27
POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM 0 1 Department of Electrical engineering , S.I.E.T, Dhenkanal WELCOME

6 PHASE TRANSMISSION SYSTEM

Embed Size (px)

Citation preview

Page 1: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

01Department of Electrical engineering , S.I.E.T, Dhenkanal

WELCOME

Page 2: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX

PHASE TRANSMISSION SYSTEM

Presented by:

S NAIBEDYA LALATENDU

EE-11s-05

1101230185

Under the guidance of:

AUROBINDO BEHERA

Asst. Professor

02Department of Electrical engineering , S.I.E.T, Dhenkanal

Page 3: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

WE WILL DISCUSS ON INTRODUCTION

POWER TRANSMISSION OPTIMIZATION

CONSTRUCTION OF SIX PHASE SYSTEM

FEASIBILITY

ECONOMIC CONSIDERATIONS

FAULTS & PROTECTION

CONSIDERATIONS FOR FUTURE DESIGN

CONCLUSION

REFERENCE

03Department of Electrical engineering , S.I.E.T, Dhenkanal

Page 4: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

INTRODUCTION

High Phase Order(HPO) ?

What is six phase transmission system ?

Why is it required ?

Where has it been implemented ?

04Department of Electrical engineering , S.I.E.T, Dhenkanal

Page 5: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

SIX PHASE IMPLEMENTATION

IN 1978 THE US DEPT. OF ENERGY SPONSERED A PROJECT FOR CONSTRUCTION &

TESTING OF A 6 & 12 (336 METER) PHASE LINE IN MALTA,NEWYORK.

IN 1988 FIRST DESIGN TO DEMONSTRATE THE COMMERCIAL FEASIBILITY OF HPO

SYSTEM WAS UNDERTAKEN BY EMPIRE STATE ELECTRIC ENERGY RESEARCH

CORPORATION(ESEERCO) , NEWYORK STATE ELECTRIC & GAS CORPORATION(NYSEG)

POWER TECHNOLOGIES INCORPORATED(PTI).

IT WAS A 2.4 KM LINE BETWEEN GOUDEY & OKLADE SUBSTATIONS JUST OUTSIDE

BINGHAMTON , NY.

A 115 KV DOUBLE CKT 3 PHASE WAS RUN AS 93 KV 6 PHASE LINE(WHICH

INCIDENTLY WAS EQUIVALENT TO TWO , 161 KV DOUBLE CKT 3 PHASE LINE ).

05Department of Electrical engineering , S.I.E.T, Dhenkanal

Page 6: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

POWER TRANSMISSION OPTIMIZATION

What is Power Transmission Optimization ?

How can it be achieved ?

06Department of Electrical engineering , S.I.E.T, Dhenkanal

Page 7: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

Optimal protection and switching device placement

Generation scheduling

Maintenance scheduling

Operative control

Constrained load flow

Power plant operation optimizer

FACTS (Flexible AC Transmission System) control

Dynamic load modelling

Short-Term load forecast

Network reconfiguration and load reduction etc.

07Department of Electrical engineering , S.I.E.T, Dhenkanal

POWER OPTIMIZATION TECHNIQUES

Page 8: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

08Department of Electrical engineering , S.I.E.T, Dhenkanal

3Φ Voltage(KV)

6Φ Voltage(KV)

Power Increment Factor

69 69 1.732

115 93 1.38

138 138 1.732

POWER OPTIMIZED USING SIX PHASE TRANSMISSION

Page 9: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

CONSTRUCTION OF SIX PHASE TRANSMISSION SYSTEM

09Department of Electrical engineering , S.I.E.T, Dhenkanal

THREE PHASE TO SIX PHASE CONVERSION USING TRANSFORMERS

Page 10: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

010Department of Electrical engineering , S.I.E.T, Dhenkanal

Vph = Vline for six phase system

SIX PHASE VOLTAGE PHASOR DIAGRAM

Page 11: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

011Department of Electrical engineering , S.I.E.T, Dhenkanal

SIX PHASE VOLTAGE PHASOR DIAGRAM

HENCE IT IS MATHEMATICALLY PROVED THAT Vph =Vline

Page 12: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

FEASIBILITY(TRANSFER CAPABILITY)

Consider 3 practical cases as follows :

A: 138 KV, 3 phase double circuit line configuration

B: 230 KV, 3ph transmission line configuration

C: 138 KV, 6 phase transmission line configuration

12Department of Electrical engineering , S.I.E.T, Dhenkanal

Page 13: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

FEASIBILITY(ELECTRIC FIELD)

13Department of Electrical engineering , S.I.E.T, Dhenkanal

Page 14: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

FEASIBILITY(LIGHTNING PERFORMANCE)

14Department of Electrical engineering , S.I.E.T, Dhenkanal

SYSTEM VOLTAGE(PHASE-GROUND)

MAX (KV)

SYSTEM PHASE ORDER

BASIC LIGHTNING INSULATION LEVEL

MIN BIL(KV) MAX BIL(KV)

83.72 450 450

450 450

139.72 3 650 750

6 750 900

209.60 3 900 1050

6 1050 1050

317.55 3 1425 1425

6 1550 1675

461.89 3 1925 2050

6 2050 2175

Page 15: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

FEASIBILITY(RELIABILITY ASPECT)

More power demand can be met at the load point since power transfer capability is more in 6 phase systems.

Voltage regulation and efficiency are better due to less inductive reactance of the 6 phase line for the same power transfer.

It is proved that six phase line is more stable for both symmetrical & unsymmetrical faults.

15Department of Electrical engineering , S.I.E.T, Dhenkanal

Page 16: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

OTHER SALIENT POINTS

16Department of Electrical engineering , S.I.E.T, Dhenkanal

IN CHANGING EXISTING THREE PHASE SYSTEM TO SIX PHASE SYSTEM

RADIO NOISE DECREASES BY 8.6 Db.

AUDIBLE NOISE DECREASES BY 12.1 Db.

PEAK SURFACE ELECTRIC FIELD GRADIENT CHANGED FROM

14.04 to 10.51 KVARMS/cm.

TOTAL CORONA LOSS REDUCES ON A LINE CHANGED FROM THREE

PHASE DOUBLE CIRCUIT TO SIX PHASE LINE FROM 2046 W TO 338 W PER

CONDUCTOR. PERFECTLY COMPATIBLE WITH THE EXISTING THREE PHASE NETWORK. LINE SPACE COMPACTION. REDUCED SURGE IMPEDANCE LOADING.

DUE TO LESS ANGLE ( i.e. 60o)BETWEEN PHASES CURRENTS ARE BETTER

BALANCED.

Page 17: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

ECONOMIC CONSIDERATIONS

17Department of Electrical engineering , S.I.E.T, Dhenkanal

DUE TO SMALLER,LIGHTER STRUCTURES OF HPO LINES , THE LINE COST IS LESS THAN THAT OF CONVENTIONAL THREE PHASE LINE.

THE ADDED PHASE REQUIRES ADDITIONAL TRANSFORMER & CIRCUIT BREAKERS.

HENCE AFTER A BREAKEVEN DISTANCE (225.86 KM)SIX PHASE &

THREE PHASE LINES WILL COST EQUAL.

HOWEVER HERE Right of Way IS NOT TAKEN INTO CONSIDERATION DUE TO ITS VARIABLE NATURE.

Page 18: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

BREAKEVEN DISTANCE

18Department of Electrical engineering , S.I.E.T, Dhenkanal

THE BREKEVEN DISTANCE IS CALCULATED TO BE

BETWEEN 200 AND 250 KM.

BUT THE ACTUAL VALUE

IS 225.86 KM WHICH FALLS

EXACTLY WITHIN THE GIVEN LIMITS.

R = SOUTH AFRICAN RAND ;THE CURRENCY OF SOUTH AFRICA

Page 19: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

RIGHT OF WAY

19Department of Electrical engineering , S.I.E.T, Dhenkanal

THE ELECTRICITY (SUPPLY) ACT, 1948 CHAPTER V ,Section 53 ( Provision of accommodation and right of way)

(1) Where the Board for the purposes of any arrangements which it has made with any licensee under this Act requires accommodation on, in, under or over the premises of the licensee for any works or apparatus to be provided by the Board, the licensee shall, if suitable and sufficient accommodation exists, grant such accommodation free of cost to the Board, or if such accommodation does not exist, it shall be provided upon such terms and conditions as may be agreed between the Board and the licensee.

(2) The Board and any licensee shall each have a right of access at all times to his own property on, in, over and under the property of the other.

Page 20: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

SIX PHASE FAULTS

20Department of Electrical engineering , S.I.E.T, Dhenkanal

FAULT TYPE TOTAL NO. OF COMBINATIONS

SIGNIFICANT NO. OF

COMBINATIONS

FAULTED PHASES

6 PHASE 1 1 abcdef

6 PHASE TO NEUTRAL 1 1 abcdefg

5 PHASE 6 1 bcdef

5 PHASE TO NEUTRAL 6 1 bcdefg

4 PHASE 15 3 bcef,abcd,abdf

4 PHASE TO NEUTRAL 15 3 bcefg,abcdg,abdfg

3 PHASE 20 3 bdf,abd,abf

3 PHASE TO NEUTRAL 20 3 bdfg,abdg,abfg

2 PHASE 15 3 ad,bf,bc

2 PHASE TO NEUTRAL 15 3 adg,bfg,bcg

1 PHASE TO NEUTRAL 6 1 ag

TOTAL 120 23

Page 21: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

SIX PHASE PROTECTION SYSTEMS

21Department of Electrical engineering , S.I.E.T, Dhenkanal

THERE ARE THREE PROTECTION SCHEMES :

1. PRIMARY (PILOT BASED CURRENT DIFFERENTIAL RELAY)2. SECONDARY (FIBER OPTICS BASED SEGREGATED PHASE

COMPARISION PROTECTION)3. TERTIARY(NON COMMUNICATION BASED COMMONLY KNOWN AS

DISTANCE PROTECTION)

THERE ARE THREE TRIPPING OPTIONS :

1. SWITCHING ALL SIX PHASES SIMULTANEOUSLY2. SWITCHING AS SETS OF THREE PHASE LINES3. SWICHING ONE PHASE AT ATIME

Page 22: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

CONSIDERATIONS FOR FUTURE DESIGN

22Department of Electrical engineering , S.I.E.T, Dhenkanal

UPCOMING SUBSTATIONS & SWITCHYARDS MUST BE DESIGNED TO CATER THE EXTRA EQUIPMENTS REQUIRED FOR THREE TO SIX PHASE TRANSMISSION.

RESEARCH NEEDS TO BE DONE IN FINDING MORE ECONOMICAL WAYS FOR THE TRANSFORMATION OF EXISTING 3Φ SYSTEM TO 6ΦSYSTEM.

SPECAILIZED DESIGN APPROACH FOR INCREASED CAPACITY ON TERMINAL EQUIPMENTS.

Page 23: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

CONCLUSION

23Department of Electrical engineering , S.I.E.T, Dhenkanal

UNARGUABLY IT IS A POWERFUL METHOD OF TRANSMISSION BUT ECONOMICALLY INFEASIBLE AT THIS POINT OF TIME.

IN THE FORESEEABLE FUTURE , WITH RISE IN DEMAND & LAND COST IT WILL BECOME ECONOMICALLY MORE ACCEPTABLE.

IT IS VITALLY IMPORTANT TO BE AWARE OF THIS TECHNOLOGY AS A POSSIBLE KEY PLAYER IN FUTURE TRANSMISSION.

HOWEVER RESEARCH STILL NEEDS TO BE DONE TO FIND OUT MORE ECONOMICAL WAYS OF TRANSFORMING THE EXISTING THREE PHASE SYSTEMS TO SIX PHASE SYSTEMS SO THAT THE ECONOMICAL CONSTRAINTS COULD BE RELAXED TO A LARGER EXTENT.

Page 24: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

REFERENCES

24Department of Electrical engineering , S.I.E.T, Dhenkanal

[1] T.L.Landers , R.J Richeda , E. Krizakas . “High Phase Order Economics:Constructing a New Transmission Line,” IEEE Transaction on Power Delivery,Vol.13, No. 4, 1998.[2] T.F Dorazio . “High Phase Order Transmission”, IEEE 1990.[3] James R.Stewart , Laurie J.Oppel , Gary C. Thomann , ThomasF..Dorazio , Matthew T.Brown , “Insulation Coordination, Environmental andSystem Analyisis Of Existing Double Circuit Line Reconfigured To Six PhaseOperation”, IEEE Transaction on Power Delivery, Vol. 7, No. 3, 1993.[4] R. V. Rebbapragada , M.T.Brown , T.F Dorazio , J.R Stewart, “DesignModification And Layout Of Utility Substations For Six Phase Transmission,”IEEE Transaction on Power Delivery, Vol. 8, No. 1.[5] Alexander Apostolov , William George. “Protecting NYSEG’sSixPhase Transmission Line,” New York State Electric & Gas Corporation, 1992.[6] First A. Zakir Husain, Second B. Ravindra Kumar Singh, and Third C.Shri Niwas Tiwari , Multi-phase (6-Phase & 12-Phase) Transmission Linesperformance characteristics, INTERNATIONAL JOURNAL of MATHEMATICSAND COMPUTERS IN SIMULATION, Issue 2, Vol 1, 2007

Page 25: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

REFERENCES(CONT.)

25Department of Electrical engineering , S.I.E.T, Dhenkanal

[7] Venkata , S.S.; Guyker, W.C.; Booth, W.H.; Kondragunta, J.; Saini, N.K.;Stanek,E.K.; Energy Systems Group Department of Electrical EngineeringUniversity of Washington, 138-kV, six phase Transmission System, IEEE Trans,Volume PAS-101 Issue 5, May 1982.[8] Transmission Line Compaction Using High Phase Order Transmission ,Jacob Bortnik , A dissertation submitted to the faculty of Engineering ,University of Witwatersrand , Johannesburg for the fulfilment of Degree ofM.Sc in Engineering.[9] THE ELECTRICITY (SUPPLY) ACT, 1948, CHAPTER V:the works and tradingprocedure of the board and the generating company , SECTION 53 : provisionof accommodation and right of way[10] http://www.ukessays.com/essays/engineering/six-phase-converted-transmission-line-engineering-essay.php[11] Suresh Chandra , Srivasta M. , JSPL , Angul , Power optimizationusing six phase transmission system , AICTE sponsored National Seminar onPower & Energy system for Future – 26th & 27th april 2013,pages 8-10.

Page 26: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

26Department of Electrical engineering , S.I.E.T, Dhenkanal

Page 27: 6 PHASE TRANSMISSION SYSTEM

POWER OPTIMIZATION USING SIX PHASE TRANSMISSION SYSTEM

27Department of Electrical engineering , S.I.E.T, Dhenkanal