Upload
vodieu
View
223
Download
3
Embed Size (px)
Citation preview
145
Chapter 6
TRANSMISSION LOADING RELIEF
6.1. INTRODUCTION
Transmission Loading Relief (TLR) is a sequence of actions taken
during operations planning or during real-time operation to avoid or
remedy security violations associated with the transmission system.
Informal or “local” TLR has been in existence so long as
transmission lines have been subject to limitations. System planners
and operators have developed unique systematic procedures to
prevent transmission loading problems and they vary across the
interconnected grid of each control area. Issues of security raised due
to financial transactions are resolved by formal TLR procedures with
consistency and fairness. These procedures are briefly summarized
below.
The process starts when a security coordinator identifies a
transmission facility within its security area that is about to, or has
exceeded the operating security limit. At this point the security
coordinator may invoke TLR.
146
6.2. TLR PROCEDURES
This NERC TLR procedure involves following “levels” [37]:
TLR Level 1: Notify security coordinators of situation
In this level transmission system is secure. In this level, some of
the transmission facilities are exceed or approach their security limits
causes contingency of a transmission or generation, or other operating
problems The reliability coordinator will inform condition to other
reliability coordinator.
TLR Level 2: Hold interchange transactions at current level
In this level also transmission system is secure and one or more
transmission facilities are expected to approach, or are approaching,
or are at their operating security limit. The reliability coordinator
holds interchange transactions and allowed to change additional
interchange transactions with constraints. In this stage quick decision
required to move higher TLR Levels (3 and above) to allow interchange
transactions because it is a transient state. Time for this level is not
more than 30 minutes.
TLR Levels 3a: Reallocate firm and non-firm transmission service
In this level also transmission system is secure and one or more
transmission facilities are expected to approach, or are approaching,
or are at their operating security limit. The reliability coordinator shall
give preference to those interchange transactions using firm
transmission service, followed by those using higher priority non-firm
147
transmission service. According to the transmission service priorities
interchange transactions can be held or curtailed, shall be reallocated
(reloaded) within operating conditions permit.
TLR Level 3b: Curtail non-firm transactions
In this level also one or more transmission facilities are expected to
approach, or approaching, or at their operating security limit.
Curtailments are required for two reasons:
a) Interchange transactions for a higher priority transmission
service are allowed.
b) To mitigate an existing operating security limit violation.
During the period of operating security limit violation, all new
interchange transactions are held by the reliability coordinator using
non-firm transmission. Interchange transactions using firm
transmission service will be allowed.
TLR Level 4: Reconfigure transmission
In this level one or more transmission facilities are operating above
their security limit. Before the reliability coordinator orders
curtailment of interchange transactions using firm transmission
service, he will request the transmission providers in his reliability
area to attempt to reconfigure their transmission systems to allow the
interchange transactions to continue. Transmission reconfiguration
may be implemented as long as it does not jeopardize the operating
security of the interconnection. Transactions using non-firm
148
transmission service will be curtailed or held from starting. Some
transactions using firm transmission service will be allowed to start.
TLR Level 5a: Reallocation of transmission services
In this level one or more transmission facilities are operating at
their security limit and the system is secure. At this point, the
reliability coordinator shall begin the process of curtailing interchange
transactions using firm transmission service until the operating
security limit violation has been mitigated. Further reconfiguration of
transmission services is not possible or effective. Available re-dispatch
options will continue to be implemented.
TLR Level 5b: Curtail firm transmission service
In this level one or more transmission facilities are operating above
their security limit and all non-firm interchange transactions are at or
above curtailment threshold. Further reconfiguration of transmission
services is not possible or effective. A three-step process is followed for
curtailment of firm interchange transactions:
• Identifying the known re-dispatch options.
• Calculating the percent of overload due to constrained
transactions.
• Curtailments of firm interchange transactions.
Available re-dispatch options will continue to be implemented.
149
TLR Level 6: Implement emergency procedures
In this level one or more transmission facilities are operating above
their security limit due to the removal from service of a generating
unit or another transmission facility. If the transmission loading
condition is deemed critical to bulk system reliability by a reliability
coordinator, the reliability coordinator has the authority to
immediately direct the control areas in his reliability area to re-
dispatch generation, or reconfigure transmission, or reduce load to
mitigate the critical condition until interchange transactions can be
reduced utilizing the TLR procedures or other procedures to return the
system to a secure state. All control areas should comply with all
requests from their reliability coordinator. However, the control area
operator should immediately notify his reliability coordinator if the
reliability coordinator’s request is unclear or would seem to cause an
operating problem.
TLR Level 0 – TLR concluded
The TLR procedures initiated by the reliability coordinator should
be notified to all other reliability coordinators within the
interconnection to operate the system in a “normal” state, allowing
reestablishment of interchange transactions according to the
transmission priorities.
150
6.3. LIMITATIONS
The transmission relief procedure depends on the results of off-line
ATC, which has a number of limitations:
a) Computation of off-line ATC doesn’t consider the effect of the
actual transactions in/out of the region. It is a non-
simultaneous computation.
b) The non-peak hour operating conditions differ from that at peak
hour. Generally, the magnitude of flows will be larger at the
peak hour and the most restrictive condition is computed for
ATC. Sub-utilization of system capabilities is resulted when ATC
is underestimated during non-peak hours.
c) Numerical errors are present in off-line ATC because it often
neglects the influence of reactive power, uses linear models and
assumes constant distribution factors.
6.4. PROBLEMS IN TLR DUE TO THE ABOVE
LIMITATIONS
These limitations create the following problems in TLR:
a) By using daily offline ATC computations can result in
inaccurate TLR decisions.
b) New constrained facilities can be originated when TLR
procedures are implemented.
151
c) There is a need of precise and fast coordination among all the
coordinators and participants in the operating grid since TLR is
an iterative process that changes from one level to another.
d) Market’s efficiency is affected due to the opens opportunities for
economic gaming of TLR procedures.
6.5. METHODS TO ALLEVIATE TRANSMISSION LOADING RELIEF
The following are some of typical means of controls to mitigate the
transmission emergencies.
1. Generator active power adjustment
2. Phase angle regulator adjustment
3. Interchange schedule adjustment
4. Generator reactive power adjustment
5. Transformer tap adjustment
6. Shunt capacitor/reactor switching or synchronous condenser
adjustment
7. Transmission line switching
8. Pumped storage generator operation
9. Economic load Management/Customer load shedding
10. Distributed generation
11. Transmission System Expansion
The following are the methods listed and explained below, to
alleviate transmission loading relief.
1. Sensitivity based load curtailment
152
2. Economic load management
3. VAR support
4. Re-dispatching and coordinated re-dispatching
5. Counter trading
1. Sensitivities based load curtailment:
In this method, load curtailment is done by use of the system
sensitivities those are PTDFs, LODFs and TLRs. PTDFs determine the
sensitivity of the flow on an element such as transmission line to a
single power transfer. TLR Sensitivities determine the sensitivity of the
flow on the single monitored element such as a transmission line to
many different transactions in the system. In other words, TLR
sensitivities gauge the sensitivity of a single monitored element to
many different power transfers. Transmission Line Relief (TLR)
sensitivities can be considered as the inverse of the Power Transfer
Distribution Factors (PTDFs). Both TLR sensitivities and PTDFs
measure the sensitivity of the flow on a line to load curtailment.
2. Economic load management for transmission loading relief:
Another possible solution for TLR management is to find customers
who will volunteer to lower their consumption when transmission
congestion occurs. By lowering the consumption, the congestion will
“disappear” resulting in a significant reduction in bus marginal costs.
A strategy to decide how much load should be curtailed for what
customer is discussed here. The anticipated effect of this congestion
relief solution is to encourage consumers to be elastic against high
153
prices of electricity. Hence, this congestion relief procedure could
eventually protect all customers from high electricity prices in a
deregulated environment. A set of indices are used to represent the
level of effective and agreeable load curtailment in congested
conditions.
This method has three indices that are computed to calculate the
overall index for the load management. The three factors considered
for the index calculations are:
1. Power Flow Effect through Sensitivity Index,
2. Economic Factor for Locational Marginal Price (LMP) Index, and
3. Load Reduction Preference for customer load curtailment index.
3. VAR support:
In the present day scenario, unplanned power transactions are
rapidly increasing due to the competition among utilities to meet
increasing demand and if transactions are not properly controlled,
transmission lines are often operated and stressed to the limit. The
increased use of existing transmission is made possible, in part, by
reactive power compensation. The role of VAR support in the open
power market is to help manage congestion. Better utilization of the
existing power system to increase power transfer capability by
installing VAR support such as capacitor banks and FACTS (Flexible
AC Transmission Systems) devices becomes imperative. Capacitors,
Static VAR Compensator (SVC), Thyristor Controlled Series Capacitor
154
(TCSC), Unified Power Flow Controller (UPFC), are some of the
examples of FACTS devices used for VAR support.
The main advantage of FACTS devices is the possibility of their
installation for a short period compared to the planning and
construction of new transmission lines. FACTS not only improve the
transmission capacity but also reduce the losses. However, FACTS
devices are expensive.
4. Re-dispatching and coordinated re-dispatching:
Re-dispatching and coordinated re-dispatching involve re-
dispatching of generating units to relieve part of congestion. It comes
down to the introduction of corrections to the initial generation
dispatch, usually based on the prices that generators communicate to
the System Operator (SO) for up and down regulation. It might also be
a separate market. Two alternatives can be considered. If the SO only
intervenes within its own control area, the system can be optimized
locally (internal re-dispatch). A more comprehensive approach involves
several SOs and tries to find a global optimum by re-dispatching units
on both sides of the congested interconnector (coordinated re-
dispatch). The latter has the advantage of being more efficient, since
there are more nodes where power injections can be modulated.
However, it requires a strong co-ordination between SOs involved and
harmonization of market rules in the areas involved.
Re-dispatching, however, means incurring costs that cover
payments to generators for up and down regulation. This cost is borne
155
first by the SO, and can be charged in a second phase to the market
players. Re-dispatching costs are usually socialized (for example
included in transmission tariffs), but they can also be charged to
specific users causing congestion.
Re-dispatching is an effective method to solve congestion if enough
resources are available to change the load flow pattern and balance
the line loading better. If more than one SO is involved the
effectiveness increases even more, as more units are available for the
purpose. However, in some cases re-dispatching can fail to alleviate
congestion, which calls for measures as pro rata curtailment.
5. Counter trading:
The basis of Counter Trading is to make use of the electricity laws,
namely of the fact that electricity flows in opposite directions can be
net off, allowing alleviation of congestion. In order to provoke an
electricity flow in the direction opposite to congestion, the SO steps
into the market and intervenes. It buys electricity in the control zone
downstream of congestion and sells it back in the control zone
upstream. However, this intervention comes at a price. The control
zone downstream of congestion is usually a high price area. Therefore,
counter-trading involves buying expensive electricity in order to sell it
back in the low price area, making a loss. This loss is covered by
transmission tariffs.
The method, though simple, has some important drawbacks. First
of all, it assumes that a counter-trade between zones can always solve
156
inter-zonal congestion. This assumption does not have to be correct.
Zones are the aggregation of nodes. A zonal approximation thus
assumes that any transaction between zones has an identical effect on
the interconnection between them. This is obviously not true for a
network in which zones are interconnected by more than one line and
the error increases with the increased level of meshing. In order to be
able to effectively solve congestion, the SO would have to know the
topology of the network and the exact location of the involved power
injection and sink points.
In this thesis, sensitivities based load curtailment method is used.
In this method, first PTDFs are calculated and ATC is calculated by
use of these PTDFs. The ATC is calculated and updated for each
transaction on hour-ahead based.
6.6. HOUR-AHEAD ATC
Computation of hour-ahead ATC is same as off-line ATC and for
the next hours it operates on the planned model. It is used in the
Energy Management System (EMS) study mode to meet data
integration challenges.
The difficult part of hour-ahead ATC is data management and
modeling that is because the system consists thousands of buses, and
hundreds of directions and contingencies in few minutes.
To accurately compute ATC, the following information must be
provided to the solver:
157
System and transaction data: network topology, equipment
parameters, control settings, load profile, generation profile, external
model description, interchange schedule, contingency description,
subsystem description, direction description.
From existing technologies, ATC for the next hour can be computed
as follows.
Step 1. Obtain a base system case. This would give a base
topology description, generation schedule and base power
flows.
Step 2. Using system and bus load forecast functions, system
model modifications are also included to the loads.
Update generation settings and base flows, run for OPF.
Step 3. For next hour case, compute the PTDFs by solving the
power flows.
Step 4. Compute ATC based on linear methods for confirmed
reservations using a transaction analyzer which could
also be used for computations such as contingency
analysis, sensitivity analysis, interchange distribution
calculations, transaction arrangement and transmission
loading relief.
For over future hour models, hour-ahead ATC would run cyclically
and also on operator demand or new reservations are confirmed. The
economic and reliability goals of the hourly-market are achieved by
158
this core function of information system. A flow chart of the functions
is given in Appendix C.3.
6.7. TYPES OF TRANSACTIONS
In open-access electricity markets transactions can be done in
three different ways. They are:
A. Simultaneous transactions
B. Sequential transactions: off-line ATC
C. Sequential transactions-updated ATC
6.7.1. Simultaneous transactions
In a system, suppose that the transmission reservations occur
simultaneously [47], [48]. If these transactions are implemented, there
is a chance that one or more lines may be overloaded. When this
schedule is analyzed prior to implementation, TLR will have to be
invoked to relieve the overloading of these lines. Each participating
control area for the transaction will implement a local TLR procedure,
which would imply the rearrangement of its own resources, or ask the
security coordinator for a TLR procedure, which would require the
rearrangement of the resources of all the interconnection entities
involved in the transaction. Once TLR is initiated, the process
determines for each type of transaction the impact of those that affect
the loading of the facility in 5% or more based on PTDFs [51]. Then
transactions are curtailed in a progressive, prioritized manner. If no
more transactions can be curtailed, the process goes to the next TLR
level.
159
6.7.2. Sequential transactions: off-line ATC
As an alternative approach, consider a sequence of transactions
starting from base case. In this case, ATC values remain as those
computed by the off-line ATC process as the transactions take place.
1). At time t1 marketer M1 proposes a transaction in one
direction. The transfer should create no problem if there is
ATC available after the transaction is implemented.
2). At time t2 marketer M2 reads ATC for another direction and
proposes a transaction T2. There may be a chance of
overload if the transaction T2 is made considering the ATC
values prior to transaction T1 that needs to be relieved.
So, TLR procedure should be invoked to relieve this overload.
Note that in this case that for proposed transactions the values
of unreserved ATC do not change and therefore the capability for each
direction is assumed to be the one that was computed for the base
case. As this is a non-simultaneous process, new transactions can
overload the system. TLR will be needed even though the transactions
were based on posted ATC values.
6.7.3. Sequential transactions-updated ATC
Because of the disadvantage of invoking TLR procedures in the
sequential off-line ATC method, we go for this case. Start again with
the system at the initial operating point.
160
1). At time t1 marketer M1 proposes a transaction in one
direction. The transfer should create no problem if there is
ATC available after the transaction is implemented.
2). ATC values are recomputed and updated.
3). At time t2 marketer M2 reads ATC for another direction and
proposes a transaction T2. As the transaction is made based
on the updated ATC values, there should be no overload.
4). ATC values are recomputed and updated after each
transaction.
This case is an ideal case in which ATC is updated each time a
transaction takes place, is proposed, or a reservation is made. Note
that ATC values remain positive. For this ideal case, no TLR procedure
is required [93].
If a continuous ATC computation is possible, and transactions are
based on updated ATC data we can think of transactions as moving
within a secure transactional space.
6.8. RESULTS AND DISCUSSION
6.8.1. 7-bus system
The computations were done on 7-bus test system with 3-areas as
shown in Figure 6.1. Data for this system is given in Appendix A.1.
161
Figure 6.1: 7-bus test system
The system has been divided into three areas, namely; area A, area
B and area C. Area A includes buses 1, 2, 3, 4 and 5. Area B consists
of bus 6 whereas area C consists of bus 7. ATC values at initial
operating are shown in Table 6.1.
Table 6.1: 7-bus case, ATC data
Transfer
areas
Transfer
buses
ATC
(MW)
Limiting
line
A-B
1-6 54 1-2
2-6 265 2-6
4-6 281 2-6
A-C
1-7 56 1-2
2-7 106 2-5
4-7 152 4-5
B-C 6-7 111 6-7
162
6.8.1.1. Example-I of 7-bus system
Case A: Simultaneous transactions
Given this system data, suppose that the following transmission
reservations occur, which are all possible after the initial posting:
Direction 1-6:50MW
Direction 2-6:200MW
Direction 4-6:200MW
If these transactions are implemented, line 1-2 will have an over
load of 22% and line 2-6 will have an over load of 95%. When this
schedule is analyzed prior to implementation, TLR will have to be
invoked to relieve the overloading of these lines.
Case B: Sequential transaction: off-line ATC
As an alternative approach, consider a sequence of transactions
starting at the initial operating point used above. In this case, ATC
values remain as those computed by the off-line ATC process as the
transactions take place.
1. At time t1 marketer M1 proposes a transaction T1 of 50 MW from
A-B in the direction 1-6. As ATC is 54MW, the transfer should
create no problem and there should be 4MW available for
direction 1-6 after the transaction is implemented.
2. At time t2 marketer M2 reads ATC for direction 2-6 to be 265MW
and proposes a transaction T2 of 200MW. As a result, line 1-2
and 2-6 are operating near full load.
163
3. At time t3 marketer M3 reads ATC for direction 4- 6 as 281MW
and proposes a transaction T3 of 200 MW. The final results will
be overloads of 22% in line 1-2, 95% in line 2-6. TLR must be
applied in order to relieve the loading of these lines. Sequential
ATC data for this example is given in Table 6.2.
Table 6.2: Sequential ATC data of Example-I of 7-bus system
Transfer t0 t1 t2 t3
Area Bus ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
A-B 1-6 54 1-2 4 1-2 4 1-2 4 1-2
2-6 265 2-6 265 2-6 65 2-6 65 2-6
4-6 281 2-6 281 2-6 281 2-6 81 2-6
A-C 1-7 56 1-2 56 1-2 56 1-2 56 1-2
2-7 106 2-5 106 2-5 106 2-5 106 2-5
4-7 152 4-5 152 4-5 152 4-5 152 4-5
B-C 6-7 111 6-7 111 6-7 111 6-7 111 6-7
The numbers highlighted in Tables are ATC remaining after a
transaction is performed. If all the ATC numbers were computed after
t3 the results would be as shown in Table 6.3.
Table 6.3: ATC for final conditions of Example-I of 7-bus system
Transfer t3
Areas Buses ATC (MW) Limiting line
A-B
1-6 -168 1-2
2-6 -166 2-6
4-6 -186 2-6
164
A-C
1-7 -448 1-2
2-7 -438 2-5
4-7 -513 4-5
B-C 6-7 87 6-7
Case C: Sequential transaction-update ATC
Start again with the system at the initial operating point given in
Table 6.1.
1. As in Case B, at time t1 marketer M1 proposes a transaction T1
of 50 MW from A-B in the direction 1-6. As ATC is 54MW, 4MW
remain shown in column t1.Other ATC values are recomputed
and updated in column t1, the constraining elements can also
change.
2. At time t2 marketer M2 proposes a transaction in direction 2-6
of 200 MW. As ATC is 220MW there should be no problem. All
other ATC values are recomputed.
3. At time t3 marketer M3 proposes a transaction in direction 4-6
of 10 MW. As ATC is 26MW there should be no problem. All
other ATC values are recomputed.
4. At time t4 transaction T1 is cancelled relieving 50MW
indirection 1-6. All other ATC values are recomputed.
Sequential transactions-update ATC data for this example is given
in Table 6.4.
165
Table 6.4: Sequential transactions- update ATC of Example-I of 7-
bus system
Transfer t0 t1 t2 t3 t4
Area Bus ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
A-B
1-6 54 1-2 4 1-2 9 1-2 4 1-2 54 1-2
2-6 265 2-6 220 2-6 25 2-6 13 2-6 59 2-6
4-6 281 2-6 28 1-2 26 2-6 14 2-6 62 2-6
A-C
1-7 56 1-2 6 1-2 9 1-2 5 1-2 56 1-2
2-7 106 2-5 98 2-5 54 2-5 34 2-6 63 2-5
4-7 152 4-5 34 1-2 57 1-2 30 1-2 90 2-5
B-C 6-7 111 6-7 123 6-7 68 2-5 69 2-5 79 2-5
Figure 6.2: Secure transactional space for transactions in Example I
T2 (2-6)
T1 (1-6)
to
t1
T3 (4-6)
281
54
265
26
225
t 2
166
Secure transactional space: A secure transactional space (as
mentioned earlier) is now created based on the above sequential
updated ATC data. This space gives the limits for future transactions
and all transactions are to be made within its limits to reduce the
chance of overloading. It can be seen that each time a transaction is
proposed, the secure transactional space changes (it can be reduced
or augmented).
For the transactional space shown in the above Figure 6.2, the
coordinates are the transactions in directions 1-6, 2-6 and 4-6. The
center of coordinates (0, 0, 0) represents the initial operating point
where no transactions take place. At this point the secure
transactional space is given by cube t0 with dimensions {54, 265,
281}. Then T1 results in a secure transactional space given by cube t1
with dimensions {4, 220, 28}. T2 moves the operating point to (50,
200, 0) and ATC results in a secure transactional space given by cube
t2 with dimensions {9, 25, 26}. T3 moves the operating point to (50,
200, 10) and so on. As it can be seen, each time a transaction is
proposed, the secure transactional space changes (it can be reduced
or augmented) after ATC values and the distances to each boundary
are given by the ATC value for that direction.
6.8.1.2. Example-II of 7-bus system
Given this system data, suppose that the following transmission
reservations occur, which are all possible after the initial posting:
167
Direction 1-7: 50MW
Direction 2-7: 90MW
Direction 4-7: 140MW
If these transactions are implemented, line 1-2 will have over load
of 7%, line 2-5 will have over load of 64%, line 5-7 will have over load
of 29% and line 6-7 will have an over load of 45%. Sequential ATC
data for this example is given in Table 6.5.
Table 6.5: Sequential ATC data of Example-II of 7-bus system
Transfer t0 t1 t2 t3
Area Bus ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
A-B 1-6 54 1-2 54 1-2 54 1-2 54 1-2
2-6 265 2-6 265 2-6 265 2-6 265 2-6
4-6 281 2-6 281 2-6 281 2-6 281 2-6
A-C 1-7 56 1-2 6 1-2 6 1-2 6 1-2
2-7 106 2-5 106 2-5 16 2-5 16 2-5
4-7 152 4-5 152 4-5 152 4-5 12 4-5
B-C 6-7 111 6-7 111 6-7 111 6-7 111 6-7
If all the ATC numbers were computed after t3 the results would be
as shown in Table 6.6. Sequential transactions-update ATC data for
this example is given in Table 4.7. Secure transactional space is
shown in the Figure 6.3.
168
Table 6.6: ATC for final conditions sequential ATC data of
Example-II of 7-bus system
Table 6.7: Sequential transactions - update ATC sequential ATC
data of Example-II of 7-bus system
Transfer t0 t1 t2 t3 t4
Area Bus ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
A-B
1-6 54 1-2 7 1-2 5 1-2 3 1-2 51 1-2
2-6 265 2-6 248 2-6 37 2-5 15 2-5 239 2-5
4-6 281 2-6 36 1-2 25 1-2 17 1-2 258 2-6
A-C
1-7 56 1-2 07 1-2 5 1-2 3 2-5 50 2-5
2-7 106 2-5 61 2-5 08 2-5 3 2-5 48 2-5
4-7 152 4-5 44 1-2 10 2-5 05 2-5 68 2-5
B-C 6-7 111 6-7 78 2-5 9 2-5 4 2-5 60 2-5
Transfer t3
Areas Buses ATC (MW) Limiting line
A-B 1-6 -852 2-5
2-6 -651 2-5
4-6 -67 1-2
A-C 1-7 -136 1-2
2-7 -130 2-5
4-7 -185 2-5
B-C 6-7 -162 2-5
169
Figure 6.3: Secure transactional space for transactions in Example II
6.8.1.3. Example-III of 7-bus system
Given this system data, suppose that the following transmission
reservations occur, which are all possible after the initial posting:
Direction 4-6: 200MW
Direction 2-6: 200MW
Direction 6-7: 80MW
If these transactions are implemented, line 1-2 will loaded about
95% and line 2-6 will have an over load of 52%. Sequential ATC data
for this example is given in Table 6.8. If all the ATC numbers were
computed after t3 the results would be as shown in Table 6.9.
T3 (4-7)
152
t0
t 1 44
56
61
50
6
T1 (1-7)
T2 (2-7)
106
170
Table 6.8: Sequential ATC data sequential ATC data of Example-III
of 7-bus system
Transfer t0 t1 t2 t3
Area Bus ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
A-B 1-6 54 1-2 54 1-2 54 1-2 54 1-2
2-6 265 2-6 265 2-6 65 2-6 65 2-6
4-6 281 2-6 81 2-6 81 2-6 81 2-6
A-C 1-7 56 1-2 56 1-2 56 1-2 56 1-2
2-7 106 2-5 106 2-5 106 2-5 106 2-5
4-7 152 4-5 152 4-5 152 4-5 152 4-5
B-C 6-7 111 6-7 111 6-7 111 6-7 31 6-7
Table 6.9: ATC for final conditions of Example-III of 7-bus
system
Sequential transactions-update ATC data for this example is given
in Table 6.10. Secure transactional space is shown in the Figure 6.4.
Transfer t3
Areas Buses ATC (MW) Limiting line
A-B 1-6 -75 2-6
2-6 -75 2-6
4-6 -79 2-6
A-C 1-7 -201 2-6
2-7 -196 2-6
4-7 -231 2-6
B-C 6-7 -8 2-5
171
Table 6.10: Sequential transactions- update ATC of Example-III
of 7-bus system
Transfer t0 t1 t2 t3 t4
Area Bus ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
A-B
1-6 54 1-2 14 1-2 9 1-2 14 1-2 54 1-2
2-6 265 2-6 79 2-6 19 2-6 71 2-6 143 2-5
4-6 281 2-6 74 1-2 21 2-6 73 1-2 273 2-6
A-C
1-7 56 1-2 15 1-2 10 1-2 14 1-2 30 2-5
2-7 106 2-5 121 2-5 50 2-6 43 2-5 28 2-5
4-7 152 4-5 91 1-2 59 2-6 61 2-5 38 2-5
B-C 6-7 111 6-7 151 2-5 135 2-5 54 2-5 36 2-5
Figure 6.4: Secure transactional space for transactions in
Example III
T3 (6-7)
111
t0
t1
281
135
21
19
T1 (4-6)
T2 (2-6)
265
54
81 200
79
172
6.8.1.4. Example – IV of 7-bus system
Given this system data, suppose that the following transmission
reservations occur, which are all possible after the initial posting:
Direction 4-6: 200MW
Direction 4-7: 140MW
Direction 6-7: 80MW
If these transactions are implemented, line 1-2 will have over load
of 18%, line 2-5 will have over load of 31%, line 4-5 will have over load
of 9% and line 5-7 will have an over load of 33%.Sequential ATC data
for this example is given in Table 4.11. If all the ATC numbers were
computed after t3 the results would be as shown in Table 6.12.
Sequential transactions-update ATC data for this example is given in
Table 6.13. Secure transactional space is shown in the Figure 6.5.
Table 6.11: Sequential ATC data of Example-IV of 7-bus system
Transfer t0 t1 t2 t3
Area Bus ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
A-B
1-6 54 1-2 54 1-2 54 1-2 54 1-2
2-6 265 2-6 265 2-6 265 2-6 265 2-6
4-6 281 2-6 81 2-6 81 2-6 81 2-6
A-C
1-7 56 1-2 56 1-2 56 1-2 56 1-2
2-7 106 2-5 106 2-5 106 2-5 106 2-5
4-7 152 4-5 152 4-5 12 4-5 12 4-5
B-C 6-7 111 6-7 111 6-7 111 6-7 31 6-7
173
Table 6.12: ATC for final conditions sequential ATC data of
Example-IV of 7-bus system
Table 6.13: Sequential transactions- update ATC sequential ATC data of Example-IV of 7-bus system
Transfer t0 t1 t2 t3 t4
Area Bus ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
ATC
(MW)
Limit
line
A-B
1-6 54 1-2 14 1-2 2 1-2 2 1-2 16 1-2
2-6 265 2-6 78 2-6 60 2-6 80 2-5 128 2-5
4-6 281 2-6 73 1-2 7 1-2 8 1-2 87 2-6
A-C
1-7 56 1-2 15 1-2 2 1-2 2 1-2 17 2-5
2-7 106 2-5 121 2-5 84 2-5 16 2-5 56 2-5
4-7 152 4-5 90 1-2 10 1-2 10 1-2 80 2-5
B-C 6-7 111 6-7 151 2-5 105 2-5 20 2-5 70 2-5
Transfer t3
Areas Buses ATC (MW) Limiting line
A-B
1-6 -75 2-6
2-6 -75 2-6
4-6 -79 2-6
A-C
1-7 -201 2-6
2-7 -196 2-6
4-7 -231 2-6
B-C 6-7 -8 2-5
174
Figure 6.5: Secure transactional space for transactions in Example IV
6.8.2. 26-bus system
A 26-bus power system, taken from an example in a book by Sadat
is considered as a single area. Suppose that the following
transmission reservations occur, which are all possible after the initial
posting:
Direction 1-18: 200MW
Direction 2-12: 150MW
Direction 4-9: 150MW
If these transactions are implemented, line 1-18 will have over load
of 7% and line 7-9 and 4-12 will have an over load of 8%. When this
schedule is analyzed prior to implementation, TLR will have to be
invoked to relieve the overloading of these lines. Sequential
transactions-update ATC data for this case is given in Table 6.14.
T3 (6-7)
151
t0
t1
281
90
T1 (4-6)
T2 (4-7)
152
111
200 81
t2
175
‘Secure transactional space’ for this case is shown in Figure 6.6.
Table 6.14: Sequential transactions-update ATC for 26-bus system
Transferbus
t0 t1 t2 t3 t4
ATC (MW)
Limitingline
ATC (MW)
Limitingline
ATC (MW)
Limiting line
ATC (MW)
Limitingline
ATC (MW)
Limitingline
1-18 231 1-18 31 1-18 5 1-18 1 1-18 205 1-18
1-12 240 2-8 74 1-18 15 1-18 3 1-18 165 2-8
2-12 220 2-8 99 1-18 19 1-18 4 1-18 151 2-8
3-9 113 3-13 93 3-13 40 1-18 7 1-18 86 3-13
4-9 175 12-10 162 10-12 146 1-18 46 1-18 95 7-9
4-18 190 16-17 42 1-18 9 1-18 2 1-18 112 4-12
26-18 130 5-6 47 1-18 10 1-18 2 1-18 83 11-26
Figure 6.6: Secure transactional space for transactions of 26-bus system
6.8.3. IEEE 118- bus system
Suppose that the following transmission reservations occur, which
are all possible after the initial posting:
Direction 25-59: 700MW
T2 (2-12)
T1 (1-18)
220
t0
T3 (4-9)
231
175
160
99
200
145
80
t1
t2
176
Direction 100-45: 700MW
Direction 80-11: 700MW
If these transactions are implemented, line 8-5 will have over load
of 24% and line 68-81 and 80-81 will have an over load of 31%. When
this schedule is analyzed prior to implementation, TLR will have to be
invoked to relieve the overloading of these lines. Sequential
transactions-update ATC data for this case is given in Table 6.15.
‘Secure transactional space’ for this case is shown in Figure 6.7.
Table 6.15: Sequential transactions-update ATC for IEEE 118-bus system
Transfer t0 t1 t2 t3
Area Bus ATC
(MW)
Limiting line
ATC
(MW)
Limiting line
ATC
(MW)
Limiting line
ATC
(MW)
Limiting line
A-B
25-59 765 64-65 068 64-65 065 64-65 060 64-65
26-62 841 64-65 352 64-65 335 64-65 246 64-65
A-C
12-77 794 65-68 862 65-68 965 65-68 1048 65-68
26-90 836 65-68 909 65-68 1000 89-90 1007 89-90
B-A
54-11 861 38-65 835 38-65 770 38-65 665 38-65
65-27 842 38-65 816 38-65 754 38-65 650 38-65
B-C
54-77 697 65-68 758 65-68 848 54-56 864 68-69
65-82 580 65-68 630 65-68 705 65-68 673 68-69
C-A
80-11 801 65-68 739 65-68 90 81-80 89 81-80
92-32 910 65-68 835 65-68 358 81-80 100 81-80
C-B
87-54 300 86-87 300 86-87 300 86-87 93 81-80
100-45 808 86-87 700 65-68 327 81-80 77 81-80
177
Figure 6.7: Secure transactional space for transactions of IEEE 118-bus system
6.8.4. 124-bus real-time Indian utility power system of Andhra
Pradesh State grid
For this analysis in each area three independent transactions are
considered. ATC numbers used in this case are from the case 4 (a) i.e.
all generators are operating with CGS share and 100% load.
6.8.4.1. Transactions of area 1
Suppose that the following transmission reservations occur, which
are all possible after the initial posting:
Direction 30-31: 1100 MW
Direction 35-42: 700 MW
Direction 29-38: 300 MW
t1
T1 (25-59)
T3 (100-45)
T2 (80-11)
808
801
768
700
739
700
650
t0
t2
178
If these transactions are performed simultaneous transactions and
sequential transactions with off-line ATC, line 29-31 will have over
load of 10% and line 35-38 will have an over load of 66%. When this
schedule is analyzed prior to implementation, TLR will have to be
invoked to relieve the overloading of these lines.
Start with the system at the initial operating point as shown in
column t0.
1. At time t1 marketer M1 proposes a transaction T1 of 1100 MW in
the direction 30-31. As ATC is 1157MW, 57MW remain shown in
column t1.Other ATC values are recomputed and updated in
column t1, the constraining elements can also change.
2. At time t2 marketer M2 need to propose a transaction less than
140 MW in direction of 35-42 and the proposed transaction is
125MW. As ATC is 140MW there should be no problem. All other
ATC values are recomputed.
3. At time t3 marketer M3 need to propose a transaction less than
29MW in direction of 4-6 and the proposed transaction is 25
MW. As ATC is 29MW there should be no problem. All other ATC
values are recomputed.
Sequential transactions-update ATC data for this example is
given in Table 6.16. Secured transactional space for these
transactions is shown in Figure 6.8.
179
Table 6.16: Sequential transactions- update ATC in area 1 of 124-
bus real-time Indian utility power system of Andhra Pradesh State
Transfer
Bus
t0 t1 t2 t3
ATC
(MW)
Limiting
Line
ATC
(MW)
Limiting
Line
ATC
(MW)
Limiting
Line
ATC
(MW)
Limiting
Line
1-3 585 1-2 585 1-2 585 1-2 585 1-2
1-12 466 3-12 466 3-12 466 3-12 466 3-12
29-38 345 35-38 174 29-31 29 29-31 04 29-31
30-31 1157 29-31 57 29-31 03 29-31 01 29-31
30-36 626 40-84 147 29-31 25 29-31 06 29-31
29-33 389 33-30 389 33-30 389 33-30 389 33-30
35-42 776 35-38 140 29-31 15 29-31 06 29-31
Figure 6.8: Secure transactional space for transactions in Area 1
For the transactional space shown in the above Fig. 6.7, the
coordinates are the transactions in directions 1-6, 2-6 and 4-6. The
center of coordinates (0, 0, 0) represents the initial operating point
t1
T1 (30-31)
T3 (29-38)
T2 (35-42)
345
776
140 57
174
1157
t0 t2
180
where no transactions take place. At this point the secure
transactional space is given by cube t0 with dimensions {1157, 776,
345}. Then T1 results in a secure transactional space given by cube t1
with dimensions {57, 140, 174}. T2 moves the operating point to
(1100, 125, 29) and ATC results in a secure transactional space given
by cube t2 with dimensions {3, 15, 29}. T3 moves the operating point
to (1100, 125, 4) and so on. As it can be seen, each time a transaction
is proposed, the secure transactional space changes (it can be reduced
or augmented) after ATC values and the distances to each boundary
are given by the ATC value for that direction.
6.8.4.2. Transactions of area 2
Suppose that the following transmission reservations occur, which
are all possible after the initial posting:
Direction 46-21: 500 MW
Direction 15-16: 400 MW
Direction 50-59: 650 MW
If these transactions are performed simultaneous transactions and
sequential transactions with off-line ATC, line 15-16 will have over
load of 13%, line 50-59 will over load of 34%, line 57-58 will have over
load of 30%, and line 58-59 will have an over load of 6%. When this
schedule is analyzed prior to implementation, TLR will have to be
invoked to relieve the overloading of these lines. To avoid over loading
of lines need to perform following transactions.
181
Direction 46-21: 500 MW
Direction 15-16: 300 MW
Direction 50-59: 600 MW
Sequential transactions-update ATC data for this example is given
in Table 6.17.
Table 6.17: Sequential transactions- update ATC in area 2 of 124-
bus real-time Indian utility power system of Andhra Pradesh State
Transfer
bus
t0 t1 t2 t3
ATC
(MW)
Limiting
line
ATC
(MW)
Limiting
line
ATC
(MW)
Limiting
line
ATC
(MW)
Limiting
line
15-6 739 19-9 617 15-16 143 15-16 152 15-16
15-16 437 15-16 392 15-16 91 15-16 97 15-16
9-40 291 40-84 197 40-84 196 40-84 198 40-84
9-21 1120 19-9 1016 20-21 1009 19-9 1010 19-9
46-49 205 49-46 194 49-46 194 49-46 -150 57-58
46-21 572 21-47 72 21-47 141 21-47 171 21-47
50-59 682 57-58 682 57-58 685 57-58 80 57-58
50-63 324 57-63 324 57-63 324 57-63 210 50-59
6.8.4.3. Transactions of area 3
Suppose that the following transmission reservations occur, which
are all possible after the initial posting:
Direction 106-95: 600 MW
Direction 100-98: 350 MW
Direction 115-110:300 MW
182
If these transactions are performed simultaneous transactions and
sequential transactions with off-line ATC, line 102-115 over load by 3
% (double circuit), line 109-110 will over load of 6%, line 100-101will
have over load of 13% (double circuit), line 101-97 will have an over
load of 3% and line 97-98 will have an over load of 44%. When this
schedule is analyzed prior to implementation, TLR will have to be
invoked to relieve the overloading of these lines. To avoid over loading
of lines need to perform following transactions.
Direction 106-95: 600 MW
Direction 100-98: 70 MW
Direction 115-110: 275 MW
Sequential transactions-update ATC data for this example is given
in Table 6.18.
Table 6.18: Sequential transactions- update ATC in Area 3 of 124-bus real-time Indian utility system of Andhra Pradesh
Transfer
bus
t0 t1 t2 t3
ATC
(MW)
Limiting
line
ATC
(MW)
Limiting
line
ATC
(MW)
Limiting
line
ATC
(MW)
Limiting
line
115-110 337 109-110 337 109-110 337 109-110 59 109-110
115-117 196 117-102 190 117-102 190 117-102 133 102-115
100-116 337 109-110 315 100-101 227 100-101 222 100-101
100-98 397 97-98 77 97-98 07 97-98 36 97-98
100-97 525 101-97 239 101-97 178 100-101 174 100-101
104-123 446 101-103 432 101-103 432 101-103 463 101-103
106-101 910 100-101 330 106-101 295 100-101 288 100-101
106-95 737 97-98 137 97-98 13 97-98 67 97-98
183
6.8.4.4. Transactions of area 4
Suppose that the following transmission reservations occur, which
are all possible after the initial posting:
Direction 85-89: 1100 MW
Direction 78-83: 700 MW
Direction 85-88: 650 MW
If these transactions are performed simultaneous transactions and
sequential transactions with off-line ATC, line 85-88 over load by 54%,
and line 83-85 will operates at 98% of it MVA rating. When this
schedule is analyzed prior to implementation, TLR will have to be
invoked to relieve the overloading of these lines. To avoid over loading
of lines need to perform following transactions.
Direction 85-89: 1100 MW
Direction 78-83: 700 MW
Direction 85-88: 125 MW
Sequential transactions-update ATC data for this example is given
in Table 6.19.
Table 6.19: Sequential transactions- update ATC in area 4 of 124-bus real-time Indian utility power system of Andhra Pradesh State
Transfer
bus
t0 t1 t2 t3
ATC
(MW)
Limiting
line
ATC
(MW)
Limiting
line
ATC
(MW)
Limiting
line
ATC
(MW)
Limiting
line
85-89 1288 85-89 183 85-89 220 85-89 60 85-88
85-88 667 85-88 127 85-88 154 85-88 29 85-88
85-92 1093 87-92 1086 87-92 1093 87-92 1093 87-92
184
85-81 1042 81-82 1053 81-82 69 83-85 68 83-85
85-77 1292 81-77 1284 81-77 89 83-85 89 83-85
78-79 477 77-79 475 77-79 680 78-79 680 78-79
78-81 1119 81-82 1132 81-82 250 83-85 249 83-85
78-83 778 83-85 764 83-85 62 83-85 32 83-85
With these case studies and by developing more case studies for
different possible transactions, it is possible to incorporate hour-
ahead ATC functions that minimize the need for TLR as well as
enhance the utilization of transmission resources. The reduction of
the need for TLR may also be achieved by minimizing misuse of ATC,
or through alternative concepts that are more accurate and flexible for
use in reserving contract paths.
6.9. SUMMARY
In this chapter, different levels (stages) of North American Electric
Reliability Council (NERC) TLR procedures and their effects are
discussed. Different types of transactions that can be performed in
deregulated power system and their effects on transmission loading
are discussed and finally an algorithm using hour-Ahead ATC to
invoke TLR procedures is proposed. The results are discussed and
analyzed for basic 7-bus, 26-bus, IEEE 118-bus, and 124-bus-real
time Indian utility power system of Andhra Pradesh State grid.
185
Secured transactional space is defined for different transactions using
sequential transactions with update ATC to invoke TLR procedures.