395
BUILDING INFORMATION MODELINGBASED PROCESS TRANSFORMATION TO IMPROVE PRODUCTIVITY IN THE SINGAPORE CONSTRUCTION INDUSTRY LIAO LONGHUI (B.Eng., Chongqing Univ., China; M.Mgt., Harbin Inst. of Tech., China) A THESIS SUBMITTED FOR THE DEGREE OF DOCTOR OF PHILOSOPHY DEPARTMENT OF BUILDING NATIONAL UNIVERSITY OF SINGAPORE 2018 Supervisor: Associate Professor Teo Ai Lin, Evelyn Examiners: Associate Professor Hwang Bon-Gang Dr Wang Qian Professor Ma Zhiliang, Tsinghua University

building information modeling–based process transformation to improve productivity in the

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: building information modeling–based process transformation to improve productivity in the

BUILDING INFORMATION MODELING–BASED

PROCESS TRANSFORMATION TO IMPROVE

PRODUCTIVITY IN THE SINGAPORE

CONSTRUCTION INDUSTRY

LIAO LONGHUI

(B.Eng., Chongqing Univ., China; M.Mgt., Harbin Inst. of

Tech., China)

A THESIS SUBMITTED

FOR THE DEGREE OF DOCTOR OF PHILOSOPHY

DEPARTMENT OF BUILDING

NATIONAL UNIVERSITY OF SINGAPORE

2018

Supervisor:

Associate Professor Teo Ai Lin, Evelyn

Examiners:

Associate Professor Hwang Bon-Gang

Dr Wang Qian

Professor Ma Zhiliang, Tsinghua University

Page 2: building information modeling–based process transformation to improve productivity in the

I

DECLARATION

I hereby declare that this thesis is my original work and it has been written by me in

its entirety. I have duly acknowledged all the sources of information which have been

used in the thesis.

This thesis has also not been submitted for any degree in any university previously.

Liao Longhui

26 January 2018

Page 3: building information modeling–based process transformation to improve productivity in the

II

ACKNOWLEDGEMENTS

I would like to express my thanks and gratitude to the following people. Without their

time, guidance, help, support, and encouragement, this thesis would certainly not

exist.

First and foremost, I would like to thank my supervisor Associate Professor Teo Ai

Lin, Evelyn for her enlightenment, guidance, constructive feedbacks, consistent

encouragement, and incredible patience on all occasions throughout my Ph.D. study. I

would like to express my sincere gratitude to my thesis committee members Professor

Low Sui Pheng and Professor George Ofori. Their enthusiasm about research,

positive attitudes towards problem solving, and resourcefulness greatly inspired me

both in study and in career development. Without their diligent efforts, this thesis

would not be possible, and the journal articles originated from this research would not

have been published. Besides, the research scholarship from the National University

of Singapore (NUS) during my Ph.D. candidature is also gratefully acknowledged.

In addition, special thanks must go to Ms. Liu Yige and Mr. Wei Kewu from the

China Construction (South Pacific) Development Co. Pte. Ltd. for their help in the

data collection process.

I am grateful to all my colleagues in the NUS Centre of Excellence in BIM

Integration, including Mr. Vishal Kumar, Mr. Lim Yong Khoon, and Mr. Gwee Seng

Kwong for their continued support, as well as to my friends in the Department of

Building, especially Mr. Sun Yuting, Mr. Wang Yi, and Mr. Zhang Yajian for their

friendship and encouragement throughout my research.

Page 4: building information modeling–based process transformation to improve productivity in the

III

Finally, and most importantly, I am greatly indebted to my family. I heartfully thank

my wife Ms. Li Linhui for all her sacrifices and unflinching affection. I would like to

thank my parents for their unconditional and endless love and support, which powers

me in my academic pursuits all these years.

Page 5: building information modeling–based process transformation to improve productivity in the

IV

TABLE OF CONTENTS

DECLARATION.............................................................................................. I

ACKNOWLEDGEMENTS ........................................................................... II

SUMMARY ................................................................................................. VIII

LIST OF TABLES ....................................................................................... XII

LIST OF FIGURES ..................................................................................... XV

LIST OF ABBREVIATIONS .................................................................. XVII

Chapter 1: Introduction .................................................................................. 1

1.1 Background ................................................................................................ 1

1.2 Significance and Rationale of Research .................................................... 4

1.3 Research Problems .................................................................................. 13

1.4 Knowledge Gaps ..................................................................................... 15

1.5 Research Objectives ................................................................................ 18

1.6 Scope of Research ................................................................................... 20

1.7 Research Hypotheses ............................................................................... 23

1.8 Structure of the Thesis ............................................................................. 23

Chapter 2: Review of Productivity Performance and Relevant Policies in

the Singapore Construction Industry........................................................... 27

2.1 Introduction ............................................................................................. 27

2.2 Overview of Productivity Performance in Singapore ............................. 27

2.3 Productivity-Enhancing Policies in Singapore ........................................ 30

2.3.1 Higher quality workforce ........................................................................... 31

2.3.2 Higher capital investments ......................................................................... 32

2.3.3 Better integration of value chain ................................................................ 34

2.4 Summary .................................................................................................. 36

Chapter 3: Review of Traditional and BIM-Based Project Delivery ........ 37

3.1 Introduction ............................................................................................. 37

3.2 Traditional Project Delivery Process ....................................................... 37

3.3 Current Delivery Process ......................................................................... 40

3.4 Full BIM-Enabled Delivery Processes .................................................... 44

3.4.1 Integrated Project Delivery ........................................................................ 44

Page 6: building information modeling–based process transformation to improve productivity in the

V

3.4.2 Virtual Design and Construction ............................................................... 57

3.4.3 Design for Manufacturing and Assembly .................................................. 71

3.5 Comparisons among Project Delivery Processes .................................... 82

3.5.1 Differences among project delivery processes .......................................... 82

3.5.2 Relationships between full BIM-enabled processes .................................. 90

3.6 Summary .................................................................................................. 93

Chapter 4: Review of Non-Value Adding (NVA) Activities and Proposal

of a BIM Implementation Readiness (BIMIR) Evaluation Model ............ 95

4.1 Introduction ............................................................................................. 95

4.2 NVA Activities and Their Causes and Resulting Wastes ....................... 95

4.2.1 Identifying NVA activities ......................................................................... 95

4.2.2 Resulting wastes ...................................................................................... 100

4.2.3 Causes of NVA activities ......................................................................... 104

4.3 BIMIR .................................................................................................... 112

4.4 A BIMIR Model for Building Projects .................................................. 118

4.4.1 Existing BIM readiness models ............................................................... 118

4.4.2 A fuzzy BIMIR model ............................................................................. 119

4.5 Summary ................................................................................................ 133

Chapter 5: Review of Factors Affecting BIM Implementation and

Proposal of an Organizational Change Framework ................................. 135

5.1 Introduction ........................................................................................... 135

5.2 Factors Affecting BIM Implementation ................................................ 135

5.2.1 Hindrances to full BIM implementation .................................................. 135

5.2.2 Drivers for full BIM implementation ....................................................... 140

5.3 A Proposed Organizational Change Framework for BIM Implementation

......................................................................................................... 144

5.3.1 Organizational change theories ................................................................ 144

5.3.2 A proposed organizational change framework for building projects ....... 154

5.3.3 Conceptual model .................................................................................... 162

5.4 Summary ................................................................................................ 162

Chapter 6: Research Methodology ............................................................. 164

6.1 Introduction ........................................................................................... 164

6.2 Research Design .................................................................................... 166

6.2.1 Survey ...................................................................................................... 166

6.2.2 Case study ................................................................................................ 169

6.3 Methods of Data Collection ................................................................... 170

6.3.1 Questionnaires and interviews ................................................................. 170

6.3.2 Observations ............................................................................................ 175

6.3.3 Analysis of past documents ..................................................................... 176

Page 7: building information modeling–based process transformation to improve productivity in the

VI

6.4 Methods of Data Analysis ..................................................................... 176

6.5 Summary ................................................................................................ 178

Chapter 7: Data Analysis and Discussions ................................................ 180

7.1 Introduction ........................................................................................... 180

7.2 Analysis Results and Discussions of Survey I ...................................... 181

7.2.1 Profile of respondents and their organizations ......................................... 181

7.2.2 Level of agreement of NVA activities ..................................................... 184

7.2.3 BIMIR of building projects in Singapore ................................................ 192

7.2.4 Resulting wastes ...................................................................................... 198

7.2.5 Causes to NVA activities ......................................................................... 207

7.3 Analysis Results and Discussions of Survey II ..................................... 220

7.3.1 Profile of respondents and their organizations ......................................... 220

7.3.2 Hindrances to change towards full BIM implementation ........................ 223

7.3.3 Drivers for change towards full BIM implementation ............................. 235

7.3.4 Interpreting the critical hindrances to change (CHCs) and critical drivers

for change (CDCs) with the organizational change framework........................ 243

7.3.5 Proposed managerial strategies for reducing the CHCs and strengthening

the CDCs ........................................................................................................... 260

7.4 Summary ................................................................................................ 273

Chapter 8: Case Study ................................................................................. 275

8.1 Introduction ........................................................................................... 275

8.2 Background of Case Projects ................................................................. 275

8.3 Critical Changes .................................................................................... 278

8.4 Performance Assessment ....................................................................... 282

Chapter 9: Developing a BIM-Based Process Transformation (BBPT)

Model for Building Projects in Singapore ................................................. 287

9.1 Introduction ........................................................................................... 287

9.2 Comparing the CHCs and CDCs among BIMIR Statuses .................... 287

9.2.1 Profile of respondents and their organizations involved in both surveys 287

9.2.2 Linking Survey I and Survey II ............................................................... 290

9.2.3 Comparison among projects with different BIMIR ................................. 291

9.2.4 Areas needing improvement .................................................................... 295

9.3 A BBPT Model ...................................................................................... 309

9.4 Validation of the BBPT Model .............................................................. 314

9.5 Summary ................................................................................................ 318

Chapter 10: Conclusions and Recommendations ..................................... 320

10.1 Summary of Research Findings ........................................................... 320

Page 8: building information modeling–based process transformation to improve productivity in the

VII

10.1.1 Critical NVA industry practices and resulting wastes in the Singapore

construction industry......................................................................................... 320

10.1.2 A fuzzy BIMIR evaluation model for building projects ........................ 322

10.1.3 BIMIR statuses and productivity performance of building projects in

Singapore .......................................................................................................... 323

10.1.4 A proposed organizational change framework ...................................... 324

10.1.5 Critical factors hindering and driving change towards full BIM

implementation ................................................................................................. 324

10.1.6 A BBPT model....................................................................................... 327

10.2 Contributions ....................................................................................... 328

10.2.1 Contribution to scholarship .................................................................... 328

10.2.2 Contribution to practice ......................................................................... 329

10.3 Limitations ........................................................................................... 332

10.4 Recommendations for Future Research ............................................... 334

Bibliography ................................................................................................. 336

Appendices .................................................................................................... 355

Appendix 1: Questionnaire of Survey I ....................................................... 355

Appendix 2: Questionnaire of Survey II ..................................................... 363

Appendix 3: Questionnaire for the Validation of the BBPT model ............ 368

Appendix 4: A Calculation Example of the Fuzzy BIMIR Model .............. 371

Appendix 5: List of Publications from This Thesis ..................................... 375

Page 9: building information modeling–based process transformation to improve productivity in the

VIII

SUMMARY

Productivity is always a problem. In particular, productivity performance in the

Singapore construction industry did not reach the local government’s target from

2013 to 2016. To meet the productivity growth target set in 2010, the local

government has enacted a series of legislations. Among which, the most important

one is that building plans for all new building projects with a gross floor area (GFA)

of 5,000 m2 and above must be submitted in building information modeling (BIM)

format for regulatory approvals since July 2015. Even local firms started to

implement BIM, both physical and information fragmentation appeals to still exist

across the planning, design, and downstream phases. Thus, the Singapore

construction industry is using BIM partially.

This study aims to develop a BIM-based process transformation (BBPT) model to

help project teams move towards higher levels of BIM implementation, reduce

wastes, and thus enhance productivity performance in building projects in Singapore.

Firstly, the traditional project delivery process (without BIM use), current delivery

process (in the current context of Singapore), and full BIM-enabled delivery

processes were reviewed and adapted for use in the Singapore context. Full BIM-

enabled delivery approaches include Integrated Project Delivery, Virtual Design and

Construction, and Design for Manufacturing and Assembly which have been

increasingly recognized and used in the global construction industry. By comparing

the current process with the full BIM-enabled processes, non-value adding (NVA)

activities were identified. In this study, four statuses of BIM implementation

readiness (BIMIR) at the project level were defined, including status one (S1, no BIM

implementation), status two (S2, lonely BIM implementation), status three (S3,

collaborative BIM implementation), and status four (S4, full BIM implementation).

Based on the NVA activities, a fuzzy BIMIR model was developed, using the fuzzy

Page 10: building information modeling–based process transformation to improve productivity in the

IX

synthetic evaluation approach, to evaluate the BIMIR statuses of building projects

that plan to implement BIM in Singapore.

Secondly, based on Leavitt’s diamond model, MIT90s framework, and their

derivatives, an organizational change framework was proposed for building projects

implementing BIM, which consists of 29 change attributes from the perspectives of

people, process, technology, and external environment.

Two surveys and a case study were conducted in the Singapore construction industry.

The analysis results of Survey I identified 38 critical NVA activities. Using the data

related to the frequency of occurrence of these NVA activities, the BIMIR statuses of

73 surveyed building projects were evaluated. Among which, 15, 47, and 11 projects

were assessed in BIMIR S1, S2, and S3, respectively, while none in BIMIR S4. The

results of five stability tests suggested that the fuzzy BIMIR evaluation model was

stable and could be used to predict the BIMIR status of any other building project in a

similar context. In addition, it was found that as BIMIR increased, the criticality of 13

wastes in project groups of different BIMIR statuses would decrease, lessoning

detrimental effects on productivity. All the 53 causes to the critical NVA activities

that were identified from the literature review were significantly important, especially

those related to contractors.

Moreover, the analysis results of Survey II suggested that 44 hindrances to change

and 31 drivers for change had significant influence on the overall lonely BIM

implementation status in Singapore. These significant factors were interpreted with

the proposed organizational change framework. The rankings and theoretical

rationale behind these factors helped tailor managerial strategies on people (eight),

process (10), technology (five), and external environment (two) aspects.

Page 11: building information modeling–based process transformation to improve productivity in the

X

Because of the key role of the contractors, a case study of BIM implementation and

transformation (moving towards a higher BIMIR status or a more collaborative and

integrated BIM-based delivery process) was conducted in a large construction and

development firm based in Singapore. The critical changes made in Project A

(BIMIR S3) illustrated the dynamics of this firm to move from a lower BIMIR status

(S2 in Project B) towards a higher level of BIM implementation.

Lastly, the BBPT model was developed for building projects that plan to implement

BIM, which generalized the main findings of this study. This model consists of two

part-models: a BIMIR evaluation model and a BIMIR improvement model. The

former can evaluate the BIMIR status of a particular building project in the planning

stage, while the latter can analyze the critical factors that hinder this project to be in

the current BIMIR status and driver the project to change towards a higher BIMIR

status, and provide managerial strategies with four priorities for the project

organization to move towards full BIM implementation in terms of people, process,

technology, and external environment. The increased BIMIR status creates fewer

NVA activities, and thus will, by reducing detrimental effects of the resulting wastes,

improve productivity performance. The 33 projects that were involved in both

surveys illustrated the use of the BBPT model.

As little research has attempted to investigate the BIMIR of building projects and

study BIM implementation from the organizational change perspective, the

development of the fuzzy BIMIR evaluation model and the proposed organizational

change framework significantly contributes to the literature. In addition, the BBPT

model allows project leadership teams to have a good understanding of the status

quos in their projects, and how to implement prioritized transformation strategies to

move towards higher levels of BIM implementation, thus contributing to practices.

Overseas practitioners may also use this model, with minor adjustments, because

Page 12: building information modeling–based process transformation to improve productivity in the

XI

BIM implementation in publicly funded construction and building projects in the

global construction industry is also commonly encouraged, specified, or mandated.

Page 13: building information modeling–based process transformation to improve productivity in the

XII

LIST OF TABLES

Table 1.1 YoY changes in labor productivity in Singapore from 2010 to 2016 (%) 1

Table 1.2 Conclusion of existing and additional foreign worker curbs 6

Table 2.1 First CPR in Singapore 28

Table 2.2 Levy schedule for WPHs from 2014 to 2017 (S$) 31

Table 3.1 Key stakeholders and activities in the traditional delivery process 39

Table 3.2 Key stakeholders and activities in the current BIM adoption process 43

Table 3.3 Key IPD characteristics and descriptions 46

Table 3.4 BIM support for achieving IPD characteristics 49

Table 3.5 Summary of the key activities related to BIM in the current process and the

proposed IPD, VDC, and DfMA processes in the Singapore construction industry 83

Table 3.6 Major differences among the proposed project delivery processes in

Singapore 85

Table 3.7 Differences and supporting statements in literature between the traditional,

current, and full BIM-enabled processes in Singapore 87

Table 4.1 Major NVA practices characterized by project stakeholders and project

phasing in the current project delivery in Singapore 96

Table 4.2 Potential wastes affecting productivity more seriously 100

Table 4.3 Fuzzy numbers of linguistic terms 125

Table 4.4 Generic translation of NVAI score to BIMIR status 131

Table 4.5 Adjusted translation of NVAI score to BIMIR status 133

Table 5.1 Hindrances to BIM Implementation 136

Table 5.2 Drivers for full BIM implementation 141

Table 5.3 Proposed organizational change framework for building projects

implementing BIM 156

Table 6.1 Tendering limits of contractors registration system (S$ million) 168

Table 6.2 Summary of the interviews in the pilot study 172

Table 7.1 Profile of the respondents and their organizations in Survey I 182

Table 7.2 Level of agreement ranking and t-test results of the NVA activities 185

Table 7.3 Profile of the interviewees in Survey I 191

Page 14: building information modeling–based process transformation to improve productivity in the

XIII

Table 7.4 Weighting for project phasing and its NVA activities 192

Table 7.5 NVAI scores of the surveyed building projects in Singapore 194

Table 7.6 BIMIR statuses of the surveyed building projects 195

Table 7.7 Generation of five groups of random numbers 196

Table 7.8 New NVAI scores and changes of the surveyed building projects in five

stability tests 197

Table 7.9 Mean and ranking of resulting wastes 200

Table 7.10 ANOVA results of the WC between BIMIR statuses 202

Table 7.11 Post hoc test results for the wastes different between BIMIR statuses 204

Table 7.12 Spearman’s rank correlation results of the WC between BIMIR statuses

207

Table 7.13 Importance ranking and t-test results of the causes to the NVA activities

208

Table 7.14 ANOVA results of the causes between BIMIR statuses 214

Table 7.15 Post hoc test results for the causes different between BIMIR statuses 216

Table 7.16 Spearman’s rank correlation of the causes between BIMIR statuses 220

Table 7.17 Profile of the respondents and their organizations in Survey II 220

Table 7.18 Profile of the interviewees in Survey II 223

Table 7.19 Significance ranking and t-test results of the hindrances to change 224

Table 7.20 Mean scores and ranking of the CHCs between upfront and downstream

stakeholders 232

Table 7.21 Significance ranking and t-test results of the drivers for change 235

Table 7.22 Mean scores and ranking of the CDCs between upfront and downstream

stakeholders 242

Table 8.1 Profile of the interviews in the case study 275

Table 9.1 Profile of the respondents and their organizations involved in both surveys

288

Table 9.2 Overall mean scores and rankings of the CHCs and CDCs in different

samples 290

Table 9.3 Mean scores and rankings of the CHCs: BIMIR S1 vs. BIMIR S2 vs.

BIMIR S3 292

Table 9.4 Spearman’s rank correlation of the CHCs: BIMIR S1 vs. BIMIR S2 vs.

BIMIR S3 293

Page 15: building information modeling–based process transformation to improve productivity in the

XIV

Table 9.5 Mean scores and rankings of the CDCs: BIMIR S1 vs. BIMIR S2 vs.

BIMIR S3 294

Table 9.6 Spearman’s rank correlation of the CDCs: BIMIR S1 vs. BIMIR S2 vs.

BIMIR S3 295

Table 9.7 Overall paths of reducing the CHCs and strengthening the CDCs from the

organizational change perspective 297

Table 9.8 Key areas of improvement in the organizational change framework 300

Table 9.9 Priority rules of implementing strategies for changing from a lower BIMIR

status to higher BIMIR statuses 303

Table 9.10 Prioritized change areas and managerial strategies for a project

organization to move from BIMIR S1 304

Table 9.11 Prioritized change areas and managerial strategies for a project

organization to move from BIMIR S2 305

Table 9.12 Prioritized change areas and managerial strategies for a project

organization to move from BIMIR S3 306

Table 9.13 Profile of the validation experts 314

Table 9.14 Validation results of the BIMIR evaluation model 316

Table A.1 Calculation process of the NVAI of a surveyed building project 372

Page 16: building information modeling–based process transformation to improve productivity in the

XV

LIST OF FIGURES

Figure 1.1 Percentage of contractors engaging with BIM on more than 30% of their

work (by country) 3

Figure 1.2 Foreign employment changes in Singapore from 2010 to 2016 5

Figure 1.3 Rationale of the study 7

Figure 1.4 Deconstruction of the BBPT model 20

Figure 1.5 Structure of the thesis 24

Figure 3.1 Current partial BIM implementation in the Singapore construction industry

41

Figure 3.2 Eleven essential principles of IPD 47

Figure 3.3 Use of BIM in an integrated environment enables IPD process 50

Figure 3.4 Stakeholder involvement in the commonly-used IPD process overseas 51

Figure 3.5 Stakeholder involvement in the proposed IPD process for the Singapore

construction industry 53

Figure 3.6 Stakeholder involvement in the proposed VDC process for the Singapore

construction industry 65

Figure 3.7 DfMA envelope 72

Figure 3.8 Stakeholder involvement in the proposed DfMA process for the Singapore

construction industry 76

Figure 3.9 Distinctive differences and similarities of IPD, VDC, and DfMA 91

Figure 3.10 Relationships between IPD, VDC, and DfMA when using BIM 91

Figure 3.11 How integrated information supports the creation of a high-performance

building 92

Figure 4.1 Productivity and cost affected by RFI, rework, idle time, activity delay,

and change order 103

Figure 4.2 How BIM coordination enhances productivity and cost performance by

reducing major wastes 104

Figure 4.3 BIM maturity stages in previous studies 115

Figure 4.4 Triangular membership function 123

Figure 4.5 Membership functions of linguistic values 125

Figure 4.6 Central method of defuzzification 130

Page 17: building information modeling–based process transformation to improve productivity in the

XVI

Figure 4.7 Translation of NVAI score into linguistic terms (frequency of occurrence)

131

Figure 5.1 Leavitt’s diamond model 145

Figure 5.2 An enhanced diamond model 147

Figure 5.3 An organizational interaction diamond model 148

Figure 5.4 A modified Leavitt’s system model 150

Figure 5.5 A conceptual model of technology impact 151

Figure 5.6 MIT90s framework 152

Figure 5.7 Conceptual framework of collaboration adapted from MIT90s framework

154

Figure 6.1 Research methodology 165

Figure 7.1 Framework of people management from the organizational change

perspective 244

Figure 7.2 Framework of process management from the organizational change

perspective 250

Figure 7.3 Framework of technology management from the organizational change

perspective 254

Figure 7.4 Framework of external environment management from the organizational

change perspective 256

Figure 9.1 BIM-based process transformation model for building projects 310

Page 18: building information modeling–based process transformation to improve productivity in the

XVII

LIST OF ABBREVIATIONS

2D Two-Dimensional

3D Three-Dimensional

4D Four-Dimensional

5D Five-Dimensional

6D Six-Dimensional

AEC Architectural, Engineering, and Construction

AGC Association of General Contractors

AHP Analytic Hierarchy Process

AIA American Institute of Architects

AIACC American Institute of Architects, California Council

ANN Artificial Neural Network

ANOVA Analysis of Variance

BBPT BIM-Based Process Transformation

BCA Building and Construction Authority

BIM Building Information Modeling

BIMIR BIM Implementation Readiness

BLM Building Lifecycle Management

BOM Bill of Materials

CAD Computer-Aided Design

CCS Cuneco Classification System

CDMC Collaborative Decision-Making and Control

CDC Critical Driver for Change

CHC Critical Hindrance to Change

CITM Construction Industry Transformation Map

CNC Computer Numerically Controlled

CPC Construction Productivity Centre

CPCF Construction Productivity and Capability Fund

CPR Construction Productivity Roadmap

DBB Design-Bid-Build

DFA Design-Fabricate-Assemble

DfMA Design for Manufacturing and Assembly

DSS Decision-Support System

EIKP Early Involvement of Key Participants

EMS External Environment Management Strategy

Page 19: building information modeling–based process transformation to improve productivity in the

XVIII

E-submission Electronic Submission

ESC Economic Strategies Committee

FSE Fuzzy Synthetic Evaluation

FWLs Foreign Worker Levies

GDP Gross Domestic Product

GFA Gross Floor Area

GLS Government Land Sales

HDB Housing and Development Board

HR Human Resource

HVAC Heating, Ventilation, and Air Conditioning

ICT Information and Communications Technology

IDD Integrated Digital Delivery

IFC Industry Foundation Classes

IPD Integrated Project Delivery

IT Information Technology

JDVG Jointly Developed and Validated Project Goals

LOD Level of Detail

LSD Least Significant Difference

LWKP Liability Waivers among Key Participants

MAPE Mean Absolute Percentage Error

MEP Mechanical, Electrical, and Plumbing

MF Model Function

MND Ministry of National Development

MOF Ministry of Finance

MOM Ministry of Manpower

MPC Multi-Party Contract

MPE Mean Percentage Error

MYE Man-Year Entitlement

NBIMS National Building Information Modeling Standards

nD n-Dimensional

NVA Non-Value Adding

NVAI Non-Value Adding Index

OSM Off-Site Manufacture

PBUs Prefabricated Bathroom Units

PE Percentage Error

PeMS People Management Strategy

Page 20: building information modeling–based process transformation to improve productivity in the

XIX

PMET Professional, Managerial, Executive, and Technical

PROMETHEE Preference Ranking Organization Method for Enrichment

Evaluations

PrMS Process Management Strategy

PPVC Prefabricated Prefinished Volumetric Construction

QS Quantity Surveying

QTO Quantity Take-Off

RFI Request for Information

S1 Status One

S2 Status Two

S3 Status Three

S4 Status Four

SCPW Singapore Construction Productivity Week

SDOS Singapore Department of Statistics

SMCCV Sutter Medical Center Castro Valley

SMEC Small and Medium Enterprises Committee

SME Small and Medium-Sized Enterprise

SPSS Statistical Package for the Social Sciences

SRR Shared Risk and Reward

TFN Triangular Membership Number

TMS Technology Management Strategy

URA Urban Redevelopment Authority

US United States

UK United Kingdom

VAP Value-Added Per Employee

VDC Virtual Design and Construction

VE Validation Experts

WC Waste Criticality

WPHs Work Permit Holders

WTU Workforce Training and Upgrading

YoY Year-on-Year

Page 21: building information modeling–based process transformation to improve productivity in the

1

Chapter 1: Introduction

1.1 Background

The construction industry is a large contributor to Gross Domestic Product (GDP) in

the total economy of Singapore and is essential to determine economic growth. The

relationship between the construction industry and GDP in developed countries is

usually in the range of 7% to 10% and in developing countries around 3% to 6%

(Samari et al., 2014). In 2010, Singapore’s Economic Strategies Committee (ESC)

found that there is significant room to improve productivity in every sector of the

Singapore economy, and GDP growth should be driven by productivity to stay

competitive. Thus, the ESC set a target for Singapore to achieve productivity growth

of 2% to 3% per year over the next ten years to enable the local GDP to grow on

average by 3% to 5% per year (ESC, 2010).

Table 1.1 shows the year-on-year (YoY) changes in the labor productivity in

Singapore from 2010 to 2016. According to the Building and Construction Authority

(BCA, 2013a), the labor productivity figures published by the Singapore Department

of Statistics (SDOS) as well as the productivity indicator adopted by the ESC as

benchmark are measured in terms of value-added per employee (VAP). At the firm

level, VAP can be estimated by a firm’s value added over the total number of

employees on the firm’s payroll. From Table 1.1 it can be seen that the labor

productivity growth was suboptimal recently, especially in the construction sector.

Table 1.1 YoY changes in labor productivity in Singapore from 2010 to 2016 (%)

Year 2010 2011 2012 2013 2014 2015 2016

Total 11.6 2.3 -0.1 0.9 -0.2 -0.2 1.0

Construction 4.0 2.2 2.7 -5.5 1.1 1.9 -0.5

Note: The figures are based on GDP at 2010 Market Prices and Gross Value Added at

2010 Basic Prices.

Source: SDOS (2017).

Page 22: building information modeling–based process transformation to improve productivity in the

2

To meet the productivity growth target in the construction industry, the Singapore

government has undertaken a series of fundamental legislations, such as formulating

the first Construction Productivity Roadmap (CPR) in 2010 (BCA, 2011a), which

focused on helping local firms to adopt technology. Besides, continuous efforts have

been made by the BCA, such as the Construction Productivity and Capability Fund

(CPCF) and Productivity Improvement Projects scheme (Zeng and Chew, 2013). In

the meantime, local builders are required to provide project-level and trade-level

productivity figures through the Electronic Productivity Submission System.

More importantly, in this CPR, the BCA has enforced a five-year BIM adoption

roadmap, in which building information modeling (BIM) electronic submissions (e-

submissions) for regulatory approvals have been mandated in three phases. New

building projects with a gross floor area (GFA) of 20,000 m2 and above were required

to submit their architectural plans in BIM format since July 2013 and to submit their

structural and Mechanical, Electrical, and Plumbing (MEP) plans in BIM format

since July 2014. Eventually, all new building projects with a GFA of 5,000 m2 and

above were required to make architectural, structural, and MEP BIM e-submissions

since July 2015 (BCA, 2011b). This targets the local construction industry to widely

use BIM (80%). In the BIM roadmap, five strategies were proposed, including public

sector taking the lead in specifying BIM requirements for all new public sector

building projects, removing impediments by introducing BIM submission templates,

building capability and capacity by intensive BIM training programs, promoting

success stories, and incentivizing early BIM adopters (BCA, 2011a, 2011b).

According to a survey on BIM implementation by contractors which was conducted

by McGraw Hill Construction (2014a), Singapore was not among the countries in

which the contractors were engaging with BIM on more than 30% of their work

before 2015 (see Figure 1.1). In other words, the Singapore construction industry is

Page 23: building information modeling–based process transformation to improve productivity in the

3

experiencing a major shift from traditional methods towards the use of automation

that has been made possible through BIM implementation. Although the local

government has been driving the local industry to use BIM, the state of BIM adoption

is uneven in the local market (McGraw Hill Construction, 2014b). The largest

contractors tend to be very advanced to adopt BIM and thus reap the benefits more

fully, whereas the others are in the beginning phase. Overall, the Singapore

construction industry is not very BIM-ready for project-wide collaboration

throughout the construction value chain (Lam, 2014). This may cause various

inefficiencies in the project lifecycle, seriously affecting productivity (Nath et al.,

2015).

27%23% 23%

29% 28%

39%33%

37%

24%

55%

43%

50% 52% 54%

66%71% 71% 72% 73%

79%

Japan New

Zealand

South

Korea

Canada UK France Australia Germany Brazil US

2013 2015

Figure 1.1 Percentage of contractors engaging with BIM on more than 30% of their

work (by country)

Source: McGraw Hill Construction (2014a)

The identification and analysis of such inefficiencies in the building projects that

were recently completed in Singapore can improve the management of future projects.

By eliminating non-value adding (NVA) time such as idle time, waiting time, and

transportation time, productivity can be improved and projects can probably be

completed within time limit (Nath et al., 2015; Nikakhtar et al., 2015). Therefore,

changes are imperative among current industry practices in the Singapore

construction industry.

Page 24: building information modeling–based process transformation to improve productivity in the

4

1.2 Significance and Rationale of Research

Productivity performance is not only a determinant of a firm’s long-term viability, but

also a benchmark of overall competitive advantage of an industry and an economy

(Jergeas et al., 2000). Since many countries have suffered from suboptimal

productivity performance in the construction industry, much research work needs to

be done to formulate strategies for enhancing productivity (Ranasinghe et al., 2011).

Therefore, productivity improvement should be a top management priority for

construction industry leaders.

The construction industry is a prime source of employment generation which offers

job opportunities to millions of unskilled, semi-skilled, and skilled workforce.

Singapore’s Ministry of Manpower (MOM) and Ministry of National Development

(MND) (1999) observed that the most critical reason of the low or even negative

productivity growth in the Singapore construction industry was mainly a heavy

reliance on lower-skilled foreign workforce. The ESC (2010) stated that the rapid

increase in foreign workforce had enabled Singapore to grow the economy in the past

decade, but it in turn made the economy become more dependent on foreign workers.

It is a must to shift to achieving the GDP growth by expanding productivity rather

than labor force. Accordingly, the Small and Medium Enterprises Committee (SMEC,

2014) recommended that underlying the restructuring efforts are productivity

improvements through reduced reliance on the foreign manpower, supplemented by

programs and incentives for the local companies to raise productivity. Hence, the

MOM (2014, 2015) maintained its approach of taking progressive steps to raise the

quality of the construction workforce and reduce the reliance on the foreign labor,

which was in line with the government’s efforts to achieve economic growth driven

by sustained productivity improvements rather than manpower growth. As a result,

the labor market remained tight by the end of 2016 (see Figure 1.2). Much of the

Page 25: building information modeling–based process transformation to improve productivity in the

5

foreign employment growth was driven by the construction sector. These statistics

underlined that regardless of any changes in labor law or make-up of the future

workforce, there is significant scope to deliver efficiency improvements in the

industry’s overall performance levels. Thus, productivity in the local construction

industry must be improved.

Figure 1.2 Foreign employment changes in Singapore from 2010 to 2016

Source: MOM (2016)

Table 1.2 presents existing and additional foreign worker curbs, namely foreign

worker levies (FWLs) and Man-Year Entitlement (MYE), specified by the Ministry

of Finance (MOF) of Singapore. According to the ESC (2010) and Wan (2013), a

progressive increase in FWLs would incentivize the local companies to invest in

improving productivity. This is one of the most efficient and flexible ways of

ensuring that the Singapore economy’s dependence on the foreign workforce does not

grow excessively. It will allow for fluctuations in the foreign workforce to cater to

business cycles, for example, in the construction industry (ESC, 2010).

3.8

19.6

34.9 31.6

9.7 6.8

-10.1

54.4

79.8

67.1

48.4

26 22.6

-2.5

-20

-10

0

10

20

30

40

50

60

70

80

90

100

2010 2011 2012 2013 2014 2015 2016

(Thousand) Construction

Total (excluding foreign domestic workers)

Page 26: building information modeling–based process transformation to improve productivity in the

6

Table 1.2 Conclusion of existing and additional foreign worker curbs

Implementation Descriptions of foreign worker curbs

July 2010 Progressive increases in FWLs to be introduced over July 2010 to

July 2012 for S Pass and Work Permit Holders (WPHs). Progressive

cuts in MYE for construction sector to be implemented from July

2010 to July 2013

January 2012 Further increases in FWLs to be phased in from January 2012 to July

2013

July 2012 Further reduction in MYE for construction sector, bringing

cumulative cuts to 45% by July 2013

July 2013 Additional FWLs will kick in starting July 2013

July 2014 Additional FWLs to kick in

July 2015 More FWLs to kick in: in particular, this sharpens the distinction

between skilled and unskilled workers

July 2015 The MYE-waiver levy rate for higher skilled or R1 workers will be

lowered from $750 to $600 from 1 July 2015 onwards (Budget 2015)

July 2016 The levy for basic skilled or R2 WPHs employed within MYE will

be increased from $600 to $700 in July 2016 (Budget 2014)

July 2016 Basic tier levy for R2 workers will be raised from $550 currently to

$650 on 1 July 2016 (Budget 2015)

July 2017 Basic tier levy for R2 workers will be raised from $550 currently to

$650 on 1 July 2016 and then $700 on 1 July 2017 (Budget 2015)

Source: Wan (2013); MOF (2014, 2015).

Besides, the National Building Information Modeling Standards (NBIMS, 2007)

committee stated that the construction industry in developed countries such as the

United States (US) and Finland was experiencing a major shift from the traditionally

labor-intensive ways of working towards the application of automation and

integration when BIM technology was available to their construction practitioners.

This trend would result in the identification and reduction of the inefficiencies such as

design errors, waiting for instructions, and reworks, leading to improved productivity

(Alshawi, 2007; Khosrowshahi and Arayici, 2012; Nath et al., 2015, 2016). The

practitioners in the Singapore construction industry should also have the ability to

respond to such inefficiencies for productivity gain.

Figure 1.3 presents a big picture of this study’s rationale. The widely-accepted

definition of BIM proposed by the NBIMS committee stated that “a basic premise of

BIM is collaboration by different stakeholders at different phases of the life cycle of a

facility to insert, extract, update or modify information in the BIM to support and

Page 27: building information modeling–based process transformation to improve productivity in the

7

reflect the roles of that stakeholder” (NBIMS, 2007). This can transform the way that

owners, contractors, designers, planners, and the myriad of other roles come together

to perform their jobs (Autodesk, 2012). Because of the policies of promoting BIM in

Singapore, the local practitioners will be equipped with better BIM skills in a variety

of BIM workshops (Cheng, 2013). This may increase the percentage of skilled

manpower at the industry level. For instance, fewer draftspersons will be needed as

they can be replaced by more skilled BIM modelers. Kaner et al. (2008) observed in

four case studies in two middle-sized structural engineering firms that using BIM to

model and produce error-free fabrication shop drawings saved approximately 2.6%,

20.3%, 27.7%, and 47.3% of working hours, respectively, comparing with completing

the drawings traditionally with object-oriented computer-aided design (CAD) tools.

Full BIM-enabled delivery processes (Chapter 3):· Integrated project delivery· Virtual design and construction· Design for manufacturing and assembly

Current project delivery process (Chapter 3)

Traditional project delivery process (Chapter 3)

Drivers for change (Chapter 5)· People· Process· Technology· External environment

BIM-based transformation

Hindrances to change (Chapter 5)· People· Process· Technology· External environment

NVA activities in current delivery process (Chapter 4)

Wastes (Chapter 4)

Productivity

Lean philosophy

Move from CAD to BIM

Achieve

Cut down

ReduceEstablish

Affect Help

Improve

Figure 1.3 Rationale of the study

BIM implementation has been driven in the global construction industry. Smith

(2014) found that one common way for governments to commit on BIM is to

encourage, specify, or mandate BIM use in publicly funded construction and building

projects. This is consistent with some latest studies on the situation and development

Page 28: building information modeling–based process transformation to improve productivity in the

8

of world-wide BIM implementation (Cheng and Lu, 2015; Silva et al., 2016;

McAuley et al., 2017). For example, different levels of the public sector in the US

have released BIM standards to effectively implement BIM that is mandated in

various states; the third version of the National BIM Standard-US would be released

in late 2015, offering a full consensus standard for BIM in the planning, design,

construction, and operations of building projects (Cheng and Lu, 2015). The United

Kingdom (UK) government has required a minimum of Level two collaborative BIM

on all centrally funded public projects since April 2016 and issued a suite of

guidelines to specify information management in the design, construction, and

operations phases (Silva et al., 2016; McAuley et al., 2017). The large number of

large public sector owners in Norway set out particular requirements for all project

participants to use open standards for BIM since July 2016, such as the latest

Statsbygg BIM manual. Denmark developed Cuneco Classification System (CCS)

which provides a common language and methods for creating unambiguous exchange

of information throughout the construction process from idea to operation; the

standards CCS Identification and CCS Levels of Information were released in 2015

and 2016, respectively (McAuley et al., 2017). The buildingSMART Finland

published the InfraBIM requirements in 2015, which would be used as general

technical references and modeling guidelines, accompanied by the Inframodel 3 data

exchange format, during procurement and construction. Supported by the German

government and industry, Planen-bauen 4.0 would guide and steer the digital design,

construction, operation, and facility management for all types of projects as well as

all procurement types and forms of contracts since December 2015, requiring all new

projects to implement BIM from 2020 onwards. Other countries such as South Korea,

France, and Spain would include BIM implementation in all public sector projects by

2016, 2017, and March 2018, respectively (Cheng and Lu, 2015; McAuley et al.,

2017).

Page 29: building information modeling–based process transformation to improve productivity in the

9

Take the US, where BIM is largely industry-driven, for example. Individual industry

players in the US have initiated BIM adoption, prompting the government to

gradually implement corresponding policies. Because of governmental incentives and

strong promotion by software suppliers, many firms are willing to invest in BIM

software and training (Juan et al., 2017). In contrast with the US’s bottom-up

approach, a top-down approach is adopted in Singapore, where the government is the

dominant force in promoting BIM application. Cheng and Lu (2015) observed that

Singapore leads BIM implementation in Asia because many efforts have been made

by the local government to achieve industry-wide BIM implementation. Specifically,

out of the 35 BIM standards in Asia, 12 were issued by Singapore.

Despite the efforts made, changing towards a higher level of BIM implementation is

generally slow in most construction practitioners (Porwal and Hewage, 2013). One

possible reason for this is that these practitioners tend to be entrenched in the

traditional project delivery using the traditional CAD approach (Eastman et al., 2011)

or adopt a wait-and-see attitude (Juan et al., 2017). Besides, there are many

challenges for BIM implementation, such as owners’ request in limited phases and

subcontractors’ poor knowledge and skills to implement BIM (Kiani et al., 2015).

Thus, BIM implementation still needs to be enhanced in the global construction

industry.

For example, the gap analysis of the BIM adoption roadmap in Singapore revealed

that the local construction industry has been facing many issues: owners may lack

knowledge of BIM implementation and cannot see beyond initial cost; design

consultants tend to over-emphasize the BIM e-submissions and lack time to perform

design coordination; general contractors may not use the design models created by

the designers as such models were not created in the way contractors would have

built the buildings; subcontractors, especially those small- and medium-sized

Page 30: building information modeling–based process transformation to improve productivity in the

10

enterprises (SMEs), lack investment for hardware, software, and training; and facility

managers are rarely involved in the design and planning phase, and lack BIM use in

facility management (Lam, 2014). Consequently, the contractors may need to re-build

the models, taking much time, which in turn hinders the collaboration with the

designers (Sattineni and Mead, 2013).

Thus, physical and information fragmentation appears to exist between the upfront

planning and design phases and downstream phases in the Singapore construction

industry. The fragmentation problem would inevitably result in inefficient work

practices and costly changes at the later stages of a project. The litmus test for

successful project management should not be whether the project was free of poor

productivity, but rather, if productivity was enhanced progressively to the benefit of

the industry and the economy. Generally, researchers measure productivity

improvement in terms of time saving (Chelson, 2010; Fan et al., 2014; Nath et al.,

2015). But from a broader point of view, time saving is derived from the

identification and reduction of inefficiencies such as defects, reworks, overproduction,

waiting time, unnecessary inventory, too many requests for information (RFIs),

unnecessary movement, delays, incomplete design, and so on. This can be achieved

through diagnosing the NVA activities in the project lifecycle. By cutting down the

NVA activities, such inefficiencies (or wastes) can be reduced, and thus, construction

productivity at the project level can be improved (Ofori, 2005), which is consistent

with lean thinking (Ohno, 1998). Also, this concept accords with the VAP method. In

a macro sense, enhanced BIM implementation reduces the NVA activities in the

project, and fewer NVA activities need fewer man-days (fewer employees and/or less

time) to complete this project.

It has been advocated that construction practitioners should begin to embrace the

notion of Virtual Design and Construction (VDC). It is a concept or approach to build,

Page 31: building information modeling–based process transformation to improve productivity in the

11

visualize, analyze, and evaluate project performance virtually and early before a large

expenditure of time and resources is made on site. BIM forms the backbone of this

approach and its success requires a relook of the current project delivery process

(Chua and Yeoh, 2015). Besides, similar to the manufacturing industry, the

construction industry may apply the notion of Design for Manufacturing and

Assembly (DfMA), which allows discrete sections of the final construction to be

manufactured in a factory and then be transported to site for final assembly

(McFarlane and Stehle, 2014). The digital environment of product design in the

manufacturing industry has moved beyond design to enable analysis,

manufacturability, modularization, and production, and has also encompassed its

supply chain. To realize the full potential of the digital environment of a building

project in the same way, the construction industry must embrace the notion of VDC

(Kam and Fischer, 2004). Both the VDC and DfMA approaches has been promoted

by the BCA to drive the whole construction value chain to work collaboratively in the

project lifecycle. Meanwhile, Integrated Project Delivery (IPD) is another option.

This is a new project delivery method, which can be defined using its widely-

accepted principles: the relationships between the key participants in a project are

bound with multi-party collaboration contracts, and these participants participate in

the project very early, even before the design starts (El Asmar et al., 2013). Early

collaboration, under right conditions, can directly address the fragmentation problem.

To facilitate the change towards higher levels of BIM implementation, the issue

regarding whether the local industry is subjectively ready or objectively pushed by

the government to implement BIM should be studied. Key project stakeholders must

have a clear and comprehensive view of the factors that affect them to perform as

they currently use BIM in building projects and to change their current work practices.

In this study, these factors were studied from the perspectives of people, process,

technology, and external environment. In a building project context, people represent

Page 32: building information modeling–based process transformation to improve productivity in the

12

the major stakeholders (such as the government, owner, architect, engineers,

contractors, manufacturer, supplier, and facility manager) and their employees;

process refers to the work practices in the project delivery process, and how the

project is delivered (such as when referring to project delivery process or process

transformation); technology describes the tools and methods that help the project

team deliver their scopes of work; and external environment refers to the environment

in which the project team operates, such as construction market situation and local

policies.

Technology itself such as BIM tools is ready and available to enable new ways of

working that result in more predictable, accurate, and responsible building outcomes

(Autodesk, 2008). The tools have been constantly improving, and more powerful

hardware and a wide range of software can be chosen from. However, technology

alone cannot influence the required changes, and well-defined business process for

information sharing between computable models is required (Bernstein and Pittman,

2004; Khosrowshahi and Arayici, 2012). Successful process transformation from the

current partial BIM use to full BIM implementation requires the alignment of the

project stakeholders’ goals and activities with the project outcomes. Collaboration is

the precondition to BIM implementation.

The present study is timely as the policies of promoting wide BIM adoption in the

construction industry is currently underway in Singapore, and the local industry is

still trying to balance between its own way of doing things and the government

dominance. This study provides a good opportunity to address the productivity issue

by studying and promoting BIM implementation.

Page 33: building information modeling–based process transformation to improve productivity in the

13

1.3 Research Problems

Table 1.1 indicates that the productivity growth target in the Singapore construction

industry was not fulfilled since 2013. Besides, productivity is always a problem. Even

if productivity performance in next years is good enough to meet the government’s

requirement, productivity performance enhancing tools such as BIM are still needed

to make it better. Productivity is of high significance as it reflects the overall

competitiveness of an industry as well as an economy (Jergeas et al., 2000;

Ranasinghe et al., 2011). Therefore, this is an area in which much research work

needs to be done.

A series of legislations have already been proposed by the Singapore government and

implemented in recent years in the local construction industry, such as the widely

mandatory BIM e-submissions (BCA, 2011a). However, BIM implementation was

fragmented in different phases and firms. In most projects, building information

models developed by the design consultants are three-dimensional (3D) and object-

based. Although basic data are harvested from the model, such as two-dimensional

(2D) plans, elevations, sections, and quantity take-offs (QTOs) for materials and

labor (Khosrowshahi and Arayici, 2012), the deliverables are often less coordinated

and merely submitted to the government for approvals. These BIM models are

currently rarely shared with downstream quantity surveying (QS) consultants, general

contractors, trade contractors, fabricators, and facility managers. Due to these reasons,

the models need to be re-created in the construction stage and are usually unavailable

in the operations and maintenance stage. This is the issue of BIM implementation in

Singapore that causes many problems. Planning, designing, building, and managing a

building are a complex process that requires smooth communication and

collaboration among the project team, which requires open data sharing among the

project stakeholders (Khosrowshahi and Arayici, 2012). It can take years for the

Page 34: building information modeling–based process transformation to improve productivity in the

14

Singapore construction industry to completely shift to full BIM-enabled project

delivery where BIM is available in every single project phase and affordable to all the

major stakeholders.

A project is a knowledge-intensive entity. The team’s knowledge bandwidth affects

its ability to solve problems and deal with emerging challenges during the project

delivery. Such dynamics require ongoing learning and augmentation of the

knowledge bandwidth. Upgrading the local practitioners’ skills can only be realized

progressively. In addition, people seek change, but do not want to be changed (Senge,

1990). This is why management strategies and priorities are investigated in this study

to prepare process transformation options to the current urgency for the local industry.

Based on the above analysis, the research problems are:

a) The suboptimal productivity performance needs to be enhanced in the

construction industry. In particular, productivity growth from 2013 to 2016 did

not reach the Singapore government’s target;

b) NVA BIM implementation practices and their causes and influence on

productivity in the Singapore construction industry were not identified;

c) A tool for diagnosing BIM implementation levels of building projects in

Singapore was not developed;

d) The factors that affect the local construction practitioners to change towards full

BIM implementation were not identified; and

e) Process transformation strategies for building projects of different BIM

implementation levels were not formulated.

Page 35: building information modeling–based process transformation to improve productivity in the

15

1.4 Knowledge Gaps

Many studies have studied productivity in the construction industry. Some of them

have identified factors affecting productivity and their classification (Thomas et al.,

1990; Doloi, 2008; Dai et al., 2009; Chelson, 2010; Panas and Pantouvakis, 2010; Dai

and Goodrum, 2012; Dolage and Chan, 2013; Love et al., 2013; Fan et al., 2014;

Shan, 2014), and effects of BIM on productivity during construction (Chelson, 2010;

Azhar, 2011; Barlish and Sullivan, 2012; Fan et al., 2014; Shan, 2014). In the context

of Singapore, a notable study on the critical challenges and possible solutions of

productivity measurement was conducted by Hwang and Soh (2013), but this

previous study focused on productivity measurement at the trade level.

Process wastes have been identified and dealt with by researchers (Formoso et al.,

1999; Alwi et al., 2002; Forsberg and Saukkoriipi, 2007; Koskenvesa et al., 2010;

Sarhan and Fox, 2013b). Nikakhtar et al. (2015) categorized noticeable wastes (such

as waiting time, handling time, and delays) hidden in construction processes due to

the nature of operations and NVA work, and studied how they could be reduced by

adopting the lean thinking using computer simulation. Sacks et al. (2010)

recommended an interaction between BIM functionalities and the lean philosophy in

reducing construction inefficiencies. However, none of these studies have explored

the wastes produced by NVA BIM implementation activities in the project lifecycle

in the Singapore context. One of the generic principles of the lean thinking,

identifying and eliminating NVA activities, is highly recommended in this study to

specifically assist in identifying and reducing the wastes in the current practices

involving partial BIM implementation.

Besides, NVA activities and their resulting wastes may exist in the current industry

practices in the Singapore construction industry (Lam, 2014). This is because some

Page 36: building information modeling–based process transformation to improve productivity in the

16

building projects in Singapore, unless being pushed by the government, may be

unwilling to change their customized way of working to better implement BIM. Juan

et al. (2017) developed a model to predict the wiliness of the architectural

consultancy firms in Taiwan to apply automated design checking. Nevertheless, a

mathematical model that can assess the BIM implementation readiness (BIMIR)

statuses of building projects in the Singapore construction industry was not

developed. This study will fill this gap.

As can be seen from the above, there is a need to transform the Singapore

construction industry, and one of the useful tools in this transformation would be

BIM (Nath et al., 2015). It is process transformation that validates BIM

implementation in the construction industry (Arayici et al., 2011; Autodesk, 2012;

Khosrowshahi and Arayici, 2012; Enegbuma et al., 2014). Researchers (Lee et al.,

2005; Lee and Sexton, 2007) studied the process transformation in terms of people,

process, and technology. Lee and Sexton (2007) explored the feasibility of industry

absorbing and diffusing n-dimensional (nD) modeling technology, and found that

there ought to be intrinsic links between technology, people, and process. They

reported that although people appreciate the potential significant benefits of nD

modeling technology, it could be too embryonic and too far removed from the

“comfort zones” of construction firms because the technology requires heavy

investments and contains too many risks. Khosrowshahi and Arayici (2012) stated

that BIM implementation is a major change management task, involving a diversity

of risk areas. Enegbuma et al. (2014) investigated the managerial relationships

between BIM perceptions (people, process, and technology), strategic information

technology (IT) planning, collaborative planning, and BIM adoption, and pointed out

a path for major managerial decision-making choices in improving BIM maturity.

This echoes sentiment in studies concentrating on deploying automatic QTO in the

Singapore construction industry (Teo and Heng, 2007; Teo, 2008). However, no

Page 37: building information modeling–based process transformation to improve productivity in the

17

research has been carried out so far to study the process transformation strategies

from an organizational change perspective when BIM has been mandated by the local

government. In this study, external environment is added to supplement the three-

factor (people, process, and technology) structure. The strategies can provide

guidance for building projects to move towards higher BIMIR statuses.

Previous studies have reported that many factors would affect successful BIM

implementation in building projects. For example, studies of the SmartMarket Report

series (Young et al., 2008, 2009; Bernstein et al., 2010, 2012; Lee et al., 2012) may

be the most comprehensive survey studies in the US, European, and Korean markets.

Gu and London (2010) identified the factors for selecting appropriate BIM software

applications in a company and for exchanging data using the applications. Jung and

Joo (2011) considered factors such as property, relation, standards, and construction

business function when setting up a BIM framework. Khosrowshahi and Arayici

(2012) diagnosed the UK construction industry by identifying the challenges and

barriers when changing traditional construction methods towards mature BIM

adoption to develop a clear understanding of BIM implementation. Strategies such as

getting people to understand the potential and the value of BIM over 2D drafting

were recommended. Kiani et al. (2015) identified the strategic implementation of

BIM-based scheduling in Iran, and explored obstacles of using BIM in the planning

and design stages. Also, strategies for improving the efficiency of BIM

implementation in developing countries were identified. Nevertheless, these studies

failed to consider other factors such as contractual relationships among the

participating firms in the project context.

This study intends to identify the critical factors affecting building projects to change

towards higher BIMIR statuses in Singapore. Such factors are important in any type

of management or new technology adoption because these factors allow firms to

Page 38: building information modeling–based process transformation to improve productivity in the

18

focus their resources and efforts on certain areas, and also help them identify problem

areas and take necessary corrective actions.

Many articles and books have discussed the obstacles and success factors underlying

successful BIM adoption. However, these studies mostly introduced sparse

recommendations based on successful case histories (Manning and Messner, 2008;

Kuprenas and Mock, 2009), although a few presented these as the results of surveys. Case

studies have the advantage of finding unique ways of solving problems, observing new

phenomena, or testing theoretical assumption, but they are limited in their capacity for

providing a compiled list of solutions or for determining the criticality of issues. This

study will study a holistic view of the critical factors affecting the local industry to move

from their current project delivery practices towards full BIM implementation. Such

factors require high level attention and management priority to be really implemented

(Won et al., 2013).

1.5 Research Objectives

This study will assist project teams in reducing inefficiencies when using BIM in

their project delivery processes in the Singapore construction industry. Without

realizing the factors that affect successful adoption of BIM technology and work

processes in the construction industry, organizations will not be able to know what

improvement efforts need to be made, where these efforts should be focused on, and

which efforts can obtain best results (Leong and Tilley, 2008; Sarhan and Fox, 2013a).

Considering the fact that collaborative atmospheres for BIM implementation among

project teams may not exist in the short term, the construction sector must take steps

to change some unproductive current industry practices to save man power and time.

To effectively move from the current BIM adoption practices towards full BIM

Page 39: building information modeling–based process transformation to improve productivity in the

19

implementation in the local industry, considerations must be given to various NVA

activities in the project lifecycle, especially during the design stage and the design-

construction interface stage.

Based on these discussions, the aim of this study is to:

“Develop a BIM-based process transformation (BBPT) model to assist project teams

in moving towards higher levels of BIM implementation, reducing wastes, and thus

enhancing productivity performance in building projects in Singapore”.

The BBPT model will enable key project stakeholders to understand the readiness of

their projects to implement BIM, to identify critical inefficiencies and the factors that

cause the inefficiencies in their project delivery approaches, and to implement

managerial strategies for strengthening the drivers that are likely to motivate them

and overcoming the hindrances that they are likely to face. If BIM is used

collaboratively in these building projects, many inefficiencies, such as delays in

drawing production, tremendous RFIs, and waiting for conformations or instructions,

would be considerably eliminated (Eastman et al., 2011). Therefore, once the current

industry practices of partial BIM implementation are transformed through diagnosing

the key project stakeholders’ BIM implementation activities and changing them,

productivity performance will eventually be enhanced.

The specific research objectives of this study are to:

(1) Identify the critical NVA activities in the current BIM implementation practices

in Singapore, assess their influence on productivity, and examine the leading

causes to these activities;

(2) Develop a BIMIR evaluation model for building projects in Singapore;

(3) Investigate the BIMIR statuses and productivity performance of building projects

in Singapore;

Page 40: building information modeling–based process transformation to improve productivity in the

20

(4) Propose an organizational change framework for building projects that implement

BIM;

(5) Examine the critical factors driving and hindering the local construction industry

to change towards full BIM implementation; and

(6) Develop a BBPT model that can evaluate the BIMIR statuses of building

projects, propose managerial strategies for moving towards higher levels of BIM

implementation, and determine the priorities of implementing the proposed

strategies.

Figure 1.4 outlines the BBPT model and links the research aim and objectives. The

model consists of two part-models and can be further deconstructed into six

components. These components are associated with the six research objects

mentioned above. The application of the fuzzy synthetic evaluation (FSE) approach

and the definition of the four BIMIR statuses will be elaborated in Chapter four. The

detailing of the model will be developed, described, and explained in Chapter nine.

Model Part I: BIMIR evaluation(Fuzzy synthetic evaluation)

Model Part II: BIMIR movement (Organizational change perspective)

BBPT model

BIMIR statuses: (1) no BIM; (2) lonely BIM; (3) collaborative BIM; (4) full BIM

Evaluation criteria: critical NVA activities

BIMIR status evaluation of projects in Singapore;Productivity and causes in projects of four statuses

Objective1

Objective2

Objective3

Objective4

Objective5

Objective6

Organizational change framework

Hindrances to change and drivers for change

Management strategies for BIMIR improvement;Implementation priorities of strategies

Figure 1.4 Deconstruction of the BBPT model

1.6 Scope of Research

This research is driven by the increasing concern of the Singapore government about

the suboptimal productivity in the construction industry, and the need of the industry

Page 41: building information modeling–based process transformation to improve productivity in the

21

to be integrated and collaborative. BIM has been recognized by governments and

more and more professionals in the construction industry worldwide. For instance, the

US made it mandatory to use BIM in government projects since 2008 and Hong Kong

re-modelled its existing Mass Transit Railway projects for facility management

purpose (Cheng, 2013). Previous studies (Rogers, 2013; Mohd-Nor, 2014; Wong et

al., 2014) have added many managerial values to BIM implementation in the

construction industry, such as critical success factors of strategic BIM adoption in

architectural and engineering consulting services as well as BIM capabilities in QS

practices. In addition, although it is originated from automobile production

management, the lean thinking is also recognized in enhancing project performance

by eliminating wastes in the project delivery process. In this study, several specific

boundaries are identified below:

· Research focus. This study focuses on applying BIM to facilitate process

transformation in building projects in Singapore for two reasons. Firstly,

productivity performance in the local construction industry is of great concern

due to the image of low-tech of and over-reliance on the foreign workers. BIM

has been deemed as one of the useful tools in enhancing productivity

performance through optimizing project delivery process and reducing the

inefficiencies in this process (Nath et al., 2015). Secondly, it is process

transformation in the construction industry that makes BIM implementation

valuable (Arayici et al., 2011; Autodesk, 2012; Khosrowshahi and Arayici, 2012;

Enegbuma et al., 2014). Although the Singapore government has made BIM e-

submissions (all architectural and engineering plans) mandatory for all new

building projects greater than 5,000 m2 after July 2015, currently the mandate

mainly stresses on the design stage, where construction activities do not begin,

rather than full BIM implementation in the entire project lifecycle (Lam, 2014).

Design consultants work in their own areas for regulatory planning approvals,

without considering the collaboration with downstream parties and disciplines.

Page 42: building information modeling–based process transformation to improve productivity in the

22

The contractors and operations and maintenance team are usually not involved

upfront to contribute their expertise. This is not the spirit of BIM as it results in

separate BIM adoption among the major stakeholders in different phases. Thus,

there is a need for the current project delivery process to be transformed towards

full BIM-enabled delivery, namely the IPD, VDC, and DfMA approaches. This

transformation reduces wastes such as defects, change orders, waiting for

information, and reworks, enhancing overall productivity performance in building

projects in Singapore.

· Project lifecycle. The Singapore government has mandated BIM e-submissions in

the design stage, and has been driving the collaboration and integration

throughout the construction value chain. Without sufficient interactions between

design consultants, contractors, and fabricators, the efforts made for the

submissions in the design stage cannot be reused in the work during the

construction stage, let alone the operations and maintenance stage. Thus, this

study intends to identify and transform the critical NVA activities in the current

BIM-based project delivery process. In this study, the project lifecycle refers to

the planning, design, design-construction, construction, handover/closeout, and

operations and maintenance stages in the building project context. The demolition

stage is beyond the scope of this study.

· Major stakeholders. Government agencies, owners, architectural consultants,

engineering consultants, general contractors, trade contractors, fabricators,

suppliers, operations and maintenance teams, and so on are the key project

stakeholders that carry out BIM implementation activities in different stages of

the pre-defined project lifecycle. The potential causes to the NVA activities will

be examined based on these roles.

Page 43: building information modeling–based process transformation to improve productivity in the

23

1.7 Research Hypotheses

Based on the research problems identified (see Section 1.3) and the literature review

(see Chapter two to Chapter five), the following hypotheses are formulated in this

research:

Hypothesis 1: The construction industry agrees upon frequent NVA activities in the

current project delivery in the Singapore context;

Hypothesis 2: The BIMIR statuses of building projects in Singapore are low;

Hypothesis 3: The higher the BIMIR status, the lower the criticality of the wastes and

the higher the productivity performance;

Hypothesis 4: Moving towards higher levels of BIM implementation is hindered by a

set of critical hindrances which can be interpreted from the organizational

change perspective; and

Hypothesis 5: Moving towards higher levels of BIM implementation is driven by a set

of critical drivers which can be interpreted from the organizational change

perspective.

1.8 Structure of the Thesis

This thesis is organized into 10 chapters, as shown in Figure 1.5. Following this

introductory chapter, Chapter two provides an overview of productivity performance

in the Singapore construction industry. The target and present situation of

productivity performance are described. Policy initiatives that are meant to enhance

productivity are reviewed, especially those regulations related to promoting BIM

implementation in the local construction industry.

Page 44: building information modeling–based process transformation to improve productivity in the

24

Chapter 1:Introduction

Chapter 2: Review ofproductivity-related policies in Singapore

Chapter 3: Review of Traditional and BIM-based project delivery processes

Chapter 4: Review of NVA activities and proposal of a fuzzy BIMIR evaluation model

Chapter 5: Review of factors affecting BIM implementation and proposal of an organizational change framework

Chapter 6:Research design and data collection

Chapter 7:Data processing and analysis of two surveys

Chapter 8:BIM adoption and project delivery process

transformation in a construction and development firm - a case study

Chapter 9:Development of a BBPT model

Chapter 10:Conclusions, limitations, and recommendations

Part II: Research methodology

Part III: Data analysis anddiscussions

Part V: Conclusions

Part I: Literature review and proposals

Part IV: Model development

Figure 1.5 Structure of the thesis

Chapter three reviews the literature related to BIM implementation process. The

characteristics of five project delivery approaches are reviewed, namely traditional

project delivery process, current project delivery process in the Singapore

construction industry, and full BIM-enabled delivery processes (including IPD, VDC,

and DfMA) which are adapted in the context of Singapore.

Chapter four reviews the literature on the NVA activities in the project lifecycle

which also result from the comparison between the current project delivery and the

full BIM-enabled delivery. Possible resulting unproductive wastes and potential

causes contributed by the key roles are identified. Besides, four BIMIR statuses are

Page 45: building information modeling–based process transformation to improve productivity in the

25

defined with support from previous studies. Using the critical NVA activities as

evaluation criteria, a fuzzy BIMIR evaluation model for building projects is

developed.

In Chapter five, hindrances to and drivers for change towards full BIM

implementation are identified. More importantly, based on existing theories of

organizational change, an organizational change framework for building projects

using BIM is proposed, which consists of 29 change attributes in terms of people,

process, technology, and external environment. This framework also serves as the

process transformation framework.

Chapter six focuses on the research methodology. A flow chart is presented to show

the research process. Two rounds of surveys and a case study were conducted, and

data were collected through questionnaires, interviews, observations, and past

document analysis. Multiple methods were selected and explained for the data.

Chapter seven reports the in-depth data analysis results of the two surveys and

relevant discussions. The critical NVA activities in current BIM implementation

practices were identified, which enabled to calculate the BIMIR statuses of surveyed

building projects. Chapter eight describes the findings of the case study in a large

construction and development firm based in Singapore.

Chapter nine is dedicated to the development of the BBPT model for building

projects. The application of the model was explained step by step in the building

project context in Singapore. In addition, the building projects that were involved in

both surveys were used to demonstrate how this model works.

Page 46: building information modeling–based process transformation to improve productivity in the

26

Chapter ten is the final chapter and concludes the thesis. This chapter presents main

findings, contributions to scholarship and industry. Validation of the research

objectives and hypotheses as well as limitations of the study are discussed.

Recommendations for future research work are also proposed.

Page 47: building information modeling–based process transformation to improve productivity in the

27

Chapter 2: Review of Productivity Performance and Relevant

Policies in the Singapore Construction Industry

2.1 Introduction

This chapter provides an overview of existing body of background knowledge related

to productivity in the Singapore construction industry. To begin with, a general

review of productivity performance by the end of 2016 in the construction industry is

presented, which indicates the progress under the first CPR and the beginning of the

second CPR. Thereafter, principal policies related to incentives, funds, advanced

technologies, and so on under the second CPR, which would be implemented in the

next few years for enhancing productivity performance in Singapore, are reviewed.

Most of these productivity development programs are issued by the BCA, MOM,

MOF, and MND in Singapore. Finally, there is still a need for understanding the BIM

adoption status in the process of project delivery transformation for productivity gains

in Singapore.

2.2 Overview of Productivity Performance in Singapore

In 2010, the ESC (2010) recommended a challenging target for Singapore to achieve

productivity growth of 2% to 3% per year over the next ten years, more than double

the 1% rate which was achieved over the last decade. The main sources of weak

productivity growth in the last ten years were in service industries such as restaurants

and real estate services, and in the construction industry as well.

To support the ESC’s recommendation to raise productivity for sustained economic

growth, the MND and BCA incorporated the inputs of industry practitioners and the

recommendations by the International Panel of Experts, and formulated the first

Page 48: building information modeling–based process transformation to improve productivity in the

28

holistic CPR to transform the local construction industry and uplift its productivity.

Endorsed by the National Productivity and Continual Education Council in

November 2010, this roadmap aimed to build a highly integrated and technologically

advanced construction sector which is led by progressive firms and supported by a

skilled and competent workforce by 2020 (BCA, 2011a, 2011c). A four-pronged

approach was proposed (see Table 2.1).

Table 2.1 First CPR in Singapore

Prongs Associated Initiatives

Regulating demand

and supply of low cost,

lower skilled foreign

workforce through

FWL and MYE system

(1) Cutting the MYE progressively to regulate the supply of

low cost foreign workers;

(2) Imposing higher levy to moderate the demand for low

cost foreign workers.

Enhancing quality of

the construction

workforce

(1) Enhancing construction registration of tradesmen

scheme. The BCA would expand key construction trades

recognized under this scheme by 2011;

(2) Introducing new tiered-levy framework. From July 2011,

unskilled workers would be phased out from the construction

sector. Higher skilled foreign workers would be

distinguished from basic skilled workers to enjoy lower levy.

This levy differential would be progressively raised to

encourage employers to upgrade and retain more

experienced and higher skilled workers;

(3) Upgrading workforce at all levels. The Workforce

Training and Upgrading (WTU) scheme under the CPCF co-

funds training courses and skills assessments.

Imposing regulatory

requirements and

setting minimum

standards to drive

widespread adoption of

labor-saving

technology

(1) Enhancing buildability framework, which requires

architects and engineers to adopt “easier-to-construct”

building designs. A new constructability component would

also be introduced to require contractors to adopt more

labor-saving construction methods and technology;

(2) Driving BIM implementation. The BCA would mandate

BIM e-submissions of architectural, structural, and MEP

plans for building works for regulatory approvals by 2015.

Offering financial

incentives to encourage

manpower

development,

technology adoption,

and capability building

Enhancing the CPCF, including a BIM fund, to help firms

cope with upcoming manpower policy changes. This could

extend funding support to cover more firms, expand funding

scope, and raise funding support levels to push firms to

make a swift switch to technology in place of labor.

Source: BCA (2011a, 2011c).

To steer the industry towards enhancing productivity, the BCA established the

Construction Productivity Centre (CPC) in April 2010 and the Centre of Construction

Page 49: building information modeling–based process transformation to improve productivity in the

29

Information Technology in September 2010. The purposes are to educate and raise

the local industry’s awareness and ownership on productivity improvements and

manpower development. A customer-centric account management approach was

adopted to administer the incentives to encourage technology adoption, manpower

development, and capability building by the local firms (BCA, 2011a, 2011c). Some

key initiatives of the CPC include:

· Showcasing best practices and successful stories in productivity improvements

through a bi-monthly publication called “Build Smart” for industry players;

· Recognizing industry productivity leaders through awards, such as construction

productivity award and BIM award, to cultivate a culture of productivity

excellence; and

· Establishing benchmark indicators for productivity improvements to create

greater ownership in productivity improvement across the construction sector.

In the meantime, the BCA started to organize the Singapore Construction

Productivity Week (SCPW) annually in 2011. This event further heightens the

industry’s awareness of the latest initiatives and best practices for productivity

improvements. Skilled builder competition, BIM competition, BuildTech exhibition,

and site visits of innovative projects would be held. Thus, the SCPW could serve as a

learning platform for the construction industry to gain valuable insights into best

practices, new technologies, and skills that positively influence productivity

enhancement at the individual, firm, and industry levels.

The BCA and the MND would continue to review and evaluate the effectiveness of

the strategies under the first CPR to drive the industry to improve productivity and

build capabilities. Despite the abovementioned efforts made by the Singapore

government and the local industry since 2010, productivity performance was not

desirable under this CPR. It can be seen from Table 1.1 that the YoY changes in labor

Page 50: building information modeling–based process transformation to improve productivity in the

30

productivity from 2011 to 2016 in the Singapore construction industry were 2.2%

(2011), 2.7% (2012), -5.5% (2013), 1.1% (2014), 1.9% (2015), and -0.5% (2016),

respectively, measured in terms of VAP (SDOS, 2017). The figures indicated that

labor productivity: (1) overall improved in the last seven years; (2) usually increased

in a few years, followed by a decrease in a certain year; and (3) experienced smaller

and smaller yearly changes (absolute values) to some extent. The large decrease (-

5.5%) in 2013 might be because the mandatory BIM e-submissions in the

architectural discipline took effect in July 2013 and the submissions in other

disciplines were then not mandated. In conclusion, the targeted productivity growth

was not achieved from 2013 to 2016 and higher productivity gains in next few years

need to be pursued.

Challenges to improve productivity were briefly discussed. In addition to the heavy

reliance on lower-skilled foreign workforce and entrenchment in the traditional CAD-

based project delivery approach which were analyzed in Section 1.2, other challenges

were identified from the literature review. For example, Ofori (2005) found that the

major challenges to improve productivity in Singapore were delays due to compliance

with regulations, errors in design, poor skills of workers, reworks of rectifying defects,

inadequate pre-project planning, and changes in design. Hwang and Soh (2013) also

identified that lack of planning and control would be a challenge.

2.3 Productivity-Enhancing Policies in Singapore

Because of the suboptimal productivity performance, productivity-enhancing

initiatives are imperative. The second CPR was rolled out in June 2015, which adds

on the first CPR and targets three key areas, namely a higher quality workforce,

higher capital investments, and better integrated construction value chain (BCA,

2015e).

Page 51: building information modeling–based process transformation to improve productivity in the

31

2.3.1 Higher quality workforce

First, building up higher skilled or R1 workers. The MOM would require all

construction firms to have at least 10% of their WPHs to be qualified as R1 workers

from January 2017 onwards (MOF, 2014; BCA, 2015c). This is to improve the skills

profile of the construction workforce.

According to the BCA and MOM (2014), about 15% of WPHs had been qualified as

R1 workers in the Singapore construction industry, but they were unevenly

distributed across construction firms. To accelerate the formation of a higher-skilled

construction workforce across the entire industry, the BCA would implement a two-

year upgrading phase from the beginning of 2015, requiring the construction firms to

upgrade 5% of their own WPHs to R1 status by the end of 2015, and another 5% by

the end of 2016. This would enlarge the pool of R1 WPHs in Singapore. The

construction firms that failed to meet the upgrading requirement would be disallowed

from hiring new R2 WPHs, for a maximum period of 12 months, or shorter until they

met the 10% minimum R1 proportion requirement.

Next, incentivizing the upgrading of workers by widening levy differential. Table 2.2

presents the levy rates of WPHs from 2014 to 2017 in the construction sector. It can

be seen that the levy differentials between R1 workers and R2 workers would be

widened from S$250 in 2014 to S$400 till 2017.

Table 2.2 Levy schedule for WPHs from 2014 to 2017 (S$)

Time July 2014 July 2015 July 2016 July 2017

R1 R2 R1 R2 R1 R2 R1 R2

MYE Quota 300 550 300 550 300 650 300 700

MYE Waiver 700 950 600 950 600 950 600 950

Source: MOF (2015).

Also, the upgrading of workers was incentivized through co-funding the WTU

scheme under the second CPCF. To incentivize firms to adopt technology and build

Page 52: building information modeling–based process transformation to improve productivity in the

32

capability, the government would co-fund more training courses at professional,

managerial, executive, and technical (PMET) levels. Specifically, up to 90% would

be funded for local construction workers, and up to 40% for experienced foreign

workers in 2015 and 2016.

In addition, building up a local core of workforce. A variety of scholarships or

sponsorships would be provided for university students, building specialists

(supervisors and foremen), Institute of Technical Education applicants, and so on to

attract locals.

Last but not least, launching a five-year rebranding roadmap to attract and retain a

strong pipeline of local talent into the built environment sector. This roadmap was

jointly formulated by the MND, the BCA, industry stakeholders, and the Institutes of

Higher Learning in May 2014. Key initiatives under the roadmap would help drive

transformation in the sector to offer conducive work environments, better human

resource (HR) practices, and meaningful careers for attracting local talents. Beyond

these, this roadmap would also focus on raising awareness on the sector through

structured internships for students and attachment programs for teachers. A

memorandum of understanding was signed between the BCA and the construction

industry joint committee to promote the adoption of good HR practices in firms

through a new pledge for a better built environment workplace (BCA, 2014c).

2.3.2 Higher capital investments

According to BCA (2015a), S$450 million was set aside in March 2015 for the

second tranche of the CPCF in the next three years to help the construction sector

make higher investments in impactful and productive technologies as well as improve

the quality of its workforce. This added on the existing S$335 million committed to

Page 53: building information modeling–based process transformation to improve productivity in the

33

enhance productivity in the sector. It was expected to benefit about 7,000 firms to

drive higher productivity gains.

Public sectors would take the lead in government projects. Firstly, the BCA would

work with other key public agencies to operationalize their productivity roadmaps

through a structured framework, which would guide them to meeting the national

productivity growth target. Secondly, to incentivize consultants and contractors to be

more productive, tendering advantages would be given to progressive consultants and

contractors. This was gradually implemented since September 2014. Lastly, the MOF

(2014) stated that, for selected Government Land Sales (GLS) sites, the use of

productive technologies such as Prefabricated Bathroom Units (PBUs) and

Prefabricated Prefinished Volumetric Construction (PPVC) would be mandated in the

tender conditions. A minimum percentage level of prefabrication would be stipulated

for industrial GLS sites. For example, two selected GLS sites at Yishun Avenue 4 and

Jurong West Street 41 should meet these new requirements (BCA, 2014b). PPVC

involves the assembly of whole rooms or apartment units complete with internal

fixtures that are produced off-site and installed on site in a Lego-like manner.

On the other hand, the private sector would be incentivized to adopt a greater extent

of DfMA under the second tranche of the CPCF (BCA, 2015a). DfMA is the process

of designing products to optimize manufacturing functions, and to ensure minimized

cost, maximum quality, delivery time reliability, and customer satisfaction (Belay,

2009). With DfMA, maximum off-site production and assembly as well as minimum

assembly work on site can be targeted. Prefabrication enables more work to be done

in a controlled factory environment, and productivity to be raised through automation

and better quality control, much like in a manufacturing process. To support the shift

towards DfMA, a strong core of PMET personnel would be needed to lead to the

advancement of the sector. Starting with developers, architects and engineers design

Page 54: building information modeling–based process transformation to improve productivity in the

34

for off-site manufacturing and on-site assembly and installation. Also, a bigger pool

of at least 30% of higher skilled workers would be required to anchor the workforce,

which was consistent with the strategies to build up higher quality workforce

mentioned in Section 2.3.1 (BCA, 2015a).

2.3.3 Better integration of value chain

The BCA has been encouraging the local firms to collaborate with their partners in

their project teams using common BIM models. BIM enables all parties in the

construction value chain to better visualize designs, detect design problems early,

enhance planning and coordination, and reduce reworks for projects (Chelson, 2010;

Eastman et al., 2011; Khosrowshahi and Arayici, 2012). Under the BIM roadmap of

the first CPR, the BCA has mandated BIM e-submissions of all architectural,

structural, and MEP plans for building projects for regulatory approvals from July

2015 onwards. Also, it has been providing a BIM fund under the first CPCF tranche

to help firms to increasingly adopt BIM technology (BCA, 2011a). The BIM fund

intended to help the local firms to incorporate BIM technology into their work

processes at two levels:

· Firm level scheme. It supported individual firms to build up capability in BIM

modeling, visualization, value-added simulation and analysis, and project

documentation; and

· Project collaboration scheme with a cap of S$210,000. It supported the firms to

build up capability in BIM project collaboration to reduce design conflicts and

costly reworks downstream.

BCA (2015d) stated that applications for firm-level BIM adoption would not be

accepted since 22 May 2015. Applications having been accepted earlier by the BCA

would continue to be processed for approval under the first CPCF Tranche.

Page 55: building information modeling–based process transformation to improve productivity in the

35

To encourage wider adoption of BIM in the industry, the BIM funding support was

enhanced. The enhancement allowed a firm to double the number of applications

from three to six. But the firm was required to use a slightly bigger sized project and

achieve a 20% instead of a 10% productivity improvement for the fourth to sixth

application. The S$210,000 cap for project collaboration scheme was removed to

encourage more project partners to use BIM collaboratively. An one time support for

the expenditure of manpower involved in setting up the firm’s BIM deployment plan

was also added to the list of supportable items (BCA, 2015d).

Nevertheless, according to Lam (2014), only 20% applications were at project

collaboration scheme, indicating a lack of BIM collaboration under the first tranche

of the CPCF. Therefore, to help firms reap the full benefits of BIM and build up their

multidisciplinary collaboration capabilities beyond just modelling, the new BIM fund

(version two) was released in July 2015 (BCA, 2016). This fund would help BIM-

ready firms defray part (up to 70%) of their costs in training, consultancy, and

software and hardware. Applicants are required to submit a joint application together

with another firm of a different discipline.

Furthermore, the Singapore government has been driving the use of VDC, an

integrated approach that combines BIM technology and advanced management

methods to improve productivity. Specifically, it has been proven to increase

profitability, improve reliability and predictability before project execution, and

enhance project efficiency to higher levels (Li et al., 2009; Kunz and Fischer, 2012).

The BCA Academy has been partnering with the Stanford University’s Center for

Integrated Facility Engineering, a leading research center for VDC, to offer advanced

management programs at the chief executive officer as well as senior and middle

management levels. These programs aim to help the local construction industry

practitioners, from developers to consultants and contractors, to understand the value

Page 56: building information modeling–based process transformation to improve productivity in the

36

of VDC and BIM, and take an integrated approach in the planning, design,

construction, and operation processes of construction projects (BCA, 2014a).

2.4 Summary

This chapter reviewed productivity performance and relevant productivity-enhancing

polices in the Singapore construction industry. Although these initiatives formed a

holistic plan to improve productivity, this study focused on the collaboration and

integration across the entire construction value chain. One important reason for this

was the global recognition of the BIM technology that may bring considerable

changes to the project lifecycle. As a key enabler to integrate various activities along

the planning, design, construction, and operations and maintenance phases, BIM

promotion has been one of the most critical policies implemented in Singapore.

In line with the Singapore government’s efforts to slow down the growth of the

foreign workforce to a more sustainable pace, the local construction industry has to

continue to be restructured and transformed along with the rest of the local economy.

Productive growth is an effective way to remain globally competitive and to attract

and retain more locals and skilled labor. Both the local government and the industry

practitioners should be motivated and prepared to implement BIM to achieve the

targeted productivity growth.

Page 57: building information modeling–based process transformation to improve productivity in the

37

Chapter 3: Review of Traditional and BIM-Based Project

Delivery

3.1 Introduction

This chapter reviews the literature on revolutionary project delivery process of

adopting BIM in the construction industry, from the traditional project delivery

process, the current project delivery process in the Singapore context, to three

collaborative approaches that are increasingly used recently in the global construction

industry. With BIM as a facilitator, IPD, VDC, and DfMA deliver projects with

different stresses in the project lifecycle. The key activities related to BIM in these

processes are summarized. These processes are reviewed from the perspectives of

team building, technology adoption, project phasing and execution, and so on. In

addition, a comprehensive comparison among these processes is provided.

3.2 Traditional Project Delivery Process

Despite the rapid evolvement of project delivery process in the construction industry,

the traditional delivery approach was the basis for transformations. Arain (2005)

stated that history is important and knowledge from experience would assist in

making good decisions in project management now.

According to the Association of General Contractors (AGC, 2006), traditional, 2D-

based design evolved from pencils, to overlay drafting, to layers and levels seen in

CAD programs. These long market-accepted “flat” media, separate nature of the

layers, and multiple design and consulting disciplines had contributed to the 2D,

layered, and disconnected process prevalent today. In the 2D-based delivery process,

the tools and process available to a project team contributed to a distinct inability to

Page 58: building information modeling–based process transformation to improve productivity in the

38

see, think, and document from an integrated 3D (and beyond) way. For example, the

implications of a moved beam on a duct simply could not be known or seen in a 2D

environment. They must be imagined. Thus, the 2D design process allowed the

possibility that the design was not complete, as not all areas were drawn.

The roles and activities of the major stakeholders in a building project were

summarized in the traditional delivery process. According to the American Institute

of Architects and the American Institute of Architects, California Council (AIA and

AIACC, 2007), the project team includes two categories of major stakeholders,

primary participants and key supporting participants. The former is those participants

that have substantial involvement and responsibilities throughout the project,

including the owner, architect, and general contractor; the latter includes primary

design consultants (specifically, the structural engineer and MEP engineers in this

study) and subcontractors (specifically, including the manufacturer and supplier in

this study). The government and operations and maintenance team are also included

in “people” which is defined in Section 1.2. Table 3.1 presents a brief conclusion of

the major stakeholders and key activities in each project phase in the traditional

delivery process. This approach is commonly known as a design-bid-build (DBB)

method, a viable and most widely used delivery method for most construction

projects, especially for public building projects (Miller et al., 2000; Ibbs et al., 2003;

Ling et al., 2004; Autodesk, 2008). Architectural and engineering contracts tend to be

solely awarded to provide design services before the construction phase. The design

was usually not totally fixed until the construction phase because trade contractor

input was not available until then. Due to this disconnect, this delivery process

usually results in frequent claims and disputes among the participants as well as cost

and time overruns (Azhar et al., 2014). Therefore, the construction industry needed

alternative delivery methods.

Page 59: building information modeling–based process transformation to improve productivity in the

39

Table 3.1 Key stakeholders and activities in the traditional delivery process

Phases Major stakeholders Key activities

Predesign Owner, architect Owner: setting project requirements,

objectives, and so on

Schematic

design

Owner, architect;

Structural engineer, MEP

engineers

Architect: developing conceptual

design alternatives using CAD;

Owner: giving feedbacks and making

decisions

Design

development

Owner, architect;

Structural engineer, MEP

engineers

Architect and engineers: developing

detailed design using CAD;

Owner: giving feedbacks and making

final decisions

Construction

documentation

Owner, architect;

Structural engineer, MEP

engineers

Architect and engineers: producing

drawings and specifications for

downstream uses such as preparing

tender documents

Agency permit/

Bidding

Government;

Owner, architect;

Structural engineer, MEP

engineers;

Tenders (general contractor,

subcontractors)

Architect and engineers: submitting

building plans for regulatory approvals;

passing necessary documents to the

general contractor who wins the bid;

Construction Government;

Owner, architect;

Structural engineer, MEP

engineers;

General contractor,

subcontractors

General contractor: reproducing 2D

construction drawings using CAD,

doing site preparation, planning

schedule, outsourcing works to

subcontractors, communicating with

the owner and design consultants

especially for changes management and

RFIs; preparing final 2D as-built

drawings

Operations and

maintenance

Owner;

Facility manager

Owner: engaging operations and

maintenance team;

Facility manager: managing the

building based on the final 2D as-built

drawings

Source: AIA and AIACC (2007); Eastman et al. (2011); AIACC (2014).

The transformation needed in the construction industry may be achieved through the

use of technology. Nevertheless, despite large investments in equipment, CAD, and

web-based collaboration technologies over the past two decades, the industry has not

seen anticipated gains in productivity (Howard and Björk, 2008). One root cause is

the information and knowledge fragmentation both vertically over project phases and

horizontally over the value chain. Consequently, decisions made are often less than

optimal. Another reason is the inherent wastes occurred in the construction delivery

processes (Chua and Yeoh, 2015).

Page 60: building information modeling–based process transformation to improve productivity in the

40

3.3 Current Delivery Process

Productivity is always a problem that needs to be continuously addressed. In

particular, the Singapore government has expressed its great concerns in recent years

about productivity in the construction industry. As mentioned in Section 2.2, the

undesired productivity performance from 2013 to 2016 did not meet the targeted

productivity growth set in 2010. To improve this situation, the BCA has identified

and mandated BIM e-submissions as one of the key technological tools to improve

productivity in the construction industry (Nath et al., 2015).

The future of the design and construction industry is going to be driven by

technology. The best example emerging today is the use of 3D, intelligent design

information, commonly referred to as BIM, which is expected to gradually move the

Singapore construction industry away from a “2D based” delivery process towards a

“model based” process. In a 3D based delivery process, BIM technology allows

project teams to see and collaborate in 3D models. More important than the

technology-enabled way, is the information that team members get, the interactivity

and linkages that the technology fosters, and the intelligence and analysis that this

linked data promotes. Use of the intelligence housed within a BIM model allows

teams to see and interact differently, which is far more intelligent than teams involved

in a 2D based process. Model reviews, virtual huddles, and electronic computer-aided

virtual environments change the environment, duration, nature, and results of

construction process. Shop drawings may be waived when shop models or computer

numerically controlled (CNC) fabrication models are used. RFIs may become

obsolete, or at least be significantly reduced in number, and be resolved much quicker

if the models were deployed as jobsite tools (AGC, 2006).

Page 61: building information modeling–based process transformation to improve productivity in the

41

Therefore, as one of the four prongs in the first CPR mentioned in Section 2.2, BIM

e-submissions of all building plans for all new building works with a GFA of 5,000

m2 and above has been mandated by the Singapore government (BCA, 2011a, 2011c).

This initiative has been driving the local building project delivery process into a

status of partial BIM implementation (see Figure 3.1). Currently BIM implementation

in Singapore tends to stress on the design stage, where on-site activities do not begin,

and on regulatory approvals, rather than considering downstream uses.

Architectural design

Structural design

MEP design

Architectural model

Structural model

MEP model

General contractor,trade contractors,

manufacturers, suppliers

Re-producing all BIM models

Coordination, shop drawings, as-built

submissions to Architect

Not sharing, or sharing

incomplete BIM models

Submissions to government

2D drawingsfor operations &

maintenance

Figure 3.1 Current partial BIM implementation in the Singapore construction industry

It can be seen from Figure 3.1 that currently BIM is not used consistently in different

phases of a building project in Singapore. The BCA’s gap analysis of the first BIM

roadmap revealed many problems in the current state of BIM adoption, such as firm-

based rather than project-wide BIM collaboration (Lam, 2014). Specifically, the

owner may lack relevant knowledge and be detached from BIM processes. BIM

implementation requires a significant amount of resources upfront. Even though

return on investment has been widely justified (Singh et al., 2011), the owner might

not be able to see beyond initial costs. The architect and engineers tend to use their

design models only for their own benefits; they may over emphasize the mandatory

BIM e-submissions and lack time to perform design coordination for downstream

uses. More importantly, their design models are of poor quality, and rarely shared

with downstream parties because it is not their responsibilities to do that. Without

knowing the downstream BIM uses, the design team may not be able to identify the

Page 62: building information modeling–based process transformation to improve productivity in the

42

reusable project information and important information exchanges (Anumba et al.,

2010). In addition, the contractors and facility manager are usually not involved in the

design phases to contribute their expertise. Thus, the general contractor must re-build

the design models based on the 2D drawings, specifications, and incomplete design

models from the design consultants to coordinate key trades, produce shop drawings,

and develop and submit as-built BIM models to the architect during construction

(Sattineni and Mead, 2013; Lam, 2014). Moreover, most trade contractors lack BIM

skills and the facility manager rarely uses BIM (Lam, 2014).

BIM implementation in many projects can be as basic as the availability of a 3D

model produced by one or more specialty contractors or suppliers, such as a steel

fabricator or mechanical contractor (AGC, 2006). It is not unusual, particularly while

the 2D conversions continue to be the norm, for multiple models to be made available

on the same project.

The general contractor may make use of intelligent models for portions of the project

scope to assist with many of its traditional activities (AGC, 2006). Many of these

BIM uses include:

· Assisting in scoping during bidding and purchasing;

· Reviewing portions of the scope for analyses such as value engineering;

· Coordinating construction sequencing (even if just for two trades); and

· Demonstrating project approaches during marketing presentations.

Only portions of the project scope and only specific trades may be modeled in each of

the above cases. Even though, these BIM uses are not widely adopted across the

contractors in Singapore. Therefore, the current way of delivering a building project

in the Singapore construction industry can be figured out based on the traditional

delivery process as the whole process has not been changed fundamentally. In fact,

Page 63: building information modeling–based process transformation to improve productivity in the

43

those activities completed with CAD are substituted by those with 3D modeling

technology (see Table 3.2). From this table, it is notable that the key stakeholders and

the phases they become involved remain unchanged.

Table 3.2 Key stakeholders and activities in the current BIM adoption process

Phases Major stakeholders Key activities

Predesign Owner, architect Owner: setting project requirements,

objectives, and so on;

Architect: developing site model and massing

models using BIM

Schematic

design

Owner, architect;

Structural engineer,

MEP engineers;

Owner: giving feedbacks and making

decisions;

Architect: developing conceptual architectural

model using BIM;

Engineers: developing structural and MEP

models using BIM according to the conceptual

architectural model

Design

development

Owner, architect;

Structural engineer,

MEP engineers;

Owner: giving feedbacks and making final

decisions;

Architect: updating architectural BIM model;

Engineers: updating structural and MEP BIM

models according to the latest architectural

BIM model

Construction

documentation

Owner, architect;

Structural engineer,

MEP engineers;

Architect and engineers: producing drawings

and specifications for downstream uses such as

preparing tender documents

Agency permit/

Bidding

Government;

Owner, architect;

Structural engineer,

MEP engineers;

Tenders (general

contractor,

subcontractors)

Architect and engineers: submitting building

plans in BIM format for government’s

approvals; passing necessary documents (2D

drawings, and design models if willing to

share) to the general contractor who wins the

bid

Construction Government;

Owner, architect;

Structural engineer,

MEP engineers;

General contractor,

subcontractors

General contractor: re-producing 2D

construction drawings using CAD and re-

building design models using BIM for

construction uses; doing site preparation,

planning schedule, outsourcing works to

subcontractors, communicating with the owner

and design consultants especially for changes

management and RFIs; preparing final 2D as-

built drawings

Operations and

maintenance

Owner;

Facility manager

Owner: engaging operations and maintenance

team;

Facility manager: managing the building based

on the final 2D as-built drawings

Source: AIA and AIACC (2007); Eastman et al. (2011); BCA (2013b); AIACC

(2014).

Page 64: building information modeling–based process transformation to improve productivity in the

44

Overall, the current project delivery process adopted in Singapore is a partial BIM

adoption process. If the upfront design consultant team does not collaborate with the

downstream parties, the true spirit of BIM will not be realized as it results in

fragmented BIM uses between the designers, contractors, and facility manager. As a

result, there will be many problems in the construction and operations and

maintenance phases, such as frequent RFIs, change orders, and reworks. Therefore, it

is necessary to develop proper strategies to drive for better BIM collaboration and

integration throughout the construction value chain.

3.4 Full BIM-Enabled Delivery Processes

3.4.1 IPD

3.4.1.1 Overview of IPD

IPD is defined as “a project delivery approach that integrates people, systems, and

business structures and practices into a process that collaboratively harnesses the

talents and insights of all participants to optimize project results, increase value to the

owner, reduce waste, and maximize efficiency through all phases of design,

fabrication, and construction” (AIA and AIACC, 2007).

Traditional project delivery methods have been found as inefficient and litigious

(Eastman et al., 2011; Azhar et al., 2014). As a result, the construction industry is in

an urgent need of alternative delivery methods. Recently IPD has emerged as a

method with a potential to revolutionize the project delivery. It is expected to meet

the need of reducing inefficiencies and wastes that are embedded in the current

planning, design, and construction practices (Kent and Becerik-Gerber, 2010).

Page 65: building information modeling–based process transformation to improve productivity in the

45

Despite its potential, IPD implementation is still in its infancy (AIACC, 2014), and

not many projects have been reported to be delivered using this new delivery method

(Azhar et al., 2014). For instance, Khemlani (2009) studied how the IPD process was

used in an IPD project, the Sutter Medical Center Castro Valley (SMCCV) in

California. The results showed that the time for structural design was reduced from an

expected 15 months to eight months, and was informed of more information from

other disciplines than usually available, leading to better design quality. Another

metric was that despite all the time spent planning the design process and meetings to

do 3D coordination (all of which were billable hours), the cost for design was at or

below the anticipated level. Thus, the design was proceeding with higher quality, at a

faster pace, and with no quantifiable increase in the cost. The SMCCV project could

be a landmark project in the US construction industry, because it was the first one to

show that IPD was not just an utopian vision but a practical reality that could actually

be implemented in both large and small projects. In addition, credit had to go to all

the firms involved in this project, including the core IPD team and the larger project

team. Their experience and willingness to adjust their routine work practices to take

advantage of the opportunities of IPD had been the key to the success of this project.

The primary goal of IPD is to maximize collaboration and coordination for the

entirety of a project. Typically one contract for building an IPD team is agreed upon

by the owner, architect, engineers, general contractor, and any other party who may

have a primary role in the project. At a minimum, though, an IPD project includes

tight collaboration between the owner, architect and/or engineers, and general

contractor which is ultimately responsible for construction of the project, from early

design through project handover (AIACC, 2007, 2014). Any subcontractors or

consultants may have a similar agreement with one of these parties.

Page 66: building information modeling–based process transformation to improve productivity in the

46

To distinguish IPD from other delivery models, researchers (Cohen, 2010; AIACC,

2014; Azhar et al,. 2014) identified, at a minimum, early involvement of key

participants (EIKP), shared risk and reward (SRR), multi-party contract (MPC),

collaborative decision-making and control (CDMC), liability waivers among key

participants (LWKP), and jointly developed and validated project goals (JDVG) as

key characteristics of IPD projects (see Table 3.3). It is expected that by employing

these key characteristics in an IPD project, most shortfalls of the commonly-used

project delivery methods can be addressed.

Table 3.3 Key IPD characteristics and descriptions

Characteristics Descriptions

JDVG The owner, with the help of the project team, clearly defines

achievable project goals and benchmarks for measuring them. Risks

and rewards are associated with achieving the goals

EIKP Continuous involvement of the owner, architect and/or key engineers,

as well as general contractor and/or key subcontractors from early

design through project completion

SRR The IPD team members mutually share the reward of achieving

project targets and simultaneously bear the risk of missing the

targeted cost, schedule, and quality

MPC The IPD team members sign a single, multi-party agreement (or equal

interlocking agreements) that clearly defines the roles and

responsibilities of all the team members

CDMC The IPD team members agree upon a clear and specific set of

predetermined criteria for joint decision-making and collective control

of the project

LWKP The IPD team members waive any claim amongst themselves except

for in the instance of a wilful default to reinforce the sense of unity

and a collaborative environment

Source: Cohen (2010); AIACC (2014); Azhar et al. (2014).

In order for the construction industry to change with confidence from the traditional

delivery method to IPD, key IPD principles should be implemented. Although there

were many versions of the key IPD principles concluded in the last decade (AIA and

AIACC, 2007, 2009; AIACC, 2007), a latest conclusion of them (see Figure 3.2) was

given in Integrated Project Delivery: An Updated Working Definition, Version 3 by

AIACC (2014).

Page 67: building information modeling–based process transformation to improve productivity in the

47

Which are fostered

by these

Optimize thewhole

Trust Respect IntegrationJoint

ownership

The whole point

TransparencySafe

environmentGood

technologyShare risk& award

Early & clear value definition

CollaborationWhile arise

out of these

To get this

you need these

Figure 3.2 Eleven essential principles of IPD (AIACC, 2014)

A brief description of these essential principles is given below (AIACC, 2014):

(1) Optimize the whole, not the parts. The point of integrating a project team is to

deliver the whole project in a way that gives what the owner values. Whether that

is optimized design solutions, increased efficiency over the building’s lifetime, or

a fast track schedule requires that all the key parties in the project make decisions

that are best for the project, rather than their own slices of the pie.

(2) Early and clear goal definition. To optimize the whole, the team must agree on

what the “whole” is. Project goals are developed early and agreed upon by all the

key participants.

(3) Collaboration. The project team members must collaborate closely, deeply, and

continuously to optimize the whole.

(4) Integration. The team members can’t work collaboratively if they cannot easily

share information, find appropriate time and spaces to communicate, understand

how their different design processes interact with each other, and get many other

systems integrated together across disciplines.

(5) Joint ownership. Meaningful collaboration requires the key participants to have a

sense of ownership over the project and its end goals.

(6) Respect. Meaningful collaboration also requires respect to each other. The team

members mutually commit to treating each other with respect and valuing each

professional’s input. Any individuals can contribute innovative solutions, so roles

Page 68: building information modeling–based process transformation to improve productivity in the

48

are not defined as strictly as those in traditional projects, but rather assigned to

the best qualified person.

(7) Trust. Meaningful collaboration cannot occur without trust.

(8) Transparency. Trust requires transparency. All the team members have access to

accurate and latest information. Often an investment in technology compatibility

will be necessary to ensure their access to the information when they need.

(9) Safe environment. Mutual trust also requires the project environment to be safe

for the team members to provide suggestions without fear of taking responsibility

for being wrong.

(10) Shared risk and reward. An integrated project depends on best-for-project

thinking and behaviors when the team makes decisions. In reality, it is difficult

for a firm to sacrifice its own profitability for the good of the project. Risk/reward

sharing is predefined to cost or benefit the participants according to the project

outcomes rather than contributions from individual firms. Best-for-project decisions

will benefit all the participants, and one that attempts to benefit a particular firm

at the expense of the project will reduce all the participants’ profitability.

(11) Good technology. Advanced technologies are useful for the integration of

building systems together across firms and disciplines. Technologies such as BIM,

cloud servers, and teleconference tools are crucial.

In summary, IPD encourages early contribution of knowledge and experience. The

key stakeholders from each project phase must be involved in the design stage, which

shapes the project and its performance (Fischer et al., 2014).

3.4.1.2 IPD and BIM

AIACC (2007) stated that although IPD can possibly be achieved without BIM, BIM

implementation is recommended because it is essential to efficiently achieve the

Page 69: building information modeling–based process transformation to improve productivity in the

49

collaboration required for IPD. BIM technology has provided a foundation for better

and proficient collaboration among the project participants and has been proved to be

an effective tool for managing construction projects (Eastman et al., 2011). BIM tools

and processes enable the team to integrate both design and construction expertise to

effectively support design decisions (AIACC, 2014).

Azhar et al. (2014) studied how BIM was useful to achieve the above characteristics

of IPD, and found that BIM can act as a catalyst for IPD implementation because it

supports several key IPD characteristics. Table 3.4 shows the proposed relations

between attributes of BIM and the key characteristics of IPD. In some cases, the

relations between BIM attribute and IPD characteristic are direct and simple to

understand, whereas the other relationships may not be so straightforward. For

example, consistency and accuracy of data in BIM has a direct impact on decision-

making, and better-calculated goals can be set for the project with more accurate data

and collaborative team efforts. Besides, BIM has made it possible to visualize the

design prior to actual fabrication; this attribute empowers the IPD team with better

design and project control. With BIM, QTOs are easier and more accurate, leading to

better cost estimations which can in turn strengthen grounds for better risk and reward

arrangements. BIM interface allows multi-user collaboration, which can be helpful in

promoting multi-party contract.

Table 3.4 BIM support for achieving IPD characteristics (Azhar et al., 2014)

Attributes of BIM Key characteristics of IPD supported

Consistency and accuracy of data CDMC, JDVG

Design visualization CDMC, JDVG

Ease of quantity takeoff SRR, JDVG

Multi-user collaboration EIKP, JDVG, MPC

Energy efficiency and sustainability CDMC, SRR, JDVG

Reporting CDMC, JDVG, SRR

Page 70: building information modeling–based process transformation to improve productivity in the

50

Autodesk (2008) examined the impact of IPD on the building industry and found that

BIM could be central to the process changes that IPD would bring. The growing BIM

implementation is a core enabling process for the enhanced collaboration that IPD

demands. Figure 3.3 presents how the use of BIM in an integrated environment

enables the IPD working process and results in more predictable, accurate, and

responsible project outcomes. Therefore, BIM solutions enable IPD and can deliver

dramatic advances in building technology, but the full potential of BIM will not be

achieved without adopting structural changes to the existing project delivery methods.

Previous studies (Porwal and Hewage, 2013; AIACC, 2014) found that IPD has

materialized as a project delivery method that could most effectively and fully

facilitate BIM implementation in building and construction projects. Thus, the

situation when IPD does not adopt BIM was not discussed in this research.

Figure 3.3 Use of BIM in an integrated environment enables IPD process (Autodesk,

2008)

Page 71: building information modeling–based process transformation to improve productivity in the

51

3.4.1.3 IPD process

The Integrated Project Delivery: An Updated Working Definition (AIACC, 2014)

gave a common definition of the IPD process, which is mainly used in the US

construction industry and other similar countries overseas (see Figure 3.4).

Criteria

design

Detailed

design

Implementation

documents

Agency coord

/Final buyout

Agency

Owner

Architect

Engineers

General contractor

Trade contractors

Facility manager

Lifecycle phase Concept-

ualization

Sta

keho

lder

(P

eopl

e)

Constr-

uction

Closeout

Figure 3.4 Stakeholder involvement in the commonly-used IPD process overseas

(AIACC, 2014)

The project phases named in Figure 3.4 differ from those in the traditional and current

project delivery processes (predesign, schematic design, design development,

construction documentation, agency permit/bidding, construction, and operations and

maintenance) to take advantage of two critical factors (AIACC, 2014):

· In addition to the design expertise of a traditional design team, expertise in

construction aspects (scheduling, material performance and availability, means

and methods, and so on) is available throughout the design process; and

· BIM tools and processes enable the team to integrate this broader range of

knowledge in order to provide effective support for design decisions.

Therefore, inputs from a broader team which is coupled with BIM tools to model and

simulate the project will enable the design to a higher level of completion. The

conceptualization, criteria design, and detailed design phases involve more proactive

efforts than their counterparts in the traditional flow (AIA and AIACC, 2007; AIACC,

2007). Thus, the phases in the IPD process (criteria design, detailed design,

Page 72: building information modeling–based process transformation to improve productivity in the

52

implementation documents, and agency review) and those in the traditional and

current delivery processes (schematic design, design development, construction

documentation, and agency permit) are named slightly different. More or fewer

activities are included in the phases of an IPD project because efforts are moved

forward, but these phases are logically defined as the same as their traditional

counterparts. However, no study in the literature by far has attempted to investigate

the IPD process in Singapore.

The overseas IPD process needs to be adapted for use in the Singapore context, as

shown in Figure 3.5. The reasons are: (1) the Singapore construction industry is

usually policy-driven. The local government sees the value of BIM implementation

and puts it into practice, specifying or encouraging the industry to follow. For

example, the Singaporean government has lead the promotion of computer-assisted

building permit reviews, first in 2001 by implementing an electronic drawing review

system called e-Plan Check, again in 2006 by incorporating 3D automated electronic

building reviews into standard procedures, and currently by mandating building plans

e-submissions in BIM format (Eastman et al., 2011; Khosrowshahi and Arayici, 2012;

Cheng and Lu, 2015; Solihin and Eastman, 2015; Juan et al., 2017); (2) Unlike in the

US, where BIM implementation is largely industry-driven, a top-down approach is

adopted in Singapore, where the government is the dominant force promoting BIM

implementation (Juan et al., 2017). The government believes that BIM

implementation can indeed improve productivity. By far Singapore is the only

country that has mandated almost all new building projects to use BIM; and (3) As

policy makers, key government agencies in Singapore such as the Urban

Redevelopment Authority (URA) and the BCA participate early and actively in local

building projects.

Page 73: building information modeling–based process transformation to improve productivity in the

53

AR2 CrD DtD ID FB

3 HC O&M

Agency

Owner

Architect

Engineers

General contractor

Trade contractors

Facility manager

Lifecycle phase1 CC CS

Notes: 1. CC=conceptualization, AR=agency review, CrD=criteria design, DtD=detailed design,

ID=implementation documents, FB=final buyout, CS=construction, HC=handover & closeout,

O&M=operations and maintenance; 2. “AR” phase runs concurrently with “CrD”, “DtD”, and

“ID” phases; 3. “FB” phase completes the buyout of remaining contracts such as trade

contractors not involved during design and materials without long lead time.

Sta

keh

old

er (

Peo

ple

)

Figure 3.5 Stakeholder involvement in the proposed IPD process for the Singapore

construction industry (adapted from Kent and Becerik-Gerber (2010) and AIACC

(2014))

The proposed IPD approach is described in a typical IPD project. Prior to actual

kickoff of the design process, or concurrent with the very earliest steps, significant

preparatory work need to be done, including (AIACC, 2014):

· Key project participants are selected to form an IPD team through a multi-party

contract and its subcontracts (if any), including the owner, architect, key

engineers, general contractor, and key trade contractors. Key regulatory agencies

are also essential and involved;

· Team communication and coordination processes are established, and

collaboration training is done;

· The risk and reward sharing structure that will best incentivize the

accomplishment of the project’s goals is developed;

· Key technologies such as BIM and data exchange protocols are established; and

· Co-location facility and frequency are determined.

1. Conceptualization. This phase mainly includes the following activities (AIACC,

2014):

· As many key stakeholders as possible are involved to contribute their insights.

Page 74: building information modeling–based process transformation to improve productivity in the

54

· Key project parameters are captured, such as schedule and performance metrics

(economic, energy, and so on);

· Cost benchmarks are identified and initial cost targets are determined; and

· Preliminary schedule is developed.

2. Agency review. This phase actually runs concurrently with the criteria design,

detailed design, and implementation documents phases, and mainly includes the

following activities:

· The regulatory agencies provide high-level compliance information such as

relevant policies in Singapore (AIACC, 2014);

· The regulatory agencies work with the IPD team to develop a mutually agreeable

permit submittals schedule. Because of their involvement in the design process,

the general contractor and trade contractors will need to participate in submittals

preparation and respond to the agencies’ comments (AIACC, 2014);

· The IPD team applies for and obtains planning approval of one selected BIM

massing model at the end of the criteria design phase (BCA, 2013b);

· The IPD team applies for and obtains regulatory approvals of all building plans at

the end of the detailed design phase (BCA, 2013b); and

· The IPD team prepares submittals to meet legal requirements during the

implementation documents phase (AIACC, 2014).

3. Criteria design. Project targets and metrics whereby the success of the project will

be measured are developed and widely agreed upon in this phase. The following

activities are usually included (AIACC, 2014):

· Refining and fixing the key project parameters such as project scope, basic design

(massing, elevations, floor plans, and so on), system selection (structural, skin,

heating, ventilation, and air conditioning (HVAC), and so on), targeted cost,

overall schedule, and building components to be prefabricated;

Page 75: building information modeling–based process transformation to improve productivity in the

55

· Engaging all key trade contractors; and

· Developing procurement schedule.

4. Detailed design. This phase is longer and more intense than the design

development phase in the traditional and current project delivery processes because

more work is accomplished. The team finalizes all the design decisions that are

necessary to ensure that changes will not be necessary during construction. The

design is fully defined without ambiguity and uncertainty. This phase mainly includes

the following activities (AIACC, 2014):

· All building elements are defined;

· All building systems are fully engineered and coordinated. This includes the final

system coordination that in the traditional delivery process was usually deferred

until the construction phase when trade contractor input was available;

· The team will decide the level of detail (LOD) required; and

· Specifications are developed based on the fixed systems.

5. Implementation documents. Because the entire building and all the systems are

fully defined and coordinated at the beginning of this phase (the end of the detailed

design phase), this phase is much shorter than the construction documentation phase

in the traditional and current project delivery processes. This phase mainly includes

the following activities (AIACC, 2014):

· Merging the traditional shop drawing process into the design as the general

contractor, trade contractors, and suppliers have documented the construction

intent of the building systems and components;

· Commencing prefabrication of some systems and procurement of long lead items

as early as necessary because the design is fixed;

· Developing specifications to provide narrative documentation of the design intent

wherever necessary;

Page 76: building information modeling–based process transformation to improve productivity in the

56

· Generating documents where needed for processes such as financing,

procurement (bill of materials, BOM), regulatory permitting, and so on; and

· Documenting information for assembly, site layout, detailed schedule, and other

legal requirements.

6. Final buyout. IPD assumes the early involvement of all key trade contractors and

vendors, so buyout of work packages they provide occurs through developing prices

throughout the design phases, culminating at the end of the implementation

documents phase. The accelerated project definition during the criteria and detailed

design phases allows early procurement of long lead, custom, or prefabricated items.

The final buyout phase is much shorter than the bidding phase in the traditional and

current delivery methods, because downstream parties has already been engaged

earlier (AIA and AIACC, 2007). Therefore, this phase intends to complete the buyout

of remaining contracts such as trade contractors not involved during the design

process and materials without long lead time (AIACC, 2014).

7. Construction. In traditional projects, construction is often treated as the final stage

of design where design issues that were not addressed upfront are worked out.

However, in an IPD project, because construction expertise is integrated upfront

using BIM, the design is finalized during the detailed design phase and means and

methods are worked out during the implementation documents phase (AIACC, 2014).

However, some construction administration processes in the IPD project remain

similar to traditional practices. For example:

· Quality control, inspection, and testing will be relatively unchanged;

· Change orders, particularly for owner directed changes, must be formally

negotiated and documented; and

· Scheduling and progress will be periodically reviewed.

Page 77: building information modeling–based process transformation to improve productivity in the

57

8. Handover/Closeout. The pain share and gain share arrangements will be resolved

in this phase based on the achievement of the project targets. Besides, many other

aspects of the closeout of the IPD project are similar to those of traditional projects.

Some examples (AIACC, 2014) include:

· Finalization of an as-built model or other documentation. However, the model is

developed and updated using BIM;

· Punch list correction;

· Warranty obligations; and

· Occupancy and completion notification.

9. Operations and maintenance. AIA and AIACC (2007) stated that the IPD phases

concluded at the closeout phase. However, it also stated that facilities managers, end

users, contractors, and suppliers are all involved at the start of the design process in

the world of utopian IPD in the future. Fischer et al. (2014) argued that the IPD

approach brings the contractors’ and operators’ knowledge to the design stage with

user needs, and the output of the design phases must be the design of a facility that is

valuable for its users, can be built, and can be operated. Therefore, an ideal delivery

model of IPD may incorporate the operations and maintenance phase, especially as a

solution for the issue of BIM in the Singapore construction industry.

3.4.2 VDC

3.4.2.1 Overview of VDC

The concept of VDC is still continually evolving. Kunz and Fischer (2012) defines

VDC as “the use of integrated multidisciplinary performance models of design-

construction projects to support explicit and public business objectives”. Performance

models of a building project represent the goals and outcomes of different

stakeholders, including the owner and its architectural, engineering, and construction

Page 78: building information modeling–based process transformation to improve productivity in the

58

(AEC) services providers. Chua and Yeoh (2015) stated that VDC is an approach for

the designers and contractors working together as a collaborative team to build,

visualize, analyze, and evaluate the project performance on multidisciplinary models

in the design stage before tremendous time and resources are consumed during

construction.

Three stages of implementing VDC have been suggested by Kunz and Fischer (2012).

Firstly, visualization. The project team creates design models in a 3D environment to

virtually perform design, construction, and operations, based on performance metrics

(such as buildability score, constructability score, and schedule compliance) that are

predicted from the models and tracked in the process. This stage is commonly used

within the global construction industry (Li et al., 2009; Kunz and Fischer, 2012).

Secondly, integration. It tries to integrate various processes and different disciplines

involved in this project. The team develops computer-based automated methods to

reliably exchange data between disparate modeling and analysis applications.

Industry Foundation Classes (IFC) has been designed to enable this process. For

example, an integrated set of design models of different disciplines can be created

based on a shared IFC-based architectural model (Kunz and Fischer, 2012).

Fischer et al. (2014) found that visualization and simulation are the engine of VDC.

Visualization is, by far, the most effective way for the stakeholders to describe and

explain themselves accurately and to analyze their own work and that of others (Kunz

and Fischer, 2012). By using detailed and accurate 3D models, the AEC service

providers are able to communicate more clearly and effectively with each other, and

with the owner. In fact, many owners have little or no experience building anything

and cannot understand complex 2D shop drawings. 3D models are much easier for

most owners to comprehend. Meanwhile, simulation also allows a project team to

Page 79: building information modeling–based process transformation to improve productivity in the

59

make better informed predictions by showing how close different design alternatives

come to desired project outcomes and allowing the team members to see the

consequences of their decisions (Fischer et al., 2014). Also, multiple design options

can be carried forward for comparison (Parrish et al., 2008). For example, span steel

as well as precast and timber structural systems can be kept in play along with

appropriate MEP systems (Fischer et al., 2014).

Thirdly, automation. This is to automate some tasks in the design and construction

processes, which will be realized based on good visualization and integration (Kunz

and Fischer, 2012). Automated methods will be used at this implementation stage to

perform routine design tasks or help build subassemblies in a factory for on-site

installation. Moreover, Chua and Yeoh (2015) advocated the use of intelligence for

automation. In the first place, a repository of design and construction knowledge

should be built, and a series of automated tasks are then performed on the design

models by reference to this knowledge. For example, design detailing can be

automated using the knowledge from design codes, which can then drive automated

prefabrication processes. In addition, the design can be checked for manufacturability

before it is sent to the CNC cutter for automated fabrication. Gao and Fischer (2006)

found that in the design development phase, it is possible for the contractors to

integrate standard building products so that more off-site prefabrication and

assembling would be available. These building products would appear in the schedule

with precise styles and specifications for manufacturing.

In order for automation to improve design, project organizations need to dramatically

change their processes to perform more high-value design and analysis, and spend

much less time and billable efforts for routine design. To support fabrication, the

project has to change the traditional, DBB approach to a design-fabricate-assemble

(DFA) approach. Kunz and Fischer (2012) reported that automation fundamentally

Page 80: building information modeling–based process transformation to improve productivity in the

60

enables breakthrough performance in scheduling. The traditional DBB process

probably could not be compressed to build major projects within six months. In

contrast, this previous study suggested that many major projects could be built within

about six months if the DFA approach is adopted, and major subsystems are well

designed and integrated, with the fabrication being carefully crafted and controlled.

Automation capability maturity could be measured by schedule conformance or

design and construction phase productivity and cost (Kunz and Fischer, 2012). For

example, the Heathrow Airport project detailed and pre-assembled rebar cages on a

cycle time of one week or less, including detailing, fabrication, assembly, delivery,

installation, and concrete pour. On-site installation of pre-assembled systems was far

more rapidly than it ever did during field construction, leading to performance gains

in schedule performance, final product quality, and cost reliability and control (Kunz

and Fischer, 2012).

In conclusion, VDC is designed to support a multidisciplinary project team.

Appropriate stakeholders including the architect, engineers, general and multiple

specialty contractors, owner representatives, suppliers, and so on are involved early

from the early design stage to provide well-informed inputs to the design. An area

that requires significant development is user interface for multidisciplinary

stakeholders and for field workers. The user interfaces that currently exist may not

facilitate these inputs, resulting in a long design process. At the later stages of the

project, design decisions should be communicated to the field, particularly to the

crews who install various building components.

Li et al. (2009) identified eight advantages of VDC, including inspiration of novel

design, design error detection, construction plan rehearsal and optimization, detection

of unsafe areas, construction site management, construction communication, project

Page 81: building information modeling–based process transformation to improve productivity in the

61

information and knowledge management, and reduction of creeping managerialism.

The realization of VDC relies on constantly evolving solutions, and its wider

implementation depends largely on how its benefits are recognized by local

practitioners.

3.4.2.2 VDC and BIM

Autodesk (2008) found that integration of design and construction practices can

leverage new tools and technologies, including:

· BIM design tools: providing platforms for integrated processes which are built on

coordinated information and result in enhanced coordination, fewer RFIs and

change orders, and fewer reworks;

· 3D and four-dimensional (4D) visualization: enhancing scope definition,

stakeholder engagement, and decision-making;

· Model-based analyses: using digital analytical tools to understand structural

performance, cost estimates, and other inferential reasoning from the design

while it is underway;

· 4D modeling: coordinating construction activities and increasing the reliability of

scheduling;

· Fabrication from 3D models: resulting in elimination of shop drawings, better

tolerance and lead time, and faster field assembly;

· Model-based BOM: providing faster, more accurate QTOs for cost estimating,

energy analysis, and so on; and

· Laser scanning: capturing existing (as-built) conditions that can be combined

with design and construction models to provide reliable as-built models.

Most of these tools and technologies are either BIM uses or can be supported by BIM

implementation. Therefore, although being perceived mainly as a design tool or at

Page 82: building information modeling–based process transformation to improve productivity in the

62

best a visualization tool in 3D or 4D, BIM can form the backbone of VDC (Chua and

Yeoh, 2015).

Typically, a composite building information model refers to one single model that

represents overall virtual design of a building. Within this model may reside other

models. Each of them is specific to a certain scope of work such as electrical systems,

plumbing piping, mechanical equipment, structural frame, or architectural elements.

These individual models are “linked” together so that the individual files can be

viewed and compared as a composite one. In this regard, a typical project team

creates, uses, coordinates, and assembles all these different models into one

conglomerate that can be used for overall building uses.

The benefits of BIM for a building project were briefly concluded by Sattineni and

Mead (2013). Firstly, it has considerable process implications for the architect.

Because of the parametric nature of BIM, when an architect models a building,

sections and details are instantly drafted. This means that labor efforts are added to

the schematic design phase, and that at the completion of the schematic design phase,

the team has a model that is rich in information. In practice, up to two out of three

architects consider the greatest value derived from BIM to be the reduction in

reworks during the design development phase. Besides, BIM provides the architect

with a means of communicating design intent in a way previously unavailable. BIM

software can produce photo-realistic renderings of both interior and exterior surfaces

and spaces, which allows the architect to communicate its design intent to the owner

to help inform design decisions, as well as to the contractors to ensure that pricing

and scheduling efforts are as accurate as possible. This ability has fundamentally

changed the way the contractors are able to understand and plan for architectural

design.

Page 83: building information modeling–based process transformation to improve productivity in the

63

Secondly, BIM provides the contractors with many other tools. Perhaps the most

important one is the ability to coordinate complex building systems that interface

with one another. For example, building services such as MEP and fire protection

piping are typically located within ceilings, walls, and other confined spaces. As

such, they usually require considerable coordination to ensure they all fit and function

properly. Prior to BIM implementation, this process occurred in the field, by the

contractors, and typically led to tremendous RFIs and supplemental instructions from

the design team. These RFIs led to reworks and delays that were costly to the project.

With BIM, interfacing trade contractors can proactively gather together to work these

conflicts out in the virtual environment. This avoids not only the inefficient process

of seeking clarifying information in the field, but also costly work stoppages and

redesigns (Sattineni and Mead, 2013).

Thirdly, BIM is used considerably by the contractors in 4D analysis which is

generally accepted as the ability to tie the sequencing of activities on, from

construction schedule to the objects in the model. This analysis enables construction

professionals to visualize exactly how the building will be erected in sequence,

allowing the general contractor to test its scheduling logic, critical path, and uncover

otherwise unforeseen conditions that may relate to site logistics or unique

environmental conditions. The analysis also avails the general contractor of the

ability to communicate its construction plan to the owner, architect, and specialty

contractors (Sattineni and Mead, 2013).

Lastly, BIM can also provide the operations and maintenance team with tools to

better manage the property. If stipulated by the contract, intelligent information can

be added to a working model produced by the design and construction team. This

model can replace the cumbersome “operations and maintenance” manuals.

Information including maintenance schedules, the manufacturer’s contacts,

Page 84: building information modeling–based process transformation to improve productivity in the

64

warranties, and replacement parts can all be linked within the model (Sattineni and

Mead, 2013).

To summarize, the list of benefits is not exhaustive, but represents broad application

and significant power of BIM tools. BIM has many added benefits for the service

providers to improve design, preconstruction, construction, and operations and

maintenance processes.

In the VDC approach, project requirements are represented as performance models.

BIM models are integrated and multi-disciplinary, providing a good medium for the

project stakeholders to collaborate on a shared data platform. These models are also

performance models in the sense that they exhibit some level of capabilities to

analyze, evaluate, and predict project performance related to specified project

objectives. To enhance information management, a model fit for intended

downstream uses should be provided. This should ensure the necessary LODs that are

needed to be furnished to different team members at different stages of the project so

that they can correctly perform the functions required, and make the appropriate

decisions in a timely manner (Chua and Yeoh, 2015).

Gao and Fischer (2006) explored nine BIM uses (model functions, MFs) that were

manifested by 11 case projects in Finland. Such functions included:

· MF0: Establishment of design targets;

· MF1: Visualization/marketing;

· MF2: Simulation and analysis;

· MF3: Design checking (system design coordination or constructability checking);

· MF4: Construction drawings and schedules/BOM;

· MF5: QTO and cost estimation;

· MF6: Supply chain management/building product procurement;

Page 85: building information modeling–based process transformation to improve productivity in the

65

· MF7: Construction planning/4D modeling; and

· MF8: Facility management.

3.4.2.3 VDC process

Based on the above analysis on VDC and BIM, the VDC process in the Singapore

construction industry was proposed, as shown in Figure 3.6. The phases named in this

figure were consistent with those in the traditional and current delivery processes.

BIM implementation in the Singapore construction industry is usually influenced by

policies. New initiatives including VDC have been encouraged by the local

government.

BD DD CD AP/FB/PC HC O&M

Agency

Owner

Architect

Engineers

General contractorConstruction

model

Trade contractors

Facility manager

Lifecycle phase1 CC SD CS

Architectural model

Note: CC=conceptualization, BD=bidding, SD=schematic design, DD=design development,

CD=construction documentation, AP=agency permit, FB=final buyout, PC=preconstruction,

CS=construction, HC=handover & closeout, O&M=operations and maintenance.

Structural/MEP models

Sta

keh

old

er (

Peo

ple

)

Figure 3.6 Stakeholder involvement in the proposed VDC process for the Singapore

construction industry

Kunz and Fischer (2012) advocated that in a typical VDC project, all key

stakeholders should be invited to a project kickoff meeting, including the owner

representative, architect, major contractors, and a potential user. Regulatory agencies

and a facility manager are also involved in the meeting. Definition of the product

(facility), organization (participants), and process (design and construction phases) of

the project should be achieved in the meeting. The proposed VDC approach is

described below.

Page 86: building information modeling–based process transformation to improve productivity in the

66

1. Conceptualization. With the help of the principal architect, the owner sets project

requirements, including targeted schedule, cost, BIM use, and so on. The key

engineers as well as the general contractor and key specialty contractors are pre-

qualified (Khanzode et al., 2007).

2. Bidding. In this phase, the key engineers and contractors are engaged, either

separately or in a designer/contractor consortium.

3. Schematic design. This phase involves the agencies, owner, architect, structural

engineer, building systems designers (MEP engineers), and general contractor. Key

trade contractors (Khanzode et al., 2007) and the facility manager (Kunz and Fischer,

2012) should also be involved to contribute their knowledge. This phase mainly

includes the following activities (Gao and Fischer, 2006; Porwal and Hewage, 2013):

· The architect, together with the structural and MEP engineers, develops an

architectural massing model (usually selecting the best one from several

alternatives);

· The structural and MEP engineers work with the architect side by side even

though only architectural modeling is underway. They take advantages of

renderings or quantity and location information from the 3D architectural model

for their own analyses. The structural engineer normally uses the architect’s

model as a base to make strength calculations for preliminary framing plan,

evaluate the appropriateness of the architectural design, and compare different

options for the structural frame. MEP engineers conduct a computerized analysis

of the 3D spatial model, firstly simulating the architectural space model to

compare the architect’ concepts, and setting realistic targets such as sizing for

building services design. They also review the architectural model and give

feedbacks with respect to the more complicated systems. Then, they develop a

Page 87: building information modeling–based process transformation to improve productivity in the

67

structural model and MEP models when the architectural massing model is

almost fixed;

· The general contractor prepares gross square feet estimate and volume take-off

early and compares them to the owner’s cost target;

· The key trade contractors such as MEP subcontractors contribute construction

knowledge to help the MEP engineers develop their design models (Khanzode et

al., 2007; Fischer, 2008); and

· The design team applies for and obtains planning approval of one selected BIM

massing model at the end of this phase (BCA, 2013b).

4. Design development. This phase mainly includes the following activities (Gao and

Fischer, 2006):

· The architect simulates, compares, and selects building components, and

completes the architectural design model. This model is shared with the engineers

who have only to adjust, not re-create, the model to allow accurate outputs of

plans, details, and drawings;

· The structural engineer develops the structural design model based on the

architectural design model;

· The MEP engineers develop detailed MEP design models when the systems

specification is in place and the best solution of the MEP systems has been

already chosen, based on the shared architectural design model and structural

design model;

· All the building systems are engineered and coordinated by the project team. This

includes the final system coordination that in the traditional delivery approach

was usually deferred until the construction phase because the trade contractors’

inputs were not available until then;

· The general contractor uses the architectural, structural, and MEP design models

shared by the design team as bases to build a construction model. It is possible for

Page 88: building information modeling–based process transformation to improve productivity in the

68

the general contractor to integrate standard building products into this model so

that more off-site prefabrication and assembling will be available.

Constructability checking is also completed;

· The trade contractors can produce their shop models and fabrication models

based on the construction model and specific design models; and

· Specifications are developed based on the agreed and prescribed systems.

5. Construction documentation. This phase mainly includes the following activities

(Gao and Fischer, 2006):

· The design team shares its design models and 2D drawings with the owner, other

designers, and contractors where needed;

· Generating documents where needed for processes such as procurement (BOM),

permitting, and so on; and

· The project team develops specifications to provide narrative documentation of

the design intent wherever necessary;

6. Agency permit/Final buyout/Preconstruction. The following activities are

mainly included in this phase (Gao and Fischer, 2006):

· The design team applies for and obtains regulatory approvals of all building plans

of different disciplines (BCA, 2013b);

· The project team prepares submittals to meet local legal requirements where

needed (AIACC, 2014);

· The general contractor extracts quantity information of the items documented

earlier and sends accurate material lists to subcontractors to acquire their pricing;

· Prefabrication of some systems and procurement of long lead items can

commence as early as necessary since the design is fixed;

· The general contractor extracts QTOs and estimates cost; and

Page 89: building information modeling–based process transformation to improve productivity in the

69

· The general contractor simulates schedule options and finalizes the construction

schedule.

7. Construction. In this phase, the general contractor can use 3D models to control

the logistics of engineering, manufacturing, and construction. The design team can

update its design models as the project proceeds and possible changes are solved.

However, some construction administration processes in the VDC project remain

similar to traditional practices. For example:

· Quality control, inspection, and testing will be relatively unchanged;

· Change orders, particularly for owner directed changes, must be formally

negotiated, solved, and documented; and

· Scheduling and progress will be periodically reviewed.

8. Handover/Closeout. The general and specialty contractors, together with the

design team, maintain and update the construction model with the latest information.

Laser scanning technology can be used to capture the existing (as-built) conditions

that can be combined with the BIM models. Finally, a reliable as-built BIM model

that incorporates the as-built information of all the major systems and equipment in

the BIM model is created and will be moved to the operations and maintenance team.

9. Operations and maintenance. The operations and maintenance team, with

reference to the as-built model, manages the building and relevant utilities and makes

better informed operations and maintenance decisions.

Sattineni and Mead (2013) found that similar to how a carpenter needs a square to

complete a successful woodworking project, the designers and contractors need BIM

to complete a successful VDC project. Firms have many powerful tools to choose

from, and industry standards on how to use BIM technology continue to be rolled out.

Page 90: building information modeling–based process transformation to improve productivity in the

70

The construction industry is shifting towards an industry where the VDC process is

on its way to adoption, judging by user statistics (Jung and Joo, 2011). Khanzode et al.

(2007) used VDC tools to coordinate the MEP systems of a large healthcare project.

The owner, along with the architect, mechanical engineer, and general contractor,

pre-qualified the MEP subcontractors based on their abilities to coordinate and

collaborate their work with the work of other subcontractors using 3D/4D tools. The

detailed process and a pull schedule for the coordination of the MEP systems were

developed collectively by the design team, general contractor, and MEP

subcontractors. The general and specialty contractors were involved at the beginning

of the schematic design phase so that they could provide inputs into the

constructability and operations issues in the design. The MEP subcontractors were

responsible for modeling their portion of work using 3D tools in the design

development phase, and completing a fully coordinated design in 3D at the end of the

construction documentation phase. Finally, all the coordination work of the MEP

systems was done in a “Big Room”, and all the construction documents were also

generated from this room. As a result, the benefits of this VDC project in MEP

disciplines included labor savings ranging from 20% to 30% for all the MEP

subcontractors, 100% prefabrication for the plumbing contractor, less than 0.2%

rework for the mechanical subcontractor, zero conflict in the field installation of the

systems, and only a handful of RFIs for the coordination of the MEP systems. The

overall benefits to the owner included about six months’ savings on the schedule.

Kim and Fischer (2013) developed a decision-support system (DSS) using 4D model-

based analysis tools for tunnel construction. Because actual ground conditions were

much worse than those predicted in the preconstruction phase, the project schedule

delayed and much unnecessary cost overrun was caused to the general contractor.

However, following the analysis process of the DSS, the tunnel construction was

simulated. Visualization of the tunnel construction enabled more stakeholders to

Page 91: building information modeling–based process transformation to improve productivity in the

71

participate in the project review. Metrics (such as the number of trucks, amount of

concrete, hours of labor, and quantity of excavation) analyzed by the DSS speeded up

the decision-making of allocating resources to other stakeholders. Consequently, the

schedule was accelerated and overall schedule compliance was maintained.

Cho and Fischer (2010) developed an integrated system using VDC tools for supply

chain management in door, frame, and hardware installation process. Each status of

materials in a supply chain was scanned, 4D color-coded, quantified, and then

reported. Then both time logs from real-time data capturing tools and quantities

completed from VDC models were combined to create an as-built progress of the

supply chain. This progress would be compared with as-planned work plans. The

work plans were accordingly updated both daily and weekly for better alignment

between demand and supply. All the supply chain members (suppliers, field teams,

project managers, and owner) had access to the project website to see the status

reports and visualizations. This enhanced visual coordination and communication

between field crews and off-site personnel, and brought a high level of accountability.

3.4.3 DfMA

3.4.3.1 Overview of DfMA using BIM

According to McFarlane and Stehle (2014), in general, DfMA is the design and

manufacture of discrete sections of a product (or structure) which are then assembled

at one location, typically a factory for mass-production. It has been used in the

automotive and aerospace industries for many years and has been applied to many

other industries (Selvaraj et al., 2009). Nevertheless, the uptake of DfMA in the

construction industry is slow, because it is either sporadic or serves as a partial

solution, such as precast concrete elements and structural steelwork componentry.

Page 92: building information modeling–based process transformation to improve productivity in the

72

When applied to the construction industry, DfMA focuses on developing a design that

is optimized for off-site manufacture (OSM) of discrete sections of the final facility

and on-site assembly of them after being transported to site, essentially moving site-

based activities into a controlled factory environment. Figure 3.7 shows a DfMA

envelope, which consists of three major components.

Geometry

Metadata

Production

Digital engineering

3D models- visualization- finite element- numerical control- 2D drawing

production

OSM- small-scale items- panelized systems- large-scale modules- fully enclosed space:

individual rooms to complete buildings

BIM- program (time & cost)- quality & performance- safety & maintenance- environmental impacts: noise pollution, carbon footprint,

disruption to businesses & residents

Figure 3.7 DfMA envelope (McFarlane and Stehle, 2014)

Firstly, the geometry model is a 3D virtual reality model. It allows both technical and

non-technical project team members to visually understand and interrogate the design

intent. This model mainly includes the engineers’ finite element models and CNC

fabrication models that enable automated production of building elements. The

models are also used to produce 2D drawings for non-automated processes such as

the regulatory approvals and third party manufacture of small-scale items (McFarlane

and Stehle, 2014).

Secondly, production represents OSM in a factory environment. Modular

construction or OSM is part of the DfMA process (McFarlane and Stehle, 2014).

Blismas and Wakefield (2009) regarded OSM as a contributor to progress in the UK

construction industry, within the term “Modern Methods of Construction”. Modules

Page 93: building information modeling–based process transformation to improve productivity in the

73

can range from small-scale items such as electrical fittings, through large-scale items

such as precast concrete floors and panelized systems in steelwork, precast concrete

or timber, to fully enclosed spaces such as individual rooms or complete buildings

(Ross et al., 2006). The entire fit-out process, namely the manufacture and assembly

of structural and MEP modules of different scales as well as decorative elements, can

be carried out in a factory. A higher level of quality control and improved overall

quality assurance can be achieved through factory production (Blismas et al., 2006).

In addition, the metadata model is a multi-dimensional database. This model contains

all relevant project parameters. Multiple design analyses can be conducted, such as

calculating and predicting the impacts of time, sequencing, scheduling, costs,

sustainability, constructability, and so on, allowing the team to assess different design

options and select the best one (McFarlane and Stehle, 2014).

The basis of DfMA is virtual reality modeling of the building, which includes four

significant elements, namely the discretization of the construction, 3D design

collaboration, 4D construction planning, and five-dimensional (5D) costing. All of

them should be interrogated and improved by the project team until the optimum

solution is reached (McFarlane and Stehle, 2014). As indicated in Figure 3.7, BIM is

part of DfMA. To adopt the DfMA approach, two of the major components, namely

3D geometry and metadata model, need full implementation of BIM.

Nevertheless, the design consultants also need to know how they will source what

they are drawing and ensure “fit” confidence on site. DfMA is a key driver of these

capabilities (Chandler, 2015). By using DfMA, a virtual reality project is constructed

and improved by the project team through several iterations. It allows all the key

stakeholders to participle interactively in the design and planning processes (Gibb and

Page 94: building information modeling–based process transformation to improve productivity in the

74

Isack, 2003), and ensures that all the project parameters are met prior to commencing

actual construction on site.

Some key advantages of DfMA include (Gibb and Isack, 2003; Blismas et al., 2006;

Blismas and Wakefield, 2009; McFarlane and Stehle, 2014):

· Interactive participation in the design and planning processes by all key

stakeholders, leading to optimum design solutions, such as rapid implementation

of design changes with the parametric nature of BIM;

· Minimizing on-site operations/activities;

· Reduced the number of site personnel;

· Reduced congested work areas and multi-trade interfaces;

· Reduced construction time and testing and commissioning time;

· Accurate project completion date;

· Reduced wastage (factory wastage is reduced to near-zero and on-site wastage is

significantly reduced);

· High quality or very predictable quality finishes;

· Enabling inspection and controlling off-site works; and

· Providing certainty of project cost outcomes.

As a subset of DfMA, OSM has long been recognized internationally as offering

numerous benefits to most parties in the construction process. It is further recognized

as a key vehicle for driving process improvements. For example, the Australian

construction industry had identified OSM as a key vision for improving the industry

over the next decade (Hampson and Brandon, 2004). This echoed sentiments overseas,

especially the UK. Like the UK, the Australian construction industry had been

characterized as adversarial and inefficient; therefore, structural and cultural reforms

were urgently needed. This call for efficiency and productivity improvements across

these industries suggested that OSM be a major role to play. Indeed, the UK

Page 95: building information modeling–based process transformation to improve productivity in the

75

government has proposed OSM as an important contributor to change the local

construction industry (Blismas and Wakefield, 2009).

Similar to the UK and Australia, the Singapore government has identified similar

initiatives, trying to achieve a quantum leap in productivity improvement. The BCA

and Singapore Press Holdings Limited (BCA and SPH, 2015) suggested that local

construction practitioners need to change their mindsets to focus on designing for

labor-efficient construction and moving as much construction work to off-site as

possible. To support the DfMA approach, an additional S$450 million has been set

aside to support the firms that adopt impactful construction technologies, and to train

and upgrade their workers to keep updated with technological advancements.

In October 2017, the BCA formulated a construction industry transformation map

(CITM), which envisions an advanced and integrated construction industry with

widespread adoption of leading technologies, led by progressive and collaborative

firms, and supported by a skilled and competent construction workforce. Key global

trends and challenges, such as digital revolution, rapid urbanization, and climate

change, increasingly impact the construction industry. To tackle these challenges, the

CITM identifies three key transformation areas, including Integrated Digital Delivery

(IDD), DfMA, and green buildings (BCA, 2017a).

However, currently the use of OSM or DfMA is not widespread, even though it may

be intuitively appealing. A major reason posited for the reluctance among owners and

contractors to adopt OSM is that they have difficulty ascertaining the benefits that

such an approach would add to a project (Pasquire and Gibb, 2002; Gibb and Isack,

2003). According to McFarlane and Stehle (2014), the greatest benefit of DfMA can

be realized subject to the combination of all the three components in the envelope

including the use of BIM. Thus, using advanced technologies such as BIM is

Page 96: building information modeling–based process transformation to improve productivity in the

76

encouraged by the Singapore government to drive the local construction industry to

transit to a higher degree of DfMA adoption (BCA and SPH, 2015).

3.4.3.2 DfMA process

Blismas and Wakefield (2009) reported that the real advantages of OSM or DfMA

can only be realized through a thorough understanding of the principles underpinning

manufacturing. Therefore, DfMA adoption requires fundamental structural changes to

the construction industry, compared to the manufacturing industry. The DfMA

approach changes the way people in the building industry work, both in terms of the

process and the product. However, there is little information about how the DfMA

approach may be used in the project lifecycle in the Singapore construction industry.

Based on the above analysis on DfMA and BIM, a proposed DfMA process for use in

the Singapore construction industry was figured out in this study (see Figure 3.8).

Manu-

facture

Substr-

ucture

Supers-

tructure

Fit-

out

Agency

Owner

Architect

Engineers

General contractor2

Manufacturer3

Subcontractors4

Facility manager

Notes: 1. CC=conceptualization, BD=bidding, SD=schematic design, DD=design development,

CD=construction documentation, AP=agency permit, FB=final buyout, CS=construction,

HC=handover & closeout, O&M=operations and maintenance; 2. General contractor: may be

manufacturer if conventional construction is not included; 3. Manufacturer: manufacturing team,

including factory based operatives, site erection teams, and so on; 4. Subcontractors: mainly for

traditional construction, including ground works, substructure, and so on; 5. Final buyout: the

engagement of the subcontractors that will complete traditional construction.

CD AP/FB5 CS HC O&M

Sta

keh

old

er (

Peo

ple

)

Lifecycle phase1 CC BD SD DD

Figure 3.8 Stakeholder involvement in the proposed DfMA process for the Singapore

construction industry (adapted from Ross et al. (2006) and McFarlane and Stehle

(2014))

Page 97: building information modeling–based process transformation to improve productivity in the

77

The project phases named in this figure were in line with their counterparts in the

traditional and current delivery processes, but the construction phase was divided into

four stages, namely manufacture, substructure, superstructure, and fit-out. As

mentioned in Section 1.2, BIM promotion in Singapore adopts a top-down approach.

The local government has been driving the incorporation of BIM into the DfMA

process.

McFarlane and Stehle (2014) advocated that to obtain an optimum solution, all key

stakeholders (both technical and non-technical) should be interactively involved in

the design and planning process. According to Figure 3.8, project phases and key

activities in a typical DfMA project are described below.

1. Conceptualization. With the help of the prime architect, the owner sets project

requirements, including schedule, cost, BIM uses, and so on. Key regulatory agencies

in Singapore also participate in the phase.

2. Bidding. Key engineers such as structural and MEP engineers are engaged. Since

all key stakeholders are required to contribute in the design stage, the general

contractor and the manufacturer should also be engaged to avoid them working at risk

in a financial manner before the construction phase. A two-stage contract, instead of

the contract that was traditionally awarded after the design stage, should be used

(Gibb and Isack, 2003; Ross et al., 2006). The manufacturing team will also act as the

general contractor if conventional construction is not included in this project.

3. Schematic design. This phase involves the agencies, owner, architect, structural

engineer, building systems designers (MEP engineers), general contractor, and

manufacturer. The higher the level of OSM, the more important it is to get the

manufacturer involved as early as possible (Ross et al., 2006). The facility manager

Page 98: building information modeling–based process transformation to improve productivity in the

78

should also be involved to contribute operations knowledge ahead of time. This phase

mainly includes the following activities (Gibb and Isack, 2003; Ross et al., 2006;

McFarlane and Stehle, 2014):

· Fixing key project parameters such as project scope, basic design (massing,

elevations, floor plans, and so on), system selection (structural, skin, HVAC, and

so on), and building components to be prefabricated;

· The architect, together with the structural and MEP engineers, general contractor,

and manufacturer, develops an architectural massing model (usually selecting the

best one from several alternatives);

· The structural and MEP engineers work with the architect side by side even

though only architectural modeling is underway. They take advantages of

renderings or quantity and location information from the architectural model for

their own analyses, which is similar with those of the VDC approach. Apart from

this, the design team also gets inputs from the general contractor and

manufacturer to develop the designs that are suitable for off-site manufacturing

and assembly in downstream phases. The engineers and contractors review the

architectural model and give feedbacks with respect to the more complicated

systems. Then, the engineers develop a structural model and MEP models when

the architectural massing model is almost fixed; and

· The design team applies for and obtains planning approval of one selected BIM

massing model at the end of this phase (BCA, 2013b).

4. Design development. During this phase, all the design decisions that are necessary

to ensure that changes during construction will not be necessary are finalized. The

design is fully and unambiguously fixed otherwise changes will be very costly after

manufacture of building elements and modules begins (Blismas and Wakefield, 2009).

This phase mainly includes the following activities (Gann, 1996; Gibb and Isack,

2003; Ross et al., 2006):

Page 99: building information modeling–based process transformation to improve productivity in the

79

· All building elements are defined;

· The LOD required is determined;

· The architect simulates compares, and selects building components, and

completes the architectural design model, which is shared with the engineers who

only need to adjust, not re-create, the model to allow accurate outputs of plans,

details, and drawings;

· The structural engineer develops the structural design model based on the

architectural design model;

· The MEP engineers develop the detailed MEP design models when the systems

specification is in place and the best solution of the MEP systems has been

already selected, based on the architectural design model and the structural design

model shared upfront;

· All building systems are fully engineered and coordinated, which includes final

system coordination;

· Specifications are developed based on the agreed and prescribed systems;

· The general contractor uses the architectural, structural, and MEP design models

shared by the design team as bases to build a construction model. Constructability

checking is completed; and

· The manufacturer creates its fabrication models in different disciplines based on

the models shared upfront.

5. Construction documentation. This phase mainly includes the following activities:

· The design team shares its design models and 2D drawings with the owner, other

designers, contractors, and manufacturer where needed;

· Generating documents where needed for processes such as procurement (BOM),

permitting, and so on;

· The manufacturer creates shop drawings if necessary from the shared models

(design models and construction model) or directly uses these models;

Page 100: building information modeling–based process transformation to improve productivity in the

80

· The project team develops specifications to provide narrative documentation of

the design intent wherever necessary; and

· The construction (including manufacture and assembly) team documents

information for fabrication, assembly, site layout, detailed schedule, and testing

and commissioning procedures.

6. Agency permit/Final buyout. Since the general contractor and manufacturer are

engaged before the design phase, this phase refers to the engagement of the

subcontractors that will complete the conventional construction, including ground

works, substructure, and so on. Thus, this phase mainly includes the following

activities (Ross et al., 2006):

· The project team applies for and obtains regulatory approvals of all building

plans of different disciplines (BCA, 2013b);

· The project team prepares submittals to meet the local legal requirements where

needed;

· The general contractor extracts QTOs and estimates cost;

· The general contractor extracts quantity information of the building components

documented earlier and sends accurate BOM to the subcontractors to acquire

their pricing. This is similar with the traditional process; and

· The general contractor simulates schedule options and finalizes the construction

schedule.

7. Construction. Since the DfMA approach is designed mainly for those parts that

can be prefabricated off site, including superstructure and fit-out. The construction

phase is divided into four phases (see Figure 3.8), and mainly consists of the

following activities (Ross et al., 2006):

· Manufacturing and assembling of the building systems and modules, and

transporting them to the site for installation;

Page 101: building information modeling–based process transformation to improve productivity in the

81

· The subcontractors complete the ground works and substructure on site; and

· The superstructure and fitting out processes can take place in the factory before

or while the ground works and substructure are being done on-site, leading to the

overall effect of compressing the on-site phase and activities.

8. Handover/Closeout. The general contractor, manufacturer, and design consultants

constantly maintain and update the construction model and fabrication models with

the latest information. With support from the laser scanning technology, a reliable as-

built BIM model that incorporates the existing (as-built) information of all the

systems and equipment is created and provided for the operations and maintenance

team. Besides, many other aspects of the closeout of the DfMA project are also

similar to those of traditional projects, including (AIACC, 2014):

· Punch list correction;

· Warranty obligations; and

· Occupancy and completion notification.

9. Operations and maintenance. The operations and maintenance team, with

reference to the as-built model which contains much intelligent information, manages

the building and relevant utilities and makes better informed operations and

maintenance decisions. The cumbersome “operations and maintenance” manuals are

discarded. The intelligent information includes, but not limited to maintenance

schedules, manufacturers’ contacts, warranties, and replacement parts (Sattineni and

Mead, 2013).

McFarlane and Stehle (2014) suggested a new procurement method to better

implement the DfMA approach. To develop an optimal design that suits for

manufacture and assembly, the owner may establish a contract with a single party

(either a contractor or a designer/contractor consortium) which assumes the full

Page 102: building information modeling–based process transformation to improve productivity in the

82

responsibility for both the design and construction of the building. The owner gives

the freedom to the winning contractor (or consortium) to propose and realize an

innovative design, including the use of new materials, and production and assembly

techniques. The only requirement is that the design should meet the owner’s

functional requirements. This may be ideal in the future once more and more firms

are able to take responsibilities in both the design and construction work.

3.5 Comparisons among Project Delivery Processes

3.5.1 Differences among project delivery processes

Based on the above review and analysis of the traditional, current, and full BIM-

enabled collaborative processes, the key activities related to BIM in these processes

are presented in Table 3.5. The major differences that make them uniquely defined in

a building project in the Singapore context can be concluded (see Table 3.6). It can be

seen that both the traditional process and current process are unproductive. Even

though the Singapore government has mandated BIM submissions of all building

plans, BIM collaboration between the design phase and downstream phases is not

widely achieved currently. Thus, process transformation is imperative in the local

construction industry.

In terms of the full BIM-enabled processes, IPD, VDC, and DfMA are commonly

recognized and used internationally. IPD is driven by the owner and satisfying the

owner’ demands is at the heart of the IPD process (Autodesk, 2008). It relies on the

collective expertise of all the key stakeholders throughout the project process,

particularly in the early stages. The resulting increase in project knowledge creates a

better understanding of the project earlier in the design process, enabling the IPD

team to more effectively assess their project options and consider how to align them

with the owner’s goals. Thus, all the key stakeholders in IPD are on the same boat,

Page 103: building information modeling–based process transformation to improve productivity in the

83

Table 3.5 Summary of the key activities related to BIM in the current process and the

proposed IPD, VDC, and DfMA processes in the Singapore construction industry

Phases Processes Key activities related to BIM

CC Current The owner and the architect set project requirements

IPD The key stakeholders are engaged, form an IPD team by a

multi-party contract, jointly set project goals and benchmarks,

outline BIM goals and potential BIM uses (such as 4D

modeling and model updating) based on the project

characteristics, stakeholders’ goals and capabilities, and desired

risk allocations, and identify the responsible stakeholders for

the BIM uses and information exchanges;

The team agrees on the reward/risk sharing arrangements

VDC

/DfMA

The owner and the architect set project requirements and outline

the BIM goals and potential BIM uses (such as 3D site analysis

and code validation) based on the project characteristics

SD

(criteria

design for

IPD)

Current The architect and engineers create their design models with

little collaboration and without the construction, fabrication,

and operations and maintenance inputs from the downstream

people

IPD All key project parameters (such as scope, basic design, system

selection, schedule, cost target, quality levels, prefabricated

components, buildability, and constructability) are set;

All the key trade contractors are engaged to input their site

expertise

VDC The design team and construction team agree on the multi-party

collaboration contracts to share data, identify the data

exchanges between the key firms, and define the exchange

procedures and formats;

The engineers and contractors work together with the architect

to develop architectural model; the facility manager may also

contribute to the design

DfMA The engineers, general contractor, and manufacturer are

engaged with two-stage contracts, further outline the BIM goals

and potential BIM uses (such as 3D coordination and digital

fabrication) according to their goals and capabilities as well as

risk allocations, and identify the responsible parties for the BIM

uses and the collaboration methods (such as regular meetings)

of data exchanges;

The engineers, general contractor, and manufacturer contribute

in the architectural modeling

DD

(detailed

design for

IPD)

Current The building elements may not be well defined;

The building systems may not be coordinated until the

construction phase

IPD All the building systems are fully engineered and coordinated,

with required LOD

VDC

/DfMA

The engineers build the structural and MEP models based on

the architectural model;

The general contractor creates the construction model and

fabrication model (if any) using the design models as bases

CD

(implemen

-tation

documents

for IPD)

Current The design team produces 2D drawings and specifications for

the downstream uses such as regulatory submissions and tender

documents preparation;

Prefabrication of some building components cannot commence

due to design uncertainties

Page 104: building information modeling–based process transformation to improve productivity in the

84

IPD

/VDC

/DfMA

The contractors and manufacturer document the construction

intent of the building systems and components to produce shop

and/or fabrication drawings;

The fabrication of the building systems, especially those long-

lead items, begins as the design is fixed;

The team generates documents for permitting, assembly,

detailed schedule, and so on

AP

(agency

review for

IPD)

Current

/VDC

/DfMA

The designers apply for planning approvals in BIM format

IPD Since the regulatory agencies participate actively in the design

stage, the team applies for planning approvals and responds to

the agency comments in parallel with the design stage

BD Current The designers only pass 2D drawings or incomplete design

models to potential contractors

IPD Since the key contractors have been engaged either in the

conceptualization phase or in the design stage, this phase entails

the buyout of remaining contracts such as the trade contractors

not involved in design and materials without long lead time

VDC The trade contractors that were not involved in the design stage

are engaged

DfMA Since the general contractor and manufacturer have been

engaged in the early design stage, this phase engages the

subcontractors to complete the conventional construction such

as the ground works and substructure

CS Current The general contractor re-builds the BIM models for

construction uses and their own submissions;

Due to the disconnection between the upfront and downstream

parties, RFIs may be frequently raised for the designers to

respond, and reworks need to be completed where necessary;

A low percentage of building components would be

prefabricated

IPD

/VDC

The team uses the models to guide construction, and reviews

and updates the models until completion

DfMA The manufacturer produces building systems and modules in

the factory environment before or while the ground works and

substructure are being done on-site

HC Current The team may spend much time and many resources to resolve

the disputes between the stakeholders

IPD The team finalizes the as-built BIM models and specifications

for operations and maintenance and resolves the risk and reward

sharing arrangements

VDC

/DfMA

The team finalizes the as-built BIM models and specifications

O&M Current The operations and maintenance team uses 2D as-built

drawings to manage the building unless the owner pays for the

3D as-built models

IPD

/VDC

/DfMA

The operations and maintenance team uses 3D as-built models

as planned in the project beginning to manage the building

Note: CC=conceptualization; SD=schematic design; DD=design development;

CD=construction documentation; AP=agency permit; BD=bidding; CS=construction;

HC=handover/closeout; O&M=operations and maintenance.

Page 105: building information modeling–based process transformation to improve productivity in the

85

(Source: Adapted from Gibb and Isack (2003); Gao and Fischer (2006); Ross et al.

(2006); AIA and AIACC (2007); Anumba et al. (2010); Kunz and Fischer (2012);

BCA (2013b); Porwal and Hewage (2013); AIACC (2014); Lam (2014); McFarlane

and Stehle (2014))

leading to an ideal approach of project delivery. However, the way of delivering

building projects may be still traditional now and it may not be changed in a short

time to get to the ideal IPD approach and forget about the existing way. Hence, IPD is

not very practical today due to several reasons. Among these are high degree of

concern regarding risk in relation to IPD and the close partnerships it necessitates,

and need for new legal frameworks to match the emerging IPD approach. Moreover,

many industry players feel there is a need for those within the industry to assimilate

new competencies and skills related to collaboration and information management to

support IPD. Azhar et al. (2014) found that very few projects have been delivered

under the IPD approach.

Table 3.6 Major differences among the proposed project delivery processes in

Singapore

Factors Traditional

process

Current

process

Collaborative processes

IPD VDC DfMA

Initiator None Government Owner Contractor Government

BIM use No Partially Not necessarily,

but highly

recommended

Fully, openly Fully, openly

Phase Linear,

distinct

Linear,

distinct

Lifecycle Design and

construction

Design and

construction

Party Silos,

Fragmented

Silos,

Fragmented

All the key

stakeholders

Architect,

engineers,

general

contractor,

key trade

contractors

Architect,

engineers,

general

contractor,

manufacturer

Financial

incentive

Individually

managed

Individually

managed

Shared reward Individually

managed

Individually

managed

Contract Silos Silos One multi-party

contract

Multi-party

collaboration

contracts

Multi-party

collaboration

contracts

Applica-

bility

Not

productive

Not

productive

Not practical

currently, but ideal

in the long run

Practical Practical

Page 106: building information modeling–based process transformation to improve productivity in the

86

VDC is initiated by the general contractor who wants to detect problems virtually in

the design stage and hopes that during the construction stage there are fewer errors,

omissions, changes, and the like. Usually the owner frequently establish minimal

apparent risk and minimum first cost as crucial selection criteria for a new project

(Kunz and Fischer, 2012). Only the general contractor and key trade contractors

working side by side with the design consultants on the platform of BIM during the

design phase make the VDC approach more practical and affordable for building

projects.

In Singapore, DfMA is driven by the government as an enabler to on-site productivity

(BCA and SPH, 2015). This echoes sentiments in other countries, especially the UK

and Australia in which similar policies had been implemented (Blismas and

Wakefield, 2009). It will be better if the owner of a building project is enthusiastic on

this approach. Similar to the VDC process, the DfMA approach involves not only the

general contractor, but also the manufacturer in the design phase to develop the

design that maximizes OSM of those parts that can be prefabricated. It also leaves

conventional construction. Hence, the DfMA approach is also practical, especially

when the local government stresses on it.

Besides, Table 3.7 provides other differences between the traditional, current, and full

BIM-enabled delivery processes from the perspectives of risk management,

communication, design review and feedback, decision-making, dispute resolution,

change management, responsibility, and project team culture. Key points and related

statements are briefly described with support from previous studies.

Page 107: building information modeling–based process transformation to improve productivity in the

87

Table 3.7 Differences and supporting statements in literature between the traditional, current, and full BIM-enabled processes in Singapore

Project factor Traditional process Current process IPD VDC DfMA

Focus 2D based;

information and

knowledge

fragmentation

Mandatory to use

BIM before

construction starts

Built on collaboration, all key

stakeholders work together

till project closeout towards

common project goals

Using 3D/4D modeling of

BIM to manage

data/information and

integrate processes and

different disciplines in

design and construction

phases

Develop designs that

optimize OSM and

on-site installation

Risk Individually

managed,

transformed to the

greatest extent

possible (AIACC,

2006; AIA and

AIACC, 2007)

Individually

managed,

transformed to the

greatest extent

possible (AIACC,

2006; AIA and

AIACC, 2007)

Collectively managed,

appropriately shared

(AIACC, 2006; AIA and

AIACC, 2007)

Sharing risk reports that

includes description of risks,

assessed probability of

occurrence, affected parties

who can help fix or who

must respond if it becomes

real (Kunz and Fisher, 2012)

Reduced on-site risk;

better controlled in a

factory environment

(Blismas and

Wakefield, 2009)

Communicati

on/technology

Paper-based, 2D;

analog (AIACC,

2006; AIA and

AIACC, 2007)

Paper-based, 2D

drawings or

incomplete design

BIM models passed

to downstream

stakeholders

Digitally based, virtual;

3D/4D/5D/six-dimensional

(6D) BIM, shared BIM

models; concise, open, and

trusting (AIACC, 2006; AIA

and AIACC, 2007)

Virtual, 3D/4D/5D/6D BIM,

shared BIM models that fit

for the intended downstream

use (Kunz and Fisher, 2012;

Chua and Yeoh, 2015)

Digitally based,

augmented reality,

3D/4D/5D BIM,

shared BIM models

(McFarlane and

Stehle, 2014)

Design

review

/feedback

2D, slowly,

fragmented in

different phases and

disciplines; often

many changes and

RFIs in later phases

(AIA and AIACC,

2007)

Slowly, fragmented

in different phases

and disciplines, 2D

(AIA and AIACC,

2007); 3D only

among designers or

incomplete 3D

models from design

team to downstream

parties

Rapid feedback from

teammates, within a few

days; team members view

their interactions from a

“customer-supplier” point of

view (Fischer et al., 2014);

designers fully understand the

ramifications of their

decisions (AIA and AIACC,

2007)

Rapid feedback from

teammates, within a few

days; team members can

learn to view their

interactions from a

“customer-supplier” point of

view (Fischer et al., 2014);

design decisions

communicated to the field

(Fischer, 2008)

Rapid feedback from

other disciplines and

the manufacturer

(Gibb and Isack,

2003)

Decision-

making

Challenging to make

group decisions,

inadequate

Challenging to make

group decisions,

inadequate

All team members agree on

decision-making method

predetermined; all decisions

Collaboratively making

design decisions; working

together to reduce decision-

Designers, together

with the manufacturer

and site experts, make

Page 108: building information modeling–based process transformation to improve productivity in the

88

communication

between key

members (AIA and

AIACC, 2009)

communication

between key

members (AIA and

AIACC, 2007)

are measured against shared

goals about what’s best for

the project (AIA and AIACC,

2007)

making latency (Khanzode

et al., 2007)

decisions during the

design phase (Gibb

and Isack, 2003)

Dispute

resolution

Often claims,

thrusting the parties

into adversarial

positions; team is

crippled (AIA and

AIACC, 2007)

Often claims,

thrusting the parties

into adversarial

positions; team is

crippled (AIA and

AIACC, 2007)

Promptly resolved internally

without filing claims and

adopting adversarial positions

(AIA and AIACC, 2007)

– Agreed on the

tolerances and

standards of units by

mockups and

prototypes to avoid

disputes (Ross et al.,

2006)

Change

management

Managed and

updated in silos

when changes occur;

many change orders

and reworks after

construction starts

(AIACC, 2014)

Managed and

updated in silos

when changes occur;

many change orders

and reworks after

construction starts

(AIACC, 2014)

Avoiding changes by putting

much more efforts during

design; also involving owner

during design to avoid

owner’s changes in later

phases; limited RFIs

(AIACC, 2014)

Very few change orders

related to field conflicts due

to 4D visualization and

simulation (Khanzode et al.,

2007)

Avoiding changes by

fixing design together

with the general

contractor and

manufacturer and

using standard,

modular components

in design model

(Blismas and

Wakefield, 2009)

Responsibility Using guarantees,

penalties, and risk

transfers; excelling

in assessing liability

but doing very little

to avoid risks which

reinforces

individualistic

behavior (Fischer et

al., 2014)

Using guarantees,

penalties, and risk

transfers; excelling

in assessing liability

but doing very little

to avoid risks which

reinforces

individualistic

behavior (Fischer et

al., 2014)

Clearly defining

responsibilities in a no-blame

culture leading to

identification and resolution

of problems, not

determination of liability

(AIA and AIACC, 2009);

placing responsibility on the

most able person with

decisions being made on a

best-for-project basis

(AIACC, 2006; AIA and

AIACC, 2007)

– –

Page 109: building information modeling–based process transformation to improve productivity in the

89

Team culture Individualistic

behavior for own

interests, easily turn

into adversarial

relationships (AIA

and AIACC, 2007);

since agreements are

made between two

firms, rather than

amongst the entire

team, they reinforce

individualism rather

than project

optimization

(Fischer et al., 2014)

Individualistic

behavior for own

interests, easily turn

into adversarial

relationships (AIA

and AIACC, 2007);

since agreements are

made between two

firms, rather than

amongst the entire

team, they reinforce

individualism rather

than project

optimization (Fischer

et al., 2014)

Trust and respect; open

sharing and transparent;

rewarding best-for- project

behavior (AIA and AIACC,

2007, 2009; AIACC, 2007);

working in a “Big Room”

(Fischer et al., 2014)

Open sharing; the general

contractor, key trade

contractors, and engineers

work side by side with the

architect in a “Big Room” to

model the project and

coordinate their designs

(Khanzode et al., 2007);

clustering, to identify

optimal organizational

configurations to implement

“Big Room” design

strategies (Chua and Yeoh,

2015)

Open sharing; the

general contractor,

manufacturer, and

engineers work side

by side with the

architect to develop

optimal designs that

suit for OSM and on-

site erecting (Ross et

al., 2006; Blismas and

Wakefield, 2009)

Page 110: building information modeling–based process transformation to improve productivity in the

90

3.5.2 Relationships between full BIM-enabled processes

According to AIA and AIACC (2007, 2009), IPD is built on collaboration which

requires all the key stakeholders of a building project to be involved early and work

together before the construction phase. Without trust-based collaboration, IPD will

falter and participants will remain in the adverse and antagonistic relationships that

plague the construction industry today. IPD promises better outcomes, but outcomes

will not change unless people responsible for delivering those outcomes change. The

advent of IPD is influencing hiring practices toward people with collaboration skills,

rather than people capable of BIM. So it may not necessarily involve BIM, but the

use of BIM is strongly recommended as BIM facilitates collaboration (AIACC, 2007;

Autodesk, 2008; AIACC, 2014; Fischer et al., 2014).

As mentioned in Section 3.4.2, VDC tries to integrate various processes and multiple

disciplines involved in a project. The construction industry is shifting into the

integration stage and finally the automation stage. Both of them are based on data

sharing between the design and construction phases. Therefore, it stresses on

integration of processes. It is notable that even the terms “integration” and

“collaboration” are interchangeable, they focus on different contents. The former is

on data and process, and the latter on project participants.

Essentially, DfMA tries to move site-based activities into a controlled factory

environment. It requires very well-developed designs that encourage the efficient off-

site prefabrication of modular and portable elements for easy transportation and rapid

on-site assembly. So, the essence here is designs because it is very expensive for any

design changes once the manufacture process commences. Meanwhile, advanced

techniques are required to develop such designs.

Page 111: building information modeling–based process transformation to improve productivity in the

91

The above analysis reveals the distinctive differences between the proposed IPD,

VDC, and DfMA approaches, with the use of BIM or the concept of IDD being the

key similarity of the approaches (see Figure 3.9). Enabled by BIM, IDD is a new

concept that was proposed by the Singapore government. This concept aims to

integrate various processes and stakeholders along the construction value chain

through advanced information and communications technology (ICT) and smart

technologies (BCA, 2017a). The early involvement of major stakeholders also serves

as an important similarity. In addition, all these approaches can be applied subject to

external environment, such as the local policies and constriction market situation.

People

Process Technology

Collaboration

IPD

Design

DfMA

Integration

VDCBIM (IDD)

Figure 3.9 Distinctive differences and similarities of IPD, VDC, and DfMA

On the other hand, provided that BIM technology is used in the project, VDC and

DfMA could be seen as subsets of IPD (see Figure 3.10). Table 3.6 indicates that

what VDC and DfMA stress on a project is also included in the IPD approach once

BIM is fully used. The is consistent with the finding of Porwal and Hewage (2013)

that IPD has materialized as a project delivery method that could most effectively and

fully facilitate BIM implementation in the construction industry.

IPD

VDC DfMA

Figure 3.10 Relationships between IPD, VDC, and DfMA when using BIM

Page 112: building information modeling–based process transformation to improve productivity in the

92

Fischer et al. (2014) proposed a framework of using IPD (see Figure 3.11). It is best

understood by working backwards, from the product (integrated building systems)

which integrated project teams have agreed to deliver, to integrated information.

Sharing information is a lynchpin of the IPD team. Information must remain

consistent across all disciplines, and everyone must have access to all latest

information, at any time. BIM allows the team to explore many design options, and to

discuss how different designs will add value (or not) and how they will affect

performance targets. As mentioned in Section 3.4.2, visualization and simulation are

the engine of VDC, and serve as tools in this framework to connect integrated

information. Hence, it can be concluded that VDC is a subset of IPD if BIM is fully

used in the IPD process. Meanwhile, BIM can also help establish an appropriate off-

site fabrication strategy, and understand the operability and sustainability of an

intentional design. With BIM fully used in the whole process, off-site fabrication and

on-site installation are encouraged. Autodesk (2008) examined how BIM is central to

process changes that IPD would bring. Fabrication from BIM models is suggested in

the IPD approach to integrate the design and construction phases, resulting in

elimination of shop drawings, better tolerance and lead time, and faster field

assembly. Thus, DfMA is also a subset of IPD given that BIM is fully implemented.

High performance

building

Integrated building systems

Integrated processes

Integrated organization

Integrated information

(BIM+)

Collaboration, co-location

Visualization, simulation

Productionmanagement

Measurable value

Figure 3.11 How integrated information supports the creation of a high-performance

building (Fischer et al., 2014)

Therefore, IPD is too ideal to be implemented currently and may not necessarily use

BIM, while both VDC and DfMA are practical in the short term (see Table 3.6). VDC

and DfMA are somewhat similar and overlap to some extent (see Figure 3.10). Hence,

Page 113: building information modeling–based process transformation to improve productivity in the

93

VDC, DfMA, or a hybrid of them can be a good solution in the short term and IPD

should be explored and gradually applied in the future in the Singapore construction

industry. Nevertheless, although BIM may not necessarily be incorporated in the IPD

process, it is recommended by researchers (AIACC, 2007; Autodesk, 2008; Succar,

2009; El Asmar et al., 2013; AIACC, 2014; Fischer et al., 2014). The IPD approach

has many benefits that VDC and DfMA do not provide, such as financial incentives

being shared with downstream contractors and risks being managed by the most able

parties. It is the downstream contractors that finally complete and monitor on-site

activities to build a facility. Hence, this study will investigate process transformation

strategies to the VDC, DfMA, and IPD processes.

3.6 Summary

This chapter reviewed the literature on five project delivery processes, namely the

traditional project delivery process, current process, and three full BIM-enabled

processes. The latter consists of IPD, VDC, and DfMA, which are either commonly

recognized in driving process improvement and increasingly used in the global

construction industry, or greatly encouraged and supported by the Singapore

government. All of them were adapted for use in the local construction industry. Key

activities, especially those related to BIM, in each project phase of these delivery

methods were identified. By comparing the traditional and current processes with the

full BIM-enabled processes, it is concluded that much should be done to shift the

local construction industry to be more collaborative and integrated with the use of

BIM. Moreover, the relationships between the IPD, VDC, and DfMA approaches

were explored. VDC, DfMA, or a hybrid of them was recommended to be

implemented in the short term, while the IPD approach should be explored and

gradually applied in the long term in the Singapore construction industry. Even

though recently the CITM has been released by the local government, it will take

Page 114: building information modeling–based process transformation to improve productivity in the

94

years before the local industry widely adopts the DfMA approach or BIM at large in

practice. Thus, it is believed that this study was still novel and practically significant.

Page 115: building information modeling–based process transformation to improve productivity in the

95

Chapter 4: Review of NVA Activities and Proposal of a BIMIR

Evaluation Model

4.1 Introduction

The majority of building project teams in the Singapore construction industry need to

operate in an environment that promotes the widespread use of BIM. It is therefore

necessary to understand to what extent the project teams are capable and ready to

implement BIM in their building projects. This chapter first provides a review on the

NVA activities in the project lifecycle by comparing the key activities between the

current delivery process and the full BIM-enabled delivery processes which were

discussed in Chapter three. Subsequently, the chapter reviews the resulting wastes of

the NVA activities, and the causes to these NVA activities in terms of the roles of the

major stakeholders. Finally, to evaluate the BIMIR status in building projects, a

model is developed based on the NVA activities, using the FSE approach.

4.2 NVA Activities and Their Causes and Resulting Wastes

4.2.1 Identifying NVA activities

The BIM uses currently adopted in the Singapore construction industry were partial.

Without knowing the downstream BIM uses in a building project, the design team

may not be able to identify the reusable project information and important

information exchanges (Anumba et al., 2010). Compared with the IPD, VDC, and

DfMA processes, this partial BIM adoption created major NVA practices in the

current project delivery process, which would result in various wastes and consume

time (Nikakhtar et al., 2015) and manpower, leading to productivity loss. These NVA

practices were depicted by project phasing and major stakeholders (see Table 4.1), and

could be translated into a total of 44 common NVA activities. The detailed descriptions

Page 116: building information modeling–based process transformation to improve productivity in the

96

Table 4.1 Major NVA practices characterized by project stakeholders and project phasing in the current project delivery in Singapore

Phases Conceptualization Schematic

design

Design

development

Construction

documentation

Agency

permit/

Bidding/

preconstruction

Construction

(including

manufacture)

Handover/

Closeout/Operations

and maintenance

Agency

(AG)

Lack of

involvement

(AIACC, 2014)

Lack of

involvement

(AIACC,

2014)

Lack of

involvement

(AIACC, 2014)

– – – –

Owner

(OW)

Inadequate

project objectives

(Arain, 2005)

Resistance to use

BIM in the whole

project (Gibb and

Isack, 2003)

No reward/risk

sharing

arrangements are

set in beginning

(AIACC, 2014)

Lack of

involvement

(Arain, 2005)

Not joint

controlled by

OW, AR,

EGs, GC, and

all key TCs

(AIACC,

2014)

Lack of

involvement

(Arain, 2005)

Insufficient

design review

and feedback

Not engaged

GC, TCs, MF,

and FM early

(Ross et al.,

2006; AIA and

AIACC, 2007;

Kunz and

Fischer, 2012;

AIACC, 2014)

Changes from

owner

Insufficient LOD of

2D as-built

drawings

Not as-built BIM

model

No reward sharing

arrangements

between all key

participants

(AIACC, 2014)

Architect

(AR)

Unclear design

intent

Not working

side by side

with EGs and

contractors

(Gao and

Fischer, 2006)

Not sharing

BIM model

with EGs

Not applying

Not working side

by side with EGs

(Gao and Fischer,

2006)

Not sharing

complete BIM

model with EGs

(Gao and Fischer,

2006)

Not sharing

Not

coordinated

design model

(AIACC,

2014)

Insufficient

communication

with EGs

Only passing

2D drawings or

incomplete 3D

BIM model to

GC, TCs, and

MF

Design changes

Long RFIs

response time as

design model

cannot directly

guide site work

Not updated design

BIM model

Page 117: building information modeling–based process transformation to improve productivity in the

97

for planning

approval

(BCA, 2013b)

complete BIM

model early

Engineers

(EG)

Lack of

involvement

Lack of

involvement

early in this

phase to

contribute in

architectural

modeling

(feedbacks)

(Gao and

Fischer, 2006)

Not applying

for planning

approvals

(BCA, 2013b)

Coordination of

building systems

deferred until the

construction phase

because TC input

is not available

until then (AIACC,

2014)

Not

coordinated

design model

(AIACC,

2014)

Insufficient

communication

with other

designers

Only passing

2D drawings or

incomplete 3D

BIM models to

GC, TCs, and

MF

Design changes

Long RFIs

response time

Not updated design

BIM models

General

contractor

(GC)

Lack of

involvement (not

appointed)

Lack of

involvement

(not

appointed)

Lack of

involvement to

contribute

construction

knowledge (AIA

and AIACC, 2007;

AIACC, 2014)

Construction

model not

developed due to

unwillingness of

the design team to

share BIM models

(Gao and Fischer,

2006)

Information

such as BOM,

assembly,

layout, detailed

schedule, test

and

commissioning

procedures not

documented

after the design

phase (AIACC,

2014)

Long-lead

items are not

identified and

defined during

Re-building

BIM model

due to

unavailable or

insufficient

documents (2D

drawings or

incomplete 3D

BIM models)

(Eastman et al.,

2011)

Extending 2D

drawings

(without BIM)

from designers

to guide

Too much

RFIs/OW

changes/design

changes/paperwork

(AIA and AIACC,

2007; Eastman et

al., 2011)

Insufficient

communication

with OW, AR,

EGs, and

subcontractors

(including TCs and

MF)

Low OSM rate

Much more disputes

with owner and

designers

Insufficient LOD of

2D as-built

drawings

Not as-built BIM

model with review

by AR

Page 118: building information modeling–based process transformation to improve productivity in the

98

design so that

their

procurement is

not begun as

early as

possible

(AIACC,

2014)

construction

Not BIM-

based

construction

schedule

planning

(BCA and SPH,

2015)

Congested and

many interfaces on

site (Blismas and

Wakefield, 2009

Differences

between actual and

planned site

conditions without

3D visualization

(Kim and Fischer,

2013)

Key trade

contractor

(TC, such as

structural

and MEP

contractors)

Lack of

involvement (not

appointed)

Lack of

involvement

Lack of

involvement to

contribute

site/constructability

knowledge

Shop drawings

cannot be

merged into

this phase

(AIACC,

2014)

– Incomplete 2D

shop drawings or

BIM models

Too much

RFIs/OW

changes/design

changes

Manufacturer

/Supplier

(MS)

Lack of

involvement (not

appointed)

Lack of

involvement

Lack of

involvement to

contribute

knowledge of

material selection,

transportation, site

erection, and so on

(Gibb and Isack,

2003)

Shop drawings

cannot be

merged into

this phase

(AIACC,

2014)

Prefabrication

of some

systems cannot

commence

because the

– Incomplete 2D

shop drawings or

BIM models

Too much

RFIs/OW

changes/design

changes

Low OSM rate

(BCA and SPH,

2015)

Page 119: building information modeling–based process transformation to improve productivity in the

99

design is not

fixed (AIACC,

2014)

Superstructure and

fitting out cannot

take place in the

factory totally

before or while the

ground works and

substructure are

being done on-site

(Ross et al., 2006)

Facility

manager

(FM)

Lack of

involvement (not

appointed)

Lack of

involvement

Lack of

involvement to

contribute

knowledge of

operations and

maintenance (Kunz

and Fischer, 2012)

– – – Insufficient design

and construction

information for

operations and

maintenance

Page 120: building information modeling–based process transformation to improve productivity in the

100

of these NVA activities were presented in Section 7.2.2. It should be noted that in this

study, “architect” represents architectural consultancy firms and “engineers”

represent consultancy firms in respective disciplines to reflect the Singapore context.

4.2.2 Resulting wastes

Previous studies reported that NVA work held a considerable portion in most

construction processes (Agbulos and AbouRizk, 2003; Dunlop and Smith, 2004;

Farrar et al., 2004; Al-Sudairi, 2007; Nikakhtar et al., 2015). This work even

exceeded 50% of the total work in some cases (Al-Sudairi, 2007). To quantify the

effect of the NVA activities in the current process on productivity, a total of 13 kinds

of potential resulting wastes that would be more impactful have been identified from

the literature review (see Table 4.2). The identification and reduction of these wastes

would result in potential time savings, leading to enhanced productivity performance.

Table 4.2 Potential wastes affecting productivity more seriously

Code Wastes References

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

W01 Defects x x x x x x x x x

W02 RFIs x x x x x

W03 Reworks/abortive works x x x x x x x

W04 Waiting/idle time x x x x x x x x x

W05 Change orders x x x

W06 Activity delays x x x x x

W07 Overproduction/reproduction x x x x x x x x x x x

W08 Transporting/handling

materials

x x x x x x x x

W09 Unnecessary inventory x x x x x x x x

W10 Excess processing beyond

standard

x x x x x

W11 Unnecessary movement of

people and equipment

x x x x x x

W12 Design deficiencies (errors,

omissions, additions)

x x x x

W13 Safety issues (injuries) x x x x x

Note: (1) Abdel-Razek et al. (2007); (2) Alarcon (1997); (3) Alwi et al. (2002); (4)

Arayici et al. (2011); (5) Chua and Yeoh (2015); (6) Eastman et al. (2011); (7)

Ekanayake and Ofori (2004); (8) Fan et al. (2014); (9) Formoso et al. (1999); (10)

Forsberg and Saukkoriipi (2007); (11) Lee et al. (1999); (12) Nikakhtar et al. (2015);

(13) Ohno (1988); (14) Senaratne and Wijesiri (2008); (15) Teo et al. (2014); (16)

Page 121: building information modeling–based process transformation to improve productivity in the

101

Wong et al. (2014); (17) Wu and Low (2011); (18) Wu and Low (2012). x indicates

the inclusion of the specific waste in the reference.

The wastes were analyzed in the construction industry. Among these potential wastes,

defects, waiting/idle time, overproduction, transporting materials, unnecessary

inventory, excess processing beyond standard, and unnecessary movement of people

and equipment are seven major wastes that stem from the Toyota production system,

while the remainder is raised by previous construction management studies. It should

be noted that some similar wastes have been combined, such as waiting time and idle

time, whereas some are overlapping with each other to some extent but may be used

in different situations, such as waiting time and activity delays, defects and reworks,

and overproduction and necessary inventory. Specifically, in the building project

context, the wastes can be interpreted as follows:

W01: Defects. Every defective part requiring repairs would add extra cost of time,

manpower, materials, and facilities. Paperwork would also be created.

W02: RFIs. RFIs usually result from incomplete design information and design

inefficiencies, and require extra communication for clarification between

individuals or parties, especially between the contractors and the specific

designers during construction.

W03: Reworks/abortive works. Abortive works due to poor quality require field staff

to demolish and build again. Redesigns may be needed if such works are

completed using wrong construction methods.

W04: Waiting time/idle time. Waiting or idle time is produced when two

interdependent work processes are not completely aligned, due to such reasons

as breakdowns, changeovers, poor site layout, and waiting for materials or the

owner’s or the designers’ approvals.

W05: Change orders, which are often driven by the designers and the owner. Such

orders would create field conflicts, re-designs, wasted products and work

processes, and reworks. With BIM implementation, change orders can be

Page 122: building information modeling–based process transformation to improve productivity in the

102

drastically reduced because the owner’s intent would be better represented in

3D models (Fan et al., 2014; Fischer et al., 2014).

W06: Activity delays. Any violation to schedule compliance would cause wasted

time and efforts on site. This waste could happen when the work processes are

not well defined and completely synchronized, and can be reduced by quicker

project layout and detailed scheduling capability of BIM functions (Gao and

Fischer, 2006; Fan et al., 2014).

W07: Overproduction/reproduction, which describes producing more items than

required or producing earlier, due to reasons such as uncertain design

information. This is a detrimental waste because it causes other wastes such as a

high level of inventory.

W08: Transporting/handling materials. This waste describes the movement of

materials from one location to another, which is not directly related to a value

adding work process in the construction stage (Nikakhtar et al., 2015). Reasons

such as poor design and poor site layout would cause such a waste.

W09: Unnecessary inventory. This waste occurs when there is excess supply of raw

material, work in progress or finished goods, which requires extra labor and

equipment to handle during construction (Nikakhtar et al., 2015).

W10: Excess processing beyond standard, which occurs when performing unneeded

work processes. An engineer, for example, is wasting time and efforts if

trimming 1 mm of flash from a class C area of a window when 6 mm of flash is

acceptable. This often occurs due to poor design, unclear specifications, re-

entering data and duplicated data, lack of standards, poor communication,

unnecessary documentation, and so on.

W11: Unnecessary movement of people and equipment. This waste is characterized

by those movements of man or machine which are not as easy to achieve as

possible. Examples are unneeded travel between work stations, and excessive

machine movements from start point to work start point, which may be due to

Page 123: building information modeling–based process transformation to improve productivity in the

103

poorly-designed layout. A good solution is to simulate the work processes

before actual construction in the virtual environment.

W12: Design deficiencies (errors, omissions, additions). Uncertainty or

incompleteness of design information in the design stage would seriously affect

productivity performance as it will inevitably cause many field problems in the

later stages.

W13: Safety issues (injuries). It is impossible in the building project to significantly

enhance productivity without considering safety issues. Dealing with any

injuries and accidents consume extra time and manpower.

Because of reduced wastes, time and manpower can be saved, leading to schedule

compliance and enhanced productivity. For example, Chelson (2010) explained the

relationships between RFIs, reworks, idle time, activity delays, change orders, and

affected productivity and cost in an inefficient project (see Figure 4.1 and Figure 4.2).

Due to poorly coordinated and unclear building plans being used on site in the current

practices, tremendous RFIs are raised from the contractors. Such RFIs mean

increased field conflicts which cause workers’ idle time waiting for the consultants’

responses and potential reworks where necessary, resulting in decreased productivity.

§ Poorly coordinated and unclear plans § Constructability

problems§ Construction delays

§ Contractor productivity rates decrease

§ Cost of construction increases

Number of RFIs increases

Rework increases

Change orders increase

Figure 4.1 Productivity and cost affected by RFI, rework, idle time, activity delay,

and change order (Chelson, 2010)

Page 124: building information modeling–based process transformation to improve productivity in the

104

Plans coordination with BIM – number of RFIs decreases

Fewer field conflicts/confusion - reworks and idle time decreases, prefabrication increases

Contractor productivity rates increase - reduced owner-enbaled change orders, increased profits

RFI

Rework

Figure 4.2 How BIM coordination enhances productivity and cost performance by

reducing major wastes (Chelson, 2010)

However, with full BIM use, all building systems can be fully defined, engineered,

and coordinated so that these RFIs would occur earlier and informally during the

design stage. The requests for clarification are issued before field personnel are

situated in the field attempting to install work according to an imperfect plan. Thus,

the number of RFIs is greatly reduced. This means fewer conflicts and confusion can

be found during construction, further decreasing reworks and idle time. As a result,

productivity performance will be increased and fewer change orders are needed (see

Figure 4.2). Both the owner and the contractors benefit from this process. The

contractors keep profits they realized by their BIM implementation activities. If the

owner was the sponsor of BIM, then they can obtain productivity savings as well.

4.2.3 Causes of NVA activities

An effective analysis of the NVA activities produced in the current project delivery in

Singapore requires a comprehensive understanding of their root causes, including but

not limited to: (1) the design team is not required by the owner and is unwilling to

share its models with the contractors; (2) the contractors have not recognized the

potential value of BIM, or worry about high learning curve of BIM; and (3) the

fragmentation between the design phase and the construction phase. The contractors

Page 125: building information modeling–based process transformation to improve productivity in the

105

are not engaged upfront to input their construction knowledge. In this study, the

causes were observed and categorized according to the roles of the major

stakeholders in a building project.

1. Agency (where “AG” represents “agency”):

AG01: Currently focusing on the design stage to move from 2D drafting practices to

3D working environment by developing a set of BIM submission templates

and guidelines to help professionals understand the new process of regulatory

submissions using BIM (Zahrizan et al., 2013);

AG02: Mandating the use of BIM (such as BIM submissions) in no way guarantees

that the primary principles of collaboration, and best-for-project thinking will

be followed (AIACC, 2014); and

AG03: Unclear legislation and qualifications for precasters (versus concreter) and

inadequate codes for OSM varieties, for example, to address tilt-up rather than

other precast products (Blismas and Wakefield, 2009).

2. Owner (where “OW” represents “owner”):

OW01: Owner inertia against the use of BIM or off-site prefabrication due to limited

knowledge and inexperience (Gibb and Isack, 2003; Blismas and Wakefield,

2009);

OW02: The owner frequently establishes minimal apparent risk and minimum first

cost as crucial selection criteria for new projects (Kunz and Fischer, 2012);

OW03: The owner’s financial problems (Arain, 2005);

OW04: Unaware of the benefits of BIM and building lifecycle management (BLM).

As indicated in a BIM survey, many owners are still unaware of BIM or BLM

and thus need for professional guidelines on leveraging BIM (Khosrowshahi

and Arayici, 2012);

Page 126: building information modeling–based process transformation to improve productivity in the

106

OW05: Traditional contracts often tend to create incentives for individual firms to

protect their own interests at the expense of the project, rather than embrace

best-for-project thinking (AIA and AIACC, 2009);

OW06: The owner awards architectural and engineering contracts solely based on

qualification to provide the design services before the construction phase. The

lowest cost contractors then build such a project (Azhar et al., 2014);

OW07: Goals set between the owner and architect are vague and poorly defined, and

rarely passed on to people working in later stages of the project (Fischer et al.,

2014);

OW08: Using mechanisms such as guarantees, penalties, and risk transfers does not

address the fundamental causes of poor performance, and leads to focusing on

assessing liability but doing very little to avoid the risks (Fischer et al., 2014);

OW09: Perceiving design fees for OSM as more expensive than traditional process,

even though they are potentially lower by using standard products (Blismas

and Wakefield, 2009); and

OW10: The owner’s desire for particular structures or traditional finishes may inhibit

OSM and limit design options (Blismas and Wakefield, 2009).

3. Architect (where “AR” represents “architect”):

AR01: The final set of drawings and specifications must contain sufficient details to

facilitate construction bids. Because of potential liability, the architect may

choose to include fewer details in the drawings or insert language indicating

that the drawings cannot be relied on for dimensional accuracy. These

practices often lead to misinterpretation and disputes with contractors, as

errors and omissions are detected and responsibility and extra costs reallocated

(Arain, 2005; Eastman et al., 2011);

AR02: Its design model shows intent but does not show exact dimensions of every

component, while construction models/drawings show more at a higher LOD

Page 127: building information modeling–based process transformation to improve productivity in the

107

and precision because the constructors have to build from them (AIACC,

2014);

AR03: Not required by contract to share design models with the contractors (Kiani et

al., 2015);

AR04: Its design model or drawings fit for mandatory BIM submissions, but not fit

for intended downstream use because of insufficient LOD and precision for

every component (Chua and Yeoh, 2015);

AR05: Does not understand field operations enough and lacks construction input in

design (Chelson, 2010);

AR06: Lack of skilled BIM experts in the local market to engage (Kiani et al., 2015);

AR07: Project design decisions are at the sole discretion of the designers, without

complete knowledge of the impact on construction (AIACC, 2014);

AR08: Does not model everything the contractors need for QTOs. For example,

architectural modeling usually does not differentiate between the walls that

stop at the ceiling and those that extend to the structural floor above (AIACC,

2014);

AR09: Spending much time and effort locating, recreating, or transferring fragmented

information when working on a fragmented team (Fischer et al., 2014);

AR10: Unless asked and encouraged, the architect will not even consider the lifecycle

value of or incremental changes to the project (Kunz and Fischer, 2012); and

AR11: Limited expertise of OSM and its processes in the marketplace, especially for

SMEs, with design philosophy based on traditional methods that are unsuited

to OSM (Blismas and Wakefield, 2009).

4. Engineers (where “EG” represents “engineers”):

EG01: Their design models show intent but do not show exact dimensions of every

component, while construction models/drawings show more at a higher LOD

Page 128: building information modeling–based process transformation to improve productivity in the

108

and precision because the constructors have to build from them (AIACC,

2014);

EG02: Not required by contract to share design models with the contractors (Kiani et

al., 2015);

EG03: Their design models or drawings fit for mandatory BIM submission, but not fit

for intended downstream use because of insufficient LOD and precision for

every component (Chua and Yeoh, 2015);

EG04: Do not understand field operations enough and lack construction input in the

design (Chelson, 2010);

EG05: Lack of skilled BIM experts in the local market to engage (Kiani et al., 2015);

EG06: Project design decisions are at the sole discretion of the designers, without

complete knowledge of the impact on construction (AIACC, 2014);

EG07: Spending much time and effort locating, recreating, or transferring fragmented

information when working on a fragmented team (Fischer et al., 2014);

EG08: Unless asked and encouraged, engineers will not even consider the lifecycle

value of or incremental changes to the project (Kunz and Fischer, 2012);

EG09: Limited expertise of OSM and its processes in the marketplace, especially for

SMEs, with design philosophy based on traditional methods that are unsuited

to OSM (Blismas and Wakefield, 2009); and

EG10: Downstream designers have to make extra efforts to reconfigure or reformat

the data that are viewed differently by upstream designers (Gao and Fischer,

2006; Eastman et al., 2011).

5. General contractor (where “GC” represents “general contractor”):

GC01: Not required by the owner and agencies to adopt BIM (Kiani et al., 2015);

GC02: Lack of skilled BIM experts to engage to help construction/site manager and

unable to see how BIM benefits them (Fox and Hietanen, 2007; Chelson, 2010;

Zahrizan et al., 2013; Kiani et al., 2015);

Page 129: building information modeling–based process transformation to improve productivity in the

109

GC03: Only 2D drawings or incomplete 3D models (such as insufficient LOD) are

shared from the design team (Chua and Yeoh, 2015);

GC04: Costly training and high learning curve (initial productivity loss) for the

general contractor to use BIM (Eastman et al., 2011);

GC05: Many firms are reluctant and inexperienced to use BIM, and still seem to be

happy to continue using the traditional CAD practices (Khosrowshahi and

Arayici, 2012);

GC06: Most construction players have little knowledge of BIM and do not know how,

when, and what to start to use it (Zahrizan et al., 2013);

GC07: Lack of national BIM standards and guidelines for the general contractor

(Zahrizan et al., 2013);

GC08: Doubt about the effectiveness of BIM because limited data have proven the

effectiveness (Zahrizan et al., 2013);

GC09: Afraid of the unknown and resistant to change from comfortable daily routine

to the new work process (Zahrizan et al., 2013);

GC10: Lack of legal support from local authorities such as software price subsidies

(Kiani et al., 2015);

GC11: Lack of tangible benefits of BIM and limited evidence to warrant its use

(Khosrowshahi and Arayici, 2012; Zahrizan et al., 2013; Kiani et al., 2015);

GC12: Not thinking of changing conventional working methods and no demand for

BIM uses (Khosrowshahi and Arayici, 2012; Kiani et al., 2015);

GC13: Having to make extra efforts to reconfigure or reformat the data that are

viewed differently by upstream designers (Gao and Fischer, 2006; Eastman et

al., 2011);

GC14: Reluctance to adopt OSM (Blismas and Wakefield, 2009); and

GC15: Limited expertise of OSM and its processes in the marketplace, especially for

SMEs, with design philosophy based on traditional methods that are unsuited

to OSM (Blismas and Wakefield, 2009).

Page 130: building information modeling–based process transformation to improve productivity in the

110

6. Trade contractors (where “TC” represents “trade contractor”, such as structural

and MEP contractors):

TC01: Not required by the owner or general contractor or agencies to adopt BIM

(Kiani et al., 2015);

TC02: Lack of skilled BIM experts to engage to help site staff and unable to see how

BIM benefits them (Fox and Hietanen, 2007; Chelson, 2010; Zahrizan et al.,

2013; Kiani et al., 2015);

TC03: Only 2D drawings or incomplete 3D models (such as insufficient LOD) are

shared from the designers or general contractor (Chua and Yeoh, 2015);

TC04: Costly training and high learning curve (initial productivity loss) for trade

contractors to use BIM (Eastman et al., 2011);

TC05: Many firms are reluctant and inexperienced to use BIM, and still seem to be

happy to continue using the traditional CAD practices (Khosrowshahi and

Arayici, 2012);

TC06: Most construction players have little knowledge of BIM and do not know how,

when, and what to start to use it (Zahrizan et al., 2013);

TC07: Lack of national BIM standards and guidelines for the trade contractors

(Zahrizan et al., 2013);

TC08: Doubt about the effectiveness of BIM because limited data have proven the

effectiveness (Zahrizan et al., 2013);

TC09: Afraid of the unknown and resistant to change from comfortable daily routine

to the new work process (Zahrizan et al., 2013);

TC10: Lack of legal support from local authorities such as software price subsidies

(Kiani et al., 2015);

TC11: Lack of tangible benefits of BIM and limited evidence to warrant its use

(Khosrowshahi and Arayici, 2012; Zahrizan et al., 2013; Kiani et al., 2015);

TC12: Not thinking of changing conventional working methods and no demand for

BIM uses (Khosrowshahi and Arayici, 2012; Kiani et al., 2015);

Page 131: building information modeling–based process transformation to improve productivity in the

111

TC13: Downstream contractors have to make extra efforts to reconfigure or reformat

data that are viewed differently by upstream stakeholders (Gao and Fischer,

2006; Eastman et al., 2011); and

TC14: Limited expertise of OSM and its processes in the marketplace, especially for

SMEs, with design philosophy based on traditional methods that are unsuited

to OSM (Blismas and Wakefield, 2009).

7. Manufacturer/Supplier (where “MS” represents “manufacturer/supplier”):

MS01: The design must be fixed early and fit for off-site prefabrication and on-site

assembly, and does not permit any changes as these are expensive once

fabrication has commenced (Gibb and Isack, 2003; Blismas and Wakefield,

2009; Selvaraj et al., 2009);

MS02: Not required by the owner or general contractor or agencies to adopt BIM in

manufacture (Kiani et al., 2015);

MS03: Lack of skilled BIM experts to engage and unable to see how BIM benefits

the manufacturer/supplier (Fox and Hietanen, 2007; Chelson, 2010; Zahrizan

et al., 2013; Kiani et al., 2015);

MS04: Only 2D drawings or incomplete 3D models (such as insufficient LOD) are

shared from the designers or general contractor (Chua and Yeoh, 2015);

MS05: Costly training and high learning curve (initial productivity loss) for the

manufacturer/supplier to use BIM (Eastman et al., 2011);

MS06: Many firms are reluctant and inexperienced to use BIM, and still seem to be

happy to continue using the traditional CAD practices (Khosrowshahi and

Arayici, 2012); and

MS07: Market protection from traditional suppliers/manufacturers to use BIM and

OSM (Blismas and Wakefield, 2009).

8. Facility manager (where “FM” represents “facility manager”):

Page 132: building information modeling–based process transformation to improve productivity in the

112

FM01: Not required by the owner and/or subsequently not involved in the design

phase (AIA and AIACC, 2007; Kunz and Fischer, 2012).

In summary, the identified NVA activities are mostly caused by these reasons which

were translated into a total of 53 causes in six roles (government agency, owner,

architect/engineers, contractor, manufacturer/supplier, and facility manager). The

detailed descriptions of these causes were presented in Section 7.2.5.

4.3 BIMIR

To successfully implement a new technology or technological process (such as BIM),

many factors should be taken into consideration, such as personal attitudes,

relationships between project participants, specific project characteristics, legal

issues, and individuals’ resistance to change (O’Brien, 2000; Nitithamyong and

Skibniewski, 2003). The attitudes toward the new technology or technological

processes are affected by potential financial loss in the first projects and the

perception of peers’ attitudes. A survey in Taiwan indicated that about 93% of the

local architectural firms would be psychologically ready to implement BIM to

maintain competitiveness in the local industry if their competitors had already done

so (Juan et al., 2017). Thus, at the project level, the primary participants may not

participate equally even though the resources are in place.

Without a clear knowledge of benchmark, metrics, and guidance, project teams might

hesitate and the adoption rate of BIM implementation was not high. The firms usually

learned from successful BIM implementation cases. During the last decade, the firms

that planned to use BIM had to overcome technical and organizational difficulties and

did not clearly know where they were moving (Won et al., 2013). Lee (2007a)

Page 133: building information modeling–based process transformation to improve productivity in the

113

proposed that BIM implementation of a building project could be classified into four

phases according to the level of organization involved:

(1) First phase: personal adoption

In this phase, there is only one BIM modeler who produces and maintains a BIM

model. Others may use the data produced from this model, but no collaboration

between the modeler and the users is involved. For example, a single architect

develops a design model and produces drawings purely from the model without

any data exchange with others. Another example is that a subcontracted BIM

modeler creates a BIM model that is not or cannot be actively used in the project,

and the model is only produced for presentation purposes or meeting the client’s

request.

(2) Second phase: adoption within a team of a party

A team of several people in a primary project participant may work

collaboratively using interoperable BIM software applications. For instance, in an

architectural consultancy firm, an architectural model is created and used only by

the architectural staff of this party.

(3) Third phase: adoption across different types of teams within a party

Several teams with different roles and responsibilities in a primary project

participant collaborate to complete their own scopes of work. For example, a BIM

model developed by one team is shared with estimators or schedulers within this

party to do planning.

(4) Fourth phase: adoption across parties

The major difference between this phase and the third phase is that this phase

involves much more complex coordination and collaboration issues across

different parties with different BIM capabilities and interoperability issues

between different BIM tools. In this phase, for example, BIM implementation

activities require BIM detailers from different teams or parties to openly share

their models, such as for consolidation and clash detection.

Page 134: building information modeling–based process transformation to improve productivity in the

114

The level of BIM implementation varies by company. While early and aggressive

BIM implementers may have reached the fourth phase, other firms were still

struggling in the first phase. The lessons and experience revealed that fundamental

innovations and changes are expected both within individual parties and cross-

organization environments to drive widespread BIM implementation towards the

fourth phase and beyond.

In addition, Succar (2009) and Khosrowshahi and Arayici (2012) identified BIM

maturity and subdivided it into Pre-BIM status and three BIM maturity stages, which

could be depicted in Figure 4.3. Specifically, the Pre-BIM status described the

traditional project delivery using the traditional 2D CAD approach in the design,

detailing, and documentation. Besides, the BIM Stage One was characterized by

single-discipline models which did not have any modifiable parametric attributes.

Also, significant model-based data interchanges between different disciplines were

not involved, and the deliverables generated from the models were mostly CAD-like

documents. Moreover, compared with the stages mentioned above, the BIM Stage

Two involved necessary contractual amendments because of the need of sharing

models between disciplines. Such collaboration may occur within one project phase

or between two phases to encourage fast-tracking. Furthermore, the BIM Stage Three

created, shared, and maintained semantically-rich models across project phases

through model servers and common databases, which would enable virtual complex

analyses at an early stage. Since the contractual documents were reconsidered where

necessary, the downstream parties were involved upfront to activate concurrent

construction.

Page 135: building information modeling–based process transformation to improve productivity in the

115

Pre-BIM Status: traditional practice

BIM Stage 1: object-based modeling

BIM Stage 3: network-based integration

BIM Stage 2: model-based collaboration

· 2D drafting and detailing· Document-based and linear workflow· Asynchronous communication· Adversarial relationship· Risk avoidance· Lack of interoperability

· 3D object-oriented model· Single-disciplinary model· Automated and coordinated 3D visualizations· Basic data harvested from the model such as

2D plans, elevations, sections, and QTOs· Adversarial relationship· Asynchronous communication

· Multi-disciplinary data share and exchange· 4D and 5D analysis· Clash detection between disciplines· Contractual amendments· Asynchronous communication· Fast-tracking

· Semantically-rich nD model· Complex analysis at early stages· Multi-disciplines use the same model through

a common database· Concurrent construction· Major contractual reconsideration· Synchronize communication· Multi-user server for collaboration

Migration from 2D to 3D

Modeling to

collaboration

Collaboration to integration

Figure 4.3 BIM maturity stages in previous studies (Succar, 2009; Khosrowshiahi and

Arayici, 2012)

In this study, the implementation readiness of a project team that plans to use BIM

was defined as “the psychological willingness or the state of being prepared for

performing BIM implementation activities”. The implementation readiness described

the condition or situation of the team in the project planning and preparation stage.

Since BIM implementation practices in this project team were still in preparation at

this stage, the term “readiness” was used. To help the Singapore construction industry

move towards higher levels of BIM implementation, this study proposed four statuses

of BIMIR in the building project context:

(1) BIMIR status one (S1): no BIM implementation

In particular, this status does not involve any BIM implementation activities in the

project delivery, so it describes the traditional approach of project delivery. The

traditional 2D CAD approach is used in the design, detailing, and documentation.

Page 136: building information modeling–based process transformation to improve productivity in the

116

The industry suffers from low investment in technology and paper-based

information exchange. Many NVA activities will inevitably occur in the project

delivery. Thus, the Pre-BIM status proposed by Succar (2009) and Khosrowshahi

and Arayici (2012) pertains to this readiness status.

(2) BIMIR status two (S2): lonely BIM implementation

This is the first stage in implementing BIM, gradually moving from the traditional

2D drafting to object-based 3D parametric design (Forgues and Lejeune, 2015).

This readiness status is characterized by the situation that each discipline or

primary project participant may adopt BIM, and such adoption is in silos. In other

words, this status does not involve any significant model-based data sharing

between different disciplines or parties, which is also not required by the main

form of contract. Thus, the level of collaboration is weak, and NVA activities will

occur often. Based on these characteristics, the aforementioned first, second, and

third phases of BIM implementation proposed by Lee (2007a) as well as the BIM

Stage One (Succar, 2009; Khosrowshahi and Arayici, 2012) are closely related to

this readiness status. It should be noted that most BIM implementation activities

guided by the first Singapore BIM roadmap would typically lead to the lonely

BIM implementation. The term “lonely BIM” was widely used in previous BIM

implementation studies (Abbasnejad and Moud, 2013; Kuiper and Holzer, 2013;

Das et al., 2014; Forgues and Lejeune, 2015; Gibbs et al., 2015; Poirier et al.,

2015), which describes the opposite of “collaborative BIM”.

(3) BIMIR status three (S3): collaborative BIM implementation

The collaborative BIM implementation involves multidisciplinary or multi-

stakeholder collaboration in the design, detailing, analysis, and documentation.

The semantically-rich models are shared through proprietary or non-proprietary

formats and multi-user access platforms (such as BIM Server). Meanwhile, some

contractual documents need to be amended to allow data sharing and incentivize

downstream parties to actively participate upfront. In a building project under this

Page 137: building information modeling–based process transformation to improve productivity in the

117

readiness status, the level of collaboration may vary from project to project. In

such a project, the occurrence of the NVA activities is not very often. Generally

speaking, the more NVA activities occur or the NVA activities occur more

frequently, the lower the level of collaboration and readiness status would be.

Therefore, the fourth phase proposed by Lee (2007a) as well as the BIM Stage

Two and the BIM Stage Three proposed by Succar (2009) and Khosrowshahi and

Arayici (2012) are closely associated with this readiness status established in this

study. In particular, the BIM Stage Three involves closer collaboration than the

BIM Stage Two. The communication pattern tends to be synchronized in the

former stage and be asynchronous in the latter stage. Typically, the second

Singapore BIM roadmap has been encouraging the local construction value chain

to implement BIM in a more collaborative manner.

(4) BIMIR status four (S4): full BIM implementation

Specifically, this is the highest readiness status of BIM implementation

established in this study. Succar (2009) argued that IPD could be used to denote

an approach to or an ultimate goal of implementing BIM. Thus, a building project

under this readiness status should follow the six key characteristics or principles of

IPD (see Table 3.3).

The four BIMIR statuses were developed for the building project teams that operate

in the Singapore context. These statuses were different from the levels of the BIM

Maturity Model which is specifically used in the UK and consists of a large set of

well-defined UK-centric requirements and deliverables (standards and guidelines)

(Government Construction Client Group, 2011). Besides, the BIM Maturity Model

cannot be used to assess BIM capabilities of organizations or teams. This model

cannot use BIM levels to establish an organization’s ability to collaborate with others,

conduct model-based analysis, or deliver high-quality 4D construction scheduling.

Page 138: building information modeling–based process transformation to improve productivity in the

118

Instead, with the NVA activities being sub-criteria, BIMIR statuses can be measured

in building project teams.

4.4 A BIMIR Model for Building Projects

4.4.1 Existing BIM readiness models

To evaluate a project’s BIMIR, the project leadership team should make efforts to

understand its current BIM capabilities and practices in the project planning stage.

The efforts are necessary because this can help the leadership team to obtain a clear

view of the strengths and weaknesses of its BIM implementation. Based on the

evaluation result, the management staff can purposively figure out appropriate

strategies and prioritize resources to improve the weak areas.

The literature review showed that few studies by far have been conducted to assess

BIM capabilities and BIMIR status of a project team. Juan et al. (2017) developed a

model to assess the technology acceptance and organizational readiness of Taiwanese

architectural firms to adopt BIM and BIM-based building permit review process.

After recognizing the benefits of BIM implementation, the Taiwanese government

had been planning to enact a policy that would revolutionize the local construction

industry. BIM-based e-submissions would be incorporated into the local building

permit review process. The local architectural firms would be mostly affected as they

are involved in the early stages of building projects (Juan et al., 2017).

In particular, to study the local architects’ experience of and willingness to implement

BIM, Juan et al. (2017) identified 22 items to assess their BIM acceptance, and

categorized the items into four groups of attributes: BIM technology usage, external

environments, internal factors, and employees, based on the highly interrelated

technology acceptance model (Davis, 1989), knowledge management system (Zhang

Page 139: building information modeling–based process transformation to improve productivity in the

119

et al., 2009), and balanced scorecard (Ashurst et al., 2012). In addition, to assess

whether the architectural firms were ready to adopt BIM, Juan et al. (2017) also

established 18 assessment items. Based on the theory of readiness for workplace

change management (Becker, 2004), these assessment items were further classified

into six groups of attributes, namely leadership, business performance, operating

environment, organizational culture, technological environment, and workforce

demographics. This would help the architectural firms assess their organizational

readiness to adopt BIM and reflect upon their organizational work practices and

current technology capabilities.

Organizational readiness was contended to be highly related to the staff’s technology

acceptance within a firm (Venkatesh, 2000). With the organizational readiness

assessment, the Taiwanese architectural firms’ internal readiness to adopt a new

technology could be obtained. The staff would be willing to accept the new

technology when they are ready for organizational change (Tsikriktsis, 2004).

Therefore, organizational readiness plays a critical role in the successful adoption of

the new technology and technological process such as BIM.

Although the model proposed by Juan et al. (2017) can be used to assess the BIMIR,

it focused at the firm (the architectural firms) level in the Taiwanese context, rather

than at the project (building projects) level which includes the whole construction

value chain. Hence, this study proposes a BIMIR evaluation for evaluating the

BIMIR statuses of building projects in Singapore.

4.4.2 A fuzzy BIMIR model

This study assumed that BIMIR of a building project in Singapore could be evaluated

by a NVA index (NVAI). In this study, NVAI is defined as “the degree to which a

Page 140: building information modeling–based process transformation to improve productivity in the

120

project frequently produces critical NVA activities in the project lifecycle”. The

NVAI score could be measured by the frequency of occurrence of the critical NVA

activities in the project lifecycle. Generally speaking, the readiness was negatively

related to the frequency of occurrence of the critical NVA activities. As shown in

Section 7.2.2, a total of 44 common NVA activities were identified in a building

project. Among which, six, nine, nine, six, three, eight, and three common NVA

activities belonged to the project phases of conceptualization (P1), schematic design

(P2), design development (P3), construction documentation (P4), agency

permit/bidding/preconstruction (P5), construction (including manufacture) (P6), and

handover/closeout/operations and maintenance (P7), respectively. These NVA

activities enable the project leadership team to easily understand the criteria and

evaluate its BIMIR status according to its planning of BIM implementation activities.

If the critical NVA activities would have occurred more thoroughly and frequently in

their current implementation practices, BIMIR status of this project can be deemed as

lower. It should be noted that the importance of these critical NVA activities and

project phases varies, so they should be assigned with different weights.

The critical NVA activities were distributed in seven project phases. In this study, the

project phases were considered as evaluation criteria, and the NVA activities as sub-

criteria. Thus, the issue of evaluating the BIMIR status of this building project by

assessing the critical NVA activities became a multiple-criteria decision-making

process. Thus, in the three-layer BIMIR evaluation model, the first layer was the

BIMIR status (or NVAI score) of the building project, the second layer consisted of

the seven project phases, and each phase comprised of a few NVA activities (the third

layer). The literature review identified four commonly-used multi-criteria analysis

methods, namely the FSE, artificial neural network (ANN), preference ranking

organization method for enrichment evaluations (PROMETHEE), and analytic

hierarchy process (AHP). Since the PROMETHEE is not applicable to determine the

Page 141: building information modeling–based process transformation to improve productivity in the

121

weights, this method was not applied in this study. Although the AHP method can

determine the weights, its pairwise comparisons are not suitable to the seven project

phases. This is because: (1) these phases are interrelated along the project timeline,

rather than being considered in parallel; and (2) pairwise comparisons usually involve

inexact or incomplete information and are thus hard for decision makers to make

accurate expressions of relative preferences (Lin et al., 2008). Thus, this method was

also not taken into account.

The proposed BIMIR evaluation model in this study is used for self-assessment by

the project leadership team in the project planning and preparation stage, which could

be achieved by using the FSE or the ANN method. Following the establishment of the

technology acceptance assessment items and the organizational readiness assessment

items for the Taiwanese architectural firms, Juan et al. (2017) further categorized the

10 groups of attributes into five new assessment variables (project collaboration and

communication, technology investment and training, organizational structure and

operating environment, technical environment and support, and leadership and

executive power). A predictive model was developed to help the local architects

evaluate the readiness to implement BIM in their firms, which was based on the ANN

method and in particular, a back-propagation learning algorithm with feed-forward

architecture. The output of this model was BIM adoption decision (“yes” or “no”),

with a good overall prediction of 81.3%.

Nevertheless, the FSE method has advantages over the ANN method in terms of data

precision. The former, as pioneered by Zadeh (1965), can address decision problems

involving uncertainty (Chen and Hwang, 1992). This is because the FSE method is

able to deal with vague, imprecise, and ambiguous data, use natural language and

linguistic terms (Higgins and Goodman, 1993), and quantify the linguistic facet of

available data and preferences for individual or group decision-making. In particular,

Page 142: building information modeling–based process transformation to improve productivity in the

122

the decision-making process in the real world is often influenced by human factors,

such as subjective human thinking and preferences. In these circumstances, the

judgments are expressed by means of linguistic terms instead of real numbers. Such

problems related to the vagueness and imprecision in human judgments cannot be

solved by the ANN method. When the project leadership team self-assesses its

BIMIR in the project planning stage, subjective judgments will inevitably occur in

certain team members. For example, when required to rate the frequency of

occurrence of a NVA activity using a five-point or seven-point scale, a BIM expert

may be uncertain between “3” and “4”. Since it is impossible to rate “3.5”, the expert

can only provide a response, “3” or “4”. If the expert finally selects “3”, there is also

possibility for being “4”, and vice versa. In this case, the issue of uncertainty is

created, which can be solved by fuzzy set theory. Therefore, the FSE was adopted in

the development of the BIMIR evaluation model in this study.

In an universe of discourse 𝑈, a fuzzy subset 𝐴 of 𝑈 allows partial membership, and

can be defined as:

𝐴 = {(𝑢, 𝜇𝑎(𝑢))|𝑢 ∈ 𝑈} (4.1)

where 𝜇𝑎(𝑢) is the membership function of the fuzzy set 𝐴, which can also be written

as 𝐴(𝑢). 𝐴(𝑢) maps each element 𝑢 in 𝑈 to a real number (function value) ranging

from 0 to 1. This real number specifies the degree to which 𝑢 belongs to 𝐴. When

𝐴(𝑢) is large, its grade of membership of 𝑢 in 𝐴 is strong.

The key in fuzzy modeling is to define fuzzy numbers, and the result of calculations

would strongly depend on the shape of the membership function adopted. Ross (2010)

found that in practical applications, five types of membership functions had been

Page 143: building information modeling–based process transformation to improve productivity in the

123

widely used: (1) triangular; (2) trapezoidal; (3) S function; (4) Gaussian; and (5) Z

function. In this study, the triangular one (see Figure 4.4) was used, and fuzzy and

qualitative opinions expressed by BIM experts in Singapore were represented as

triangular fuzzy numbers (TFNs). The reasons of using TFN were: (1) it has been

most commonly used (Tah and Carr, 2000; Chou and Chang, 2008; Lam et al., 2010;

Xia et al., 2011; Nieto-Morote and Ruz-Vila, 2011, 2012; Zhao et al., 2013; Işik and

Aladağ, 2017); (2) it is easy to process qualitative information in a fuzzy environment

(Chou and Chang, 2008; Nieto-Morote and Ruz-Vila, 2012) because it is linear

(Mayor and Trillas, 1986); and (3) its representation with a simpler function shape

tends to be more intuitive (Chou and Chang, 2008) and more natural interpretation

(Nieto-Morote and Ruz-Vila, 2011, 2012).

U

1

A(u)

0a b cu

Figure 4.4 Triangular membership function

A TFN can be denoted as a triplet (𝑎, 𝑏, 𝑐) where 𝑎, 𝑏, and 𝑐 are real numbers, and

𝑎 < 𝑏 < 𝑐. Its membership function 𝐴(𝑢) is defined as equation (4.2):

𝐴(𝑢) = {

𝑢−𝑎

𝑏−𝑎, 𝑎 ≤ 𝑢 ≤ 𝑏

𝑐−𝑢

𝑐−𝑏, 𝑏 ≤ 𝑢 ≤ 𝑐

0, 𝑢 < 𝑎 𝑜𝑟 𝑢 > 𝑐

(4.2)

where 𝑎, 𝑏, and 𝑐 represents the lower bound, strongest grade membership, and upper

bound of 𝐴(𝑢), respectively, as shown in Figure 4.4. Meanwhile, the primary fuzzy

Page 144: building information modeling–based process transformation to improve productivity in the

124

arithmetic operations of any two TFNs, 𝐴1 = (𝑎1, 𝑏1, 𝑐1) and 𝐴2 = (𝑎2, 𝑏2, 𝑐2), are

indicated below (Chen and Hwang, 1992):

(1) Addition: 𝐴1+𝐴2 = (𝑎1+𝑎2, 𝑏1+𝑏2, 𝑐1+𝑐2);

(2) Subtraction: 𝐴1−𝐴2 = (𝑎1−𝑐2, 𝑏1−𝑏2, 𝑐1−𝑎2);

(3) Multiplication: 𝐴1×𝐴2 = (𝑎1×𝑎2, 𝑏1×𝑏2, 𝑐1×𝑐2);

(4) Multiplication of any real number and a TFN, 𝑘×𝐴 = (𝑘×𝑎, 𝑘×𝑏, 𝑘×𝑐);

(5) Division: 𝐴1∕𝐴2 = (𝑎1/𝑐2, 𝑏1/𝑏2, 𝑐1/𝑎2); and

(6) Division by any real number, 𝐴/𝑘 = (𝑎/𝑘, 𝑏/𝑘, 𝑐/𝑘).

The root of the FSE method lies in the concept of linguistic variables. Unlike the

numerical variables whose values are numbers, linguistic variables are the variables

whose values are linguistic terms such as words and sentences in a natural or artificial

language (Zadeh, 1975), and thus are not directly mathematically operable (Nieto-

Morote and Ruz-Vila, 2012). This concept plays a fundamental role in the decision-

making problems in which it may be difficult for decision makers to assign exact

numerical values to linguistic variables due to the unavailability or uncertainty of

information involved (Nieto-Morote and Ruz-Vila, 2012). Because of great

subjectivity, in these cases the decision makers tend to use linguistic variables instead

of numerical variables. In addition, to overcome the difficulty of mathematically

operating the linguistic variables, the linguistic terms should be transformed to fuzzy

numbers to characterize the meaning of the terms. In this study, the linguistic variable

was defined as the frequency of occurrence of each critical NVA activity within each

project phase. The determination of the number of conversion scales is usually

intuitive (Chen and Hwang, 1992). Following the scale of “seven plus or minus two”

(Miller, 1956), this study adopted the scale of five. This would generate large amount

of information from users and bring convenience to the users to make the subjective

Page 145: building information modeling–based process transformation to improve productivity in the

125

judgments. The linguistic values were defined as: never, rarely, sometimes, often, and

always. These fuzzy terms were transformed into TFNs, respectively.

A triangular fuzzy set usually needs to overlap with its neighboring fuzzy set by 25%

to 50% of the fuzzy set base (Cox, 1998). The intersection of two overlapping

membership functions should be at least 50% for control applications and a little

lower for classification (Driankov et al., 1996). Therefore, 50% was adopted in this

study (see Figure 4.5).

U

1

A(u)

0 0.25 0.5 0.75 1

Rarely Sometimes Often AlwaysNever

Figure 4.5 Membership functions of linguistic values

The Likert rating scale is suitable to obtain accurate data and the results are easy to

interpret (Ekanayake and Ofori, 2004). As shown in Table 4.3, a five-point Likert

rating scale (1=never, 2=rarely, 3=sometimes, 4=often, and 5=always) was used in a

survey to measure the frequency of occurrence of the critical NVA activities as

indicated by the BIM experts who had been implementing BIM in the Singapore

construction industry.

Table 4.3 Fuzzy numbers of linguistic terms

Linguistic term Range of percentile of possibility Fuzzy number

Never 0-25 (0, 0, 0.25)

Rarely 0-50 (0, 0.25, 0.50)

Sometime 25-75 (0.25, 0.50, 0.75)

Often 50-100 (0.50, 0.75, 1)

Always 75-100 (0.75, 1, 1)

Page 146: building information modeling–based process transformation to improve productivity in the

126

In this study, decision criteria and sub-criteria do not have the same importances so

they need to be weighted. The NVA activities that were not critically agreed upon by

the BIM experts in Singapore were subsequently excluded. The weighting could be

assigned to the critical NVA activities according to their respective mean scores. The

mean scoring method was recommended by Chan and Kumaraswamy (1996) who

calculated the relative importance of causes of delay in building projects based on the

views of the owners, consultants, and contractors in Hong Kong. In particular, the

mean score (𝑀𝑖) of a particular critical NVA activity can be calculated using equation

(4.3):

𝑀𝑖 =∑ (𝑓𝑖𝑠𝑖)𝑛

𝑖=1

𝑛 (4.3)

where:

𝑛 represents the total number of responses;

𝑀𝑖 represents the mean score of a particular critical NVA activity 𝑖;

𝑠𝑖 represents the score that the BIM experts rated the critical NVA activity; and

𝑓𝑖 represents the frequency of each rating on the critical NVA activity, and ∑ 𝑓𝑖 =𝑛𝑖=1

1.

Then, the mean score (𝑀𝑝) of a particular project phase can be calculated using

equation (4.4) which was also applied in previous construction management studies

(Xu et al., 2010b; Zhao et al., 2016a):

𝑀𝑝 = ∑ 𝑀𝑖𝑝𝑘

𝑖=1 (4.4)

where:

𝑘 represents the number of critical NVA activities within a project phase;

𝑀𝑝 represents the mean score of a particular project phase 𝑝;

𝑀𝑖𝑝

represents the mean score of critical NVA activity 𝑖 under project phase 𝑝; and

Page 147: building information modeling–based process transformation to improve productivity in the

127

∑ 𝑀𝑖𝑘𝑖=1 represents the summation of the mean scores of all the 𝑘 critical NVA

activities within a project phase.

In addition, to calculate the weighting of each project phase, the weighting of each

critical NVA activity within each project phase should be determined. The weights

assigned to the critical NVA activities within a project phase can be calculated using

equation (4.5):

𝑊𝑖 =𝑀𝑖

∑ 𝑀𝑖𝑘𝑖=1

(4.5)

where:

𝑘 represents the number of critical NVA activities within a project phase;

𝑊𝑖 represents the weighting of a particular critical NVA activity 𝑖 in the project phase,

and ∑ 𝑊𝑖 = 1𝑘𝑖=1 ;

𝑀𝑖 represents the mean score of critical NVA activity 𝑖; and

∑ 𝑀𝑖𝑘𝑖=1 represents the summation of the mean scores of all the 𝑘 critical NVA

activities within the project phase.

Similarly, to calculate the overall NVAI, the weighting of each project phase should

be determined. The weights assigned to the project phases can be calculated using

equation (4.6):

𝑊𝑝 =𝑀𝑝

∑ 𝑀𝑝𝑞𝑝=1

(4.6)

where:

𝑞 represents the number of project phases in a project (in this study, 𝑞=7);

𝑊𝑝 represents the weighting of a particular phase 𝑝, and ∑ 𝑊𝑝𝑞𝑝=1 = 1;

Page 148: building information modeling–based process transformation to improve productivity in the

128

𝑀𝑝 represents the mean score of phase 𝑝, which can be calculated by summing the

mean scores of all the critical NVA activities within this phase; and

∑ 𝑀𝑝𝑞𝑝=1 represents the summation of the mean scores of all the phases in the project

lifecycle.

Such weighted-mean methods of determining the weighting of critical factors and

factor groups were also adopted in previous construction management studies (Yeung

et al., 2007; Xu et al., 2010a; Xu et al., 2010b; Xia et al., 2011; Zhao et al., 2016a).

Subsequently, to evaluate the BIMIR status via the NVAI score of the building

project, the data related to the frequencies of occurrence of all the critical NVA

activities, which were rated by the BIM experts involved in the building project,

should be input to the proposed FSE model. In particular, the frequency of occurrence

of a NVA activity can be calculated using equation (4.7):

𝐹𝑖𝑝

= (𝑓𝑖1𝑝

, 𝑓𝑖2𝑝

, 𝑓𝑖3𝑝

) =1

𝑟× ∑ 𝐹𝑖𝑗

𝑝𝑟𝑗=1 (4.7)

where:

𝐹𝑖𝑝

represents the TFN of the frequency of occurrence of NVA activity 𝑖 within

project phase 𝑝;

𝑟 represents the number of the users who participated in evaluating the NVAI in a

building project; and

𝐹𝑖𝑗𝑝

represents the TFN of the frequency of occurrence of NVA activity 𝑖 within

project phase 𝑝 evaluated by user j; and 𝑓𝑖1𝑝

, 𝑓𝑖2𝑝

, and 𝑓𝑖3𝑝

represent the lower bound,

strongest grade membership, and upper bound of 𝐹𝑖𝑝

, respectively.

Page 149: building information modeling–based process transformation to improve productivity in the

129

Next, the frequency of occurrence of each project phase where the critical NVA

activities within this phase frequently occur in this building project can be calculated

using equation (4.8):

𝐹𝑝 = (𝑓1𝑝

, 𝑓2𝑝

, 𝑓3𝑝

) = ∑ (𝑊𝑖 × 𝐹𝑖𝑝

)𝑘𝑖=1 (4.8)

where:

𝐹𝑝 represents the TFN of the frequency of occurrence of project phase 𝑝;

𝑘 represents the number of critical NVA activities within project phase 𝑝;

𝑊𝑖 represents the weighting of NVA activity 𝑖, and ∑ 𝑊𝑖 = 1𝑘𝑖=1 ; and

𝑓1𝑃, 𝑓2

𝑃, and 𝑓3𝑃 represent the lower bound, strongest grade membership, and upper

bound of 𝐹𝑝, respectively.

Therefore, the NVAI (a fuzzy set 𝑁𝑉𝐴𝐼) of this building project can be calculated

using the following equations (4.9 and 4.10):

𝑁𝑉𝐴𝐼 = (𝑛𝑣𝑎𝑖1, 𝑛𝑣𝑎𝑖2, 𝑛𝑣𝑎𝑖3) = ∑ (𝑊𝑝 × 𝐹𝑝) =𝑞𝑝=1 ∑ {𝑊𝑝 × ∑ (𝑊𝑖 × 𝐹𝑖

𝑝)𝑘

𝑖=1 }𝑞𝑝=1 (4.9)

𝑛𝑣𝑎𝑖𝑡 = ∑ (𝑊𝑝 × 𝑓𝑡𝑝

), (𝑡 = 1, 2, 3)𝑞𝑝=1 (4.10)

where:

𝑛𝑣𝑎𝑖1, 𝑛𝑣𝑎𝑖2, and 𝑛𝑣𝑎𝑖3 represent the lower bound, strongest grade membership, and

upper bound of 𝑁𝑉𝐴𝐼, respectively;

𝑊𝑝 represents the weighting of phase 𝑝; and

𝑓𝑡𝑝 can be calculated using equation 4.8.

The operation of defuzzifying the fuzzy numbers is an important procedure for the

evaluation in a fuzzy environment. To transform the TFNs of the 𝑁𝑉𝐴𝐼 into a non-

fuzzy crisp number, a single value that adequately represents the TFNs and indicates

a final rating in the interval [0, 1] would be produced. Four methods for the

Page 150: building information modeling–based process transformation to improve productivity in the

130

defuzzification process, namely centroid method (or center of area), mean of maximal,

𝛼-cut method, and signed distance method, were commonly used (Yager, 1980; Klir

and Yuan, 1995; Chou and Chang, 2008).

The centroid method (see Figure 4.6) was used in this study because of the following

reasons: (1) it is relatively simple and most widely used (Chou and Chang, 2008; Lam

et al., 2010; Nieto-Morote and Ruz-Vila, 2011; Zhao et al., 2013; Işik and Aladağ,

2017); (2) the defuzzified value moves smoothly around output fuzzy region; and (3)

it could reflect the actual situation and the perceptions of the local BIM experts.

U

1A(u)

0a bu*

Figure 4.6 Central method of defuzzification

As shown in Figure 4.6, this method was intended to figure out the point (𝑢∗) which

represents the center of gravity of the fuzzy set using equation (4.11):

𝑢∗ = ∫ 𝐴(𝑢)𝑢𝑑𝑢𝑏

𝑎(∫ 𝐴(𝑢) 𝑑𝑢

𝑏

𝑎)⁄ (4.11)

Since this study adopted the triangular fuzzy set, the point indicating the center of

gravity (the crisp number of NVAI score) could be calculated using the following

equation:

NVAI score = 1/3 × (𝑛𝑣𝑎𝑖1 + 𝑛𝑣𝑎𝑖2 + 𝑛𝑣𝑎𝑖3) (4.12)

Page 151: building information modeling–based process transformation to improve productivity in the

131

As indicated in Figure 4.7, the crisp number would be in the interval [0, 1] and fall

into two adjacent linguistic terms. Thus, the NVAI score could be interpreted as the

linguistic term with a higher membership value.

U

1

A(u)

0 0.25 0.5 0.75 1

Rarely Sometimes Often AlwaysNever

Figure 4.7 Translation of NVAI score into linguistic terms (frequency of occurrence)

Furthermore, it should be noted that the BIMIR status of the building project was

negatively associated with the NVAI score. The abovementioned translation of the

NVAI score into the frequency of occurrence of the critical NVA activities was

generic. However, because the number (5) of the frequency of occurrence of the

critical NVA activities was not equal to the number (4) of the previously-defined

BIMIR statuses (see Table 4.4), the translation of the NVAI score into the BIMIR

status needed to be adjusted.

Table 4.4 Generic translation of NVAI score to BIMIR status

Linguistic term NVAI score BIMIR status

Always 0.875≤ Index score S1 (no BIM implementation)

Often 0.625≤ Index score <0.875 S2 (lonely BIM implementation)

Sometimes 0.375≤ Index score <0.625 S3 (collaborative BIM implementation)

Rarely 0.125≤ Index score <0.375 S4 (full BIM implementation)

Never Index score <0.125 S4 (full BIM implementation)

Because the basic purpose of the FSE approach is to re-assign the responses of

discrete numbers (such as 1, 2, 3, 4, and 5) to a new continuous interval [0, 1],

adjustment to the translation based on this interval is justified and would not violate

the logic of the fuzzy set theory.

Page 152: building information modeling–based process transformation to improve productivity in the

132

Literally both linguistic terms “often” and “always” could signify BIMIR S1 (no BIM

implementation) because the critical NVA activities occurred very frequently. Among

the interval [0.625, 0.875] of the linguistic term “often”, the crisp numbers ranging

from 0.750 to 0.875 were the half whose membership values were higher than the

other half. As indicated in Table 4.3, such a range fell into two adjacent fuzzy regions

“often” and somewhat “always” before the defuzzification process, and were

translated to BIMIR S2 (lonely BIM implementation). However, literally speaking,

this range signified that the critical NVA activities occurred very frequently, and in

other words, almost all the critical NVA activities occurred frequently. Thus, it may

bias the reality that the NVAI scores in this range were classified into BIMIR S2

(lonely BIM implementation). Instead, it should be considered more logical and

rational to translate the NVAI scores in the range of 0.750–0.875 to a lower BIMIR

status (S1, no BIM implementation). Likewise, among the interval [0.125, 0.375]

indicating the linguistic term “rarely”, the crisp numbers between 0.250 and 0.375,

before the defuzzification process, belonged to two neighboring fuzzy regions “rarely”

and somewhat “sometimes”, and were translated to BIMIR S4 (full BIM

implementation). Literally speaking, however, this range indicated that the critical

NVA activities did not occur very frequently. In other words, there were a small

number of critical NVA activities that occurred quite frequently. Thus, it would

possibly reflect the real situation if the NVAI scores in the range of 0.250 to 0.375

would be translated to a lower BIMIR status, namely BIMIR S3 (collaborative BIM

implementation), rather than BIMIR S4 (full BIM implementation).

Therefore, based on the above semantic analysis, the translation of the crisp numbers

of NVAI scores into BIMIR statuses should be slightly adjusted to solve the problem

of unequal numbers between the BIMIR statuses and the linguistic terms. As shown

in Table 4.5, the NVAI score ranges were classified into four divisions. In particular,

compared with the NVAI scores of the original dividing lines (see Figure 4.7), the

Page 153: building information modeling–based process transformation to improve productivity in the

133

NVAI scores of the new dividing lines increased by 0.125 (one eighth of the whole

interval). For instance, together with the range of 0.875–1.000, the range of 0.750–

0.875 was grouped into BIMIR S1 (no BIM implementation); the range 0.500–0.625

was adjusted from BIMIR S3 (collaborative BIM implementation) to BIMIR S2

(lonely BIM implementation); the range 0.250–0.375 was moved from BIMIR S4

(full BIM implementation) to BIMIR S3 (collaborative BIM implementation).

Table 4.5 Adjusted translation of NVAI score to BIMIR status

BIMIR status NVAI score

S1 (no BIM implementation) 0.75≤ Index score

S2 (lonely BIM implementation) 0.50≤ Index score <0.75

S3 (collaborative BIM implementation) 0.25≤ Index score <0.50

S4 (full BIM implementation) Index score <0.25

Overall, such adjustments were considered logical and reasonable and would not

violate the rationale and basis of the fuzzy set theory because: (1) the crisp numbers

were not translated to the original rating scale (frequency of occurrence), but

translated to BIMIR statuses; and (2) this study aimed to study BIMIR statuses in the

Singapore construction industry. Instead, the adjustments would make the evaluation

results more accurate and closer to the reality.

Therefore, the proposed fuzzy BIMIR model could provide a tool for project

leadership teams to evaluate and understand the extent to which their project teams

are capable and ready to implement BIM towards higher levels of BIM

implementation. The evaluation results can be either a crisp number or a linguistic

term to indicate the NVAI score and the BIMIR status.

4.5 Summary

The chapter reviewed the literature on the NVA activities in the current project

lifecycle process in Singapore. A total of 13 resulting wastes and 53 potential causes

Page 154: building information modeling–based process transformation to improve productivity in the

134

contributed by the key stakeholders were identified from the literature review. Four

BIMIR statuses were defined in this study, with support from previous studies, and

the definition was consistent with the local government’s BIM policies. Using the

critical NVA activities as evaluation criteria, a fuzzy BIMIR evaluation model for

building projects was developed. In this model, the BIMIR status of a building project

could be assessed by the NVAI, which could be measured by the frequency of

occurrence of the critical NVA activities in the project lifecycle. The BIMIR was

assumed to be negatively related to the frequency of occurrence of such activities.

Page 155: building information modeling–based process transformation to improve productivity in the

135

Chapter 5: Review of Factors Affecting BIM Implementation

and Proposal of an Organizational Change Framework

5.1 Introduction

This chapter identifies, from the literature review, the factors that hinder and drive the

transformation towards full BIM implementation in the Singapore construction

industry. As no theory on the process transformation using BIM is found in the

literature, this chapter reviews the literature on the theories of intra- and inter-

organizational change, including Leavitt’s diamond model and MIT90s framework as

well as their derivatives. These theories are then adapted to propose an organizational

change framework for building projects using BIM, which sets the foundation for

interpreting the factors affecting change towards full BIM implementation. Since the

main blocks of the proposed framework (people, process, technology, and external

environment) consist of a number of attributes that can guide the changes, this

framework can also serve as a theoretical model for process transformation.

5.2 Factors Affecting BIM Implementation

5.2.1 Hindrances to full BIM implementation

Previous studies have reported that many factors hindered BIM implementation in the

construction industry. Through the literature review analyzing 31 previous global

studies on BIM implementation, this study has identified 47 hindrances which would

increase project teams’ difficulty in implementing BIM collaboratively, as shown in

Table 5.1 (where “H” represents “hindrance”). However, these previous studies failed

to identify and understand the 47 hindrances comprehensively. It would be difficult

for project teams to implement BIM without considering all these hindrances. More

importantly, there was little information about how the hindrances may influence BIM

Page 156: building information modeling–based process transformation to improve productivity in the

136

Table 5.1 Hindrances to BIM implementation

Code Hindrances to full BIM implementation References

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

H01 Executives failing to recognize the value of BIM-based processes

and needing training

√ √ √ √ √ √

H02 Concerns over or uninterested in sharing liabilities and financial

rewards

√ √ √ √ √ √

H03 Construction lawyers and insurers lacking understanding of

roles/responsibilities in new process

√ √ √ √

H04 Lack of skilled employees and need for training them on BIM and

OSM

√ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √

H05 Industry’s conservativeness, fear of the unknown, and resistance

to change comfortable routines

√ √ √ √ √ √ √ √ √ √

H06 Employees still being reluctant to use new technology after being

pushed to training programs

√ √ √

H07 Unfamiliarity to use BIM and entrenchment in 2D drafting √ √ √ √ √ √ √ √ √ √ √

H08 Financial benefits cannot outweigh implementation and

maintenance costs

√ √ √ √ √

H09 Lack of sufficient evidence to warrant BIM use √ √ √ √ √

H10 Liability of BIM such as the liability for common data for

subcontractors

√ √ √ √

H11 Resistance to changes in corporate culture and structure √ √ √ √ √ √ √ √

H12 Need for all key stakeholders to be on board to exchange

information

√ √ √ √ √ √ √ √ √ √ √

H13 Lack of trust/transparency/communication/partnership and

collaboration skills

√ √ √ √ √ √ √ √ √ √ √ √ √

H14 BIM operators lacking field knowledge √ √ √ √

H15 Field staff dislike BIM coordination meetings looking at a screen √ √ √ √

H16 Lack of consultants’ feedbacks on subcontractors’ model

coordination

H17 Few benefits from BIM go to designers while most to contractors

and owners

H18 Lack of legal support from authorities √ √ √ √

H19 Lack of owner request or initiative to adopt BIM √ √ √ √

H20 Decision-making depending on relationships between project

stakeholders

√ √

H21 Owners set minimal risk and minimum first cost as crucial

selection criteria

√ √ √ √

Page 157: building information modeling–based process transformation to improve productivity in the

137

H22 Poor knowledge of using OSM and assessing its benefits √

H23 Requiring higher onsite skills to deal with low tolerance OSM

interfaces

H24 OSM relies on suppliers to train contractors to install correctly √

H25 Owners’ desire for particular structures or finishes when

considering OSM

H26 Market protection from traditional suppliers/manufacturers and

limited OSM expertise

H27 Contractual relationships among stakeholders and need for new

frameworks

√ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √

H28 Traditional contracts protect individualism rather than best-for-

project thinking

√ √ √ √

H29 Lack of effective data interoperability between project

stakeholders

√ √ √ √ √ √ √ √ √ √ √

H30 Owners cannot receive low-price bids if requiring 3D models √

H31 Firms’ unwillingness to invest in training due to initial cost and

productivity loss

√ √ √ √

H32 Assignment of responsibility/risk to constant updating for broadly

accessible BIM information

√ √ √

H33 Lack of standard contracts to deal with responsibility/risk

assignment and BIM ownership

√ √ √ √ √ √ √

H34 BIM model issues (e.g., ownership and management) √ √ √ √

H35 Poor understanding of OSM process and its associated costs √

H36 OSM requires design to be fixed early using BIM √ √

H37 Seeing design fees of OSM as more expensive than traditional

process

H38 Difficulty in logistics and stock management of OSM √ √

H39 Unclear legislations and qualifications for precasters and

inadequate codes for OSM varieties

H40 Interpretations resulted from unclear contract documents √

H41 Using monetary incentive for team collaboration results in

blaming rather than resolving issues

H42 Costly investment in BIM hardware and software solutions √ √ √ √ √ √ √ √ √

H43 Interoperability issues such as software selection and insufficient

standards

√ √ √ √ √

H44 Need for increasingly specialized software for specialized

functions

√ √ √ √

H45 Difficulty in multi-discipline and construction-level integration √ √

Page 158: building information modeling–based process transformation to improve productivity in the

138

H46 Technical needs for multiuser model access in multi-discipline

integration

√ √ √

H47 Firms cannot make most use of IFC and use proprietary formats √ √ √

Total number of hindrances studied 3 6 8 5 3 2 11 3 9 14 7 18 5 3 9 1 4 6 4 15 15 13 10 6 2 4 5 3 4 7 13

Note: (1) AIA and AIACC (2007); (2) AIA and AIACC (2009); (3) Aranda-Mena et al. (2009); (4) Arayici et al. (2011); (5) Autodesk (2008); (6) Autodesk

(2012); (7) Azhar et al. (2014); (8) Bernstein and Pittman (2004); (9) Bernstein et al. (2012); (10) Blismas and Wakefield (2009); (11) Chelson (2010); (12)

Eastman et al. (2011); (13) Fischer et al. (2014); (14) Fischer (2008); (15) Forsythe et al. (2015); (16) Fox and Hietanen (2007); (17) Gao and Fischer

(2006); (18) Ghaffarianhoseini et al. (2017); (19) Gibb and Isack (2003); (20) Juan et al. (2017); (21) Kent and Becerik-Gerber (2010); (22) Khosrowshahi

and Arayici (2012); (23) Kiani et al. (2015); (24) Kunz and Fischer (2012); (25) McFarlane and Stehle (2014); (26) Miettinen and Paavola (2014); (27)

Porwal and Hewage (2013); (28) Ross et al. (2006); (29) Sattineni and Mead (2013); (30) Turk (2016); (31) Zahrizan et al. (2013). √ indicates the inclusion

of the specific hindrance in the reference.

Page 159: building information modeling–based process transformation to improve productivity in the

139

implementation in the Singapore context. For example, Eastman et al. (2011)

investigated many hindrances but did not study governments’ active participation in

the design stage to specify BIM use. Khosrowshahi and Arayici (2012) identified the

hindrances to BIM implementation at high maturity levels for the contractors in the

UK, but failed to investigate the factors for other roles in the construction value

chain. Autodesk (2012) revealed that executives’ failure to recognize the value of

BIM would reduce employees’ willingness and enthusiasm to work with BIM, while

Zahrizan et al. (2013) reported that the employees may entrench themselves into the

traditional way of working even after being pushed by the management to attend

training programs. Sattineni and Mead (2013) found that commonly-used contractual

structures would inevitably lead to duplicate efforts made by different parties to

create digital information models, but rarely examined the influence of cultural

factors and individuals’ competencies on BIM implementation. Azhar et al. (2014)

explored legal, cultural, and technological issues of BIM implementation, but failed

to identify the hindrances related to the new work processes. Zahrizan et al. (2013)

and Kiani et al. (2015) identified unsupportive culture such as the unwillingness to

change that hindered the BIM implementation in Malaysia and Iran, respectively, but

did not study the governments’ active roles in the design process to specify BIM uses.

Juan et al. (2017) studied the factors hindering the Taiwan construction industry to be

ready to adopt BIM, but was limited to the architectural firms.

Confront with these hindrances, the projects teams tend to find it difficult to

implement BIM openly and collaboratively. The percentage of building projects

implementing BIM with a relatively high collaboration level was not high. For

example, Lam (2014) reported that almost all consultancy firms in Singapore had

implemented BIM, but 80% of such BIM implementation was firm-based, rather than

based on project-wide collaboration. The duplicate efforts for the designers and the

contractors to create building information models respectively are not uncommon

Page 160: building information modeling–based process transformation to improve productivity in the

140

bothin Singapore (Lam, 2014) and overseas (Sattineni and Mead, 2013). Actually,

people seek change, but do not want to be changed (Senge, 1990). Hence, it is critical

to get major stakeholders to understand the potential value and benefits of full BIM

implementation (Arayici et al., 2011; Khosrowshahi and Arayici, 2012). Once the

major stakeholders change to implement their part of BIM, an integrated process of

delivering the project using shared BIM models can be realized. This study intends to

fill the gap by investigating the hindrances with significant influence on BIM

implementation in building projects in Singapore, and reveal the theoretical rationale

behind these hindrances, extending the relevant literature.

5.2.2 Drivers for full BIM implementation

In addition to the hindrances, BIM implementation has been motivated by driving

factors. In this study, a total of 32 factors driving for full BIM implementation have

been identified from 35 previous studies related to BIM implementation in various

countries, as listed in Table 5.2 (where “D” represents “driver”) which also shows the

number of the drivers studied by each reference. These previous studies usually

investigated only a few specific drivers that enhanced BIM implementation in

particular countries rather than studying all these drivers comprehensively. For

example, among the references that involved 10 or more drivers, Gao and Fischer

(2006) and Kunz and Fischer (2012) focused on driving the contractors and designers

to work collaboratively on design models so that construction issues can be identified

and solved virtually before actual construction commences, but the involvement of

owners and facility managers was limited in this process. Eastman et al. (2011)

studied the majority of the identified factors but did not identify the key role of

government agencies in terms of their financial support such as subsidizing BIM

implementation cost (infrastructure purchase and upgrading, training, and

consultancy costs). Khosrowshahi and Arayici (2012) proposed a roadmap for BIM

Page 161: building information modeling–based process transformation to improve productivity in the

141

Table 5.2. Drivers for full BIM implementation

Code Drivers for full BIM implementation References

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

D01 BIM vision and leadership from the management √ √ √ √ √ √ √ √ √

D02 Changes in organizational structure and culture √ √ √ √ √ √ √ √

D03 Stakeholders seeing the value of adopting their own part of

BIM

√ √ √ √ √ √ √ √

D04 Training on new skillsets and new ways of working √ √ √ √ √ √ √ √ √ √ √ √ √ √ √

D05 Owner’s requirement and leadership to adopt BIM √ √ √ √ √ √ √

D06 Regulatory agencies’ early participation to BIM use √ √ √ √

D07 Gaining competitive advantages from full BIM use √ √ √

D08 All disciplines sharing models in a “Big Room” √ √ √ √ √ √ √ √ √ √ √ √ √

D09 Government support such as subsidizing training, software,

and consultancy costs

√ √ √ √ √ √

D10 Enabling subcontractors to use lower-skilled labor on site √ √ √

D11 OSM lowering safety risks by controlling work in factory √ √ √ √ √

D12 Alignment of the interests of all stakeholders √ √

D13 Governance of BIM-related policies and standards √ √ √ √ √

D14 Data sharing and access on BIM platforms √ √ √ √ √ √ √ √ √

D15 3D visualization enabling design communication √ √ √ √ √ √ √ √ √

D16 Four-dimensional simulation before construction √ √ √ √ √ √ √ √

D17 Design coordination between disciplines through clash

detection and resolution

√ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √

D18 Complex design analysis in sustainability, material

selection, and constructability

√ √ √ √ √ √ √ √ √

D19 Project lifecycle costing √ √ √ √

D20 Producing models and drawings for construction and

fabrication

√ √ √ √ √ √ √ √

D21 High accuracy of model-based documentation √ √ √

D22 More off-site fabrication and assembly of standard

elements

√ √ √ √ √ √ √ √ √

D23 Automatic model updating and drawing production to deal

with design changes and their implications

√ √ √

D24 Lifecycle information management improving operations

and maintenance

√ √ √ √ √ √ √

D25 Increasing use of design-build and fast-track approach √ √

D26 On-site work proceeds in parallel with off-site production √ √ √ √

Page 162: building information modeling–based process transformation to improve productivity in the

142

D27 OSM standardizes design and manufacturing processes,

simplifying construction and testing and commissioning

processes

√ √ √ √ √

D28 OSM enabling better quality and consistency of building

elements

√ √ √

D29 OSM reduces building wastes, especially on-site wastes √ √ √ √

D30 Integrating model management tools with enterprise

systems to share data

D31 Increasing complexity in buildings, project delivery, and

marketplace

√ √ √ √

D32 New technologies such as CNC machines √ √ √ √ √

Total number of drivers studied 6 4 5 7 4 3 3 8 5 8 5 12 1 5 5 11 3 4 11 1 5 10 4 10 2 11 4 12 4 5 3 2 3 11 4

Note: (1) AIACC (2014); (2) Aranda-Mena et al. (2009); (3) Arayici et al. (2011); (4) Autodesk (2012); (5) Azhar et al. (2014); (6) BCA (2013b); (7)

Bernstein and Pittman (2004); (8) Blismas and Wakefield (2009); (9) Blismas et al. (2006); (10) Cheng and Lu (2015); (11) Chua and Yeoh (2015); (12)

Eastman et al. (2011); (13) Fischer et al. (2014); (14) Fischer (2008); (15) Forsythe et al. (2015); (16) Gao and Fischer (2006); (17) Ghaffarianhoseini et al.

(2017); (18) Gibb and Isack (2003); (19) Juan et al. (2017); (20) Kent and Becerik-Gerber (2010); (21) Khanzode et al. (2007); (22) Khosrowshahi and

Arayici (2012); (23) Kiani et al. (2015); (24) Kunz and Fischer (2012); (25) Li et al. (2009); (26) McFarlane and Stehle (2014); (27) Miettinen and Paavola

(2014); (28) Oo (2014); (29) Porwal and Hewage (2013); (30) Ross et al. (2006); (31) Sattineni and Mead (2013); (32) Selvaraj et al. (2009); (33) Turk

(2016); (34) Won et al. (2013); (35) Zahrizan et al. (2013). √ indicates the inclusion of the specific driver in the reference.

Page 163: building information modeling–based process transformation to improve productivity in the

143

implementation in the UK construction industry but did not drive off-site

prefabrication which facilities BIM use. Won et al. (2013) investigated the critical

factors that were commonly considered to enhance BIM implementation in a firm,

which was different from the present research studying the factors at the project level.

Without the consensus of all the major stakeholders in the project to implement BIM

collaboratively, the project-wide implementation of BIM cannot be realized based on

individual parties’ efforts. This previous study also lacked the consideration of

government aspects and new construction methods such as off-site prefabrication.

McFarlane and Stehle (2014) concentrated on incorporating the OSM process into

BIM implementation. Juan et al. (2017) studied the factors that would increase

architectural firms’ motivation and readiness to implement BIM, such as the pressure

from their competitors, which was limited in the architectural firms in Taiwan. Oo

(2014) identified the critical cultural and individual factors for the architectural firms

in Singapore to shift from the traditional work practices towards BIM work processes,

but the implementation was also firm-based; meanwhile, this said study failed to

identify the factors driving the new construction methods and motivating the

collaborative relationships among the primary participants. Other previous studies

investigated even fewer drivers. Therefore, none of the previous studies had provided

a comprehensive understanding of the 32 drivers.

Because of these drivers, the percentage of overall BIM adoption in the Singapore

construction industry has been growing (Lam, 2014; BCA, 2016). Perhaps the most

important economic driver for BIM systems and their adoption will be the intrinsic

value that their quality of information will provide to building owners. Improved

information quality, building products, visualization tools, cost estimates, and

analyses lead to better decision-making during the design stage and fewer wastes in

the downstream phases, reducing both first costs for construction and lifecycle

costs. Together with the value of building models for operations and maintenance, a

Page 164: building information modeling–based process transformation to improve productivity in the

144

snowball effect is likely, where clients demand the use of BIM on their projects

(Eastman et al., 2011). Overall, a holistic view of all the identified drivers should be

established for the project teams to implement BIM openly and collaboratively. This

study would extend the relevant literature by identifying the drivers with significant

influence on changing towards full BIM implementation in building projects in

Singapore and demonstrating the theoretical rationale behind these drivers.

5.3 A Proposed Organizational Change Framework for BIM

Implementation

5.3.1 Organizational change theories

Organizational change is defined as “an empirical observation of difference in form,

quality or long term state of an organizational entity, coming out of the deliberate

introduction of new styles of thinking, acting or operating, and looking for the

adaptation to the environment or for a performance improvement” (Pardo-del-Val et

al., 2012). Michel et al. (2013) advocated that organizations operating in a changing

environment need sustainable organizational changes for their own survival,

development, and success. Among existing organizational change theories, Leavitt’s

diamond theory was selected in this study because it assesses organizations’ current

level of functioning and activities for designing better strategies of implementing new

technologies (Dahlberg et al., 2016), which is consistent with the Singapore

government’s encouragement to use BIM in the local industry. BIM has been

emerging as a new technology or technological process which has been proven to be

beneficial to building projects (Eastman et al., 2011; Singh et al., 2011).

Nevertheless, many firms may not know how to implement BIM and deal with the

changes brought to their organizations (Zahrizan et al., 2013).

Page 165: building information modeling–based process transformation to improve productivity in the

145

5.3.1.1 Leavitt’s diamond model and its derivatives

Leavitt’ diamond model, also known as Leavitt’s system model, was developed as a

mechanism for analyzing the organization-wide effects when changes take place

(Leavitt, 1965). This model regards an organization as an interdependent system, and

identifies four interrelated major components, namely task, people, technology, and

structure (see Figure 5.1). The definitions of the four components are generic. Firstly,

“task” refers to what the organization tries to achieve and how things are being done

to get close to goals, which should be considered in a qualitative way. Secondly,

“people” refer to the staff of the organization who carry out the “task”. The

organization should not only look into the individuals’ roles and responsibilities, but

also their characteristics, such as skillsets, knowledge, and efficiency. Thirdly,

“structure” refers to the hierarchy, relationships, communication patterns, and

collaboration between different management levels, departments, and employees.

Last but not least, “technology” enables “people” to perform the “task”, such as

computers, equipment, working methods, and software applications.

People

Task

Structure Technology

Figure 5.1 Leavitt’s diamond model (Leavitt, 1965)

The “technology” applied now in the construction industry has evolved since 1965

when the diamond model was established. The younger generation is usually IT

savvy and more used to incorporate ICT into the project delivery process. While this

model served as the fundamental theory of organizational change in this study, the

digital technology would be described at the later paragraphs of this section.

Page 166: building information modeling–based process transformation to improve productivity in the

146

The organization can be thought of as maintaining a balance of the four areas. It is

crucial to understand the connection between the four components to successfully

implement an integrated change. One common mistake when preparing an

organization for a change initiative is to treat the initiative in isolation from the rest of

the organization. This is because it is almost impossible to implement a change

strategy without considering its impact on other processes, departments, or

individuals. Hence when a change happens in any one of the four areas it affects the

entire system. A changed technology will necessarily affect the people involved in it,

the structure in which they work, and the task they perform. Similarly, changes to

task, structure, and people will have similar knock-on effects. Thus, Leavitt’s theory

can be helpful to firms that plan to apply new technology to the workplace in a way

that lessens stress and encourages teamwork (Smith et al., 1992).

Leavitt and Bahrami (1988) further developed the diamond model to emphasize the

inter-relationships between these components: (1) people issues, including

motivation, skill, and rewards; (2) business structure, including processes,

organization, and job definition; (3) control mechanisms, including performance

indicators and management information; and (4) technology, including operational

systems and information delivery.

The model has been widely recognized and applied in previous studies in novel and

critical ways. Smith et al. (1992) used the diamond model to assess how

organizational change had been managed in the Management Information Center of

the British Institute of Management over a 10-year period. This result showed that it

was not satisfactory to manage change reactively nor to attempt to manage a flatter

structure in the same way as a multi-layered structure.

Page 167: building information modeling–based process transformation to improve productivity in the

147

By drawing on the notions of objective and subjective realities from the arena of

sociology of knowledge, Sarker (2000) further developed the diamond model (see

Figure 5.2) and used it as a frame for informing the implementation of code-

generators. Broad guidelines were formulated for managing the implementation of

“interpretively flexible” information technologies in four steps: (1) self-understanding

through self-reflection; (2) identifying and understanding all important stakeholder

groups; (3) identifying the stakeholders who may resist; and (4) modifying the

objective or subjective realities as appropriate.

Structure

(e.g. power,

influence)

Tasks

(e.g. important,

satisfying)

People

(e.g. qualified,

useless)

Technology

(e.g. facilitating

communication

Structure

(e.g. organization

charts)

Tasks

(e.g. typing,

programming)

People

(e.g. manager,

programmer)

Technology

(e.g. mainframe,

code generator)

C

U

L

T

U

R

E

The Domain of Subjective Reality The Domain of Objective Reality

Figure 5.2 An enhanced diamond model (Sarker, 2000)

Hoff and Scheele (2014) argued that Leavitt’s diamond model did not explain how

the four components are interrelated, other than by stating that everything affects

everything else. Wigand (2007) examined the impact of IT (e-mail) on structure,

people, and tasks, as well as the interaction of these components with other

organizational factors and external forces. An organizational interaction diamond

model was established, as shown in Figure 5.3, which was built on the studies of

Chandler (1962), Leavitt and Bahrami (1988), and Scott Morton (1991). The

interaction model illustrated how an organization redesigns itself by concentrating on

management processes, structure, strategies, people, and tasks, to meet the demands

of external forces (such as new technology and changing market). This said study

Page 168: building information modeling–based process transformation to improve productivity in the

148

found that IT efforts would be opportunities to create new ways of working by

redesigning the tasks, changing the roles of the individuals, and spanning

organizational boundaries.

Figure 5.3 An organizational interaction diamond model (Wigand, 2007)

Chang et al. (2009) identified 21 critical factors for mobile commerce adoption and

arranged the factors into a model which incorporated the four components in

Leavitt’s diamond model. The results revealed that the majority of the top 10 critical

success factors could be categorized as “technology” and “task” areas. Meanwhile, it

was found that the support capabilities of IT vendor, senior management support, and

capabilities of the project team were the top three factors for the mobile commerce

adoption. Similarly, Ranjbari (2013) studied 69 factors that would affect the

implementation of information management systems and further divided these factors

into 29 factors which could be linked to different aspects of Leavitt’s diamond model.

This formed the foundation for the integrated multi-perspective framework of

implementing information management systems.

Page 169: building information modeling–based process transformation to improve productivity in the

149

Wilfling and Baumoel (2011) argued that although models and methods for managing

change have been widely adopted, business change projects were not always as

successful as intended. One possible reason was the missing integration of the

cultural and emotional aspects of change in the models. This said study developed an

advanced enterprise architecture model by extending the existing meta model of

enterprise architecture with the core artifact “cultural and emotional specification”.

The organizational diamond model established by Leavitt and Bahrami (1988) served

as the primary construct and conceptual base. This advanced model not only

represented a strategic and organizational as well as IT view on the structures of the

information system, but also offered a cultural and emotional view by characterizing

the organizational culture and people’s behavior. Thus, the comprehensive and

advanced model provided a holistic understanding of the change projects and thereby

filled the gaps between strategy, processes, and IT.

Dahlberg et al. (2016) argued that the four basic components in Leavitt’s diamond

model articulated the basis of component interrelations, but the factors were generic

and lacked contemporary constructs. This is because new constructs such as business

models, corporate governance, and IT became established after the time Leavitt’s

diamond model was built. This previous study then modified the wording of some

factors in the theory by: (1) replacing “technology” with “technology, IT services,

and information”; (2) modifying “structure” into “strategy, business model, and

governance”; and (3) replacing “task” into “tasks and processes”, as shown in Figure

5.4. It should be noted that such modifications were regarded as updates of Leavitt’s

theory to reflect contemporary constructs, not as changes to the logic of the original

theory. Dahlberg et al. (2016) remarkably applied the modified diamond model to

investigate the determinants of chief information officers (CIOs)’ roles and tasks in

an organizational context. It was found that the factors of the modified model could

be used to understand, describe, and/or classify the findings of both evolutionary and

Page 170: building information modeling–based process transformation to improve productivity in the

150

CIO role studies. For example, Weill and Woerner (2013) proposed four roles

(embedded, IT services, external people, and enterprise process) for CIOs based on

how they allocated their time between various tasks, and found that the “strategy,

business model, and governance” component appeared as the main determinant for

the embedded CIO’s role because the biggest part of their time was allocated to the

tasks related to this component. In the meantime, the modified diamond model was

also validated through interviews with 36 CIOs within six industries covering the

time period from 1960s to present times. All the components had significant effect on

the CIOs’ roles and tasks. This provided a clear indication that the modification of

Leavitt’ diamond model was a useful description of the factors that defined CIOs’

role and tasks at any particular time in any specific organization, and showed how

those tasks changed.

Strategy, business model, governance

Tasks, processesTechnology,

IT services, information

People

Figure 5.4 A modified Leavitt’s system model (Dahlberg et al., 2016)

5.3.1.2 MIT90s framework

It was predicted that the advent of computer and management science would

significantly change the structure and processes of most corporations. Chandler

(1962) found that changes in an organization’s structure followed changes in the

firm’s strategy and that the organizational structure often had to be modified

continuously until it was effective in supporting the firm’s strategy. By incorporating

this finding, Rockart and Scott Morton (1984) constructed a conceptual model to help

people understand the impact of adopting new technologies on their organizations

(see Figure 5.5). The conceptual model of technology impact particularized Leavitt’s

Page 171: building information modeling–based process transformation to improve productivity in the

151

diamond model by: (1) changing its generic “task” into the broader concept of “the

organization’s strategy”. This would not violate to Leavitt’s model, because

“strategy” represents a summing of the organization’s tasks; (2) adding “corporate

culture” to expand organization structure; (3) adding a box for “management

processes”, such as plans creation, meetings, discussions, and evaluations; and (4)

adding two driving forces in the external environment which were separated from the

four boxes characterizing the organization with a permeable membrane. This

membrane allowed the five internal elements to be exposed to the external driving

forces. “Management processes” was placed in the middle because it was seen as part

of the glue that holds the organization together. As shown in Figure 5.5, the external

socioeconomic environment and the newly-developed technology are two principal

driving forces external to the organization, which put the internal elements (its

technology, strategy, processes, people, and structure) into motion. Consequently, the

change in any of the internal elements required equilibrating changes in other

elements to maintain the balance required for the organization to be effective, such as

the changed relationships and communication patterns among the individuals. Thus, it

is crucial to find the link between strategic ideas and the implementation of new

technologies.

Organization structure and the corporate culture

The organization’s strategy

Technology

Individuals and roles

Management processes

Externalsocio-economic

environment

External technological environment

Figure 5.5 A conceptual model of technology impact (Rockart and Scott Morton,

1984)

In addition, this conceptual model paved the way for the development of MIT90s

framework (see Figure 5.6). This framework was designed to encourage

Page 172: building information modeling–based process transformation to improve productivity in the

152

organizations to understand the dynamics of transformation when acquiring new

technologies (Scott Morton, 1991). It helped the managers of educational

organizations to understand the impact that ICT would have on institutional missions,

organizational structures, and operating practices. This framework assumed that an

institution’s effectiveness in using ICT for teaching and learning was a function of six

inter-related elements: external environment, structure, strategy, management

processes, technology, and individuals and roles. Other assumptions included: (1)

managing change was about taking heed of the interaction of the six elements and

their configurations rather than just about managing the elements themselves; (2) the

fit between internal configuration and the external environment was important; and

(3) cultural issues mediated the strategy-technology relationship. The major

difference between the aforementioned conceptual model of technology impact and

the MIT90s framework is the scope of organizational culture. The former regarded

organizational culture as a very important dimension of organizational structure

(Schein, 1982), while the latter recognized organizational culture as an integral part

of the organization, including organizational structure, management processes, and

individuals and roles.

Structure

Strategy Technology

Individuals and roles

Management processes

Externalsocio-economic

environment

External technological environment

CultureOrganizational

border

Figure 5.6 MIT90s framework (Scott Morton, 1991)

Page 173: building information modeling–based process transformation to improve productivity in the

153

Mistry (2008) applied the MIT90s framework to benchmark e-learning as a separate

entity to more conventional learning and teaching practices. A total of 21 e-learning

themes were identified and then fitted into the six elements of the framework. This

encouraged the institutions to understand the evolutionary and revolutionary

transformation from conventional learning and teaching practices to e-learning

practices, and evaluate the acquisition of e-learning tool-kits over a period of six

months.

Despite the fact that the MIT90s framework was developed for individual enterprise

contexts, researchers have justified its application in the cross-enterprise

environment. In particular, Verdecho et al. (2012) conceptualized the collaborative

inter-enterprise context in the renewable energy sector as an organization that pursues

common objectives. This previous study adapted the main blocks of the MIT90s

framework to propose a conceptual framework of collaboration (see Figure 5.7). This

framework classified the factors that influenced the cross-enterprise collaboration into

four groups: strategy, business processes and infrastructure, organizational structure,

and culture. It should be noted that the strategic factors were in an upper level

because strategic aspects (such as the need of being competitive) could drive the

collaboration among enterprises. The collaboration pyramid in Figure 5.7 indicated

that in order for the collaboration to be effective and sustainable in the cross-

enterprise environment, it was necessary to manage and balance the four groups of

factors. In addition, the application of this collaboration framework was validated

through a case study in a project in the renewable energy sector. Most of the primary

project participants, namely raw material suppliers, sub-assembly suppliers,

engineering enterprise, and promoter enterprise, worked within different business

sectors. The application was performed at photovoltaic solar energy business unit

dedicated to the design, construction, operation, and maintenance of photovoltaic

solar energy plants. This application substantiated the argument that the

Page 174: building information modeling–based process transformation to improve productivity in the

154

establishments of intra- and inter-organizational technology deployment are similar

(Croteau and Bergeron, 2009; De Haes et al., 2012).

· Process alignment· IS/ICTs interoperability· Complementary skills· Coordination between activities

· Collaboration leadership· Compatibility of management styles· Joint decision-making· Multidisciplinary teams

· Trust· Commitment· Cooperation· Information shared· Conflict management

· Joint vision· Design of the inter-enterprise

supply chain/network· Equity· Top management support

Business processes

and infrastructure

Organizational

structure

Culture

Balance

Collaboration

Strategy

Figure 5.7 Conceptual framework of collaboration adapted from MIT90s framework

(Verdecho et al., 2012)

5.3.2 A proposed organizational change framework for building projects

Leavitt’s organization model was also applied in construction management studies.

For example, Kasimu et al. (2012) adapted the model’s four interrelated factors to

outline key variables in the development of a knowledge management

implementation framework to create, capture, acquire, update, transfer, store, share,

and use knowledge in construction firms. It was found that successful implementation

of this framework would rely on the commitment, attitude, behaviors, dedication, and

personal interest of the top management or knowledge experts in the construction

firms.

Although Leavitt’s model and the MIT90s framework have been applied to study the

effects of the changes within individual organizations, little is known about the

Page 175: building information modeling–based process transformation to improve productivity in the

155

changes to inter-organization contexts when implementing BIM other than the

traditional CAD. The building project context in the construction industry is also

representative in a cross-enterprise environment. A building project team that

implements BIM is a collaborative inter-enterprise environment, which can be seen as

a large project organization in which the project participants (business units)

collectively work to achieve common project goals within constraints (Verdecho et

al., 2012). Thus, BIM implementation in building projects is justified as an

organizational change (Azhar et al., 2014), because individual participants may be

entrenched in the traditional drafting practices or in fragmented BIM adoption, and

need to adapt to a new project delivery process using BIM.

Lyytinen and Newman (2008) stated that Leavitt’s model’s four-factor classification

was good because it is simple, extensive, and sufficiently well defined. If needed, it

can be easily extended with other categories to obtain richer vocabulary. For

example, Kwon and Zmud (1987) augmented the model with the concept of an

environment; while other studies had included also culture (Davis et al., 1992).

This study proposed an organizational change framework for managing the

transformation towards full BIM implementation in the Singapore construction

industry (see Table 5.3). The four-component classification was structured by

adapting the main blocks of the aforementioned models and frameworks, and a total

of 11 organizational change factors and 29 change attributes have been established

based on the literature review analyzing 20 previous studies. The conceptual

constructs were interpreted in the subsequent sections.

Page 176: building information modeling–based process transformation to improve productivity in the

156

Table 5.3 Proposed organizational change framework for building projects implementing BIM

Components Factors Attributes Code References

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

People Inter-enterprise

structure

Contractual relationship PeS1 √ √ √

Leadership PeS2 √ √ √ √ √

Reward arrangement PeS3 √ √ √

Involvement PeS4 √ √ √ √

Risk allocation PeS5 √ √

Conflict management PeS6 √ √ √ √

Corporate

culture

Sharing PeC1 √ √ √ √ √ √

Willingness to change PeC2 √ √ √ √

Commitment on new ways PeC3 √ √ √ √ √

Trust and transparency PeC4 √ √ √

Individuals and

roles

Mindset and attitude PeI1 √ √ √ √ √ √

Knowledge, skills and experience PeI2 √ √ √ √ √ √

Training and education PeI3 √ √ √ √

Process Management

processes

Communication PrM1 √ √ √ √ √ √ √ √

Controlling and decision-making PrM2 √ √ √ √ √ √

Corporate

strategy

Goals and requirements setting PrS1 √ √ √

Vision and mission PrS2 √ √ √ √ √ √

Top management support PrS3 √ √ √

Processes alignment PrS4 √ √ √

Task Coordination and simulation PrT1 √ √ √ √

Documentation PrT2 √ √ √

Production PrT3 √ √ √

Model management PrT4 √ √ √

Technology Infrastructure Hardware and software solutions TI √ √ √ √ √ √ √

Data exchange Interoperability TD √ √ √ √ √ √

Construction

method

Prefabrication TC √ √

External

environment

Socioeconomic

environment

Policy ES1 √ √ √ √

Changing market ES2 √ √

Technological

environment

New technological solutions ET √ √ √ √

Page 177: building information modeling–based process transformation to improve productivity in the

157

Note: (1) Alshaher (2013); (2) Bikson and Eveland (1990); (3) Bobbitt and Behling (1981); (4) Croteau and Bergeron (2009); (5) Dahlberg et

al. (2016); (6) Dahlberg (2016); (7) Higgins (2005); (8) Juan et al. (2017); (9) Kasimu et al. (2012); (10) Lyytinen and Newman (2008); (11)

Mitchell (2013); (12) Oraee et al. (2017); (13) Price and Chahal (2006); (14) Rockart and Scott Morton (1984); (15) Sarker (2000); (16)

Smith et al. (1992); (17) Teo and Heng (2007); (18) Verdecho et al. (2012); (19) Wigand (2007); (20) Wilfling and Baumoel (2011). √

indicates the inclusion of the specific change attribute in the corresponding reference.

Page 178: building information modeling–based process transformation to improve productivity in the

158

5.3.2.1 People

In this component, a total of 13 organizational change attributes pertaining to three

people-related factors (inter-enterprise structure, corporate culture, and individuals

and roles) were identified. A project team that implements BIM is a relational system

of BIM-based network (Oraee et al., 2017). In particular, “inter-enterprise structure”

refers to the contractual structure, business model, and governance (Rockart and Scott

Morton, 1984; Scott Morton, 1991; Verdecho et al., 2012; Dahlberg et al., 2016) of

the collaborative project organization, which defines the authorities, roles,

responsibilities, tasks, and business interests of the team members (Verdecho et al.,

2012). The inter-enterprise network relies on the collaboration between the team

members. Accordingly, five attributes, namely contractual relationship (PeS1),

reward arrangement (PeS3), stakeholder involvement (PeS4), risk allocation (PeS5),

and conflict management (PeS6) should be included in this factor (see Table 5.3). The

project team is a hierarchical structure, in which the leadership (PeS2) team and

personnel should be in place to make final decisions when problems occur. Besides,

“corporate culture” (Rockart and Scott Morton, 1984; Scott Morton, 1991; Verdecho

et al., 2012) describes the values and beliefs that provide rules of behavior (Smircich,

1983) of the individual project participants. Verdecho et al. (2012) found that

information sharing (PeC1), executive commitment (PeC3), and trust (PeC4) in other

stakeholders could facilitate the inter-enterprise collaboration in the project team, and

therefore these attributes should be comprised in the cultural factor. Willingness to

change (PeC2) should also be included in this factor as it directly influences the

behaviors of the stakeholders (Teo and Heng, 2007), such as to implement BIM alone

or share models with others. In addition, “individuals and roles” (Rockart and Scott

Morton, 1984; Scott Morton, 1991; Wigand, 2007) characterizes the thinking,

attitudes, and competencies of the employees. Thus, the mindset and personal

attitudes (PeI1) as well as the knowledge and skills (PeI2) of the individuals should

Page 179: building information modeling–based process transformation to improve productivity in the

159

be coved in this factor. Since the individuals tend to lack sufficient knowledge of the

new way of working, it is reasonable to also take account in training and education

(PeI3) to provide technology support (Juan et al., 2017).

5.3.2.2 Process

In this component, a total of 10 organizational change attributes were established,

which were associated with three organizational change factors, namely management

processes, corporate strategy, and tasks. Process refers to various work practices with

or without BIM uses to convert resources into products and services in the project

lifecycle. As part of it, the “management processes” (Rockart and Scott Morton,

1984; Scott Morton, 1991) is considered as an important factor, which describes the

communication (such as meetings and discussions) among the stakeholders, and the

collective decision-making process in the building project context. Thus,

communication (PrM1) and controlling/decision-making (PrM2) should be included

in the attributes of this factor. Meanwhile, the “task” in Leavitt’s model was updated

with “tasks and processes” (Dahlberg et al., 2016) to reflect the contemporary

constructs, without changing the model’s logic. This categorized the “task” (Leavitt,

1965) into the process component to represent the characteristics of routine work

(BIM activities to be completed) for adequate process development, such as

coordinating models of specific disciplines (PrT1), providing feedbacks, documenting

design and construction intent (PrT2), producing drawings and building elements

(PrT3), and managing and updating models (PrT4). More importantly, the “task” in

Leavitt’s model was replaced by the organizational strategy which represents a

summing of an organization’ tasks. In this study, “corporate strategy” (Rockart and

Scott Morton, 1984; Scott Morton, 1991; Dahlberg et al., 2016) was proposed to

represent the stakeholders’ strategic tasks in the higher level. This factor provides a

common understanding of what needs to be achieved and how to achieve the goals,

Page 180: building information modeling–based process transformation to improve productivity in the

160

identifies each party’s role, and formalizes the commitment of the executive

management (Verdecho et al., 2012). Thus, four attributes, namely goals and

requirements setting (PrS1), vision and mission (PrS2), top management support

(PrS3), and process alignment (PrS4) should be taken into consideration in this factor.

5.3.2.3 Technology

This component consisted of three technology-related factors (infrastructure, data

exchange, and construction method) in the proposed organizational change

framework. BIM-related technologies, which have been counted among the most

critical IT innovations worldwide (Juan et al., 2017), can be seen as evolutionary and

revolutionary changes to the IT, ICT, and CAD that have been widely established and

adopted in the literature. “Infrastructure” includes powerful hardware and software

and external applications (TI). “Data exchange” provides necessary support to

execute all kinds of tasks and management processes. Thus, the “interoperability”

(TD) between disparate disciplines, models, applications, and management systems

should be ensured. In the meantime, “construction method” is a critical determinant

of productivity performance. Off-site fabrication and on-site installation (TC) has

been recognized to reduce waste and improve productivity in projects and studies

(Blismas and Wakefield, 2009), which can be facilitated by advancing technologies.

The technology component (Rockart and Scott Morton, 1984; Leavitt and Bahrami

1988; Scott Morton, 1991; Wigand, 2007; Dahlberg et al., 2016) in the proposed

organizational change framework does not change its function and logic in Leavitt’s

model and the MIT90s framework. This is because the BIM-related tools, with

emphasis on information exchange, are more advanced than ever and reflect the

contemporary situation.

Page 181: building information modeling–based process transformation to improve productivity in the

161

5.3.2.4 External environment

The external environment component describes the external driving forces that may

put the internal components of the project organization into motion, including

external socioeconomic and technological environments. The motion would result in

changes to the internal factors until a new balance is established. The inter-enterprise

context, therefore, needs to change or redesign itself by focusing on the

abovementioned people, process, and technology components to meet the demands of

the external forces (Wigand, 2007). In terms of “socioeconomic environment”, policy

(ES1) and changing market (ES2) are regarded as two impactful external forces in

this study. This is because changes in these two aspects would have a more important

role in a city-state (Singapore) than in a big country (Guo, 2006). The national

standards and legislations were formulated rapidly in Singapore (Cheng and Lu,

2015; Juan et al., 2017), which all the local project teams must comply with. In

addition, technologies related to BIM have been constantly improving; more powerful

hardware and a wide range of software and external applications become available to

choose from. Thus, the attribute “new technological solutions” (ET) is coved in the

“technological environment” factor. It should be noted that the external forces are

regarded more as change triggers to the internal components, rather than changes

occurred in the project organizations.

The proposed four-component classification (see Table 5.3) echoes sentiments in

previous studies conducted in Singapore (Teo and Heng, 2007; Teo, 2008) which

focused on deploying automated QTO system in terms of people, process, and

technology in the local construction industry. Therefore, it is believed that the

proposed organizational change framework expands the global body of knowledge

related to organizational change and BIM implementation, and can be appropriately

used in the Singapore construction industry.

Page 182: building information modeling–based process transformation to improve productivity in the

162

Based on the literature review, this research found that the 29 attributes of the

proposed organizational change framework were able to interpret the hindrances to

change and the drivers for change towards full BIM implementation identified in

Section 5.2. The detailed interpretations would be presented in Section 7.3.4.

5.3.3 Conceptual model

This section presents the derivation of the conceptual model of this study. This study

aims to develop the BBPT model that can propose managerial strategies for building

projects to move from the current project delivery approach towards higher levels of

BIM implementation, and thus improve their productivity performance. The key of

this BBPT model is the four-component (people, process, technology, and external

environment) structure, which is consistent with the proposed organizational change

framework. The model would be developed based on the assumption that BIM

implementation in the building project context can be conceptualized as a big

organization, which has been justified (Croteau and Bergeron, 2009; De Haes et al.,

2012; Verdecho et al., 2012). Since the main blocks of the proposed framework

(people, process, technology, and external environment) consist of a number of

attributes that can guide the industry to change, the proposed organizational change

framework (see Table 5.3) forms a foundation of the BBPT model and therefore can

theoretically serve as the conceptual model for process transformation in this study.

5.4 Summary

In this chapter, 47 hindrances to change and 32 drivers for change towards full BIM

implementation were identified. Based on the existing theories of organizational

change, an organizational change framework for building projects using BIM was

proposed, which consists of 29 change attributes on people, process, technology, and

Page 183: building information modeling–based process transformation to improve productivity in the

163

external environment aspects. Since the main blocks (people, process, technology,

and external environment) are four key areas that need to be changed in BIM

implementation and process transformation, this framework can also serve as the

theoretical model for the BBPT model.

Page 184: building information modeling–based process transformation to improve productivity in the

164

Chapter 6: Research Methodology

6.1 Introduction

This chapter aims to address research design, methods of data collection, and

methods of data analysis in this research. It is recommended that combining multiple

methods be used in the research field of project management, because this approach

can overcome some inherent limitations of using a single method and facilitate a

comprehensive understanding of a given project management research phenomenon

(Love et al., 2002). Besides, although combining both qualitative and quantitative

approaches may need more time, money, and energy, it has been suggested to be used

in the research design and data collection due to its greater utility (Tashakkori and

Teddlie, 1998; Abowitz and Toole, 2010).

Figure 6.1 illustrates the overall research methodology in this study. The literature on

project delivery processes with different levels of BIM implementation (see Chapter

three), potential factors affecting BIM implementation, and theories of organizational

change (see Chapter five) were reviewed. Based on the literature review, the

similarities and differences of these delivery processes were examined. By comparing

the industry practices in the current, partial BIM process with their counterparts in the

full BIM-enabled processes, plenty of NVA activities in the current process were

identified. Using these NVA activities as evaluation attributes, a fuzzy BIMIR model

was proposed (see Chapter four). With the data related to the frequency of occurrence

of these activities collected from the first survey (coded as Survey I), the BIMIR

statuses of building projects in Singapore were evaluated. The differences of resulting

wastes and leading causes in building projects with different BIMIR statuses were

examined. Follow-up interviews were conducted with the practitioners who originally

participated in Survey I. In addition, the theories of organizational change were

Page 185: building information modeling–based process transformation to improve productivity in the

165

reviewed and modified to propose an organizational change framework in Chapter

five. This framework is suited for studying process transformation in building

projects that plan to implement BIM. In addition, factors driving and hindering the

change towards full BIM implementation were identified from the literature review.

The data related to the significance of these factors were collected in the second

survey (coded as Survey II). Based on the interpretation of the hindrances and drivers

with the organizational change framework, managerial strategies were tailored to help

move towards higher BIMIR statuses.

Need for research: Suboptimal productivity performanceIncreasing recognition of BIM potential

Problem statement: Partial BIM implementation in current project delivery

Possible solution: Transforming current project delivery into full BIM-enabled delivery

Literature review

Construction industry

Potential wastes

Construction value chain

Productivity-related policies

Organizational readiness

Full BIM-based delivery:§ IPD/VDC/DfMA

Survey I

An in-depth understanding of full BIM implementationCase study

BBPT model

Managerial strategies for changing from current BIMIR status towards higher BIMIR statuses

Research scope:Building projects in Singapore

Leading causes for surveyed projects of different BIMIR

A fuzzy BIMIR evaluation model

Widely-agreedNVA activities

Frequency of occurrence of NVA activities

Questionnaires

Interviews

Proposed definition of four BIMIR statuses

Survey IIQuestionnaires

Interviews

NVA index scores

Analysis of past documents

Participant observations

Critical CHCs and CDCs

Wastes reduction between projects of various BIMIR

Organizational change theories:· Leavitt’s diamond theory· MIT90s framework

A proposed organizational change framework

NVA activities in current industry practices

Potential causes

Factors driving and hindering change towards full BIM use

Existing classifications of BIM implementation and BIM maturity

Productivity measurement

Technology adoption

BIMIR statuses

Significantly important causes

Conclusions and recommendations

BIM

Figure 6.1 Research methodology

Page 186: building information modeling–based process transformation to improve productivity in the

166

6.2 Research Design

The research design is to develop a plan for testing the hypotheses formulated in

Section 1.7. There are four common types of research designs, namely case studies,

surveys, experiments, and regression (Tan, 2012). Case studies are used to understand

or interpret particular instances with a small number of cases; surveys are used to

infer broad population characteristics, opinions, attitudes, or reasons for certain

actions or preferences from a sample; an experiment is used to test cause-effect

relationships by manipulating variables; a regression design is used to examine the

associations between variables when the above experimental design becomes

cumbersome.

6.2.1 Survey

As a systematic method of collecting data based on a sample, the survey technique

has been widely used to collect professional views on critical factors in previous

construction management studies (Teo et al., 2007; Zhao et al., 2013; Hwang et al.,

2017). This study involves to collect professional views on the NVA activities in the

current project delivery process in building projects in Singapore and their resulting

wastes and potential causes as well as the factors hindering and driving BIM

implementation. Hence, a survey would be conducted in this research.

Since the number of questions in the survey was large, this survey was arranged into

two parts which were coded as Survey I and Survey II (see Figure 6.1). The basic

purpose was to increase response rate and avoid any confusion or unwillingness of

potential respondents. Survey I was expected to collect the key stakeholders’ views

on the level of agreement on and the frequency of occurrence of the NVA activities

after BIM implementation had been mandated by the local government since July

2015, on the frequency of occurrence of the resulting wastes and their impact on

Page 187: building information modeling–based process transformation to improve productivity in the

167

productivity, and on the relative importance of the potential causes to the NVA

activities according to their past or ongoing building projects. These views could be

used to verify the NVA activities identified in the literature review, to examine the

severity of the resulting wastes on productivity, and to figure out more important

causes. Survey II was intended to gain a fundamental understanding of the critical

factors that had drove or hindered BIM implementation in their projects.

The population for this study was comprised of all the organizations in the Singapore

construction industry. Initially, the sampling frame consisted of 1318 organizations

that had registered in the government agencies or institutes at the time of this

research, including the BCA, the URA, the Housing and Development Board (HDB),

the building developers registered with the Real Estate Developers’ Association of

Singapore, the architectural consultancy firms registered with the Singapore Institute

of Architects, the structural and MEP consultancy firms registered with the

Association of Consulting Engineers Singapore, the larger contractors registered with

the BCA, and the facility management firms registered with the Association of

Property and Facility Managers. Among the contractors, it is considered logical to

select only the larger ones because they tend to have adequate resources for BIM

implementation. The registered contractors were classified into two categories based

on their businesses: construction workheads and specialist workheads. The tendering

limits for the contractors with different financial grades in both workheads were

presented in Table 6.1. Previous studies (Zhao et al., 2014b, 2015) that had surveyed

the construction firms in Singapore considered A1, A2, Single grade, and L6

contractors as large firms, and others as SMEs. Meanwhile, another study (Teo et al.,

2007) classified A2–C3 contractors as SMEs recommended by SPRING Singapore.

In this study, the contractors of B2 and L5 grades and below were excluded in the

sample frame, while B1 contractors were included because their tendering limits are

large and about three times as large as those of B2 and L5 contractors. The

Page 188: building information modeling–based process transformation to improve productivity in the

168

contractors with multiple financial grades were calculated according to their highest

tendering limits, rather than being calculated repeatedly. In addition, the larger

construction firms of a few workheads that are not related to BIM (such as SY01b,

SY02, and SY10) were also excluded. Hence, a total of 570 registered contractors

were obtained in the survey.

Table 6.1 Tendering limits of contractors registration system (S$ million)

Time

Period

Construction Workheads

(CW01 and CW02)

Specialist Workheads

(CR, ME, MW, and SY)

A1 A2 B1 B2 C1 C2 C3 Single

grade L6 L5 L4 L3 L2 L1

1 July

2015-30

June 2016

unlimited 90 42 14 4.2 1.4 0.7 unlimited unlimited 14 7 4.2 1.4 0.7

1 July

2016-30

June 2017

unlimited 85 40 13 4 1.3 0.65 unlimited unlimited 13 6.5 4 1.3 0.65

Note: CW01=General building; CW02=Civil engineering.

Source: BCA (2017b) https://www.bca.gov.sg/ContractorsRegistry/contractors_tend

ering_limits.html.

Since the survey was arranged in two stages. The 1318 organizations were equally

and randomly divided in all the disciplines into two sub-sampling frames for the two

surveys. To logically link Survey I and Survey II, a question was added at the end of

Survey I, asking if the potential respondents would be willing to participate in the

next stage (Survey II) of this study. Thus, after the first half (659) of these

organizations was selected for Survey I, the rest 659 organizations, along with the

organizations that had been involved in Survey I and were willing to participate in

Survey II, were obtained for Survey II. This was deemed as appropriate for the

distribution of the potential respondents. Since there were sampling frames,

probability samples should be adopted. There are four common types of probability

sampling, including simple sampling, systematic sampling, stratified sampling, and

cluster sampling. Simple random sampling was used in the data collection because

each organization was as likely to be drawn as the others.

Page 189: building information modeling–based process transformation to improve productivity in the

169

According to Gao and Fischer (2006), BIM implementation usually follows two kinds

of strategies, namely top-down approach (from company-wide research and

development to project-based use of BIM models) and bottom-up approach (from

project-based use of BIM models to company-wide research and development). The

former should be prioritized since corporate vision and executive leadership are

crucial (Autodesk, 2012). Hence, the senior management from the sampled

organizations would be first contacted prior to the middle management. On the other

hand, BIM is ultimately driven and successfully implemented through efforts on the

“shop floor” by the individuals. They apply BIM in their day-to-day execution of

projects. Therefore, some experienced staff who were not at the management level,

such as site experts, would also be approached.

6.2.2 Case study

According to Yin (2014), a case study is an empirical inquiry that investigates a

contemporary phenomenon in depth and within its real-life context. It may lead to

new and creative insights, development of new theories, and have high validity with

practitioners (Voss et al., 2002). Yin (2014) suggested that case studies focus on

questions about “what, why, and how”. Because this study attempted to investigate

how BIM could be incorporated into the project delivery processes to transform the

current industry practices and thus assist in productivity improvement in Singapore, a

case study would be adopted.

The case study intended to provide an in-depth understanding of how a specific

building project in Singapore actually moved from the current delivery process to a

more collaborative or integrated one, and of what the result was in terms of

productivity growth. It could be best understood by working backwards. The

implementation of managerial strategies for strengthening the drivers for change and

Page 190: building information modeling–based process transformation to improve productivity in the

170

overcoming the hindrances to change were tracked, which resulted in changes in the

BIM implementation activities contributed by the key stakeholders in the project

lifecycle. Once the implementation activities had been changed, the potential wastes

might be reduced, achieving productivity improvement.

Voss et al. (2002) recommended that for a given set of available resources, the fewer

the case studies, the greater the opportunity for in-depth observations. In this study,

given the resource limitation, one case study was conducted in a large construction

and development firm operating in Singapore, which had been delivering many

building projects simultaneously. One of the projects of higher BIMIR status was

selected, which would be compared with one of the typical projects of relatively

lower BIMIR status in this firm. Since firms are usually participating in more than

one project at a time, it is expected that the findings in this case study could be

generalized to other firms. The investment in BIM implementation is meant to

enhance the capabilities of a firm in the process transformation. Thus, the

generalization was justified.

6.3 Methods of Data Collection

In this study, questionnaires, interviews, observations, and analysis of past documents

were used to collect both qualitative and quantitative data. No single method of data

collection is ideal and using a combination of methods has been highly recommended

(Abowitz and Toole, 2010).

6.3.1 Questionnaires and interviews

Among various methods of data collection, questionnaire has been recognized as the

most cost-effective and popular way to collect information (Gravetter and Forzano,

Page 191: building information modeling–based process transformation to improve productivity in the

171

2012). Questionnaires and interviews have been widely used by researchers in

previous studies related to BIM implementation (Arayici et al., 2011; Khosrowshahi

and Arayici, 2012; Wong et al., 2014). Thus, questionnaires and personal interviews

were designed to collect data in this research. Terminologies used were explained in

the questionnaires to ensure that the potential respondents were clear about the

questions.

Two preliminary questionnaires were developed based on the literature review.

Specifically, the causes identified in Section 4.2.3 may be merged in the preliminary

questionnaire if they had similar statements. The causes in the “Architect” group and

“Engineers” group were merged into the “Architect/Engineers” group, and so did

those in the “General contractor” group and “Key trade contractors” group. The

questionnaires were revised based on the comments from five BIM experts who

participated in a pilot study. Interviews were conducted with these experts in the pilot

study to solicit their comments on the readability, accuracy, and comprehensiveness

of the questionnaires. The profile of the experts could be found in Table 6.2. All the

experts, who were from large firms and had at least three years’ experience of

implementing BIM in building projects in Singapore, were selected out of

convenience to pretest the questionnaires. Three of them were project manager,

corporate BIM manager, and technical manager of large construction and

development firms with over 10 years’ experience in this field; the other two included

one quantity surveying in charge from a general construction firm and one senior

architectural associate from a large architectural consultancy firm, with more than

five years’ work experience. Based on their comments, new NVA activities, wastes,

causes, drivers for change, and hindrances to change were added to the questionnaires.

For example, “the general contractor’s BIM team does modeling but not coordination

for trade contractors” and “the general contractor requires but does not train the trade

contractors to use BIM” were added as two new causes for “general contractor”;

Page 192: building information modeling–based process transformation to improve productivity in the

172

while two new causes (“high cost to engage BIM experts or outsource to BIM

drafters” and “the trade contractors use CAD and cannot integrate BIM models from

the general contractor to their site models”) were added for “key trade contractors”.

In addition, revisions were made to improve the readability and accuracy of the

statements of these items. Footnotes were added to explain the terminologies used.

Table 6.2 Summary of the interviews in the pilot study

Method BIM

expert

Work

experience

Designation Firm Duration

time

Face to

face

E1 16-20 years Project manager Construction and

development

1 hour

E2 16-20 years Technical manager Construction and

development

E3 11-15 years Corporate BIM

manager

Construction and

development

E4 5-10 years Quantity surveying

in charge

General

construction firm

1 hour

Over

telephone

E5 5-10 years Senior architectural

associate

Architectural

consultancy firm

25

minutes

The questionnaires were sent to the organizations in the respective sub-sampling

frames through emails or handed to them personally. The final questionnaire of

Survey I included five sections (see Appendix 1). The first section presented the

research objectives and the author’s contact details in a brief introductory letter. The

second section solicited the profile of the respondents and their organizations, such as

their affiliations, working experience, main businesses, and project characteristics. In

the third section, the NVA activities were listed. Because these activities were

collected from the literature, their validity of being NVA should be checked. The

respondents were requested to rate the level of agreement and the frequency of

occurrence of the NVA activities according to one of their past or ongoing building

projects, using two five-point Likert scales (1 = strongly disagree, 2 = disagree, 3 =

unsure, 4 = agree, and 5 = strongly agree; 1 = never, 2 = rarely, 3 = sometimes, 4 =

often, and 5 = always). The measurement of the level of agreement was believed to be

reliable because the Likert scale system has been deemed effective in measuring the

Page 193: building information modeling–based process transformation to improve productivity in the

173

attitudes of the respondents (Albaum, 1997). In addition, open-ended questions were

also presented to invite the respondents to suggest other NVA activities that they

deemed critical and reasonable. The fourth section asked the respondents to rate the

frequency of occurrence and the impact on productivity of the resulting wastes from

the abovementioned NVA activities in the same project mentioned in the third section.

Regarding the rating scale for the impact on productivity, 1 = insignificant effect, 2 =

minor detrimental effect, 3 = moderate detrimental effect, 4 = significant detrimental

effect, and 5 = catastrophic effect. The last section requested the respondents to rate

the importance of each potential cause in the same project, using another five-point

Likert scale (1 = not important, 2 = slightly important, 3 = moderately important, 4 =

very important, and 5 = extremely important). In this section, open-ended questions

were also presented to ask for suggesting other important causes. According to the

“seven plus or minus two” principle (Miller, 1956), the scale of five was adopted,

which is convenient for respondents to judge. The problem of poor response rate

could potentially be lessened by follow-up emails. As mentioned in Section 6.2.1, at

the end of this survey, the respondents were asked whether they were willing to be

involved in the next stage of this study.

After closing the questionnaire survey and data analysis, post-survey interviews were

conducted with four experts who had originally participated in this survey and

possessed BIM implementation experience in Singapore. In the interviews, the

experts were presented with the survey results to seek their comments. To gain an in-

depth understanding, they were also invited to provide possible explanations for the

NVA activities and their causes that were agreed upon as critical ones.

In Survey II, the final questionnaire consisted of four sections (see Appendix 2). The

relevant research objectives related to this survey and the author’s contact details

were presented in the beginning, followed by the questions to profile the respondents

Page 194: building information modeling–based process transformation to improve productivity in the

174

and their organizations. Next, the potential respondents were requested to rate the

significance of the 47 hindrances to change and 32 drivers for change towards full

BIM implementation, using a five-point Likert scale (1 = very insignificant, 2 =

insignificant, 3 = neutral, 4 = significant, and 5 = very significant). Similar to Survey

I, new respondents should make judgments based on the status quo in one of their

past or ongoing building projects. Those who participated in both surveys should

provide their answers with reference to the same projects they used in Survey I.

Lastly, new drivers or hindrances, which they deemed rational and significant, were

allowed to be added to complement the factors identified from the literature review.

Besides, five experts who were originally included in the data sample were

interviewed for their comments on relevant analysis results of Survey II. They were

also asked to provide possible explanations for the results.

In addition, having conducted the two surveys, face to face interviews were

performed with the management staff and a BIM coordinator from a large

construction and development firm based in Singapore in the case study. These

interviewees were working in a building project (Project A) and also had experience

in delivering another project (Project B) of a lower BIMIR status in the same firm.

During the interviews, after collecting the basic information related to the

interviewees, the projects, and the firm, open-ended questions were raised for the

interviewees. This allowed them to express what and how they changed their BIM

implementation activities in Project A, compared with those in Project B, other than

being constrained by a fixed set of possible responses.

Finally, after the BBPT model was developed, a total of six professionals from six

different building projects in Singapore were interviewed to validate the model. It

should be noted that these experts were not involved in the data collection of the two

Page 195: building information modeling–based process transformation to improve productivity in the

175

surveys mentioned in Section 6.2.1. The reason of using an even number of the

experts rather than an odd one was that this study would use statistics to test the

validity of the BIMIR evaluation model, instead of using a median response to ensure

reproducibility. During the validation process, these professionals were first requested

to estimate the NVAI scores and the BIMIR statuses of their building projects based

on their experience and judgments, and then rate the frequency of occurrence (or

implementation level) of the critical NVA activities according to the actual

circumstances of the projects (see Appendix 3). To improve the accuracy of the

estimation, the NVAI scores and the frequency of occurrence were assigned in the

form of percentage. Thus, there were at least two decimal places in the fractional part

of the scores. Then, to test the validity of the proposed fuzzy BIMIR evaluation

model in the BBPT model, the NVAI scores and BIMIR statuses estimated by the

experts were compared with those calculated by the BBPT model. In addition, the

experts were invited to comment on the BBPT model in terms of user-friendliness of

the model and the usefulness of the managerial strategies to help their leadership

teams make decisions to move towards higher BIMIR statuses.

6.3.2 Observations

In the case study, passive participant observations were conducted. The author sat in

weekly project meetings in the construction site office. Information related to the

behavioral patterns (such as body language, verbal expressions, meeting rules, data

exchange procedures, and communication patterns with others) of the key

stakeholders of Project A were recorded. The author also visited the construction site

at times to gain a knowledge of background factors, such as site layout and filed

staff’s feelings.

Page 196: building information modeling–based process transformation to improve productivity in the

176

6.3.3 Analysis of past documents

To gain a good understanding of the project and reduce observer bias, past documents

were collected and analyzed. The documents in Project A included their internal

documents (such as minutes of meetings of the weekly project meetings, construction

schedule, construction drawings produced from their building information models,

RFI documents and responses, and productivity figures), academic literature

regarding BIM adoption in the case firm projects, and media coverage. The internal

documents were collected by interpersonal networking, while the literature and media

coverage were available on the Internet. Analysis of past documents helped in the

conduct of the case study, which intended to understand how the case firm moved

from Project B towards the more productive Project A in terms of BIM

implementation.

6.4 Methods of Data Analysis

To begin with, Cronbach’s alpha coefficient was calculated to test the reliability and

internal consistency of the data collected from the surveys. The alpha coefficient

ranges from 0 to 1 and should exceed 0.7 for a scale to be reliable (Nunnally, 1978).

The threshold may decrease to 0.6 in exploratory research (Robinson et al., 1991)

Many studies have advocated that Likert scale data could be analyzed using

parametric statistical methods, such as t-test (Binder, 1984; Hwang et al., 2014).

Allan (1976) stated that the power and flexibility derived from parametric methods

can outweigh possible small biases. Allen and Seaman (2007) found that conclusions

and interpretations drawn from the parametric methods could be easier and more

informative. Thus, t-test was used to analyze the data in this study. Specifically, in

terms of the data collected in Survey I, one-sample t-test, which can test the null

hypothesis that the population mean (usually 3 in a five-point Likert scale) is equal to

Page 197: building information modeling–based process transformation to improve productivity in the

177

a specified value, was used to test whether all the NVA activities were significantly

agreed as critical NVA activities by the respondents and whether their potential

causes were significantly important.

In addition, the ranking technique was used. The NVA activities were ranked overall

and internally in each project phase according to the mean scores of the level of

agreement. These scores were also used to calculate the weights of the evaluation

criteria and sub-criteria, using equations 4.3 to 4.6. Likewise, the potential causes to

the NVA activities were also ranked overall and internally under each project role

according to their importance mean scores.

The surveyed building projects were classified into four groups by their BIMIR

statuses which were assessed based on the frequency of occurrence data, using

equations 4.7 to 4.12 and Table 4.5. To measure the mean score difference of the

resulting wastes and important causes between the four groups of building projects,

one-way analysis of variance (ANOVA) were performed. Moreover, to measure the

degree of agreement associated with the severity ranking of the wastes and the

importance ranking of the causes between the four groups of projects, Spearman’s

rank correlation coefficients were calculated and statistically tested. The Spearman’s

rank correlation computes the correlation between the rankings among multiple

groups, and has been widely used in project management research (Arain, 2005;

Hwang et al., 2009). A significance level of 0.05 (two-tailed) was used for this

analysis. The multi-group comparisons results were expected to reveal positive

changes as BIMIR status increased.

Likewise, as for the data related to the drivers for and hindrances to change towards

full BIM implementation that were collected in Survey II, the one-sample t-test was

also adopted to check whether these factors had statistically significant influence on

Page 198: building information modeling–based process transformation to improve productivity in the

178

BIM implementation in the Singapore constriction industry, and these factors were

ranked. Besides, independent-samples t-test was used to check whether there were

differences in the significance mean scores of the critical hindrances and drivers

between different groups of surveyed organizations. Regarding the responses of those

who completed both surveys, the one-way ANOVA and the Spearman’s rank

correlation were also applied to check the changes between the four groups of

building projects. The Statistical Package for the Social Sciences (SPSS) software

was used to conduct the quantitative data analysis for this study.

Furthermore, conversation analysis and content analysis were adopted to analyze the

data collected in the case study. The former could study the weekly project meetings,

and the latter dealt with the interviews data.

6.5 Summary

This study combined multiple methods in the research design, data collection, and

data analysis. Two surveys were conducted to validate the NVA activities and their

resulting wastes and potential causes as well as the factors affecting change towards

full BIM implementation in building projects in Singapore. The first questionnaire

was expected to obtain the data related to the level of agreement and frequency of

occurrence of the NVA activities, the frequency of occurrence and impact on

productivity of the wastes, and the importance of the causes. The second

questionnaire intended to obtain the significance of the hindrances to change and

drivers for change. Post-survey interviews were conducted to better understand the

survey results. In addition, a case study was performed in a large construction and

development firm to gain an in-depth understanding of its process transformation and

technology adoption. Moreover, professionals were contacted to validate the BBPT

model. Personal interviews, passive observations, and analysis of past documents

Page 199: building information modeling–based process transformation to improve productivity in the

179

were also used to collect data. A variety of statistical analysis methods would be used

to analyze the data.

Page 200: building information modeling–based process transformation to improve productivity in the

180

Chapter 7: Data Analysis and Discussions

7.1 Introduction

This chapter presents the analysis of the data collected from the two surveys. All the

five hypotheses are tested in this chapter. Among which, Hypotheses 1, 4, and 5 were

tested in a conventional way (inferential statistics), which involved tests of

significance (p-values) at the 0.05 level. Hypotheses 2 and 3 were tested in a new

way, which involved evaluation of BIMIR status using the proposed fuzzy BIMIR

model, and observation of surveyed building projects and their wastes in different

BIMIR statuses.

Specifically, Survey I received 73 completed responses from the AEC service

providers in Singapore. The analysis results indicated that 38 of the 44 NVA

activities identified from the literature review were validated by the respondents as

critical NVA activities. The six activities that were not significantly agreed by the

industry were excluded, with support from post-survey interviews. Using the data

related to the level of agreement of 38 critical NVA activities, the weighting of the

fuzzy BIMIR model was determined. The BIMIR statuses of the 73 surveyed building

projects were evaluated using the fuzzy BIMIR model. Among which, 15, 47, and 11

projects were in BIMIR S1, S2, and S3, while no projects were in BIMIR S4. Thus, it

was observed that Hypothesis 2 that “the BIMIR statuses of building projects in

Singapore are low” was supported (see Section 7.2.3.2). Five tests that randomly

excluded 3 responses suggested that this model was stable and thus could be used to

predict the BIMIR status of any other building project in similar contexts. Besides,

the criticality of the 13 wastes was analyzed. The mean scores and rankings of the

wastes in project groups of different BIMIR statuses were checked. It was found that

as BIMIR increased, productivity was less influenced by the 13 wastes. Therefore, it

Page 201: building information modeling–based process transformation to improve productivity in the

181

was observed that Hypothesis 3 that “the higher the BIMIR status, the lower the

criticality of the wastes and the higher the productivity performance” was also

supported (see Section 7.2.4.2). Moreover, all the 53 causes to the NVA activities

were found to be significantly important. Similarly, the mean scores and rankings of

the causes among the projects of various BIMIR statuses were also tested.

Survey II was completed with 89 data sets collected from practitioners in the

Singapore construction industry. The analysis results suggested that 44 out of the 47

hindrances and 31 out of the 32 drivers had significant influence on the overall lonely

BIM implementation in Singapore. In addition, these significant factors were

interpreted with the proposed organizational change framework. Accordingly,

managerial strategies were formulated on people, process, technology, and external

environment aspects.

7.2 Analysis Results and Discussions of Survey I

7.2.1 Profile of respondents and their organizations

Questionnaire Survey I was expected to investigate the level of agreement on and the

frequency of occurrence of the NVA activities, the frequency of occurrence of the

resulting wastes and their impact on productivity, and the relative importance of the

potential causes to these NVA activities in building projects in Singapore. From April

to August 2016, a total of 659 questionnaires were sent out, and 73 completed

questionnaires were received. It has been considered as appropriate that these

questionnaires were obtained based on the respondents’ willingness to participate in

the study (Wilkins, 2011). A response rate of 11.08% was acceptable because it fell

within the general response rate of 10%–15% for Singapore surveys (Teo et al.,

2007). The profile of the respondents and their organizations is presented in Table

7.1.

Page 202: building information modeling–based process transformation to improve productivity in the

182

Table 7.1 Profile of the respondents and their organizations in Survey I

Characteristics Categorization Frequency Percentage (%)

Organization

Main business Architectural firm 11 15.1

Structural engineering firm 9 12.3

MEP engineering firm 9 12.3

General construction firm 23 31.5

Trade construction firm 1 1.4

Facility management firm 1 1.4

Others 19 26.0

BCA financial grade A1 22 30.1

B1 2 2.7

C3 2 2.7

Single grade 1 1.4

L6 6 8.2

L4 1 1.4

L2 1 1.4

L1 2 2.7

Not applicable 36 49.3

Years of BIM adoption 0 year 9 12.3

1-3 years 34 46.6

4-5 years 17 23.3

6-10 years 11 15.1

Over 10 years 2 2.7

Respondent

Discipline Government agent 4 5.5

Developer 3 4.1

Architect 15 20.5

Structural designer 11 15.1

MEP designer 8 11.0

General contractor 19 26.0

Trade contractor 5 6.8

Supplier/Manufacturer 2 2.7

Facility manager 6 8.2

Years of experience 5-10 years 31 42.5

11-15 years 14 19.2

16-20 years 5 6.8

21-25 years 4 5.5

Over 25 years 19 26.0

In terms of the responding organizations, 23 (31.5%) of the organizations were

general construction firms, and 11 (15.1%), nine (12.3%), nine (12.3%), one (1.4%),

and one (1.4%) were architectural firms, structural engineering firms, MEP

engineering firms, a trade construction firm, and a facility management firm,

respectively. Moreover, the main businesses of the 19 organizations listed in the

“others” category included the BCA, the URA, the HDB, developers, precasters, a

Page 203: building information modeling–based process transformation to improve productivity in the

183

facility management firm, and other consultancy firms such as multidisciplinary

consultancy firms and a BIM consultancy firm. This indicated a good balance of the

distribution of the industry players.

Based on the organizations’ financial grades, over half (50.7%) of the organizations

were registered contractors with the BCA. Among which, 22 (30.1%) were A1

contractors, followed by six (8.2%) L6 contractors, two (2.7%) B1 contractors, and

one (1.4%) single grade contractor. The inclusion of small- and medium-sized

contractors (two for C3, two for L1, one for L4, and one for L2) was because some

contractors were subsidiaries of larger contractors, or their grades were renewed by

the BCA during the five-month survey. The remaining 36 (49.3%) organizations

comprised of government agencies, developers, consultancy firms, and a facility

management firm.

As for experience of implementing BIM, 34 (46.6%) of the organizations started to

adopt BIM in their building projects in last one to three years, and 17 (23.3%) had

four to five years’ BIM implementation experience. Only two firms had implemented

BIM over 10 years. Because BIM implementation had been mandated by the local

government since July 2015, it was reasonable that over half (58.9%) had no more

than three years’ experience. The nine (12.3%) organizations that had not

implemented BIM at the time of this research were not excluded in the subsequent

data analysis. The reason was that the Singapore government had made huge efforts

in promoting BIM implementation. For instance, the aforementioned mandate was

accompanied by a new BIM fund to grow the collaboration capabilities of the

practitioners beyond just modelling within their own firms, which would defray part

of the initial costs in training, consultancy, software, and hardware (BCA, 2016).

Because of these efforts, all the respondents should have been equipped with BIM

knowledge, skills, or experience. Even though the nine organizations had not

Page 204: building information modeling–based process transformation to improve productivity in the

184

implemented BIM in their current projects, it did not mean that the respondents did

not have BIM knowledge. In the Singapore context, the respondents should have

insights into BIM implementation; they must had plans to implement BIM in the near

future projects as mandated. Thus, their responses were used subsequently. This

result indicated that the local construction industry had been moving from the

traditional delivery approach into the new approach of building planning, design,

construction, and operations using BIM.

With respect to the 73 respondents’ disciplines, 19 (26.0%) of them worked as

general contractors, while 15 (20.5%), 11 (15.1%), 8 (11.0%) were architects,

structural designers, and MEP designers, respectively. As for working experience, 31

(42.5%) of the respondents had worked for five to 10 years in the Singapore

construction industry, implying that they were more interested in the emerging new

way of planning, designing, building, and operating building projects. In addition, 19

(26.0%) of the respondents had over 25 years’ work experience in this field. Most of

them were at the management level.

According to the profile, it could be concluded that the respondents and their

organizations could be well representative of key BIM implementers in the local

construction value chain, thus assuring the response quality. It was expected that the

data collected from them were reliable.

7.2.2 Level of agreement of NVA activities

The reliability of the 73 responses was tested by calculating the Cronbach’s alpha

coefficient. As recommended by Nunnally (1978), the generally agreed upon lower

limit for the Cronbach’s alpha is 0.7 for a scale to be reliable and 0.6 being

questionable. The coefficient for all the 44 NVA activities was 0.934, indicating high

Page 205: building information modeling–based process transformation to improve productivity in the

185

data reliability. The results in Table 7.2 indicated that the Cronbach’s alpha

coefficients for the NVA activities met such requirement in all project phases, except

the conceptualization phase (P1). The coefficient of 0.632 was questionable.

Nevertheless, Robinson et al. (1991) stated that the threshold may decrease to 0.6 for

newly-developed measures in exploratory research, which was consistent with the

NVA activities scale in this study. Thus, this coefficient was considered acceptable.

Table 7.2 Level of agreement ranking and t-test results of the NVA activities

Code NVA activities Mean Overall

rank

Internal

rank

p-

value

P1: Conceptualization (α = 0.632)

# Lack of involvement by government agency 3.18 40 – 0.224

N1.1 Inadequate project objectives and performance

metrics set by owner

3.51 25 3 0.000*

# Owner resists to use BIM in the whole project 2.81 44 – 0.137

N1.2 No reward/risk sharing arrangements among

major stakeholders are set by owner

3.85 11 1 0.000*

N1.3 Lack of involvement by engineers (not

appointed)

3.41 31 4 0.003*

N1.4 Lack of involvement by general contractor (not

appointed)

3.73 17 2 0.000*

P2: Schematic design (α = 0.799)

# Lack of involvement by government agency 2.89 43 – 0.392

N2.1 Lack of joint control and agreement on project

targets and metrics by major stakeholders

3.51 25 5 0.000*

N2.2 Architect, engineers, and contractors do not

work together in design modeling

3.66 20 4 0.000*

# Architect does not share its complete model with

engineers

3.16 41 – 0.255

# Architect and engineers do not submit their

schematic design models for regulatory

approvals

3.21 39 – 0.083

N2.3 Engineers not involved early in this phase to

contribute in architectural modeling

3.49 27 6 0.001*

N2.4 Lack of involvement by general contractor and

key trade contractors to contribute site

knowledge (not appointed)

3.92 6 1 0.000*

N2.5 Lack of involvement by manufacturer/supplier

(not appointed) to contribute fabrication

knowledge

3.92 6 1 0.000*

N2.6 Lack of involvement by facility manager (not

appointed) to contribute operations and

maintenance knowledge

3.92 6 1 0.000*

P3: Design development (α = 0.772)

# Lack of involvement by government agency 2.93 42 – 0.567

N3.1 Insufficient design review and feedback by

owner

3.26 38 8 0.032*

Page 206: building information modeling–based process transformation to improve productivity in the

186

N3.2 Architect, engineers, and contractors do not

work together in design modeling

3.56 22 5 0.000*

N3.3 Architect does not share its complete model with

engineers and contractors

3.27 37 7 0.047*

N3.4 Coordination of building systems is deferred

until construction phase due to unavailable trade

contractor input until then

4.10 2 2 0.000*

N3.5 Lack of involvement by general contractor and

key trade contractors to contribute site

knowledge (not appointed)

4.21 1 1 0.000*

N3.6 Construction model is not developed due to

unwillingness of architect and engineers to share

their BIM models

3.30 36 6 0.044*

N3.7 Lack of involvement by manufacturer/supplier

(not appointed) to contribute knowledge of

material selection, transportation, site erection,

and so on

4.03 3 3 0.000*

N3.8 Lack of involvement by facility manager (not

appointed) to contribute operations and

maintenance knowledge

3.92 6 4 0.000*

P4: Construction documentation (α = 0.876)

N4.1 Not fully defined and coordinated between

architectural, structural, and MEP design models

3.75 16 3 0.000*

N4.2 Insufficient communication between architect

and engineers

3.45 29 5 0.001*

N4.3 Information such as bill of materials, assembly,

layout, detailed schedule, testing and

commissioning procedures is not documented

after design

3.52 23 4 0.000*

N4.4 Long-lead items are not identified and defined

during design for early procurement

3.45 29 5 0.001*

N4.5 Shop drawing process is not merged into design

as contractors and manufacturer/supplier cannot

document construction intent

3.82 12 2 0.000*

N4.6 Prefabrication of some systems cannot start as

design is not fixed

3.97 4 1 0.000*

P5: Agency permit/Bidding/Preconstruction (α = 0.748)

N5.1 Architect and engineers only pass 2D drawings

or incomplete 3D BIM models to contractors and

manufacturer/supplier

3.88 10 1 0.000*

N5.2 General contractor has to re-build BIM model

based on insufficient documents from designers

3.79 13 2 0.000*

N5.3 General contractor extends 2D drawings

(without BIM) from designers to guide

construction

3.79 13 2 0.000*

P6: Construction (including Manufacture) (α = 0.787)

N6.1 Owner and designers enable changes during

construction

3.93 5 1 0.000*

N6.2 Architect and engineers need long time to

respond to contractors’ RFIs as their design

models cannot directly guide site work

3.70 19 4 0.000*

N6.3 Architect and engineers do not update their

design models

3.60 21 5 0.000*

N6.4 Contractors and manufacturer/supplier have 3.77 15 2 0.000*

Page 207: building information modeling–based process transformation to improve productivity in the

187

excessive RFIs and paperwork

N6.5 General contractor communicates insufficiently

with other key stakeholders

3.36 34 8 0.005*

N6.6 Low proportion of building components in

superstructure and fitting out using OSM

3.40 32 7 0.000*

N6.7 Congestion and many interfaces on site 3.73 17 3 0.000*

N6.8 Incomplete 2D drawings or 3D BIM models for

trade contractors and manufacturer/supplier

3.49 27 6 0.000*

P7: Handover/Closeout/Operations and maintenance (α = 0.772)

N7.1 As-built BIM models are not handed to facility

manager who uses insufficient levels of detail

2D as-built drawings

3.52 23 1 0.000*

N7.2 Many disputes/claims/litigations between

general contractor and owner and designers

3.37 33 2 0.001*

N7.3 Facility manager does not have sufficient BIM-

based design and construction information for

operations and maintenance

3.33 35 3 0.008*

*The one-sample t-test result was significant at the 0.05 level (two-tailed).

#The NVA activity was not significantly agreed upon by the respondents as a critical

NVA activity.

The NVA activities were ranked according to their level of agreement mean scores

which ranged from 2.81 to 4.21. To test whether each NVA activity was significantly

agreed upon by the local professionals, the one-sample t-test was performed. The test

value of 3.00 and the significance level of 0.05 (two-tailed) were adopted in this

study. The activities that obtained mean scores above 3.00 and p-values below 0.05

were deemed as critical NVA activities. The analysis results (see Table 7.2)

suggested that 38 activities were widely-agreed upon NVA activities in the current

industry practices in the Singapore construction industry. Thus, Hypothesis 1 that

“the construction industry agrees upon frequent NVA activities in the current project

delivery in the Singapore context” was supported.

The top 10 critical NVA activities were highlighted and discussed. Among which, the

top three overall rankings were occupied by the NVA activities in the design

development phase (P3), namely “lack of involvement by general contractor and key

trade contractors to contribute site knowledge (not appointed)” (N3.5, mean = 4.21,

ranked first), “coordination of building systems is deferred until construction phase

Page 208: building information modeling–based process transformation to improve productivity in the

188

due to unavailable trade contractor input until then” (N3.4, mean = 4.10, ranked

second), and “lack of involvement by manufacturer/supplier (not appointed) to

contribute knowledge of material selection, transportation, site erection, and so on”

(N3.7, mean = 4.03, ranked third). This substantiated the argument by Gao and

Fischer (2006) that the participation of the contractors and the manufacturer/supplier

in the detailed design stage is of great importance in a building project that

implements BIM. Without their early involvement, detailed off-site manufacture and

site activities cannot be well coordinated in the virtual design environment before

actual construction commences (AIACC, 2014). Upfront architect and engineers may

not have sufficient construction knowledge and experience to support the detailed

design coordination. As a result, the problems that traditionally would happen on site

remain unsolved until the construction stage where these problems would inevitably

take place. In addition, another highly-ranked NVA activity in this phase was

obtained by “lack of involvement by facility manager (not appointed) to contribute

operations and maintenance knowledge” (N3.8, mean = 3.92, ranked sixth),

suggesting that the operations and maintenance team should also be appointed and

involved no later than the design development phase (Kunz and Fischer, 2012). Their

proactive participation would significantly improve the flow of information

throughout the design, construction, and operations and maintenance phases, and

enrich operations and maintenance information which tended to be unavailable in the

current industry practices. Currently, data in the BIM model tended to be less relevant

for operations and maintenance.

The fourth-ranked NVA activity was “prefabrication of some systems cannot start as

design is not fixed” (N4.6, mean = 3.97) in the construction documentation phase

(P4), implying that in the current project delivery, design was usually not fixed even

after the design stage. Consequently, off-site production work that would potentially

enhance the efficiency of carrying out construction activities cannot start proactively.

Page 209: building information modeling–based process transformation to improve productivity in the

189

Apart from the unavailable contractor input in the design stage, not fixing design

early could be attributed to unclear owner conception from the beginning, which

would affect the design consultants’ understanding of the owner’s brief. As a result,

there would be frequent change orders enabled by the owner and the design

consultants in the later stages of the project, significantly affecting project

productivity. Therefore, the NVA activity “owner and designers enable changes

during construction” (N6.1, mean = 3.93) in the construction phase (P6) received the

fifth highest overall rating.

Three NVA activities in the schematic design phase (P2) obtained the sixth most

agreement, including “lack of involvement by general contractor and key trade

contractors to contribute site knowledge (not appointed)” (N2.4, mean = 3.92), “lack

of involvement by manufacturer/supplier (not appointed) to contribute fabrication

knowledge” (N2.5, mean = 3.92), and “lack of involvement by facility manager (not

appointed) to contribute operations and maintenance knowledge” (N2.6, mean =

3.92). This was in line with AIACC (2014) and Azhar et al. (2014) which found that

the building project changing to fully implement BIM should engage the downstream

parities from the early design stage. Although their proactive involvement would be

most important in the detailed design phase when a great number of construction

details are required, the participation even earlier would have a larger impact on the

finalization of project targets and metrics as well as key deign parameters.

Another highly ranked NVA activity was “architect and engineers only pass 2D

drawings or incomplete 3D BIM models to contractors and manufacturer/supplier”

(N5.1, mean = 3.88) in the bidding and preconstruction phase (P5). A common

situation was that the design consultants are usually not required by the owner and are

unwilling to share their models with the contractors, which would pose extra costs to

the latter for re-building the design models (Sattineni and Mead, 2013; Lam, 2014).

Page 210: building information modeling–based process transformation to improve productivity in the

190

In addition, the design models may be of poor quality and sharing such models would

expose the consultants to liability issues.

In terms of the internal rankings within each phase, apart from the top 10 critical

NVA activities that were distributed from the schematic design phase to the

construction phase, “no reward/risk sharing arrangements among major stakeholders

are set by owner” (N1.2, mean = 3.85) and “as-built BIM models are not handed to

facility manager who use insufficient levels of detail 2D as-built drawings” (N7.1,

mean = 3.52) received the highest ratings in their respective phases. Reward and risk

sharing arrangements in the project team ensure the team members to work in a best-

for-project manner and build trust-based collaboration throughout the project

completion. This was because they would be on the same boat; their corporate

benefits were subject to the success of this project. Meanwhile, using BIM in the

operations and maintenance phase drawn much attention in previous studies (Aranda-

Mena et al., 2009; Khosrowshahi and Arayici, 2012).

Nevertheless, six NVA activities obtained either mean scores below 3.00 or p-values

above 0.05, indicating that such activities did not obtain wide agreement from the

local BIM experts in the current industry practices, despite their occurrence in some

projects in Singapore. The activities included: (1) “lack of involvement by

government agency” (mean = 3.18; p-value = 0.224) and “owner resists to use BIM in

the whole project” (mean = 2.81; p-value = 0.137) in the conceptualization phase; (2)

“lack of involvement by government agency” (mean = 2.89; p-value = 0.392),

“architect does not share its complete model with engineers” (mean = 3.16; p-value =

0.255), and “architect and engineers do not submit their schematic design models for

regulatory approvals” (mean = 3.21; p-value = 0.083) in the schematic design phase;

and (3) “lack of involvement by government agency” (mean = 2.93; p-value = 0.567)

in the design development phase.

Page 211: building information modeling–based process transformation to improve productivity in the

191

Post-survey interviews were conducted with four experts who had originally

participated in this survey and possessed BIM implementation experience in

Singapore. The profile of these experts were presented in Table 7.3. In the post-

survey interviews, the experts were presented with the survey results. They

commented that the findings of this survey were reasonable and in agreement with

their expectations. To gain an in-depth understanding, they were also invited to

provide possible explanations for the six NVA activities that were not widely agreed

upon as critical NVA activities. There comments were used to support the exclusion

of such NVA activities.

Table 7.3 Profile of the interviewees in Survey I

Interviewee Work experience Designation Firm

1 15 years Project manager General construction firm

2 10 years Senior engineer MEP consultancy firm

3 8 years Quantity surveying in

charge

General construction firm

4 11 years Deputy contracts manager Construction and

development firm

Firstly, the experts participating in the post-survey interviews argued that the

Singapore government has been proactive on BIM implementation, so the NVA

activities “lack of involvement by government agency” in the conceptualization phase

and the design phases were not significantly agreed upon. In addition, even the owner

may have a cost-beneficial thinking and does not have experience in implementing

BIM (Lam, 2014), the post-survey interviewees highlighted that BIM implementation

has been considered definitely beneficial to the owner in the long-term (Smith, 2014).

Thus, “owner resists to use BIM in the whole project” was contradicted by the local

circumstances. Moreover, “architect does not share its complete model with

engineers” was not perceived critical in the Singapore construction industry. The

experts involved in the post-survey interviews stated that the architect usually shared

CAD-like documents with the engineers because the latter tended to be customized

Page 212: building information modeling–based process transformation to improve productivity in the

192

into the traditional way of working. It is possible that the architect would share its

design model if both of them were using compatible BIM tools in the design. Thus,

this NVA activity was not deemed critical in the local construction industry.

Furthermore, the government agencies’ strict review process on the building plans e-

submissions in BIM format now made it impossible that “architect and engineers do

not submit their schematic design models for regulatory approvals” before the project

could proceed to the next phases.

7.2.3 BIMIR of building projects in Singapore

7.2.3.1 Weights of project phasing and NVA activities

Using equations 4.5 and 4.6 described in Section 4.2.2 and the data related to the

level of agreement of the critical NVA activities, this study calculated the weights of

all the seven project phases and 38 critical NVA activities, as shown in Table 7.4. An

example of demonstrating the calculation process was presented in Appendix 4. As

shown in Table 7.4, the project phases’ weights ranged from 0.073 to 0.213.

Table 7.4 Weighting for project phasing and its NVA activities

Project phasing NVA

activity

Mean score of

level of agreement

Mean of

phasing

Weight of

NVA activity

Weight of

phasing

P1: Conceptualization N1.1 3.51 14.49 0.242 0.104

N1.2 3.85 0.266

N1.3 3.41 0.235

N1.4 3.73 0.257

P2: Schematic design N2.1 3.51 22.41 0.156 0.161

N2.2 3.66 0.163

N2.3 3.49 0.156

N2.4 3.92 0.175

N2.5 3.92 0.175

N2.6 3.92 0.175

P3: Design development N3.1 3.26 29.64 0.110 0.213

N3.2 3.56 0.120

N3.3 3.27 0.110

N3.4 4.10 0.138

N3.5 4.21 0.142

N3.6 3.30 0.111

N3.7 4.03 0.136

N3.8 3.92 0.132

Page 213: building information modeling–based process transformation to improve productivity in the

193

P4: Construction

documentation

N4.1 3.75 21.97 0.171 0.158

N4.2 3.45 0.157

N4.3 3.52 0.160

N4.4 3.45 0.157

N4.5 3.82 0.174

N4.6 3.97 0.181

P5: Agency permit/

Bidding/Preconstruction

N5.1 3.88 11.47 0.338 0.082

N5.2 3.79 0.331

N5.3 3.79 0.331

P6: Construction

(including Manufacture)

N6.1 3.93 28.97 0.136 0.208

N6.2 3.70 0.128

N6.3 3.60 0.124

N6.4 3.77 0.130

N6.5 3.36 0.116

N6.6 3.40 0.117

N6.7 3.73 0.129

N6.8 3.49 0.121

P7: Handover/Closeout/

Operations and

maintenance

N7.1 3.52 10.22 0.345 0.073

N7.2 3.37 0.330

N7.3 3.33 0.326

Sum – – 139.18 – 1.000

The average weights of the seven project phases (the weight of a phase divided by the

number of critical NVA activities included in this phase) and rankings were 0.0260

(5), 0.0268 (2), 0.0266 (3), 0.0263 (4), 0.0275 (1), 0.0260 (5), and 0.0245 (7),

respectively. This was consistent with the results in Table 7.2 that the critical NVA

activities in the agency permit/bidding/preconstruction phase were essential to BIM

implementation, and that the activities in the schematic design phase and the design

development phase occupied the most positions in the top 10 overall rankings.

7.2.3.2 BIMIR of the surveyed building projects

Using the proposed fuzzy BIMIR model described in Section 4.4.2 and the data

related to the frequency of occurrence of the 38 critical NVA activities collected from

Survey I, this study calculated the NVAI scores of all the 73 building projects (coded

in chronological order) in Singapore. As shown in Table 7.5, the NVAI scores ranged

from 0.323 to 0.905. An example is presented to demonstrate the calculation process

of the proposed fuzzy BIMIR model (see Appendix 4). According to Figure 4.7, the

Page 214: building information modeling–based process transformation to improve productivity in the

194

NVAI scores were translated into the linguistic terms (frequency of occurrence). The

overall average NVAI score of the 73 surveyed building projects in Singapore was

0.634 (“often”), suggesting that the critical NVA activities very frequently occurred

in the Singapore construction industry. These NVAI scores could serve as a ballpark

benchmark, with which local project building projects could compare.

Table 7.5 NVAI scores of the surveyed building projects in Singapore

Project code NVAI score Linguistic

term

Project code NVAI score Linguistic

term

01 0.694 often 38 0.837 often

02 0.608 sometimes 39 0.760 often

03 0.527 sometimes 40 0.677 often

04 0.352 rarely 41 0.851 often

05 0.602 sometimes 42 0.763 often

06 0.341 rarely 43 0.630 often

07 0.608 sometimes 44 0.369 rarely

08 0.571 sometimes 45 0.551 sometimes

09 0.664 often 46 0.730 often

10 0.905 always 47 0.521 sometimes

11 0.755 often 48 0.669 often

12 0.685 often 49 0.488 sometimes

13 0.680 often 50 0.738 often

14 0.577 sometimes 51 0.323 rarely

15 0.572 sometimes 52 0.790 often

16 0.711 often 53 0.759 often

17 0.490 sometimes 54 0.688 often

18 0.496 sometimes 55 0.819 often

19 0.538 sometimes 56 0.736 often

20 0.669 often 57 0.500 sometimes

21 0.741 often 58 0.791 often

22 0.632 often 59 0.621 sometimes

23 0.438 sometimes 60 0.614 sometimes

24 0.729 often 61 0.404 sometimes

25 0.605 sometimes 62 0.541 sometimes

26 0.790 often 63 0.685 often

27 0.681 often 64 0.513 sometimes

28 0.739 often 65 0.792 often

29 0.796 often 66 0.651 often

30 0.503 sometimes 67 0.621 sometimes

31 0.590 sometimes 68 0.668 often

32 0.494 sometimes 69 0.635 often

33 0.720 often 70 0.629 often

34 0.643 often 71 0.521 sometimes

35 0.833 often 72 0.424 sometimes

36 0.811 often 73 0.500 sometimes

37 0.705 often – – –

Note: the average NVAI score of the surveyed building projects in Singapore was

0.634 (“often”).

Page 215: building information modeling–based process transformation to improve productivity in the

195

According to the adjusted translation method in Table 4.5, these NVAI scores were

also translated into BIMIR statuses. As Table 7.6 indicates, while only 11 (15.07%)

surveyed building projects in Singapore had implemented BIM in a collaborative

manner (BIMIR S3), 62 (84.93%) projects had lower BIMIR statuses (15 for BIMIR

S1 and 47 for BIMIR S2), implying that either no BIM (BIMIR S1) or lonely BIM

(BIMIR S2) was implemented in these building projects. It was notable that no

project surveyed had implemented BIM fully (BIMIR S4) in Singapore. In addition,

the overall average BIMIR status (translated from the overall average NVAI score of

0.634) was S2 (lonely BIM implementation). These findings were consistent with the

Singapore context that most building projects were adopting fragmented, firm-based

BIM uses (Lam, 2014). Since the mandatory BIM implementation took effect in July

2015, the local construction industry had been moving from the traditional project

delivery into BIM-based project delivery and was shifting to collaborative BIM

implementation. Thus, Hypothesis 2 that “the BIMIR statuses of building projects in

Singapore are low” was supported.

Table 7.6 BIMIR statuses of the surveyed building projects

NVAI score N % BIMIR status

0.75≤ Index score 15 20.55 S1 (No BIM implementation)

0.50≤ Index score <0.75 47 64.38 S2 (Lonely BIM implementation)

0.25≤ Index score <0.50 11 15.07 S3 (Collaborative BIM implementation)

7.2.3.3 Stability tests of the proposed FSE model

The stability of the proposed fuzzy BIMIR model was tested five times. In each test,

three random numbers were generated from the random numbers table and set aside.

The proposed model was then re-developed by changing the weights of the evaluation

criteria (project phases) and sub-criteria (critical NVA activities). The NVAI scores

of the 73 projects were re-calculated. The level of agreement mean scores of the

remaining 70 responses were used to re-calculate the weights.

Page 216: building information modeling–based process transformation to improve productivity in the

196

The generation of the five groups of random numbers were explained. Firstly, the 73

surveyed building projects were coded from 01 to 73 (see Table 7.5). Secondly, the

five tests used five groups of random numbers which were generated from the first

five rows of the random numbers table. In each row, the selection started from the

first random number and moved rightwards, and stopped when a list of three random

numbers were generated. Those numbers that are either greater than 73 or repeated

were ignored. For example, the first three random numbers (03, 47, and 43) in the

first row were used in the first test. Consequently, five groups of random numbers

were generated, as shown in Table 7.7.

Table 7.7 Generation of five groups of random numbers

Test Random numbers Location in random numbers table

1 03, 47, 43 #1, #2, and #3 (1st row)

2 24, 67, 62 #3, #4, and #5 (2nd

row)

3 16, 02, 27 #1, #3, and #4 (3rd

row)

4 12, 56, 26 #1, #2, and #5 (4th row)

5 55, 59, 35 #1, #2, and #4 (5th row)

According to the fuzzy BIMIR model described in Section 4.4.2 and the frequencies

of occurrence of the 38 critical NVA activities from Survey I, new NVAI scores of all

the 73 building projects in Singapore were calculated, as shown in Table 7.8.

Compared with the results presented in Table 7.5, the new NVAI scores obtained in

all the five stability tests either remained the same or only slightly changed by 0.001.

It should be noted that due to decimal representation, some NVAI scores (such as the

fourth test score of Project 02) seemed to change by 0.001 in Table 7.8, but actually

the score changes were 0.000. Thus, such test scores were not noted in the table. Also,

some NVAI scores (such as the third test score of Project 16) seemed to remain

unchanged, but actually the scores changed by 0.001. Thus, such test scores were

noted in the table. In addition, BIMIR statuses in the five tests remained unchanged.

Therefore, it could be concluded that the fuzzy BIMIR model proposed in this study

Page 217: building information modeling–based process transformation to improve productivity in the

197

showed stable evaluation results and could be used for prediction in other building

projects in Singapore.

Table 7.8 New NVAI scores and changes of the surveyed building projects in five

stability tests

Project

code

NVAI

score

NVAI score

in test #1

NVAI score

in test #2

NVAI score

in test #3

NVAI score

in test #4

NVAI score

in test #5

01 0.694 0.694 0.694 0.695a 0.694 0.693

b

02 0.608 0.608 0.608 0.608 0.607 0.608

03 0.527 0.527 0.527 0.528 0.527 0.527

04 0.352 0.352 0.352 0.351 0.352 0.352

05 0.602 0.602 0.602 0.603 0.602 0.602

06 0.341 0.341 0.341 0.341 0.341 0.341

07 0.608 0.608 0.608 0.608 0.608 0.608

08 0.571 0.571 0.571 0.572a 0.571 0.570

b

09 0.664 0.664 0.664 0.664 0.664 0.664

10 0.905 0.905 0.905 0.905 0.905 0.905

11 0.755 0.755 0.755 0.755 0.755 0.755

12 0.685 0.685 0.685 0.685 0.685 0.685

13 0.680 0.680 0.680 0.681 0.680 0.680

14 0.577 0.577 0.578 0.578 0.577 0.577

15 0.572 0.572 0.572 0.572a 0.572 0.571

16 0.711 0.711 0.711 0.711b 0.711 0.711

17 0.490 0.490 0.490 0.490 0.490 0.490

18 0.496 0.496 0.496 0.496 0.496 0.496

19 0.538 0.538 0.539 0.538 0.539 0.539

20 0.669 0.669 0.669 0.669 0.670 0.670

21 0.741 0.741 0.741 0.741 0.741 0.741

22 0.632 0.632 0.632 0.631 0.632 0.632

23 0.438 0.438 0.438 0.438 0.438 0.438

24 0.729 0.729 0.728b 0.729 0.729 0.728

25 0.605 0.606 0.605 0.605 0.605 0.605

26 0.790 0.790 0.790 0.790 0.790 0.790

27 0.681 0.681 0.681 0.680b 0.681 0.681

28 0.739 0.739 0.739 0.739 0.739 0.739

29 0.796 0.797 0.796 0.797 0.797 0.797

30 0.503 0.503 0.503 0.502 0.503 0.504a

31 0.590 0.590 0.590 0.590 0.591 0.591

32 0.494 0.494 0.494 0.494 0.494 0.494

33 0.720 0.720 0.719 0.720 0.720 0.720

34 0.643 0.643 0.643 0.643 0.643 0.643

35 0.833 0.833 0.833 0.833 0.833 0.833

36 0.811 0.811 0.811 0.811 0.811 0.811

37 0.705 0.705 0.705 0.705 0.705 0.705

38 0.837 0.837 0.837 0.837 0.837 0.837

39 0.760 0.760 0.760 0.760 0.760 0.760

40 0.677 0.677 0.677 0.677 0.677 0.677

41 0.851 0.851 0.851 0.850 0.851 0.851

42 0.763 0.763 0.763 0.763 0.763 0.763

43 0.630 0.629 0.629 0.629 0.630 0.630

Page 218: building information modeling–based process transformation to improve productivity in the

198

44 0.369 0.369 0.369 0.369 0.369 0.369

45 0.551 0.551 0.551 0.551 0.551 0.551

46 0.730 0.730 0.731 0.730 0.730 0.730

47 0.521 0.521 0.521 0.521 0.521 0.521

48 0.669 0.670 0.669 0.670a 0.669 0.669

b

49 0.488 0.488 0.488 0.488 0.488 0.489

50 0.738 0.738 0.738 0.738b 0.738 0.738

51 0.323 0.323 0.323 0.323 0.323 0.323

52 0.790 0.790 0.790 0.791a 0.790 0.790

53 0.759 0.759 0.759 0.759 0.759 0.759

54 0.688 0.688 0.688 0.688 0.688 0.688

55 0.819 0.819 0.819 0.820 0.819 0.819

56 0.736 0.736 0.736 0.736 0.736 0.736

57 0.500 0.500 0.500 0.500 0.500 0.500

58 0.791 0.791 0.791 0.791 0.791 0.791

59 0.621 0.621 0.621 0.622a 0.621 0.620

b

60 0.614 0.614 0.615 0.614 0.614 0.615

61 0.404 0.404 0.405 0.404 0.404 0.405

62 0.541 0.541 0.541 0.541 0.541 0.541

63 0.685 0.684 0.685 0.685 0.685 0.685

64 0.513 0.513 0.513 0.513 0.513 0.513

65 0.792 0.792 0.792 0.792 0.792 0.793

66 0.651 0.651 0.652 0.652a 0.651 0.651

67 0.621 0.621 0.620 0.620 0.621 0.621

68 0.668 0.668 0.668 0.668 0.668 0.668

69 0.635 0.635 0.635 0.635 0.635 0.635

70 0.629 0.629 0.629 0.629 0.629 0.629

71 0.521 0.521 0.521 0.521 0.521 0.521

72 0.424 0.424 0.424 0.424 0.424 0.424

73 0.500 0.500 0.500 0.500 0.500 0.500

Note: BIMIR statuses in the five tests remained the same. aThe NVAI score increased by 0.001.

bThe NVAI score decreased by 0.001.

7.2.4 Resulting wastes

The Cronbach’s alpha coefficient value was 0.901, indicating that the data related to

the resulting wastes of the critical NVA activities in building projects in Singapore

had high reliability.

7.2.4.1 Overall ranking

It was not necessary to conduct the one-sample t-test to check whether a waste was

statistically significant in affecting productivity performance (issue of “yes or no”).

Page 219: building information modeling–based process transformation to improve productivity in the

199

Unlike the NVA activities, all the 13 wastes identified from the literature review were

deemed significant. As explained in Section 4.2.2, these wastes indeed consume time

and efforts and thus hurt productivity performance. Instead, it would be helpful to

study the criticality of these wastes in influencing productivity (issue of “degree”).

In this study, waste criticality (WC) was defined to measure how critical to

productivity performance a waste is in the partial BIM-based current industry

practices. The WC of waste 𝑙 rated by respondent 𝑗 was calculated as the root square

of the product of the waste’s impact on productivity (𝐼𝑃) and frequency of occurrence

(𝐹𝑂), which keeps the scale of 𝑊𝐶 consistent with 𝐼𝑃 and 𝐹𝑂, as shown in equation

(7.1). The criticality of a factor has been used in previous construction management

studies (Zhao et al., 2016a).

𝑊𝐶𝑙𝑗

= √𝐹𝑂𝑙𝑗

× 𝐼𝑃𝑙𝑗 (7.1)

As Table 7.9 indicates, the WC mean scores of the 13 resulting wastes ranged from

2.81 to 3.60. These wastes were ranked based on their overall mean scores. The mean

scores of frequency of occurrence and impact on productivity ranged from 2.68 to

3.89 and from 2.77 to 3.66, respectively. It is notable that the largest and smallest

mean score belonged to W02 and W13 for frequency of occurrence as well as W03

and W09 for impact on productivity. Thus, none of the 13 resulting wastes had a very

high frequency of occurrence and a very low impact on productivity, or vice versa. In

the subsequent paragraphs, the top five critical wastes were analyzed and discussed.

The local BIM experts’ comments collected in the post-survey interviews were also

used to gain a clear understanding of the most critical wastes.

Page 220: building information modeling–based process transformation to improve productivity in the

200

Table 7.9 Mean and ranking of resulting wastes

Code Resulting wastes Frequency of

occurrence

Impact on

productivity

WC

Mean Rank Mean Rank Mean Rank

W01 Defects 3.71 2 3.34 6 3.49 4

W02 RFIs 3.89 1 3.29 7 3.53 2

W03 Reworks/abortive works 3.62 3 3.66 1 3.60 1

W04 Waiting/idle time 3.56 5 3.47 4 3.48 5

W05 Change orders 3.58 4 3.41 5 3.46 7

W06 Activity delays 3.51 7 3.48 3 3.47 6

W07 Overproduction/reproduction 3.19 8 3.05 8 3.10 8

W08 Transporting/handling materials 3.05 10 2.97 10 2.98 10

W09 Unnecessary inventory 2.99 12 2.77 13 2.83 12

W10 Excess processing beyond standard 3.08 9 2.95 11 2.99 9

W11 Unnecessary movement of people and

equipment

3.04 11 2.90 12 2.94 11

W12 Design deficiencies (errors, omissions,

additions)

3.53 6 3.53 2 3.51 3

W13 Injuries/safety issues 2.68 13 3.05 9 2.81 13

“Reworks/abortive works” was recognized as the most critical waste (mean = 3.60),

indicating that building projects in Singapore had suffered from a great deal of

abortive works. This result echoed the post-survey interviewees who reported that

abortive works usually happened throughout the construction phase and influenced a

lot of trades on site. Actually, the trade contactors rarely used BIM tools (Lam, 2014)

and tended to arrange their construction activities ahead of time, which may not be

updated, planned, and reflected in the design models. Consequently, clashes were

often detected during the construction stage, leading to abortive works and extra time

and manpower to redo the works.

“RFIs” received the second highest rating in the waste ranking (mean = 3.53). This

result indicated that productivity performance of building projects in Singapore was

seriously affected by frequent enquiries and clarifications between downstream and

upfront key stakeholders. In the post-survey interviews, the experts stated that plenty

of time and efforts were wasted in paperwork. Since the design models of different

disciplines were not well coordinated, design issues were postponed until the

construction stage where the contractors often needed to request for clarifications or

Page 221: building information modeling–based process transformation to improve productivity in the

201

confirmations of verbal instructions. Nevertheless, the design consultants may be

wary of providing early and incomplete information to the contractors because of

potential liabilities (Eastman et al., 2011; AIACC, 2014). This process of requesting

and responding would waste huge efforts, and even affect the project progress.

“Design deficiencies (errors, omissions, additions)” occupied the third position (mean

= 3.51), suggesting that the collaboration was poor between the design consultants

and downstream parities in the design stage. This result substantiated the finding of

Nikakhtar et al. (2015) that a productive delivery should prevent deficiencies from

being made through mistake-proofing in the planning stage. Because of unclear

owner conception and poorly coordinated design models, design errors and changes

were common in the later stages of the project. As a result, construction activities

prone to errors could not be identified in time and thus delaying the construction

progress.

“Defects” was ranked fourth in the waste ranking (mean = 3.49), implying that

defective products were often produced in the construction phase, seriously affecting

productivity performance in the project. As the most obvious waste, every defective

item would require repairs and reworks as well as paperwork.

Another highly ranked waste was “waiting/idle time” (mean = 3.48), suggesting that

the field staff often spent much time waiting for instructions and confirmation from

the design consultants, materials supply, and so on. The professionals participating in

the post-survey interviews also highlighted that it was not uncommon that due to poor

planning and coordination among various trades on the construction site, construction

activities were suspended until getting responses, and the field staff were idle.

Page 222: building information modeling–based process transformation to improve productivity in the

202

7.2.4.2 Comparison among different BIMIR statuses

As shown in Table 7.6, out of the 73 surveyed building projects in Singapore, 15, 47,

and 11 belonged to BIMIR S1 (no BIM implementation), S2 (lonely BIM

implementation), and S3 (collaborative BIM implementation), respectively. This

section investigated the differences in the mean scores and rankings of the resulting

wastes between the three BIMIR groups.

As shown in Table 7.10, the WC mean scores ranged from 2.80 to 3.89 in the BIMIR

S1 group of building projects, from 2.70 to 3.69 in the S2 group of projects, and from

2.83 to 3.52 in the S3 group of projects. Overall, the mean values gradually decreased

as BIMIR status increased. The overall mean scores of the 13 wastes in the three

groups declined from 3.56 (S1) to 3.17 (S2) and further 3.13 (S3). Therefore, it was

concluded that BIM implementation could prevent the wastes from occurring, which

definitely enhanced productivity performance in the Singapore construction industry.

Thus, Hypothesis 3 that “the higher the BIMIR status, the lower the criticality of the

wastes and the higher the productivity performance” was supported.

Table 7.10 ANOVA results of the WC between BIMIR statuses

Code S1 (no BIM) S2 (lonely BIM) S3 (collaborative BIM) ANOVA

Criticality mean Rank Criticality mean Rank Criticality mean Rank p-value

W01 3.75 5 3.45 5 3.30 3 0.321

W02 3.81 4 3.45 4 3.52 1 0.364

W03 3.69 7 3.69 1 3.11 8 0.123

W04 3.72 6 3.49 2 3.14 5 0.200

W05 3.89 1 3.33 7 3.42 2 0.105

W06 3.81 2 3.45 6 3.08 9 0.045*

W07 3.44 9 2.98 8 3.11 7 0.141

W08 3.27 11 2.90 9 2.96 11 0.268

W09 3.25 12 2.70 13 2.83 13 0.047*

W10 3.59 8 2.77 12 3.12 6 0.007*

W11 3.41 10 2.80 10 2.89 12 0.060

W12 3.81 3 3.47 3 3.25 4 0.272

W13 2.80 13 2.77 11 3.01 10 0.757

Note: criticality = root square of the product of the impact on productivity and the

frequency of occurrence. *The mean score difference was significant at the 0.05 level.

Page 223: building information modeling–based process transformation to improve productivity in the

203

To test whether the mean scores differed between the three BIMIR status groups, the

one-way ANOVA were performed using SPSS. There are three main assumptions for

the ANOVA: (1) the wastes were normally distributed in each status group; (2) the

samples were independent in all the groups; and (3) homogeneity of variances in all

the groups. The first assumption was not an issue because the one-way ANOVA can

tolerate the data that are non-normal. Since the data were collected through an online

survey, the second assumption was also achieved. In the test of homogeneity of

variances, p-values of all the 13 wastes were greater than 0.05, so the null hypothesis

that the three groups had equal variances was accepted. Thus, the homogeneity of

variances was ensured in the three groups, and the third assumption was achieved.

It should be noted that with SPSS, unequal sample sizes in the three groups would not

harm the one-way ANOVA. Calculating sums of squares required different formulas

if the sample sizes were unequal, but SPSS could automatically use right ones. A

practical issue was that very unequal sample sizes might affect the “homogeneity of

variances” assumption. The ANOVA was considered robust to moderate departures

from this assumption, but the departure should be small when the sample sizes were

very different. According to Keppel and Wickens (2004), there was not a good rule of

thumb for the point at which unequal sample sizes made the heterogeneity of

variances a problem.

In addition, a post hoc test of the ANOVA could reveal detailed multiple comparisons

between any two groups. In SPSS, if equal variances (homogeneity of variances)

were assumed, post hoc tests such as least significant difference (LSD) could be used;

otherwise, tests such as Games-Howell should be used. In this study, the LSD method

was adopted because this method applied standard t-tests to all possible pairs of group

means. The results were presented in Table 7.11. The p-values below 0.05 indicated

that significant differences in the mean scores existed. The ANOVA results in Table

Page 224: building information modeling–based process transformation to improve productivity in the

204

7.10 showed that the mean scores of three wastes (W06, W09, and W10) significantly

differed between the three groups at the 0.05 level, and the multiple comparisons (see

Table 7.11) revealed that another four wastes (W03, W05, W07, and W11) also had

different mean scores between different groups. Since three groups were involved in

this study, this section would analyze and discuss the differences based on the

multiple comparison results.

Table 7.11 Post hoc test results for the wastes different between BIMIR statuses

Waste Multiple

comparisons

Mean

difference

p-

value

Waste Multiple

comparisons

Mean

difference

p-

value

W01 S1 S2 0.299 0.210 W08 S1 S2 0.371 0.107

S3 0.446 0.163 S3 0.310 0.312

S2 S3 0.147 0.583 S2 S3 -0.061 0.812

W02 S1 S2 0.357 0.157 W09 S1 S2 0.551 0.014*

S3 0.291 0.387 S3 0.417 0.157

S2 S3 -0.067 0.814 S2 S3 -0.134 0.587

W03a S1 S2 0.002 0.995 W10 S1 S2 0.822 0.002

*

S3 0.584 0.090 S3 0.466 0.179

S2 S3 0.583 0.046* S2 S3 -0.356 0.223

W04 S1 S2 0.228 0.340 W11a S1 S2 0.613 0.018

*

S3 0.578 0.074 S3 0.519 0.132

S2 S3 0.349 0.198 S2 S3 -0.094 0.744

W05a S1 S2 0.557 0.035

* W12 S1 S2 0.335 0.215

S3 0.467 0.182 S3 0.562 0.121

S2 S3 -0.090 0.759 S2 S3 0.227 0.456

W06 S1 S2 0.364 0.097 W13 S1 S2 0.029 0.918

S3 0.732 0.014* S3 -0.211 0.583

S2 S3 0.368 0.136 S2 S3 -0.240 0.459

W07a S1 S2 0.453 0.049

* – – – – –

S3 0.322 0.291 – – –

S2 S3 -0.131 0.610 – – – – aAdditional waste that was not statistically significant in the ANOVA (Table 7.10).

*The mean difference was significant at the 0.05 level.

The WC mean score of “reworks/abortive works” decreased by 0.583 from the

BIMIR S2 group (mean = 3.69, ranked top) to the S3 group (mean = 3.11, ranked

eighth). This was because that compared with lonely BIM implementation, a project

team that implemented BIM collaboratively targeted not only the design consultants

and the general contractor, but also plenty of trade contractors. Thus, the construction

planning of the trade contactors was incorporated into the team’s planning using

Page 225: building information modeling–based process transformation to improve productivity in the

205

BIM, and the site status could be reflected and continuously updated in the design

models virtually. As a result, clashes were often detected before actual construction

activities were carried out, and the quality of the activities was improved because of

fewer modifications and compromises on the project site (Fan et al., 2014),

significantly reducing the abortive works on site.

“Change orders” was ranked top in the S1 group (mean =3.89) and seventh in the S2

group (mean = 3.33). The difference of the mean scores between the two groups was

significant (0.557), implying that even lonely BIM implementation could drastically

reduce the influence of change orders on productivity performance. This was

probably because the owner’s intent was better represented in 3D design models

(Fischer et al., 2014), and thus fewer design errors, omissions, and additions were

needed in the construction stage.

“Activity delays” obtained a higher mean score in the S1 group (mean = 3.81, ranked

second) than that in the S3 group (mean = 3.08, ranked ninth), suggesting that as

BIMIR status became much higher, the WC score decreased by 0.732. Apart from

fewer reworks as mentioned earlier, collaborative BIM adoption involved key

contractors early, which facilitated quicker project layout planning, a higher

proportion of work using prefabrication, and more detailed scheduling. Thus,

schedule compliance could be guaranteed (Chelson, 2010; Fan et al., 2014).

“Overproduction/reproduction” received the mean scores of 3.44 (ranked ninth) and

2.98 (ranked eighth) in the S1 and S2 groups, respectively. This result indicated that

the WC score of this waste decreased by 0.453 when the project changed to

implement BIM. Accuracy of building objects is one of the most important

advantages in the 3D design models (Eastman et al., 2011). Given that the project

Page 226: building information modeling–based process transformation to improve productivity in the

206

schedule was well complied with, the team could have a better understanding of the

timing and the quantity of production.

The mean score of “unnecessary inventory” in the S1 group (mean =3.25, ranked

twelfth) was significantly higher than that in the S2 group (mean = 2.70, ranked

bottom), by 0.551. As mentioned above, the timing and the quantity of finished

elements were better understood with BIM implementation to avoid overproduction,

which would in return control the procurement of materials and the work under

production. As a result, an appropriate level of inventory was ensured.

“Excess processing beyond standard” obtained a significantly higher score in the S1

group (mean = 3.59, ranked eighth) than that in the S2 group (mean = 2.77, ranked

twelfth), decreasing by 0.822. Although the information fragmentation still existed

across the design stage and the construction stage in lonely BIM implementation, the

design models that represented the project outcomes as needed could provide clearer

specifications and more accurate documentation of construction intent. This ensured

that unneeded work processes may be reduced to some extent.

The mean scores of “unnecessary movement of people and equipment” in the S1

group (mean = 3.41, ranked eighth) was significantly higher than that in the S2 group

(mean = 2.80, ranked twelfth). When the contractors changed to use BIM, the better

project planning, such as quicker and optimized site layout, could be done ahead of

actual construction. Thus, field personnel were better guided in carrying out activities

on site, substantially reducing unneeded movements.

Furthermore, the Spearman’s rank correlation was conducted to check the WC

ranking difference between the three BIMIR status groups of building projects. As

shown in Table 7.12, the results indicated that despite significant differences in the

Page 227: building information modeling–based process transformation to improve productivity in the

207

WC mean scores and rankings of the seven resulting wastes, the correlation

coefficients between any two groups were greater than 0.5 and significant at the 0.05

level. Therefore, there were statistically significant agreement on the rankings of all

the 13 wastes between the three readiness groups. The BIMIR S1 group and S2 group

shared nine common wastes in their respective top 10 wastes, and the S2 group and

the S3 group shared eight common wastes.

Table 7.12 Spearman’s rank correlation results of the WC between BIMIR statuses

BIMIR Test statistics S1 (no BIM) S2 (lonely BIM) S3 (collaborative BIM)

S1 (no BIM) Correlation

coefficient

1.000 0.643 0.758

p-value – 0.018* 0.003

*

S2 (lonely BIM) Correlation

coefficient

– 1.000 0.582

p-value – – 0.037*

S3

(collaborative

BIM)

Correlation

coefficient

– – 1.000

p-value – – – *Correlation was significant at the 0.05 level (two-tailed).

7.2.5 Causes to NVA activities

The overall Cronbach’s alpha coefficient value of the data related to the importance

of the causes to the critical NVA activities was 0.971, implying high data reliability.

It was notable that the coefficient value of the “government agency” group was 0.635.

This was acceptable in this study because: (1) the threshold of 0.7 could decrease to

0.6 for newly-developed measures in exploratory research (Robinson et al., 1991);

and (2) the scale only included three items. Hair et al. (2009) revealed that positive

relationship to the number of items in the scale should be considered in assessing the

Cronbach’s alpha coefficient, and that decreasing the number of items will decrease

the coefficient value.

Page 228: building information modeling–based process transformation to improve productivity in the

208

7.2.5.1 Overall ranking

As shown in Table 7.13, the mean scores of the 53 causes to NVA activities ranged

from 3.27 to 4.00. These causes were ranked based on their overall mean scores.

Similar to the analysis of the 13 resulting wastes, the one-sample t-test was performed

to test whether these factors were statistically important causes to the critical NVA

activities identified earlier. The analysis results indicated that all the causes obtained

mean scores above 3.00, with p-values below 0.05. Thus, these factors significantly

caused the critical NVA activities in the current industry practices in Singapore.

Table 7.13 Importance ranking and t-test results of the causes to the NVA activities

Code Causes to NVA activities Mean Overall

rank

Internal

rank

p-

value

R1: Government agency (α = 0.635)

C1.01 Focusing on design stage by developing BIM

submission templates and guidelines

3.55 44 2 0.001*

C1.02 Mandating BIM submissions cannot guarantee

collaboration and best-for-project thinking

3.60 38 1 0.000*

C1.03 Unclear legislations and qualifications for

precasters (versus concreter) and inadequate

codes for OSM varieties

3.44 50 3 0.000*

R2: Owner (α = 0.870)

C2.01 Inertia against use of BIM or off-site

prefabrication

3.64 34 2 0.000*

C2.02 Establishing minimal apparent risk and

minimum first cost as crucial selection criteria

3.58 42 4 0.000*

C2.03 Unaware of the benefits of BIM and lifecycle

management

3.59 40 3 0.000*

C2.04 Creating incentives for individual firms to

protect their own interests

3.42 52 8 0.000*

C2.05 Awarding architectural and engineering design

contracts solely based on qualification

3.51 47 6 0.000*

C2.06 Setting vague goals with architect and rarely

passing them on to downstream parties

3.78 15 1 0.000*

C2.07 Focusing on assessing liability and risk transfers

using mechanisms such as guarantees and

penalties

3.53 45 5 0.000*

C2.08 Perceiving design fees for OSM as more

expensive than traditional process

3.44 50 7 0.000*

C2.09 Desire for particular structures or traditional

finishes

3.27 53 9 0.010*

R3: Architect/Engineers (α = 0.887)

C3.01 Because of potential liability, architect includes

fewer details in drawings or indicates that the

drawings cannot be relied on for dimensional

accuracy

3.66 31 10 0.000*

Page 229: building information modeling–based process transformation to improve productivity in the

209

C3.02 Architect does not model what contractors need

for QTOs

3.74 19 6 0.000*

C3.03 Not required by contract to share design models

with contractors

3.77 16 4 0.000*

C3.04 Design models/drawings fit for mandatory BIM

submissions, but not fit for intended

downstream use

4.00 1 1 0.000*

C3.05 Architect and engineers do not understand field

operations enough and lack construction input in

design

3.89 4 2 0.000*

C3.06 Lack of skilled BIM experts to engage 3.89 4 2 0.000*

C3.07 No complete knowledge of their design

decisions’ impact on construction

3.77 16 4 0.000*

C3.08 Architect and engineers spend much time and

effort locating, recreating, or transferring

fragmented information

3.71 22 7 0.000*

C3.09 Unless asked and encouraged, architect and

engineers do not consider lifecycle value of or

incremental changes

3.70 27 8 0.000*

C3.10 Limited expertise of OSM and its processes in

the market for architect and engineers

3.67 29 9 0.000*

C3.11 Downstream designers have to make extra

efforts to reconfigure or reformat data

3.66 31 10 0.000*

R4: General contractor/Key trade contractors (α = 0.962)

C4.01 General contractor not required by owner and

government to adopt BIM

3.62 37 18 0.000*

C4.02 General contractor only has 2D drawings or

incomplete 3D model shared from designers

3.71 22 11 0.000*

C4.03 General contractor has to make extra efforts to

reconfigure or reformat data

3.92 3 1 0.000*

C4.04 General contractor’s reluctance to adopt OSM 3.52 46 21 0.000*

C4.05 General contractor’s BIM team does modeling

but not coordination for trade contractors

3.71 22 11 0.000*

C4.06 General contractor requires but does not train

trade contractors to use BIM

3.60 38 19 0.000*

C4.07 Lack of skilled BIM experts to engage to help

construction manager and unable to see how

BIM benefit them

3.89 4 2 0.000*

C4.08 Training cost and high learning curve (initial

productivity loss) to use BIM

3.85 9 5 0.000*

C4.09 Reluctant and inexperienced to use BIM and

happy to continue using traditional CAD

3.88 7 3 0.000*

C4.10 Having little knowledge of BIM and do not

know how, when, and what to use it

3.75 18 9 0.000*

C4.11 Lack of national BIM standards and guidelines

for contractors

3.81 13 8 0.000*

C4.12 Doubt about the effectiveness of BIM because

of limited evidence

3.74 19 10 0.000*

C4.13 Afraid of the unknown and resistant to change

from comfortable daily routine

3.67 29 14 0.000*

C4.14 Lack of legal support from authority 3.49 48 22 0.000*

C4.15 Lack of tangible benefits of BIM to warrant its use 3.64 34 16 0.000*

C4.16 Not thinking of changing conventional methods

and no demand for BIM use

3.58 42 20 0.000*

Page 230: building information modeling–based process transformation to improve productivity in the

210

C4.17 Limited expertise of OSM and its processes in

the market for contractors

3.66 31 15 0.000*

C4.18 Trade contractors not required by general

contractor/owner/government to adopt BIM

3.64 34 16 0.000*

C4.19 High cost for trade contractors to engage BIM

experts or outsource to BIM drafters

3.71 22 11 0.000*

C4.20 Trade contractors only have 2D drawings or

incomplete 3D model shared from designers or

general contractor

3.84 10 6 0.000*

C4.21 Trade contractors have to make extra efforts to

reconfigure or reformat data

3.88 7 3 0.000*

C4.22 Trade contractors use CAD and cannot integrate

BIM models from general contractor into their

site models

3.84 10 6 0.000*

R5: Manufacturer/Supplier (α = 0.916)

C5.01 Does not permit design changes as these are

expensive once fabrication has commenced

3.95 2 1 0.000*

C5.02 Not required by owner/general

contractor/government to adopt BIM in

manufacture

3.71 22 5 0.000*

C5.03 Lack of skilled BIM experts to engage and

unable to see how BIM benefit them

3.82 12 2 0.000*

C5.04 Only 2D drawings or incomplete 3D model

shared from designers or general contractor

3.74 19 4 0.000*

C5.05 Training cost and high learning curve (initial

productivity loss) to use BIM

3.68 28 6 0.000*

C5.06 Reluctant and inexperienced to use BIM and

still happy to continue using CAD

3.81 13 3 0.000*

C5.07 Market protection from traditional

suppliers/manufacturers

3.49 48 7 0.000*

R6: Facility manager

C6.01 Not required by owner to use BIM and not

involved in design phase to contribute

knowledge

3.59 40 1 0.000*

*The one-sample t-test result was significant at the 0.05 level (two-tailed).

The causes with top 10 statistical significance were analyzed. In the

“Architect/Engineers” (R3) group, there were three leading causes with high

importance. Specifically, “design models/drawings fit for mandatory BIM

submissions, but not fit for intended downstream use” (C3.04, mean = 4.00) received

the highest overall rating among the 53 causes, and “architect and engineers do not

understand field operations enough and lack construction input in design” (C3.05,

mean = 3.89) was ranked fourth. These results indicated that the design consultants in

Singapore tended to focus on the regulatory submissions and did not have enough

time or construction knowledge to input sufficient precision and details in the design

Page 231: building information modeling–based process transformation to improve productivity in the

211

modeling or coordination for the contractors (Lam, 2014). In the post-survey

interviews, the professionals highlighted on-going change requests in their projects

and the importance of trade contractors in the design detailing and coordination.

Considering that the critical NVA activities related to “lack of involvement by

various downstream parties to contribute their insights in the design stage” were most

agreed upon by the local BIM experts, it was common that the design models were

purely created by the design consultants, and the high scores of such causes supported

the lonely BIM implementation in the construction industry. In addition, the cause

“lack of skilled BIM experts to engage” (C3.06, mean = 3.89) was also ranked fourth.

Similar to the cases studies conducted overseas (Chelson, 2010), BIM experts in

Singapore were not enough, and BIM operators were typically young, did not have

much site knowledge, and were not able to consider the downstream uses in the

design. The post-survey interviewees also emphasized that the design consultants

tended to lack enough fees that could allow them to engage BIM experts from the

market.

The cause “does not permit design changes as these are expensive once fabrication

has commenced” (C5.01, mean = 3.95) under the “Manufacturer/Supplier” (R5)

group obtained the second highest importance, indicating that large-scale

prefabrication of building components either commenced at a later stage or was not

based on the 3D design model. The professionals participating in the post-survey

interviews stated that the collaboration with manufacturers/suppliers led to productive

construction processes. However, due to the tight project schedule and costly

changes, the design was not fixed until the construction stage in the current project

delivery, which produced a number of NVA activities, such as “lack of involvement

by manufacturer/supplier” and “insufficient construction documentation”.

Page 232: building information modeling–based process transformation to improve productivity in the

212

The remaining highly ranked causes were under the “General contractor/Key trade

contractors” (R4) group. Among the top 10 causes, the third most important cause

was “general contractor has to make extra efforts to reconfigure or reformat data”

(C4.03, mean = 3.92). Based on the analysis of the aforementioned two causes (C3.04

and C3.05), the design consultants’ models were not created as the contractors had

usually built the building. Thus, it was not uncommon that the general contractor

needed to make repeated efforts (Sattineni and Mead, 2013). Moreover, “lack of

skilled BIM experts to engage to help construction manager and unable to see how

BIM benefit them” (C4.07, mean = 3.89) also occupied the fourth position in the

overall ranking, “training cost and high learning curve (initial productivity loss) to

use BIM” (C4.08, mean = 3.85) was ranked ninth, and “reluctant and inexperienced

to use BIM and happy to continue using traditional CAD” (C4.09, mean = 3.88)

received the seventh highest rating. As mentioned earlier, although some young

practitioners were equipped with BIM skillsets, the construction market was short of

experienced BIM experts who could use BIM to guide construction activities on site.

Also, the professionals involved in the post-survey interviews reported that such

experts were expensive in the current market. Due to the constraint of project budget,

the management tried to balance training cost and the benefits that BIM

implementation could add to the project. Therefore, confronted with the high costs

and initial productivity loss in first projects, the management may decide to use the

traditional CAD approach in most of the planning and construction processes. Hence,

these causes resulted in many NVA activities in the construction stage.

On the other hand, three leading causes were related to the trade contractors,

including “trade contractors have to make extra efforts to reconfigure or reformat data

” (C4.21, mean = 3.88, ranked seventh), “trade contractors only have 2D drawings or

incomplete 3D model shared from designers or general contractor” (C4.20, mean =

3.84, ranked tenth), and “trade contractors use CAD and cannot integrate BIM models

Page 233: building information modeling–based process transformation to improve productivity in the

213

from general contractor into their site models” (C4.22, mean = 3.84, occupied the

tenth position). Most of the trade contractors were SMEs who were usually still using

the traditional design tools and practices and did not care about the collaboration with

other trades on site, as advised by the interviewees. Meanwhile, since BIM was still

relatively new in the market and the cost was limited, it was not possible that the

trade contractors could train up enough BIM experts in the short term. Hence, the

constraints faced by the trade contractors would produce quite a number of NVA

activities in the current project delivery practices.

In terms of the internal rankings under each project role, apart from the top 10

important causes that were under three groups (R3 to R5), “mandating BIM

submissions cannot guarantee collaboration and best-for-project thinking” (C1.02,

mean = 3.60) received the highest rating under “Government agency” (R1).

Singapore is currently the only country that has mandated almost all public and

private building projects to implement BIM (Cheng and Lu, 2015; McAuley et al.,

2017). A local BIM expert participating in the post-survey interviews argued that

such mandate may lead some practitioners to implement BIM only for regulatory

approvals and continue to act as before. Thus, NVA activities were still produced.

Besides, “setting vague goals with architect and rarely passing them on to

downstream parties” (C2.06, mean = 3.78) was ranked top under the group of

“Owner” (R2), indicated that uncertainty of information and unwillingness to share

would create NVA activities, no matter whether BIM tools were used or not. Last but

not least, “not required by owner to use BIM and not involved in design phase to

contribute knowledge” (C6.01, mean = 3.59) was the only important cause identified

under “Facility manager” (R6) in this study. The contract with the operations and

maintenance team was directly responsible for those NVA activities related to

operations and maintenance.

Page 234: building information modeling–based process transformation to improve productivity in the

214

7.2.5.2 Comparison among different BIMIR statuses

Similar to the resulting wastes, the importance of the leading causes to the critical

NVA activities was likely to differ between different BIMIR groups. Thus, this

section investigated the differences in the mean scores and rankings of the leading

cause between the three BIMIR status groups of building projects.

As shown in Table 7.14, the importance mean scores ranged from 3.13 to 4.33 in the

BIMIR S1 group of building projects, from 3.34 to 4.11 in the S2 group of building

projects, and from 2.64 to 3.82 in the S3 group of building projects. Overall, the

higher the BIMIR status, the lower the mean scores. Thus, the causes became less and

less important when BIM was increasingly implemented in the surveyed building

projects in Singapore.

Table 7.14 ANOVA results of the causes between BIMIR statuses

Causes to

NVA

activities

S1 (no BIM) S2 (lonely BIM) S3 (collaborative

BIM)

ANOVA

Mean Overall

rank

Internal

rank

Mean Overall

rank

Internal

rank

Mean Overall

rank

Internal

rank

p-value

R1: Government agency

C1.01 3.33 51 3 3.66 40 2 3.36 10 1 0.616

C1.02 3.40 47 2 3.72 30 1 3.36 10 1 0.482

C1.03 3.67 31 1 3.45 52 3 3.09 25 3 0.297

R2: Owner

C2.01 3.80 24 3 3.68 38 3 3.27 15 3 0.308

C2.02 3.60 35 4 3.60 47 5 3.45 6 1 0.865

C2.03 3.53 40 5 3.70 34 2 3.18 18 4 0.322

C2.04 3.33 51 8 3.53 49 6 3.09 25 7 0.383

C2.05 3.47 44 6 3.66 40 4 2.91 42 9 0.028*

C2.06 3.87 15 1 3.85 22 1 3.36 10 2 0.202

C2.07 3.87 15 1 3.51 51 8 3.18 18 4 0.211

C2.08 3.47 44 6 3.53 49 6 3.00 36 8 0.253

C2.09 3.13 53 9 3.34 53 9 3.18 18 4 0.689

R3: Architect/Engineers

C3.01 4.00 11 6 3.66 40 10 3.18 18 8 0.142

C3.02 4.20 3 3 3.81 28 5 2.82 49 11 0.002*

C3.03 4.20 3 3 3.70 34 8 3.45 6 4 0.141

C3.04 4.33 1 1 4.04 3 1 3.36 10 6 0.014*

C3.05 3.87 15 7 3.91 15 3 3.82 1 1 0.955

C3.06 3.73 26 10 4.04 3 1 3.45 6 4 0.141

C3.07 3.67 31 11 3.85 22 4 3.55 4 2 0.478

Page 235: building information modeling–based process transformation to improve productivity in the

215

C3.08 4.07 10 5 3.72 30 6 3.18 18 8 0.031*

C3.09 3.87 15 7 3.68 38 9 3.55 4 2 0.620

C3.10 3.80 24 9 3.72 30 6 3.27 15 7 0.220

C3.11 4.27 2 2 3.64 44 11 2.91 42 10 0.002*

R4: General contractor /Key trade contractors

C4.01 3.60 35 13 3.62 46 22 3.64 2 1 0.996

C4.02 3.87 15 6 3.83 25 16 3.00 36 11 0.036*

C4.03 4.20 3 1 3.94 11 8 3.45 6 2 0.106

C4.04 3.53 40 16 3.66 40 21 2.91 42 14 0.080

C4.05 3.73 26 9 3.87 21 15 3.00 36 11 0.027*

C4.06 3.87 15 6 3.70 34 19 2.82 49 19 0.021*

C4.07 4.20 3 1 3.98 8 5 3.09 25 5 0.002*

C4.08 3.73 26 9 4.06 2 2 3.09 25 5 0.011*

C4.09 3.87 15 6 4.11 1 1 2.91 42 14 0.001*

C4.10 3.40 47 20 4.00 5 3 3.18 18 4 0.007*

C4.11 3.60 35 13 4.00 5 3 3.27 15 3 0.096

C4.12 3.73 26 9 3.94 11 8 2.91 42 14 0.005*

C4.13 3.40 47 20 3.94 11 8 2.91 42 14 0.008*

C4.14 3.40 47 20 3.72 30 18 2.64 53 22 0.012*

C4.15 3.47 44 19 3.91 15 11 2.73 52 21 0.003*

C4.16 3.67 31 12 3.70 34 19 2.91 42 14 0.083

C4.17 3.53 40 16 3.89 19 13 2.82 49 19 0.003*

C4.18 3.53 40 16 3.83 25 16 3.00 36 11 0.044*

C4.19 3.60 35 13 3.89 19 13 3.09 25 5 0.059

C4.20 4.00 11 5 3.96 10 7 3.09 25 5 0.020*

C4.21 4.13 8 3 3.98 8 5 3.09 25 5 0.016*

C4.22 4.13 8 3 3.91 15 11 3.09 25 5 0.017*

R5: Manufacturer/Supplier

C5.01 4.20 3 1 3.94 11 2 3.64 2 1 0.261

C5.02 3.87 15 4 3.74 29 6 3.36 10 2 0.408

C5.03 3.73 26 5 4.00 5 1 3.18 18 3 0.035*

C5.04 3.93 14 3 3.83 25 5 3.09 25 4 0.041*

C5.05 3.60 35 7 3.85 22 4 3.09 25 4 0.079

C5.06 4.00 11 2 3.91 15 3 3.09 25 4 0.025*

C5.07 3.67 31 6 3.55 48 7 3.00 36 7 0.239

R6: Facility manager

C6.01 3.87 15 1 3.64 44 1 3.00 36 1 0.093 *The mean difference was significant at the 0.05 level.

To check the differences in the mean scores between the three BIMIR status groups,

the one-way ANOVA and its post hoc test were conducted. The p-values below 0.05

indicated the significant differences in the mean scores. Similar to the ANOVA

conducted in Section 7.2.4.2, out of the three main assumptions, the first and second

assumptions were achieved with no doubt. The third assumption (homogeneity of

variances in the three groups) should be checked. In the test of homogeneity of

variances, 51 out of the 53 causes obtained p-values over 0.05 and two (C1.02 and

Page 236: building information modeling–based process transformation to improve productivity in the

216

C4.07) below 0.05. Thus, the null hypothesis that the three groups had equal

variances could not be determined, and more actions needed to be performed.

In SPSS, two types of post hoc tests can be performed. In this one-way ANOVA, the

LSD method was selected under “Equal Variances Assumed”, and the Games-Howell

method was adopted under “Equal Variances Not Assumed”. It was found that the

statistically significant differences resulted from the Games-Howell method were

completely included in those resulted from the LSD method. Therefore, the post hoc

test results of the LSD method were used in the subsequent data analysis, as shown in

Table 7.15. It was concluded that the homogeneity of variances was ensured in the

three groups and the third assumption was achieved.

Table 7.15 Post hoc test results for the causes different between BIMIR statuses

Cause Multiple comparisons Mean difference p-value

R2: Owner

C2.05 S1 S2 -0.193 0.431

S3 0.558 0.092

S2 S3 0.750 0.008*

R3: Architect/Engineers

C3.01a S1 S2 0.340 0.269

S3 0.818 0.049*

S2 S3 0.478 0.170

C3.02 S1 S2 0.391 0.170

S3 1.382 0.000*

S2 S3 0.990 0.003*

C3.04 S1 S2 0.291 0.239

S3 0.970 0.004*

S2 S3 0.679 0.017*

C3.08 S1 S2 0.343 0.166

S3 0.885 0.009*

S2 S3 0.542 0.055

C3.11 S1 S2 0.628 0.028*

S3 1.358 0.001*

S2 S3 0.729 0.024*

R4: General contractor/Key trade contractors

C4.02 S1 S2 0.037 0.899

S3 0.867 0.028*

S2 S3 0.830 0.013*

C4.03a S1 S2 0.264 0.314

S3 0.745 0.036*

S2 S3 0.482 0.106

Page 237: building information modeling–based process transformation to improve productivity in the

217

C4.04a S1 S2 -0.126 0.665

S3 0.624 0.113

S2 S3 0.750 0.025*

C4.05 S1 S2 -0.139 0.620

S3 0.733 0.054

S2 S3 0.872 0.007*

C4.06 S1 S2 0.165 0.584

S3 1.048 0.011*

S2 S3 0.884 0.011*

C4.07 S1 S2 0.221 0.362

S3 1.109 0.001*

S2 S3 0.888 0.002*

C4.08 S1 S2 -0.330 0.243

S3 0.642 0.092

S2 S3 0.973 0.003*

C4.09 S1 S2 -0.240 0.390

S3 0.958 0.012*

S2 S3 1.197 0.000*

C4.10 S1 S2 -0.600 0.026*

S3 0.218 0.538

S2 S3 0.818 0.008*

C4.11a S1 S2 -0.400 0.211

S3 0.327 0.443

S2 S3 0.727 0.046*

C4.12 S1 S2 -0.203 0.450

S3 0.824 0.024*

S2 S3 1.027 0.001*

C4.13 S1 S2 -0.536 0.082

S3 0.491 0.231

S2 S3 1.027 0.004*

C4.14 S1 S2 -0.323 0.310

S3 0.764 0.075

S2 S3 1.087 0.003*

C4.15 S1 S2 -0.448 0.139

S3 0.739 0.070

S2 S3 1.188 0.001*

C4.16a S1 S2 -0.035 0.910

S3 0.758 0.075

S2 S3 0.793 0.028*

C4.17 S1 S2 -0.360 0.193

S3 0.715 0.055

S2 S3 1.075 0.001*

C4.18 S1 S2 -0.296 0.315

S3 0.533 0.178

S2 S3 0.830 0.015*

C4.19a S1 S2 -0.294 0.329

S3 0.509 0.207

S2 S3 0.803 0.020*

C4.20 S1 S2 0.043 0.878

S3 0.909 0.016*

S2 S3 0.867 0.007*

C4.21 S1 S2 0.155 0.592

S3 1.042 0.008*

Page 238: building information modeling–based process transformation to improve productivity in the

218

S2 S3 0.888 0.008*

C4.22 S1 S2 0.218 0.438

S3 1.042 0.007*

S2 S3 0.824 0.011*

R5: Manufacturer/Supplier

C5.03 S1 S2 -0.267 0.337

S3 0.552 0.140

S2 S3 0.818 0.011*

C5.04 S1 S2 0.104 0.704

S3 0.842 0.023*

S2 S3 0.739 0.018*

C5.05a S1 S2 -0.251 0.402

S3 0.509 0.205

S2 S3 0.760 0.027*

C5.06 S1 S2 0.085 0.759

S3 0.909 0.016*

S2 S3 0.824 0.010*

R6: Facility manager

C6.01a S1 S2 0.228 0.452

S3 0.867 0.036*

S2 S3 0.638 0.065 aAdditional cause that was not statistically significant in the ANOVA (Table 7.14).

*The mean difference was significant at the 0.05 level.

As indicated in Table 7.15, the post hoc tests revealed that the mean scores of 32

causes significantly differed between the three groups at the 0.05 level. Since a great

number of causes were identified in the tests, this study explained the causes in

categories rather than discussed them one by one.

It is notable that out of the 32 causes, only two causes (C3.11 and C4.10) were

different between the BIMIR S1 group and S2 group of building projects.

Specifically, “downstream designers have to make extra efforts to reconfigure or

reformat data ” (C3.11) received the second highest rating (mean = 4.27) and a low

score (mean = 2.98, ranked 44th) in the BIMIR S1 and S2 groups, respectively. This

result was consistent with the NVA activity “architect does not share its complete

model with engineers in the schematic phase” that according to the survey results,

was not perceived critical in the Singapore construction industry. The architect

usually shared CAD-like documents and probably its design model with the

engineers, while the engineers may tend to complete their design work using the

Page 239: building information modeling–based process transformation to improve productivity in the

219

traditional way. Thus, the need for the engineers to reconfigure data was not closely

associated with BIM implementation, but with the collaboration within the design

consultant team. Meanwhile, “having little knowledge of BIM and do not know how,

when, and what to use it” (C4.10) was ranked 47th in the S1 group (mean = 3.40) and

fifth in the S2 group (mean = 4.00). The difference of the mean scores was significant

(-0.600), implying that compared with years ago, local firms now already had some

knowledge and experience of BIM implementation. Therefore, the issues regarding

how, when, and what to perform BIM work processes had been somewhat addressed,

resulting in fewer NVA activities. Furthermore, since there was still weak

collaboration in terms of the whole project team, the importance ratings of other

causes did not significantly change. In contrast, because of the collaboration among

the major stakeholders that implemented their part of BIM, the majority of the causes

(the remaining 30 causes) had statistically become less important between the S1

group and the S3 group as well as between the S2 group and the S3 group.

The one-way ANOVA results were also supported by the Spearman’s rank

correlation between the three BIMIR groups. As shown in Table 7.16, the correlation

coefficient value between the BIMIR S1 group and the BIMIR S2 group was 0.277,

significant at the 0.05 level. The statistical significance indicated that overall the

rankings in the two groups were correlated and agreed upon, although there were still

differences in between suggested by the minor correlation coefficient (0.277). On the

contrary, the coefficient values between the S1 group and the S3 group as well as

between the S2 group and the S3 group were not significant, implying that most of

the causes were no longer important in the S3 group of building projects.

BIMIR status is a “snapshot” of BIM implementation which would be influenced by

the interactions between the hindrances to and drivers for BIM implementation.

Page 240: building information modeling–based process transformation to improve productivity in the

220

Therefore, the analysis of the hindering and driving factors of BIM implementation

are presented in the subsequent sections.

Table 7.16 Spearman’s rank correlation of the causes between BIMIR statuses

BIMIR status Test statistics S1 (no BIM) S2 (lonely BIM) S3 (collaborative BIM)

S1 (no BIM) Correlation

coefficient

1.000 0.277 0.180

p-value – 0.045* 0.196

S2 (lonely

BIM)

Correlation

coefficient

– 1.000 0.035

p-value – – 0.802

S3

(collaborative

BIM)

Correlation

coefficient

– – 1.000

p-value – – – *Correlation was significant at the 0.05 level (two-tailed).

7.3 Analysis Results and Discussions of Survey II

7.3.1 Profile of respondents and their organizations

Survey II intended to identify the critical factors that hindered and drove BIM

implementation in building projects in Singapore. From May to August 2016, the

final questionnaires were sent to the remaining 659 out of the 1318 organizations as

well as the 33 organizations that responded to survey I and were willing to participate

in Survey II. Finally, 89 completed questionnaires were received, yielding a response

rate of 12.86% which fell within the general response rate of 10%–15% for Singapore

surveys (Teo et al., 2007). The profile of the 89 respondents and their organizations is

presented in Table 7.17.

Table 7.17 Profile of the respondents and their organizations in Survey II

Characteristics Categorization Frequency Percentage (%)

Organization

Main business Architectural firm 18 20.2

Structural engineering firm 6 6.7

MEP engineering firm 13 14.6

General construction firm 30 33.7

Trade construction firm 3 3.4

Facility management firm 3 3.4

Others 16 18.0

Page 241: building information modeling–based process transformation to improve productivity in the

221

BCA financial grade A1 27 30.3

A2 2 2.2

B1 1 1.1

C1 1 1.1

C3 3 3.4

Single grade 2 2.2

L6 5 5.6

L3 1 1.1

Not applicable 47 52.8

Years of BIM adoption 0 year 10 11.2

1-3 years 42 47.2

4-5 years 22 24.7

6-10 years 13 14.6

Over 10 years 2 2.2

Respondent

Discipline Government agent 2 2.2

Developer 6 6.7

Architect 22 24.7

Structural designer 9 10.1

MEP designer 9 10.1

General contractor 28 31.5

Trade contractor 6 6.7

Supplier/Manufacturer 2 2.2

Facility manager 5 5.6

Years of experience 5-10 years 40 44.9

11-15 years 11 12.4

16-20 years 8 9.0

21-25 years 9 10.1

Over 25 years 21 23.6

In terms of the respondent organizations, 30 (33.7%) of the organizations were

general construction firms, followed by 18 (20.2%) architectural firms, 13 (14.6%)

MEP engineering firms, six (6.7%) structural engineering firms, three (3.4%) trade

construction firms, and three (3.4%) facility management firms, respectively. In

addition, the 16 organizations listed in the “others” category included the BCA, the

HDB, developers, precasters, and other consultancy firms such as multidisciplinary

consultancy firms, a project management consultancy firm, and a BIM consultancy

firm. Thus, the sample had a good balance of different industry players, and the

respondent organizations were representative of the key BIM implementers in the

construction value chain.

Page 242: building information modeling–based process transformation to improve productivity in the

222

When the organizations were measured by the financial grades in the contractors

registry of the BCA, 42 (47.2%) of the surveyed organizations were registered

contractors. Among which, 27 (30.3%), five (5.6%), two (2.2%), two (2.2%), and one

(1.1%) held the grades of A1, L6, A2, single grade, and B1, respectively. Because of

similar reasons with the questionnaire Survey I, there were also small- and medium-

sized contractors (three for C3, one for C1, and one for L3). The rest 47 (52.8%)

organizations included government agencies, developers, and various consultancy

firms.

Regarding the BIM implementation experience, about half (47.2%) of the

organizations had one to three years’ experience in their building projects in

Singapore, followed by 22 (24.7%) and 13 (14.6%) organizations having four to five

years and six to ten years’ experience, respectively. Only two firms had implemented

BIM in their building projects for more than 10 years. Since the mandatory BIM

implementation took effect in July 2015, it was considered reasonable that over half

(58.4%) of the organizations had just started to implement BIM in last three years.

Those organizations that had no BIM implementation experience in Singapore were

included in the following data analysis. In addition to the reason stated in Section

7.2.1, the 10 professionals should have a say in “which factors among the 47 potential

hindrances and 32 potential drivers should be considered when implementing BIM in

the near future projects”. Thus, their ratings were also important. This provided clear

evidence that the local construction industry had been moving from traditional project

delivery into BIM-based project delivery, and was shifting to industry-wide BIM

implementation. Thus, the data could reflect the views of key BIM users on the

hindrances to and drivers for change towards full BIM implementation in the

Singapore construction industry, thus assuring the response quality.

Page 243: building information modeling–based process transformation to improve productivity in the

223

In terms of the respondents, the top three disciplines were: general contractor

(31.5%), architect (24.7%), and structural designer (10.1%) and MEP designer

(10.1%), while there were only two (2.2%) government agents and manufacturers

(suppliers), respectively. In addition, 55.1% of the respondents had over 10 years’

experience in the construction industry, and 30 (33.7%) of them had worked over 20

years.

Similar to the interviews conducted after Survey I, post-survey interviews were

performed to solicit comments on the hindrances to and drivers for BIM

implementation, especially those that were not found statistically significant. The

profile of the interviewees who had originally participated in Survey II and had more

than three years’ BIM implementation experience in Singapore was presented in

Table 7.18. The experts commented that overall the findings of this survey were

reasonable. There comments were used to support the explanation of the hindering

and driving factors as well as the exclusion of insignificant factors.

Table 7.18 Profile of the interviewees in Survey II

Interviewee Work experience Designation Firm

1 15 years Project manager General construction firm

2 5 years Quantity surveyor General construction firm

3 10 years Senior engineer MEP consultancy firm

4 8 years Quantity surveying in

charge

General construction firm

5 11 years Deputy contracts manager Construction and

development firm

7.3.2 Hindrances to change towards full BIM implementation

7.3.2.1 Overall ranking

As shown in Table 7.19, the data related to the respondents’ perceptions of the

hindrances’ influence on BIM implementation in building projects in Singapore

obtained the Cronbach’s alpha coefficient value of 0.974, showing high data

Page 244: building information modeling–based process transformation to improve productivity in the

224

reliability. The mean scores of the 47 hindrances to BIM implementation ranged from

3.17 to 3.79, and these hindrances were ranked based on their mean scores. To test

whether the hindrances had statistically significant influence on BIM implementation,

the one-sample t-test was performed. The test results implied that BIM

implementation in building projects in Singapore was negatively affected by 44

critical hindrances to change (CHCs). The ranking of the CHCs could enable the

practitioners to understand which areas of activities of BIM implementation are

worthwhile to pay more attention to and to prioritize for resource investments.

Table 7.19 Significance ranking and t-test results of the hindrances to change

Code Hindrances to change towards full BIM implementation Mean Rank p-

value

H01 Executives failing to recognize the value of BIM-based

processes and needing training

3.64 8 0.000*

H02 Concerns over or uninterested in sharing liabilities and

financial rewards

3.48 21 0.000*

H03 Construction lawyers and insurers lacking understanding of

roles/responsibilities in new process

3.26 41 0.028*

H04 Lack of skilled employees and need for training them on

BIM and OSM

3.69 3 0.000*

H05 Industry’s conservativeness, fear of the unknown, and

resistance to change comfortable routines

3.69 3 0.000*

H06 Employees still being reluctant to use new technology after

being pushed to training programs

3.42 28 0.001*

H07 Entrenchment in 2D drafting and unfamiliarity to use BIM 3.69 3 0.000*

H08 Financial benefits cannot outweigh implementation and

maintenance costs

3.37 33 0.004*

H09 Lack of sufficient evidence to warrant BIM use 3.54 13 0.000*

H10 Liability of BIM such as the liability for common data for

subcontractors

3.33 37 0.010*

H11 Resistance to changes in corporate culture and structure 3.43 23 0.001*

H12 Need for all key stakeholders to be on board to exchange

information

3.79 1 0.000*

H13 Lack of trust/transparency/communication/partnership and

collaboration skills

3.33 37 0.009*

H14 BIM operators lacking field knowledge 3.62 11 0.000*

H15 Field staff dislike BIM coordination meetings looking at a

screen

3.43 23 0.000*

H16 Lack of consultants’ feedbacks on subcontractors’ model

coordination

3.34 35 0.005*

H17 Few benefits from BIM go to designers while most to

contractors and owners

3.17 46 0.178

H18 Lack of legal support from authorities 3.20 45 0.083

H19 Lack of owner request or initiative to adopt BIM 3.43 23 0.001*

H20 Decision-making depending on relationships between 3.28 40 0.019*

Page 245: building information modeling–based process transformation to improve productivity in the

225

project stakeholders

H21 Owners set minimal risk and minimum first cost as crucial

selection criteria

3.35 34 0.003*

H22 Poor knowledge of using OSM and assessing its benefits 3.34 35 0.002*

H23 Requiring higher onsite skills to deal with low tolerance

OSM interfaces

3.42 28 0.000*

H24 OSM relies on suppliers to train contractors to install

correctly

3.26 41 0.037*

H25 Owners’ desire for particular structures or finishes when

considering OSM

3.17 46 0.152

H26 Market protection from traditional suppliers/manufacturers

and limited OSM expertise

3.42 28 0.001*

H27 Contractual relationships among stakeholders and need for

new frameworks

3.71 2 0.000*

H28 Traditional contracts protect individualism rather than best-

for-project thinking

3.65 7 0.000*

H29 Lack of effective data interoperability between project

stakeholders

3.43 23 0.000*

H30 Owners cannot receive low-price bids if requiring 3D

models

3.31 39 0.012*

H31 Firms’ unwillingness to invest in training due to initial cost

and productivity loss

3.63 10 0.000*

H32 Assignment of responsibility/risk to constant updating for

broadly accessible BIM information

3.52 17 0.000*

H33 Lack of standard contracts to deal with responsibility/risk

assignment and BIM ownership

3.54 13 0.000*

H34 BIM model issues (e.g., ownership and management) 3.53 15 0.000*

H35 Poor understanding of OSM process and its associated costs 3.51 19 0.000*

H36 OSM requires design to be fixed early using BIM 3.49 20 0.000*

H37 Seeing design fees of OSM as more expensive than

traditional process

3.45 22 0.000*

H38 Difficulty in logistics and stock management of OSM 3.40 31 0.001*

H39 Unclear legislations and qualifications for precasters and

inadequate codes for OSM varieties

3.25 43 0.024*

H40 Interpretations resulted from unclear contract documents 3.39 32 0.000*

H41 Using monetary incentive for team collaboration results in

blaming rather than resolving issues

3.22 44 0.041*

H42 Costly investment in BIM hardware and software solutions 3.66 6 0.000*

H43 Interoperability issues such as software selection and

insufficient standards

3.52 17 0.000*

H44 Need for increasingly specialized software for specialized

functions

3.43 23 0.000*

H45 Difficulty in multi-discipline and construction-level

integration

3.53 15 0.000*

H46 Technical needs for multiuser model access in multi-

discipline integration

3.64 8 0.000*

H47 Firms cannot make most use of IFC and use proprietary

formats

3.56 12 0.000*

Note: Cronbach’s alpha coefficient value = 0.974. *The one-sample t-test result was significant at the 0.05 level (two-tailed).

Page 246: building information modeling–based process transformation to improve productivity in the

226

The top rank of “need for all key stakeholders to be on board to exchange

information” (H12, mean = 3.79) echoed previous studies (El Asmar et al., 2013;

Forsythe et al., 2015) which found that the early involvement of all the major

stakeholders in a building project, especially the contractors, in the design stage to

share expertise and information is critical to creating and fixing optimal design

models early. Such models help solve the potential issues that would traditionally

occur during construction, and pave the way for the collaboration among the

stakeholders in later stages. The widely-accepted definition of BIM proposed by the

NBIMS committee stated that “a basic premise of BIM is collaboration by different

stakeholders at different phases of the life cycle of a facility to insert, extract, update

or modify information in the BIM to support and reflect the roles of that stakeholder”

(NBIMS, 2007). This survey result was also consistent with the finding of Kent and

Becerik-Gerber (2010) that the involvement of the manufacturers (suppliers) and

trade contractors was limited in the design stage. BIM implementation would be

efficient if the entire team ranging from the owner, the design consultants, to the

specialty contractors could actively participate and contribute from the early design

stage throughout project completion.

“Contractual relationships among stakeholders and need for new frameworks” (H27,

mean = 3.71) was the second most significant hindrance, indicating that the

temporary contractual structure in building projects in Singapore was not

collaborative and posed challenges in collaborative BIM implementation. This

finding was in line with the finding of Fischer et al. (2014) that as disputes raised, the

lack of new frameworks would easily thrust the primary participants into adversarial

positions. Often the parties’ only recourse was to claim, which would force them to

act in their own best interests, crippling the project team (AIA and AIACC, 2007).

For example, the downstream parties, if involved upfront, would work at risk upfront

Page 247: building information modeling–based process transformation to improve productivity in the

227

in a financial manner and lack motivation and enthusiasm to work collaboratively

with others (Ross et al., 2006).

“Lack of skilled employees and need for training them on BIM and OSM” (H04,

mean = 3.69) was ranked third in the overall ranking, implying that the Singapore

construction industry still suffered from the lack of skilled personnel who could lead

BIM modeling and management teams. The employees tended to be reluctant to

adopt the new technology and participate in the new workflow (Zahrizan et al., 2013).

One example of such reluctance was that many firms could not take advantage of the

commonly-used data exchange format (IFC) and still used proprietary formats, which

would not enable smooth data exchange with other team members. In addition, the

experts involved in the post-survey interviews highlighted the concern about the

management’s willingness to train their employees.

“Industry’s conservativeness, fear of the unknown, and resistance to change

comfortable routines” (H05, mean = 3.69) occupied the third position in the overall

ranking, suggesting that such negative mindsets and behaviors were rooted in the

local construction industry. This value proposition established conservative and

unsupportive culture of most firms, significantly hindering local BIM

implementation. This finding was consistent with previous studies (Khosrowshahi

and Arayici, 2012; Zahrizan et al., 2013) which found inadequate marginal utility to

be realized by using BIM. The stakeholders tended to be conservative and reluctant to

change their customized ways of working and blaming. Although the executives of

many firms changed to use 3D tools, their leadership style appealed to continue to

keep a 2D mindset.

“Entrenchment in 2D drafting and unfamiliarity to use BIM” (H07, mean = 3.69)

were also ranked third, revealing that many firms in Singapore had little expertise and

Page 248: building information modeling–based process transformation to improve productivity in the

228

experience in implementing BIM. This was in agreement with the survey result that

58.4% of the responding firms had no more than three years’ BIM experience, and

with the finding of Kiani et al. (2015) that many firms were satisfied with their

conventional work methods to complete their work and therefore saw BIM uses as

extra efforts. For example, upfront BIM operators tended to lack enough field

knowledge to know what they were modeling and its constraint in the actual

construction; as a result, the digital models may not be developed correctly.

“Costly investment in BIM hardware and software solutions” (H42, mean = 3.66)

received the sixth highest rating, implying that costly BIM infrastructure significantly

hindered BIM implementation. In the post-survey interviewees, the experts reported

that currently the hardware in offices may not be powerful enough to run relevant

BIM software at an efficient speed. For example, huge file sizes and required storage

space as well as high speed data transmission between users would pose challenges to

the current office environment. Although half of the initial purchase cost of the

hardware and software solutions were subsidized by the local government,

subsequent upgrading or subscription fees would be no longer funded.

“Traditional contracts protect individualism rather than best-for-project thinking”

(H28, mean = 3.65) was ranked seventh among the 47 hindrances. As mentioned

earlier, even BIM technology has been used by the design consultants and possibly

the contractors, the technological process has been suffering from physical and

information fragmentation in different stages of the project. The creation, integration,

and use of digital design models would potentially raise many liability issues under

the traditional contracts. This was because little collaboration was built within the

project team (Lam, 2014). For example, the upfront parties were cautious about

providing incomplete or wrong design information to the downstream parties

(Eastman et al., 2011), whereas the latter was anxious about providing professional

Page 249: building information modeling–based process transformation to improve productivity in the

229

advice in the design modeling due to potential liabilities (AIACC, 2014). Such issues

urged the roles and responsibilities to be established in standard contracts. Although

the BIM Particular Conditions in Singapore has been drafted (BCA, 2015b), the main

form of contract in Singapore was still based on the adversarial system, leading to

individualism and isolated working environment.

“Executives failing to recognize the value of BIM-based processes and needing

training” (H01, mean = 3.64) occupied the eighth position in the overall ranking. This

result substantiated the finding of Khosrowshahi and Arayici (2012) that the

executives of the primary participants may be unwilling to change when they had

long been psychologically entrenched in the traditional drafting practices. BIM

implementation requires not only powerful infrastructure, but also competent and

experienced personnel that could be trained or engaged from the market (Anumba et

al., 2010). The local practitioners needed training and technical support in practice as

most of them were not knowledgeable and experienced about a higher level of BIM

implementation. In most cases, the executives can determine the allocation of the

capital investment to purchase and upgrade the infrastructure, and the sponsorship of

training programs (Zhao et al., 2014a). However, the experts participating in the post-

survey interviews revealed that the management of many firms tended to ensure

things under control as they previously did, because the cost and benefits of BIM

implementation were difficult to estimate and foresee. Thus, without the executive

support, training sessions could not be arranged, and a higher resource allocation

priority could not be obtained, leading to the lack of supporting resources and

expertise among the major stakeholders.

“Technical needs for multiuser model access in multi-discipline integration” (H46,

mean = 3.64) was ranked eighth. This result was consistent with previous studies

(Azhar et al., 2014; Juan et al., 2017) which found that multi-discipline model

Page 250: building information modeling–based process transformation to improve productivity in the

230

integration would require technical expertise, protocols, and advanced infrastructure

for multiuser model access. The post-survey interviewees also pointed out that

different parties tended to use various software or software versions, which created a

difficulty in integrating digital models across disciplines.

“Firms’ unwillingness to invest in training due to initial cost and productivity loss”

(H31, mean = 3.63) obtained the tenth position, indicated that the local practitioners

did not actively invest in training their staff and adopting new technologies. The post-

survey interviewees emphasized the importance of financial capabilities. While the

biggest firms were able to ride on the BIM wave, a huge number of SMEs and foreign

firms based in Singapore faced adoption challenges such as lacking the capital

investment for BIM tools and trainings to build up BIM expertise (Lam, 2014;

Forsythe et al., 2015).

In addition, the three insignificant hindrances were analyzed. It has been verified in

numerical studies and projects that BIM implementation have many benefits, such as

facilitating information integration across the project lifecycle as well as close

collaboration among the primary participants (Rezgui et al., 2013). It may be still

biased or ignored that such benefits could reduce plenty of wastes such as RFIs. In

this regard, less manpower would be needed in the whole project team, which could

support the exclusion of “few benefits from BIM go to designers while most to

contractors and owners” (H17). Moreover, Singapore has been one of the leading

countries in terms of developing BIM implementation standards (Cheng and Lu,

2015), specifying the local industry to use BIM by mandates, and equipping the firms

with BIM capabilities by subsidizing part of their purchasing, training, and

consultancy fees (BCA, 2016). Thus, “lack of legal support from authorities” (H18)

was not a significant hindrance. Furthermore, one possible explanation for excluding

“owners’ desire for particular structures or finishes when considering OSM” (H25)

Page 251: building information modeling–based process transformation to improve productivity in the

231

was that this hindrance was related to the owner’s special requirement of OSM,

which was drastic. Also, the experts suggested that such particular desire would not

seriously affect the design modeling as long as the owner expresses clearly and early.

7.3.2.2 Comparison among different stakeholders

This section investigated the differences in the mean scores and rankings of the CHCs

among different stakeholders. In this study, based on the BCA financial grades in

Table 7.17, the responding organizations were categorized into two groups: upfront

stakeholders and downstream stakeholders. The former consisted of government

agencies, developers, and consultancy firms; the latter included construction firms,

precasters, and facility management firms. Among the 89 responding organizations,

42 had BCA financial grades, and three were facility management firms. Since one of

the facility management firms also had a BCA financial grade, the numbers of the

organizations in the upfront group and the downstream group were 45 and 44,

respectively. The reason of this categorizing was that the upfront stakeholders were

either policymakers, owners, or the firms required to submit building plans in BIM

format for regulatory approvals at earlier stages, while the downstream firms were not

or less affected by this policy. The BCA found that almost all the local consultants

had used BIM, but only large contractors were likely to adopt BIM (Lam, 2014).

To check whether there were differences in the significance mean scores of the CHCs

between the two groups of responding organizations, the independent-samples t-test

was performed. The p-values below 0.05 represented statistically significant

differences in the mean scores. Besides, the Spearman’s rank correlation was

conducted to test whether there was agreement on the rankings of the CHCs between

the two groups. A summary of the mean scores and rankings as well as the test results

are presented in Table 7.20.

Page 252: building information modeling–based process transformation to improve productivity in the

232

Table 7.20 Mean scores and ranking of the CHCs between upfront and downstream

stakeholders

Code Upfront stakeholders

(N=45)

Downstream stakeholders

(N=44)

Independent-

samples t-test

Mean Rank Mean Rank p-value

H01 3.71 12 3.57 4 0.550

H02 3.62 19 3.34 26 0.242

H03 3.36 39 3.16 38 0.399

H04 3.84 2 3.52 9 0.201

H05 3.80 5 3.57 4 0.338

H06 3.56 24 3.27 31 0.221

H07 3.82 3 3.55 7 0.268

H08 3.49 28 3.25 32 0.339

H09 3.76 7 3.32 29 0.075

H10 3.44 35 3.20 34 0.334

H11 3.49 28 3.36 23 0.606

H12 4.00 1 3.57 4 0.067

H13 3.47 32 3.18 36 0.243

H14 3.78 6 3.45 14 0.220

H15 3.67 17 3.18 36 0.033*

H16 3.64 18 3.02 44 0.007*

H19 3.47 32 3.39 20 0.751

H20 3.44 35 3.11 40 0.160

H21 3.31 42 3.39 20 0.744

H22 3.31 42 3.36 23 0.808

H23 3.33 41 3.50 11 0.417

H24 3.27 44 3.25 32 0.946

H26 3.36 39 3.48 12 0.606

H27 3.73 8 3.68 1 0.831

H28 3.69 14 3.61 2 0.763

H29 3.69 14 3.16 38 0.019*

H30 3.51 26 3.11 40 0.105

H31 3.82 3 3.43 17 0.085

H32 3.62 19 3.41 19 0.307

H33 3.60 21 3.48 12 0.583

H34 3.71 12 3.34 26 0.078

H35 3.49 28 3.52 9 0.884

H36 3.53 25 3.45 14 0.737

H37 3.51 26 3.39 20 0.564

H38 3.47 32 3.34 26 0.584

H39 3.40 37 3.09 42 0.152

H40 3.58 22 3.20 34 0.080

H41 3.38 38 3.07 43 0.153

H42 3.73 8 3.59 3 0.568

H43 3.58 22 3.45 14 0.603

H44 3.49 28 3.36 23 0.596

H45 3.73 8 3.32 29 0.074

H46 3.73 8 3.55 7 0.444

H47 3.69 14 3.43 17 0.232

Note: The Spearman’s rank correlation coefficient is 0.474 (p-value=0.000). *The hindrance was statistically significant at the 0.05 level (two-tailed).

Page 253: building information modeling–based process transformation to improve productivity in the

233

The mean scores of the upfront stakeholders were found to be generally higher than

those of the downstream ones. This result revealed that in a building project, the

upfront stakeholders usually gave more weight to the CHCs than the downstream

participants. The experts participating in the post-survey interviews reported that

teamwork among the design consultants was in an urgent need. They argued that

compared with the contractors who were headed by the general contractor, the

consultants usually could not develop a “frozen” set of models at an appropriate time

for all the stakeholders to work on it. Besides, the independent-samples t-test results

indicated that the means of three CHCs significantly differed between the two groups

of organizations, which would be analyzed and discussed below.

“Field staff dislike BIM coordination meetings looking at a screen” (H15) received a

significantly higher mean score from the upfront stakeholders (mean = 3.67) than

from the downstream stakeholders (mean = 3.18). This result implied that the upfront

stakeholders thought that the field staff were not ready to implement BIM. The

experts participating in the post-survey interviewees stated that the coordination of

work among the key stakeholders using BIM models, whether in face-to-face

meetings or via video conferencing, would have greater lifecycle impact. But in

reality, experienced and skilled field staff usually hesitated to learn new ways of

working and could not see how they could benefit from such models (Zahrizan et al.,

2013). The staff even fell burdened, because BIM implementation was seen not as a

mainstream activity on site but rather as add-ons to the existing meetings and site

work on call.

“Lack of consultants’ feedbacks on subcontractors’ model coordination” (H16) had a

large mean difference between the upfront stakeholders (mean = 3.64) and the

downstream firms (mean = 3.02). This result indicated that the upfront stakeholders

were not well prepared to use BIM and collaborate with the downstream parties. In

Page 254: building information modeling–based process transformation to improve productivity in the

234

the project that a post-survey interviewee participated, the consultants were focusing

only on the mandatory submissions in BIM format (Lam, 2014), and the BIM models

they created were not accurate enough for downstream uses. In addition, building a

property in the virtual platform is as tough as building the property on an actual site.

The other professional pointed out that the contractors did not have a suitable

candidate that could lead an in-house modeling team, and few resources of the

contractors were put into the modelling. To reduce potential clashes and paperwork,

the contractors’ modeling team and site engineers expected that the owner and design

consultants could provide useful feedbacks to help their model coordination at the

construction level, but at times the upfront parties were not able to give adequate

useful feedbacks in the coordination meetings (Chelson, 2010). In this case, BIM

implementation may not really be a helping hand to guide construction activities, but

rather be additional work or burden to the contractors.

The mean of “lack of effective data interoperability between project stakeholders”

(H29) was significantly distinct between the upfront parties (mean = 3.69) and the

downstream participants (mean = 3.16), suggesting that the upfront stakeholders had

difficulties in exchanging data (Arayici et al., 2011; Azhar et al., 2014). In the post-

survey interviews, the professionals highlighted that although the design consultants

used 3D software to design and produce submittals, different consultants concentrated

on their own submittals rather than the collaboration among disciplines. On the other

hand, the consultants still kept a 2D mindset. For example, pipes were represented by

lines in the 3D models. Consequently, the designs could not match among different

disciplines. In the meantime, most interviewees argued that the IT infrastructure in

their offices were not powerful enough to run the software at high speeds. Also, not

all the stakeholders used the same software or the same versions of the software.

Moreover, due to the lack of standards to follow, the parties came up with their own

Page 255: building information modeling–based process transformation to improve productivity in the

235

models using proprietary formats. Thus, the models were not compatible, creating

difficulties in interoperating effectively among different stakeholders.

Furthermore, despite the statistically significant differences in the mean scores of the

three CHCs, the Spearman’s rank correlation coefficient of 0.474 with a p-value of

0.000 indicated significant agreement on the rankings of the 44 CHCs between the

two groups of organizations.

7.3.3 Drivers for change towards full BIM implementation

7.3.3.1 Overall ranking

As shown in Table 7.21, the Cronbach’s alpha coefficient value of the data related to

the influence of the drivers on BIM implementation in building projects in Singapore

was 0.968, implying that the data had high reliability. The mean scores of the 32

drivers for BIM implementation ranged from 2.88 to 3.99. These drivers were ranked

based on the overall mean scores. Similar to the analysis of the hindrances, the one-

sample t-test was also performed to check whether the influence of the drivers was

statistically significant. The test results suggested that 31 out of the 32 drivers

obtained p-values below 0.05, indicating that their mean scores were significantly

different from the test value of 3.00. Thus, the 31 critical drivers for change (CDCs)

had significantly driven BIM implementation in building projects in Singapore.

Table 7.21 Significance ranking and t-test results of the drivers for change

Code Drivers for change towards full BIM implementation Mean Rank p-

value

D01 BIM vision and leadership from the management 3.99 1 0.000*

D02 Changes in organizational structure and culture 3.64 11 0.000*

D03 Stakeholders seeing the value of adopting their own part of

BIM

3.71 9 0.000*

D04 Training on new skillsets and new ways of working 3.82 4 0.000*

D05 Owner’s requirement and leadership to adopt BIM 3.90 3 0.000*

D06 Regulatory agencies’ early participation to BIM use 3.76 6 0.000*

D07 Gaining competitive advantages from full BIM use 3.79 5 0.000*

Page 256: building information modeling–based process transformation to improve productivity in the

236

D08 All disciplines sharing models in a ‘Big Room’ 3.63 12 0.000*

D09 Government support such as subsidizing training, software,

and consultancy costs

3.69 10 0.000*

D10 Enabling subcontractors to use lower-skilled labor on site 2.88 32 0.316

D11 OSM lowering safety risks by controlling work in factory 3.30 26 0.008*

D12 Alignment of the interests of all stakeholders 3.44 21 0.000*

D13 Governance of BIM-related policies and standards 3.57 16 0.000*

D14 Data sharing and access on BIM platforms 3.62 13 0.000*

D15 3D visualization enabling design communication 3.75 7 0.000*

D16 4D simulation before construction 3.45 19 0.000*

D17 Design coordination between disciplines through clash

detection and resolution

3.92 2 0.000*

D18 Complex design analysis in sustainability, material

selection, and constructability

3.45 19 0.000*

D19 Project lifecycle costing 3.26 30 0.016*

D20 Producing models and drawings for construction and

fabrication

3.75 7 0.000*

D21 High accuracy of model-based documentation 3.58 15 0.000*

D22 More off-site fabrication and assembly of standard

elements

3.53 17 0.000*

D23 Automatic model updating and drawing production to deal

with design changes and their implications

3.48 18 0.000*

D24 Lifecycle information management improving operations

and maintenance

3.29 27 0.007*

D25 Increasing use of design-build and fast-track approach 3.35 23 0.004*

D26 On-site work proceeds in parallel with off-site production 3.28 28 0.007*

D27 OSM standardizes design and manufacturing processes,

simplifying construction and testing and commissioning

processes

3.26 30 0.019*

D28 OSM produces building elements with better quality and

consistency

3.31 24 0.006*

D29 OSM reduces building wastes, especially on-site wastes 3.27 29 0.024*

D30 Integrating model management tools with enterprise

systems to exchange data

3.60 14 0.000*

D31 Increasing complexity in buildings, project delivery, and

marketplace

3.40 22 0.001*

D32 New technologies such as CNC machines 3.31 24 0.003*

Note: Cronbach’s alpha coefficient value = 0.968. *The one-sample t-test result was significant at the 0.05 level (two-tailed).

“BIM vision and leadership from the management” (D01, mean = 3.99) was

recognized as the most significant factor in driving BIM implementation. This result

substantiated the argument of Autodesk (2012) and Miettinen and Paavola (2014) that

BIM implementation starts with a well-articulated vision sponsored in the project.

Autodesk (2012) advocated that top-down approaches are very important in

individual organizations who serve as part of the project leadership team. Thus,

without the vision and mission from the management and the executive leadership

Page 257: building information modeling–based process transformation to improve productivity in the

237

behind it, dedicated resources assigned to the adoption of the new way of working

would be probably wasted.

“Design coordination between disciplines through clash detection and resolution”

(D17, mean = 3.92) received the second position in the driver ranking, substantiating

the value of fully coordinated 3D data. This result was in line with the findings of

previous studies (Porwal and Hewage, 2013; Sattineni and Mead, 2013) that full BIM

implementation would enable the development of a composite design model in the

design stage. Such a well-coordinated model could enable multiple downstream

disciplines to document the construction intent and collaborate with other trades on

site in the later stages of the project.

The third most significant driver was “owner’s requirement and leadership to adopt

BIM” (D05, mean = 3.90), indicating that the contractual requirement and active

participation of the owner would motivate its service providers to implement BIM.

Successful BIM implementation also requires the top-down approaches in the project.

Therefore, as the leader of the project team, the owner plays a key role in requiring its

service providers, via certain contract documents, to implement BIM work practices

(Arayici et al., 2011; Azhar et al., 2014). This result was consistent with the findings

of Arayici et al. (2011) and Azhar et al. (2014) that without the requirement and

leadership from the owner, the service providers may continue to deliver their scopes

of work in the accustomed ways, hindering the project-wide collaboration required by

successful BIM implementation.

“Training on new skillsets and new ways of working” (D04, mean = 3.82) was ranked

fourth. The top-down approaches mentioned earlier must be accompanied by bottom-

up approaches such as training the staff to carry out specific work processes to truly

reap the advantages of BIM implementation (Autodesk, 2012). Indeed, it is

Page 258: building information modeling–based process transformation to improve productivity in the

238

challenging to change the way that the staff carried out various work activities, such

as entrenching themselves in the traditional CAD drafting due to their poor BIM

skills or psychological resistance to change. The adoption of BIM requires many

resources, such as costly infrastructure and skilled personnel either by training the

employees or engaging experts in the market, which were big challenges for many

firms, especially SMEs (Kiani et al., 2015). Thus, only the senior-level support such

as arranging training programs on the new knowledge and skillsets can enable

changes to the existing practices (Arayici et al., 2011; Azhar et al., 2014; Zhao et al.,

2014a; Kiani et al., 2015). The project and organizational context need to be changed

first, followed by changed attitudes and associated behaviors.

“Gaining competitive advantages from full BIM use” (D07, mean = 3.79) was ranked

fifth. It should be noted that firms with successful experience of implementing BIM

would surely gain a competitive advantage in meeting qualification requirements and

win bids in future construction market, which ensured the long-term viability of the

firms and drove them to enhance the capability of implementing their part of BIM in

the current project in return.

“Regulatory agencies’ early participation to BIM use” (D06, mean = 3.76) occupied

the sixth position in the ranking. This results echoed Juan et al. (2017) which found

that in Singapore, the government is the dominant force to promote BIM

implementation. In such a top-down approach, the early involvement of the local

government through mandating building plans e-submissions and standardizing

building review procedures in the design phases could minimize agency comments

and required changes to the design thereafter (AIA and AIACC, 2007).

“3D visualization enabling design communication” (D15, mean = 3.75) was ranked

seventh, indicated enhanced communication patterns in the Singapore construction

Page 259: building information modeling–based process transformation to improve productivity in the

239

industry. The functions of accurate 3D models, such as visualization, rendering,

walkthrough, and simulation, enable the project team to communicate the design

intent more clearly and effectively with each other, and with the owner. In particular,

many owners prefer 3D models and cannot understand clearly complex 2D shop

drawings because they are not trained architects. Besides, the visualization and

simulation also facilitate the design coordination across the design models from

different disciplines. Similar findings were also reported by previous studies

(Sattineni and Mead, 2013; Fischer et al., 2014; Wong et al., 2014). Moreover, the

construction impact can be easily studied when any change occurs in the later stages,

enabling the team to select the optimal design option. This is because these functions

can show how close the design comes to the expected outcomes and allow the team to

see the consequence of their decisions (Fischer et al., 2014).

“Producing models and drawings for construction and fabrication” (D20, mean =

3.75) also occupied the seventh position. Computer-based design integration enables

the project team to share data among disparate modelling and analysis applications

reliably by using exchange standards such as IFC (Kunz and Fischer, 2012).

Specifically, in the design stage, where key stakeholders including contractors

physically co-locate in a “Big Room”, the structural engineer can use the initial

architectural model as a base to do structural analysis, and adjust, not re-create, the

model to create and analyze a structural model, while the MEP engineers can create a

MEP model on the same design. The design team can then produce a composite

model by linking the structural and MEP models back into the original architectural

model (Gao and Fischer, 2006; Porwal and Hewage, 2013). In addition, based on the

high-accuracy models shared from the design team, the contractors can document the

construction intent, produce construction models and fabrication models as well as

required drawings, especially for off-site manufacturing, and constantly update the

Page 260: building information modeling–based process transformation to improve productivity in the

240

models during the construction period till the project is completed and an as-built

model is created.

“Stakeholders seeing the value of adopting their own part of BIM” (D03, mean =

3.71) obtained the ninth highest rating. This result was consistent with a previous

study (Khosrowshahi and Arayici, 2012) which advocated that getting the key

stakeholders, especially their top management, to understand the model-based

advantages over the 2D drafting practices and the competitive edge derived from

successful BIM adoption would drive them to be keen on the new way of delivering

this project. Although all key stakeholders team together, they remain responsible for

individual scopes of work and associated deliverables. The collaboration between the

designers and the contractors does not inherently result in the integration between

disciplines. If not all key stakeholders are keen on their work processes using BIM,

discipline-specific models cannot be integrated and shared openly for high-accuracy

documentation and drawings generation (Gao and Fischer, 2006; Porwal and

Hewage, 2013; Rezgui et al., 2013). For instance, it is common today for the design

team to produce one model, and for the contractors to develop their own model based

on the information provided to them (Sattineni and Mead, 2013, Lam, 2014).

Furthermore, as mentioned earlier, the top-down approach of promoting BIM is

critical in each key party. Thus, if the architect, engineers, contractors, fabricators,

and many other related practitioners do not see the value in implementing their part of

BIM work processes in the whole process, BIM implementation in this project will

likely be stunted (Khosrowshahi and Arayici, 2012; Kunz and Fischer, 2012; Kiani et

al., 2015). Thus, both the owner’ requirement and the service providers’ self-

motivations are vital to enhance BIM implementation in the project.

“Government support such as subsidizing training, software, and consultancy costs”

(D09, mean = 3.69) was ranked tenth in the driver ranking. In Singapore, part of the

Page 261: building information modeling–based process transformation to improve productivity in the

241

initial implementation costs in training, consultancy, software, and hardware would

be subsidized by the local government in a new BIM fund (BCA, 2016). Such efforts,

together with the active government participation and leadership from the early

design stage, had significantly push the local industry players to adopt BIM. In turn,

the successful BIM application would give the competitive advantage to the major

stakeholders as well as motivate the local government to provide further leadership

and support to BIM implementation in future projects, compared with the lonely BIM

implementation of many individual firms.

Furthermore, “enabling subcontractors to use lower-skilled labor on site” (D10, mean

= 2.88) was not perceived as a significant driver for BIM implementation. The

experts participating in the post-survey interviews reported that although BIM model

functions, especially the visualization of the design intent and the simulation of the

detailed scheduling, could enable the field staff to understand the design intent more

easily (Fischer et al., 2014), currently only relatively skilled workers could ride the

wave of BIM implementation. On the other hand, the local industry still did require

skilled workers for better quality and workmanship because the use of BIM could not

address all nuts and bolts in the actual construction activities (AIA and AIACC,

2009).

7.3.3.2 Comparison among different stakeholders

Similar to the CHCs, the significance of the 31 CDCs might differ among different

responding organizations. This section investigated the differences in the mean scores

and rankings of the CDCs between the upfront stakeholders and the downstream

stakeholders.

Page 262: building information modeling–based process transformation to improve productivity in the

242

To check whether the significance mean scores of the CDCs were distinct between

the two groups of responding organizations, the independent-samples t-test was

carried out. The p-values below 0.05 represented statistically significant differences

in the mean scores. In addition, the Spearman’s rank correlation was conducted to

examine whether there was agreement on the rankings of the CDCs between the two

groups of stakeholders. A summary of the mean scores and rankings as well as the

test results are presented in Table 7.22.

Table 7.22 Mean scores and ranking of the CDCs between upfront and downstream

stakeholders

Code Upfront stakeholders

(N=45)

Downstream stakeholders

(N=44)

Independent-samples t-test

Mean Rank Mean Rank p-value

D01 4.07 1 3.91 2 0.551

D02 3.78 9 3.50 16 0.273

D03 3.89 6 3.52 14 0.144

D04 3.91 4 3.73 5 0.431

D05 3.98 2 3.82 4 0.508

D06 3.91 4 3.61 10 0.171

D07 3.64 12 3.93 1 0.179

D08 3.53 16 3.73 5 0.391

D09 3.82 7 3.55 12 0.284

D11 3.27 25 3.34 26 0.741

D12 3.56 15 3.32 27 0.281

D13 3.62 13 3.52 14 0.680

D14 3.73 11 3.50 16 0.316

D15 3.78 9 3.73 5 0.827

D16 3.47 19 3.43 21 0.880

D17 3.96 3 3.89 3 0.764

D18 3.44 21 3.45 20 0.966

D19 3.38 22 3.14 31 0.255

D20 3.80 8 3.70 8 0.673

D21 3.62 13 3.55 12 0.750

D22 3.49 18 3.57 11 0.733

D23 3.47 19 3.50 16 0.887

D24 3.36 23 3.23 30 0.544

D25 3.27 25 3.43 21 0.481

D26 3.24 28 3.32 27 0.721

D27 3.11 31 3.41 23 0.168

D28 3.27 25 3.36 25 0.669

D29 3.24 28 3.30 29 0.829

D30 3.51 17 3.68 9 0.433

D31 3.31 24 3.50 16 0.405

D32 3.22 30 3.41 23 0.373

Note: The Spearman’s rank correlation coefficient is 0.787 (p-value=0.000). *The hindrance was statistically significant at the 0.05 level (two-tailed).

Page 263: building information modeling–based process transformation to improve productivity in the

243

The analysis results indicated that none of the 31 CDCs obtained significantly

different mean scores between the upfront stakeholders and the downstream

stakeholders. Besides, the overall mean scores of the upfront group (3.57) and the

downstream group (3.53) were roughly equal. This result was reasonable because

successful BIM implementation in a building project needed the entire project team,

both the upfront and downstream parties, to participate and collaborate with each

other, such as staying in close communication and exchanging data of different

disciplines (Rezgui et al., 2013). The post-survey interviewees found that although

project stakeholders remained responsible for their respective deliverables, working

on the same platform was essential for a more effective delivery.

Furthermore, the high Spearman’s rank correlation coefficient of 0.787 (p-value =

0.000) indicated significant agreement on the rankings of the 31 CDCs between the

two groups of stakeholders. This substantiated the statistically insignificant

differences.

7.3.4 Interpreting the CHCs and CDCs with the organizational change

framework

Since BIM implementation in the building project context can be conceptualized as

an organizational change, the project team is then recognized a project organization.

All the major stakeholders serve as the business units that work collaboratively with

each other in this organization. This section would interpret the significant hindrances

to and drivers for BIM implementation from the perspective of organizational change.

Page 264: building information modeling–based process transformation to improve productivity in the

244

7.3.4.1 People

Figure 7.1 shows the overall linkages between the people-related organizational

change attributes and the critical factors influencing BIM implementation in building

projects in Singapore. All the linkages between the CHCs, organizational change

attributes, and CDCs (CHC–organizational change attribute–CDC) in this figure were

analyzed point for point in this section.

H01

H02

H05

H06

H07

H10

H03

H04

H11

H12

H15

H21

H22

H13

H14

H23

H24

H32

H27

H28

PeS4

PeS5

PeC1

PeC2

PeC3

PeC4

PeS1

PeS3

PeI1

PeI2

PeI3

H33

PeS2

PeS6

H41

D02

D06

D08

D03

D04

D11

D12

D14

D25

CHCs

Organizational

change attributes

CDCs

Figure 7.1 Framework of people management from the organizational change

perspective

Inter-enterprise structure plays a key role in organizational change because it

determines the relationships among the primary project participants. Specifically,

“contractual relationships among stakeholders and need for new frameworks” (H27)

and “lack of standard contracts to deal with responsibility/risk assignment and BIM

ownership” (H33) are closely associated with “contractual relationship” (PeS1) in the

Page 265: building information modeling–based process transformation to improve productivity in the

245

attributes of organizational change, while two critical hindrances (H12 and H24) can

represent “involvement” (PeS4). As an organizational change, BIM implementation

requires all the major stakeholders in the project organization to work collaboratively

from early design through multi-party collaboration contracts or physical colocation

in a “Big Room”, enabling data sharing and optimizing the design (Kunz and Fischer,

2012; Azhar et al., 2014). In the collaborative team, the stakeholders remain

responsible for individual scopes of work and may not understand enough the work of

other disciplines, and therefore the participation and collaboration of the key

stakeholders is necessary. For example, design-build approach has been advocated by

the BCA (2013b) and a professional body (Anumba et al., 2010) to drive the

collaboration between the design team and construction team in BIM implementation.

Thus, “increasing use of design-build and fast-track approach” (D25) is pertaining to

“contractual relationship” (PeS1) and “all disciplines sharing models in a ‘Big

Room’” (D08) can represent “involvement” (PeS4). The project-wide collaboration

was plagued with the adversarial relationships among the key participants in the

existing contractual framework (Fischer et al., 2014). One possible explanation is that

the standard contracts to deal with the roles, responsibilities, and benefits of the

parties in BIM-based project delivery have not been well developed and proven to be

efficient (Eastman et al., 2011). Nevertheless, the owner requirement and continuous

participation would somewhat overcome the hostile relationship. The regulatory

agencies in Singapore would provide high-level compliance information and funds,

guiding the project team to purposefully design, build, and manage the building using

BIM (BCA, 2016). Hence, the critical driver “regulatory agencies’ early participation

to BIM use” (D06) can represent “leadership” (PeS2) in the organizational change

attributes. It was noteworthy that “leadership” (PeS2) were considered as a significant

attribute in other studies (Wigand, 2007; Kasimu et al., 2012; Verdecho et al., 2012;

Dahlberg, 2016) and can be represented by H25 which, in this study, was not deemed

as a critical hindrance. This is because this hindrance related to the owner’s special

Page 266: building information modeling–based process transformation to improve productivity in the

246

requirement of OSM was drastic given that the team is bound by multi-party

collaboration agreements.

“Traditional contracts protect individualism rather than best-for-project thinking”

(H28) can be closely linked to “reward arrangement” (PeS3) in the organizational

change attributes. In Singapore, the BIM Particular Conditions has been drafted to

guide the industry to address the procedures of handling digital data, roles and

responsibilities, intellectual property rights, each party’ extent of reliance on 3D

models, and contractual privity (BCA, 2015b). However, the main form of contract

currently used is still based on the adversarial system that prohibits collective benefits

and encourages individualism, and does not change the contractual relationships or

risk transfers in the principal agreements. The sharing of risks and rewards are not

included in the local forms of contract. Thus, another significant hindrance “concerns

over or uninterested in sharing liabilities and financial rewards” (H02) can also be

associated with “reward arrangement” (PeS3), and four hindrances related to risk and

responsibility (H02, H10, H21, and H32) can present “risk allocation” (PeS5) in the

attributes of organizational change. In addition, Kent and Becerik-Gerber (2010)

argued that monetary initiative would be a poor motivator to force the team to work

together because it might result in blaming rather than resolving issues. Thus, H41

can be linked to “conflict management” (PeS6). Since incorrect information providers

may be blamed for potential liability issues, the parties tend to be conservative in

providing information or advice to other parties (AIACC, 2014). To remove such

liability issues, the interests of the major stakeholders should be aligned (Azhar et al.,

2014). Therefore, “alignment of the interests of all stakeholders” (D12) can be

associated with “reward arrangement” (PeS3), “risk allocation” (PeS5), and “conflict

management” (PeS6) in the organizational change attributes.

Page 267: building information modeling–based process transformation to improve productivity in the

247

In addition, because of the pervasive nature, corporate culture also plays a critical role

in organizational change (Austin and Ciaassen, 2008). Removing the potential

liability concerns would facilitate open and continuous data sharing within the project

team; therefore, two significant hindrances (H02 and H12) and three drivers (D08,

D12, and D14) can be linked to “sharing” (PeC1). The team members’ willingness to

change depends largely on their awareness of new ways of design and construction,

understanding of BIM process, experience of using BIM, and level of reliance on the

traditional CAD approach. Low (1998) found that people tend to respond to change in

their accustomed ways when confronted with change, and hold a biased view of

change that fits most comfortably into their own perceptions of the reality. The staff

of the primary participants may be unwilling to change towards using BIM along with

OSM when they have been psychologically entrenched in the traditional drafting

practices (Khosrowshahi and Arayici, 2012). Thus, three critical hindrances (H05,

H07, and H11) are closely associated with “willingness to change” (PeC2), which

urges cultural change in the key stakeholders (“changes in organizational structure

and culture”, D02). Meanwhile, Zahrizan et al. (2013) reported that many firms

thought of adapting to new ways of working as extra efforts and cannot understand

the value of BIM over 2D drafting. Blismas and Wakefield (2009) found that the

owner is reluctant to understand the OSM process and worries about the cost for

unconventional design. Thus, H01 and H22 are associated with “commitment on new

ways” (PeC03). Nevertheless, the OSM approach moves more labor-intensive on-site

activities to a factory environment and creates many benefits, such as lowering injury

rate (Ross et al., 2006). In this regard, three critical drivers (D3, D08, and D11) are

related to “commitment on new ways” (PeC03) and may help to overcome the

widespread unwillingness. It should be noted that if the key parties cannot implement

their part of BIM, this project would not successfully implement BIM. The key

stakeholders’ early involvement in the “Big Room” to build trust-based collaboration

is crucial to adapt to organizational cultural change required by BIM implementation

Page 268: building information modeling–based process transformation to improve productivity in the

248

(AIA and AIACC, 2009; Autodesk, 2012; El Asmar et al., 2013). Thus, the

significant factors “lack of trust/transparency/communication/partnership and

collaboration skills” (H13) and “all disciplines sharing models in a ‘Big Room’”

(D08) can be linked to “trust and transparency” (PeC4) in the attributes of the

organizational change framework.

Furthermore, to implement an organizational change, the project organization should

ensure that the relevant individuals can adapt to the change. One challenge is to

change the thinking of both the executives and the employees of the major

stakeholders from considering only their own work to considering how the work can

affect the entire project. For example, although the employees are pushed by the

executives to attend training programs on BIM, they may still be ensnared to the

comfortable routines thereafter (Zahrizan et al., 2013). Thus, three critical hindrances

(H01, H06, and H15) can represent “mindset and attitude” (PeI1) in the

organizational change attributes. It is suggested that the negative mindsets of the

individuals toward change may be overcome by getting them to understand and

visualize the advantages of BIM work practices over the traditional drafting practices

(Khosrowshahi and Arayici, 2012). Thus, the significant driver “stakeholders seeing

the value of adopting their own part of BIM” (D03) can also be associated with this

attribute. It is worth reiteration that people tend to responds to change in their

accustomed ways, which may be influenced by their abilities and experience. The

individuals would unconsciously think whether they are qualified to be involved in

the BIM-based work practices in terms of their knowledge, skills, and experience. If

they feel that they are not competent and experienced or have not yet learnt about

similar success stories, they would not actively participate in relevant work practices,

or even undermine it. Therefore, three hindrances (H03, H14, and H23) can be linked

to “knowledge, skills, and experience” (PeI2). For example, due to the lack of

relevant expertise in using OSM together with BIM in the past projects, the

Page 269: building information modeling–based process transformation to improve productivity in the

249

employees would still be stuck to the traditional way in their first projects. Actions

should be taken to change the passive mindsets and behaviors, such as introducing

training and education programs (D04) to remove the resistance to change towards

the BIM and OSM work processes (Kiani et al., 2015). Thus, the critical hindrance

“lack of skilled employees and need for training them on BIM and OSM” (H04) and

critical driver “training on new skillsets and new ways of working” (D04) can be

related to “training and education” (PeI3). In turn, building the trust-based

collaboration between the key stakeholders as well as between the management and

the employees could ensure the effectiveness of training (Zhao et al., 2014a).

7.3.4.2 Process

Figure 7.2 presents the overall connections between the process-related

organizational change attributes and the critical factors influencing BIM

implementation in building projects in the Singapore context. All the linkages

between the CHCs, organizational change attributes, and CDCs (CHC–organizational

change attribute–CDC) in this figure were analyzed point for point in this section.

Firstly, management processes are part of the glue that holds the project organization

together (Rockart and Scott Morton, 1984). The hindrance “interpretations resulted

from unclear contract documents” (H40) represents “communications” (PrM1) in the

organizational change attributes. This is because unnecessary interpretations created

by any errors in the documents would probably harm the trust and communication

pattern between the project participants. Besides, three critical hindrances (H20, H34,

and H37) are closely associated with “controlling and decision-making” (PrM2) in

the proposed organizational change framework. “Decision-making depending on

relationships between project stakeholders” (H20) is stumbling as this causes

individualism other than the best-for-project thinking and behaviors (AIA and AIACC,

Page 270: building information modeling–based process transformation to improve productivity in the

250

CHCs

H08

H09

H16

H19

H20

H29

H30

H31

H36

H37

H38

H40

PrM2

PrS1

PrS2

PrS4

PrS3

PrT1

PrM1

PrT2

PrT3

PrT4

H34

D01

D05

D07

D13

D16

D17

D18

D19

D20

D21

D15

D23

D26

D27

D28

D24

Organizational

change attributes CDCs

Figure 7.2 Framework of process management from the organizational change

perspective

2009). Besides, the ambiguity in model authorship and ownership requirements (H34)

would inevitably cause inefficient work processes, duplicate efforts, and liability

anxieties in the lifecycle model management, which reduce the efficiency of project

management in the organization (Sattineni and Mead, 2013). Nevertheless, in the

design stage, the use of accurate 3D models enables the service providers to

communicate more clearly and effectively with each other, and with the owner.

Fischer et al. (2014) found that it is not uncommon that many owners can only

understand 3D models because they have little or no experience building anything.

Thus, the significant driver “3D visualization enabling design communication” (D15)

can solve the communication issues. Meanwhile, the driver “governance of BIM-

related policies and standards” (D13) can be linked to “controlling and decision-

making” (PrM2) since the BIM standards, guides, and best practices issued by the

local government would help the project team to make better decisions and control

the project throughout the project lifecycle (Cheng and Lu, 2015).

Page 271: building information modeling–based process transformation to improve productivity in the

251

Moreover, corporate strategy is crucial in organizational change (Dahlberg et al.,

2016). It is the owner that makes decisions whether or not to implement BIM to

achieve the project goals, which influence the service providers’ interest and

willingness to use BIM in practice. Thus, the hindrance “lack of owner request or

initiative to adopt BIM” (H19) can represent “goals and requirements setting” (PrS1)

in the attributes of organizational change. It should be noted that no established

standard fits the situation of every project and its participating firms due to the wide

variety of project types and strategic goals. Such governance of standards is not

adequate for BIM implementation in every project. Thus, the owner’s proactive

requirement, active participation, and leadership to adopt BIM (D05) is essential. In

addition, the change agent should allow the major stakeholders and their staff to

understand the vision and the impact of the change. Four critical hindrances (H08,

H09, H30, and H31) are therefore linked to “vision and mission” (PrS2). Specifically,

if the owner recognized that potential gains in productivity, quality, asset

management, and so on would outweigh the initial costs, it would push the service

providers to use BIM, ensure the quality and relevance of building information in

project requirements, and even pay for the training. However, the results indicated

that many parties lack the insights into training their staff and changing their work

processes, largely hindering BIM implementation. Cost and manpower invested in the

training as well as efforts made in adapting to the new work processes would

probably reduce productivity initially. This agrees with the finding of Eastman et al.

(2011) that many firms believe that the potential benefits of BIM are not tangible and

cannot outweigh the investments. Thus, if the firms do not have a long-term vision of

equipping their employees with new skills or if the investments cannot be subsidized

by the owner, they would still provide AEC services in the old way. The Singapore

government incentivizes BIM-ready firms to reap the full benefits of BIM and grow

their collaboration capabilities beyond just modelling by offering a new BIM fund

since July 2015 (BCA, 2016). Despite that, some survey respondents reported that the

Page 272: building information modeling–based process transformation to improve productivity in the

252

costs for subsequent upgrades or subscriptions are not funded and that the manpower

cost of carrying out BIM work practices remains a big issue. It should be noted that

any corporate strategy changes are subject to the owner and the senior management of

the participants, and thus the willingness to invest in training (H31) can also be

associated with “top management support” (PrS3) in the organizational change

attributes. As advocated by Autodesk (2012), BIM implementation is an

organizational transformation which starts with executive vision and sponsorship. In

order to avoid the pitfalls in a large-scale, radical change in the building project

context, a solid vision should be built. One example of such vision is the long-term

competitive advantages that successful BIM implementation in this project can give

to the service providers to win bids in the future market (Verdecho et al., 2012). Thus,

“gaining competitive advantages from full BIM use” (D07) can strengthen the change

attribute “vision and mission” (PrS2). Ideally, this BIM vision stems from the

executives; however, it is common for the mid-tier management to strive to put BIM

in the direct focus of the executives and seek for their sponsorship (Autodesk, 2012).

Therefore, the critical driver “BIM vision and leadership from the management”

(D01) can be associated with two attributes, PrS2 and PrS3. In the meantime,

although BIM facilitates OSM, the potential costly design changes after building

elements production require the design to be fixed early (Blismas and Wakefield,

2009). Thus, the hindrance related to the OSM process (H36) can be linked to

“process alignment” (PrS4). By moving on-site activities to a factory environment,

the standard design and production processes as well as the simplified construction

process would benefit the project team, such as reduced construction activities, site

disruptions, hazard exposures, site costs, and simplified inspection and test and

commissioning (Blismas and Wakefield, 2009; McFarlane and Stehle, 2014). Hence,

two significant drivers (D26 and D27) related to the adoption of BIM along with

OSM can be closely associated with “process alignment”’ (PrS4) in the

organizational change attributes.

Page 273: building information modeling–based process transformation to improve productivity in the

253

Furthermore, the changes in corporate strategy make sense only when specific tasks

are ultimately carried out on the shop floor (Autodesk, 2012). Two significant

hindrances (H29 and H36) can represent “coordination and simulation” (PrT1),

whereas the hindrances H40, H38, and H16 can be linked to “documentation” (PrT2),

“production” (PrT3), and “model management” (PrT4), respectively. Full BIM

implementation requires insights across multiple parties and aspects of the project.

Although a construction manager manages communication and reviews project

documentation to ensure the data quality and relevance across multi-disciplines,

changes inevitably occur. The impacts of the changes need the ongoing participation

and corresponding tasks of the relevant participants to respond to the changes. Thus,

managing this process and the related management of the model become critical to

the project (Eastman et al., 2011). On the other hand, the functions of digital

information models and the management of the models can facilitate the individuals

to carry out the day-to-day tasks, driving full BIM implementation in the project.

Specifically, four critical drivers (D16-D19) related to the development of optimal

design models can be associated with “coordination and simulation” (PrT1). The

project team can coordinate the models shared by specific disciplines and perform

analysis for sustainability, material selection, constructability, operations, and so on

(Eastman et al., 2011; Kunz and Fischer, 2012; Chua and Yeoh, 2015). Downstream

parties can document the design intent and construction intent from the fully

coordinated design models. Thus, the significant driver “high accuracy of model-

based documentation” (D21) can represent “documentation” (PrT2). In the meantime,

key contractors and manufacturers are able to use the design models shared by the

design team as bases for producing their construction models and fabrication models

as well as required drawings (Gao and Fischer, 2006; Porwal and Hewage, 2013).

Thus, two critical drivers (D20 and D28) can be associated with the change attribute

“production” (PrT3). In addition, “automatic model updating and drawing production

to deal with design changes and their implications” (D23) and “lifecycle information

Page 274: building information modeling–based process transformation to improve productivity in the

254

management improving operations and maintenance” (D24) can be linked to “model

management” (PrT4) which describes the functional and organizational relationships

of design, construction, and operations and maintenance. Whenever changes

(especially unexpected and late scope changes) take place, all these models can be

easily updated. More importantly, the project lifecycle implications of the changes

can be predicted in the digital models and thus better managed before changes would

traditionally occur in the later stages of the project (Gao and Fischer, 2006;

Khosrowshahi and Arayici, 2012).

7.3.4.3 Technology

Figure 7.3 presents the overall connections between the technology-related

organizational change attributes and the critical factors influencing BIM

implementation in the Singapore construction industry. All the linkages between the

CHCs, organizational change attributes, and CDCs (CHC–organizational change

attribute–CDC) in this figure were analyzed point for point in this section.

D22

D29

D30

H35

H42

H43

H44

H45

H46

H47

TD

TC

TI

CHCs

Organizational

change attributes CDCs

Figure 7.3 Framework of technology management from the organizational change

perspective

As an organizational change, full BIM implementation requires constantly advancing

technologies to improve the efficiency of carrying out the tasks (Azhar et al., 2014).

“Costly investment in BIM hardware and software solutions” (H42) and “need for

increasingly specialized software for specialized functions” (H44) are closely

Page 275: building information modeling–based process transformation to improve productivity in the

255

associated with “hardware and software solutions” (TI), implying that the lack of

capital investment for high-end infrastructure as well as relevant training programs is

still a big barrier for many firms, especially a great number of subcontractors,

although part of the costs would be funded by the local government (Lam, 2014;

Kiani et al., 2015). Meanwhile, four significant hindrances (H43 and H45-H47) can

represent “interoperability” (TD). Multidisciplinary integration is difficult for most

firms due to the lack of interoperability standards, the limited expertise of using IFC,

the multiuser access needed to a building information model, and the suboptimal

environment of one-or two discipline integration. In addition, OSM has been

recognized as a new construction method (Blismas and Wakefield, 2009; McFarlane

and Stehle, 2014), so the critical hindrance “poor understanding of OSM process and

its associated costs” (H35) is associated with “prefabrication” (TC). As mentioned

earlier, OSM requires design models to be fixed early to avoid costly design changes.

In this regard, detrimental resources including suppliers and contractors should be in

place in the design stage. Thus, the design cost may be perceived as higher than that

in the traditional process even though it is potentially lower by using standard

products. While the local BIM implementation was confront with various

technological challenges, motivations appear to be well recognized. Specifically,

“integrating model management tools with enterprise systems to exchange data”

(D30) can be associated with two attributes (TI and TD) of the adapted organizational

change framework. This is because such integration not only facilitates the data

sharing in individual parties, but also enables the parties to access the models and

exchange data conveniently with each other. Meanwhile, “more off-site fabrication

and assembly of standard elements” (D22) and “OSM reduces building wastes,

especially on-site wastes” (D29) may help address the “prefabrication” (TC) issues.

OSM has emerged as a new construction method and has gained wide recognition in

previous studies (Blismas and Wakefield, 2009; McFarlane and Stehle, 2014). Kunz

and Fischer (2012) argued that the project may use automated method to carry out

Page 276: building information modeling–based process transformation to improve productivity in the

256

routine design tasks or to help fabricate more standard building products in a factory.

On-site activities would be compressed and result in fewer workers and less waste on

sites, reducing costs (McFarlane and Stehle, 2014). Therefore, these drivers would

motivate the project organization to implement BIM appropriately.

7.3.4.4 External environment

Figure 7.4 illustrates the overall linkages between the organizational change attributes

on external environment aspect and the critical factors affecting BIM implementation

in building projects in Singapore. Changes in the external environment may drive the

internal components (people, process, and technology) of the project organization

into motion until reaching a rebalance (Rockart and Scott Morton, 1984; Wigand,

2007). All the linkages between the CHCs, organizational change attributes, and

CDCs (CHC–organizational change attribute–CDC) in this figure were analyzed

point for point in this section.

D09

D31

D32

H26

H39

ES1

ES2

ET

CHCs

Organizational

change attributes CDCs

Figure 7.4 Framework of external environment management from the organizational

change perspective

The significant hindrance related to legislations (H39) obviously represents “policy”

(ES1) with which the project team must comply. Moreover, due to the inadequate

expertise of OSM and its process in the local construction market, and the market

protection from large numbers of traditional suppliers in the small market, designs

tend to be unsuited to the use of off-site production and on-site assembly (Blismas

and Wakefield, 2009). Thus, “market protection from traditional

suppliers/manufacturers and limited OSM expertise” (H26) can be linked to

Page 277: building information modeling–based process transformation to improve productivity in the

257

“changing market” (ES2). As the construction market becomes increasingly complex

and requires new skill sets and increasing specializations, the Singapore government

has been offering the second BIM fund to the local construction industry to subsidize

part of the initial implementation costs, with the aim of motivating the BIM-ready

firms to grow collaboration capabilities beyond just modelling (BCA, 2016). Thus,

“increasing complexity in buildings, project delivery, and marketplace” (D31) can be

linked to “changing market” (ES2) and “government support such as subsidizing

training, software, and consultancy costs” (D09) can be closely associated with

“policy” (ES1) in the attributes of organizational change. Meanwhile, since the

technologies related to BIM have been constantly improving, more powerful

hardware and a wide range of software applications can be selected to help the project

participants to implement BIM openly. For example, the CNC machines can be used

to automate the manufacturing of standard building products for field installation

(Kunz and Fischer, 2012), driving the team to increase the use of OSM. Hence, D32

can be associated with “new technological solutions” (ET) in the organizational

change attributes which is meant to capture the constantly advancing hardware and

software applications, rather than hindering full BIM implementation (Wigand, 2007;

Dahlberg et al., 2016).

Therefore, Hypothesis 4 that “moving towards higher levels of BIM implementation

is hindered by a set of critical hindrances which can be interpreted from the

organizational change perspective” and Hypothesis 5 that “moving towards higher

levels of BIM implementation is driven by a set of critical drivers which can be

interpreted from the organizational change perspective” were supported.

Page 278: building information modeling–based process transformation to improve productivity in the

258

7.3.4.5 Importance of organizational change attributes

Based on the above analysis, among the top 10 CHCs in the overall ranking in Table

7.19, the top five and overall seven CHCs (H12, H27, H05, H07, H04, H28, and H01)

can be interpreted by some of the eight organizational change attributes on people

aspect, namely “involvement” (PeS4), “sharing” (PeC1), “contractual relationship”

(PeS1), “willingness to change” (PeC2), “training and education” (PeI3), “reward

arrangement” (PeS3), “commitment on new ways” (PeC3), and “mindset and

attitude” (PeI1) in order (see Figure 7.1). In contrast, the remainder (H42, H46, and

H31) of the top 10 CHCs can be linked to “vision and mission” (PrS2) and “top

management support” (PrS3) on process aspect as well as “hardware and software

solutions” (TI) and “interoperability” (TD) on technology aspect, respectively. None

of the top-ranked CHCs represents the organizational change attributes on external

environment aspect.

This result implied that people aspect is the key to changing successfully towards full

BIM implementation, which was consistent with the findings of Lee et al. (2005) and

Teo (2008) that the most significant problem in implementing new technologies is

people management. Thus, more collaboration needed to be built in the project teams

than those of the projects delivered using the traditional approach or using the lonely

BIM approach (Kiani et al., 2015).

Nonetheless, the project team should not overlook the two attributes (PrS2 and PrS3)

on process aspect. As the leadership team, the owner and the senior management of

service providers should have the insights into the potential and the value of BIM

over the traditional drafting practices and provide visible and continuous support to

the BIM work processes, such as building the trust among the team and arranging

training programs for the staff (Zhao et al., 2014a). It should be noted that the two

Page 279: building information modeling–based process transformation to improve productivity in the

259

attributes (TI and TD) on technology aspect would facilitate the more critical

attributes on people and process aspects. Without advances in technology, firms may

find it difficult to adapt to new workflow since such advances enable firms to share

expertise and data conveniently within the project organization (Zhao et al., 2015).

On the other hand, among the top 10 CDCs in the overall ranking of mean scores in

Table 7.21, the aforementioned top three CDCs and overall six positions (D01, D17,

D05, D07, D15, and D20) can be interpreted by some of the six organizational change

attributes on process aspect, including “vision and mission” (PrS2), “top management

support” (PrS3), “coordination and simulation” (PrT1), “goals and requirements

setting” (PrS1), “communication” (PrM1), and “production” (PrT3), respectively;

three significant drivers (D04, D06, and D03) are linked to “knowledge, skills, and

experience” (PeI2), “training and education” (PeI3), “leadership” (PeS2), “mindset

and attitude” (PeI1), and “commitment on new ways” (PeC3) on people aspect; D09

is associated with “policy” (ES1) on external environment aspect. It is notable that

none of these CDCs represents the attributes on technology aspect.

Hence, the six organizational change attributes on process aspect are more critical

areas in the successful change towards full BIM implementation in the Singapore

construction industry. This result substantiated the argument of Eastman et al. (2011)

that the most important driver would be the good information quality provided by the

fully coordinated design and construction models. These models enhance

visualization and design analyses, facilitate the use of standard building products, and

allow for maintenance and operations.

Meanwhile, the project team should not neglect the five attributes (PeI2, PeI3, PeS2,

PeI1, and PeC3) on people aspect. In order to complete the project more efficiently,

the owner has to build the knowledge and skills of its service providers such as by

Page 280: building information modeling–based process transformation to improve productivity in the

260

introducing training programs, which facilitates them to adapt to the new ways of

designing, building, and managing the building. In addition, the significant attribute

“policy” (ES1) on external environment aspect would catalyze the more critical

attributes on process and people aspects. It had been no more than five years since the

building planning submissions in BIM format became mandatory in building projects

in Singapore. Thus, many firms, especially SMEs, were still not experienced in using

the BIM technology, incorporating the BIM process into their work practices, and

delivering their scopes of BIM work (Kiani et al. 2015). So, more incentives from the

local government would drive the industry to enhance their BIM implementation.

To implement a successful organizational change towards full BIM implementation,

the project management team should prioritize their efforts and resources to the areas

related to the more critical attributes. Meanwhile, as Leavitt’s diamond theory and the

MIT90s framework indicate, the project team should understand that the interaction

and integration between these areas would facilitate more successful change in the

construction industry.

7.3.5 Proposed managerial strategies for reducing the CHCs and

strengthening the CDCs

It had been no more than five years since the building planning submissions in BIM

format became mandatory in Singapore. Hence, it was not uncommon that many

firms were still work in silos in the design, construction, and operations processes,

and remained inertial in changing their current ways of working. The theoretical

rationale behind the critical hindrances and drivers as well as the relative importance

of these factors and their respective change attributes provide a clear indication that

specific management strategies can be drawn for enhancing BIM implementation in

the building project.

Page 281: building information modeling–based process transformation to improve productivity in the

261

7.3.5.1 People

A total of eight people management strategies (PeMSs) were identified and discussed

in this section. The organizational change attributes and CHCs that were potentially

targeted by the management strategies would be elaborated.

Government support (PeMS1). The willingness of the major stakeholders to

implement BIM is influenced by government policies, competitor motivation,

financial incentives, and technological support (Juan et al., 2017). Thus, in addition to

the existing BIM fund which defrays part of infrastructure, training, and consultancy

cost (BCA, 2016), the government may lead or influence (PeS2) the industry’s

progress to change by further providing funds, especially to SMEs, to subsidize a

portion of manpower cost of carrying out BIM-related construction activities.

Furthermore, incentives such as additional GFA for the owner and a series of

objective performance milestones for the designers and contractors can be formulated

to help them get out of the conservative industry culture. Additional GFA may

motivate the owner to adopt new contractual solution to reduce the reluctance of the

designers and the financial risk of the downstream parties being involved in an earlier

stage. This strategy echoes the recommendation of the post-survey interviewees.

Standard contract (PeMS2). As mentioned earlier, under the current contractual

framework, the relationships among the project team tend to be adversarial. For

instance, the design team and the construction team tend to act as individuals by

creating different models. Thus, the BIM Particular Conditions has been partly

completed (Wickersham, 2009). An updated version should be developed and

established as the standard contract to incorporate the BIM work processes into the

contractual framework in Singapore. Such a contract should be agreed upon by all the

primary project participants (PeS4; H12 and H24) of the project, including the owner

Page 282: building information modeling–based process transformation to improve productivity in the

262

and the key designers and contractors. The manufacturers should also be bound if the

OSM approach would be adopted in this project. This helps build the collaborative

relationships and incentivize open data sharing (PeC1; H12) within the team. With

the multi-party contract, the major stakeholders will trust each other (PeC4; H13) and

act as a collaborative team (PeS1; H27 and H33).

Early involvement of major participants (PeMS3). The survey respondents cited

“need for all key stakeholders to be on board to exchange information” as their top

hindrance, substantiating the finding of Lam (2014) that most projects in Singapore

were plagued with inadequate project-wide collaboration. The involvement of the

manufacturers (suppliers) and trade contractors was limited in the design stage (Kent

and Becerik-Gerber, 2010). In the early design stage, the regulatory agencies would

provide high-level compliance information which specifies the project team to use

BIM to plan, design, build, and manage the building. The participation would

significantly avoid the required changes to the design as submitted for permit

(AIACC, 2014). Moreover, the key contractors and facility manager can input their

expertise in design modeling, allowing for coordination and constructability to be

built into the design rather than applied after problems occur in the later stages (Kunz

and Fischer, 2012). Without their knowledge and experience input upfront (PeC1;

H12), the design cannot be fixed early with sufficient constructability (PeC3; H01);

problems may occur during construction and operations and maintenance where

design changes would be costly. The standard contract should incentivize the

involvement of the key engineers and contractors from the early design stage or

before (PeS4; H12), which paves the way for the trust-based collaboration (PeC4;

H13) at the later stages of the project (Liao et al., 2017).

Sharing interests and risks (PeMS4). Sharing interests and risks should be agreed on

by all the key stakeholders in the standard contract (PeC1; H02). With this strategy,

Page 283: building information modeling–based process transformation to improve productivity in the

263

the corporate goals of the project participants are bound with the project outcomes

(PeS3; H02 and H28), which will build the necessary trust for the collaboration

among the participants (El Asmar et al., 2013). All the participants should be clearly

aware of the opportunities and responsibilities associated with the incorporation of

BIM into the project workflow. When problems occur, the sharing of risks forces the

team members to be responsible for the project (PeS5; H02, H10, H21, and H32)

rather than transferring risks or blaming others (PeS6; H41). This reduces the

designers’ potential liability due to providing inaccurate information (AIACC, 2014).

The sharing of rewards creates an environment that the team behaves in a best-for-

project manner rather than for individual benefits or even corruption. These avoid the

downstream parties from working at risk upfront. It is worth noting that individual

parties can leverage BIM only when it is successfully implemented in the project.

Removing inertia of the management and employees (PeMS5). The planning, design,

construction, and operation processes increasingly rely on the information models

(Eastman et al., 2011) which have been mandated or encouraged by the local

agencies. Keeping this in mind, the individuals of the major stakeholders should

recognize that change is inevitable to adapt to the information-oriented project

delivery (PeI1; H01, H06, and H15), and therefore break out of the conservative

culture. If the key parties cannot implement their part of BIM, this project would not

successfully implement BIM. Thus, the management should embrace possible

changes (PeC2; H05, H07, and H11), commit on the new way of working, and set the

tone of changing (PeC3; H01). With the tone at the top, the employees who carry out

day-to-day planning, design, construction, and operations work on the shop floor

have to change their passive mindsets and behaviors.

Providing project-wide and in-house training (PeMS6). The BIM vision and promise

should be complemented with a more realistic view of the adoption status (Miettinen

Page 284: building information modeling–based process transformation to improve productivity in the

264

and Paavola, 2014). As the mandatory BIM implementation started in July 2015, over

half (58.4%) of the responding organizations had no more than three years’

experience of implementing BIM. Meanwhile, the individuals’ anxiety about their

competencies should be removed. Once the project team is built, the owner should

lead BIM implementation by providing trainings (PeI3; H04) to the participants on

how to use new software applications, reinvent the workflow, assign responsibilities,

and model the construction process (PeI2; H03, H14, and H23), which would reduce

their misunderstanding and fear of the unknown. Moreover, individual parties can

provide constant in-house trainings to their employees to adapt to new policies,

procedures, and operations.

Highlighting short-term wins (PeMS7). After the project organization has perceived

BIM implementation as a priority and allocated resources in the training and BIM

implementation activities, short-term performance gains versus the traditional work

practices should be highlighted to convince the leadership team that BIM

implementation adds value to the project (PeI1; H01, H06, and H15). Such milestones

can generate energy and overcome the staff’s initial paralysis of continually carrying

out their part of BIM work practices (Autodesk, 2012). From a strategy point of view,

BIM implementation is a long-term journey spanning many years, so those who

change successfully and achieve enhanced BIM implementation will gain a

competitive advantage to win bids in the future market (Miettinen and Paavola,

2014). Thus, the short-term improvements in turn justify long-term investment such

as guaranteeing the sufficiency of the resources required in full BIM implementation

(PeC2; H05, H07, and H11) and gain confidence to adapt to the new way of working

(PeC3; H01 and H22) (Teo and Heng, 2007).

Cultivating trade contractors (PeMS8). The trade contractors may not know how to

deal with the changes brought to its staff. The on-site activities tend to be labor-

Page 285: building information modeling–based process transformation to improve productivity in the

265

intensive, and the field staff often lack sufficient skills of using digital design models

and prefer to submit their drawings in traditional CAD format. Although being

pushed to attend training programs on BIM working practices, they may still be

ensnared to the comfortable routines thereafter (Zahrizan et al., 2013). This can be

attributed to their psychological contradiction to the new processes and the shortage

of skilled personnel (Khosrowshahi and Arayici, 2012). Thus, the project leadership

team should cultivate the specialty contractors, such as by spearheading the design

modeling and coordination for them. The strategy helps incorporate trade contractors’

site knowledge to the design, build up their competencies (PeI2; H14 and H23), and

remove their entrenchment on the traditional drafting method.

7.3.5.2 Process

A total of 10 process management strategies (PrMSs) were identified and discussed

below. The organizational change attributes and CHCs that were potentially targeted

by these management strategies would be elaborated.

Owner management (PrMS1). It is the owner that makes the decision on whether to

implement BIM and on the pace of changing towards full BIM implementation in the

project organization. The lack of owner request or initiative would limit the interest

and willingness of the service providers to implement BIM in practice (Arayici et al.,

2011; Kunz and Fischer, 2012; Zahrizan et al., 2013). Managerially considering the

initial cost and apparent risks straightly forward rather than the potential value as

crucial selection criteria would limit the owner’s insight into the BIM implementation

in the project. Moreover, without the use of BIM in the design, owner-elected

changes and their lifecycle implications tend to be costly. Therefore, the owner

should rebuild its selection criteria when starting a new project, which strengthens the

positive influence from the owner’s requirement and leadership (PrS1; H19). In

Page 286: building information modeling–based process transformation to improve productivity in the

266

addition, because the designers tend to lack time and fees to allocate sufficient

resources to adopt BIM, the owner may need to require the design team to consider

the downstream uses when creating their design models, with more financial

incentives.

Government effort (PrMS2). The Singapore government has built up a BIM steering

committee to propose strategies for the local construction industry. For example, the

second version of the Singapore BIM Guide was released by the BCA in 2013 to

outline the roles and duties of the major stakeholders in implementing BIM at

different stages of the project (BCA, 2013b). This guide can help local BIM

implementers incorporate BIM uses into their day-to-day workflow, understand the

information flow, and manage information models, leading to better project control

(PrM2; H34). Meanwhile, the local government has been incentivizing the industry to

adopt productive technologies such as PPVC to manage the requirements of the

changing industry. A greater extent of OSM has been stipulated as part of the tender

conditions for industrial GLS sites (MOF, 2014), which paves the way for widespread

use of OSM (PrM2; H37).

Long-term vision and support (PrMS3). Autodesk (2012) advocated that BIM

implementation should start with a well-articulated vision supported by the project

leadership team, which was consistent with the top-ranked driver for BIM

implementation (see Table 7.21) in this study. As mentioned earlier, the management

should recognize the inevitable change towards the information-oriented project

delivery. The executives should have a visible and continual commitment on BIM

implementation. Moreover, BIM implementation is a long-term journey. Although

initial productivity loss and high implementation costs may pose financial risk in the

short term (Eastman et al., 2011), those who achieve enhanced BIM uses will gain a

competitive edge to win bids in the future market. This advantage in turn justifies the

Page 287: building information modeling–based process transformation to improve productivity in the

267

long-term investment (PrS2; H08, H09, H30, and H31) and convinces them to

guarantee the sufficient support (PrS3; H31) such as resources (Teo and Heng, 2007).

The solid vision of the team can be built through the high-profile communication

among the major stakeholders (Autodesk, 2012). In addition, the management needs

to convey the vision to the staff working on the shop floor, who otherwise cannot get

energy in the organizational transformation.

Lifecycle value proposition (PrMS4). In the project organization, the architect,

engineers, and contractors tend to be stuck to a culture and methods that minimize

cost in delivering their scopes of work, but rarely try to maximize the value of their

work (Kunz and Fischer, 2012). Previous studies (Sattineni and Mead, 2013; Lam,

2014) noted that the project delivery currently adopted in the construction industry

would cause many issues such as inefficient processes, repeated efforts, and liability

anxieties; for example, it is common for the architecture and engineering team to

create one design model, and for the main contractor and specialty contractors to

develop their own models based on the information from the design team. This is

because the design model is created without considering downstream uses and the

contractors are not involved in the design process. The value of the design work is not

maximized. In contrast, full BIM implementation requires the architectural model to

be shared with the engineers for creating their models on the same design; the key

contractors are also involved in the design stage and get the design models as bases

for creating their construction models (Gao and Fischer, 2006; Porwal and Hewage,

2013). This process would create constant value throughout the project. In addition,

periodical project meetings can be arranged to enhance the BIM use in the day-to-day

activities on the shop floor to realize the vision. Thus, this strategy can strengthen the

positive influences associated with management processes (PrM1; H40) and daily

tasks (PrT1, H29 and H36; PrT2, H40; PrT3, H38).

Page 288: building information modeling–based process transformation to improve productivity in the

268

Multi-party agreement (PrMS5). Currently, the design processes may not be

collaborative because the design team and the construction team tend to act as

individuals by creating different models (Lam, 2014). Under the lifecycle value

proposition, the new multi-party contract should allow and ideally incentivize the

primary participants to openly share data and act as a collaborative team (Kunz and

Fischer, 2012). The information flow is then ensured when model management tasks

are collaboratively completed throughout the project lifecycle (PrT4; H16), beyond

the design and construction team (PrT2; H40).

Collective decision-making (PrMS6). The major stakeholders that have shared risks

and rewards in the project organization should be involved in project management.

The contractors are no longer chary of providing advice about the design that may

benefit the whole project. The owner can empower the key service providers to

jointly set project goals and control the project. Once a problem raises, the decisions

can be collectively made according to the sources of expertise and information

(PrM2; H20 and H34), rather than the relationships with the owner (AIA and AIACC,

2009).

Moving towards IFC (PrMS7). Interoperability issues were recognized as a

significant challenge in BIM work practices (Zahrizan et al., 2013). The continual

development of IFC can tackle these issues if the participating firms use IFC

compliant software and share models using IFC rather than their proprietary formats.

In the post-survey interviews, the experts reported that different team members often

used different software or versions of software. Therefore, this strategy could

improve data interoperability efficiency in the design modeling and coordination

(PrT1; H29 and H36).

Page 289: building information modeling–based process transformation to improve productivity in the

269

Cultivating subcontractors (PrMS8). If the design consultants and general contractor

spearhead the model development, visualization, and simulation for the specialty

contractors, many management processes (PrM1; H40) and day-to-day work practices

(PrT1, H29 and H36; PrT2, H40; PrT3, H38) can be efficiently completed to truly

realize the solid vision of full BIM implementation in the project. For example, MEP

specialty contractors can contribute their construction expertise in the creation and

coordination of MEP design models, which in turn guides their construction work on

site (Khanzode et al., 2007). Without trade contractor input, the design would not be

fixed.

Building a multiuser access data platform (PrMS9). To strengthen the information

exchange and management, the project team may build a data platform that allows all

the key participants to access and link it with their data management systems (Succar,

2009). For instance, this platform would facilitate to upload submittals by the main

contractor and specialty contractors, provide feedbacks by the owner and the design

team (PrT4; H16), update the design models to deal with changes and their lifecycle

implications, and retrieve the latest models and documents.

Design for fabrication (PrMS10). The early involvement of the key participants,

especially the manufacturers or suppliers, enables to maximize the use of OSM and

fix the design early before fabrication (PrS4; H36). The benefits of OSM can be

reaped if standard building components are used in the design and production (PrT3;

H38) (McFarlane and Stehle, 2014). The components need to be carefully transported

and stored with support from best practices in lean construction.

Page 290: building information modeling–based process transformation to improve productivity in the

270

7.3.5.3 Technology

Five technology management strategies (TMSs) were identified. The organizational

change attributes and CHCs that were potentially targeted by these strategies would

be elaborated as follows.

Government effort (TMS1). The lack of national standards and guidelines remains a

concern (Zahrizan et al., 2013). Cheng and Lu (2015) observed that Singapore is one

of the leading countries for standards development in Asia because the local

government have developed 12 of the 35 BIM standards in Asia by the time of this

said study. For example, the BIM Particular Conditions has been drafted to address

the procedures of handling digital data and the extent of reliance on BIM models by

each party (BCA, 2015b). In addition to this document, a comprehensive

interoperability standard should be developed for the local industry (TD; H43).

Meanwhile, BIM software have been constantly improving to enable the cross-

discipline integration at the construction level. The post-survey interviewees,

however, reported that the hardware in many firms cannot support the advanced

software applications efficiently. Thus, apart from the primary participants’

investments to improve their infrastructures, the local government should provide

further capital support, especially for the large number of SMEs to subsidize part of

the cost of subsequent infrastructure upgrades or subscriptions (TI; H42).

Design for fabrication (TMS2). Changing the design philosophy that was currently

based on traditional methods is essential to the organizational change (Blismas and

Wakefield, 2009). The early involvement of contractors and suppliers facilitates the

design for maximizing off-site production and assembly and leaving minimum

assembly work on site (McFarlane and Stehle, 2014). This would optimize

manufacturing functions, standardize design and manufacturing processes, reduce

Page 291: building information modeling–based process transformation to improve productivity in the

271

safety risks in a factory environment, ensure maximum quality, and simplify

construction processes (PrT3; H35) (Belay, 2009).

Moving towards IFC (TMS3). Technically, data exchange among disparate modeling

and analysis applications using proprietary formats can work well for those

interoperable applications made by particular vendors. In the project involving many

parties, other applications may also be useful to this project (TI; H44). In this case,

cross-vendor data exchange standard should be agreed on. The IFC format has been

reliably to enable this process (TD; H43 and H45-H47) if the team members can

collaborate with others using it (Khosrowshahi and Arayici, 2012).

Building a multiuser access data platform (TMS4). Technically, setting up such a data

platform shifts the management of the BIM models in a single party or between a few

parties to an integrated management paradigm (Succar, 2009). Maintaining integrity

across different design models is imperative in practice (TD; H43 and H45-H47),

because changes are made to different models by their respective disciplines. Both

manual updates using IFC and smart automated transactions in BIM servers require

specialized expertise (TI; H44), which urges the development of a multi-access

platform which allows all the team members to access and link it with their data

management systems.

Providing project-wide and in-house training (TMS5). Apart from the awareness and

willingness to implement BIM, technical knowledge and ability is also needed

(Forsythe et al., 2015). For example, onsite assembly has become a new construction

method (TC; H35). In the manufacturing industry, the principles behind this method

has been widely proven to be productive (Blismas and Wakefield, 2009; McFarlane

and Stehle, 2014). Thus, training programs should be provided for the team members

Page 292: building information modeling–based process transformation to improve productivity in the

272

to understand the design, manufacture, construction, and management practices of the

OSM process and how to collaborate with other team members in the process.

7.3.5.4 External environment

Two management strategies from the external environment were proposed. The

organizational change attributes and CHCs that were potentially targeted by the

external environment management strategies (EMSs) would be elaborated below.

Government effort (EMS1). From the external environment point of view,

government efforts can be the new legislations, which add on the existing policies

and standards. For example, the guide of incorporating the use of BIM in the design,

planning, construction, and operations processes of the DfMA approach should be

developed (ES1; H39). In the meantime, apart from providing training courses for the

practitioners in the BCA Academy, encouragement and support to the relevant

education programs in local universities and colleges should also be in place (BCA,

2016). Such programs would build a talent pool of BIM implementation (ES2; H26),

especially the management talents with BIM skills that can lead the BIM teams in the

local firms.

Continuous learning and training (EMS2). A project is a knowledge-intensive entity.

The project team’s knowledge bandwidth affects its ability to deal with emerging

challenges during project delivery. Such dynamics require ongoing learning and

augmentation of knowledge bandwidth. Full BIM implementation in the project is a

process of continual examination and improvement. It also requires continuous

learning and testing of sometimes new and misunderstood BIM concepts (Autodesk,

2012). In the changing market where buildings, organizational structures, and legal

structure become increasingly complex, the project team needs continuous training

Page 293: building information modeling–based process transformation to improve productivity in the

273

and learning to support the adoption of BIM and OSM in the daily work (ES2; H26).

With support from the management, individuals should also learn new technologies

such as the use of CNC rebar bending/cutting machines and casting systems that may

drive fabricators to use BIM (ET). Such efforts would motivate the participants and

build up valuable intellectual capital in the organization.

Overall, a summary of detailed influence paths (CHC–organizational change

attribute–CDC–managerial strategy) for each CHC would be further identified in

Section 9.2.4. In addition, as indicated in Section 6.3.1, as part of the validation of the

BBPT model developed in Chapter 9, six personal interviews were conducted with

the local BIM experts from six different building projects to solicit their comments on

the usefulness of the managerial strategies in helping their project leadership teams

make decisions to move towards higher BIMIR statuses (see Appendix 3). The

validation results would be analyzed and discussed in Section 9.4.

7.4 Summary

A total of 38 NVA activities and all their causes were validated by Survey I. Using

the data related to the frequency of occurrence of such activities, the fuzzy BIMIR

model was applied to evaluate the BIMIR statuses of the surveyed building projects

in Singapore, and the results reported an overall lonely BIM implementation status.

Besides, the wastes in the project groups of different BIMIR statuses were checked. It

was found that as BIMIR increased, the wastes became less severe to productivity

and the leading causes became less important to the NVA activities. In addition, 44

CHCs and 31 CDCs were found to be significantly influential. The differences in the

significance mean scores and rankings of these factors between the upfront and

downstream stakeholders were checked and explained. In addition, the proposed

organizational change framework could be used to interpret these significant factors

Page 294: building information modeling–based process transformation to improve productivity in the

274

from the perspectives of people, process, technology, and external environment,

which helped to figure out a set of managerial strategies for process transformation

towards higher levels of BIM implementation.

Page 295: building information modeling–based process transformation to improve productivity in the

275

Chapter 8: Case Study

8.1 Introduction

Since design consultants must submit their building plans for regulatory approvals

and actually they have somewhat overemphasize the submission policy (Lam, 2014),

full BIM implementation in building projects relies heavily on contractors’ BIM

implementation activities. This chapter presents a case study of BIM implementation

in a large construction and development firm based in Singapore, which was

conducted from May 2016 to August 2016. Specifically, two residential building

projects (coded as Project A and Project B) that were involved in Survey I were

selected as the subjects of the case study. The BIMIR statuses of the projects were S3

and S2, respectively. Table 8.1 shows the profile of the six interviewees who

provided information for the two projects.

Table 8.1 Profile of the interviewees in the case study

No. Experience Title Project BIMIR status

I1 16-20 years Project manager Project A S3 (collaborative BIM

implementation) I2 11-15 years Corporate BIM manager

I3 11-15 years BIM coordinator

I4 11-15 years Deputy project manager

I5 16-20 years Technical manager Project B S2 (lonely BIM

implementation) I6 5-10 years Quantify surveyor in charge

8.2 Background of Case Projects

The case firm was a Singapore-based subsidiary of a state-owned central enterprise in

China and has been a listed corporation. Since the foundation in 1992, the firm has

completed more than 150 projects in Singapore. Currently, the firm was a BCA-

registered contractor with a financial grade of A1 under the workhead of CW01

(general building), and with a financial grade of B1 under the workhead of CW02

(civil engineering). The tendering limits of A1 and B1 were unlimited and S$40

million, respectively. As shown in Table 8.1, Project A and Project B were involved

Page 296: building information modeling–based process transformation to improve productivity in the

276

in Survey I and selected to be further investigated. The firm served as general

contractors, with its subsidiaries being structural and MEP trade contractors in both

projects. Since the BIMIR status of Project A (S3) was higher than that of Project B

(S2), this study would discuss the dynamics of the firm’s process transformation

journey from Project B to Project A by enhanced BIM adoption.

Project A involved in the design and construction of a large ongoing residential

building project with a GFA of more than 100,000 m2. Because of the huge volume of

this project as well as the experience, skills, resources, and reputation of the case

firm, Project A was selected by the Singapore government as a sample project to

showcase BIM implementation in the local context. The local government agencies

visited the construction site regularly to oversee BIM uses in this project and

productivity figures at the time of the visits.

The data were collected through participant observations, personal interviews, and

analysis of past documents. Firstly, the author passively participated in the weekly

project meetings in the construction site office over two months (from May 2016 to

July 2016) when the basement construction was about to be completed and the

structure construction was ongoing. In each project meeting, there was a BIM session

(also called technical meeting, VDC meeting, or coordination meeting). The basic

purpose of the author’ attendance in the meetings was to observe how the project

team collaborated in the BIM work processes. Specifically, the behavioral patterns

(such as body language, verbal expressions, meeting rules, model management

procedures, and provide-wide communication) of the team members were directly

observed. Notes were taken promptly and supplemented by using a recorder. The

observations ended until a milestone event when the government agencies visited the

site and the project team reported and showcased its milestone BIM uses and

resulting performance improvement. Secondly, a project manager, a corporate BIM

Page 297: building information modeling–based process transformation to improve productivity in the

277

manager, a BIM coordinator, and a deputy project manager (see Table 8.1) were

interviewed, which allowed them to provide in-depth views on BIM implementation

activities in this project. In addition, information about the BIM implementation

practices were also collected from past documents about this project. The minutes of

meetings, milestone reports, and productivity figures were collected from the project

manager and deputy project manager through personal networking and were

analyzed. The websites of the firm and Project A were regularly reviewed. The author

also visited the construction site at times to understand the site layout and filed staff’s

behaviors and feelings.

By comparison, Project B was a typical residential building project that the case firm

had been working on. A technical manager and a quantity surveyor in charge were

interviewed. The key activities related to BIM implementation could be represented

by the typical current project delivery described in Table 3.5 and very often resulted

in many NVA activities and tremendous wastes such as design changes and reworks.

The two interviewees pointed out that the biggest issue was that the design

consultants were neither able nor required by the owner to build the design models of

good quality that the contractors could use. Specifically, the owner did not push hard

enough. Apart from the lack of time and resources (Lam, 2014), the consultants did

not get sufficient fees from the design contracts, which also caused reluctance of the

consultants to use BIM. Consequently, the designs created by the consultants were

messy. For example, green lines of the construction site were not at the same location

in the architectural design and structural design, some openings for air-conditioning

were not appropriately located, and columns were occasionally meters away from

where they should be located. All these should have been done in the design stage.

However, the technical manager reported that after winning the bid and entering this

project, the general contractor struggled for a few months for the designs, because the

contractor found many design errors and discrepancies and had to come back with the

Page 298: building information modeling–based process transformation to improve productivity in the

278

consultants to discuss and finalize the designs. Especially, most MEP designs were

re-developed. Furthermore, standards of the consultants and the contractors were

different. The manager stated that the consultants had their own standards (Zahrizan

et al., 2013), such as producing 2D drawings, and the general contractor could only

create its construction model and drawings by imaging how the consultants modeled

the designs. All these practices were NVA.

Thus, BIM implementation in this project was lonely and fragmented in individual

parties, rather than on a project-wide collaboration basis. In other words, the project

delivery process was not changed except that design tools of individual parties were

upgraded, but such tools were not interoperable and integrated across parties. Even

the production of construction shop drawings still relied heavily on the traditional

CAD approach. In addition, the operations and maintenance team tended to be

unwilling to use the 3D design models because the team neither trusted nor had

access to the as-built model unless the owner bought and shared the model. The

technical manager implied that to improve productivity performance, the consultants

side needed a lot of improvements (Sattineni and Mead, 2013). This was because they

not only created a number of NVA activities upfront, but also affected BIM

implementation activities downstream.

8.3 Critical Changes

Compared with Project B, critical changes were made in Project A in terms of BIM

implementation activities and were discussed and analyzed in this section. Project A

adopted a VDC-ish approach, with the general contractor as the leading party to

coordinate and compile BIM models and construction BIM execution plan in the

construction stage. The project manager of the general contractor indicated that

moving construction activities forward to the design stage was a good way of

Page 299: building information modeling–based process transformation to improve productivity in the

279

improving its productivity performance, because the virtually coordinated design

could enhance on-site work accuracy. The corporate BIM manager believed that

collaborative BIM implementation could create value in this journey. Because of the

distinctive differences between the typical current delivery process and the VDC

delivery process, this project team needed to change the typical way of working

which was not efficient enough. The key critical hindrances encountered included the

following aspects: (1) adaptability. All the key stakeholders had to change their

preferential working habits and lacked training on the new way of working

(Autodesk, 2012); (2) trade contractors’ capabilities. They preferred to use 2D

drawings for submissions and construction, and lacked BIM skillsets; and (3) smooth

communication of information. It was difficult to get the major stakeholders to

collectively communicate, review, and coordinate digital models (AIA and AIACC,

2009; Forsythe et al., 2015). Nevertheless, to obtain the benefits of BIM, the project

team overcame the hindrances by: (1) aligning all the key stakeholders from the

beginning and providing project-wide trainings when possible; (2) spearheading BIM

model development for all the key trade contractors; and (3) involving all the key

stakeholders in the weekly project meetings to contribute knowledge. Particularly, in

this project the owner’s representatives who were BIM experts participated in the

BIM sessions very actively. This helped the service providers understand their client’

s brief.

With these strategies, the project team had managed the design well in the

construction phase through the following main changes in the BIM work practices:

(1) Sharing design models between the owner, the design consultants, the general

contractor, and the key trade contractors (AIACC, 2014). Specifically, after

obtaining the regulatory approvals, the architect and structural engineer handed

over their design models to the general contractor for further design development

and coordination in the preconstruction stage. The general contractor used the

Page 300: building information modeling–based process transformation to improve productivity in the

280

architectural design model as a reference to integrate it with the structural design

model, and created a high-level (schematic) construction model which considered

the BIM uses of downstream subcontractors;

(2) Requiring and facilitating the trade contractors to use BIM. The top-down

approach was adopted on the contractors side (Autodesk, 2012). In the tendering

stage, the general contractor passed its coordinated design models to potential

subcontractors, instead of 2D drawings, and in subcontracts, required the

subcontractors to model in their fields. The subcontractors then created their

models based on the construction model, rather than 2D CAD drawings. This

result substantiated the argument of Autodesk (2012) that the top-down approach

should be accompanied by bottom-up approaches such as educating and creating

convenience for the subcontractors to carry out their day-to-day work on the shop

floor; and

(3) Driving collaboration and coordination among the team in a “Big Room”

(Khanzode et al., 2007). The project team focused on a “build twice” concept.

Every Monday, the key stakeholders worked together in the BIM sessions to do

design coordination, discussed on RFIs and technical issues, and commented on

the design together. The high-level construction model was then virtually

displayed, communicated, reviewed, and revised collectively by all the key

stakeholders, including precast contractors, in the weekly technical meetings in

the construction site office, greatly reducing design and construction

uncertainties. The corporate BIM manager of the general contractor believed that

if its BIM team created concrete values and benefits to the other parties of the

project team, these parties would simply follow and be cooperative. The values

could be as basic as highlighting clashes in reports and showcasing them in the

3D environment. For example, in a BIM session that focused on solving

discrepancies between the general contractor and the structural consultant, other

parties also actively participated and provided advice. Besides, the general

Page 301: building information modeling–based process transformation to improve productivity in the

281

contractor presented the corporation of PBUs into the design model in the virtual

environment for the whole team to discuss, which facilitated project-wide

decision-making on the use of the PBUs before actual construction. Finally, all

the models were approved by the owner and specific design consultants and

combined to guide construction activities (including off-site production) three

levels ahead versus the actual site progress. During the construction stage, a

central data platform was used to help the team members store, view, retrieve,

review, comment, and monitor the latest composite construction model and

relevant documents. This platform enabled the general contractor to upload

submittals, as well as facilitated the owner and the consultants to provide

feedbacks in a real time manner. Thus, all the key stakeholders could share

information and update their respective models to deal with changes and their

lifecycle implications. In addition, the general contractor would also share its as-

built constriction model to the operations and maintenance team.

Although these changes indeed solved some BIM implementation issues in this

project, there were also practices that remained the same with the traditional way of

working. According to the observations and interviews, some typical issues included:

(1) The design consultants only modeled in their fields for regulatory submissions.

No multidisciplinary coordination was completed. Consequently, the general

contractor’s BIM team could not use their design models, even they were willing

to do that for saving time and efforts. The project manager stated that to change

this situation, the owner must push the consultants to create good-quality models.

Such models need to be coordinated in multi-disciplines; otherwise, burden

would still be added to the contractors.

(2) Some team members were pushed, but may not be mentally ready and

subjectively willing to implement BIM (such as for achieving key performance

indicators required by the BCA). This result echoed the finding of Kiani et al.

Page 302: building information modeling–based process transformation to improve productivity in the

282

(2015) that firms in Iran were satisfied with their conventional methods to

complete the design and construction work and therefore saw BIM uses as extra

efforts. For example, in a BIM session, after the general contractor’s BIM team

showcased how 3D design environment could help detect clashes in the basement

design, an experienced architect still found a few clashes. She emotionally argued

that “people use 3D design models, which may be not as good as before when

they had to image according to 2D documents; BIM makes people lazy now”.

The management staff and its BIM team of the general contractor responded that

“it is people’s fault, not BIM’s”. The mindset needed to be constantly changed.

The way of people doing things really matters.

(3) During the BIM sessions, the owner’s representatives and the design consultants

could not understand clearly the general contractor who could not ask specific

questions at times. This was because the trade contractors, especially those with

much work experience, were reluctant to be involved in these sessions and did

not show much interest and enthusiasm in such sessions. In these cases, the

upfront parties needed to guess, affecting the successful communication.

(4) The contractors needed more details and often raised RFIs. For example, a trade

contractor did wrongly in wall construction because insufficient details were

available after the type of the wall was changed in the design model. Besides, the

contractors could not distinguish frame width from structural openings. Thus,

with the use of BIM, NVA activities and wastes, even substantially reduced, still

existed in this project.

8.4 Performance Assessment

The critical changes that had been made in Project A resulted in enhanced milestone

productivity performance by the time of this case study. As examples, productivity

improvements for the shop drawing preparation process and the RFIs were reported

Page 303: building information modeling–based process transformation to improve productivity in the

283

in this study. The total time spent on preparing the structural and architectural shop

drawings was projected from the following activities: (1) coordinating the structural,

architectural, and MEP design provisions; (2) preparing the shop drawings; (3)

virtually reviewing and revising the designs and drawings; and (4) approving the

drawings. Meanwhile, by driving the project-wide collaboration and coordination in

the weekly technical meetings, all interfacing issues were virtually resolved, thus

substantially reducing the number of RFIs. Consequently, about 60% of the RFIs

raised were related to material or specification clarifications, rather than design

issues. The estimated time spent for preparing the structural and architectural shop

drawings in Project A were 836 man hours and 1408 man hours, and saved by 40%

and 42%, respectively, compared with Project B. The numbers of RFIs in the

architecture, structure, and MEP disciplines were 126, 63, and 15, respectively,

substantially reduced by 70% in total. The results were in line with Nath et al. (2015)

which found that using BIM to re-engineer the precast shop drawing generation

process in public building projects in Singapore would result in a substantial time

saving of 380 man hours of producing the shop drawings, leading to an overall

productivity improvement of about 36% for processing time and 38% for total time.

This study only presented the results of the time savings for the work process of

preparing the coordinated structural and architectural shop drawings as well as the

reduced number of RFIs. The reasons were that the time saving statistics were not

fully documented as the residential project was not yet completed, and that the project

team tended to be wary of providing all the statistics of the enhanced productivity

performance. Thus, it was considered reasonable that this study only reported the

figures of the shop drawing preparation processes and the RFIs as examples to

illustrate the enhanced productivity performance resulted from the BIM-based

implementation and process changes.

Page 304: building information modeling–based process transformation to improve productivity in the

284

In addition, the change towards full BIM implementation for productivity gains was

also supported by previous studies. For example, Cohen (2010) reported that an

interior tenant improvement project was completed using the IPD approach within 8.5

months, an impossible schedule with the typical traditional delivery method used by

the owner. Critical changes in the work processes were made in the project team. The

owner actively participated in the design and construction phases. The contractors

and suppliers were involved during the design stage to share their expertise; for

instance, their virtual construction manager worked together with the architectural

design consultant two days a week. Meanwhile, building officials also participated

from the early design stage to ensure that the permitting process would not impede

the schedule, saving more than one week in the planning reviews. Thus, the

documents generated from the composite design model created by the whole team

could be used for permitting, analysis, bidding, fabrication, and so on. The

contractors could procure time- and cost-variable materials and services earlier. After

the detailed design phase, the composite model was moved from the architect to the

contractors, instead of being re-built by the contractors in the early construction stage

which was NVA. During construction, the architect moved to the construction site.

This close collaboration with the contractors made many NVA activities unnecessary

and freed the architect to spend much less time reviewing and responding the RFIs

and submittals from the contractors. Consequently, there were 125 RFIs in total on

the final cost of $13.34 million, 39.61% fewer than the average of 155 RFIs per $10

million recommended by Chelson (2010). The results suggested that compared with

the typical current project delivery process, following an IPD delivery process and

monitoring the project process with a predetermined BIM implementation plan would

largely avoid the occurrence of the critical NVA activities and their resulting wastes

in the project.

Page 305: building information modeling–based process transformation to improve productivity in the

285

The case study expanded the process re-engineering of the precast shop drawings

production in Singapore (Nath et al., 2015) to the project lifecycle perspective. It is

likely that collaborative BIM implementation would help remove critical NVA

activities and wastes in the design, construction, and operations and maintenance

processes and led to a more efficient project delivery. Even the contractual structure

and the BIM work activities in the design stage of Project A remained the same with

those of the typical current project delivery process adopted in Singapore, the project-

wide BIM collaboration built in the construction stage could also significantly reduce

the critical NVA activities and their resulting wastes, enhancing productivity

performance. This finding indicated short-term wins for the project team and

represented a benchmark for adopting an appropriate BIM-based delivery process to

identify and reduce the wastes in the Singapore construction industry. Nevertheless,

the collaboration and coordination in the earlier stages of the project were not yet

achieved, and therefore a collaborative contractual structure that governs the close

project-wide collaboration and multidisciplinary coordination from the beginning

throughout project completion remains urgently needed in Singapore (Fischer et al.,

2014). Besides the owner’s awareness of and insights into the value that full BIM

implementation can add to the project, the incentives from the government like

additional GFA may motivate the owner to adopt new contractual solution to reduce

the reluctance of the design consultants and the risk of the downstream parties being

involved in an earlier stage. In addition, because in most projects in Singapore the

designers tend to lack time and fees to allocate sufficient resources to adopt BIM, the

owner may need to give more fees to the design team and require them to consider

the downstream uses when creating their design models, with more financial

incentives.

Because of the large number of foreign workforce in the Singapore construction

industry, local building project teams may involve people of different races, ages, and

Page 306: building information modeling–based process transformation to improve productivity in the

286

ways of working. Because of this unique circumstance, local experimentation and

continuous learning play a central role in BIM implementation in Singapore

(Miettinen and Paavola, 2014). Although it is difficult to change people from diverse

backgrounds, they would accept and adopt BIM if they see the concrete values.

Page 307: building information modeling–based process transformation to improve productivity in the

287

Chapter 9: Developing a BIM-Based Process Transformation

Model for Building Projects in Singapore

9.1 Introduction

This chapter presents the development of the BBPT model for building projects in

Singapore. The BBPT model intends to evaluate the BIMIR status of a building

project in the planning stage, and provide managerial strategies in terms of people,

process, technology, and external environment. This model consists of two part-

models: a BIMIR evaluation model and a BIMIR improvement model. The former

uses the 38 critical NVA activities as evaluation sub-criteria to assess the BIMIR

status of the building project and investigate the leading causes to these NVA

activities, whereas the latter analyzes the critical factors that hinder this project to be

at the current BIMIR status and motivate it to change to a higher BIMIR status from

the organizational change perspective. Managerial strategies, with different priorities,

on people, process, technology, and external environment aspects are provided for the

project organization to move towards full BIM implementation. In particular, the 33

responding projects that completed both surveys were analyzed as an example to

illustrate the BIMIR movement model, and the analysis results also served as part of

the general BBPT model. Finally, the validation results of the BBPT model from six

different building projects were presented and discussed.

9.2 Comparing the CHCs and CDCs among BIMIR Statuses

9.2.1 Profile of respondents and their organizations involved in both

surveys

The profile of the 33 respondents who had participated in both surveys is presented in

Table 9.1. It was deemed as appropriate that the 33 completed questionnaires were

Page 308: building information modeling–based process transformation to improve productivity in the

288

obtained based on their willingness to participate in the study (Wilkins, 2011).

Regarding the main businesses of these organizations, 12 (36.4%) were general

construction firms, and five (15.2%), three (9.1%), two (6.1%), two (6.1%), and one

(3.0%) were architectural firms, MEP engineering firms, structural engineering firms,

trade construction firms, and a facility management firm, respectively. Moreover, the

eight organizations in the “others” category included four developers, two precasters,

and two other consultancy firms (one multidisciplinary consultancy firm and one

BIM consultancy firm). In terms of the organizations’ BCA financial grades, 18

(54.5%) were contractors registered with the BCA. Among which, 11 (33.3%) were

A1 contractors, followed by three (9.1%) L6 contractors, two (6.1%) C3 contractors,

one (3.0%) B1 contractor, and one (3.0%) single grade contractor. The remaining 15

(45.5%) organizations were not contractors. As for the experience of BIM

implementation, 18 (54.5%) of the organizations started to use BIM in their building

projects in last one to three years, and six (18.2%) had implemented BIM for four to

five years. Five firms had implemented BIM over five years, and none had over 10

years’ relevant experience. Because of the reasons stated in Sections 7.2.1 and 7.3.1,

the four (12.1%) responding organizations without BIM implementation experience

were also included in the subsequent data analysis.

Table 9.1 Profile of the respondents and their organizations involved in both surveys

Characteristics Categorization Frequency Percentage (%)

Organization

Main business Architectural firm 5 15.2

Structural engineering firm 2 6.1

MEP engineering firm 3 9.1

General construction firm 12 36.4

Trade construction firm 2 6.1

Facility management firm 1 3.0

Others 8 24.2

BCA financial grade A1 11 33.3

B1 1 3.0

C3 2 6.1

Single grade 1 3.0

L6 3 9.1

Not applicable 15 45.5

Page 309: building information modeling–based process transformation to improve productivity in the

289

Years of BIM adoption 0 year 4 12.1

1-3 years 18 54.5

4-5 years 6 18.2

6-10 years 5 15.2

Over 10 years 0 0

Respondent

Discipline Government agent 0 0

Developer 3 9.1

Architect 7 21.2

Structural designer 3 9.1

MEP designer 2 6.1

General contractor 11 33.3

Trade contractor 3 9.1

Supplier/Manufacturer 2 6.1

Facility manager 2 6.1

Years of experience 5-10 years 15 45.5

11-15 years 6 18.2

16-20 years 1 3.0

21-25 years 1 3.0

Over 25 years 10 30.3

With respect to the disciplines, 11 (33.3%) of the 33 respondents served as general

contractors, followed by seven (21.2%) architects, three (9.1%) developers, three

(9.1%) structural engineers, three (9.1%) trade contractors, two (6.1%) MEP

designers, two (6.1%) manufacturers/suppliers, and two (6.1%) facility managers.

None government agent was involved. Moreover, 15 (45.5%) of the respondents had

five to ten years’ working experience, indicating a large proportion of young BIM

implementers. Ten (30.3%) and six (18.2%) respondents had worked for over 25

years and 11 to 15 years in the Singapore construction industry.

Therefore, the profile indicated that the 33 respondents could well represent the key

BIM implementers in the local construction industry, assuring the response quality.

According to the generally-accepted rule, statistical analysis could be performed with

a sample size larger than 30, because the central limit theorem held true (Ott and

Longnecker, 2010).

Page 310: building information modeling–based process transformation to improve productivity in the

290

9.2.2 Linking Survey I and Survey II

The data of the 33 responding projects that participated in both surveys were analyzed

for two purposes: (1) to exemplify the application of the BIMIR movement model;

and (2) to use the analysis results to predict the performance of the overall 89

surveyed projects for generalization to some extent. Firstly, the achievement of the

first purpose either would not be influenced by sample size, or relied on qualitative

characteristics of fundamentals in the general model.

Secondly, the appropriateness and reliability of using the 33 responses to predict the

89 responses should be assessed. The Spearman’s rank correlation was performed. As

shown in Table 9.2, the correlation coefficients were 0.639 and 0.850 for the 44

CHCs and the 31 CDCs, respectively, with p-values of 0.000. These test statistics

provided clear indication that the mean score rankings of all the CHCs and the CDCs

were significantly agreed upon by the 33 respondents and the overall 89 respondents.

In addition, the two groups of respondents shared seven common CHCs and CDCs in

their respective top 10 rankings, despite differences in the rankings of some CHCs

and CDCs. Thus, the sample of the 33 respondents and their organizations could be

used to link Survey I and Survey II, and identify the top-ranked hindrances and

drivers. This method was deemed reasonable, because this study would identify the

top 10 CHCs and CDCs in terms of the mean score ranking rather than mean scores.

Table 9.2 Overall mean scores and rankings of the CHCs and CDCs in different

samples

CHC Code 89 data sets 33 data sets CDC Code 89 data sets 33 data sets

Mean Rank Mean Rank Mean Rank Mean Rank

H01 3.64 8 3.70 7 D01 3.99 1 3.82 6

H02 3.48 21 3.36 40 D02 3.64 11 3.85 4

H03 3.26 41 3.45 35 D03 3.71 9 3.58 16

H04 3.69 3 3.70 7 D04 3.82 4 3.76 7

H05 3.69 3 3.58 21 D05 3.90 3 3.91 1

H06 3.42 28 3.61 16 D06 3.76 6 3.76 7

H07 3.69 3 3.67 11 D07 3.79 5 3.85 4

H08 3.37 33 3.30 43 D08 3.63 12 3.76 7

Page 311: building information modeling–based process transformation to improve productivity in the

291

H09 3.54 13 3.73 4 D09 3.69 10 3.58 16

H10 3.33 37 3.52 28 D11 3.30 26 3.39 26

H11 3.43 23 3.73 4 D12 3.44 21 3.45 23

H12 3.79 1 3.85 2 D13 3.57 16 3.64 13

H13 3.33 37 3.42 37 D14 3.62 13 3.58 16

H14 3.62 11 3.58 21 D15 3.75 7 3.67 11

H15 3.43 23 3.39 38 D16 3.45 19 3.61 15

H16 3.34 35 3.36 40 D17 3.92 2 3.91 1

H19 3.43 23 3.70 7 D18 3.45 19 3.24 30

H20 3.28 40 3.36 40 D19 3.26 30 3.30 29

H21 3.35 34 3.48 30 D20 3.75 7 3.88 3

H22 3.34 35 3.55 24 D21 3.58 15 3.70 10

H23 3.42 28 3.55 24 D22 3.53 17 3.58 16

H24 3.26 41 3.45 35 D23 3.48 18 3.67 11

H26 3.42 28 3.61 16 D24 3.29 27 3.21 31

H27 3.71 2 3.73 4 D25 3.35 23 3.39 26

H28 3.65 7 3.88 1 D26 3.28 28 3.45 23

H29 3.43 23 3.48 30 D27 3.26 30 3.48 21

H30 3.31 39 3.61 16 D28 3.31 24 3.52 20

H31 3.63 10 3.76 3 D29 3.27 29 3.48 21

H32 3.52 17 3.64 13 D30 3.60 14 3.64 13

H33 3.54 13 3.55 24 D31 3.40 22 3.39 26

H34 3.53 15 3.61 16 D32 3.31 24 3.42 25

H35 3.51 19 3.52 28 – – – – –

H36 3.49 20 3.67 11 – – – – –

H37 3.45 22 3.39 38 – – – – –

H38 3.40 31 3.61 16 – – – – –

H39 3.25 43 3.48 30 – – – – –

H40 3.39 32 3.64 13 – – – – –

H41 3.22 44 3.21 44 – – – – –

H42 3.66 6 3.58 21 – – – – –

H43 3.52 17 3.64 13 – – – – –

H44 3.43 23 3.48 30 – – – – –

H45 3.53 15 3.55 24 – – – – –

H46 3.64 8 3.70 7 – – – – –

H47 3.56 12 3.48 30 – – – – –

Note: the Spearman’s rank correlation coefficient for the CHCs between the two

samples was 0.639 (p-value = 0.000); the Spearman’s rank correlation coefficient for

the CDCs between the two samples was 0.850 (p-value = 0.000).

9.2.3 Comparison among projects with different BIMIR

9.2.3.1 CHCs

Out of the 33 surveyed building projects in Singapore, eight, 20, and five received

BIMIR statuses of S1 (no BIM implementation), S2 (lonely BIM implementation),

and S3 (collaborative BIM implementation), respectively. This section investigated

Page 312: building information modeling–based process transformation to improve productivity in the

292

the differences in the mean scores and rankings of the 44 CHCs among the three

BIMIR status groups of projects.

As shown in Table 9.3, the mean scores ranged from 3.50 to 4.13 in the BIMIR S1

group of building projects, from 3.00 to 3.90 in the S2 group of building projects, and

from 3.00 to 4.20 in the S3 group of building projects. To test whether the mean

scores differed among the three BIMIR status groups, the one-way ANOVA were

performed. The analysis results indicated that none of the 44 CHCs significantly

differed among the three status groups at the 0.05 level (see Table 9.3).

Table 9.3 Mean scores and rankings of the CHCs: BIMIR S1 vs. BIMIR S2 vs.

BIMIR S3

Code S1 (no BIM) S2 (lonely BIM) S3 (collaborative BIM) ANOVA

Mean Rank Mean Rank Mean Rank p-value

H01 3.75 23 3.60 9 4.00 4 0.760

H02 3.88 12 3.20 39 3.20 37 0.277

H03 3.88 12 3.25 38 3.60 12 0.422

H04 3.75 23 3.75 3 3.40 22 0.863

H05 3.50 42 3.60 9 3.60 12 0.983

H06 3.63 33 3.60 9 3.60 12 0.998

H07 3.88 12 3.60 9 3.60 12 0.846

H08 4.13 1 3.00 43 3.20 37 0.070

H09 4.00 8 3.60 9 3.80 7 0.643

H10 3.88 12 3.30 34 3.80 7 0.341

H11 3.50 42 3.75 3 4.00 4 0.634

H12 3.88 12 3.75 3 4.20 1 0.696

H13 3.63 33 3.30 34 3.60 12 0.763

H14 3.88 12 3.30 34 4.20 1 0.326

H15 3.63 33 3.15 40 4.00 4 0.179

H16 4.13 1 3.05 42 3.40 22 0.096

H19 3.75 23 3.55 16 4.20 1 0.526

H20 3.50 42 3.30 34 3.40 22 0.900

H21 3.75 23 3.40 28 3.40 22 0.745

H22 3.75 23 3.45 23 3.60 12 0.695

H23 3.63 33 3.45 23 3.80 7 0.741

H24 3.75 23 3.40 28 3.20 37 0.677

H26 4.00 8 3.40 28 3.80 7 0.449

H27 4.13 1 3.65 8 3.40 22 0.402

H28 4.00 8 3.90 1 3.60 12 0.836

H29 3.63 33 3.50 20 3.20 37 0.789

H30 4.13 1 3.45 23 3.40 22 0.267

H31 3.63 33 3.80 2 3.80 7 0.933

H32 4.00 8 3.55 16 3.40 22 0.486

Page 313: building information modeling–based process transformation to improve productivity in the

293

H33 3.88 12 3.45 23 3.40 22 0.630

H34 3.88 12 3.55 16 3.40 22 0.682

H35 3.75 23 3.40 28 3.60 12 0.776

H36 4.13 1 3.50 20 3.60 12 0.431

H37 4.13 1 3.10 41 3.40 22 0.064

H38 4.13 1 3.50 20 3.20 37 0.160

H39 3.88 12 3.40 28 3.20 37 0.379

H40 3.63 33 3.70 6 3.40 22 0.794

H41 3.88 12 3.00 43 3.00 44 0.077

H42 3.75 23 3.55 16 3.40 22 0.892

H43 3.75 23 3.60 9 3.60 12 0.958

H44 3.63 33 3.45 23 3.40 22 0.929

H45 3.63 33 3.60 9 3.20 37 0.717

H46 3.88 12 3.70 6 3.40 22 0.774

H47 3.75 23 3.40 28 3.40 22 0.745

Besides, the Spearman’s rank correlation was conducted to check whether there were

ranking differences among the three BIMIR status groups of building projects. As

indicated in Table 9.4, the correlation coefficients among the three BIMIR status

groups of projects were neither high nor significant at the 0.05 level. This result was

consistent with the top 10 CHCs between the three status groups. Specifically, the

BIMIR S1 and S2 groups of projects shared three common CHCs, and the S1 and S3

groups shared two common CHCs, despite the S2 and S3 groups shared five in their

respective top 10 rankings. Thus, the mean scores and rankings of the CHCs were not

significantly agreed upon by the three BIMIR status groups of projects in which BIM

implementation was hindered by different top-ranked CHCs. It was concluded that

moving from BIMIR S1 to BIMIR S2 would need fundamental changes and moving

from BIMIR S2 to BIMIR S3 would need significant changes.

Table 9.4 Spearman’s rank correlation of the CHCs: BIMIR S1 vs. BIMIR S2 vs.

BIMIR S3

BIMIR status Test statistics S1 (no BIM) S2 (lonely BIM) S3 (collaborative BIM)

S1 (no BIM) Correlation

coefficient

1.000 -0.202 -0.187

p-value – 0.188 0.225

S2 (lonely

BIM)

Correlation

coefficient

– 1.000 0.261

p-value – – 0.087

S3

(collaborative

BIM)

Correlation

coefficient

– – 1.000

p-value – – –

Page 314: building information modeling–based process transformation to improve productivity in the

294

9.2.3.2 CDCs

This section investigated the differences in the mean scores and rankings of the 31

CDCs among the three BIMIR status groups of building projects. As shown in Table

9.5, the mean scores ranged from 2.75 to 4.38 in the BIMIR S1 group of building

projects, from 3.20 to 4.10 in the S2 group of building projects, and from 3.20 to 4.00

in the BIMIR S3 group of building projects. The one-way ANOVA results suggested

that all the 31 CDCs did not have statistically significant differences among the three

groups at the 0.05 level (see Table 9.5).

Table 9.5 Mean scores and rankings of the CDCs: BIMIR S1 vs. BIMIR S2 vs.

BIMIR S3

Code S1 (no BIM) S2 (lonely BIM) S3 (collaborative BIM) ANOVA

Mean Rank Mean Rank Mean Rank p-value

D01 3.75 5 4.00 2 3.20 30 0.540

D02 4.00 2 3.85 6 3.60 8 0.845

D03 3.63 8 3.55 20 3.60 8 0.988

D04 3.75 5 3.85 6 3.40 20 0.775

D05 3.75 5 4.00 2 3.80 4 0.871

D06 3.88 3 3.80 8 3.40 20 0.653

D07 4.38 1 3.75 9 3.40 20 0.186

D08 3.63 8 3.90 5 3.40 20 0.688

D09 3.50 19 3.60 18 3.60 8 0.982

D11 3.63 8 3.30 26 3.40 20 0.764

D12 2.88 30 3.65 17 3.60 8 0.112

D13 3.50 19 3.75 9 3.40 20 0.788

D14 3.00 28 3.70 14 4.00 1 0.300

D15 3.50 19 3.75 9 3.60 8 0.885

D16 3.13 26 3.75 9 3.80 4 0.404

D17 3.63 8 4.10 1 3.60 8 0.559

D18 2.75 31 3.25 28 4.00 1 0.177

D19 3.13 26 3.30 26 3.60 8 0.695

D20 3.63 8 3.95 4 4.00 1 0.778

D21 3.63 8 3.70 14 3.80 4 0.969

D22 3.63 8 3.60 18 3.40 20 0.926

D23 3.63 8 3.70 14 3.60 8 0.979

D24 3.00 28 3.20 31 3.60 8 0.583

D25 3.63 8 3.25 28 3.60 8 0.669

D26 3.25 25 3.50 21 3.60 8 0.797

D27 3.63 8 3.45 23 3.40 20 0.897

D28 3.63 8 3.50 21 3.40 20 0.929

D29 3.50 19 3.40 24 3.80 4 0.811

D30 3.38 24 3.75 9 3.60 8 0.721

D31 3.50 19 3.40 24 3.20 30 0.890

D32 3.88 3 3.25 28 3.40 20 0.260

Page 315: building information modeling–based process transformation to improve productivity in the

295

As indicated in Table 9.6, the Spearman’s rank correlation coefficients were 0.416

(moderate correlation) between the BIMIR S1 and BIMIR S2 as well as -0.455

(moderate negative correlation) between the BIMIR S1 and BIMIR S3 groups of

projects, with p-values below 0.05. These results agreed with the fact that the two

pairs shared nine and seven common CDCs in the respective top 10 rankings,

respectively. Meanwhile, the rank correlation coefficient was 0.001 (no correlation)

between the BIMIR S2 and BIMIR S3 groups of projects, despite seven common

CDCs were shared in their respective top 10 rankings. Therefore, the top-ranked

factors driving the surveyed projects of BIMIR S1 and BIMIR S2 were similar, and

those driving the projects of BIMIR S1 and BIMIR S3 were significantly different.

Therefore, moving from BIMIR S1 towards BIMIR S2 was natural, whereas moving

towards BIMIR S3 would need structural changes in the project teams in all aspects.

Each team member should try to change their work practices and adapt to work in

collaborative networks.

Table 9.6 Spearman’s rank correlation of the CDCs: BIMIR S1 vs. BIMIR S2 vs.

BIMIR S3

BIMIR status Test statistics S1 (no BIM) S2 (lonely BIM) S3 (collaborative BIM)

S1 (no BIM) Correlation

coefficient

1.000 0.416 -0.455

p-value – 0.020* 0.010

*

S2 (lonely

BIM)

Correlation

coefficient

– 1.000 0.001

p-value – – 0.995

S3

(collaborative

BIM)

Correlation

coefficient

– – 1.000

p-value – – – *Correlation was significant at the 0.05 level (two-tailed).

9.2.4 Areas needing improvement

Based on the interpretation of the 44 CHCs and 31 CDCs with the proposed

organizational change framework in Section 7.3.4 and the explanation of the

managerial strategies for reducing the CHCs and strengthening the CDCs on people,

Page 316: building information modeling–based process transformation to improve productivity in the

296

process, technology, and external environment aspects in Section 7.3.5, the overall

influence paths of managing the CHCs and CDCs from the organizational change

perspective were figured out, as shown in Table 9.7. It can be seen from this table that

a comprehensive list of managerial strategies were prepared for project leadership

teams to choose from. Given a CHC, the associated change attribute(s) and CDC(s)

could be identified, and then the corresponding managerial strategies would be

determined. For example, if BIM implementation was hindered by one of the CHCs,

“executives failing to recognize the value of BIM-based processes and needing

training” (H01), in a building project, two organizational change attributes, namely

“commitment on new ways” (PeC3) and “mindset and attitude” (PeI1) were identified

as the key areas that required significant improvements (see Figure 7.1 and Table

9.7). Then, three strategies including “early involvement of major participants”

(PeMS3), “removing inertia of the management and employees” (PeMS5), and

“highlighting short-term wins” (PeMS7) could be used. The selection of these

strategies depended on the two CDCs (D03 and D08) by which the project team was

also motivated to implement BIM. The theoretical rationale and explanations of the

strategies could be found in Sections 7.3.4 and 7.3.5.

In addition, the local government’s leadership (PeMS1 and EMS1) and project

participants’ continuous learning and training (EMS2) were constant strategies that

every project organization needs to implement to develop, succeed, and survive in the

changing built environment.

To help building projects of lower BIMIR statuses move towards higher BIMIR

statuses, this study identified the key areas requiring improvements with priorities

from the organizational change perspective. If everything is important, nothing is

manageable. The top-ranked CHCs represented the most important areas of BIM

Page 317: building information modeling–based process transformation to improve productivity in the

297

Table 9.7 Overall paths of reducing the CHCs and strengthening the CDCs from the

organizational change perspective

CHC

code

Organizational

change attribute

CDC

code

Proposed managerial strategy

H01 PeC3 D03 PeMS5: removing inertia of the management and

employees

PeMS7: highlighting short-term wins

D08 PeMS3: early involvement of major participants

PeMS7: highlighting short-term wins

PeI1 D03 PeMS5: removing inertia of the management and

employees

PeMS7: highlighting short-term wins

H02 PeS3; PeS5;

PeC1

D12 PeMS4: sharing interests and risks

H03 PeI2 D04 PeMS6: providing project-wide and in-house

training

H04 PeI3 D04 PeMS6: providing project-wide and in-house

training

H05 PeC2 D02 PeMS5: removing inertia of the management and

employees

PeMS7: highlighting short-term wins

H06 PeI1 D03 PeMS5: removing inertia of the management and

employees

PeMS7: highlighting short-term wins

H07 PeC2 D02 PeMS5: removing inertia of the management and

employees

PeMS7: highlighting short-term wins

H08 PrS2 D01, D07 PrMS3: long-term vision and support

H09 PrS2 D01, D07 PrMS3: long-term vision and support

H10 PeS5 D12 PeMS4: sharing interests and risks

H11 PeC2 D02 PeMS5: removing inertia of the management and

employees

PeMS7: highlighting short-term wins

H12 PeS4 D08 PeMS2: standard contract

PeMS3: early involvement of major participants PeC1 D08

D14

H13 PeC4 D08 PeMS2: standard contract

PeMS3: early involvement of major participants

H14 PeI2 D04 PeMS6: providing project-wide and in-house

training

PeMS8: cultivating trade contractors

H15 PeI1 D03 PeMS5: removing inertia of the management and

employees

PeMS7: highlighting short-term wins

H16 PrT4 D23 PrMS9: building a multiuser access data platform

D24 PrMS5: multi-party agreement

PrMS9: building a multiuser access data platform

H19 PrS1 D05 PrMS1: owner management

H20 PrM2 D13 PrMS6: collective decision-making

H21 PeS5 D12 PeMS4: sharing interests and risks

H22 PeC3 D11 PeMS7: highlighting short-term wins

H23 PeI2 D04 PeMS6: providing project-wide and in-house

training

PeMS8: cultivating trade contractors

Page 318: building information modeling–based process transformation to improve productivity in the

298

H24 PeS4 D08 PeMS2: standard contract

H26 ES2 D31 EMS1: government effort

EMS2: continuous learning and training

H27 PeS1 D25 PeMS2: standard contract

H28 PeS3 D12 PeMS4: sharing interests and risks

H29 PrT1 D16 PrMS4: lifecycle value proposition

PrMS7: moving towards IFC

PrMS8: cultivating subcontractors D17

D18

D19

H30 PrS2 D01, D07 PrMS3: long-term vision and support

H31 PrS2 D01, D07 PrMS3: long-term vision and support

PrS3 D01

H32 PeS5 D12 PeMS4: sharing interests and risks

H33 PeS1 D25 PeMS2: standard contract

H34 PrM2 D13 PrMS2: government effort

PrMS6: collective decision-making

H35 TC D22 TMS2: design for fabrication

TMS5: providing project-wide and in-house

training D29

H36 PrS4 D26, D27 PrMS10: design for fabrication

PrT1

D16 PrMS4: lifecycle value proposition

PrMS7: moving towards IFC

PrMS8: cultivating subcontractors D17

D18

D19

H37 PrM2 D13 PrMS2: government effort

H38 PrT3 D20 PrMS4: lifecycle value proposition

PrMS8: cultivating subcontractors

D28 PrMS10: design for fabrication

H39 ES1 D09 EMS1: government effort

H40 PrM1 D15 PrMS4: lifecycle value proposition

PrMS8: cultivating subcontractors

PrT2 D21 PrMS4: lifecycle value proposition

PrMS5: multi-party agreement

PrMS8: cultivating subcontractors

H41 PeS6 D12 PeMS4: sharing interests and risks

H42 TI D30 TMS1: government effort

H43 TD D30 TMS1: government effort

TMS3: moving towards IFC

TMS4: building a multiuser access data platform

H44 TI D30 TMS3: moving towards IFC

TMS4: building a multiuser access data platform

H45 TD D30 TMS3: moving towards IFC

TMS4: building a multiuser access data platform

H46 TD D30 TMS3: moving towards IFC

TMS4: building a multiuser access data platform

H47 TD D30 TMS3: moving towards IFC

TMS4: building a multiuser access data platform

Extra PeS2 D06 PeMS1: government support

ET D32 EMS1: government effort

EMS2: continuous learning and training

Page 319: building information modeling–based process transformation to improve productivity in the

299

implementation, and the top-ranked drivers represented the most important

motivations that the projects already beard in mind and could somewhat control.

Given resource constraints of a building project, the leadership team should allocate

resources to the most important areas (top 10 factors) rather than all the key areas (all

critical factors).

Table 9.3 and Table 9.5 presents the top 10 CHCs and CDCs for the eight surveyed

building projects of BIMIR S1, 20 surveyed projects of BIMIR S2, and five surveyed

projects of BIMIR S3. Based on the interpretation of the top 10 CHCs with the

proposed organizational change frameworks in Figures 7.1 to 7.4, the most important

organizational change attributes for the three BIMIR status groups of surveyed

building projects were obtained (see Table 9.8) and discussed below.

Among the most important areas, some areas should be further targeted with

emphasis. As shown in Table 9.8, the building projects of BIMIR S1 (no BIM

implementation) should primarily target “vision and mission” (PrS2) for

improvement, which was required by three top-ranked CHCs. This was consistent

with the survey finding that the respondents cited “BIM vision and leadership from

the management” (D01) as their top CDC. It was advocated that BIM implementation

starts with a well-articulated vision that is supported by the management staff

(Autodesk, 2012; Miettinen and Paavola, 2014). Thus, these projects should

incorporate such a vision into their project goals and individual corporate goals as

well, which echoes with the local government’s vision, mission, and support to drive

the local industry to implement BIM or IDD in the CTIM (BCA, 2017a). Besides,

time and efforts dedicated to BIM implementation would give the teams and firms a

competitive edge in the future market. These can be meaningful for them to start to

embark on BIM implementation.

Page 320: building information modeling–based process transformation to improve productivity in the

300

Table 9.8 Key areas of improvement in the organizational change framework

Component Factor Change attribute BIMIR

S1

BIMIR

S2

BIMIR

S3

People Inter-enterprise

structure

Contractual relationship √ √

Leadership

Reward arrangement √ √

Involvement √ √

Risk allocation √ √

Conflict management

Corporate

culture

Sharing √ √

Willingness to change √√√ √

Commitment on new ways √ √

Trust and transparency

Individuals and

roles

Mindset and attitude √√ √√

Knowledge, skills and

experience

√√

Training and education √

Process Management

processes

Communication √

Controlling and decision-

making

Corporate

strategy

Goals and requirements setting √

Vision and mission √√√ √√ √√

Top management support √ √

Processes alignment √

Task Coordination and simulation √

Documentation √

Production √

Model management √

Technology Infrastructure Hardware and software

solutions

Data exchange Interoperability √√√

Construction

method

Prefabrication

External

environment

Socioeconomic

environment

Policy

Changing market √ √

Technological

environment

New technological solutions

√ indicates the area required by one CHC to be improved for changing to a high

BIMIR status.

√√ indicates the area required by two CHCs to be improved for changing to a high

BIMIR status.

√√√ indicates the area required by three CHCs to be improved for changing to a high

BIMIR status.

The building projects of BIMIR S2 (lonely BIM implementation) should firstly target

“willingness to change” (PeC2) and “interoperability” (TD) for improvements, which

were required by three top-ranked CHCs, followed by “mindset and attitude” (PeI1)

and “vision and mission” (PrS2). For example, some stakeholders in the projects that

Page 321: building information modeling–based process transformation to improve productivity in the

301

implemented lonely BIM might take advantage of information asymmetry at the

expense of others and see collaborating toward a “win-win situation” as preventing

them from optimizing the amount of benefits they could have won (Forsythe et al.,

2015). As a result, project-wide transparency and collaboration could not be built in

the project teams. The construction and operations expertise could not be

substantially input into the upfront design modeling and multidisciplinary

coordination, and potential liability issues would inevitably be raised in the dynamic

project management in different phases. Therefore, the awareness of being

collaborative and open data exchange were essential to shifting from lonely BIM

implementation to collaborative or full BIM implementation.

The building projects of BIMIR S3 (collaborative BIM implementation) should

emphasize “mindset and attitude” (PeI1), “knowledge, skills and experience” (PeI2),

and “vision and mission” (PrS2) for improvements, which were all required by two

top-ranked CHCs. The results indicated that to change from collaborative BIM

implementation towards full BIM implementation, the BIM vision from the top

management, more positive attitudes toward changing, and sufficient knowledge and

experience among the project organizations are crucial.

Meanwhile, “vision and mission” (PrS2) and “mindset and attitude” (PeI1) were two

key organizational change attributes that were at least highlighted twice in two or

three BIMIR status groups of projects. These were also the areas that need to be

constantly improved for changing towards full BIM implementation.

With the CHC-change attribute–CDC–managerial strategy paths presented in Table

9.7, the managerial strategies for the surveyed projects of the three BIMIR statuses

could be determined. Nevertheless, the interaction between the CHCs and the CDCs

should be taken into consideration when a project organization decides to implement

Page 322: building information modeling–based process transformation to improve productivity in the

302

the strategies. This study formulated four priority rules that were coded in If-Then

conditional statements for the project team to prioritize the implementation of the

proposed managerial strategies and the allocation of resources as well (see Table 9.9).

The priority rules include:

(1) Rule A (Priority one). Among the overall influence paths in Table 9.7, if a path

beginning with a top-ranked CHC (among top 10) does not involve top-ranked

CDCs (among top 10), then the CHC must be overcome and its associated

organizational change attribute(s) must be improved with respective managerial

strategies indicated on this path;

(2) Rule B (Priority two). If a path beginning with a top-ranked CHC (among top 10)

involves top-ranked CDCs (among top 10), then the CHC should be further

overcome and its associated organizational change attribute(s) should be further

improved with respective managerial strategies indicated on this path, despite

already having some motivations to improve this area in the project organization;

(3) Rule C (priority three). If a path beginning with a non-top-ranked CHC (not

among top 10) does not involve top-ranked CDCs (among top 10), then the CHC

may need to be further overcome and its associated organizational change

attribute(s) may need to be further improved with respective managerial strategies

indicated on this path, and resources should be assigned to implement these

managerial strategies; and

(4) Rule D (priority four). If a path beginning with a non-top-ranked CHC (not

among top 10) involves top-ranked CDCs (among top 10), then the CHC might

be further overcome and its associated organizational change attribute(s) might be

further improved with respective managerial strategies indicated on this path

given that the project organization has relatively sufficient resources. It should be

noted that the change may be not necessarily from BIMIR Si to BIMIR Si+1, but

from the current BIMIR status to full BIM implementation (BIMIR S4).

Page 323: building information modeling–based process transformation to improve productivity in the

303

Table 9.9 Priority rules of implementing strategies for changing from a lower BIMIR

status to higher BIMIR statuses

Rule If (CHC scenario) Then (decision) Priority

A Top 10 CHCs, without corresponding

top 10 CDCs (CHCs-CHCs∩CDCs)

Must improve/overcome 1 (top)

B Top 10 CHCs, with corresponding top

10 CDCs (CHCs∩CDCs)

Should further

improve/overcome, despite

already having some

motivation

2

C Non-top 10 CHCs, without

corresponding top 10 CDCs

May need some improvement

(assigning resources)

3

D Non-top 10 CHCs, with corresponding

top 10 CDCs

Might further improve (if

having sufficient resources)

4

(bottom)

The BIM Project Execution Planning Guide defines the resources of each party as

personnel (BIM team), tools and their training, and IT support (Anumba et al., 2010).

In addition, capital investment should also be included in the resources (Zhao et al.,

2014a). Insufficiency of any kind of the resources would hinder BIM implementation.

This tallies with the post-survey interviews that the local practitioners need training

and technical support for BIM implementation in practice as they are not

knowledgeable and experienced enough about higher levels of BIM implementation.

In most cases, the senior management can determine the allocation of the resources.

While the biggest firms are able to ride on the BIM wave, a huge number of SMEs

face adoption challenges such as lacking the capital investment for BIM tools and

trainings to build up BIM competencies (Forsythe et al., 2015).

Following these priority rules, the key areas of organizational change attributes and

managerial strategies on people, process, technology, and external environment

aspects for the surveyed building projects of BIMIR S1, S2, and S3 groups could be

identified, as shown in Table 9.10, Table 9.11, and Table 9.12, respectively.

Managerial strategies of higher priorities were discussed below, and those of lower

priorities may also be implemented, depending on actual situations facing projects.

Page 324: building information modeling–based process transformation to improve productivity in the

304

Table 9.10 Prioritized change areas and managerial strategies for a project organization to move from BIMIR S1

Change

attribute

People Process Technology External

MS1 MS2 MS3 MS4 MS5 MS6 MS7 MS8 MS1 MS2 MS3 MS4 MS5 MS6 MS7 MS8 MS9 MS10 MS1 MS2 MS3 MS4 MS5 MS1 MS2

PeS1 B

PeS2 D

PeS3 A

PeS4 D D

PeS5 A

PeS6 C

PeC1 C C C

PeC2 D D

PeC3 D D D

PeC4 D D

PeI1 D D

PeI2 D D

PeI3 D

PrM1 C C

PrM2 A C

PrS1 D

PrS2 B

PrS3 D

PrS4 A

PrT1 A A A

PrT2 D D D

PrT3 B B B

PrT4 A A

TI C C C

TD C C C

TC C C

ES1 C

ES2 A A

ET D D

Note: MS=managerial strategy;

A The project organization must improve in this area with respective managerial strategy;

B The project organization should further improve in this area with respective managerial strategy, despite already having some motivation in this area;

C The project organization may need to improve in this area with respective managerial strategy;

D The project organization might further improve in this area with respective managerial strategy if having sufficient resources.

Page 325: building information modeling–based process transformation to improve productivity in the

305

Table 9.11 Prioritized change areas and managerial strategies for a project organization to move from BIMIR S2

Change

attribute

People Process Technology External

MS1 MS2 MS3 MS4 MS5 MS6 MS7 MS8 MS1 MS2 MS3 MS4 MS5 MS6 MS7 MS8 MS9 MS10 MS1 MS2 MS3 MS4 MS5 MS1 MS2

PeS1 A

PeS2 D

PeS3 A

PeS4 B B

PeS5 C

PeS6 C

PeC1 A A C

PeC2 B B

PeC3 B A A

PeC4 D D

PeI1 A A

PeI2 D D

PeI3 B

PrM1 B B

PrM2 D D

PrS1 D

PrS2 B

PrS3 B

PrS4 C

PrT1 C C C

PrT2 A A A

PrT3 D D C

PrT4 C C

TI D D D

TD B B B

TC C C

ES1 C

ES2 C C

ET C C

Note: MS=managerial strategy;

A The project organization must improve in this area with respective managerial strategy;

B The project organization should further improve in this area with respective managerial strategy, despite already having some motivation in this area;

C The project organization may need to improve in this area with respective managerial strategy;

D The project organization might further improve in this area with respective managerial strategy if having sufficient resources.

Page 326: building information modeling–based process transformation to improve productivity in the

306

Table 9.12 Prioritized change areas and managerial strategies for a project organization to move from BIMIR S3

Change

attribute

People Process Technology External

MS1 MS2 MS3 MS4 MS5 MS6 MS7 MS8 MS1 MS2 MS3 MS4 MS5 MS6 MS7 MS8 MS9 MS10 MS1 MS2 MS3 MS4 MS5 MS1 MS2

PeS1 D

PeS2 C

PeS3 D

PeS4 A A

PeS5 B

PeS6 D

PeC1 A A D

PeC2 B B

PeC3 A B A

PeC4 C C

PeI1 B B

PeI2 A A

PeI3 C

PrM1 D D

PrM2 C C

PrS1 B

PrS2 A

PrS3 A

PrS4 C

PrT1 D D D

PrT2 D D D

PrT3 D D C

PrT4 D D

TI D D D

TD D D D

TC C C

ES1 D

ES2 A A

ET C C

Note: MS=managerial strategy;

A The project organization must improve in this area with respective managerial strategy;

B The project organization should further improve in this area with respective managerial strategy, despite already having some motivation in this area;

C The project organization may need to improve in this area with respective managerial strategy;

D The project organization might further improve in this area with respective managerial strategy if having sufficient resources.

Page 327: building information modeling–based process transformation to improve productivity in the

307

The analysis results in Table 9.10 indicated that the key areas that urgently needed to

be changed for the surveyed projects of BIMIR S1 (no BIM implementation) were

related to the following organizational change factors: task, corporate strategy, inter-

enterprise structure, and external socioeconomic environment, which were consistent

with the results in Table 9.8. To improve such areas, the managerial strategies,

including “lifecycle value proposition” (PrMS4), “multi-party agreement” (PrMS5),

“moving towards IFC” (PrMS7), “cultivating subcontractors” (PrMS8), “building a

multiuser access data platform” (PrMS9), “design for fabrication” (PrMS10),

“sharing interests and risks” (PeMS4), “government effort” (EMS1), and “continuous

learning and training” (EMS2) needed to be implemented with priorities. Since the

Singapore government has made plenty of efforts in driving the local firms to

implement BIM, such as the mandatory BIM e-submissions and new BIM funds

(Cheng and Lu, 2015; BCA, 2016), the local construction market had been changed

under the first CPR. The availability of some BIM infrastructure and experts was

ensured. Thus, self-motivation (vision and mission) and planning of the project teams

to adopt new technologies, such as BIM and OSM, or technological processes would

be of the greatest importance to improve the efficiency of carrying out various tasks.

Table 9.11 suggested that there was an urgent need for the surveyed projects of

BIMIR S2 (lonely BIM implementation) to change their practices in the following

organizational change factors: corporate culture, individuals and roles, inter-

enterprise structure, and task. Based on the priority rules, five strategies on people

aspect, including “standard contract” (PeMS2), “early involvement of major

participants” (PeMS3), “sharing interests and risks” (PeMS4), “removing inertia of

the management and employees” (PeMS5), and “highlighting short-term wins”

(PeMS7), were selected for the urgent need for building trust-based collaboration in

the project teams. Meanwhile, “lifecycle value proposition” (PrMS4), “multi-party

agreement” (PrMS5), and “cultivating subcontractors” (PrMS8) could be used to

Page 328: building information modeling–based process transformation to improve productivity in the

308

more efficiently perform project delivery tasks. In addition, Forsythe et al. (2015)

advocated that open data sharing should be ensured to create “win-win” situations in

the project organizations, rather than fragmented information flow.

The analysis results in Table 9.12 implied that the areas related to corporate culture,

individuals and roles, inter-enterprise structure, corporate strategy, and external

socioeconomic environment in the organizational change framework were deemed

key to the transformation of the surveyed projects of BIMIR S3 (collaborative BIM

implementation). The following managerial strategies, namely “standard contract”

(PeMS2), “early involvement of major participants” (PeMS3), “providing project-

wide and in-house training” (PeMS6), “highlighting short-term wins” (PeMS7),

“cultivating trade contractors” (PeMS8), “long-term vision and support” (PrMS3),

“government effort” (EMS1), and “continuous learning and training” (EMS2) were

prioritized for improvements. The major stakeholders in the building projects of

BIMIR S3 had already work relatively collaboratively with each other. The main

form of contract (PeMS2) could be more integrated, to which some agreements could

be attached, such as multi-party collaboration agreements to incentivize all the major

stakeholders to participate and share insights upfront, including specialty consultants

and contractors that were usually not early involved. Meanwhile, the strategy

“sharing interests and risks” (PeMS4) was also prioritized. Once people are on the

same boat, they can perform in a best-for-project manner. Nevertheless, such efforts

also need the government’s legal support (Eastman et al., 2011).

Although the sample size of 33 met the basic requirement for generalizing the main

findings of this study, the sizes in each BIMIR status group were not large. Thus, the

analysis results in Tables 9.10, 9.11, and 9.12 were considered more as snapshots for

illustrating the BIMIR movement model, than as the generalization of the main

findings in this study.

Page 329: building information modeling–based process transformation to improve productivity in the

309

9.3 A BBPT Model

To generalize the findings from the surveyed building projects and the case study in

the Singapore construction industry, the BBPT model was developed for building

projects that plan to implement BIM, as shown in Figure 9.1. The model consists of

six fundamental stages that are included in two parts of the model: BIMIR status

evaluation and BIMIR status movement. The deconstruction of the model was also

demonstrated in Figure 1.4. The basic purpose of developing this model was to help

project management teams improve their BIMIR statuses and transform their project

delivery approaches for productivity gains.

The first step in this model is to obtain and compile corporate goals of primary

project participants and their typical work practices (such as BIM uses, daily work

processes, information exchange procedures, data management, and communication

patterns). After starting a building project, the owner engages its team members in

stages to build a specific project organization as the project proceeds. Normally, all

the key parties have documented their standard corporate practices of providing

specific AEC services in the building projects that they have been working on in

Singapore. The key activities related to BIM implementation in the Singapore

construction industry may echo sentiments in Table 3.5. They tend not to be

productive enough due to the partial implementation of BIM. Although the local

government has been driving the local firms to implement BIM, the state of BIM

adoption is uneven in the market. The largest firms, such as some principal design

consultants and general contractors, tend to be very advanced to adopt BIM and thus

reap the benefits more fully, whereas the others may be in the beginning phase. The

beginners account for a large proportion of the design consultants and trade contractors.

Page 330: building information modeling–based process transformation to improve productivity in the

310

Are there significantNVA activities?

1. obtain and compile typical work practices being carried out by the major stakeholders in different

phases of their building projects in Singapore

2. compare these work practices with the 38 critical NVA activities (Table 7.2)

No

Build a project team at the beginningof a new building project

Yes

BIMIR S4: Full BIM implementation

A proposed FSE model (Equations 4.7 to 4.12 and Table 4.5)

BIMIR S2: lonely BIM

Leading causes to the critical NVA activities in each BIMIR

status(Table 7.14)

BIMIR S3: collaborative BIM

Key parties for BIMIR S1

BIMIR S1: no BIM

Project team input: implementation level of the NVA activities

A proposed organizational change framework for building projects that implement BIM (Table 5.3)

Project team input:significance of CHCs (Table 7.19)

Project team input: significance of CDCs (Table 7.21)

5. determine priorities of strategies to be implemented using the rule: f (top 10 CHCs, top 10 CDCs) (Table 9.9)

Managerial strategies:§ People§ Process§ Technology§ External environment

Change attributes on people

Change attributes on process

Change attributes on technology

Change attributes on external environment

4. identify critical factors affecting change towards full BIM implementation

Overall paths: CHCs-change attributes-CDCs-managerial strategies (Table 9.7)

6. implement managerial strategies vis-a-vis key change areas for transforming from BIMIR S1 (e.g. Table 9.10 for the surveyed projects)

Implement managerial strategies vis-a-vis key change areas for transforming from BIMIR S2 (e.g. Table 9.11 for the surveyed projects)

Implement managerial strategies vis-a-vis key change areas for transforming from BIMIR S3 (e.g. Table 9.12 for the surveyed projects)

Weighting of project phases and the 38

NVA activities (Table 7.4)

Key parties for BIMIR S2

Key parties for BIMIR S3

Part II:

BIMIR

movement

Part I:

BIMIR

evaluation

Amongtop 10?

CHCs

Yes

Amongtop 10?

CDCs

No

Yes

Priority one Priority three Priority four

Amongtop 10?

Yes

No

Priority two

NoCDCs

3. evaluate the BIMIR status of this project

Figure 9.1 BIM-based process transformation model for building projects

Page 331: building information modeling–based process transformation to improve productivity in the

311

In addition, facility managers tend to operate building facilities in a conventional

manner; BIM is usually not used in the operations and maintenance stage. Although

the BIM Particular Conditions was released, the main form of contract currently

adopted in Singapore is still based on the traditional adversarial system (BCA, 2015).

Overall, the Singapore construction industry is not fully BIM-ready for project-wide

collaboration at different phases of the building project (Lam, 2014).

The second step is to compare these typical work practices with their counterparts

among the 38 critical NVA activities in the project lifecycle, as shown in Table 7.2. If

no NVA activities are found in the typical work practices that are carried out by the

major stakeholders in this project, then this project can be judged as BIMIR S4 and is

planning on full BIM implementation. Nevertheless, the post-survey interviewees

observed that currently very few building projects were adopting a full BIM

implementation approach in the Singapore construction industry. Only a few firms

had been trying to deliver their projects using the principles of IPD, and such a

delivery approach was IPD-ish, rather than full BIM implementation at all.

The next step in the BBPT model is to evaluate the BIMIR status of this project using

the proposed fuzzy BIMIR evaluation model (see equations 4.7 to 4.12 and Table

4.5). The weighting of the seven project phases and 38 critical NVA activities were

presented in Table 7.4. The project organization can input the implementation level

(frequency of occurrence) of the 38 critical NVA activities, according to their

compiled typical work practices (obtained in the first step), using the five-point scale

(1 = very low, 2 = low, 3 = medium, 4 = high, and 5 = very high; or alternatively, 1 =

never, 2 = rarely, 3 = sometimes, 4 = often, and 5 = always). Following the

calculation process that can be found in Appendix 4, the BIMIR status can be

obtained. Given the specific BIMIR status of this project, the leading causes to the

critical NVA activities can be referred to in Table 7.14, which also indicates the

Page 332: building information modeling–based process transformation to improve productivity in the

312

responsible team members that mostly contributed to the critical NVA activities and

would take the lead in implementing managerial strategies which would be

determined later.

Step four is to identify the factors that significantly drive this project to be at the

current BIMIR status (calculated in the third step) and prevent the project being at a

higher status. Specifically, the project leadership team needs to input the significance

level of the 44 CHCs (see Table 7.19) and 31 CDCs (see Table 7.21) in terms of

affecting their BIM implementation activities in the planning stage of this project.

Two methods can be used: (1) collective rating. The team provides its inputs after

open discussions collectively according to the actual situation of this project; and (2)

multiple team members participate and provide their ratings independently. To avoid

confusion, such as many factors sharing the same rakings, a Likert scale with a wide

range or a percentile ranking should be used in the first case. In the second case, the

data related to the significance level provided by all the team members should be

averaged. A five-point scale can be used in the rating, namely 1 = very insignificant,

2 = insignificant, 3 = neutral, 4 = significant, and 5 = very significant. Based on the

significance rating, the CHCs and CDCs could be ranked. For example, the rankings

of the CHCs and CDCs for the BIMIR S1, S2, and S3 groups of surveyed projects

can be found in Table 9.3 and Table 9.5, respectively. Since the numbers of the

surveyed projects for BIMIR S1 (8) and S3 (5) were relatively small, the ranking

results in the two tables were regarded as an example. To increase the prediction

accuracy and reflect the contemporary situation of this project, the project leadership

team may re-assign the significance level of the CHCs and CDCs according to their

actual circumstances and particular project characteristics, using the rating scale

mentioned above.

Page 333: building information modeling–based process transformation to improve productivity in the

313

Using the proposed framework in Table 5.3, the CHCs and CDCs can be interpreted

from the organizational change perspective, as indicated in Figures 7.1 to 7.4. The

generic overall paths that linked the CHCs and CDCs to the organizational change

attributes and managerial strategies in terms of people, process, technology, and

external environment are presented in detail in Table 9.7.

Step five is to determine the priorities of the proposed managerial strategies to be

implemented in this particular project for prediction. Based on the top 10 rankings of

the CHCs and CDCs obtained in Step four, the key areas of organizational change can

be ascertained and the managerial strategies on people, process, technology, and

external environment aspects are therefore selected as well. Following the rules (see

Table 9.9) that consider the interaction function between the top-ranked CHCs and

CDCs, the four-level priorities of implementing the selected managerial strategies in

this particular building project organization can be determined. The highest

management priority is coded as priority one (rule A).

Last but not least, the project leadership team can develop its resources allocation and

leveling plan to implement the managerial strategies with different priorities.

Considering the affordability of necessary resources for BIM implementation (such as

BIM experts, software and their training, hardware, IT, and capital investment) and

the If-Then conditional statements in Table 9.9, the managerial strategies can be

prioritized, subject to the sponsorship from the senior management of the project

organization and of the team members. For example, the four-level priorities of the

managerial strategies for the surveyed projects of BIMIR S1, S2, and S3 groups can

be referred to in Table 9.10, Table 9.11, and Table 9.12, respectively. With the

prioritized strategies well planned in the project beginning stage and implemented in

the design, construction, and operations stages of this particular building project, it is

expected that the BIMIR status would be improved.

Page 334: building information modeling–based process transformation to improve productivity in the

314

Although the BCA has issued the CITM in October 2017, the BBPT model developed

in this study still contributes to scholarship and practice. The implementation of the

CITM is based on widespread BIM implementation in the local construction industry,

which is the main focus of this study.

9.4 Validation of the BBPT Model

To prove that the BBPT model was effective for building projects in Singapore, a

total of six professionals were interviewed to solicit their comments on the quality,

degree of accuracy, and observed robustness of the model, as indicated in Section

6.3.1. These experts participating in the validation were coded as VE1, VE2, VE3,

VE4, VE5, and VE6 (see Table 9.13).

Table 9.13 Profile of the validation experts

Interviewee Experience Designation Firm

VE1 17 years Senior design manager Developer

VE2 16 years Project manager General construction firm

VE3 11 years Project manager General construction firm

VE4 11 years Senior engineer MEP consultancy firm

VE5 12 years Contracts manager Construction and development firm

VE6 6 years Senior quantity surveyor General construction firm

The number of experts was considered adequate for validating a project model, with

references to previous construction management studies. Specifically, Liu and Ling

(2005) used one expert with three cases to verify a fuzzy system for mark-up

estimations. Arain and Low (2006) used four professionals with one case to validate a

knowledge-based decision support system for managing variation orders. Imriyas

(2009) used five experts with one case to validate an expert system for insurance

premium rating.

Previous construction management studies (Liu and Ling, 2005; Lim et al., 2012;

Ling et al., 2012; Zhao et al., 2016b) have examined the validity of their models or

Page 335: building information modeling–based process transformation to improve productivity in the

315

systems by calculating percentage error (PE), mean PE (MPE), and mean absolute PE

(MAPE). This approach was also adopted to determine the validity of the BBPT

model in this study in terms of NVAI scores. As indicated in Section 6.3.1, the NVAI

scores estimated by the professionals regarding their building projects were coded as

𝑁𝑉𝐴𝐼𝐸, and the NVAI scores calculated from the BBPT model were coded as 𝑁𝑉𝐴𝐼𝑀.

In this study, the PE, MPE, and MAPE could be calculated using the following

equations:

𝑃𝐸 =(𝑁𝑉𝐴𝐼𝐸 − 𝑁𝑉𝐴𝐼𝑀)

𝑁𝑉𝐴𝐼𝐸⁄ × 100% (9.1)

𝑀𝑃𝐸 =∑ 𝑃𝐸𝑎

𝑛 (9.2)

𝑀𝐴𝑃𝐸 =∑|𝑃𝐸𝑎|

𝑛 (9.3)

where:

𝑎 represents validation expert 𝑎;

𝑛 represents the number of the valuation experts (𝑛 = 6).

The MPE was used to check whether the results calculated from the BBPT model

tended to be over (positive signs) or below (negative signs) the experts’ judgment,

and the MAPE reported the magnitude of the model’s errors (Liu and Ling, 2005). A

lower MAPE indicated a lower magnitude of the errors and a higher accuracy of the

model.

The validation results are presented in Table 9.14. The PE values ranged from -

31.32% to 30.84%, and the MPE values ranged from -11.59% to 12.29%. The MPE

signs implied that the model was likely to underestimate the frequency of occurrence

of the critical NVA activities in project beginning and completion, and overestimate it

from the design development phase to the construction phase as well as project NVAI

Page 336: building information modeling–based process transformation to improve productivity in the

316

score. Besides, only two phases received MPE values over 10%, suggesting that the

results of the BIMIR evaluation model were consistent with the experts’ estimations.

Table 9.14 Validation results of the BIMIR evaluation model

NVAI

score

PE (%) MPE

(%)

MAPE

(%) VE1 VE2 VE3 VE4 VE5 VE6

P1 4.30 4.68 6.27 13.52 13.52 2.63 7.49 7.49

P2 0.66 -14.57 -13.60 22.29 10.40 12.96 3.02 12.41

P3 -4.27 -12.70 -27.85 -16.47 8.77 7.90 -7.44 12.99

P4 -21.12 1.44 -14.99 -27.34 2.33 0.25 -9.90 11.25

P5 -25.00 -14.87 26.06 -2.38 23.08 -15.38 -1.42 17.79

P6 -30.46 22.93 -25.44 -31.32 -0.84 -4.44 -11.59 19.24

P7 -15.38 30.84 16.67 9.77 21.00 10.86 12.29 17.42

Project -27.25 0.30 -8.92 1.14 7.28 3.38 -4.01 8.04

BIMIR 0 0 0 0 0 0 0 0

In addition, the MAPE values ranged from 7.49% to 19.24%, indicating that the

BIMIR evaluation model had an assessment accuracy range of 80.76% to 92.51%. In

particular, the MAPE value of the projects’ NVAI scores was 8.04%. Moreover, the

BIMIR statuses of the projects that VE2 and VE3 participated in were estimated to be

BIMIR S3, and those of the other projects were BIMIR S2. These estimations were in

line with the adjusted translation of calculated NVAI scores to BIMIR statuses (see

Table 4.5). Thus, the model can be used to evaluate NVAI scores or BIMIR statuses

of project phases and projects.

Previous studies (Fayek and Sun, 2001; Fayek and Oduba, 2005) stated that a fuzzy

expert system would be reliable if the discrepancy between the defuzzified value and

the actual value was no more than 33%. Lee (2007b) reported a fuzzy operator that

showed the prediction accuracy range of 66.50% to 84.68%. Ling et al. (2012)

developed mathematical models to predict corporate competitiveness, with the MAPE

values of 14.40% and 22.20%. Zhao et al. (2016b) developed a knowledge-based

decision support system which had the accuracy ranging from 83.70% to 92.90% in

assessing 16 enterprise risk management maturity criteria as well as overall enterprise

Page 337: building information modeling–based process transformation to improve productivity in the

317

risk management maturity of Chinese construction firms. Compared with the previous

studies, the fuzzy BIMIR evaluation model in the BBPT model was deemed robust

and valid.

Moreover, the usefulness of the managerial strategies provided by the BBPT model

and their priorities were commented by the experts. All the experts believed that the

prioritized strategies were helpful to their project teams that planned to transform

towards higher BIMIR statuses. Specifically, VE2, VE4, and VE6 opined that these

managerial strategies provided a comprehensive solution that a building project

needed to enhance its BIM implementation from the organizational change

perspective. VE2 stated that a project organization, especially when BIM was first

implemented in the project, would easily refer to the strategies for help in the

decision-making process. VE4 reported that the strategies and their priorities

highlighted for the projects in each BIMIR status were reasonable, and that these

strategies were general and may not be applicable to every project due to the nature of

the project; therefore, the project should appropriately expand the strategies to figure

out an optimal solution according to the actual circumstances of this project.

However, VE3 revealed that large developers may emphasize more on marketing

than technical innovation, so the project organization would be fully ready to adopt

the BIM implementation strategies only when all the project stakeholders could

benefit. Also, VE1 pointed out that small projects would not need to change in every

aspect to adopt a number of strategies because BIM implementation would be more

helpful in huge projects. Nevertheless, VE1 admitted that the identification of the

systematically prioritized strategies catered to the Singapore context that even smaller

projects tended to be mandated to implement BIM. VE5 thought that a clear

understanding of the strategies at the project beginning was beneficial, which would

save much time and manpower in the project delivery. Therefore, the usefulness of

Page 338: building information modeling–based process transformation to improve productivity in the

318

the managerial strategies and the appropriateness of determining their priorities to the

project organization’s decision-making could be seen as valid.

Furthermore, the user-friendliness and functionality of the BBPT model were also

discussed. All the experts agreed that the BBPT model (see Figure 9.1) was user-

friendly and could function well in their projects. Specifically, VE1 reported that the

model seemed a little complicated. However, VE6 reported that since this model

required a project leadership team to input its project data (such as BIM

implementation activities and relevant factors), the team could get reasonable

exclusive strategies with different priorities suggested. Also, VE4 thought that overall

the model could close the gap between project team members for enhancing BIM

implementation, and that this model was theoretical, practical, and systematical. VE5

expressed that the model provided an intuitional view for the leadership team.

Nevertheless, VE6 suggested that it would be better to provide foreign versions of the

BBPT model as a large proportion of the construction workforce in Singapore were

foreigners.

9.5 Summary

The chapter presented the development of the BBPT model for building projects that

plan to implement BIM in the Singapore construction industry. Illustrated using the

33 surveyed building projects, the BBPT model can evaluate the BIMIR status of a

particular building project in the project beginning, and provide managerial strategies

from the perspectives of people, process, technology, and external environment. This

model consists of a BIMIR evaluation part-model and a BIMIR improvement part-

model. The overall influence paths that link the CHCs and CDCs with the

organizational change attributes and management strategies were figured out. Based

on the proposed four-level priority rules, appropriate managerial strategies can be

Page 339: building information modeling–based process transformation to improve productivity in the

319

prioritized to optimize the consumption of relevant resources. With such strategies

being well planned in the project beginning and implementation activities well

implemented at the later stages of this particular project, the BIMIR status is expected

to be improved. In addition, the BBPT model was validated by six practitioners in

Singapore, and recognized as an useful tool for enhancing BIM implementation in the

local construction industry.

Page 340: building information modeling–based process transformation to improve productivity in the

320

Chapter 10: Conclusions and Recommendations

10.1 Summary of Research Findings

10.1.1 Critical NVA industry practices and resulting wastes in the

Singapore construction industry

The first objective of this study was to identify critical NVA activities in current

project delivery in the Singapore construction industry, assess their influence on

productivity, and examine leading causes to these activities. As Table 4.1 indicates,

plenty of NVA industry practices were contributed by major stakeholders in different

project phases. These practices were compiled into 44 common NVA activities and of

which, 38 were deemed critical by the local practitioners participating in Survey I.

The six NVA activities that obtained either mean scores below 3.00 or p-values above

0.05 were excluded. The exclusion was supported by the comments from four post-

survey interviews. “Lack of involvement by general contractor and key trade

contractors to contribute site knowledge (not appointed)” (N3.5), “coordination of

building systems is deferred until construction phase due to unavailable trade

contractor input until then” (N3.4), “lack of involvement by manufacturer/supplier

(not appointed) to contribute knowledge of material selection, transportation, site

erection, and so on” (N3.7), “prefabrication of some systems cannot start as design is

not fixed”(N4.6), “owner and designers enable changes during construction” (N6.1),

“lack of involvement by general contractor and key trade contractors to contribute

site knowledge (not appointed)” (N2.4), “lack of involvement by

manufacturer/supplier (not appointed) to contribute fabrication knowledge” (N2.5),

“lack of involvement by facility manager (not appointed) to contribute operations and

maintenance knowledge” (N2.6), “lack of involvement by facility manager (not

appointed) to contribute knowledge of operations and maintenance” (N3.8), “architect

and engineers only pass 2D drawings or incomplete 3D BIM models to contractors

Page 341: building information modeling–based process transformation to improve productivity in the

321

and manufacturer/supplier” (N5.1) were the top 10 critical NVA activities. Thus,

Hypothesis 1, stating that “the construction industry agrees upon frequent NVA

activities in the current project delivery in the Singapore context”, was supported.

A total of 13 types of wastes were identified from the literature review to quantify the

impact of the critical NVA activities on productivity in the current project delivery.

Among these wastes, defects, waiting/idle time, overproduction,

transporting/handling materials, unnecessary inventory, excess processing beyond

standard, and unnecessary movement of people and equipment are major wastes in

the Toyota production system, while RFIs, reworks/abortive works, change orders,

activity delays, design deficiencies (errors, omissions, additions), and safety issues

(injuries) were raised by previous construction management studies.

A total of 53 causes to the critical NVA activities were identified. Among which,

“design models/drawings fit for mandatory BIM submissions, but not fit for intended

downstream use” (C3.04), “does not permit design changes as these are expensive

once fabrication has commenced” (C5.01), “general contractor has to make extra

efforts to reconfigure or reformat data” (C4.03), “architect and engineers do not

understand field operations enough and lack construction input in design” (C3.05),

“lack of skilled BIM experts to engage” (C3.06), “lack of skilled BIM experts to

engage to help construction manager and unable to see how BIM benefit them”

(C4.07), “reluctant and inexperienced to use BIM and happy to continue using

traditional CAD” (C4.09), “trade contractors have to make extra efforts to reconfigure

or reformat data ” (C4.21), “training cost and high learning curve (initial productivity

loss) to use BIM” (C4.08), “trade contractors only have 2D drawings or incomplete

3D model shared from designers or general contractor” (C4.20), and “trade

contractors use CAD and cannot integrate BIM models from general contractor into

Page 342: building information modeling–based process transformation to improve productivity in the

322

their site models” (C4.22) were the top 10 leading causes. Thus, the first research

objective was fulfilled.

10.1.2 A fuzzy BIMIR evaluation model for building projects

BIMIR was negatively related to a NVAI continuum, which was measured by the

frequency of occurrence of the 38 critical NVA activities in the seven project phases.

The second objective of this study was to develop a BIMIR model to evaluate the

BIMIR statuses of building projects. A building project consists of many phases, and

each of them involves a number of activities that are produced by various major

stakeholders. The phases served as the evaluation criteria, and the 38 critical NVA

activities as evaluation attributes (sub-criteria). To enable BIM implementers to easily

understand these attributes and assess their BIMIR statuses by considering their

current BIM implementation practices, the NVA activities were originally identified

from the literature review and the pilot study.

Using equations 4.3 to 4.6 and the level of agreement mean scores of the critical

NVA activities, the weights of the seven project phases and the 38 critical NVA

activities were calculated. To deal with the problems involving vague, uncertain, and

subjective judgments in the implementation of the critical NVA activities, the FSE

approach was adopted in this model. Following equations 4.7 to 4.12 for computing

the NVAI score and Table 4.5 for the translation mechanism, the BIMIR status of any

building project can be computed. Thus, a fuzzy BIMIR evaluation model has been

developed, achieving the second research objective.

Page 343: building information modeling–based process transformation to improve productivity in the

323

10.1.3 BIMIR statuses and productivity performance of building projects

in Singapore

The third research objective was to investigate the BIMIR statuses and productivity

performance of building projects in Singapore. The data related to the frequency of

occurrence of the 38 critical NVA activities were collected from 73 building projects.

By inputting the data into the fuzzy BIMIR evaluation model, the NVAI scores of the

projects were calculated, ranging from 0.323 to 0.905, and the BIMIR statuses of

these projects were obtained. Among the 73 surveyed projects, 15 (20.55%) were in

BIMIR S1 where no BIM implementation activities were carried out, 47 (64.38%)

were in BIMIR S2 (lonely BIM implementation), the remaining 11 (15.07%) were in

BIMIR S3 (collaborative BIM implementation), and none were regarded as BIMIR

S4 (full BIM implementation). Although some projects were assessed to be in BIMIR

S3, the average BIMIR status of the surveyed building projects in Singapore was S2

(lonely BIM implementation), implying that their overall BIMIR status was low.

Thus, Hypothesis 2 that “the BIMIR statuses of building projects in Singapore are

low” was accepted.

The WC mean scores of the 13 wastes were calculated, ranging from 2.81 to 3.60.

Among which, “reworks/abortive works” (W03), “RFIs” (W02), “design deficiencies

(errors, omissions, additions)” (W12), “defects” (W01), and “waiting/idle time”

(W04) were the top five critical wastes. The WC mean scores ranged from 2.80 to

3.89 in the BIMIR S1 group of building projects, from 2.70 to 3.69 in the BIMIR S2

group of projects, and from 2.83 to 3.52 in the S3 group of projects. These values

decreased as BIMIR status increased. Therefore, BIM implementation could reduce

wastes and enhance productivity performance in the Singapore construction industry.

In addition, the post hoc test of the one-way ANOVA revealed that the mean scores

of seven wastes (W03, W05, W06, W07, W09, W10, and W11) differed between

Page 344: building information modeling–based process transformation to improve productivity in the

324

different BIMIR status groups of projects. Thus, Hypothesis 3 that “the higher the

BIMIR status, the lower the criticality of the wastes and the higher the productivity

performance” was supported, and the third research objective of this study was

achieved.

10.1.4 A proposed organizational change framework

The fourth research objective was to propose an organizational change framework for

building projects that plan to implement BIM. Among theories of organizational

change, Leavitt’s diamond theory and the MIT90s framework were selected because

of their constant evolvement to design better strategies for promoting new

technologies. This echoes with the Singapore government’s encouragement to

promote BIM in the local construction industry. BIM has been emerging as a new

technology or technological process, and its implementation has been proven to be an

organizational transformation (Azhar et al., 2014). Based on Leavitt’s diamond

model, the MIT90s framework, and their derivatives, this study first proposed an

organizational change framework which would be suitable for the building project

context using BIM. The proposed organizational change framework consists of four

components (people, process, technology, and external environment), which can be

further divided into 11 factors and 29 change attributes. In each project organization,

these attributes are essential to the journey of technology adoption and process

transformation. Thus, the fourth objective was fulfilled.

10.1.5 Critical factors hindering and driving change towards full BIM

implementation

Process transformation towards higher levels of BIMIR status can be influenced by

the interactions between the hindrances for and drivers to BIM implementation. The

Page 345: building information modeling–based process transformation to improve productivity in the

325

fifth research objective was to examine the critical factors hindering and driving the

construction industry to change towards full BIM implementation, and to analyze

them with the proposed organizational change framework. A total of 47 hindrances

and 32 drivers were identified from the comprehensive literature review. The data

related to the significance of these factors in affecting the change towards full BIM

implementation were collected in Survey II.

The analysis results suggested that 44 out of the 47 hindrances significantly hindered

BIM implementation in building projects in Singapore. Among which, “need for all

key stakeholders to be on board to exchange information” (H12), “contractual

relationships among stakeholders and need for new frameworks” (H27), “lack of

skilled employees and need for training them on BIM and OSM” (H04), “industry’s

conservativeness, fear of the unknown, and resistance to change comfortable

routines” (H05), “entrenchment in 2D drafting and unfamiliarity to use BIM” (H07),

“costly investment in BIM hardware and software solutions” (H42), “traditional

contracts protect individualism rather than best-for-project thinking” (H28),

“executives failing to recognize the value of BIM-based processes and needing

training” (H01), “technical needs for multiuser model access in multi-discipline

integration” (H46), and “firms’ unwillingness to invest in training due to initial cost

and productivity loss” (H31) obtained the top 10 significant influence. In contrast,

“few benefits from BIM go to designers while most to contractors and owners”

(H17), “lack of legal support from authorities” (H18), and “owners’ desire for

particular structures or finishes when considering OSM” (H25) did not have

statistically significant influence on BIM implementation. The three factors tended to

be either drastic or bias the reality and were excluded in the subsequent discussion.

In terms of the drivers for BIM implementation, the analysis results implied that 31

out of the 32 factors significantly drove BIM implementation in the Singapore

Page 346: building information modeling–based process transformation to improve productivity in the

326

construction industry. Particularly, “BIM vision and leadership from the

management” (D01), “design coordination between disciplines through clash

detection and resolution” (D17), “owner’s requirement and leadership to adopt BIM”

(D05), “training on new skillsets and new ways of working” (D04), “gaining

competitive advantages from full BIM use” (D07), “regulatory agencies’ early

participation to BIM use” (D06), “3D visualization enabling design communication”

(D15), “producing models and drawings for construction and fabrication” (D20),

“stakeholders seeing the value of adopting their own part of BIM” (D03), and

“government support such as subsidizing training, software, and consultancy costs”

(D09) were the top 10 influential factors. Meanwhile, “enabling subcontractors to use

lower-skilled labor on site” (D10) was not perceived as a significant driver for BIM

implementation. The exclusion of this driver was supported by the post-survey

interviewees that skilled workers were still needed in the local industry to ensure

good quality and workmanship.

The critical hindrances and drivers were compared between the upfront stakeholders

and the downstream stakeholders. The independent-samples t-test results indicated

that “field staff dislike BIM coordination meetings looking at a screen” (H15), “lack

of consultants’ feedbacks on subcontractors’ model coordination” (H16), and “lack of

effective data interoperability between project stakeholders” (H29) were significantly

different between the two groups of surveyed organizations, while none of the critical

drivers were statistically distinct between the two groups of stakeholders.

As mentioned earlier, BIM implementation could be regarded as an organizational

change in the building project context. A building project team can be representative

of a cross-enterprise environment and a large project organization in which the

project participants work collaboratively to achieve common project goals within

constraints (Verdecho et al., 2012). Hence, the 44 CHCs and 31 CDCs were

Page 347: building information modeling–based process transformation to improve productivity in the

327

interpreted with the 29 attributes of the proposed organizational change framework

(see Figures 7.1 to 7.4). Thus, Hypothesis 4 that “moving towards higher levels of

BIM implementation is hindered by a set of critical hindrances which can be

interpreted from the organizational change perspective” and Hypothesis 5 that

“moving towards higher levels of BIM implementation is driven by a set of critical

drivers which can be interpreted from the organizational change perspective” were

partially supported. Furthermore, the managerial strategies in terms of people (eight),

process (10), technology (five), and external environment (two) aspects were also

tailored (see Section 7.3.5). Therefore, the fifth objective that “examine the critical

factors driving and hindering the local construction industry to change towards full

BIM implementation” was achieved.

10.1.6 A BBPT model

The last objective of this study was to develop a BBPT model for building projects.

This model can evaluate the BIMIR statuses of building projects, propose appropriate

managerial strategies to improve their BIMIR statuses, and determine the priority of

implementing these strategies. The BBPT model was developed to generalize the

above findings to any building projects in the construction industry, and consisted of

two part-models: a BIMIR evaluation model and a BIMIR movement model (see

Figure 9.1). With a project team’s ratings on the frequency of occurrence of the

critical NVA activities in the project, the evaluation model can compute its BIMIR

status and provide leading causes to these NVA activities. In addition, with the

ratings on the CHCs and CDCs in this project, the improvement model can tailor

managerial strategies on people, process, technology, and external environment

aspects for the project organization to move towards higher BIMIR statuses, and

determine the priorities of these strategies to be implemented with resources. The 33

projects that were involved in both surveys were analyzed as the example to illustrate

Page 348: building information modeling–based process transformation to improve productivity in the

328

the BIMIR movement model. Finally, the validation results from six interviews

implied that the discrepancies between the experts’ estimations and the calculated

values were accepted, and that the managerial strategies and their priorities provided

in the BBPT model were useful. Hence, the sixth research objective was also fulfilled.

Based on the above summary, it could be concluded that the research aim of this

study, “develop a BBPT model to assist project teams in moving towards higher

levels of BIM implementation, reducing wastes, and thus enhancing productivity

performance in building projects in Singapore”, was achieved.

10.2 Contributions

10.2.1 Contribution to scholarship

The study significantly contributes to the global body of knowledge related to BIM

implementation. The first contribution of this study is a proposed four-stage BIMIR

status in the building project context, ranging from no BIM implementation to full

BIM implementation (see Section 4.3). The implementation readiness is described by

the psychological willingness or the state of being prepared for performing BIM

implementation activities. This classification covers the stages in the existing BIM

implementation phases or maturity classification (Lee, 2007a; Succar, 2009;

Khosrowshahi and Arayici, 2012).

The second contribution is a proposed fuzzy BIMIR evaluation model for building

projects. Different from the existing BIM readiness model that used the ANN method

and focused on the architectural consultancy firms in Taiwan (Juan et al., 2017), the

proposed model in this study adopts the FSE approach which can solve the problems

related to vague, uncertain, and subjective judgments in the implementation of the

critical NVA activities. The proposed model evaluates the BIMIR statuses of building

Page 349: building information modeling–based process transformation to improve productivity in the

329

projects in which all the major stakeholders are involved. The model consists of

seven project phases and 38 critical NVA activities, which have been validated in

Survey I. These evaluation criteria and sub-criteria are more comprehensive than the

existing model in the literature. Using this proposed model, the BIMIR status of any

building project can be assessed.

Thirdly, since little research has been carried out to investigate BIM implementation

in the construction industry as an organizational evolution, this present study is the

first to adapt existing theories of organizational change into the building project

context and propose an organizational change framework for building projects that

plan to implement BIM (see Table 5.3). The four-factor structure was constructed by

adapting the main blocks of Leavitt’s diamond model and the MIT90s framework as

well as their modifications. This adaption is supported with justifications in the

existing literature (Rockart and Scott Morton, 1984; Scott Morton, 1991; Teo and

Heng, 2007; Lyytinen and Newman, 2008; Croteau and Bergeron, 2009; De Haes et

al., 2012; Verdecho et al., 2012; Dahlberg et al., 2016).

Lastly, although a number of studies have investigated the CHCs and CDCs in the

process transformation, few studies have attempted to investigate these factors from

the organizational change perspective. This study interprets the 44 CHCs and 31

CDCs with the proposed organizational change framework, thus expanding the

existing literature related to organizational change and BIM implementation.

10.2.2 Contribution to practice

This study also significantly contributes to the practice. Specifically, 38 critical NVA

activities are identified, which provides a comprehensive picture of the current

industry practices, compared with the full BIM-enabled project delivery methods. To

Page 350: building information modeling–based process transformation to improve productivity in the

330

estimate the impact of these NVA activities on productivity performance, 13 potential

wastes are identified. Among which, seven wastes are widely accepted and used in

the Toyota production system. The critical NVA activities and disruptive wastes help

the construction industry to rethink its current work processes and ensure that all

practitioners are aware of the opportunities, roles, and responsibilities associated with

incorporating BIM implementation into the current project delivery workflow

(Anumba et al., 2010).

Based on the interpretation of the CHCs and CDCs with the proposed organizational

change framework, a set of specific managerial strategies are identified to diminish

the negative influence of the CHCs and strengthen the positive influence of the CDCs

on people, process, technology, and external environment aspects.

The BBPT model developed in this study can help any building project evaluate its

BIMIR status in the planning stage and move towards a higher BIMIR status with

support from the proposed managerial strategies. As part of this model, the fuzzy

BIMIR evaluation model allows the project team to obtain a clear view of the status

quo in the building project. When they use the model, they need to rethink about the

typical work practices carried out by the team members. This thinking process is

likely to help determine the key parties that need to implement managerial strategies

at the later stages of this project. More importantly, with the ratings of the CHCs and

CDCs in the project, the BIMIR movement model can purposely propose appropriate

strategies for the project leadership team. The team should consider its project

context, such as project goal, the team members’ goals and collaboration skills, and

desired risk allocations (Barley, 1986; Anumba et al., 2010). Based on the proposed

four-level priorities rules (see Table 9.9), the resources allocated for implementing

these strategies can be prioritized efficiently. It is likely that the critical NVA

Page 351: building information modeling–based process transformation to improve productivity in the

331

activities and wastes in the design, construction, and operations and maintenance

processes would be removed, leading to a more efficient project delivery.

The process transformation improves productivity although it is not directly measured

with exact figures. In the context of mandatory BIM submissions in Singapore, most

building projects must implement BIM. For example, if lonely BIM is implemented

in a project, BIM work processes tend not to be properly planned and implemented

due to the lack of collaboration. This may lead to disordered construction process on

site and require extra time or manpower to deal with the process, significantly

affecting productivity. In contrast, keeping this in mind, the local industry players

may start to prepare for transforming their delivery processes to reduce improperly

implemented BIM work activities. If the prioritized strategies are well planned from

project beginning and implemented in the later phases, this project’s BIMIR status

increases from BIMIR S2 to BIMIR S3 or BIMIR S4. With reference to the BBPT

model, because every strategy is collectively undertaken by the project team or

properly assigned to the stakeholder(s) who can best undertake it, the stakeholder(s)

involved in this process will no longer produce the critical NVA activities that would

inevitably be created in the lonely BIM-based delivery. The reduction of the critical

NVA activities contributes to fewer wastes and smooth construction process on site.

So, fewer man-days (fewer employees and/or less time) are needed to complete the

project. Therefore, according to the VAP method, increasing BIMIR status in the

project planning and execution stage will indeed improve productivity performance.

In addition, a case study was conducted in a large construction and development firm

based in Singapore. This reveals how changes were implemented when implementing

BIM in Project A of a higher BIMIR status, compared with its typical ongoing Project

B of a lower BIMIR status. Since Project A was selected as a sample project to

promote BIM in Singapore. The findings from the case study can be generalized. The

Page 352: building information modeling–based process transformation to improve productivity in the

332

implication drawn from this case study allows the local BIM implementers to

understand the dynamics of process transformation when acquiring BIM technology

and work processes in their projects.

Finally, the governments that are still adopting a wait-and-see attitude should have

the clear understanding that without their leadership, encouragement, mandates, and

support, the construction industry may still be stuck to the unproductive way in the

changing market (Silva et al., 2016). Those having yet made efforts in driving BIM

implementation can refer to the managerial implications drawn from this study to

efficiently provide their support on purpose, such as conditionally mandating BIM

uses in their building projects, establishing national data exchange standards for

multidisciplinary model integration, providing technical support such as by defraying

a proportion of capital investments in consultancy, training, software purchase,

subscription, and updating, and promoting successful cases of BIM implementation.

10.3 Limitations

While this study has achieved the research objectives, there are limitations to the

conclusions. Firstly, the critical NVA activities and the factors hindering and driving

to change towards full BIM implementation were identified from the literature

review, which may not be exhaustive enough or continue to hold true as time passes.

Secondly, some wastes such as RFIs and workers’ waiting time may be interrelated,

and therefore it is not possible to achieve complete accuracy when estimating time

savings. Nevertheless, this study did not directly measure productivity.

Thirdly, among the 33 building projects that were involved in both surveys, the

numbers of projects distributed in BIMIR S1 (eight), BIMIR S2 (20), and BIMIR S3

Page 353: building information modeling–based process transformation to improve productivity in the

333

(five) were not large. However, the situation was that most surveyed projects were

regarded to be in BIMIR S2 (see Table 7.6). Besides, this study mainly used these

projects to exemplify the BIMIR movement part of the BBPT model, rather than to

predict the managerial strategies for the whole industry. When it comes to a particular

project, the BBPT model would look into the CHCs (see Table 7.19) and CDCs (see

Table 7.21), and the four priority rules remain unchanged. Therefore, this limitation is

overcome.

Finally, the data of the two surveys and one case study were collected and analyzed in

the Singapore context, which may cause geographical limitation when interpreting

and generalizing the main findings of this study. Nonetheless, the theoretical and

practical implications drawn from this study are not limited to the building projects in

Singapore. Although the BBPT model was proposed for building projects in

Singapore in response to the mandatory BIM e-submissions policy and the local

government’s encouragement for project-wide BIM collaboration. Overseas

practitioners may also use this model. This is because: (1) like the public sector

taking the lead to adopt BIM in Singapore for enhanced productivity, BIM adoption

in publicly funded construction and building projects in the construction industry

overseas is also commonly encouraged, specified, or mandated (Smith, 2014;

McAuley et al., 2017); (2) the theoretical rational behind the CHCs and CDCs can be

used globally to interpret the hindrances to and drivers for change towards full BIM

implementation in their projects; and (3) overseas practitioners can use BIM

implementation fundamentals and follow the method used in this study, with minor

adjustments, to prepare their customized lists of key BIM work practices and critical

NVA activities, potential wastes, hindrances, drivers, and associated managerial

strategies in their projects according to their specific project characteristics and

political contexts.

Page 354: building information modeling–based process transformation to improve productivity in the

334

10.4 Recommendations for Future Research

This study forms the foundation for future research on promoting BIM implantation

in the construction industry. It should be clarified that this study had already been

moved forward and substantially completed before the CITM was issued by the BCA

in October 2017. The CITM would not damage the contributions of this study. This is

because: (1) although the DfMA approach was promoted in both this study and the

CITM, the IPD and VDC approaches were exclusively highlighted in this study; (2) it

is expected that the Singapore construction industry needs to take years before the

DfMA approach or BIM at large are widely adopted in practice; and (3) BIM

implementation is the engine of the adoption of IDD in the CITM (BCA, 2017a).

Thus, it is believed that this study is novel and practically significant. Instead, the

main findings of this study can serve to support the fulfillment of the CITM in

Singapore.

Future work needs to be done in the following areas. Firstly, this study found that

executive vision and sponsorship significantly drove BIM implementation. The

management staff can only be convinced by concrete benefits. Thus, apart from the

reduced wastes and enhanced productivity, future work needs to be done to develop a

set of metrics that can measure project performance in all key aspects (time, cost,

quality, environment, client satisfaction, and so on). These metrics should be able to

demonstrate more tangible BIM implementation benefits to the management staff.

For example, SMEs and foreign firms based in Singapore may consider first costs as

the most critical and sometimes, the only factor in take-up of BIM (Kunz and Fischer,

2012). Practitioners need clear guidance for BIM implementation in practice because

they tend not to be knowledgeable and experienced about higher levels of BIM

implementation (Khosrowshahi and Arayici, 2012; Juan et al., 2017).

Page 355: building information modeling–based process transformation to improve productivity in the

335

Secondly, future research should investigate interaction mechanisms among the 44

CHCs and 31 CDCs. The theoretical rational behind the mechanisms would be found

in the theories of organizational change as well. Using the structural equation

modeling technique, the cause-effect relationships among these factors would be

disclosed, which may further help project leadership teams to understand fewer and

essential factors.

Thirdly, implementing the proposed managerial strategies to move towards higher

levels of BIMIR status requires the project leadership teams to tailor clear action

plans. Thus, future work is also needed to identify specific actionable change

activities.

Last but not least, future research can develop a benchmarking system for BIMIR

status. A database would be established, which contains the BIMIR statuses of a large

number of building projects and AEC services providers participating in these

projects in Singapore. The benchmarking system would help users to make better

informed decisions, such as allowing developers or principal design consultants to

select qualified bidders to build qualified BIM teams.

Page 356: building information modeling–based process transformation to improve productivity in the

336

Bibliography

Abbasnejad, B., and Moud, H. I. (2013). BIM and basic challenges associated with its

definitions, interpretations and expectations. International Journal of

Engineering Research and Applications (IJERA), 3(2), 287–294.

Abdel-Razek, R. H., Abd-Elshakour, H., and Abdel-Hamid, M. (2007). Labor

productivity: benchmarking and variability in Egyptian projects. International

Journal of Project Management, 25(2), 189–197.

Abowitz, D. A., and Toole, T. M. (2010). Mixed method research: fundamental issues

of design, validity, and reliability in construction research. Journal of

Construction Engineering and Management, 136(1), 108–116.

Agbulos, A., and AbouRizk, S. M. (2003). An application of lean concepts and

simulation for drainage operations maintenance crews. In Proceedings of the

2003 Winter Simulation Conference (pp.1534–1540). New Orleans, LA.

AGC. (2006). The contractors’ guide to BIM. The Associated General Contractors of

America.

AIA and AIACC. (2007). Integrated project delivery: a guide. Sacramento (CA):

American Institute of Architects.

AIA and AIACC. (2009). Experiences in collaboration: on the path to IPD.

Sacramento (CA): American Institute of Architects.

AIACC. (2006). Project delivery frequently asked questions. Sacramento (CA):

American Institute of Architects, California Council.

AIACC. (2007). Integrated project delivery: a working definition. Sacramento (CA):

American Institute of Architects, California Council.

AIACC. (2014). Integrated project delivery: an updated working definition.

Sacramento (CA): American Institute of Architects, California Council.

Alarcon, L. (1997). Lean construction. Rotterdam: A.A. Balkema.

Albaum, G. (1997). The Likert scale revisited: an alternative version. Journal of the

Market Research Society, 39(2), 331–348

Allan, G. B. (1976). Ordinal-scaled variables and multivariate analysis: comment on

Hawkes. American Journal of Sociology, 1498–1500

Allen, I. E., and Seaman, C. A. (2007). Likert scales and data analyses. Quality

Progress, 40(7), 64–65.

Alshaher, A. A. F. (2013). The mckinsey 7S model framework for e-learning system

readiness assessment. International Journal of Advances in Engineering &

Technology, 6(5), 1948–1966.

Alshawi, M. (2007). Rethinking IT in construction and engineering: organizational

readiness. London and New York: Taylor and Francis.

Page 357: building information modeling–based process transformation to improve productivity in the

337

Al-Sudairi, A. A. (2007). Evaluating the effect of construction process characteristics

to the applicability of lean principles. Construction Innovation: Information,

Process, Management, 7(1), 99–121.

Alwi, S., Hampson, K., and Mohamed, S. (2002). Non value-adding activities: a

comparative study of Indonesian and Australian construction projects. In

Proceedings of the 10th Annual Conference of the International Group for Lean

Construction (pp. 627–638). Gramado, Brazil.

Anumba, C., Dubler, C., Goodman, S., Kasprzak, C., Kreider, R., Messner, J., Saluja,

C., and Zikic, N. (2010). BIM project execution planning guide – version 2.0.

Computer Integrated Construction Research Program, Pennsylvania State

University, University Park, PA.

Arain, F. M. (2005). Knowledge-based decision support system (KBDSS) for

management of variation orders for school building projects in Singapore.

Unpublished doctoral thesis, Department of Building, National University of

Singapore.

Arain, F. M., and Low, S. P. (2006). Knowledge-based decision support system for

management of variation orders for institutional building projects. Automation in

Construction, 15(3), 272–291.

Aranda-Mena, G., Crawford, J., Chevez, A., and Froese, T. (2009). Building

information modelling demystified: does it make business sense to adopt BIM?.

International Journal of Managing Projects in Business, 2(3), 419–434.

Arayici, Y., Coates, P., Koskela, L., Kagioglou, M., Usher, C., and O’Reilly, K.

(2011). BIM adoption and implementation for architectural practices. Structural

Survey, 29(1), 7–25.

Ashurst, C., Freer, A., Ekdahl, J., and Gibbons, C. (2012). Exploring IT-enabled

innovation: a new paradigm?. International Journal of Information Management,

32(4), 326–336.

Austin, M. J., and Ciaassen, J. (2008). Impact of organizational change on

organizational culture. Journal of Evidence-Based Social Work, 5(1), 321–359.

Autodesk. (2008). Improving building industry results through integrated project

delivery and building information modeling. Autodesk Whitepaper, San Rafael

(CA): Autodesk, Inc.

Autodesk. (2012). A framework for implementing a BIM business transformation.

Project Transformer, San Rafael (CA): Autodesk, Inc.

Azhar, N., Kang, Y., and Ahmad, I. U. (2014). Factors influencing integrated project

delivery in publicly owned construction projects: an information modelling

perspective. Procedia Engineering, 77, 213–221.

Azhar, S. (2011). Building information modeling (BIM): trends, benefits, risks, and

challenges for the AEC industry. Leadership and Management in Engineering,

11(3), 241–252.

Page 358: building information modeling–based process transformation to improve productivity in the

338

Barley, S. R. (1986). Technology as an occasion for structuring: evidence from

observations of CT scanners and the social order of radiology departments.

Administrative Science Quarterly, 31, 78–108.

Barlish, K., and Sullivan, K. (2012). How to measure the benefits of BIM - a case

study approach. Automation in Construction, 24, 149–159.

BCA and MOM. (2014). Raising the quality and productivity of the construction

workforce to boost economic competitiveness. Singapore: Building and

Construction Authority and Ministry of Manpower.

BCA and SPH. (2015). Singapore construction productivity week showcases

advanced technologies to improve collaboration in the built environment sector.

Retrieved 7 Oct 2015 from the World Wide Web:

http://www.sph.com.sg/media_releases/2592.

BCA. (2011a). Construction productivity roadmap. Singapore: Building and

Construction Authority.

BCA. (2011b). International experts impressed with BCA’s plans to transform

Singapore’s building and construction sector. Retrieved 12 May, 2015 from the

World Wide Web: http://www.bca.gov.sg/Newsroom/pr02112011_BI.html.

BCA. (2011c). Overview on construction productivity roadmap. Singapore: Building

and Construction Authority.

BCA. (2013a). Defining value added productivity. Retrieved 12 May, 2015 from the

World Wide Web: http://www.bca.gov.sg/VAP/vap.html.

BCA. (2013b). Singapore BIM guide version 2. Singapore: Building and Construction

Authority.

BCA. (2014a). BCA to unveil second construction productivity roadmap next year.

Singapore: Building and Construction Authority.

BCA. (2014b). BCA-URA joint release: new regulations to improve productivity in

the construction sector. Retrieved 7 Jul, 2015 from the World Wide Web:

http://www.bca.gov.sg/Newsroom/pr06112014_BCA.html.

BCA. (2014c). Built environment sector calls for more local talent. Retrieved 7 Jul,

2015 from the World Wide Web:

http://www.bca.gov.sg/Newsroom/pr22052014_BCA.html.

BCA. (2015a). About 7,000 firms to benefit from S$450 million - boost for

construction productivity. Singapore: Building and Construction Authority.

BCA. (2015b). BIM particular conditions version 2. Singapore: Building and

Construction Authority.

BCA. (2015c). Raising the quality and productivity of the construction workforce.

Retrieved 7 May, 2015 from the World Wide Web:

http://www.bca.gov.sg/manpower/raisequalityofworkforce.html.

BCA. (2015d). Technology adoption: BIM fund (enhanced). Retrieved 7 May, 2015

from the World Wide Web: http://www.bca.gov.sg/BIM/bimfund.html.

Page 359: building information modeling–based process transformation to improve productivity in the

339

BCA. (2015e). The second construction productivity roadmap. Build Smart,

Singapore: Building and Construction Authority.

BCA. (2016). Reaching new milestones with design for manufacturing and assembly.

Build Smart, Singapore: Building and Construction Authority.

BCA. (2017a). Construction ITM to pave the way for digital integration and better

jobs. Retrieved 15 Jan, 2018 from the World Wide Web:

https://www.bca.gov.sg/newsroom/others/PR_ConstructionITM_231017.pdf.

BCA. (2017b). Contractors registration system - tendering limits. Retrieved 24 Jan,

2018 from the World Wide Web:

https://www.bca.gov.sg/ContractorsRegistry/contractors_tendering_limits.html.

Becker, F. (2004). Offices at work: uncommon workspace strategies that add value

and improve performance. San Francisco (CA): Jossey-Bass.

Belay, A. M. (2009). Design for manufacturability and concurrent engineering for

product development. World Academy of Science, Engineering and Technology,

25, 240–246.

Bernstein, H. M., Jones, S. A., and Russo, M. A. (2012). The business value of BIM

in North America: Multi-year trend analysis and user rating (2007–2012).

Bedford (MA): McGraw-Hill Construction.

Bernstein, H. M., Jones, S. A., and Gudgel, J. E. (2010). The business value of BIM in

Europe: getting building information modeling to the bottom line in the United

Kingdom, France and Germany. Bedford (MA): McGraw-Hill Construction.

Bernstein, P. G., and Pittman, J. H. (2004). Barriers to the adoption of building

information modelling in the building industry. Autodesk Building Solutions, San

Rafael (CA): Autodesk, Inc.

Bikson, T. K., and Eveland, J. D. (1990). The interplay of work group structures and

computer support. In J. Galegher, R. Kraut, and C. Egido (Eds.), Intellectual

Teamwork: Social and Technological Foundations of Cooperative Work (pp.245–

289). Hillsdale (NJ): Lawrence Erlbaum.

Binder, A. (1984). Restrictions on statistics imposed by method of measurement:

some reality, much mythology. Journal of Criminal Justice, 12(5), 467–481.

Blismas, N., and Wakefield, R. (2009). Drivers, constraints and the future of offsite

manufacture in Australia. Construction Innovation, 9(1), 72–83.

Blismas, N., Pasquire, C., and Gibb, A. (2006). Benefit evaluation for off‐site

production in construction. Construction Management and Economics, 24(2),

121–130.

Bobbitt Jr, H. R., and Behling, O. C. (1981). Organizational behavior: a review of the

literature. The Journal of Higher Education, 5, 29–44.

Chan, D. W. M., and Kumaraswamy, M. M. (1996). An evaluation of construction

time performance in the building industry. Building and Environment, 31(6),

569–578.

Page 360: building information modeling–based process transformation to improve productivity in the

340

Chandler, A. D. (1962). Strategic and structure: chapters in the history of American

industrial enterprise. Cambridge (MA): MIT Press.

Chandler, D. (2015). Modern methods of construction. Retrieved 7 Oct 2015 from the

World Wide Web: https://sourceable.net/modern-methods-of-construction/#.

Chang, S. I., Peng, T. C., Hung, Y. C., Chang, I. C., and Hung, W. H. (2009). Critical

success factors of mobile commerce adoption: a study based on the system life

cycle and diamond model. In Proceedings of 2009 Eighth International

Conference on Mobile Business (pp.126–130). IEEE.

Chelson, D. E. (2010). The effects of building information modeling on construction

site productivity. Doctoral thesis, Department of Civil Engineering, University of

Maryland, College Park, MD.

Chen, S. J., and Hwang, C. L. (1992). Fuzzy multiple attribute decision making

methods. In: Fuzzy Multiple Attribute Decision Making. Lecture Notes in

Economics and Mathematical Systems, 375. Springer, Berlin, Heidelberg.

Cheng, J. C., and Lu, Q. (2015). A review of the efforts and roles of the public sector

for BIM adoption worldwide. Journal of Information Technology in

Construction, 20, 442–478.

Cheng, T. F. (2013). Singapore BIM roadmap. Singapore: Building and Construction

Authority.

Cho, S., and Fischer, M. (2010). Real-time supply chain management using virtual

design and construction and lean. In Proceedings of the 18th Annual Conference

of the International Group for Lean Construction (pp.212–221). Haifa, Israel.

Chou, S. Y., and Chang, Y. H. (2008). A decision support system for supplier

selection based on a strategy-aligned fuzzy SMART approach. Expert Systems

with Applications, 34(4), 2241–2253.

Chua, D. K., and Yeoh, J. K. (2015). Understanding the science of virtual design and

construction: what it takes to go beyond building information modelling. In W. J.

O’Brien, S. Ponticelli (Eds.), Proceedings of the 2015 ASCE International

Workshop on Computing in Civil Engineering (pp.692–699). Austin, TX.

Cohen, J. (2010). Integrated project delivery: case studies. Sacramento (CA):

American Institute of Architects, California Council.

Cox, E. (1998). The fuzzy systems handbook (2nd ed.). Boston (MA): AP

Professional.

Croteau, A. M., and Bergeron, F. (2009). Interorganizational governance of

information technology. In: Proceedings of the 42nd Hawaii International

Conference on System Sciences. Washington, DC: IEEE Computer Society.

Dahlberg T. (2016). The creation of inter-organisational IT governance for social

welfare and healthcare IT-lessons from a case study. International Journal of

Networking and Virtual Organisations, 16(1), 38–71.

Dahlberg, T, Hokkanen, P, and Newman, M. (2016). How Business strategy and

technology impact the role and the tasks of CIOs: an evolutionary model.

Page 361: building information modeling–based process transformation to improve productivity in the

341

International Journal of IT/Business Alignment and Governance (IJITBAG), 7(1),

1–19.

Dai, J., and Goodrum, P. M. (2012). Generational differences on craft workers’

perceptions of the factors affecting labour productivity. Canadian Journal of

Civil Engineering, 39(9), 1018–1026.

Dai, J., Goodrum, P. M., and Maloney, W. F. (2009). Construction craft workers’

perceptions of the factors affecting their productivity. Journal of Construction

Engineering and Management, 135(3), 217–226.

Das, M., Cheng, J. C., and Shiv Kumar, S. (2014). BIMCloud: a distributed cloud-

based social BIM framework for project collaboration. In: Computing in Civil

and Building Engineering (2014) (pp. 41–48).

Davis, F. D. (1989). Perceived usefulness, perceived ease of use, and user acceptance

of information technology. MIS Quarterly: Management Information Systems,

13(3), 319–339.

Davis, G. B., Lee, A. S., Nickles, K. R., Chatterjee, S., Hartung, R., and Wu, Y.

(1992). Diagnosis of an information system failure: a framework and interpretive

process. Information & Management, 23(5), 293–318.

De Haes, S., Van Grembergen, W., Gemke, D., and Thorp, J. (2012). Inter-

organizational governance of information technology: learning from a global

multi-business-unit environment. International Journal of IT/Business Alignment

and Governance, 3(1), 27–46.

Dolage, D. A. R., and Chan, P. (2013). Productivity in construction-a critical review

of research. Engineer: Journal of the Institution of Engineers, Sri Lanka, 46(4),

31–42.

Doloi, H. (2008). Application of AHP in improving construction productivity from a

management perspective. Construction Management and Economics, 26(8), 841–

854.

Driankov, D., Hellendoorn, H., and Reinfrank, M. (1996). An introduction to fuzzy

control. New York (NY): Springer.

Dunlop, P., and Smith, S. D. (2004). Planning, estimation and productivity in the lean

concrete pour. Engineering, Construction and Architectural Management, 11(1),

55–64.

Eastman, C., Teicholz, P., Sacks, R., and Liston, K. (2011). BIM handbook: a guide

to building information modeling for owners, managers, designers, engineers and

contractors (2nd ed.). New Jersey: John Wiley & Sons.

Ekanayake, L. L., and Ofori, G. (2004). Building waste assessment score: design-

based tool. Building and Environment, 39(7), 851–861.

El Asmar, M., Hanna, A. S., and Loh, W. Y. (2013). Quantifying performance for the

integrated project delivery system as compared to established delivery systems.

Journal of Construction Engineering and Management, 139(11), 04013012.

Page 362: building information modeling–based process transformation to improve productivity in the

342

Enegbuma, W. I., Aliagha, U. G., and Ali, K. N. (2014). Measurement of theoretical

relationships in Building Information Modelling adoption in Malaysia. In

Proceedings of the 31st International Symposium on Automation and Robotics in

Construction and Mining (pp.1000–1008). Sydney, Australia.

ESC. (2010). Report of the Economic Strategies Committee. Singapore: Economic

Strategies Committee.

Fan, S. L., Skibniewski, M. J., and Hung, T. W. (2014). Effects of building

information modeling during construction. Journal of Applied Science and

Engineering, 17(2), 157–166.

Farrar, J. M., AbouRizk, S. M., and Mao, X. (2004). Generic implementation of lean

concepts in simulation models. Lean Construction Journal, 1(1), 1–23.

Fayek, A. R., and Oduba, A. (2005). Predicting industrial construction labor

productivity using fuzzy expert systems. Journal of Construction Engineering

and Management, 131(8), 938–941.

Fayek, A. R., and Sun, Z. (2001). A fuzzy expert system for design performance

prediction and evaluation. Canadian Journal of Civil Engineering, 28(1), 1–25.

Fischer M, Reed D, Khanzode A, and Ashcraft H. (2014). A simple framework for

integrated project delivery. In: B. T. Kalsaas, L. Koskela, T. A. Saurin (Eds),

Proceedings of the 22nd Annual Conference of the International Group for Lean

Construction (pp.1319–1330). Oslo, Norway.

Fischer, M. (2008). Reshaping the life cycle process with virtual design and

construction methods. In P. Brandon and T. Kocatürk (Eds.), Virtual Futures for

Design, Construction and Procurement (104–112). Malden (MA): Blackwell

Publishing Ltd.

Forgues, D., and Lejeune, A. (2015). BIM: in search of the organisational architect.

International Journal of Project Organisation and Management, 7(3), 270–283.

Formoso, C. T., Isatto, E. L., and Hirota, E. H. (1999). Method for waste control in

the building industry. In Proceedings of the 7th Annual Conference of the

International Group for Lean Construction (pp.325–334). University of

California, Berkeley, CA.

Forsberg, A., and Saukkoriipi, L. (2007). Measurement of waste and productivity in

relation to lean thinking. In Proceedings of the 15th Annual Conference of the

International Group for Lean Construction (pp.18–20). East Lansing, MI.

Forsythe, P., Sankaran, S., and Biesenthal, C. (2015). How far can BIM reduce

information asymmetry in the Australian construction context?. Project

Management Journal, 46(3), 75–87.

Fox, S., and Hietanen, J. (2007). Interorganizational use of building information

models: potential for automational, informational and transformational effects.

Construction Management and Economics, 25(3), 289–296.

Gann, D. M. (1996). Construction as a manufacturing process? similarities and

differences between industrialized housing and car production in Japan.

Construction Management & Economics, 14(5), 437–450.

Page 363: building information modeling–based process transformation to improve productivity in the

343

Gao, J., and Fischer, M. (2006). Case studies on the implementation and impacts of

Virtual Design and Construction (VDC) in Finland. Technical Report, Center for

Integrated Facility Engineering (CIFE), Stanford University, Stanford, CA.

Ghaffarianhoseini, A., Tookey, J., Ghaffarianhoseini, A., Naismith, N., Azhar, S.,

Efimova, O., and Raahemifar, K. (2017). Building Information Modelling (BIM)

uptake: clear benefits, understanding its implementation, risks and challenges.

Renewable and Sustainable Energy Reviews, 75, 1046–1053.

Gibb, A., and Isack, F. (2003). Re-engineering through pre-assembly: client

expectations and drivers. Building Research & Information, 31(2), 146–160.

Gibbs, D. J., Emmitt, S., Lord, W., and Ruikar, K. (2015). BIM and construction

contracts: CPC 2013’s approach. Proceedings of the Institution of Civil

Engineers-Management, Procurement & Law, 168(6), 285–293.

Government Construction Client Group. (2011). A report for the Government

Construction Client Group. Building Information Modelling (BIM) Working

Party Strategy Paper.

Gravetter, F. J., and Forzano, L. B. (2012). Research methods for the behavioral

sciences (4th ed.). Belmont, CA: Cengage Learning.

Gu, N., and London, K. (2010). Understanding and facilitating BIM adoption in the

AEC industry, Automation in Construction, 19(8), 988–999.

Guo, S. (2006). The political economy of Asian transition from communism.

Hampshire (England): Ashgate Publishing Limited.

Hair, J. F., Black, W. C., Babin, B. J., and Anderson, R. E. (2009). Multivariate data

analysis (7th ed.). Upper Saddle River (NY): Prentice Hall.

Hampson, K., and Brandon, P. (2004). Construction 2020: a vision for Australia’s

property and construction industry. Cooperative Research Centre for

Construction Innovation, Brisbane, Australia.

Higgins, C. M., and Goodman, R. M. (1993). Learning fuzzy rule-based neural

networks for control. In Advances in Neural Information Processing Systems

(pp.350–357).

Higgins, J. M. (2005). The eight ‘S’s of successful strategy execution. Journal of

Change Management, 5(1), 3–13.

Hoff, J., and Scheele, C. E. (2014). Theoretical approaches to digital services and

digital democracy: the merits of the contextual new medium theory model. Policy

& Internet, 6(3), 241–267.

Howard, R., and Björk, B. C. (2008). Building information modelling – experts’

views on standardization and industry deployment. Advanced Engineering

Informatics, 22(2), 271–280.

Hwang, B. G., and Soh, C. K. (2013). Trade-level productivity measurement: critical

challenges and solutions. Journal of Construction Engineering and Management,

139(11), 04013013.

Page 364: building information modeling–based process transformation to improve productivity in the

344

Hwang, B. G., Thomas, S. R., Haas, C. T., and Caldas, C. H. (2009). Measuring the

impact of rework on construction cost performance. Journal of Construction

Engineering and Management, 135(3), 187–198.

Hwang, B. G., Zhao, X., and Goh, K. J. (2014). Investigating the client-related

rework in building projects: the case of Singapore. International Journal of

Project Management, 32, 698–708.

Hwang, B. G., Zhu, L., and Tan, J. S. H. (2017). Identifying critical success factors

for green business parks: case study of Singapore. Journal of Management in

Engineering, 33(5), 04017023.

Ibbs, C. W., Kwak, Y. H., Ng, T., and Odabasi, A. M. (2003). Project delivery

systems and project change: quantitative analysis. Journal of Construction

Engineering and Management, 129(4), 382–387.

Imriyas, K. (2009). An expert system for strategic control of accidents and insurers’

risks in building construction projects. Expert Systems with Applications, 36(2),

4021–4034.

Işik, Z., and Aladağ, H. (2017). A fuzzy AHP model to assess sustainable

performance of the construction industry from urban regeneration perspective.

Journal of Civil Engineering and Management, 23(4), 499–509.

Jergeas, G. F., Chishty, S. M., and Leitner, J. M. (2000). Construction productivity: a

survey of industry practices. AACE International Transaction, 6, 1–7.

Juan, Y. K., Lai, W. Y., and Shih, S. G. (2017). Building information modeling

acceptance and readiness assessment in Taiwanese architectural firms. Journal of

Civil Engineering and Management, 23(3), 356–367.

Jung, Y., and Joo, M. (2011). Building information modelling (BIM) framework for

practical implementation. Automation in Construction, 20(2), 126–133.

Kam, C., and Fischer, M. (2004). Capitalizing on early project decision-making

opportunities to improve facility design, construction, and life-cycle

performance—POP, PM4D, and decision dashboard approaches. Automation in

Construction, 13(1), 53–65.

Kaner, I., Sacks, R., Kassian, W., and Quitt, T. (2008). Case studies of BIM adoption

for precast concrete design by mid-sized structural engineering firms. Itcon, 13,

303–323.

Kasimu, M. A., Roslan, B. A., and Fadhlin, B. A. (2012). Knowledge management

models in civil engineering construction firms in Nigeria. Interdisciplinary

Journal of Contemporary Research In Business, 4(6), 936–950.

Kent, D. C., and Becerik-Gerber, B. (2010). Understanding construction industry

experience and attitudes toward integrated project delivery. Journal of

Construction Engineering and Management, 136(8), 815–825.

Keppel, G., and Wickens, T. (2004). Design and analysis: A researcher’s handbook

(4th ed.). Upper Saddle River (NY): Prentice Hall.

Page 365: building information modeling–based process transformation to improve productivity in the

345

Khanzode, A., Fisher, M., and Reed, D. (2007). Challenges and benefits of

implementing virtual design and construction technologies for coordination of

mechanical, electrical, and plumbing systems on large healthcare project. In

Proceedings of 24th CIB W78 Conference (pp.205–212). University of Maribor,

Maribor, Slovenia.

Khemlani, L. (2009). Sutter Medical Center Castro Valley: case study of an IPD

project. Retrieved 29 Sept, 2015 from the World Wide Web:

http://www.aecbytes.com/buildingthefuture/2009/Sutter_IPDCaseStudy.html.

Khosrowshahi, F., and Arayici, Y. (2012). Roadmap for implementation of BIM in

the UK construction industry. Engineering, Construction and Architectural

Management, 19(6), 610–635.

Kiani, I., Sadeghifam, A. N., Ghomi, S. K., and Marsono, A. K. B. (2015). Barriers to

implementation of Building Information Modeling in scheduling and planning

phase in Iran. Australian Journal of Basic and Applied Sciences, 9(5), 91–97.

Kim, J. I., and Fischer, M. (2013). Requirements to enhance the decision-making

process for tunnel construction by Virtual Design and Construction (VDC). In

Proceedings of the 2013 ASCE International Workshop on Computing in Civil

Engineering (pp.323-330). University of Southern California, Los Angeles, CA.

Klir, G. J., and Yuan, B. (1995). Fuzzy sets and fuzzy logic theory and applications.

London: Prentice Hall PTR.

Koskenvesa, A., Koskela, L. J., Tolonen, T., and Sahlsted, S. (2010). Waste and labor

productivity in production planning case Finnish construction industry. In

Proceedings of the 18th Annual Conference of the International Group for Lean

Construction (pp.477–486). Haifa, Israel.

Kuiper, I., and Holzer, D. (2013). Rethinking the contractual context for Building

Information Modelling (BIM) in the Australian built environment industry.

Construction Economics and Building, 13(4), 1–17.

Kunz, J., and Fischer, M. (2012). Virtual design and construction: themes, case

studies and implementation suggestions. CIFE Working Paper No. 97, Center for

Integrated Facility Engineering (CIFE), Stanford University, Stanford, CA.

Kuprenas, J. A., and Mock, C. S. (2009). Collaborative BIM modeling case study—

Process and results. Computing in Civil Engineering, ASCE, Austin, TX.

Kwon, T. H., and Zmud, R. (1987). Unifying the fragmented models of information

systems implementation. In: Boland R, Hirschheim R, editors. Critical Issues in

Information Systems Research (pp.227–251). New York: John Wiley & Sons.

Lam, K. C., Tao, R., and Lam, M. C. K. (2010). A material supplier selection model

for property developers using Fuzzy Principal Component Analysis. Automation

in Construction, 19(5), 608–618.

Lam, S. W. (2014). The Singapore BIM roadmap. Government BIM Symposium

2014. Retrieved 29 Sept, 2015 from the World Wide Web: http://bimsg.org/wp-

content/uploads/2014/10/BIM-SYMPOSIUM_MR-LAM-SIEW-WAH_Oct-13-

v6.pdf.

Page 366: building information modeling–based process transformation to improve productivity in the

346

Leavitt, H. J. (1965). Applied organizational change in industry: structural,

technological and humanistic approaches. In J. March (Ed.), Handbook of

Organizations (pp.1144–1170). Chicago: Rand McNally.

Leavitt, H. J., and Bahrami, H. (1988). Managerial psychology: managing behaviour

in organisations (5th ed.). Chicago: University of Chicago Press.

Lee, A. and Sexton, M. G. (2007). nD modelling: industry uptake considerations.

Construction Innovation, 7(3), 288–302.

Lee, A., Wu, S., Marshall-Ponting, A. J., Aouad, G., Cooper, R., Tah, J. H. M.,

Abbott, C., and Barrett, P. S. (2005). nD modelling roadmap – a vision for nD-

enabled construction, University of Salford, Salford, UK.

Lee, G. (2007a). BIM collaboration methods for improving the efficiency of BIM.

BIM Workshop, Construction Association of Korea, Seoul, South Korea.

Lee, G., Lee, J., and Jones, S. A. (2012). The business value of BIM in South Korea.

Bedford (MA): McGraw-Hill Construction.

Lee, S. (2007b). Application and verification of fuzzy algebraic operators to landslide

susceptibility mapping. Environmental Geology, 52(4), 615–623.

Lee, S. H., Diekmann, J. E., Songer, A. D., and Brown, H. (1999). Identifying waste:

applications of construction process analysis. In: Proceedings of the 7th Annual

Conference of the International Group for Lean Construction (pp.63–72).

Berkeley, CA.

Leong, M. S., and Tilley, P. (2008). A lean strategy to performance measurement –

reducing waste by measuring ‘next’ customer needs. In Proceedings of the 16th

Annual Conference of the International Group for Lean Construction (pp.757–

768). Manchester, UK.

Li, H., Lu, W., and Huang, T. (2009). Rethinking project management and exploring

virtual design and construction as a potential solution. Construction Management

and Economics, 27(4), 363–371.

Liao, L., Teo, E. A. L., and Low, S. P. (2017). A project management framework for

enhanced productivity performance using building information modelling.

Construction Economics and Building, 17(3), 1–26.

Lim, B. T. H., Ling, F. Y. Y., Ibbs, C. W., Raphael, B., and Ofori, G. (2012).

Mathematical models for predicting organizational flexibility of construction

firms in Singapore. Journal of Construction Engineering and Management,

138(3), 361–375.

Lin, C. C., Wang, W. C., and Yu, W. D. (2008). Improving AHP for construction

with an adaptive AHP approach (A3). Automation in Construction, 17(2), 180–

187.

Ling, F. Y. Y., Chan, S. L., Chong, E., and Ee, L. P. (2004). Predicting performance

of design-build and design-bid-build projects. Journal of Construction

Engineering and Management, 130(1), 75–83.

Page 367: building information modeling–based process transformation to improve productivity in the

347

Ling, F. Y. Y., Li, S., Low, S. P., and Ofori, G. (2012). Mathematical models for

predicting Chinese A/E/C firms’ competitiveness. Automation in Construction,

24, 40–51.

Liu, M., and Ling, F. Y. Y. (2005). Modeling a contractor’s markup estimation.

Journal of Construction Engineering and Management, 131(4), 391–399.

Love, P. E. D., Holt, G. D., and Li, H. (2002). Triangulation in construction

management research. Engineering, Construction and Architectural

Management, 9(4), 294–303.

Love, P. E., Zhou, J., Sing, C. P., and Kim, J. T. (2013). Documentation errors in

instrumentation and electrical systems: toward productivity improvement using

system information modeling. Automation in Construction, 35, 448–459.

Low, S. P. (1998). Managing total service quality: a systemic view. Managing

Service Quality, 8(1), 34–45.

Lyytinen, K., and Newman, M. (2008). Explaining information systems change: a

punctuated socio-technical change model. European Journal of Information

Systems, 17(6), 589–613.

Manning, R., and Messner, J. I. (2008). Case studies in BIM implementation for

programming of healthcare facilities. ITcon, 13, 446–457.

Mayor, G., and Trillas, E. (1986). On the representation of some aggregation

functions. In: Proceedings of the 16th ISMVL (pp.110–114). Blacksburg, VA.

McAuley, B., Hore, A., and West, R. (2017). BICP global BIM study–lessons for

Ireland’s BIM programme. Technical Report, School of Surveying and

Construction Management, Dublin Institute of Technology, Dublin, Ireland.

McFarlane, A., and Stehle, J. (2014). DfMA: engineering the future. In: Proceedings

of Council on Tall Buildings and Urban Habitat (CTBUH) 2014 Shanghai

Conference (508–516), Shanghai, China.

McGraw Hill Construction. (2014a). The business value of BIM for construction in

major global markets: how contractors around the world are driving innovation

with Building Information Modelling. McGraw Hill Financial.

McGraw Hill Construction. (2014b). The business value of BIM for owners. McGraw

Hill Construction: SmartMarket Report.

Michel, A., By, R. T, and Burnes, B. (2013). The limitations of dispositional

resistance in relation to organizational change. Management Decision, 51(4),

761–780.

Miettinen, R., and Paavola, S. (2014). Beyond the BIM utopia: approaches to the

development and implementation of building information modeling. Automation

in Construction, 43, 84–91.

Miller, G. A. (1956). The magical number seven, plus or minus two: some limits on

our capacity for processing information. Psychological Review, 63(2), 81–97.

Page 368: building information modeling–based process transformation to improve productivity in the

348

Miller, J. B., Garvin, M. J., Ibbs, C. W., and Mahoney, S. E. (2000). Toward a new

paradigm: simultaneous use of multiple project delivery methods. Journal of

Management in Engineering, 16(3), 58–67.

Mistry, V. (2008). Benchmarking e-learning: trialling the “MIT90s” framework.

Benchmarking: An International Journal, 15(3), 326–340.

Mitchell, G. (2013). Selecting the best theory to implement planned change:

improving the workplace requires staff to be involved and innovations to be

maintained. Nursing Management, 20(1), 32–37.

MOF. (2014). Budget 2014 - opportunities for the future, assurance for our seniors.

Singapore: Ministry of Finance.

MOF. (2015). Budget 2015 - building our future, strengthening social security.

Singapore: Ministry of Finance.

Mohd-Nor, M. F. I., and Grant, M. P. (2014). Building Information Modelling (BIM)

in the Malaysian architecture industry. Wseas Transactions on Environment and

Development, 10, 264–273.

MOM and MND. (1999). Construction 21. Singapore: Ministry Of Manpower and

Ministry of National Development.

MOM. (2014). Statement on labor market developments. Retrieved 13 May, 2015

from the World Wide Web: http://www.mom.gov.sg/newsroom/mom-

statements/2014/15-sep-2014---statement-on-labour-market-developments.

MOM. (2015). Statement on labor market developments. Retrieved 13 May, 2015

from the World Wide Web: http://www.mom.gov.sg/newsroom/mom-

statements/2015/13-mar-2014---statement-on-labour-market-developments.

MOM. (2016). Labor market report 2016. Singapore: Ministry of Manpower.

Nath, T., Attarzadeh, M., and Tiong, R. L. (2016). Precast workflow productivity

measurement through BIM adoption. Proceedings of the Institution of Civil

Engineers-Management, Procurement and Law, 169(5), 208–216.

Nath, T., Attarzadeh, M., Tiong, R. L., Chidambaram, C., and Yu, Z. (2015).

Productivity improvement of precast shop drawings generation through BIM-

based process re-engineering. Automation in Construction, 54, 54–68.

NBIMS. (2007). United States national building information modeling standard

version 1 ‐ part 1: Overview, principles, and methodologies. National Institute of

Building Sciences.

Nieto-Morote, A., and Ruz-Vila, F. (2011). A fuzzy approach to construction project

risk assessment. International Journal of Project Management, 29(2), 220–231.

Nieto-Morote, A., and Ruz-Vila, F. (2012). A fuzzy multi-criteria decision-making

model for construction contractor prequalification. Automation in Construction,

25, 8–19.

Nikakhtar, A., Hosseini, A. A., Wong, K. Y., and Zavichi, A. (2015). Application of

lean construction principles to reduce construction process waste using computer

Page 369: building information modeling–based process transformation to improve productivity in the

349

simulation: a case study. International Journal of Services and Operations

Management, 20(4), 461–480.

Nitithamyong, P., and Skibniewski, M. J. (2003). Critical success/failure factors in

implementation of web-based construction project management systems. In

Proceedings of Construction Research Congress (pp.1–8). ASCE, Reston, VA.

Nunnally, J. C. (1978). Psychometric theory (2nd ed.). New York (NY): McGraw-

Hill.

O’Brien, W. J. (2000). Implementation issues in project web sites: a practitioner’s

viewpoint. Journal of Management in Engineering, 16(3), 34–39.

Ofori, G. (2005). Productivity of the construction industry in Singapore. Retrieved 25

May, 2018 from the World Wide Web:

http://www.bdg.nus.edu.sg/pdf/Constr%20Productivity%20(2005-03).pdf.

Ohno, T. (1988). Toyota production system: beyond large-scale production. Portland

(OR): Productivity Press.

Oo, T. Z. (2014). Critical success factors for application of BIM for Singapore

architectural firms. Master’s thesis, Heriot‐Watt University, Edinburgh, Scotland,

UK.

Oraee, M., Hosseini, M. R., Papadonikolaki, E., Palliyaguru, R., and Arashpour, M.

(2017). Collaboration in BIM-based construction networks: a bibliometric-

qualitative literature review. International Journal of Project Management, 35(7),

1288–1301.

Panas, A., and Pantouvakis, J. P. (2010). Evaluating research methodology in

construction productivity studies. The Built & Human Environment Review, 3(1),

63–85.

Pardo-del-Val M, Martínez-Fuentes C, and Roig-Dobón S. (2012). Participative

management and its influence on organizational change. Management Decision,

50(10), 1843–1860.

Parrish, K., Wong, J. M., Tommelein, I. D., and Stojadinovic, B. (2008). Set-based

design: case study on innovative hospital design. In Proceedings of the 16th

Annual Conference of the International Group for Lean Construction (IGLC 16)

(pp.413–423). Manchester, UK.

Pasquire, C. L., and Gibb, A. G. F. (2002). Considerations for assessing the benefits

of standardization and pre-assembly in construction. Journal of Financial

Management of Property and Construction, 7(3), 151–61.

Poirier, E., Staub-French, S., and Forgues, D. (2015). Embedded contexts of

innovation: BIM adoption and implementation for a specialty contracting SME.

Construction Innovation, 15(1), 42–65.

Porwal, A., and Hewage, K. N. (2013). Building Information Modeling (BIM)

partnering framework for public construction projects. Automation in

Construction, 31, 204–214.

Page 370: building information modeling–based process transformation to improve productivity in the

350

Price, A. D., and Chahal, K. (2006). A strategic framework for change management.

Construction Management and Economics, 24(3), 237–251.

Ranasinghe, U., Ruwanpura, J., and Liu, X. (2011). Streamlining the construction

productivity improvement process with the proposed role of a construction

productivity improvement officer. Journal of Construction Engineering and

Management, 138(6), 697–706.

Ranjbari, M. (2013). A model in information management system using interior

relation layers. Global Journal of Science, Engineering and Technology, 5, 108–

113

Rezgui, Y., Beach, T., and Rana, O. (2013). A governance approach for BIM

management across lifecycle and supply chains using mixed-modes of

information delivery. Journal of Civil Engineering and Management, 19(2), 239–

258.

Robinson, J. P., Shaver, P. R., and Wrightsman, L. S. (Eds.). (1991). Measures of

Personality and Social Psychological Attitudes. San Diego (CA): Academic Press.

Rockart, J. F., and Scott Morton, M. S. (1984). Implications of changes in

information technology for corporate strategy. Interfaces, 14(1), 84–95.

Rogers, J. P. (2013). The strategic adoption of building Information Modelling by

Malaysian engineering consulting services firms. Doctoral thesis, Southern Cross

University, Lismore, Australia.

Ross, K., Cartwright, P., and Novakovic, O. (2006). A guide to modern methods of

construction. Bucks (England): NHBC Foundation, IHS BRE Press.

Ross, T. J. (2010). Fuzzy logic with engineering applications (3rd ed.). New York

(NY): John Wiley & Sons.

Sacks, R., Koskela, L., Dave, B. A., and Owen, R. (2010). Interaction of lean and

building information modeling in construction. Journal of Construction

Engineering and Management, 136(9), 968–980.

Samari, M., Esmaeilifar, R., and Shafiei, M. W. M. (2014). Green building: strategic

approach to sustainable economy. The International Journal of Business &

Management, 2(7), 198–202.

Sarhan, S., and Fox, A. (2013a). Barriers to implementing lean construction in the

UK construction industry. The Built & Human Environment Review, 6, 1–17.

Sarhan, S., and Fox, A. (2013b). Performance measurement in the UK construction

industry and its role in supporting the application of lean construction concepts.

Australasian Journal of Construction Economics and Building, 13(1), 23–35.

Sarker, S. (2000). Toward a methodology for managing information systems

implementation: a social constructivist perspective. Informing Science, 3(4), 195–

206.

Sattineni, A., and Mead K. (2013). Coordination guidelines for virtual design and

construction. In: Proceedings of the 30th International Association for

Automation and Robotics in Construction. Montreal, Canada.

Page 371: building information modeling–based process transformation to improve productivity in the

351

Schein, E. H. (1982). Organizational culture. Cambridge (MA): MIT Press.

Scott Morton, M. (1991). The corporation of the 1990s: information technology and

organisational transformation. Oxford (UK): Oxford University Press.

SDOS. (2017). Yearbook of statistics Singapore, 2017. Singapore: Department of

Statistics.

Selvaraj, P., Radhakrishnan, P., and Adithan, M. (2009). An integrated approach to

design for manufacturing and assembly based on reduction of product

development time and cost. International Journal of Advanced Manufacturing

Technology, 42(1–2), 13–29.

Senaratne, S., and Wijesiri, D. (2008). Lean construction as a strategic option: testing

its suitability and acceptability in Sri Lanka. Lean Construction Journal, 4(1),

34–48.

Senge, P. M. (1990). The fifth discipline: the art and practice of the learning

organization. New York: Currency Doubleday.

Shan, Y. (2014). Integrated information modeling of construction project

productivity. Doctoral thesis, Department of Civil, Environmental, and

Architectural Engineering, University of Colorado at Boulder, Boulder, CO.

Silva, M. J. F., Salvado, F., Couto, P., and e Azevedo, Á. V. (2016). Roadmap

proposal for implementing building information modelling (BIM) in Portugal.

Open Journal of Civil Engineering, 6, 475–481.

Singh, V., Gu, N., and Wang, X. (2011). A theoretical framework of a BIM-based

multi-disciplinary collaboration platform. Automation in Construction, 20(2),

134–144.

SMEC. (2014). Recommendations for budget 2015. Singapore Business Federation.

Smircich, L. (1983). Concepts of culture and organizational analysis. Administrative

Science Quarterly, 28(3), 339–58.

Smith C, Norton B, and Ellis D. (1992). Leavitt’s diamond and the flatter library: a

case study in organizational change. Library Management, 13(5), 18–22.

Smith, P. (2014). BIM implementation – global strategies. Procedia Engineering, 85,

482–492.

Solihin, W., and Eastman, C. (2015). Classification of rules for automated BIM rule

checking development. Automation in Construction, 53, 69–82.

Succar, B. (2009). Building information modelling framework: a research and

delivery foundation for industry stakeholders. Automation in construction, 18(3),

357–375.

Tah, J. H. M., and Carr, V. (2000). A proposal for construction project risk

assessment using fuzzy logic. Construction Management & Economics, 18(4),

491–500.

Page 372: building information modeling–based process transformation to improve productivity in the

352

Tan, W. (2012). Practical research methods (4th ed.). Singapore: Pearson Custom

Publishing.

Tashakkori, A., and Teddlie, C. (1998). Mixed methodology: combining qualitative

and quantitative approaches. Thousand Oaks (CA): SAGE Publications.

Teo, A. L. (2008). Online survey: factors deterring the development of automated

quantity taking-off system. In Proceedings of CIB W055 – W065 Joint

International Symposium. Dubai, United Arab Emirates.

Teo, A. L. E., Ofori, G., Tjandra, I. K., and Kim, H. (2014). The potential of BIM for

safety and productivity. In Proceedings of CIB W099 International Conference

Achieving Sustainable Construction Health and Safety (pp.618–627). Lund,

Sweden.

Teo, A. L., and Heng, P. S. N. (2007). Deployment framework to promote the

adoption of automated quantities taking-off system. In P. X. W. Zou, S. Newton,

J. Wang (Eds.), Proceedings of CRIOCM 2007 International Research

Symposium on Advancement of Construction Management and Real Estate

(pp.928–43). Sydney, Australia.

Teo, E. A. L., Chan, S. L., and Tan, P. H. (2007). Empirical investigation into factors

affecting exporting construction services in SMEs in Singapore. Journal of

Construction Engineering and Management, 133(8), 582–91.

Thomas, H. R., Maloney, W. F., Horner, R. M. W., Smith, G. R., Handa, V. K., and

Sanders, S. R. (1990). Modeling construction labor productivity. Journal of

Construction Engineering and Management, 116(4), 705–726.

Tsikriktsis, N. (2004). A technology readiness-based taxonomy of customers a

replication and extension. Journal of Service Research, 7(1), 42–52.

Turk, Ž. (2016). Ten questions concerning building information modelling. Building

and Environment, 107, 274–284.

Venkatesh, V. (2000). Determinants of perceived ease of use: integrating control,

intrinsic motivation, and emotion into the technology acceptance model.

Information Systems Research, 11(4), 342–365.

Verdecho, M. J., Alfaro-Saiz, J. J., Rodriguez-Rodriguez, R., and Ortiz-Bas, A.

(2012). A multi-criteria approach for managing inter-enterprise collaborative

relationships. Omega, 40, 249–263.

Voss, C., Tsikriktsis, N., and Frohlich, M. (2002). Case research in operations

management. International Journal of Operations & Production Management,

22(2), 195–219.

Wan, M. (2013). Singapore economics: labour pains. Credit Suisse.

Weill, P., and Woerner, S. L. (2013). The future of the CIO in a digital economy. MIS

Quarterly Executive, 12(2), 65–75.

Wickersham, J. (2009). Legal and business implications of Building Information

Modeling (BIM) and Integrated Project Delivery (IPD), BIM-IPD legal and

business issues. Lafayette (LA): Rocket Press Publishing.

Page 373: building information modeling–based process transformation to improve productivity in the

353

Wigand, D. (2007). Building on Leavitt’s diamond model of organizations: the

organizational interaction diamond model and the impact of information

technology on structure, people, and tasks. In Proceedings of the 13th Americas

Conference on Information Systems. Keystone, CO.

Wilfling, S., and Baumoel, U. (2011). A comprehensive information model for

business change projects. In Proceedings of the 17th Americas Conference on

Information Systems. Detroit, MI.

Wilkins, J. R. (2011). Construction workers’ perceptions of health and safety training

programmes. Construction Management and Economics, 29(10), 1017–1026.

Won, J., Lee, G., Dossick, C., and Messner, J. (2013). Where to focus for successful

adoption of building information modeling within organization. Journal of

Construction Engineering and Management, 139(11), 04013014.

Wong, P. F., Salleh, H., and Rahim, F. A. M. (2014). Capability of Building

Information Modelling application in quantity surveying practice. Journal of

Surveying, Construction and Property, 5(1), 1–13.

Wu, P., and Low, S. P. (2011). Lean production, value chain and sustainability in

precast concrete factory - a case study in Singapore. Lean Construction Journal,

2011, 19–36.

Wu, P., and Low, S. P. (2012). Lean management and low carbon emissions in

precast concrete factories in Singapore. Journal of Architectural Engineering,

18(2), 176–186.

Xia, B., Chan, A. P. C., and Yeung, J. F. Y. (2011). Developing a fuzzy multicriteria

decision-making model for selecting design-build operational variations. Journal

of Construction Engineering and Management, 137(12), 1176–1184.

Xu, Y., Chan, A. P. C., and Yeung, J. F. Y. (2010a). Developing a fuzzy risk

allocation model for PPP projects in China. Journal of Construction Engineering

and Management, 136(8), 894–903.

Xu, Y., Yeung, J. F. Y., Chan, A. P. C., Chan, D. W. M., Wang, S. Q., and Ke, Y.

(2010b). Developing a risk assessment model for PPP projects in China–A fuzzy

synthetic evaluation approach, Automation in Construction, 19(7), 929–943.

Yager, R. R. (1980). On a general class of fuzzy connectives. Fuzzy Sets & Systems, 4,

235–242.

Yeung, J. F. Y., Chan, A. P. C., Chan, D. W. M., and Li, L. K. (2007). Development

of a partnering performance index (PPI) for construction projects in Hong Kong:

a Delphi study. Construction Management and Economics, 25(12), 1219–1237.

Yin, R. K. (2014). Case study research: design and methods (5th ed.). Thousand

Oaks (CA): SAGE Publications.

Young, N. W., Jones, S. A., and Bernstein, H. M. (2008). Building information

modeling (BIM): transforming design and construction to achieve greater

industry productivity. Bedford (MA): McGraw-Hill Construction.

Page 374: building information modeling–based process transformation to improve productivity in the

354

Young, N. W., Jones, S. A., Bernstein, H. M., and Gudgel, J. E. (2009). The business

value of BIM. Bedford (MA): McGraw-Hill Construction.

Zadeh, L. A. (1965). Fuzzy sets. Information and Control. 8(3), 338.

Zadeh, L. A. (1975). The concept of a linguistic variable and its application to

approximate reasoning. Information Sciences, 8(3), 199–249.

Zahrizan, Z., Ali, N. M., Haron, A. T., Marshall-Ponting, A., and Hamid, Z. A.

(2013). Exploring the adoption of Building Information Modelling (BIM) in the

Malaysian construction industry: a qualitative approach. International Journal of

Research in Engineering and Technology, 2(8), 384–395.

Zeng, H. J., and Chew, B. H. (2013). Basic concept in construction productivity

enhancement. Singapore: Building and Construction Authority.

Zhang, X., Mao, X., and AbouRizk, S. M. (2009). Developing a knowledge

management system for improved value engineering practices in the construction

industry. Automation in Construction 18(6), 777–789.

Zhao, X., Hwang, B. G., and Gao, Y. (2016a). A fuzzy synthetic evaluation approach

for risk assessment: a case of Singapore's green projects. Journal of Cleaner

Production, 115, 203–213.

Zhao, X., Hwang, B. G., and Low, S. P. (2013). Developing fuzzy enterprise risk

management maturity model for construction firms. Journal of Construction

Engineering and Management, 139(9), 1179–1189.

Zhao, X., Hwang, B. G., and Low, S. P. (2014a). Enterprise risk management

implementation in construction firms: an organizational change perspective.

Management Decision, 52(5), 814–833.

Zhao, X., Hwang, B. G., and Low, S. P. (2014b). Investigating enterprise risk

management maturity in construction firms. Journal of Construction Engineering

and Management, 140(8), 05014006.

Zhao, X., Hwang, B. G., and Low, S. P. (2015). Enterprise risk management in

international construction firms: drivers and hindrances. Engineering,

Construction and Architectural Management, 22(3), 347–366.

Zhao, X., Hwang, B. G., and Low, S. P. (2016b). An enterprise risk management

knowledge-based decision support system for construction firms. Engineering,

Construction and Architectural Management, 23(3), 369–384.

Page 375: building information modeling–based process transformation to improve productivity in the

355

Appendices

Appendix 1: Questionnaire of Survey I

Survey on Non-Value Adding (NVA) Activities in Current Project

Delivery Process in the Singapore Construction Industry

Section I: Introduction

Building information modeling (BIM) is both an advanced technology and an intelligent 3D

model-based process. It equips project teams with insights and tools to more efficiently plan,

design, construct, and manage buildings.

The Singapore government has mandated BIM e-submissions of all building plans for new

building projects with a gross floor area of 5,000 m2 and above since July 2015. Nevertheless,

consultants tend to focus too much on BIM submissions for regulatory approvals, instead of

considering downstream uses. Thus, contractors and facility managers may lack quality BIM

models from the consultants. Some contractors deal with this situation by building their own

BIM teams and re-create the models. This is partial BIM adoption as it creates many NVA

activities, such as using poorly coordinated building systems and unclear plans on site. These

activities may result in wastes such as defects, requests for information, waiting for

instructions, and reworks, seriously affecting productivity.

The study aims to apply BIM to transform the current project delivery process into full BIM-

enabled processes in the Singapore construction industry to reduce critical NVA activities, and

thus enhance productivity. This survey seeks to identify the critical NVA activities and their

causes in the current process in Singapore construction industry, and evaluate the wastes

resulted from such activities. I assure you that the information provided by you will be kept

strictly confidential and will be used for academic purpose only. Any reports resulting from

this survey will make no identifiable reference to the specific sources of data. No individual

company or person will be identified in this study.

I will send you a summary of the results if you would like to leave your e-mail address in

General Information section.

Thank you for sparing your valuable time.

Sincerely,

LIAO Longhui, Ph.D. candidate

Department of Building, National University of Singapore

Page 376: building information modeling–based process transformation to improve productivity in the

356

Section II: General Information

1. How would you classify your organization’s main business?

□ Architectural firm □ Structural engineering firm □ MEP engineering firm

□ General construction firm □ Trade construction firm □ Facility management firm

□ Others, specify_________________________________________________.

2. If your organization is “contractor” or “supplier”, its financial grade under BCA:

___________; otherwise, please go to Q3.

3. Your designation/position.

□ Government agent □ Owner □ Architect

□ Structural designer □ MEP designer □ General contractor

□ Trade contractor □ Manufacturer/Supplier □ Facility manager

4. Your e-mail address (if you would like to receive a summary of the results):

_________________________________________________.

5. Years of your work experience in the construction industry.

□ 5-10 □ 11-15 □ 16-20 □ 21-25 □ > 25

6. Years of implementing BIM in your organization.

□ 0 □ 1-3 □ 4-5 □ 6-10 □ > 10

Section III: Non-Value Adding (NVA) Activities

The following activities are identified from academic literature by comparing current project

delivery process (consultants tend to overemphasize mandatory BIM submissions, rather than

collaborating with downstream parties who are usually not involved upfront) with full BIM-

enabled processes (Integrated Project Delivery1, Virtual Design and Construction, and Design

for Manufacturing and Assembly) and are grouped according to project phases. Please rate the

level of agreement on these activities as NVA activities using a five-point scale (1=strongly

disagree, 2=disagree, 3=unsure, 4=agree, 5=strongly agree) and the frequency of occurrence

(1=never, 2=rarely, 3=sometimes, 4=often, and 5=always) of the activities in a building

project that you are participating (or recently participated).

1 Key features of Integrated Project Delivery: (1) owner continuously involves architect,

and/or engineers, general contractor, and/or key trade contractors from early design through

project completion; (2) they sign a single, multi-party agreement; (3) they waive any claim

amongst themselves except for in the instance of a wilful default; (4) they clearly define

achievable goals, jointly make decisions and control the project, and mutually share the

reward of achieving project targets and bear the risk of missing the targeted cost.

Page 377: building information modeling–based process transformation to improve productivity in the

357

No. NVA activities

in current project delivery process

Level of

agreement

(1=strongly

disagree,

5=strongly

agree)

Frequency of

occurrence

(1=never,

5=always)

P1. Conceptualization 1 2 3 4 5 1 2 3 4 5

1.1 Lack of involvement by government agency

1.2 Inadequate project objectives and performance metrics

set by owner

1.3 Owner resists to use BIM in the whole project

1.4 No reward/risk sharing arrangements among major

stakeholders are set by owner

1.5 Lack of involvement by engineers (not appointed)

1.6 Lack of involvement by general contractor (not

appointed)

P2. Schematic design 1 2 3 4 5 1 2 3 4 5

2.1 Lack of involvement by government agency

2.2 Lack of joint control and agreement on project targets and

metrics by major stakeholders

2.3 Architect, engineers, and contractors do not work

together in design modeling

2.4 Architect does not share its complete model with

engineers

2.5 Architect and engineers do not submit their schematic

design models for regulatory approvals

2.6 Engineers not involved early in this phase to contribute in

architectural modeling

2.7 Lack of involvement by general contractor and key trade

contractors to contribute site knowledge (not appointed)

2.8 Lack of involvement by manufacturer/supplier (not

appointed) to contribute fabrication knowledge

2.9 Lack of involvement by facility manager (not appointed)

to contribute operations and maintenance knowledge

P3. Design development 1 2 3 4 5 1 2 3 4 5

3.1 Lack of involvement by government agency

3.2 Insufficient design review and feedback by owner

3.3 Architect, engineers, and contractors do not work

together in design modeling

3.4 Architect does not share its complete model with

engineers and contractors

3.5 Coordination of building systems is deferred until

construction phase due to unavailable trade contractor

input until then

3.6 Lack of involvement by general contractor and key trade

contractors to contribute site knowledge (not appointed)

3.7 Construction model is not developed due to

unwillingness of architect and engineers to share their

BIM models

3.8 Lack of involvement by manufacturer/supplier (not

appointed) to contribute knowledge of material selection,

transportation, site erection, and so on

3.9 Lack of involvement by facility manager (not appointed)

to contribute operations and maintenance knowledge

P4. Construction documentation 1 2 3 4 5 1 2 3 4 5

4.1 Not fully defined and coordinated between architectural,

structural, and MEP design models

4.2 Insufficient communication between architect and

engineers

Page 378: building information modeling–based process transformation to improve productivity in the

358

4.3 Information such as bill of materials, assembly, layout,

detailed schedule, testing and commissioning procedures

is not documented after design

4.4 Long-lead items are not identified and defined during

design for early procurement

4.5 Shop drawing process is not merged into design as

contractors and manufacturer/supplier cannot document

construction intent

4.6 Prefabrication of some systems cannot start as design is

not fixed

P5. Agency permit/Bidding/Preconstruction 1 2 3 4 5 1 2 3 4 5

5.1 Architect and engineers only pass 2D drawings or

incomplete 3D BIM models to contractors and

manufacturer/supplier

5.2 General contractor has to re-build BIM model based on

insufficient documents from designers

5.3 General contractor extends 2D drawings (without BIM)

from designers to guide construction

P6. Construction (including Manufacture) 1 2 3 4 5 1 2 3 4 5

6.1 Owner and designers enable changes during construction

6.2 Architect and engineers need long time to respond to

contractors’ requests for information (RFIs) as their

design models cannot directly guide site work

6.3 Architect and engineers do not update their design

models

6.4 Contractors and manufacturer/supplier have excessive

RFIs and paperwork

6.5 General contractor communicates insufficiently with

other key stakeholders

6.6 Low proportion of building components in superstructure

and fitting out using off-site manufacture (OSM)

6.7 Congestion and many interfaces on site

6.8 Incomplete 2D drawings or 3D BIM models for trade

contractors and manufacturer/supplier

P7. Closeout/Closeout/Operations and maintenance 1 2 3 4 5 1 2 3 4 5

7.1 As-built BIM models are not handed to facility manager

who uses insufficient levels of detail 2D as-built

drawings

7.2 Many disputes/claims/litigations between general

contractor and owner and designers

7.3 Facility manager does not have sufficient BIM-based

design and construction information for operations and

maintenance

If there are other NVA activities that you deem as important and rational, please list them

below and provide your ratings:

Phase Other NVA activity Level of

agreement

Frequency of

occurrence

Section IV: Wastes

Page 379: building information modeling–based process transformation to improve productivity in the

359

The following wastes are resulted from the NVA activities mentioned in Section III. Please

rate the frequency of occurrence (1=never, 2=rarely, 3=sometimes, 4=often, and 5=always)

and the impact on productivity of these wastes (1=insignificant effect, 2=minor detrimental

effect, 3=moderate detrimental effect, 4=significant detrimental effect, and 5=catastrophic

effect) in the same project mentioned in Section III.

No. Wastes

resulted from the NVA activities

Frequency of

occurrence

(1=never,

5=always)

Impact on

productivity

(1=insignificant

effect

5=catastrophic

effect)

1 2 3 4 5 1 2 3 4 5

1 Defects

2 RFIs

3 Reworks/abortive works

4 Waiting/idle time

5 Change orders

6 Activity delays

7 Overproduction/reproduction

8 Transporting/handling materials

9 Unnecessary inventory

10 Excess processing beyond standard

11 Unnecessary movement of people and equipment

12 Design deficiencies (errors, omissions, additions)

13 Safety issues (injuries)

If there are other wastes resulted from the NVA activities (mentioned in Section III) that you

deem as important and rational, please list them below and provide your ratings:

Other waste Frequency of

occurrence

Impact on

productivity

Section V: Causes

The following are possible causes to the NVA activities mentioned in Section III, and are

categorized into six groups based on project roles. Please rate the importance of these causes

(1=not important, 2=slightly important, 3=moderately important, 4=very important, and

5=extremely important) in the same project mentioned in Section III.

No. Causes

to the NVA activities Rating

importance

(1=not

important,

5=extremely

important)

R1: Government agency 1 2 3 4 5

Page 380: building information modeling–based process transformation to improve productivity in the

360

1.1 Focusing on design stage by developing BIM submission templates and

guidelines

1.2 Mandating BIM submissions cannot guarantee collaboration and best-

for-project thinking

1.3 Unclear legislations and qualifications for precasters (versus concreter)

and inadequate codes for OSM varieties

R2: Owner (α = 0.870) 1 2 3 4 5

2.1 Inertia against use of BIM or off-site prefabrication

2.2 Establishing minimal apparent risk and minimum first cost as crucial

selection criteria

2.3 Unaware of the benefits of BIM and lifecycle management

2.4 Creating incentives for individual firms to protect their own interests

2.5 Awarding architectural and engineering design contracts solely based

on qualification

2.6 Setting vague goals with architect and rarely passing them on to

downstream parties

2.7 Focusing on assessing liability and risk transfers using mechanisms

such as guarantees and penalties

2.8 Perceiving design fees for OSM as more expensive than traditional

process

2.9 Desire for particular structures or traditional finishes

R3: Architect/Engineers 1 2 3 4 5

3.1 Because of potential liability, architect includes fewer details in

drawings or indicates that the drawings cannot be relied on for

dimensional accuracy

3.2 Architect does not model what contractors need for quantity take-offs

3.3 Not required by contract to share design models with contractors

3.4 Design models/drawings fit for mandatory BIM submissions, but not fit

for intended downstream use

3.5 Architect and engineers do not understand field operations enough and

lack construction input in design

3.6 Lack of skilled BIM experts to engage

3.7 No complete knowledge of their design decisions’ impact on

construction

3.8 Architect and engineers spend much time and effort locating,

recreating, or transferring fragmented information

3.9 Unless asked and encouraged, architect and engineers do not consider

lifecycle value of or incremental changes

3.10 Limited expertise of OSM and its processes in the market for architect

and engineers

3.11 Downstream designers have to make extra efforts to reconfigure or

reformat data

R4: General contractor/Key trade contractors 1 2 3 4 5

4.1 General contractor not required by owner and government to adopt BIM

4.2 General contractor only has 2D drawings or incomplete 3D model

shared from designers

4.3 General contractor has to make extra efforts to reconfigure or reformat

data

4.4 General contractor’s reluctance to adopt OSM

4.5 General contractor’s BIM team does modeling but not coordination for

trade contractors

4.6 General contractor requires but does not train trade contractors to use

BIM

4.7 Lack of skilled BIM experts to engage to help construction manager

and unable to see how BIM benefit them

4.8 Training cost and high learning curve (initial productivity loss) to use

BIM

4.9 Reluctant and inexperienced to use BIM and happy to continue using

traditional CAD

Page 381: building information modeling–based process transformation to improve productivity in the

361

4.10 Having little knowledge of BIM and do not know how, when, and what

to use it

4.11 Lack of national BIM standards and guidelines for contractors

4.12 Doubt about the effectiveness of BIM because of limited evidence

4.13 Afraid of the unknown and resistant to change from comfortable daily

routine

4.14 Lack of legal support from authority

4.15 Lack of tangible benefits of BIM to warrant its use

4.16 Not thinking of changing conventional methods and no demand for

BIM use

4.17 Limited expertise of OSM and its processes in the market for

contractors

4.18 Trade contractors not required by general contractor/owner/government

to adopt BIM

4.19 High cost for trade contractors to engage BIM experts or outsource to

BIM drafters

4.20 Trade contractors only have 2D drawings or incomplete 3D model

shared from designers or general contractor

4.21 Trade contractors have to make extra efforts to reconfigure or reformat

data

4.22 Trade contractors use CAD and cannot integrate BIM models from

general contractor into their site models

R5: Manufacturer/Supplier 1 2 3 4 5

5.1 Does not permit design changes as these are expensive once fabrication

has commenced

5.2 Not required by owner/general contractor/government to adopt BIM in

manufacture

5.3 Lack of skilled BIM experts to engage and unable to see how BIM

benefit them

5.4 Only 2D drawings or incomplete 3D model shared from designers or

general contractor

5.5 Training cost and high learning curve (initial productivity loss) to use

BIM

5.6 Reluctant and inexperienced to use BIM and still happy to continue

using CAD

5.7 Market protection from traditional suppliers/manufacturers

R6: Facility manager 1 2 3 4 5

6.1 Not required by owner to use BIM and not involved in design phase to

contribute knowledge

If there are other causes to the NVA activities (mentioned in Section III) that you deem as

important and rational, please list them below and provide your rating (s):

Role Other cause Importance

Do you mind participating in next stage (Survey II) of this study?

□ Yes

□ No, your e-mail address (if NOT indicated in the “General Information” section):

___________________________________________________________________________.

Page 382: building information modeling–based process transformation to improve productivity in the

362

Thank you once again.

If you have any queries about the survey, please feel free to contact LIAO Longhui.

Tel: (65) 9628 8127;

Email: [email protected]; [email protected]

Page 383: building information modeling–based process transformation to improve productivity in the

363

Appendix 2: Questionnaire of Survey II

Survey on Factors Driving and Hindering Process Transformation

towards Full BIM-Enabled Project Delivery Processes in the Singapore

Construction Industry

Section I: Introduction

Building information modeling (BIM) is both an advanced technology and an intelligent 3D

model-based process. It equips project teams with insights and tools to more efficiently plan,

design, construct, and manage buildings.

The Singapore government has mandated BIM e-submissions of all building plans for new

building projects with a gross floor area of 5,000 m2 and above since July 2015. Nevertheless,

consultants tend to focus too much on BIM submissions for regulatory approvals, instead of

considering downstream uses. Thus, contractors and facility managers may lack quality BIM

models from the consultants. Some contractors deal with this situation by building their own

BIM teams and re-create the models. This is partial BIM adoption as it creates many NVA

activities, such as using poorly coordinated building systems and unclear plans on site. These

activities may result in wastes such as defects, requests for information, waiting for

instructions, and reworks, seriously affecting productivity.

The study aims to apply BIM to transform the current project delivery process into full BIM-

enabled processes (Integrated Project Delivery1, Virtual Design and Construction, and Design

for Manufacturing and Assembly) in the Singapore construction industry to reduce critical non-

value adding (NVA) activities, and thus enhance productivity. This survey seeks to identify

the critical factors hindering and driving the change towards full BIM implementation. I

assure you that the information provided by you will be kept strictly confidential and will be

used for academic purpose only. Any reports resulting from this survey will make no

identifiable reference to the specific sources of data. No individual company or person will be

identified in this study.

I will send you a summary of the results if you would like to leave your e-mail address in

General Information section.

Thank you for sparing your valuable time.

1 Key features of Integrated Project Delivery: (1) owner continuously involves architect,

and/or engineers, general contractor, and/or key trade contractors from early design through

project completion; (2) they sign a single, multi-party agreement; (3) they waive any claim

amongst themselves except for in the instance of a wilful default; (4) they clearly define

achievable goals, jointly make decisions and control the project, and mutually share the

reward of achieving project targets and bear the risk of missing the targeted cost.

Page 384: building information modeling–based process transformation to improve productivity in the

364

Sincerely,

LIAO Longhui, Ph.D. candidate

Department of Building, National University of Singapore

Section II: General Information

1. How would you classify your organization’s main business?

□ Architectural firm □ Structural engineering firm □ MEP engineering

firm

□ General construction firm □ Trade construction firm □ Facility

management firm

□ Others, specify_____________________________.

2. If your organization is “contractor” or “supplier”, its financial grade under BCA:______;

otherwise, please go to Q3.

3. Your designation/position.

□ Government agent □ Owner □ Architect

□ Structural designer □ MEP designer □ General contractor

□ Trade contractor □ Manufacturer/Supplier □ Facility manager

4. Your e-mail address (if you would like to receive a summary of the results):

________________________________________________________________.

5. Years of your work experience in the construction industry:

□ 5-10 □ 11-15 □ 16-20 □ 21-25 □ > 25

6. Years of implementing BIM in your organization:

□ 0 □ 1-3 □ 4-5 □ 6-10 □ > 10

Section III: Hindrances to Change towards Full BIM Implementation

The following are hindrances to change from current project delivery process (consultants

tend to overemphasize mandatory BIM submissions, rather than collaborating with

downstream parties who are usually not involved upfront) towards full BIM-enabled

processes (Integrated Project Delivery, Virtual Design and Construction, and Design for

Manufacturing and Assembly). Please rate the significance of these hindrances (1=very

insignificant, 2=insignificant, 3=neutral, 4=significant, and 5=very significant) in a building

project that you are participating (or recently participated). If you have previously participated

in Another Survey of this study, please provide your ratings according to the same building

project you referred to in Another Survey.

Page 385: building information modeling–based process transformation to improve productivity in the

365

No. Hindrances to change

towards full BIM-enabled delivery processes Significance

(1=very

insignificant,

5=very

significant)

1 2 3 4 5

H01 Executives failing to recognize the value of BIM-based processes and

needing training

H02 Concerns over or uninterested in sharing liabilities and financial

rewards

H03 Construction lawyers and insurers lacking understanding of

roles/responsibilities in new process

H04 Lack of skilled employees and need for training them on BIM and

off-site manufacture (OSM)

H05 Industry’s conservativeness, fear of the unknown, and resistance to

change comfortable routines

H06 Employees still being reluctant to use new technology after being

pushed to training programs

H07 Entrenchment in 2D drafting and unfamiliarity to use BIM

H08 Financial benefits cannot outweigh implementation and maintenance

costs

H09 Lack of sufficient evidence to warrant BIM use

H10 Liability of BIM such as the liability for common data for

subcontractors

H11 Resistance to changes in corporate culture and structure

H12 Need for all key stakeholders to be on board to exchange information

H13 Lack of trust/transparency/communication/partnership and

collaboration skills

H14 BIM operators lacking field knowledge

H15 Field staff dislike BIM coordination meetings looking at a screen

H16 Lack of consultants’ feedbacks on subcontractors’ model coordination

H17 Few benefits from BIM go to designers while most to contractors and

owners

H18 Lack of legal support from authorities

H19 Lack of owner request or initiative to adopt BIM

H20 Decision-making depending on relationships between project

stakeholders

H21 Owners set minimal risk and minimum first cost as crucial selection

criteria

H22 Poor knowledge of using OSM and assessing its benefits

H23 Requiring higher onsite skills to deal with low tolerance OSM

interfaces

H24 OSM relies on suppliers to train contractors to install correctly

H25 Owners’ desire for particular structures or finishes when considering

OSM

H26 Market protection from traditional suppliers/manufacturers and

limited OSM expertise

H27 Contractual relationships among stakeholders and need for new

frameworks

H28 Traditional contracts protect individualism rather than best-for-

project thinking

H29 Lack of effective data interoperability between project stakeholders

H30 Owners cannot receive low-price bids if requiring 3D models

H31 Firms’ unwillingness to invest in training due to initial cost and

productivity loss

H32 Assignment of responsibility/risk to constant updating for broadly

accessible BIM information

H33 Lack of standard contracts to deal with responsibility/risk assignment

and BIM ownership

Page 386: building information modeling–based process transformation to improve productivity in the

366

H34 BIM model issues (e.g., ownership and management)

H35 Poor understanding of OSM process and its associated costs

H36 OSM requires design to be fixed early using BIM

H37 Seeing design fees of OSM as more expensive than traditional process

H38 Difficulty in logistics and stock management of OSM

H39 Unclear legislations and qualifications for precasters and inadequate

codes for OSM varieties

H40 Interpretations resulted from unclear contract documents

H41 Using monetary incentive for team collaboration results in blaming

rather than resolving issues

H42 Costly investment in BIM hardware and software solutions

H43 Interoperability issues such as software selection and insufficient

standards

H44 Need for increasingly specialized software for specialized functions

H45 Difficulty in multi-discipline and construction-level integration

H46 Technical needs for multiuser model access in multi-discipline

integration

H47 Firms cannot make most use of Industry Foundation Classes and use

proprietary formats

If there are other hindrances that you deem as important and rational, please list them below

and provide your ratings:

Other hindrance Significance

Section IV: Drivers for Change towards Full BIM Implementation

The following are drivers for change from current project delivery process (consultants tend

to overemphasize mandatory BIM submissions, rather than collaborating with downstream

parties who are usually not involved upfront) towards full BIM-enabled processes

(Integrated Project Delivery, Virtual Design and Construction, and Design for Manufacturing

and Assembly). Please rate the significance of these drivers (1=very insignificant,

2=insignificant, 3=neutral, 4=significant, and 5=very significant) in the same project

mentioned in Section III. If you have previously participated in Another Survey of this study,

please provide your ratings according to the same building project you referred to in Another

Survey.

No. Drivers for change

towards full BIM-enabled delivery processes Significance

(1=very

insignificant,

5=very

significant)

1 2 3 4 5

D01 BIM vision and leadership from the management

D02 Changes in organizational structure and culture

D03 Stakeholders seeing the value of adopting their own part of BIM

D04 Training on new skillsets and new ways of working

D05 Owner’s requirement and leadership to adopt BIM

Page 387: building information modeling–based process transformation to improve productivity in the

367

D06 Regulatory agencies’ early participation to BIM use

D07 Gaining competitive advantages from full BIM use

D08 All disciplines sharing models in a ‘Big Room’

D09 Government support such as subsidizing training, software, and

consultancy costs

D10 Enabling subcontractors to use lower-skilled labor on site

D11 OSM lowering safety risks by controlling work in factory

D12 Alignment of the interests of all stakeholders

D13 Governance of BIM-related policies and standards

D14 Data sharing and access on BIM platforms

D15 3D visualization enabling design communication

D16 4D simulation before construction

D17 Design coordination between disciplines through clash detection and

resolution

D18 Complex design analysis in sustainability, material selection, and

constructability

D19 Project lifecycle costing

D20 Producing models and drawings for construction and fabrication

D21 High accuracy of model-based documentation

D22 More off-site fabrication and assembly of standard elements

D23 Automatic model updating and drawing production to deal with

design changes and their implications

D24 Lifecycle information management improving operations and

maintenance

D25 Increasing use of design-build and fast-track approach

D26 On-site work proceeds in parallel with off-site production

D27 OSM standardizes design and manufacturing processes, simplifying

construction and testing and commissioning processes

D28 OSM produces building elements with better quality and consistency

D29 OSM reduces building wastes, especially on-site wastes

D30 Integrating model management tools with enterprise systems to

exchange data

D31 Increasing complexity in buildings, project delivery, and marketplace

D32 New technologies such as Computer Numerically Controlled machines

If there are other drivers that you deem as important and rational, please list them below and

provide your ratings:

Other driver Significance

Would you like to be interviewed in next stage of this study?

□ Yes, your e-mail address (if NOT indicated in the “General Information” section):

__________________________________________________________________________.

□ No

Thank you once again.

If you have any queries about the survey, please feel free to contact LIAO Longhui.

Tel: (65) 9628 8127;

Email: [email protected]; [email protected].

Page 388: building information modeling–based process transformation to improve productivity in the

368

Appendix 3: Questionnaire for the Validation of the BBPT model

Validation of the BIM-Based Process Transformation Model for

Enhancing BIM Implementation and Improving Productivity in Building

Projects in Singapore

Section I: Introduction

You are invited to assess the BIM-based process transformation (BBPT) model for enhancing

BIM implementation and improving productivity performance in building projects in

Singapore. The BBPT model serves as an internal evaluation tool for project leadership teams

in the project planning stage. The objectives of the BBPT model are to: evaluate BIM

implementation readiness (BIMIR) status of a building project in the project planning stage,

and provide management strategies with different priorities for the project team to change

towards a higher BIMIR status. After the transformation, the productivity of this project is

expected to be improved.

The information that you provide will be kept strictly confidential and be used solely for

academic purposes. Your name and your project’s name will not appear in the study.

Thank you for your kind assistance.

Sincerely,

LIAO Longhui, Ph.D. candidate

Department of Building, National University of Singapore

Section II: General Information

1. Your designation: _________________________.

2. Your work experience in the construction industry: ________years.

3. Your e-mail address: __________________________________________.

4. Years of adopting BIM in your firm: ________years.

5. BCA financial grade of your firm: □ ________ □ not applicable.

6. Name of the building project that you are participating (or recently participated): ________.

7. Type of this project: □ public project □ private project.

8. Role of your firm in this project: _________________________________.

Section III: BIM Implementation Readiness (BIMIR) Status Evaluation

Page 389: building information modeling–based process transformation to improve productivity in the

369

Implementation readiness of a project team that plans to implement BIM is defined as “the

psychological willingness or the state of being prepared for performing BIM implementation

activities”. BIMIR describes the condition or situation of the team in the project planning

stage. In this section, please provide information based on the project you indicated in Section

II, Question 6.

1. Compared with full BIM-enabled delivery approaches (Integrated Project Delivery1, Virtual

Design and Construction, and Design for Manufacturing and Assembly), please estimate

which BIMIR status this building project is in, according to your experience and judgment.

□ BIMIR status one (no BIM implementation)

□ BIMIR status two (lonely BIM implementation: BIM is used in single parties, with low

level of collaboration or no collaboration among the parties)

□ BIMIR status three (collaborative BIM implementation: BIM is used in key parties, with

medium or high level of collaboration among the parties)

□ BIMIR status four (full BIM implementation)

2. Compared with full BIM-enabled delivery approaches (Integrated Project Delivery, Virtual

Design and Construction, and Design for Manufacturing and Assembly), currently there are

many activities in different project phases that do not add value to the complete delivery

process of this project and the final building. Please estimate the frequency of occurrence

(0%–100%) of non-value adding activities in each phase in this project.

Code Project phase Frequency of occurrence of non-value

adding activities in each phase in this

project (%)

P1 Conceptualization Score: _______________________%

P2 Schematic design Score: _______________________%

P3 Design development Score: _______________________%

P4 Construction documentation Score: _______________________%

P5 Agency permit/Bidding/Preconstruction Score: _______________________%

P6 Construction (including Manufacture) Score: _______________________%

P7 Handover/Closeout/Operations and

maintenance Score: _______________________%

Overall non-value adding index score Score: _______________________%

3. Please use the BBPT model to evaluate the BIMIR status of this project.

4. Do you think the managerial strategies provided by the BBPT model are useful and their

priorities are appropriate for your project to move towards a higher BIMIR status?

1 Key features of Integrated Project Delivery: (1) owner continuously involves architect,

and/or engineers, general contractor, and/or key trade contractors from early design through

project completion; (2) they sign a single, multi-party agreement; (3) they waive any claim

amongst themselves except for in the instance of a wilful default; (4) they clearly define

achievable goals, jointly make decisions and control the project, and mutually share the

reward of achieving project targets and bear the risk of missing the targeted cost.

Page 390: building information modeling–based process transformation to improve productivity in the

370

_________________________________________________________________________

_________________________________________________________________________

_________________________________________________________________________.

5. What do you think of the functionality and user-friendliness of the BBPT model for

enhancing BIM implementation to reduce wastes and improve productivity in the

Singapore construction industry?

_________________________________________________________________________

_________________________________________________________________________

_________________________________________________________________________.

Page 391: building information modeling–based process transformation to improve productivity in the

371

Appendix 4: A Calculation Example of the Fuzzy BIMIR Model

The fuzzy BIMIR model developed in Section 4.4.2 is adopted to evaluate the BIMIR status

of a surveyed building project in Singapore to illustrate the calculation process. The level of

agreement rating scores of the critical NVA activities were collected from Survey I. Using

equation 4.3, the mean scores of the critical NVA activities (𝑀𝑖) were calculated, as shown in

Table 7.2. Using equation 4.5 to 4.6, the weights of the critical NVA activities (𝑊𝑖 ) and

project phases (𝑊𝑝) were obtained, which are presented in Table 7.4. For example, the weight

of critical NVA activity N1.1 in the first project phase (P1, conceptualization) was calculated

as follows:

𝑊1 =𝑀1

∑ 𝑀𝑖4𝑖=1

= 3.51 (3.51 + 3.85 + 3.41 + 3.73) = 0.242⁄

The mean score of the first phase (𝑀1) was calculated as shown:

𝑀1 = ∑ 𝑀𝑖1 = 3.51 + 3.85 + 3.41 + 3.73 = 14.49

4

𝑖=1

The weight of the first phase (𝑊1) could be calculated as following:

𝑊1 =𝑀1

∑ 𝑀17𝑝=1

= 14.49 (14.49 + 22.41 + 29.64 + 21.97 + 11.47 + 28.97 + 10.22) = 0.104⁄

In this example, the frequencies of occurrence of the 38 critical NVA activities were rated

using the five-point scale (1=never, 2=rarely, 3=sometimes, 4=often, and 5=always). The

input data assigned by the corresponding respondent are shown in Table A.1. Since only one

response (𝑟 = 1) was received regarding this project, the TFN (𝐹𝑖𝑝

) of the frequency of

occurrence of the critical NVA activities in all phases were directly obtained according to

Table 4.3. The critical NVA activity N1.1 obtained the linguistic value of “always” and could

be transferred to the TFN of (0.75, 1.00, 1.00). Using the addition and multiplication

operations as well as equation 4.8, the TFN (𝐹1) of the frequency of occurrence of the first

project phase (P1) can be calculated as follows:

Page 392: building information modeling–based process transformation to improve productivity in the

372

𝐹1 = (𝑓1𝑝

, 𝑓2𝑝

, 𝑓3𝑝

) = ∑(𝑊𝑖 × 𝐹𝑖𝑝

)

𝑘

𝑖=1

= (0.75 × 0.242 + 0.50 × 0.266 + 0.75 × 0.235 + 0.75 × 0.257, 1.00

× 0.242 + 0.75 × 0.266 + 1.00 × 0.235 + 1.00 × 0.257, 1.00 × 0.242

+ 1.00 × 0.266 + 1.00 × 0.235 + 1.00 × 0.257) = (0.684, 0.934, 1.000)

Then, using equation 4.9, the TFN of the 𝑁𝑉𝐴𝐼 of this project can be calculated:

𝑁𝑉𝐴𝐼 = (𝑛𝑣𝑎𝑖1, 𝑛𝑣𝑎𝑖2, 𝑛𝑣𝑎𝑖3)

= ∑(𝑊𝑝 × 𝐹𝑝) =

𝑞

𝑝=1

∑ {𝑊𝑝 × ∑(𝑊𝑖 × 𝐹𝑖𝑝

)

𝑘

𝑖=1

}

𝑞

𝑝=1

= (0.104 × (0.684, 0.934, 1.000) + 0.161 × (0.711, 0.961, 1.000)

+ 0.213 × (0.529, 0.779, 0.965) + 0.158 × (0.295, 0.545, 0.795) + 0.082× (0.502, 0.752, 0.917) + 0.208 × (0.318, 0.568, 0.784) + 0.073

× (0.250, 0.500, 0.750))

= (0.071 + 0.114 + 0.113 + 0.047 + 0.041 + 0.066 + 0.018, 0.097+ 0.155 + 0.166 + 0.086 + 0.062 + 0.118 + 0.037, 0.104 + 0.161+ 0.206 + 0.126 + 0.076 + 0.163 + 0.055) = (0.471, 0.721, 0.890)

Thus, 𝑛𝑣𝑎𝑖1 , 𝑛𝑣𝑎𝑖2, 𝑛𝑣𝑎𝑖3 are 0.471, 0.721, and 0.890, respectively. The crisp number of the

NVAI score of this project can be calculated using equation 4.12:

NVAI score=1∕3×(𝑛𝑣𝑎𝑖1 + 𝑛𝑣𝑎𝑖2 + 𝑛𝑣𝑎𝑖3)=1/3× (0.471 + 0.721 + 0.890) = 0.694

According to the adjusted translation rules presented in Table 4.5, the NVAI score can be

translated into: BIMIR S2 (lonely BIM implementation).

Page 393: building information modeling–based process transformation to improve productivity in the

373

Table A.1 Calculation process of the NVAI of a surveyed building project

Phase Critical NVA

activity 𝐹𝑖𝑗

𝑝 𝐹𝑖

𝑝= (𝑓𝑖1

𝑝, 𝑓𝑖2

𝑝, 𝑓𝑖3

𝑝) Weight of critical NVA

activity 𝐹𝑝 = ∑(𝑊𝑖 × 𝐹𝑖𝑝

)

𝑘

𝑖=1

Weight of

phase 𝑊𝑝 × 𝐹𝑝

P1 N1.1 (0.75, 1.00, 1.00) (0.75, 1.00, 1.00) 0.242 (0.684, 0.934, 1.000) 0.104 (0.071, 0.097, 0.104)

N1.2 (0.50, 0.75, 1.00) (0.50, 0.75, 1.00) 0.266

N1.3 (0.75, 1.00, 1.00) (0.75, 1.00, 1.00) 0.235

N1.4 (0.75, 1.00, 1.00) (0.75, 1.00, 1.00) 0.257

P2 N2.1 (0.50, 0.75, 1.00) (0.50, 0.75, 1.00) 0.156 (0.711, 0.961, 1.000) 0.161 (0.114, 0.155, 0.161)

N2.2 (0.75, 1.00, 1.00) (0.75, 1.00, 1.00) 0.163

N2.3 (0.75, 1.00, 1.00) (0.75, 1.00, 1.00) 0.156

N2.4 (0.75, 1.00, 1.00) (0.75, 1.00, 1.00) 0.175

N2.5 (0.75, 1.00, 1.00) (0.75, 1.00, 1.00) 0.175

N2.6 (0.75, 1.00, 1.00) (0.75, 1.00, 1.00) 0.175

P3 N3.1 (0.50, 0.75, 1.00) (0.50, 0.75, 1.00) 0.110 (0.529, 0.779, 0.965) 0.213 (0.113, 0.166, 0.206)

N3.2 (0.75, 1.00, 1.00) (0.75, 1.00, 1.00) 0.120

N3.3 (0.50, 0.75, 1.00) (0.50, 0.75, 1.00) 0.110

N3.4 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.138

N3.5 (0.50, 0.75, 1.00) (0.50, 0.75, 1.00) 0.142

N3.6 (0.50, 0.75, 1.00) (0.50, 0.75, 1.00) 0.111

N3.7 (0.50, 0.75, 1.00) (0.50, 0.75, 1.00) 0.136

N3.8 (0.75, 1.00, 1.00) (0.75, 1.00, 1.00) 0.132

P4 N4.1 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.171 (0.295, 0.545, 0.795) 0.158 (0.047, 0.086, 0.126)

N4.2 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.157

N4.3 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.160

N4.4 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.157

N4.5 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.174

N4.6 (0.50, 0.75, 1.00) (0.50, 0.75, 1.00) 0.181

P5 N5.1 (0.75, 1.00, 1.00) (0.75, 1.00, 1.00) 0.338 (0.502, 0.752, 0.917) 0.082 (0.041, 0.062, 0.076)

N5.2 (0.50, 0.75, 1.00) (0.50, 0.75, 1.00) 0.331

N5.3 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.331

P6 N6.1 (0.75, 1.00, 1.00) (0.75, 1.00, 1.00) 0.136 (0.318, 0.568, 0.784) 0.208 (0.066, 0.118, 0.163)

N6.2 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.128

N6.3 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.124

N6.4 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.130

N6.5 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.116

N6.6 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.117

Page 394: building information modeling–based process transformation to improve productivity in the

374

N6.7 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.129

N6.8 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.121

P7 N7.1 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.345 (0.250, 0.500, 0.750) 0.073 (0.018, 0.037, 0.055)

N7.2 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.330

N7.3 (0.25, 0.50, 0.75) (0.25, 0.50, 0.75) 0.326

Sum – – 1 – 1 (0.471, 0.721, 0.890)

NVAI score – – – – – 0.694

Page 395: building information modeling–based process transformation to improve productivity in the

375

Appendix 5: List of Publications from This Thesis

Liao, L., and Teo, E. A. L. (Published online, January 15, 2018). Managing critical

drivers for building information modelling implementation in the Singapore

construction industry: An organizational change perspective. International Journal of

Construction Management. DOI: 10.1080/15623599.2017.1423165.

Liao, L., and Teo, E. A. L. (2018). Organizational change perspective on people

management in BIM implementation in building projects. Journal of Management in

Engineering, 34 (3), 04018008.

Liao, L., and Teo, E. A. L. (2017). Critical success factors for enhancing the building

information modelling implementation in building projects in Singapore. Journal of

Civil Engineering and Management, 23(8), 1029–1044.

Liao, L., Teo, E. A. L., and Low, S. P. (2017). A project management framework for

enhanced productivity performance using building information modeling.

Construction Economics and Building, 17(3), 1–26.