CCEB QM/FMCCEB QM/FMProduction Production StatusStatus
TIM CERN May.09TIM CERN May.09
Gert Viertel, Ulf Roeser, Andreas Sabellek
IEKP - Universität Karlsruhe (TH)
2009-05-10 TIM May09, CERN IEKP,Andreas Sabellek p.2
Univ. of Univ. of KarlsruheKarlsruhe
Cryocooler Electronics Cryocooler Electronics System OverviewSystem Overview
4 Cryocoolers
120 VDC infrom PDS
CAN BusJMDC
4 x VAC out
Cernox Cryogenic temperature sensors
Dallas temperature sensors
Zenith RadiatorsPT1000 Temperature sensors
3D Hall probes
HEAT
CCEB
USCM task program by A.Lebedevautonomously regulatespower to Cryocoolers
2009-05-10 TIM May09, CERN IEKP,Andreas Sabellek p.3
Univ. of Univ. of KarlsruheKarlsruhe
3
Cryocooler Electronics BoxCryocooler Electronics BoxUniversal SlowControl Module
Interface Board
Monitor & Oscillator
3D Hall Probeand PTS readout
CryoCooler PowerAmplifier Module
DC/DCConverter board
USCMUSCM
CCBT 0CCBT 1
CCIF 0 A/BCCIF 1 A/BCCIF 2 A/BCCIF 3 A/B
CCMO 0CCMO 1
CCPA 0 A/BCCPA 1 A/BCCPA 2 A/BCCPA 3 A/BCCDC A/B
ControlSide
PowerSide
CCEB CratesEM1: ETHZEM2: CERN (forCC operation)QM: in prod.FM: in prod.
2009-05-10 TIM May09, CERN IEKP,Andreas Sabellek p.4
Univ. of Univ. of KarlsruheKarlsruhe
FM/QM Board StatusFM/QM Board Status• Status: All boards were assembled and delivered by Contraves company Zürich by April, 30th
• Currently last board level test are performed at ETH Zürich and final coating/assembly is prepared
Board type Number needed (1xFM, 1xQM CCEB)
Now available for Crate assembly
Status Expected date to be available
USCM 4 4 now
CCBT 4 - coating done; to be retested 25. May 09
CCIF 8 10 now
CCMO 4 6 now
CCBP 2+2 - PCA done; boards under test and coating 25. May 09
CCPA 8 10 coating done 12. May 09
CCDC 2 - PCA done; boards under test and coating 25. May 09
CCEB Crate
ready for assembly (from CSIST)
2009-05-10 TIM May09, CERN IEKP,Andreas Sabellek p.5
Univ. of Univ. of KarlsruheKarlsruhe
CCPA Board Level TestCCPA Board Level Testquantity:4 FM, 2 FS, 4 QM
before coating:- check of output voltage puls shape- load test- adjustment of HW current limit (max power 150W/CC @126V)- calibration of voltage*current readout- relais check (launch lock)- full functional test
10 x CCPA
• all failures could be repaired and defective parts were replaced
boards before final mechanical assembly
2009-05-10 TIM May09, CERN IEKP,Andreas Sabellek p.6
Univ. of Univ. of KarlsruheKarlsruhe
Production ScheduleProduction Schedule
Dates QM&FM :
May 25 – June 5 CCEB Crate Assembly (CERN)
June 8 – July 3 CCEB ESS/TVT at SERMS (Terni)(U. Roeser / A. Sabellek / J. Schneider / [M. Droege])
by G. Viertel
2009-05-10 TIM May09, CERN IEKP,Andreas Sabellek p.7
Univ. of Univ. of KarlsruheKarlsruhe
SummarySummary
• all CCEB boards are delivered and show no major problem; last boards on the way for final coating
• CCEB 1 x QM and 1 x FM assembly end May
• preparation for ESS and TVT qualification/acceptance test at SERMS in Terni in June board level testing at ETH Zürich