines, total cost will be approximately 1,180 million USD.
Chapter 7. Distribution System Planning
7-19
Tabl
e 7-
7-1
Res
ult o
f Cos
t Est
imat
ion
in e
ach
Pack
age
(Exi
stin
g Su
bsta
tion)
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
120
33
11,0
19,2
40
150,2
37
40,7
70
61,1
54
1,2
71,4
00
1-
223
41
11,1
93,6
83
175,9
50
47,7
47
71,6
21
1,4
89,0
00
2-
15
67
1959,7
56
141,4
69
38,3
90
57,5
85
1,1
97,2
00
2-
213
87
11,4
10,2
93
207,8
78
56,4
12
84,6
18
1,7
59,2
00
1-
134
91
1,1
59,6
92
170,9
39
46,3
88
69,5
82
1,4
46,6
00
1-
262
14
12,0
22,6
87
298,1
45
80,9
07
121,3
61
2,5
23,1
00
1-
376
20
12,4
92,6
25
367,4
14
99,7
05
149,5
57
3,1
09,3
00
1-
492
22
12,9
76,3
51
438,7
16
119,0
54
178,5
81
3,7
12,7
00
2-
185
81
2,6
20,5
71
386,2
74
104,8
23
157,2
34
3,2
68,9
00
2-
2125
12
13,8
18,9
03
562,9
09
152,7
56
229,1
34
4,7
63,7
00
2-
3155
16
14,7
28,6
36
697,0
04
189,1
45
283,7
18
5,8
98,5
00
2-
4171
19
15,2
23,3
45
769,9
24
208,9
34
313,4
01
6,5
15,6
00
2-
5188
22
15,7
46,9
14
847,0
99
229,8
77
344,8
15
7,1
68,7
00
2-
6199
24
16,0
86,3
40
897,1
30
243,4
54
365,1
80
7,5
92,1
00
2-
7204
25
16,2
41,6
23
920,0
19
249,6
65
374,4
97
7,7
85,8
00
2-
8212
26
16,4
83,4
86
955,6
70
259,3
39
389,0
09
8,0
87,5
00
1-
1137
12
14,1
65,2
24
613,9
57
166,6
09
249,9
13
5,1
95,7
00
1-
2198
16
15,9
69,6
17
879,9
25
238,7
85
358,1
77
7,4
46,5
00
1-
3233
20
17,0
23,6
49
1,0
35,2
90
280,9
46
421,4
19
8,7
61,3
00
1-
4239
22
17,2
18,7
75
1,0
64,0
52
288,7
51
433,1
27
9,0
04,7
00
2-
124
61
838,1
43
123,5
43
33,5
26
50,2
89
1,0
45,5
00
2-
258
14
11,9
07,2
47
281,1
29
76,2
90
114,4
35
2,3
79,1
00
2-
394
16
12,9
68,1
74
437,5
11
118,7
27
178,0
90
3,7
02,5
00
2-
499
18
13,1
34,4
40
462,0
18
125,3
78
188,0
66
3,9
09,9
00
2-
5118
20
13,7
04,7
46
546,0
82
148,1
90
222,2
85
4,6
21,3
00
2-
6139
21
14,3
21,7
89
637,0
34
172,8
72
259,3
07
5,3
91,0
00
3-
114
41
527,5
77
77,7
65
21,1
03
31,6
55
658,1
00
3-
277
71
2,3
78,7
08
350,6
23
95,1
48
142,7
22
2,9
67,2
00
3-
382
91
2,5
44,9
74
375,1
31
101,7
99
152,6
98
3,1
74,6
00
3-
489
10
12,7
57,9
77
406,5
27
110,3
19
165,4
79
3,4
40,3
00
Chi
nsal
i
1 2 31
Chi
lund
u
2
Tota
l(U
S$)
33k
V B
ayExt
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Aze
le
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
1
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
2
Chapter 7. Distribution System Planning
7-20
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
172
11
12,2
78,3
39
335,8
29
91,1
34
136,7
00
2,8
42,0
00
1-
2116
29
13,7
45,8
71
552,1
44
149,8
35
224,7
52
4,6
72,6
00
1-
3122
34
13,9
73,9
46
585,7
62
158,9
58
238,4
37
4,9
57,1
00
1-
4139
37
14,4
97,5
15
662,9
37
179,9
01
269,8
51
5,6
10,2
00
1-
5186
39
15,8
75,9
02
866,1
12
235,0
36
352,5
54
7,3
29,6
00
1-
6194
41
16,1
28,7
48
903,3
81
245,1
50
367,7
25
7,6
45,0
00
2-
162
81
12,7
58,5
38
406,6
10
110,3
42
165,5
12
3,4
41,0
00
2-
275
85
13,1
77,6
50
468,3
88
127,1
06
190,6
59
3,9
63,8
00
2-
392
88
13,7
01,2
19
545,5
62
148,0
49
222,0
73
4,6
16,9
00
1-
148
14
11,6
18,6
47
238,5
90
64,7
46
97,1
19
2,0
19,1
00
1-
257
19
11,9
33,3
01
284,9
70
77,3
32
115,9
98
2,4
11,6
00
1-
381
23
12,6
69,8
73
393,5
41
106,7
95
160,1
92
3,3
30,4
00
1-
499
26
13,2
22,3
02
474,9
69
128,8
92
193,3
38
4,0
19,5
00
1-
5125
27
13,9
83,6
46
587,1
92
159,3
46
239,0
19
4,9
69,2
00
2-
1184
21
15,6
20,4
91
828,4
64
224,8
20
337,2
29
7,0
11,0
00
2-
2198
23
16,0
46,4
97
891,2
57
241,8
60
362,7
90
7,5
42,4
00
2-
3211
24
16,4
32,6
60
948,1
78
257,3
06
385,9
60
8,0
24,1
00
2-
4243
25
17,3
67,1
64
1,0
85,9
25
294,6
87
442,0
30
9,1
89,8
00
1-
139
61
1,2
71,0
44
187,3
53
50,8
42
76,2
63
1,5
85,5
00
1-
288
18
12,8
16,9
79
415,2
25
112,6
79
169,0
19
3,5
13,9
00
1-
3124
21
13,8
88,8
89
573,2
25
155,5
56
233,3
33
4,8
51,0
00
1-
4129
22
14,0
44,1
72
596,1
13
161,7
67
242,6
50
5,0
44,7
00
1-
5141
23
14,4
01,4
75
648,7
80
176,0
59
264,0
89
5,4
90,4
00
1-
170
61
2,1
65,7
05
319,2
26
86,6
28
129,9
42
2,7
01,5
00
1-
295
12
12,9
53,1
02
435,2
89
118,1
24
177,1
86
3,6
83,7
00
1-
3132
16
14,0
64,8
55
599,1
62
162,5
94
243,8
91
5,0
70,5
00
1-
4151
21
14,6
68,1
10
688,0
82
186,7
24
280,0
87
5,8
23,0
00
1-
5168
24
15,1
91,6
79
765,2
57
207,6
67
311,5
01
6,4
76,1
00
1-
6175
26
15,4
15,6
65
798,2
72
216,6
27
324,9
40
6,7
55,5
00
1-
7195
28
16,0
14,8
31
886,5
90
240,5
93
360,8
90
7,5
02,9
00
1-
8206
29
16,3
43,2
74
935,0
03
253,7
31
380,5
96
7,9
12,6
00
Fig
Tre
e12
Chip
ili
Cove
ntr
y11 2
Chip
ata
1
Tota
l(U
S$)
33k
V B
ayExt
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-21
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
12
33
1499,7
60
73,6
65
19,9
90
29,9
86
623,4
00
1-
260
39
12,2
39,5
38
330,1
09
89,5
82
134,3
72
2,7
93,6
00
1-
373
40
12,6
25,7
01
387,0
30
105,0
28
157,5
42
3,2
75,3
00
2-
110
17
1554,9
14
81,7
95
22,1
97
33,2
95
692,2
00
2-
234
20
11,2
80,5
03
188,7
47
51,2
20
76,8
30
1,5
97,3
00
2-
343
22
11,5
62,2
09
230,2
71
62,4
88
93,7
33
1,9
48,7
00
2-
4113
26
13,6
26,3
43
534,5
25
145,0
54
217,5
81
4,5
23,5
00
2-
5147
27
14,6
18,5
67
680,7
80
184,7
43
277,1
14
5,7
61,2
00
3-
139
29
11,5
23,6
49
224,5
87
60,9
46
91,4
19
1,9
00,6
00
3-
2102
45
13,5
17,5
57
518,4
90
140,7
02
211,0
53
4,3
87,8
00
1-
116
11
1662,1
77
97,6
05
26,4
87
39,7
31
826,0
00
1-
291
18
12,9
03,5
59
427,9
86
116,1
42
174,2
14
3,6
21,9
00
1-
3120
24
13,8
06,3
97
561,0
65
152,2
56
228,3
84
4,7
48,1
00
1-
4126
28
14,0
23,4
89
593,0
65
160,9
40
241,4
09
5,0
18,9
00
1-
5146
32
14,6
44,6
21
684,6
20
185,7
85
278,6
77
5,7
93,7
00
1-
6150
35
14,7
93,0
09
706,4
93
191,7
20
287,5
81
5,9
78,8
00
1-
7154
38
14,9
41,3
98
728,3
65
197,6
56
296,4
84
6,1
63,9
00
2-
126
16
11,0
05,6
92
148,2
40
40,2
28
60,3
42
1,2
54,5
00
2-
229
27
11,2
13,0
83
178,8
09
48,5
23
72,7
85
1,5
13,2
00
2-
348
38
11,8
82,2
35
277,4
43
75,2
89
112,9
34
2,3
47,9
00
2-
4117
48
13,9
83,4
05
587,1
56
159,3
36
239,0
04
4,9
68,9
00
2-
5137
54
14,6
26,5
03
681,9
49
185,0
60
277,5
90
5,7
71,1
00
2-
6165
56
15,4
56,5
50
804,2
99
218,2
62
327,3
93
6,8
06,5
00
1-
18
71
387,3
66
57,0
98
15,4
95
23,2
42
483,2
00
1-
225
10
1910,9
35
134,2
72
36,4
37
54,6
56
1,1
36,3
00
1-
333
13
11,1
74,7
64
173,1
61
46,9
91
70,4
86
1,4
65,4
00
Kaf
we T
ow
n1
Kab
we
1 2
Isoka
1 2 3
Tota
l(U
S$)
33k
V B
ayExt
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-22
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
140
28
11,5
41,5
26
227,2
22
61,6
61
92,4
92
1,9
22,9
00
1-
279
48
12,8
86,7
24
425,5
05
115,4
69
173,2
03
3,6
00,9
00
1-
3132
59
14,5
37,1
17
668,7
74
181,4
85
272,2
27
5,6
59,6
00
1-
4167
62
15,5
80,1
67
822,5
20
223,2
07
334,8
10
6,9
60,7
00
1-
5208
66
16,8
07,3
59
1,0
03,4
09
272,2
94
408,4
42
8,4
91,5
00
1-
6219
67
17,1
35,8
02
1,0
51,8
22
285,4
32
428,1
48
8,9
01,2
00
1-
7227
68
17,3
77,6
66
1,0
87,4
73
295,1
07
442,6
60
9,2
02,9
00
2-
159
24
12,0
45,9
36
301,5
72
81,8
37
122,7
56
2,5
52,1
00
2-
2107
29
13,4
86,1
31
513,8
58
139,4
45
209,1
68
4,3
48,6
00
2-
3111
30
13,6
12,5
54
532,4
93
144,5
02
216,7
53
4,5
06,3
00
3-
174
19
12,4
23,9
22
357,2
88
96,9
57
145,4
35
3,0
23,6
00
3-
2279
38
18,5
48,9
02
1,2
60,1
13
341,9
56
512,9
34
10,6
63,9
00
3-
3364
44
111,0
67,9
01
1,6
31,4
16
442,7
16
664,0
74
13,8
06,1
00
3-
4383
50
111,6
82,1
39
1,7
21,9
55
467,2
86
700,9
28
14,5
72,3
00
3-
5389
56
111,9
21,1
96
1,7
57,1
92
476,8
48
715,2
72
14,8
70,5
00
3-
6470
60
114,3
02,7
90
2,1
08,2
40
572,1
12
858,1
67
17,8
41,3
00
3-
7494
62
115,0
17,3
96
2,2
13,5
74
600,6
96
901,0
44
18,7
32,7
00
3-
8512
63
115,5
47,8
60
2,2
91,7
64
621,9
14
932,8
72
19,3
94,4
00
1-
114
33
1846,0
80
124,7
13
33,8
43
50,7
65
1,0
55,4
00
1-
225
66
11,5
25,9
74
224,9
30
61,0
39
91,5
58
1,9
03,5
00
1-
332
86
11,9
47,6
51
287,0
85
77,9
06
116,8
59
2,4
29,5
00
1-
439
99
12,2
92,4
48
337,9
08
91,6
98
137,5
47
2,8
59,6
00
1-
546
109
12,6
04,2
97
383,8
75
104,1
72
156,2
58
3,2
48,6
00
1-
648
119
12,7
71,8
45
408,5
72
110,8
74
166,3
11
3,4
57,6
00
1-
761
123
13,1
90,9
57
470,3
49
127,6
38
191,4
57
3,9
80,4
00
1-
866
125
13,3
57,2
23
494,8
57
134,2
89
201,4
33
4,1
87,8
00
Kan
sunsw
a1
Kal
abo
1 2 3
Tota
l(U
S$)
33k
V B
ayExt
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-23
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
155
21
11,8
97,5
47
279,7
00
75,9
02
113,8
53
2,3
67,0
00
1-
278
27
12,6
27,2
25
387,2
55
105,0
89
157,6
33
3,2
77,2
00
1-
3136
30
14,3
34,0
55
638,8
42
173,3
62
260,0
43
5,4
06,3
00
1-
4161
32
15,0
77,5
21
748,4
30
203,1
01
304,6
51
6,3
33,7
00
1-
5166
34
15,2
43,7
87
772,9
38
209,7
51
314,6
27
6,5
41,1
00
1-
6179
36
15,6
40,9
33
831,4
77
225,6
37
338,4
56
7,0
36,5
00
1-
7201
38
16,2
97,8
19
928,3
03
251,9
13
377,8
69
7,8
55,9
00
1-
8206
39
16,4
53,1
02
951,1
91
258,1
24
387,1
86
8,0
49,6
00
1-
9210
40
16,5
79,5
25
969,8
26
263,1
81
394,7
72
8,2
07,3
00
2-
155
15
11,8
31,6
50
269,9
86
73,2
66
109,8
99
2,2
84,8
00
2-
2144
28
14,5
42,9
69
669,6
37
181,7
19
272,5
78
5,6
66,9
00
2-
3194
36
16,0
73,8
34
895,2
87
242,9
53
364,4
30
7,5
76,5
00
2-
4245
40
17,5
89,6
26
1,1
18,7
16
303,5
85
455,3
78
9,4
67,3
00
2-
5294
41
19,0
14,7
51
1,3
28,7
80
360,5
90
540,8
85
11,2
45,0
00
2-
6305
42
19,3
43,1
94
1,3
77,1
93
373,7
28
560,5
92
11,6
54,7
00
2-
7357
44
110,8
65,8
81
1,6
01,6
38
434,6
35
651,9
53
13,5
54,1
00
3-
1177
24
15,4
51,4
19
803,5
43
218,0
57
327,0
85
6,8
00,1
00
3-
2250
30
17,6
24,0
98
1,1
23,7
97
304,9
64
457,4
46
9,5
10,3
00
3-
3260
32
17,9
34,6
64
1,1
69,5
74
317,3
87
476,0
80
9,8
97,7
00
4-
113
19
1663,4
60
97,7
94
26,5
38
39,8
08
827,6
00
4-
271
34
12,5
02,0
84
368,8
09
100,0
83
150,1
25
3,1
21,1
00
4-
399
37
13,3
43,1
14
492,7
77
133,7
25
200,5
87
4,1
70,2
00
1-
151
13
11,6
94,2
44
249,7
33
67,7
70
101,6
55
2,1
13,4
00
1-
262
21
12,0
99,5
67
309,4
78
83,9
83
125,9
74
2,6
19,0
00
1-
398
28
13,2
15,4
08
473,9
53
128,6
16
192,9
24
4,0
10,9
00
1-
4109
35
13,6
09,7
48
532,0
79
144,3
90
216,5
85
4,5
02,8
00
1-
5113
42
13,8
02,0
68
560,4
27
152,0
83
228,1
24
4,7
42,7
00
1-
6120
49
14,0
80,9
68
601,5
37
163,2
39
244,8
58
5,0
90,6
00
1-
7145
52
14,8
35,4
18
712,7
44
193,4
17
290,1
25
6,0
31,7
00
2-
110
98
11,4
44,5
25
212,9
24
57,7
81
86,6
71
1,8
01,9
00
2-
226
107
12,0
05,1
31
295,5
58
80,2
05
120,3
08
2,5
01,2
00
3 4
Kao
ma
Kap
iri M
posh
i1 21 2
Tota
l(U
S$)
33k
V B
ayExt
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-24
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
111
81
484,9
29
71,4
79
19,3
97
29,0
96
604,9
00
1-
245
15
11,5
43,0
50
227,4
46
61,7
22
92,5
83
1,9
24,8
00
1-
364
20
12,1
46,3
04
316,3
67
85,8
52
128,7
78
2,6
77,3
00
1-
4129
23
14,0
55,1
55
597,7
32
162,2
06
243,3
09
5,0
58,4
00
1-
5140
26
14,4
05,5
64
649,3
83
176,2
23
264,3
34
5,4
95,5
00
1-
6223
34
16,8
88,8
09
1,0
15,4
15
275,5
52
413,3
29
8,5
93,1
00
1-
7260
36
17,9
78,5
95
1,1
76,0
50
319,1
44
478,7
16
9,9
52,5
00
1-
8271
38
18,3
18,0
22
1,2
26,0
82
332,7
21
499,0
81
10,3
75,9
00
1-
9277
40
18,5
13,1
47
1,2
54,8
43
340,5
26
510,7
89
10,6
19,3
00
1-
10
305
41
19,3
32,2
11
1,3
75,5
74
373,2
88
559,9
33
11,6
41,0
00
1-
11
307
42
19,4
00,9
14
1,3
85,7
01
376,0
37
564,0
55
11,7
26,7
00
1-
12
320
43
19,7
87,0
77
1,4
42,6
21
391,4
83
587,2
25
12,2
08,4
00
2-
158
19
11,9
62,1
61
289,2
24
78,4
86
117,7
30
2,4
47,6
00
2-
274
28
12,5
22,7
67
371,8
57
100,9
11
151,3
66
3,1
46,9
00
2-
383
35
12,8
59,3
88
421,4
76
114,3
76
171,5
63
3,5
66,8
00
2-
4148
44
14,8
34,1
35
712,5
55
193,3
65
290,0
48
6,0
30,1
00
2-
5161
48
15,2
53,2
47
774,3
32
210,1
30
315,1
95
6,5
52,9
00
1-
119
21
649,9
12
95,7
97
25,9
96
38,9
95
810,7
00
1-
234
41
1,1
04,7
78
162,8
45
44,1
91
66,2
87
1,3
78,1
00
1-
367
61
2,0
79,1
25
306,4
64
83,1
65
124,7
47
2,5
93,5
00
1-
476
81
2,3
60,8
31
347,9
88
94,4
33
141,6
50
2,9
44,9
00
1-
5125
10
13,7
96,9
38
559,6
71
151,8
78
227,8
16
4,7
36,3
00
1-
6130
12
13,9
63,2
03
584,1
79
158,5
28
237,7
92
4,9
43,7
00
1-
7145
14
14,4
18,0
70
651,2
26
176,7
23
265,0
84
5,5
11,1
00
1-
8199
16
15,9
98,4
77
884,1
79
239,9
39
359,9
09
7,4
82,5
00
2-
191
13
12,8
48,6
45
419,8
92
113,9
46
170,9
19
3,5
53,4
00
2-
2133
16
14,0
93,7
15
603,4
16
163,7
49
245,6
23
5,1
06,5
00
2-
3150
18
14,6
06,3
01
678,9
72
184,2
52
276,3
78
5,7
45,9
00
2-
4159
20
14,8
88,0
07
720,4
95
195,5
20
293,2
80
6,0
97,3
00
2-
5237
23
17,1
72,0
38
1,0
57,1
63
286,8
82
430,3
22
8,9
46,4
00
1 2
Kas
em
pa
1 2
Kas
ama
Tota
l(U
S$)
33k
V B
ayExt
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-25
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
134
22
11,3
02,4
69
191,9
85
52,0
99
78,1
48
1,6
24,7
00
1-
283
30
12,8
04,4
73
413,3
81
112,1
79
168,2
68
3,4
98,3
00
1-
385
36
12,9
28,0
90
431,6
02
117,1
24
175,6
85
3,6
52,5
00
1-
491
39
13,1
34,1
99
461,9
83
125,3
68
188,0
52
3,9
09,6
00
1-
599
42
13,3
98,0
28
500,8
71
135,9
21
203,8
82
4,2
38,7
00
1-
6109
44
13,7
08,5
94
546,6
49
148,3
44
222,5
16
4,6
26,1
00
1-
7128
46
14,2
78,9
00
630,7
13
171,1
56
256,7
34
5,3
37,5
00
1-
8148
47
14,8
67,0
84
717,4
11
194,6
83
292,0
25
6,0
71,2
00
1-
123
31
11,0
83,8
54
159,7
61
43,3
54
65,0
31
1,3
52,0
00
1-
229
36
11,3
11,9
29
193,3
79
52,4
77
78,7
16
1,6
36,5
00
1-
340
41
11,6
84,3
03
248,2
67
67,3
72
101,0
58
2,1
01,0
00
1-
454
44
12,1
21,2
92
312,6
80
84,8
52
127,2
78
2,6
46,1
00
2-
133
12
11,1
63,7
81
171,5
42
46,5
51
69,8
27
1,4
51,7
00
2-
256
26
11,9
81,3
21
292,0
48
79,2
53
118,8
79
2,4
71,5
00
2-
361
30
12,1
69,5
53
319,7
93
86,7
82
130,1
73
2,7
06,3
00
2-
469
32
12,4
22,3
99
357,0
63
96,8
96
145,3
44
3,0
21,7
00
2-
575
33
12,6
06,5
42
384,2
06
104,2
62
156,3
93
3,2
51,4
00
3-
175
13
12,3
86,8
85
351,8
28
95,4
75
143,2
13
2,9
77,4
00
3-
289
22
12,8
89,7
71
425,9
54
115,5
91
173,3
86
3,6
04,7
00
3-
391
27
13,0
02,4
05
442,5
56
120,0
96
180,1
44
3,7
45,2
00
3-
494
30
13,1
21,9
34
460,1
75
124,8
77
187,3
16
3,8
94,3
00
3-
5120
33
13,9
05,2
43
575,6
35
156,2
10
234,3
15
4,8
71,4
00
3-
6154
36
14,9
19,4
32
725,1
27
196,7
77
295,1
66
6,1
36,5
00
3-
7156
38
14,9
99,1
18
736,8
73
199,9
65
299,9
47
6,2
35,9
00
3-
8160
40
15,1
36,5
24
757,1
27
205,4
61
308,1
91
6,4
07,3
00
3-
9178
42
15,6
77,9
70
836,9
36
227,1
19
340,6
78
7,0
82,7
00
Kaw
ambw
a Tea
1
Kitw
e
1 2 3
Tota
l(U
S$)
33k
V B
ayExt
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-26
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
166
14
12,1
38,1
27
315,1
61
85,5
25
128,2
88
2,6
67,1
00
1-
298
19
13,1
16,5
62
459,3
83
124,6
63
186,9
94
3,8
87,6
00
1-
3118
24
13,7
48,6
77
552,5
57
149,9
47
224,9
21
4,6
76,1
00
1-
4123
29
13,9
47,8
92
581,9
22
157,9
16
236,8
74
4,9
24,6
00
1-
5179
33
15,6
07,9
85
826,6
20
224,3
19
336,4
79
6,9
95,4
00
1-
6223
37
16,9
21,7
57
1,0
20,2
71
276,8
70
415,3
05
8,6
34,2
00
1-
7233
41
17,2
54,2
89
1,0
69,2
87
290,1
72
435,2
57
9,0
49,0
00
1-
8265
44
18,2
10,7
58
1,2
10,2
71
328,4
30
492,6
46
10,2
42,1
00
1-
9284
46
18,7
81,0
65
1,2
94,3
34
351,2
43
526,8
64
10,9
53,5
00
1-
10
304
48
19,3
80,2
31
1,3
82,6
52
375,2
09
562,8
14
11,7
00,9
00
1-
11
309
50
19,5
46,4
97
1,4
07,1
60
381,8
60
572,7
90
11,9
08,3
00
1-
122
13
1857,3
03
126,3
67
34,2
92
51,4
38
1,0
69,4
00
1-
232
24
11,2
66,7
15
186,7
15
50,6
69
76,0
03
1,5
80,1
00
1-
348
28
11,7
72,4
07
261,2
54
70,8
96
106,3
44
2,2
10,9
00
1-
473
30
12,5
15,8
73
370,8
41
100,6
35
150,9
52
3,1
38,3
00
2-
113
15
1619,5
29
91,3
19
24,7
81
37,1
72
772,8
00
2-
231
22
11,2
15,8
89
179,2
23
48,6
36
72,9
53
1,5
16,7
00
2-
342
25
11,5
66,2
98
230,8
73
62,6
52
93,9
78
1,9
53,8
00
2-
457
31
12,0
65,0
95
304,3
96
82,6
04
123,9
06
2,5
76,0
00
2-
583
33
12,8
37,4
22
418,2
38
113,4
97
170,2
45
3,5
39,4
00
2-
693
35
13,1
47,9
88
464,0
15
125,9
20
188,8
79
3,9
26,8
00
Leopa
rd's
Hill
1 1 2
Luan
o
Tota
l(U
S$)
33k
V B
ayExt
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-27
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
155
19
11,8
75,5
81
276,4
62
75,0
23
112,5
35
2,3
39,6
00
1-
259
26
12,0
67,9
01
304,8
10
82,7
16
124,0
74
2,5
79,5
00
1-
3116
30
13,7
56,8
54
553,7
63
150,2
74
225,4
11
4,6
86,3
00
1-
4207
37
16,4
59,9
97
952,2
08
258,4
00
387,6
00
8,0
58,2
00
2-
146
17
11,5
93,8
75
234,9
38
63,7
55
95,6
33
1,9
88,2
00
2-
2109
29
13,5
43,8
51
522,3
66
141,7
54
212,6
31
4,4
20,6
00
2-
3124
38
14,0
75,5
97
600,7
46
163,0
24
244,5
36
5,0
83,9
00
2-
4133
47
14,4
34,1
83
653,6
01
177,3
67
266,0
51
5,5
31,2
00
2-
5177
53
15,7
69,9
21
850,4
90
230,7
97
346,1
95
7,1
97,4
00
2-
6181
58
15,9
40,2
76
875,6
00
237,6
11
356,4
17
7,4
09,9
00
2-
7186
62
16,1
28,5
07
903,3
46
245,1
40
367,7
10
7,6
44,7
00
3-
125
39
11,2
29,4
37
181,2
20
49,1
77
73,7
66
1,5
33,6
00
3-
247
54
12,0
29,1
01
299,0
91
81,1
64
121,7
46
2,5
31,1
00
1-
1122
50
14,1
49,6
71
611,6
64
165,9
87
248,9
80
5,1
76,3
00
1-
2137
56
14,6
48,4
69
685,1
87
185,9
39
278,9
08
5,7
98,5
00
1-
3142
62
14,8
58,6
66
716,1
70
194,3
47
291,5
20
6,0
60,7
00
1-
4170
68
15,7
32,6
44
844,9
95
229,3
06
343,9
59
7,1
50,9
00
2-
166
25
12,2
58,9
39
332,9
69
90,3
58
135,5
36
2,8
17,8
00
2-
286
31
12,9
02,0
36
427,7
62
116,0
81
174,1
22
3,6
20,0
00
2-
3118
37
13,8
91,4
54
573,6
03
155,6
58
233,4
87
4,8
54,2
00
2-
4122
43
14,0
72,7
91
600,3
32
162,9
12
244,3
67
5,0
80,4
00
2-
5152
49
15,0
04,4
89
737,6
65
200,1
80
300,2
69
6,2
42,6
00
2-
6190
52
16,1
34,1
19
904,1
73
245,3
65
368,0
47
7,6
51,7
00
2-
7204
54
16,5
60,1
25
966,9
67
262,4
05
393,6
08
8,1
83,1
00
3-
110
12
1500,0
00
73,7
00
20,0
00
30,0
00
623,7
00
3-
217
18
1767,9
17
113,1
91
30,7
17
46,0
75
957,9
00
3-
324
24
11,0
35,8
35
152,6
83
41,4
33
62,1
50
1,2
92,1
00
Luw
ingu
1 2 3
Lundaz
i
1 2 3
Tota
l(U
S$)
33k
V B
ayExt
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-28
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
1240
141
18,5
54,5
94
1,2
60,9
52
342,1
84
513,2
76
10,6
71,0
00
1-
2271
143
19,4
71,2
20
1,3
96,0
64
378,8
49
568,2
73
11,8
14,4
00
1-
3274
145
19,5
79,7
66
1,4
12,0
64
383,1
91
574,7
86
11,9
49,8
00
1-
4296
147
110,2
36,6
52
1,5
08,8
89
409,4
66
614,1
99
12,7
69,2
00
1-
5302
149
110,4
31,7
78
1,5
37,6
51
417,2
71
625,9
07
13,0
12,6
00
1-
6308
151
110,6
26,9
04
1,5
66,4
12
425,0
76
637,6
14
13,2
56,0
00
1-
7314
153
110,8
22,0
30
1,5
95,1
74
432,8
81
649,3
22
13,4
99,4
00
1-
8327
154
111,2
08,1
93
1,6
52,0
95
448,3
28
672,4
92
13,9
81,1
00
1-
9339
155
111,5
65,4
96
1,7
04,7
61
462,6
20
693,9
30
14,4
26,8
00
1-
181
51
2,4
72,1
82
364,4
01
98,8
87
148,3
31
3,0
83,8
00
1-
2132
71
3,9
66,0
09
584,5
92
158,6
40
237,9
61
4,9
47,2
00
1-
3144
91
4,3
34,2
95
638,8
78
173,3
72
260,0
58
5,4
06,6
00
1-
4174
11
15,2
22,0
62
769,7
35
208,8
82
313,3
24
6,5
14,0
00
1-
5186
13
15,5
90,3
48
824,0
21
223,6
14
335,4
21
6,9
73,4
00
1-
6245
15
17,3
15,0
55
1,0
78,2
44
292,6
02
438,9
03
9,1
24,8
00
1-
7283
16
18,4
22,7
19
1,2
41,5
14
336,9
09
505,3
63
10,5
06,5
00
1-
8329
18
19,7
72,2
46
1,4
40,4
35
390,8
90
586,3
35
12,1
89,9
00
1-
9350
19
110,3
89,2
90
1,5
31,3
88
415,5
72
623,3
57
12,9
59,6
00
2-
115
21
534,4
72
78,7
81
21,3
79
32,0
68
666,7
00
2-
226
31
862,9
15
127,1
94
34,5
17
51,7
75
1,0
76,4
00
2-
337
51
1,2
02,3
41
177,2
26
48,0
94
72,1
40
1,4
99,8
00
2-
467
61
2,0
79,1
25
306,4
64
83,1
65
124,7
47
2,5
93,5
00
2-
576
71
2,3
49,8
48
346,3
69
93,9
94
140,9
91
2,9
31,2
00
Man
sa
1 2
Maa
mba
1
Tota
l(U
S$)
33kV
Bay
Ext
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-29
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
155
22
11,9
08,5
30
281,3
18
76,3
41
114,5
12
2,3
80,7
00
1-
2126
35
14,1
00,3
69
604,3
97
164,0
15
246,0
22
5,1
14,8
00
1-
3142
44
14,6
60,9
75
687,0
31
186,4
39
279,6
59
5,8
14,1
00
1-
4186
52
16,0
18,6
79
887,1
57
240,7
47
361,1
21
7,5
07,7
00
1-
5207
55
16,6
57,6
88
981,3
47
266,3
08
399,4
61
8,3
04,8
00
1-
6211
57
16,7
95,0
94
1,0
01,6
01
271,8
04
407,7
06
8,4
76,2
00
1-
7214
58
16,8
92,6
57
1,0
15,9
82
275,7
06
413,5
59
8,5
97,9
00
2-
141
13
11,4
05,6
44
207,1
93
56,2
26
84,3
39
1,7
53,4
00
2-
268
19
12,2
50,7
62
331,7
64
90,0
30
135,0
46
2,8
07,6
00
2-
372
22
12,3
99,1
50
353,6
36
95,9
66
143,9
49
2,9
92,7
00
2-
480
27
12,6
84,9
45
395,7
63
107,3
98
161,0
97
3,3
49,2
00
1-
144
91
1,4
48,2
92
213,4
79
57,9
32
86,8
98
1,8
06,6
00
1-
276
16
12,4
48,6
93
360,9
39
97,9
48
146,9
22
3,0
54,5
00
1-
386
19
12,7
70,2
42
408,3
35
110,8
10
166,2
15
3,4
55,6
00
1-
4131
22
14,1
01,8
92
604,6
21
164,0
76
246,1
14
5,1
16,7
00
1-
5163
25
15,0
58,3
61
745,6
06
202,3
34
303,5
02
6,3
09,8
00
Maz
abuka
1
Map
osa
1 2
Tota
l(U
S$)
33k
V B
ayExt
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-30
FC
(U
S$)
33/0
.4 T
r100k
VA
(36,0
00)
(13,7
00)
(99,3
00)
(0.8
016
6747
)(0
.11816
629
)(0
.03206
67)
(0.0
4810
005)
1-
155
41
1,71
0,8
39
252,1
79
68,4
34
102,6
50
2,1
34,1
00
1-
2146
14
14,
446,9
30
655,4
80
177
,877
266,8
16
5,5
47,1
00
1-
3180
16
15,
450,1
36
803,3
54
218
,005
327,0
08
6,7
98,5
00
1-
4216
18
16,
511,0
63
959,7
35
260
,443
390,6
64
8,1
21,9
00
1-
5236
19
17,
099,2
46
1,0
46,4
33
283
,970
425,9
55
8,8
55,6
00
1-
6272
20
18,
149,1
90
1,2
01,1
96
325
,968
488,9
51
10,1
65,3
00
1-
7303
21
19,
054,8
34
1,3
34,6
88
362
,193
543,2
90
11,2
95,0
00
2-
137
27
11,
443,9
63
212,8
41
57,7
59
86,6
38
1,8
01,2
00
2-
244
38
11,
766,7
95
260,4
27
70,6
72
106,0
08
2,2
03,9
00
2-
395
55
13,
425,3
65
504,9
01
137
,015
205,5
22
4,2
72,8
00
2-
4104
65
13,
794,9
33
559,3
76
151
,797
227,6
96
4,7
33,8
00
2-
5150
69
15,
166,4
26
761,5
34
206
,657
309,9
86
6,4
44,6
00
2-
6211
72
16,
959,8
36
1,0
25,8
84
278
,393
417,5
90
8,6
81,7
00
2-
7265
78
18,
584,1
75
1,2
65,3
13
343
,367
515,0
51
10,7
07,9
00
2-
8314
81
110,
031,2
65
1,4
78,6
15
401
,251
601,8
76
12,5
13,0
00
2-
9321
84
110,
266,2
34
1,5
13,2
49
410
,649
615,9
74
12,8
06,1
00
2-
10
367
85
111,
604,7
78
1,7
10,5
52
464
,191
696,2
87
14,4
75,8
00
1-
119
29
194
6,4
49
139,5
07
37,8
58
56,7
87
1,1
80,6
00
1-
240
42
11,
695,2
86
249,8
86
67,8
11
101,7
17
2,1
14,7
00
1-
346
49
11,
945,3
26
286,7
42
77,8
13
116,7
20
2,4
26,6
00
1-
485
52
13,
103,8
16
457,5
04
124
,153
186,2
29
3,8
71,7
00
1-
593
54
13,
356,6
62
494,7
74
134
,266
201,4
00
4,1
87,1
00
22
-1
32
34
11,
376,5
43
202,9
03
55,0
62
82,5
93
1,7
17,1
00
1-
1160
28
15,
004,7
30
737,7
00
200
,189
300,2
84
6,2
42,9
00
1-
2167
43
15,
371,4
93
791,7
61
214
,860
322,2
90
6,7
00,4
00
1-
3170
54
15,
578,8
84
822,3
31
223
,155
334,7
33
6,9
59,1
00
Mfu
we
1
Mbal
a
1 2
Mbe
resh
i1
Tota
l(U
S$)
33kV
Bay
Ext
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Uns
kille
dLab
or
LC
(U
S$)
Unit C
ost
(U
S$) & A
mount
33kV
DL
Subs
tation
Feede
r
Chapter 7. Distribution System Planning
7-31
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
123
11
1864,1
98
127,3
83
34,5
68
51,8
52
1,0
78,0
00
1-
252
21
11,8
10,9
67
266,9
38
72,4
39
108,6
58
2,2
59,0
00
1-
388
26
12,9
04,8
42
428,1
76
116,1
94
174,2
91
3,6
23,5
00
1-
4106
31
13,4
79,2
37
512,8
42
139,1
69
208,7
54
4,3
40,0
00
1-
5115
35
13,7
82,9
08
557,6
03
151,3
16
226,9
75
4,7
18,8
00
1-
6129
39
14,2
30,8
80
623,6
34
169,2
35
253,8
53
5,2
77,6
00
1-
7135
42
14,4
36,9
89
654,0
15
177,4
80
266,2
19
5,5
34,7
00
1-
8183
48
15,8
88,1
67
867,9
20
235,5
27
353,2
90
7,3
44,9
00
1-
9187
50
16,0
25,5
73
888,1
73
241,0
23
361,5
34
7,5
16,3
00
1-
173
14
12,3
40,1
48
344,9
39
93,6
06
140,4
09
2,9
19,1
00
1-
2107
20
13,3
87,2
86
499,2
88
135,4
91
203,2
37
4,2
25,3
00
1-
3119
26
13,7
99,5
03
560,0
49
151,9
80
227,9
70
4,7
39,5
00
1-
4156
35
14,9
66,1
70
732,0
17
198,6
47
297,9
70
6,1
94,8
00
1-
5167
38
15,3
16,5
78
783,6
67
212,6
63
318,9
95
6,6
31,9
00
1-
6250
42
17,7
55,8
92
1,1
43,2
23
310,2
36
465,3
54
9,6
74,7
00
1-
7274
44
18,4
70,4
99
1,2
48,5
57
338,8
20
508,2
30
10,5
66,1
00
1-
8301
45
19,2
60,7
02
1,3
65,0
33
370,4
28
555,6
42
11,5
51,8
00
1-
147
41
11,8
86,3
24
278,0
45
75,4
53
113,1
79
2,3
53,0
00
1-
255
48
12,1
94,0
84
323,4
09
87,7
63
131,6
45
2,7
36,9
00
1-
370
52
12,6
70,9
16
393,6
95
106,8
37
160,2
55
3,3
31,7
00
1-
476
56
12,8
88,0
07
425,6
94
115,5
20
173,2
80
3,6
02,5
00
2-
116
28
1848,8
86
125,1
26
33,9
55
50,9
33
1,0
58,9
00
2-
2136
52
14,5
75,6
77
674,4
58
183,0
27
274,5
41
5,7
07,7
00
2-
3142
58
14,8
14,7
35
709,6
95
192,5
89
288,8
84
6,0
05,9
00
2-
4147
64
15,0
24,9
32
740,6
78
200,9
97
301,4
96
6,2
68,1
00
2-
5160
67
15,4
33,0
61
800,8
37
217,3
22
325,9
84
6,7
77,2
00
Mku
shi Far
m B
lock
1
Mongu
1 2
Mku
shi
1
Tota
l(U
S$)
33k
V B
ayExt
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-32
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
126
91
928,8
12
136,9
07
37,1
52
55,7
29
1,1
58,6
00
1-
254
13
11,7
80,8
24
262,4
95
71,2
33
106,8
49
2,2
21,4
00
2-
151
91
1,6
50,3
13
243,2
57
66,0
13
99,0
19
2,0
58,6
00
2-
267
18
12,2
10,9
19
325,8
91
88,4
37
132,6
55
2,7
57,9
00
2-
386
25
12,8
36,1
39
418,0
49
113,4
46
170,1
68
3,5
37,8
00
2-
4138
31
14,4
02,7
58
648,9
69
176,1
10
264,1
65
5,4
92,0
00
2-
5156
34
14,9
55,1
87
730,3
98
198,2
07
297,3
11
6,1
81,1
00
3-
158
17
11,9
40,1
96
285,9
86
77,6
08
116,4
12
2,4
20,2
00
3-
2154
24
14,7
87,6
38
705,7
01
191,5
06
287,2
58
5,9
72,1
00
3-
3191
26
15,8
77,4
25
866,3
36
235,0
97
352,6
46
7,3
31,5
00
1-
127
61
924,7
23
136,3
05
36,9
89
55,4
83
1,1
53,5
00
1-
274
14
12,3
69,0
08
349,1
93
94,7
60
142,1
40
2,9
55,1
00
1-
3179
24
15,5
09,1
39
812,0
51
220,3
66
330,5
48
6,8
72,1
00
1-
4202
31
16,2
49,8
00
921,2
24
249,9
92
374,9
88
7,7
96,0
00
1-
5206
32
16,3
76,2
23
939,8
59
255,0
49
382,5
73
7,9
53,7
00
1-
6213
33
16,5
89,2
26
971,2
56
263,5
69
395,3
54
8,2
19,4
00
1-
7224
34
16,9
17,6
69
1,0
19,6
69
276,7
07
415,0
60
8,6
29,1
00
1-
8243
35
17,4
76,9
92
1,1
02,1
13
299,0
80
448,6
20
9,3
26,8
00
1-
9245
36
17,5
45,6
95
1,1
12,2
40
301,8
28
452,7
42
9,4
12,5
00
1-
10
254
37
17,8
16,4
18
1,1
52,1
45
312,6
57
468,9
85
9,7
50,2
00
2-
138
91
1,2
75,1
32
187,9
55
51,0
05
76,5
08
1,5
90,6
00
2-
248
10
11,5
74,7
15
232,1
14
62,9
89
94,4
83
1,9
64,3
00
2-
366
11
12,1
05,1
79
310,3
05
84,2
07
126,3
11
2,6
26,0
00
3-
127
17
11,0
45,5
35
154,1
12
41,8
21
62,7
32
1,3
04,2
00
3-
237
34
11,5
20,8
43
224,1
73
60,8
34
91,2
51
1,8
97,1
00
3-
341
35
11,6
47,2
66
242,8
08
65,8
91
98,8
36
2,0
54,8
00
3-
457
36
12,1
20,0
10
312,4
91
84,8
00
127,2
01
2,6
44,5
00
3-
5113
39
13,7
69,1
20
555,5
71
150,7
65
226,1
47
4,7
01,6
00
3-
6122
40
14,0
39,8
43
595,4
75
161,5
94
242,3
91
5,0
39,3
00
3-
7142
41
14,6
28,0
26
682,1
74
185,1
21
277,6
82
5,7
73,0
00
Mpongw
e
1 2 3
Mpik
a
1 2 3
Tota
l(U
S$)
33k
V B
ayExt
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-33
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
115
81
600,3
69
88,4
95
24,0
15
36,0
22
748,9
00
1-
227
16
11,0
34,5
52
152,4
94
41,3
82
62,0
73
1,2
90,5
00
1-
340
22
11,4
75,6
29
217,5
09
59,0
25
88,5
38
1,8
40,7
00
1-
462
28
12,1
76,4
47
320,8
10
87,0
58
130,5
87
2,7
14,9
00
1-
590
33
13,0
39,4
42
448,0
16
121,5
78
182,3
67
3,7
91,4
00
2-
171
61
2,1
94,5
65
323,4
80
87,7
83
131,6
74
2,7
37,5
00
2-
274
32
12,5
66,6
99
378,3
33
102,6
68
154,0
02
3,2
01,7
00
2-
3112
58
13,9
48,9
34
582,0
75
157,9
57
236,9
36
4,9
25,9
00
2-
4114
66
14,0
94,5
17
603,5
34
163,7
81
245,6
71
5,1
07,5
00
2-
5150
72
15,1
99,3
75
766,3
91
207,9
75
311,9
62
6,4
85,7
00
2-
6158
78
15,4
96,1
52
810,1
36
219,8
46
329,7
69
6,8
55,9
00
Mso
ro1
1-
129
17
11,1
03,2
55
162,6
20
44,1
30
66,1
95
1,3
76,2
00
1-
111
12
1528,8
60
77,9
54
21,1
54
31,7
32
659,7
00
1-
225
23
11,0
53,7
12
155,3
18
42,1
48
63,2
23
1,3
14,4
00
1-
337
33
11,5
09,8
61
222,5
54
60,3
94
90,5
92
1,8
83,4
00
1-
454
36
12,0
33,4
30
299,7
29
81,3
37
122,0
06
2,5
36,5
00
1-
598
37
13,3
14,2
54
488,5
23
132,5
70
198,8
55
4,1
34,2
00
1-
6140
38
14,5
37,3
58
668,8
09
181,4
94
272,2
41
5,6
59,9
00
1-
7194
39
16,1
06,7
82
900,1
44
244,2
71
366,4
07
7,6
17,6
00
2-
143
14
11,4
74,3
47
217,3
20
58,9
74
88,4
61
1,8
39,1
00
2-
298
22
13,1
49,5
11
464,2
40
125,9
80
188,9
71
3,9
28,7
00
2-
3102
25
13,2
97,9
00
486,1
12
131,9
16
197,8
74
4,1
13,8
00
3-
130
20
11,1
65,0
63
171,7
31
46,6
03
69,9
04
1,4
53,3
00
3-
287
34
12,9
63,8
45
436,8
73
118,5
54
177,8
31
3,6
97,1
00
3-
3125
43
14,1
59,3
72
613,0
94
166,3
75
249,5
62
5,1
88,4
00
3-
4134
47
14,4
63,0
43
657,8
55
178,5
22
267,7
83
5,5
67,2
00
Mporo
koso
1 2
Mum
bwa
1 2 3
Tota
l(U
S$)
33k
V B
ayExt
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-34
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
184
71
2,5
80,7
28
380,4
01
103,2
29
154,8
44
3,2
19,2
00
1-
2106
10
13,2
48,5
97
478,8
45
129,9
44
194,9
16
4,0
52,3
00
1-
3118
12
13,6
16,8
83
533,1
31
144,6
75
217,0
13
4,5
11,7
00
1-
4124
14
13,8
12,0
09
561,8
93
152,4
80
228,7
21
4,7
55,1
00
1-
5127
16
13,9
20,5
55
577,8
92
156,8
22
235,2
33
4,8
90,5
00
2-
195
71
2,8
98,1
88
427,1
95
115,9
28
173,8
91
3,6
15,2
00
2-
298
14
13,0
61,6
48
451,2
89
122,4
66
183,6
99
3,8
19,1
00
3-
168
81
2,1
29,9
50
313,9
56
85,1
98
127,7
97
2,6
56,9
00
3-
292
10
12,8
44,5
57
419,2
89
113,7
82
170,6
73
3,5
48,3
00
1-
119
10
1737,7
75
108,7
48
29,5
11
44,2
66
920,3
00
1-
260
43
12,2
83,4
70
336,5
85
91,3
39
137,0
08
2,8
48,4
00
1-
3156
47
15,0
97,9
64
751,4
43
203,9
19
305,8
78
6,3
59,2
00
1-
4169
49
15,4
95,1
10
809,9
83
219,8
04
329,7
07
6,8
54,6
00
1-
5211
51
16,7
29,1
97
991,8
88
269,1
68
403,7
52
8,3
94,0
00
1-
6230
52
17,2
88,5
20
1,0
74,3
32
291,5
41
437,3
11
9,0
91,7
00
1-
127
38
11,2
76,1
74
188,1
09
51,0
47
76,5
70
1,5
91,9
00
1-
276
48
12,8
00,1
44
412,7
43
112,0
06
168,0
09
3,4
92,9
00
1-
3101
55
13,5
98,5
25
530,4
25
143,9
41
215,9
12
4,4
88,8
00
1-
4123
60
14,2
88,3
60
632,1
07
171,5
34
257,3
02
5,3
49,3
00
1-
5136
63
14,6
96,4
89
692,2
65
187,8
60
281,7
89
5,8
58,4
00
1-
6165
66
15,5
66,3
78
820,4
88
222,6
55
333,9
83
6,9
43,5
00
1-
7196
68
16,4
83,0
05
955,5
99
259,3
20
388,9
80
8,0
86,9
00
1-
116
14
1695,1
26
102,4
62
27,8
05
41,7
08
867,1
00
1-
219
20
1847,6
03
124,9
37
33,9
04
50,8
56
1,0
57,3
00
1-
330
30
11,2
74,8
92
187,9
20
50,9
96
76,4
94
1,5
90,3
00
1-
438
34
11,5
49,7
03
228,4
27
61,9
88
92,9
82
1,9
33,1
00
1-
565
37
12,3
61,8
73
348,1
42
94,4
75
141,7
12
2,9
46,2
00
2-
113
19
1663,4
60
97,7
94
26,5
38
39,8
08
827,6
00
2-
220
34
11,0
30,2
23
151,8
55
41,2
09
61,8
13
1,2
85,1
00
2-
366
59
12,6
32,3
55
388,0
11
105,2
94
157,9
41
3,2
83,6
00
2-
482
63
13,1
38,0
47
462,5
50
125,5
22
188,2
83
3,9
14,4
00
2-
5121
65
14,2
85,5
54
631,6
93
171,4
22
257,1
33
5,3
45,8
00
Nche
lenge
1 2
Nak
onde
1
Nam
pundw
e1
Muz
um
a
1 2 3
Tota
l(U
S$)
33k
V B
ayExt
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-35
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
141
33
11,6
25,3
01
239,5
70
65,0
12
97,5
18
2,0
27,4
00
1-
289
44
13,1
31,3
93
461,5
69
125,2
56
187,8
84
3,9
06,1
00
1-
399
52
13,5
07,8
56
517,0
60
140,3
14
210,4
71
4,3
75,7
00
Pensu
lo1
1-
110
71
445,0
86
65,6
06
17,8
03
26,7
05
555,2
00
1-
125
14
1954,8
66
140,7
48
38,1
95
57,2
92
1,1
91,1
00
1-
237
15
11,3
12,1
69
193,4
15
52,4
87
78,7
30
1,6
36,8
00
1-
347
16
11,6
11,7
52
237,5
73
64,4
70
96,7
05
2,0
10,5
00
11
-1
38
38
11,5
93,6
35
234,9
03
63,7
45
95,6
18
1,9
87,9
00
2-
126
26
11,1
15,5
20
164,4
28
44,6
21
66,9
31
1,3
91,5
00
2-
280
38
12,8
05,7
56
413,5
70
112,2
30
168,3
45
3,4
99,9
00
2-
3202
58
16,5
46,3
36
964,9
34
261,8
53
392,7
80
8,1
65,9
00
3-
119
19
1836,6
20
123,3
18
33,4
65
50,1
97
1,0
43,6
00
3-
237
38
11,5
64,7
75
230,6
49
62,5
91
93,8
86
1,9
51,9
00
3-
392
50
13,2
83,8
70
484,0
45
131,3
55
197,0
32
4,0
96,3
00
1-
161
71
1,9
16,9
47
282,5
59
76,6
78
115,0
17
2,3
91,2
00
1-
2144
21
14,4
66,0
89
658,3
04
178,6
44
267,9
65
5,5
71,0
00
1-
3175
28
15,4
37,6
30
801,5
10
217,5
05
326,2
58
6,7
82,9
00
1-
1154
26
14,8
09,6
04
708,9
39
192,3
84
288,5
76
5,9
99,5
00
1-
2161
36
15,1
21,4
53
754,9
05
204,8
58
307,2
87
6,3
88,5
00
1-
3174
43
15,5
73,5
13
821,5
39
222,9
41
334,4
11
6,9
52,4
00
1-
4202
49
16,4
47,4
91
950,3
64
257,9
00
386,8
49
8,0
42,6
00
Sesh
eke
1
Sere
nje
1
Sen
anga
2 3
Sam
fya
1
Ndo
la1
Tota
l(U
S$)
33k
V B
ayExt
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-36
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,0
00)
(13,7
00)
(99,3
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
183
16
12,6
50,7
13
390,7
17
106,0
29
159,0
43
3,3
06,5
00
1-
290
20
12,8
96,6
65
426,9
70
115,8
67
173,8
00
3,6
13,3
00
1-
3100
24
13,2
29,1
97
475,9
86
129,1
68
193,7
52
4,0
28,1
00
1-
4106
26
13,4
24,3
23
504,7
47
136,9
73
205,4
59
4,2
71,5
00
1-
5108
28
13,5
04,0
08
516,4
93
140,1
60
210,2
41
4,3
70,9
00
1-
6112
30
13,6
41,4
14
536,7
47
145,6
57
218,4
85
4,5
42,3
00
1-
7115
32
13,7
49,9
60
552,7
46
149,9
98
224,9
98
4,6
77,7
00
1-
8120
34
13,9
16,2
26
577,2
54
156,6
49
234,9
74
4,8
85,1
00
1-
9143
36
14,6
01,9
72
678,3
34
184,0
79
276,1
18
5,7
40,5
00
1-
10
172
38
15,4
60,8
79
804,9
37
218,4
35
327,6
53
6,8
11,9
00
1-
11
204
39
16,3
95,3
82
942,6
83
255,8
15
383,7
23
7,9
77,6
00
1-
12
208
40
16,5
21,8
05
961,3
18
260,8
72
391,3
08
8,1
35,3
00
1-
13
221
41
16,9
07,9
69
1,0
18,2
39
276,3
19
414,4
78
8,6
17,0
00
11
-1
65
38
12,3
72,8
56
349,7
60
94,9
14
142,3
71
2,9
59,9
00
2-
111
10
1506,8
94
74,7
17
20,2
76
30,4
14
632,3
00
2-
232
15
11,1
67,8
69
172,1
45
46,7
15
70,0
72
1,4
56,8
00
2-
341
19
11,4
71,5
41
216,9
06
58,8
62
88,2
92
1,8
35,6
00
2-
457
23
11,9
77,2
33
291,4
45
79,0
89
118,6
34
2,4
66,4
00
3-
152
51
1,6
35,2
41
241,0
36
65,4
10
98,1
14
2,0
39,8
00
3-
2127
17
13,9
31,5
38
579,5
11
157,2
62
235,8
92
4,9
04,2
00
3-
3157
22
14,8
52,2
53
715,2
25
194,0
90
291,1
35
6,0
52,7
00
3-
4234
26
17,1
18,4
06
1,0
49,2
58
284,7
36
427,1
04
8,8
79,5
00
3-
5246
30
17,5
08,6
58
1,1
06,7
81
300,3
46
450,5
19
9,3
66,3
00
Sin
azongw
e1
Solw
ezi
2 3
Tota
l(U
S$)
33k
V B
ayExt
ensi
on
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-37
FC
(U
S$)
33/0.4
Tr
100kV
A(3
6,00
0)
(13,
700)
(99,
300)
(0.8
01667
47)
(0.1
181
662
9)(0
.0320
667
)(0
.048
10005
)1
-1
64
71
2,00
3,52
729
5,3
2180
,141
120,
212
2,49
9,2
001
-2
72
91
2,25
6,37
333
2,5
9190
,255
135,
382
2,81
4,6
001
-3
83
10
12,
584,
816
381,0
04103
,393
155,
089
3,22
4,3
001
-4
87
11
12,
711,
239
399,6
38108
,450
162,
674
3,38
2,0
001
-5
94
13
12,
935,
225
432,6
54117
,409
176,
114
3,66
1,4
002
-1
58
10
11,
863,
316
274,6
5474
,533
111,
799
2,32
4,3
002
-2
116
14
13,
581,
129
527,8
61143
,245
214,
868
4,46
7,1
002
-3
122
16
13,
776,
255
556,6
22151
,050
226,
575
4,71
0,5
002
-4
124
18
13,
855,
940
568,3
68154
,238
231,
356
4,80
9,9
002
-5
151
20
14,
657,
127
686,4
63186
,285
279,
428
5,80
9,3
002
-6
155
21
14,
783,
550
705,0
98191
,342
287,
013
5,96
7,0
003
-1
32
21
11,
233,
766
181,8
5849
,351
74,
026
1,53
9,0
003
-2
71
23
12,
381,
273
351,0
0195
,251
142,
876
2,97
0,4
003
-3
109
26
13,
510,
903
517,5
09140
,436
210,
654
4,37
9,5
003
-4
113
28
13,
648,
308
537,7
63145
,932
218,
899
4,55
0,9
003
-5
147
30
14,
651,
515
685,6
36186
,061
279,
091
5,80
2,3
003
-6
151
31
14,
777,
938
704,2
71191
,118
286,
676
5,96
0,0
003
-7
155
32
14,
904,
361
722,9
06196
,174
294,
262
6,11
7,7
003
-8
164
34
15,
186,
067
764,4
30207
,443
311,
164
6,46
9,1
00
Vic
toria
Fal
ls
1 2 3
Tota
l(U
S$)
33k
V B
ayExt
ens
ion
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
Subs
tation
Feeder
Chapter 7. Distribution System Planning
7-38
Tabl
e 7-
7-2
Res
ult o
f Cos
t Est
imat
ion
in e
ach
Pack
age
(Pro
pose
d Su
bsta
tion
by Z
ESC
O)
FC
(U
S$)
33/0.4
Tr
100
kVA
2.5
MV
A5M
VA
10M
VA
15M
VA
(36,0
00)
(40,0
00)
(13,
700)
(600
,000)
(800
,000
)(1
,000
,000
)(1
,300,
000)
(0.8
01667
47)
(0.1
1816
629)
(0.0
320
667)
(0.0
4810
005
)1
-1
230
70.5
210
00.5
09,
529,
982
1,40
4,72
538
1,19
957
1,79
911,
887,7
001
-2
268
70.5
290
00.5
010
,714,
526
1,57
9,32
842
8,58
164
2,87
213,
365,3
001
-3
278
70.5
320
00.5
011
,036,
075
1,62
6,72
444
1,44
366
2,16
513,
766,4
002
-1
1170
.56
00
0.5
03,
044,
893
448,
819
121,
796
182,
694
3,79
8,2
002
-2
8470
.516
00
0.5
05,
261,
504
775,
549
210,
460
315,
690
6,56
3,2
002
-3
130
70.5
220
00.5
06,
654,
962
980,
946
266,
199
399,
298
8,30
1,4
002
-4
171
70.5
260
00.5
07,
882,
155
1,16
1,83
531
5,28
647
2,92
99,
832,2
002
-5
189
70.5
300
00.5
08,
445,
567
1,24
4,88
233
7,82
350
6,73
410,
535,0
001
-1
372
21
00
02,
898,
349
427,
218
115,
934
173,
901
3,61
5,4
001
-2
1272
41
00
03,
180,
055
468,
742
127,
202
190,
803
3,96
6,8
001
-3
1772
61
00
03,
346,
320
493,
250
133,
853
200,
779
4,17
4,2
001
-4
4072
101
00
04,
054,
032
597,
567
162,
161
243,
242
5,05
7,0
001
-5
4472
121
00
04,
191,
438
617,
821
167,
658
251,
486
5,22
8,4
001
-6
4972
141
00
04,
357,
704
642,
328
174,
308
261,
462
5,43
5,8
001
-7
5472
161
00
04,
523,
970
666,
836
180,
959
271,
438
5,64
3,2
001
-8
6172
191
00
04,
758,
939
701,
471
190,
358
285,
536
5,93
6,3
001
-9
110
7221
10
00
6,19
5,04
691
3,15
424
7,80
237
1,70
37,
727,7
001
-10
122
7222
10
00
6,55
2,34
996
5,82
026
2,09
439
3,14
18,
173,4
001
-1
2290
120
00.5
04,
053,
551
597,
496
162,
142
243,
213
5,05
6,4
001
-2
5090
140
00.5
04,
883,
598
719,
845
195,
344
293,
016
6,09
1,8
001
-3
9590
150
00.5
06,
193,
282
912,
894
247,
731
371,
597
7,72
5,5
002
-1
182
9049
00
0.5
09,
077,
521
1,33
8,03
236
3,10
154
4,65
111,
323,3
002
-2
216
9051
00
0.5
010
,080,
728
1,48
5,90
640
3,22
960
4,84
412,
574,7
001
-1
4268
100
00.5
03,
903,
319
575,
352
156,
133
234,
199
4,86
9,0
001
-2
127
6820
00
0.5
06,
466,
250
953,
129
258,
650
387,
975
8,06
6,0
001
-3
162
6823
00
0.5
07,
509,
299
1,10
6,87
530
0,37
245
0,55
89,
367,1
001
-4
200
6825
00
0.5
08,
627,
946
1,27
1,76
534
5,11
851
7,67
710,
762,5
002
-1
3668
320
00.5
03,
971,
781
585,
443
158,
871
238,
307
4,95
4,4
002
-2
8668
500
00.5
05,
612,
474
827,
282
224,
499
336,
748
7,00
1,0
002
-3
150
6860
00
0.5
07,
569,
344
1,11
5,72
630
2,77
445
4,16
19,
442,0
002
-4
182
6863
00
0.5
08,
525,
814
1,25
6,71
034
1,03
351
1,54
910,
635,1
002
-5
186
6865
00
0.5
08,
663,
220
1,27
6,96
434
6,52
951
9,79
310,
806,5
001
-1
347
.531
00
0.5
02,
351,
050
346,
546
94,
042
141,
063
2,93
2,7
001
-2
8947
.543
00
0.5
04,
964,
807
731,
816
198,
592
297,
888
6,19
3,1
001
-3
114
47.5
500
00.5
05,
763,
187
849,
497
230,
528
345,
791
7,18
9,0
001
-4
127
47.5
530
00.5
06,
171,
316
909,
656
246,
853
370,
279
7,69
8,1
001
-5
130
47.5
560
00.5
06,
290,
845
927,
275
251,
634
377,
451
7,84
7,2
002
-1
2047
.519
00
0.5
02,
709,
877
399,
438
108,
395
162,
593
3,38
0,3
002
-2
5747
.529
00
0.5
03,
887,
526
573,
024
155,
501
233,
252
4,84
9,3
002
-3
142
47.5
350
00.5
06,
406,
526
944,
326
256,
261
384,
392
7,99
1,5
002
-4
261
47.5
380
00.5
09,
873,
818
1,45
5,40
739
4,95
359
2,42
912,
316,6
002
-5
305
47.5
410
00.5
011
,176,
607
1,64
7,43
944
7,06
467
0,59
613,
941,7
00
New
SS a
t Luk
ulu
1 2
New
SS a
t C
hilu
ndu
1 2
New
SS a
t Kab
om
po
1 2
New
SS a
t C
ham
a
1 2
New
SS a
t C
hav
um
a1
Tota
l(U
S$)
New
SS
Fore
ign
Cost
sD
om
estic
Cost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$) & A
mount
33k
VD
L66k
VTL
Sub
stat
ion
Fee
der
Chapter 7. Distribution System Planning
7-39
FC
(U
S$)
33/0.4
Tr
100
kVA
2.5
MV
A5M
VA
10M
VA
15M
VA
(36,0
00)
(40,0
00)
(13,
700)
(600
,000)
(800
,000
)(1
,000
,000
)(1
,300,
000)
(0.8
01667
47)
(0.1
1816
629)
(0.0
320
667)
(0.0
4810
005
)1
-1
1495
40
10
04,
135,
642
609,
596
165,
426
248,
139
5,15
8,8
001
-2
5995
150
10
05,
555,
155
818,
833
222,
206
333,
309
6,92
9,5
001
-3
8095
220
10
06,
238,
095
919,
499
249,
524
374,
286
7,78
1,4
001
-4
9595
260
10
06,
714,
927
989,
784
268,
597
402,
896
8,37
6,2
001
-5
150
9535
01
00
8,40
1,07
41,
238,
324
336,
043
504,
064
10,
479,5
001
-6
198
9538
01
00
9,81
9,30
41,
447,
372
392,
772
589,
158
12,
248,6
001
-7
206
9541
01
00
10,0
83,
133
1,48
6,26
040
3,32
560
4,98
812,
577,7
001
-8
232
9544
01
00
10,8
66,
442
1,60
1,72
043
4,65
865
1,98
713,
554,8
001
-1
3168
91
00
03,
655,
042
538,
756
146,
202
219,
303
4,55
9,3
001
-2
7268
171
00
04,
926,
166
726,
120
197,
047
295,
570
6,14
4,9
001
-1
132
5217
00
0.33
05,
928,
251
873,
828
237,
130
355,
695
7,39
4,9
001
-2
223
5222
00
0.33
08,
609,
428
1,26
9,03
534
4,37
751
6,56
610,
739,4
001
-3
334
5231
00
0.33
011
,911,
736
1,75
5,79
747
6,46
971
4,70
414,
858,7
001
-4
446
5236
00
0.33
015
,198,
974
2,24
0,33
860
7,95
991
1,93
818,
959,2
002
-1
4452
170
00.
330
3,38
8,56
849
9,47
713
5,54
320
3,31
44,
226,9
002
-2
9152
270
00.
330
4,85
4,81
871
5,60
319
4,19
329
1,28
96,
055,9
002
-3
123
5233
00
0.33
05,
844,
236
861,
444
233,
769
350,
654
7,29
0,1
002
-4
153
5237
00
0.33
06,
753,
968
995,
539
270,
159
405,
238
8,42
4,9
003
-1
1252
70
00.
330
2,35
5,21
934
7,16
194,
209
141,
313
2,93
7,9
003
-2
2252
110
00.
330
2,68
7,75
139
6,17
610
7,51
016
1,26
53,
352,7
001
-1
2353
41
00
02,
888,
248
425,
730
115,
530
173,
295
3,60
2,8
001
-2
3253
61
00
03,
169,
954
467,
253
126,
798
190,
197
3,95
4,2
001
-3
3853
81
00
03,
365,
079
496,
015
134,
603
201,
905
4,19
7,6
001
-4
5553
111
00
03,
888,
648
573,
189
155,
546
233,
319
4,85
0,7
001
-5
7653
131
00
04,
516,
675
665,
761
180,
667
271,
000
5,63
4,1
001
-6
8553
141
00
04,
787,
398
705,
665
191,
496
287,
244
5,97
1,8
001
-7
147
5317
10
00
6,60
9,66
897
4,26
926
4,38
739
6,58
08,
244,9
001
-8
173
5318
10
00
7,37
1,01
21,
086,
492
294,
840
442,
261
9,19
4,6
001
-9
190
5319
10
00
7,87
2,61
51,
160,
428
314,
905
472,
357
9,82
0,3
001
-1
3047
.511
00
0.5
02,
910,
614
429,
026
116,
425
174,
637
3,63
0,7
001
-2
7947
.527
00
0.5
04,
500,
481
663,
374
180,
019
270,
029
5,61
3,9
001
-3
8147
.533
00
0.5
04,
624,
098
681,
595
184,
964
277,
446
5,76
8,1
001
-4
126
47.5
390
00.5
05,
988,
697
882,
738
239,
548
359,
322
7,47
0,3
001
-5
156
47.5
440
00.5
06,
909,
412
1,01
8,45
227
6,37
641
4,56
58,
618,8
001
-6
172
47.5
490
00.5
07,
426,
086
1,09
4,61
029
7,04
344
5,56
59,
263,3
001
-7
221
47.5
520
00.5
08,
873,
176
1,30
7,91
235
4,92
753
2,39
111,
068,4
001
-8
230
47.5
550
00.5
09,
165,
865
1,35
1,05
436
6,63
554
9,95
211,
433,5
001
-9
251
47.5
560
00.5
09,
782,
908
1,44
2,00
739
1,31
658
6,97
512,
203,2
001
-10
270
47.5
570
00.5
010
,342,
232
1,52
4,45
141
3,68
962
0,53
412,
900,9
002
-1
2747
.518
00
0.5
02,
900,
914
427,
597
116,
037
174,
055
3,61
8,6
002
-2
6047
.530
00
0.5
03,
985,
089
587,
405
159,
404
239,
105
4,97
1,0
002
-3
8347
.533
00
0.5
04,
681,
818
690,
103
187,
273
280,
909
5,84
0,1
00
New
SS a
t Zam
bez
i
1 2
New
SS a
t N
yim
ba1
New
SS a
t M
um
bezi
1
New
SS a
t M
win
ilunga
1 2 3
New
SS a
t M
ufu
mbw
e1
Tota
l(U
S$)
New
SS
Fore
ign
Cost
sD
om
estic
Cost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$) & A
mount
33k
VD
L66k
VTL
Sub
stat
ion
Fee
der
Chapter 7. Distribution System Planning
7-40
Tabl
e 7-
7-3
Res
ult o
f Cos
t Est
imat
ion
in e
ach
Pack
age
(Pro
pose
d Su
bsta
tion
by C
onsu
ltant
) FC
(U
S$)
33/0.4
Tr
100
kVA
2.5
MV
A5M
VA
10M
VA
15M
VA
(36,0
00)
(40,0
00)
(13,
700)
(600
,000)
(800
,000
)(1
,000
,000
)(1
,300,
000)
(0.8
01667
47)
(0.1
1816
629)
(0.0
320
667)
(0.0
4810
005
)1
-1
613
320
00
0.5
1,46
2,56
221
5,58
358,
502
87,
754
1,82
4,4
001
-2
1013
590
00
0.5
1,87
4,53
927
6,30
874,
982
112,
472
2,33
8,3
001
-3
1413
730
00
0.5
2,14
3,73
931
5,98
885,
750
128,
624
2,67
4,1
001
-4
1513
800
00
0.5
2,24
9,47
933
1,57
589,
979
134,
969
2,80
6,0
001
-5
2713
870
00
0.5
2,67
2,67
939
3,95
510
6,90
716
0,36
13,
333,9
002
-1
1713
400
00
0.5
1,86
7,88
527
5,32
774,
715
112,
073
2,33
0,0
002
-2
3713
570
00
0.5
2,63
1,79
438
7,92
810
5,27
215
7,90
83,
282,9
002
-3
7413
600
00
0.5
3,73
2,56
455
0,18
214
9,30
322
3,95
44,
656,0
002
-4
7813
630
00
0.5
3,88
0,95
257
2,05
515
5,23
823
2,85
74,
841,1
002
-5
8513
650
00
0.5
4,10
4,93
860
5,07
016
4,19
824
6,29
65,
120,5
001
-1
911
530
00
0.5
1,71
5,64
925
2,88
868,
626
102,
939
2,14
0,1
001
-2
2211
710
00
0.5
2,28
8,52
033
7,32
991,
541
137,
311
2,85
4,7
001
-3
5611
800
00
0.5
3,36
8,60
749
6,53
513
4,74
420
2,11
64,
202,0
002
2-
111
1167
00
00.
51,
927,
128
284,
060
77,
085
115,
628
2,40
3,9
001
-1
421
.541
00
00.
51,
776,
255
261,
821
71,
050
106,
575
2,21
5,7
001
-2
1421
.582
00
00.
52,
515,
152
370,
735
100,
606
150,
909
3,13
7,4
002
2-
17
21.5
410
00
0.5
1,86
2,83
527
4,58
374,
513
111,
770
2,32
3,7
001
-1
4622
.527
00
00.
52,
866,
683
422,
551
114,
667
172,
001
3,57
5,9
001
-2
107
22.5
490
00
0.5
4,86
8,76
771
7,65
919
4,75
129
2,12
66,
073,3
001
-3
205
22.5
710
00
0.5
7,93
8,67
21,
170,
165
317,
547
476,
320
9,90
2,7
001
-4
220
22.5
860
00
0.5
8,53
6,31
61,
258,
258
341,
453
512,
179
10,
648,2
002
-1
2322
.522
00
00.
52,
147,
988
316,
615
85,
920
128,
879
2,67
9,4
002
-2
3122
.544
00
00.
52,
620,
491
386,
262
104,
820
157,
229
3,26
8,8
002
-3
7122
.563
00
00.
53,
983,
566
587,
180
159,
343
239,
014
4,96
9,1
002
-4
101
22.5
650
00
0.5
4,87
1,33
271
8,03
719
4,85
329
2,28
06,
076,5
002
-5
129
22.5
660
00
0.5
5,69
0,39
683
8,76
822
7,61
634
1,42
47,
098,2
001
-1
2333
750
00
13,
587,
863
528,
853
143,
515
215,
272
4,47
5,5
001
-2
4333
110
00
01
4,54
9,46
367
0,59
418
1,97
927
2,96
85,
675,0
001
-3
6033
137
00
01
5,33
6,62
078
6,62
121
3,46
532
0,19
76,
656,9
001
-1
1220
100
00.5
01,
498,
317
220,
853
59,
933
89,
899
1,86
9,0
001
-2
9920
360
00.5
04,
294,
693
633,
040
171,
788
257,
682
5,35
7,2
001
-3
131
2042
00
0.5
05,
284,
111
778,
881
211,
364
317,
047
6,59
1,4
001
-4
145
2043
00
0.5
05,
699,
134
840,
056
227,
965
341,
948
7,10
9,1
002
-1
1620
140
00.5
01,
657,
688
244,
344
66,
308
99,
461
2,06
7,8
002
-2
5120
250
00.5
02,
788,
600
411,
041
111,
544
167,
316
3,47
8,5
00
1A
zele
5
Aze
le 6
1 2
Tota
l(U
S$)
New
SS
Fore
ign
Cost
sD
om
estic
Cost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$) & A
mount
33k
VD
L66k
VTL
Aze
le 1
21
Sub
stat
ion
Fee
der
2
Aze
le 4
1A
zele
3
11A
zele
2
Chapter 7. Distribution System Planning
7-41
FC
(U
S$)
33/0.4
Tr
100kV
A2.5
MV
A5M
VA
10M
VA
15M
VA
(36,0
00)
(40,0
00)
(13,7
00)
(600,0
00)
(800,0
00)
(1,0
00,0
00)
(1,3
00,0
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
11
-1
14
75
33
00
0.3
30
3,4
36,
027
506,4
73
137,4
41
206,1
62
4,2
86,1
00
22
-1
975
32
00
0.3
30
3,2
80,
744
483,5
84
131,2
30
196,8
45
4,0
92,4
00
33
-1
50
75
15
00
0.3
30
4,2
77,
297
630,4
76
171,0
92
256,6
38
5,3
35,5
00
1-
18
26
42
01
00
2,1
67,
228
319,4
51
86,6
89
130,0
34
2,7
03,4
00
1-
227
26
49
01
00
2,7
92,
448
411,6
09
111,6
98
167,5
47
3,4
83,3
00
1-
343
26
53
01
00
3,2
98,
140
486,1
48
131,9
26
197,8
88
4,1
14,1
00
1-
11
38
47
00
10
2,5
65,
256
378,1
20
102,6
10
153,9
15
3,1
99,9
00
1-
256
38
68
00
10
4,3
83,
197
646,0
86
175,3
28
262,9
92
5,4
67,6
00
1-
11
12
67
00
10
1,9
51,
178
287,6
05
78,0
47
117,0
71
2,4
33,9
00
1-
236
12
77
00
10
3,0
71,
108
452,6
83
122,8
44
184,2
66
3,8
30,9
00
1-
355
12
80
00
10
3,6
52,
397
538,3
66
146,0
96
219,1
44
4,5
56,0
00
1-
11
66
49
00
10
3,4
85,
089
513,7
04
139,4
04
209,1
05
4,3
47,3
00
1-
26
66
66
00
10
3,8
16,
097
562,4
95
152,6
44
228,9
66
4,7
60,2
00
1-
340
66
74
00
10
4,8
85,
201
720,0
82
195,4
08
293,1
12
6,0
93,8
00
1-
466
66
80
00
10
5,7
01,
459
840,3
99
228,0
58
342,0
88
7,1
12,0
00
1-
133
41.5
11
00.5
00
2,7
24,
627
401,6
12
108,9
85
163,4
78
3,3
98,7
00
1-
239
41.5
16
00.5
00
2,9
52,
702
435,2
30
118,1
08
177,1
62
3,6
83,2
00
1-
345
41.5
19
00.5
00
3,1
58,
810
465,6
11
126,3
52
189,5
29
3,9
40,3
00
1-
450
41.5
21
00.5
00
3,3
25,
076
490,1
18
133,0
03
199,5
05
4,1
47,7
00
1-
560
41.5
22
00.5
00
3,6
24,
659
534,2
77
144,9
86
217,4
80
4,5
21,4
00
2-
134
41.5
13
00.5
00
2,7
75,
453
409,1
04
111,0
18
166,5
27
3,4
62,1
00
2-
257
41.5
21
00.5
00
3,5
27,
096
519,8
96
141,0
84
211,6
26
4,3
99,7
00
2-
384
41.5
26
00.5
00
4,3
61,
231
642,8
48
174,4
49
261,6
74
5,4
40,2
00
2-
494
41.5
28
00.5
00
4,6
71,
797
688,6
26
186,8
72
280,3
08
5,8
27,6
00
1-
120
44
21
01
00
2,8
60,
109
421,5
82
114,4
04
171,6
07
3,5
67,7
00
1-
238
44
33
01
00
3,5
11,
384
517,5
80
140,4
55
210,6
83
4,3
80,1
00
1-
355
44
39
01
00
4,0
67,
901
599,6
11
162,7
16
244,0
74
5,0
74,3
00
1-
462
44
42
01
00
4,3
02,
870
634,2
46
172,1
15
258,1
72
5,3
67,4
00
1-
577
44
48
01
00
4,8
01,
667
707,7
69
192,0
67
288,1
00
5,9
89,6
00
1-
685
44
49
01
00
5,0
43,
531
743,4
20
201,7
41
302,6
12
6,2
91,3
00
1-
12
46
25
01
00
2,4
48,
693
360,9
39
97,9
48
146,9
22
3,0
54,5
00
1-
28
46
32
01
00
2,6
98,
733
397,7
95
107,9
49
161,9
24
3,3
66,4
00
1-
319
46
35
01
00
3,1
28,
748
461,1
79
125,1
50
187,7
25
3,9
02,8
00
Lunda
zi 1
1
Luan
o 1
1 2
Luan
o 2
11 1
Kas
ama
1
Kas
ama
2
1 1
Kab
we 1
Kab
we 2
Isoka
1
Tota
l(U
S$)
New
SS
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Uns
kille
dLab
or
LC
(U
S$)
Unit C
ost
(U
S$) & A
mount
33kV
DL
66kV
TL
Subs
tation
Feede
r
Chapter 7. Distribution System Planning
7-42
FC
(U
S$)
33/0.4
Tr
100
kVA
2.5
MV
A5M
VA
10M
VA
15M
VA
(36,0
00)
(40,0
00)
(13,
700)
(600
,000)
(800
,000
)(1
,000
,000
)(1
,300,
000)
(0.8
01667
47)
(0.1
1816
629)
(0.0
320
667)
(0.0
4810
005
)1
-1
2450
270
01
03,
394,
180
500,
304
135,
767
203,
651
4,23
3,9
001
-2
4250
500
01
04,
166,
266
614,
110
166,
651
249,
976
5,19
7,0
001
-3
4750
590
01
04,
409,
412
649,
950
176,
376
264,
565
5,50
0,3
001
-4
7150
650
01
05,
167,
949
761,
759
206,
718
310,
077
6,44
6,5
001
-5
8050
710
01
05,
493,
587
809,
758
219,
743
329,
615
6,85
2,7
001
-1
1137
250
00
0.5
2,29
9,58
333
8,96
091,
983
137,
975
2,86
8,5
001
-2
4437
370
00
0.5
3,38
3,75
849
8,76
813
5,35
020
3,02
64,
220,9
001
-3
6337
470
00
0.5
4,04
1,92
759
5,78
316
1,67
724
2,51
65,
041,9
001
-4
8137
560
00
0.5
4,66
0,25
368
6,92
418
6,41
027
9,61
55,
813,2
001
-5
113
3763
00
00.
55,
660,
654
834,
384
226,
426
339,
639
7,06
1,1
002
-1
1937
280
00
0.5
2,56
3,41
237
7,84
910
2,53
615
3,80
53,
197,6
002
-2
3737
470
00
0.5
3,29
1,56
648
5,17
913
1,66
319
7,49
44,
105,9
002
-3
4437
610
00
0.5
3,64
7,34
653
7,62
114
5,89
421
8,84
14,
549,7
002
-4
7237
720
00
0.5
4,57
6,23
967
4,54
018
3,05
027
4,57
45,
708,4
002
-5
7937
780
00
0.5
4,84
4,15
671
4,03
219
3,76
629
0,64
96,
042,6
001
-1
1326
170
00.5
01,
796,
457
264,
799
71,
858
107,
787
2,24
0,9
001
-2
1926
250
00.5
02,
057,
480
303,
274
82,
299
123,
449
2,56
6,5
001
-3
4126
380
00.5
02,
835,
177
417,
907
113,
407
170,
111
3,53
6,6
002
-1
826
270
00.5
01,
761,
985
259,
718
70,
479
105,
719
2,19
7,9
002
-2
1526
380
00.5
02,
084,
816
307,
303
83,
393
125,
089
2,60
0,6
002
-3
2026
460
00.5
02,
316,
979
341,
524
92,
679
139,
019
2,89
0,2
002
-4
3226
530
00.5
02,
740,
180
403,
904
109,
607
164,
411
3,41
8,1
002
-5
4426
560
00.5
03,
119,
448
459,
809
124,
778
187,
167
3,89
1,2
001
-1
1420
40
00.
330
1,35
3,85
619
9,55
954,
154
81,
231
1,68
8,8
001
-2
4220
140
00.
330
2,27
1,76
533
4,86
090,
871
136,
306
2,83
3,8
001
-3
6820
170
00.
330
3,05
5,07
545
0,32
012
2,20
318
3,30
43,
810,9
001
-4
8020
190
00.
330
3,42
3,36
150
4,60
613
6,93
420
5,40
24,
270,3
002
-1
2620
130
00.
330
1,79
9,02
226
5,17
771,
961
107,
941
2,24
4,1
002
-2
3820
230
00.
330
2,25
5,17
133
2,41
490,
207
135,
310
2,81
3,1
002
-3
6820
310
00.
330
3,20
8,83
447
2,98
412
8,35
319
2,53
04,
002,7
002
-4
7320
350
00.
330
3,39
7,06
650
0,73
013
5,88
320
3,82
44,
237,5
002
-5
8820
400
00.
330
3,88
4,88
157
2,63
415
5,39
523
3,09
34,
846,0
002
-6
108
2043
00
0.33
04,
495,
030
662,
570
179,
801
269,
702
5,60
7,1
003
-1
4320
180
00.
330
2,34
4,55
734
5,58
993,
782
140,
673
2,92
4,6
003
-2
5820
210
00.
330
2,81
0,40
641
4,25
611
2,41
616
8,62
43,
505,7
003
-3
6620
240
00.
330
3,07
4,23
445
3,14
412
2,96
918
4,45
43,
834,8
003
-4
7120
260
00.
330
3,24
0,50
047
7,65
212
9,62
019
4,43
04,
042,2
003
-5
7820
280
00.
330
3,46
4,48
651
0,66
713
8,57
920
7,86
94,
321,6
003
-6
8620
300
00.
330
3,71
7,33
254
7,93
714
8,69
322
3,04
04,
637,0
003
-7
104
2033
00
0.33
04,
269,
761
629,
365
170,
790
256,
186
5,32
6,1
003
-8
114
2036
00
0.33
04,
591,
310
676,
762
183,
652
275,
479
5,72
7,2
003
-9
120
2038
00
0.33
04,
786,
436
705,
524
191,
457
287,
186
5,97
0,6
00
Maz
abuk
a 1
1 2 3
Luw
ingu
3
1 2
Luw
ingu
11
Luw
ingu
2
1 2
Tota
l(U
S$)
New
SS
Fore
ign
Cost
sD
om
estic
Cost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$) & A
mount
33k
VD
L66k
VTL
Sub
stat
ion
Fee
der
Chapter 7. Distribution System Planning
7-43
FC
(U
S$)
33/0.4
Tr
100
kVA
2.5
MV
A5M
VA
10M
VA
15M
VA
(36,0
00)
(40,0
00)
(13,
700)
(600
,000)
(800
,000
)(1
,000
,000
)(1
,300,
000)
(0.8
01667
47)
(0.1
1816
629)
(0.0
320
667)
(0.0
4810
005
)1
-1
1725
310
00
0.5
2,15
3,84
031
7,47
786,
154
129,
230
2,68
6,7
001
-2
2325
380
00
0.5
2,40
3,88
035
4,33
396,
155
144,
233
2,99
8,6
001
-3
5325
440
00
0.5
3,33
5,57
849
1,66
613
3,42
320
0,13
54,
160,8
001
-4
6725
470
00
0.5
3,77
2,56
755
6,07
915
0,90
322
6,35
44,
705,9
001
-5
7525
480
00
0.5
4,01
4,43
059
1,73
016
0,57
724
0,86
65,
007,6
002
-1
625
150
00
0.5
1,66
0,65
424
4,78
166,
426
99,
639
2,07
1,5
002
-2
2525
420
00
0.5
2,50
5,53
236
9,31
710
0,22
115
0,33
23,
125,4
002
-3
3625
610
00
0.5
3,03
1,66
644
6,86
912
1,26
718
1,90
03,
781,7
002
-4
7525
690
00
0.5
4,24
5,07
062
5,72
616
9,80
325
4,70
45,
295,3
002
-5
8825
750
00
0.5
4,68
6,14
769
0,74
118
7,44
628
1,16
95,
845,5
002
-6
111
2579
00
00.
55,
393,
859
795,
058
215,
754
323,
632
6,72
8,3
001
-1
1132
130
10
02,
127,
706
313,
625
85,
108
127,
662
2,65
4,1
001
-2
2832
240
10
02,
739,
137
403,
751
109,
566
164,
348
3,41
6,8
001
-3
3232
310
10
02,
931,
457
432,
099
117,
258
175,
887
3,65
6,7
001
-4
4832
360
10
03,
448,
132
508,
257
137,
925
206,
888
4,30
1,2
001
-5
5132
400
10
03,
578,
644
527,
494
143,
146
214,
719
4,46
4,0
001
-6
8032
420
10
04,
437,
550
654,
098
177,
502
266,
253
5,53
5,4
001
-1
5826
220
00
0.5
3,27
0,32
248
2,04
813
0,81
319
6,21
94,
079,4
001
-2
8626
380
00
0.5
4,25
4,12
962
7,06
117
0,16
525
5,24
85,
306,6
001
-3
9426
460
00
0.5
4,57
2,87
267
4,04
418
2,91
527
4,37
25,
704,2
001
-4
9726
530
00
0.5
4,73
6,33
269
8,13
818
9,45
328
4,18
05,
908,1
001
-5
236
2672
00
00.
58,
956,
550
1,32
0,20
135
8,26
253
7,39
311,
172,4
002
-1
6026
250
00
0.5
3,36
0,99
149
5,41
213
4,44
020
1,65
94,
192,5
002
-2
6426
370
00
0.5
3,60
8,22
553
1,85
514
4,32
921
6,49
44,
500,9
002
-3
7726
460
00
0.5
4,08
2,25
160
1,72
616
3,29
024
4,93
55,
092,2
002
-4
100
2658
00
00.
54,
877,
826
718,
995
195,
113
292,
670
6,08
4,6
002
-5
136
2665
00
00.
55,
993,
667
883,
470
239,
747
359,
620
7,47
6,5
002
-6
155
2671
00
00.
56,
607,
904
974,
009
264,
316
396,
474
8,24
2,7
002
-7
161
2676
00
00.
56,
835,
979
1,00
7,62
827
3,43
941
0,15
98,
527,2
002
-8
185
2680
00
00.
57,
572,
551
1,11
6,19
930
2,90
245
4,35
39,
446,0
001
-1
319
220
00
0.5
1,45
8,55
421
4,99
258,
342
87,
513
1,81
9,4
001
-2
1519
430
00
0.5
2,03
5,51
430
0,03
681,
421
122,
131
2,53
9,1
001
-3
4219
640
00
0.5
3,04
5,37
444
8,89
012
1,81
518
2,72
23,
798,8
001
-4
5119
660
00
0.5
3,32
7,08
049
0,41
413
3,08
319
9,62
54,
150,2
002
-1
3119
480
00
0.5
2,55
2,18
937
6,19
410
2,08
815
3,13
13,
183,6
002
-2
5819
700
00
0.5
3,57
3,03
252
6,66
714
2,92
121
4,38
24,
457,0
002
-3
7119
920
00
0.5
4,18
9,83
561
7,58
416
7,59
325
1,39
05,
226,4
002
-4
9319
950
00
0.5
4,85
7,70
471
6,02
919
4,30
829
1,46
26,
059,5
00
Mongu
1
1 2
Mongu
2
1 2
Mfu
we 1
1
Mbe
resh
i 1
1 2
Tota
l(U
S$)
New
SS
Fore
ign
Cost
sD
om
estic
Cost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$) & A
mount
33k
VD
L66k
VTL
Sub
stat
ion
Fee
der
Chapter 7. Distribution System Planning
7-44
FC
(U
S$)
33/0.
4 Tr
100
kVA
2.5
MV
A5M
VA
10M
VA
15M
VA
(36,0
00)
(40,0
00)
(13,
700)
(600
,000)
(800
,000
)(1
,000
,000
)(1
,300,
000)
(0.8
01667
47)
(0.1
1816
629)
(0.0
320
667)
(0.0
4810
005
)1
-1
7452
.531
00
0.5
04,
560,
446
672,
213
182,
418
273,
627
5,68
8,7
001
-2
108
52.5
450
00.5
05,
695,
447
839,
512
227,
818
341,
727
7,10
4,5
002
-1
3352
.521
00
0.5
03,
267,
356
481,
610
130,
694
196,
041
4,07
5,7
002
-2
168
52.5
390
00.5
07,
361,
151
1,08
5,03
829
4,44
644
1,66
99,
182,3
002
-3
216
52.5
460
00.5
08,
823,
313
1,30
0,56
235
2,93
352
9,39
911,
006,2
001
-1
5778
150
10
04,
952,
301
729,
972
198,
092
297,
138
6,17
7,5
001
-2
118
7830
01
00
6,87
7,50
51,
013,
749
275,
100
412,
650
8,57
9,0
001
-3
124
7839
01
00
7,14
9,51
11,
053,
842
285,
980
428,
971
8,91
8,3
001
-1
3911
160
00
0.3
31,
997,
916
294,
494
79,
917
119,
875
2,49
2,2
001
-2
4611
300
00
0.3
32,
353,
696
346,
936
94,
148
141,
222
2,93
6,0
001
-3
100
1142
00
00.3
34,
043,
931
596,
078
161,
757
242,
636
5,04
4,4
001
-4
117
1149
00
00.3
34,
611,
432
679,
728
184,
457
276,
686
5,75
2,3
001
-5
168
1156
00
00.3
36,
160,
173
908,
013
246,
407
369,
610
7,68
4,2
001
-6
306
1158
00
00.3
310
,164,
823
1,49
8,30
140
6,59
360
9,88
912,
679,6
001
-7
319
1159
00
00.3
310
,550,
986
1,55
5,22
242
2,03
963
3,05
913,
161,3
002
-1
3211
270
00
0.3
31,
916,
707
282,
524
76,
668
115,
002
2,39
0,9
002
-2
118
1135
00
00.3
34,
486,
532
661,
318
179,
461
269,
192
5,59
6,5
002
-3
142
1143
00
00.3
35,
267,
035
776,
364
210,
681
316,
022
6,57
0,1
003
-1
4011
120
00
0.3
31,
982,
844
292,
273
79,
314
118,
971
2,47
3,4
003
-2
105
1115
00
00.3
33,
891,
695
573,
638
155,
668
233,
502
4,85
4,5
003
-3
120
1116
00
00.3
34,
335,
578
639,
067
173,
423
260,
135
5,40
8,2
001
-1
6646
200
00.5
04,
000,
321
589,
650
160,
013
240,
019
4,99
0,0
001
-2
7546
270
00.5
04,
336,
941
639,
268
173,
478
260,
216
5,40
9,9
001
-3
9546
410
00.5
05,
067,
901
747,
012
202,
716
304,
074
6,32
1,7
001
-4
114
4647
00
0.5
05,
682,
139
837,
551
227,
286
340,
928
7,08
7,9
001
-5
145
4649
00
0.5
06,
598,
765
972,
662
263,
951
395,
926
8,23
1,3
002
2-
112
4648
00
0.5
02,
749,
399
405,
263
109,
976
164,
964
3,42
9,6
001
-1
1639
250
00.5
02,
387,
767
351,
958
95,
511
143,
266
2,97
8,5
001
-2
2639
360
00.5
02,
797,
178
412,
306
111,
887
167,
831
3,48
9,2
001
-3
3939
400
00.5
03,
216,
290
474,
083
128,
652
192,
977
4,01
2,0
002
-1
839
170
00.5
02,
069,
024
304,
975
82,
761
124,
141
2,58
0,9
002
-2
1539
250
00.5
02,
358,
907
347,
704
94,
356
141,
534
2,94
2,5
002
-3
4139
290
00.5
03,
153,
199
464,
783
126,
128
189,
192
3,93
3,3
002
-4
4839
330
00.5
03,
399,
150
501,
037
135,
966
203,
949
4,24
0,1
002
-5
5439
360
00.5
03,
605,
259
531,
417
144,
210
216,
316
4,49
7,2
002
-6
6339
390
00.5
03,
897,
948
574,
560
155,
918
233,
877
4,86
2,3
001
-1
444
90
00.5
02,
026,
054
298,
642
81,
042
121,
563
2,52
7,3
001
-2
3244
290
00.5
03,
053,
792
450,
131
122,
152
183,
228
3,80
9,3
001
-3
4644
400
00.5
03,
578,
644
527,
494
143,
146
214,
719
4,46
4,0
002
-1
144
80
00.5
01,
928,
491
284,
261
77,
140
115,
709
2,40
5,6
002
-2
4944
180
00.5
03,
423,
601
504,
641
136,
944
205,
416
4,27
0,6
002
-3
7044
420
00.5
04,
293,
250
632,
828
171,
730
257,
595
5,35
5,4
002
-4
103
4448
00
0.5
05,
311,
528
782,
923
212,
461
318,
692
6,62
5,6
00
Nch
elen
ge 1
1 21M
uzu
ma
2
Muzu
ma
3
1 2
Muzu
ma
1
1 2 3
Mpi
ka 1
1 2
Mpi
ka 2
1
Tota
l(U
S$)
New
SS
Fore
ign
Cost
sD
om
estic
Cost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$) & A
mount
33k
VD
L66k
VTL
Sub
stat
ion
Fee
der
Chapter 7. Distribution System Planning
7-45
FC
(U
S$)
33/0.4
Tr
100k
VA
2.5M
VA
5MV
A10
MV
A15
MV
A(3
6,0
00)
(40,0
00)
(13,7
00)
(600,0
00)
(800,0
00)
(1,0
00,0
00)
(1,3
00,0
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
14
14
45
00
10
1,8
60,
269
274,2
05
74,4
11
111,6
16
2,3
20,5
00
1-
27
14
74
00
10
2,2
65,
352
333,9
14
90,6
14
135,9
21
2,8
25,8
00
1-
316
14
81
00
10
2,6
01,
972
383,5
32
104,0
79
156,1
18
3,2
45,7
00
1-
420
14
82
00
10
2,7
28,
395
402,1
67
109,1
36
163,7
04
3,4
03,4
00
1-
11
60
24
01
00
2,8
57,
784
421,2
39
114,3
11
171,4
67
3,5
64,8
00
1-
228
60
36
01
00
3,7
68,
799
555,5
23
150,7
52
226,1
28
4,7
01,2
00
1-
341
60
40
01
00
4,1
87,
911
617,3
01
167,5
16
251,2
75
5,2
24,0
00
1-
460
60
43
01
00
4,7
69,
200
702,9
83
190,7
68
286,1
52
5,9
49,1
00
1-
135
53
12
01
00
3,4
82,
764
513,3
62
139,3
11
208,9
66
4,3
44,4
00
1-
247
53
22
01
00
3,9
38,
913
580,5
98
157,5
57
236,3
35
4,9
13,4
00
1-
363
53
29
01
00
4,4
77,
553
659,9
94
179,1
02
268,6
53
5,5
85,3
00
1-
469
53
35
01
00
4,7
16,
611
695,2
31
188,6
64
282,9
97
5,8
83,5
00
1-
586
53
37
01
00
5,2
29,
197
770,7
87
209,1
68
313,7
52
6,5
22,9
00
1-
6124
53
38
01
00
6,3
36,
861
934,0
57
253,4
74
380,2
12
7,9
04,6
00
1-
131
15.5
70
00.5
01,8
69,
408
275,5
52
74,7
76
112,1
65
2,3
31,9
00
1-
240
15.5
14
00
0.5
02,2
06,
029
325,1
70
88,2
41
132,3
62
2,7
51,8
00
1-
357
15.5
21
00
0.5
02,7
73,
529
408,8
20
110,9
41
166,4
12
3,4
59,7
00
1-
494
15.5
35
00
0.5
03,9
95,
110
588,8
82
159,8
04
239,7
07
4,9
83,5
00
2-
126
15.5
25
00
0.5
01,9
22,
799
283,4
22
76,9
12
115,3
68
2,3
98,5
00
2-
234
15.5
32
00
0.5
02,2
30,
560
328,7
86
89,2
22
133,8
34
2,7
82,4
00
2-
364
15.5
39
00
0.5
03,1
73,
240
467,7
38
126,9
30
190,3
94
3,9
58,3
00
2-
471
15.5
45
00
0.5
03,4
41,
158
507,2
29
137,6
46
206,4
69
4,2
92,5
00
2-
587
15.5
51
00
0.5
03,9
68,
815
585,0
06
158,7
53
238,1
29
4,9
50,7
00
1-
136
51.5
14
00
0.5
03,2
44,
990
478,3
14
129,8
00
194,6
99
4,0
47,8
00
1-
277
51.5
28
00
0.5
04,5
82,
011
675,3
91
183,2
80
274,9
21
5,7
15,6
00
1-
3115
51.5
35
00
0.5
05,7
55,
572
848,3
75
230,2
23
345,3
34
7,1
79,5
00
1-
4122
51.5
42
00
0.5
06,0
34,
472
889,4
85
241,3
79
362,0
68
7,5
27,4
00
1-
5171
51.5
49
00
0.5
07,5
25,
493
1,1
09,2
62
301,0
20
451,5
30
9,3
87,3
00
2-
1214
51.5
52
00
0.5
08,7
99,
423
1,2
97,0
40
351,9
77
527,9
65
10,9
76,4
00
2-
2238
51.5
58
00
0.5
09,5
57,
961
1,4
08,8
49
382,3
18
573,4
78
11,9
22,6
00
2-
3250
51.5
59
00
0.5
09,9
15,
264
1,4
61,5
16
396,6
11
594,9
16
12,3
68,3
00
Pensu
lo 1
1 2
Pensu
lo 2
1 2
Zam
bezi
11
Mw
inilu
nga
11
Ndola
11
Tota
l(U
S$)
New
SS
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Uns
kille
dLab
or
LC
(U
S$)
Unit C
ost
(U
S$) & A
mount
33kV
DL
66kV
TL
Subs
tation
Feede
r
Chapter 7. Distribution System Planning
7-46
FC
(U
S$)
33/0.4
Tr
100kV
A2.5
MV
A5M
VA
10M
VA
15M
VA
(36,0
00)
(40,0
00)
(13,7
00)
(600,0
00)
(800,0
00)
(1,0
00,0
00)
(1,3
00,0
00)
(0.8
0166747)
(0.1
1816629)
(0.0
320667)
(0.0
4810005)
1-
157
19.5
11
00
0.5
02,7
91,9
67
411,5
38
111,6
79
167,5
18
3,4
82,7
00
1-
277
19.5
17
00
0.5
03,4
35,0
65
506,3
31
137,4
03
206,1
04
4,2
84,9
00
1-
384
19.5
22
00
0.5
03,6
91,9
99
544,2
03
147,6
80
221,5
20
4,6
05,4
00
1-
4108
19.5
26
00
0.5
04,4
28,5
71
652,7
74
177,1
43
265,7
14
5,5
24,2
00
1-
5127
19.5
30
00
0.5
05,0
20,8
43
740,0
75
200,8
34
301,2
51
6,2
63,0
00
2-
11
19.5
13
00
0.5
01,1
97,7
71
176,5
52
47,9
11
71,8
66
1,4
94,1
00
2-
225
19.5
24
00
0.5
02,0
11,2
23
296,4
56
80,4
49
120,6
73
2,5
08,8
00
2-
357
19.5
43
00
0.5
03,1
43,4
18
463,3
42
125,7
37
188,6
05
3,9
21,1
00
1-
128
19
33
00
0.5
02,1
80,6
16
321,4
24
87,2
25
130,8
37
2,7
20,1
00
1-
266
19
39
00
0.5
03,3
43,1
94
492,7
89
133,7
28
200,5
92
4,1
70,3
00
1-
370
19
45
00
0.5
03,5
24,5
31
519,5
18
140,9
81
211,4
72
4,3
96,5
00
2-
116
19
21
00
0.5
01,7
02,5
01
250,9
50
68,1
00
102,1
50
2,1
23,7
00
2-
224
19
31
00
0.5
02,0
43,2
10
301,1
70
81,7
28
122,5
93
2,5
48,7
00
1-
11
118
16
00
10
4,7
90,1
23
706,0
67
191,6
05
287,4
07
5,9
75,2
00
1-
2184
118
50
00
10
10,4
44,9
25
1,5
39,5
89
417,7
97
626,6
96
13,0
29,0
00
1-
3232
118
68
00
10
12,0
27,8
98
1,7
72,9
20
481,1
16
721,6
74
15,0
03,6
00
1-
4266
118
76
00
10
13,0
97,0
02
1,9
30,5
06
523,8
80
785,8
20
16,3
37,2
00
1-
18
11
12
00.5
00
1,0
36,0
75
152,7
18
41,4
43
62,1
65
1,2
92,4
00
1-
220
11
19
00.5
00
1,4
59,2
75
215,0
98
58,3
71
87,5
57
1,8
20,3
00
1-
352
11
27
00.5
00
2,4
70,6
59
364,1
77
98,8
26
148,2
40
3,0
81,9
00
2-
124
11
14
00.5
00
1,5
19,8
01
224,0
20
60,7
92
91,1
88
1,8
95,8
00
2-
238
11
24
00.5
00
2,0
33,6
70
299,7
64
81,3
47
122,0
20
2,5
36,8
00
1-
130
11.5
39
00
00.5
2,1
83,9
83
321,9
20
87,3
59
131,0
39
2,7
24,3
00
1-
287
11.5
63
00
00.5
4,0
92,5
93
603,2
51
163,7
04
245,5
56
5,1
05,1
00
2-
118
11.5
36
00
00.5
1,8
04,7
14
266,0
16
72,1
89
108,2
83
2,2
51,2
00
2-
246
11.5
50
00
00.5
2,7
66,5
54
407,7
92
110,6
62
165,9
93
3,4
51,0
00
2-
3140
11.5
66
00
00.5
5,6
55,1
23
833,5
69
226,2
05
339,3
07
7,0
54,2
00
1-
137
107
90
10
05,2
39,1
37
772,2
52
209,5
66
314,3
48
6,5
35,3
00
1-
262
107
16
01
00
6,0
37,5
18
889,9
34
241,5
01
362,2
51
7,5
31,2
00
1-
3120
107
22
01
00
7,7
77,2
97
1,1
46,3
78
311,0
92
466,6
38
9,7
01,4
00
1-
4154
107
28
01
00
8,8
24,4
35
1,3
00,7
27
352,9
77
529,4
66
11,0
07,6
00
1-
5164
107
33
01
00
9,1
67,9
49
1,3
51,3
62
366,7
18
550,0
77
11,4
36,1
00
1-
6253
107
36
01
00
11,7
69,4
40
1,7
34,8
23
470,7
78
706,1
66
14,6
81,2
00
1-
7274
107
39
01
00
12,4
08,4
50
1,8
29,0
13
496,3
38
744,5
07
15,4
78,3
00
1-
8293
107
41
01
00
12,9
78,7
56
1,9
13,0
77
519,1
50
778,7
25
16,1
89,7
00
1-
195
45
17
01
00
5,0
12,7
47
738,8
82
200,5
10
300,7
65
6,2
52,9
00
1-
2437
45
32
01
00
15,0
47,6
19
2,2
18,0
29
601,9
05
902,8
57
18,7
70,4
00
1-
3450
45
35
01
00
15,4
55,7
48
2,2
78,1
87
618,2
30
927,3
45
19,2
79,5
00
1-
4477
45
40
01
00
16,2
89,8
83
2,4
01,1
39
651,5
95
977,3
93
20,3
20,0
00
1 1
Sesh
eke
1
Sesh
eke
2
Senan
ga 3
1 2
Senan
ga 1
1
Senan
ga 2
1 2
Sam
fya
21 2
Sam
fya
1
1 2
Tota
l(U
S$)
New
SS
Fore
ign
Cost
sD
om
est
icC
ost
sSki
lled
Lab
or
Pac
kage
Unsk
illed
Lab
or
LC
(U
S$)
Unit C
ost
(U
S$)
& A
mount
33kV
DL
66kV
TL
Subst
atio
nFeeder
Chapter 7. Distribution System Planning
7-47
7.6. Discussion on Low Cost Electrification
7.6.1. Present Situation
We had a discussion with REA and ZESCO, and following contents were confirmed.
Commission year’s demand is used for distribution system design.
As for the voltage calculation for distribution line, it is carried out by hand calculation by ordinary. In case more detailed calculation is needed, PSS/E (Power System Simulation for Engineers) is used.
The design and construction of distribution line is carried out according to the ZESCO standard. This standard was established referring to British standard (BS).
To reduce the distribution cost, SWER (Single Wire Earth Return) system is adopted in a part of distribution system.
Some conductor disconnection accidents were occurred by the thunder.
7.6.2. Present Situation
Based on the result of present situation, following contents were proposed.
If distribution system is designed by using the commission year’s demand, it has a possibility to construct new distribution line shortly after new distribution line construction is finished. Therefore, it is necessary to make the distribution system reasonable in consideration of the future plan (future demand, distribution system planning around the target area), distribution system loss and so on.
Distribution line route will be selected in consideration of distance, road condition, geographical condition, etc. In addition, distribution system will be expanded and constitute the complex network in the future, and some loads of substation may be shift to other substations or construct new substation. Depending on this situation, it is recommended to adopt the software that could carry out distribution analysis easily base on the map information system. The following table shows the comparison of some kinds of software.
The facility cost of SWER is cheaper, but this it is easy to cause the unbalance of phase current by this system. Therefore, it is necessary to adjust the load on each phase to control the phase current.
As the ground wire is not applied to 33kV distribution line, the conductor disconnection by the thunder is occurred in some area. Therefore, it is necessary to collect and analyse the accident data, and compare the total cost of facility cost and O&M cost in the case of with or without ground wire. If the total cost is reduced in the case of with ground wire, it is recommended to modify the existing facilities in that area.
7-48
Chapter 7. Distribution System Planning