Upload
blaze-mcdonald
View
224
Download
0
Tags:
Embed Size (px)
Citation preview
Black SeaRegional Transmission Planning ProjectBy Predrag MikšaEKC - Electricity Coordinating Center
Istanbul, March 2011
Black Sea Transmission Project
History of BSTP
BSTP Established in 2004 with signing of the Sofia Memorandum of Understanding (MOU)
Members reaffirmed commitment in 2007/2008 with signing of Phase II MOU
Phase I concluded in 2007
Phase II was concluded in February 2010
Black Sea Transmission Project
BSTP Project Goals
Promote regional transmission planning among Black Sea TSO’s
Harmonize transmission planning principles and methodologies
Identify priority investments in national transmission systems & interconnections between countries
Black Sea Transmission Project
BSTP Project Objectives
Create sustainable international expert transmission planning Working Group (WG)
Support common planning software platform (PSS/E)
Analyze the regional system to identify bottlenecks (congestion)
Identify potential transmission investments needed to enhance trade
Promote analytical results to policy & regulatory authorities
Black Sea Transmission Project
BSTP Phase I & II Results
Phase I and II of the BSTP Developed and Refined Load Flow and Dynamic Regional Transmission System Models for 2015 and 2020
Identified Net Transfer Capacities Based on Technical Limitations of the Network
Findings Confirmed the Network is Generally Robust Stability Issues in the Caucasus Region Lack of Connections (Synchronous or
Asynchronous) Limits Transfer Both Within the Region and with Neighboring Region
Black Sea Transmission Project
TASK#1 Regional model – modeled systems
Transmission networks of all power systems in the region
Russia Romania Georgia
Ukraine Bulgaria Armenia
Moldova Turkey Equivalent of western and south-eastern UCTE grid (ENTSO-E)
Modeled
Equivalented
RUS
GEO
AZB
BUL
BLR
EST
GRE
HUN
LAT
LIT
MKD
POL
ROM
SVK
TUR
UKR
SCG Black Sea
MLD
ARM
Black Sea Transmission Project
TASK#1 Regional model - characteristics
High voltage network-transmission network750kV,500kV,400kV,330kV,220kV,150kV,110
kV networkGenerator units at their nominal voltage levelStep-up transformers for main generation
capacities All new substations and lines that are
expected to be operational till 2020 (according to the long term development plans)
Development of Regional model Guidelines
Black Sea Transmission Project
TASK #1 Regimes to model/update
Load flow Model update/upgrade Regimes to model
Present situation 2010 Winter peak, 2010 Summer off-peak 2010 Summer peak
Realistic plans 2015 2015 Winter peak 2015 Summer peak 2015 Summer off-peak
Realistic plans 2020 2020 Winter peak 2020 Summer peak 2020 Summer off-peak
Black Sea Transmission Project
TASK #1 Regimes to model/update
Load/Demand modeling Proposal medium load/demand forecasts
Renewables Identifying (put them in adequate zone by type) Rough estimation about connection Necessary network reinforcements to support
renewables Network reinforcements modeling
Realistic plans Plans vs realization (past analyses) Other projects
Black Sea Transmission Project
8822 7604
205 1000
1306
19
1235
61
2823 4015
Black Sea Region - total
2935 1371 44 1520
3243130555
796 1000
5430654622
784
-1100
1871516904
724 1050
10271 9417
220 545
1175 1151 23 0
1963 1937 26 0
TASK#2 Regional data collection demand/generation
Load/Demand data High demand scenario Medium demand scenario Low demand scenario
Generation expansion plans Realistic scenario Type of new power plants, and
fuel used Renewables
Level of engagement Level of development
Integration of data to Regional report
50
52
54
56
58
60
62
64
66
68
SCENARIU MEDIU SCENARIU MAXIM SCENARIU MINIM
Black Sea Transmission Project
TASK#3 – Renewables data collection
Renewables Generation expansion plans Wind Small hydro Other Estimated connection to grid Market approach (feed in tariff
and price,…) Rules of engagement
Each country to prepare country report, Model integrator to prepare regional overview and regional report
Black Sea Transmission Project
TASK#4 – OPF data collection
Questionnaire is developed to collect generation data Generation data
Type of power plant (thermal, hydro, nuclear etc…
Type of fuel used (gas, coal – lignite, brown coal, nuclear fuel imported etc…)
Fixed running costs Variable running costs Rules of engagement
Two parts Obligatory
Type of power plant (hydro, gas fired, coal…) Fuel used and pricing and Fuel energy (caloric value
of fuel) Installed capacity (max, min production level) …
Non obligatory (dependable on model building approach)
Other economical data (question for availability…) OPF training
Black Sea Transmission Project
TASK#5 – OPF model construction
PSSE OPF is tool used to find an optimum operating position considering the cost of competing objectives such as minimizing: Fuel Costs Power Slack Generation Transmission System Technical Losses Cross Boarder (Interface) Flows Reactive Generation Reserves Required
Generation data Type of power plant (thermal, hydro, nuclear
etc… Type of fuel used (gas, coal – lignite, brown
coal, nuclear fuel imported etc…) Fixed running costs Variable running costs Rules of engagement Generic generation cost curves (in first step, to be
adjusted by project participants according to real data)
Network data Network grid code rules and recommendations Technical constraints
Black Sea Transmission Project
TASK#5 – OPF model construction
Generic Cost Curve will be developed by USEA and EKC (based on questionnaire collected data)
To be reviewed, revised and approved by TSO’s (depending on the approach they chose)
TSOs will enter themselves network OPF data (thermal limits, voltage limitations…)
USEA and EKC will integrate these in regional model to be used for regional and national OPF studies
Black Sea Transmission Project
Task#6 – Regional model analyses
Load flow analyses loading of the network feasibility of base case exchanges voltage profile analyses contingency analyses (n-1 security check)
Border capacity overview Evaluation of network transfer capabilities Evaluation of Renewables integration
High renewables engagement scenario Critical loss of wind power (selection of
scenarios) Identify the existing potential for electric
power trade in the region Verify values through dynamic analyses
Critical regimes (exchange) Select outage to investigate Monitor machines
Russia
Georgia
Azerbajan
Albania
BIH
Bulgaria
Belarus
Croatia
Czech republic
Greece
Italy
Hungary
Makedonia
Poland
Romania
Slovakia
Turkey
Ukraine
SRB
Iraq
Iran
Black Sea
Armenia
10
00 3
00
0
500
1850
750 75
0
1600850
200200
1350
200 14
00
75
0 75
0
12
00 1
50
0
60
0 40
0
1100
3000 30
00
Black Sea Transmission Project
Russia
Georgia
Azerbajan
Albania
Austria
BIH
Bulgaria
Belarus
Croatia
Czech republic
Germany
Greece
Italy
Hungary
Makedonia
Poland
Romania
Slovakia
Slovenia
Turkey
Ukraine
SRB
Iraq
Iran
Black Sea
Armenia
3400
13001450
1500
18001100
750 75
0
TASK#7 – Market analyses
Generation surplus projections in Black Sea region and electricity market scenarios in the period 2010 - 2020 analyses of present and future
generation expansion plans and electricity prices (according to production costs and fuel costs)
evaluation of transfer capacities (ENTSO-E methodology)
Identifying market realistic scenarios (using PSS/E OPF)
Evaluation of network adequacy
Black Sea Transmission Project
Thank You!Thank You!