Upload
ravi-jain
View
221
Download
0
Embed Size (px)
Citation preview
8/8/2019 Biomass Power Generation Plant Installation Project Report
1/30
[1]
INTRODUCTION
PURPOSE OF THE PLAN
This Bio-diesel Project Plan will provide a definition of the project, including the
projects goals and objectives. Additionally, the Plan will serve as an agreement
between the following parties: Project Sponsor, Steering Committee, Project
Manager, Project Team, and other personnel associated with and/or affected by the
project.
The Project Plan defines the following:
Project purpose Business and project goals and objectives Scope and expectations Roles and responsibilities Assumptions and constraints Project management approach Ground rules for the project Project budget Project timeline Organizational Design
BACKGROUND INFORMATION/AVAILABLE ALTERNATIVES
An inspection of the saline lands around Srikakulam was conducted and found
suitable for Jatropha plantation. This has led to the idea of a bio-diesel unit.
The alternative technologies available are:
Trans-esterification and Dilute-acid esterification
This project employs the Trans-esterification technology due to the easy availability
of raw material and lower fixed costs.
8/8/2019 Biomass Power Generation Plant Installation Project Report
2/30
[2]
PROJECT APPROACH
The project is decomposed into the following phases:
Phase I: Feasibility Study
Phase II: Licensing & Registration
Phase III: Project Planning
Phase IV: Supplier Service Level Agreements
Phase V: Order/Install Equipment
Phase VI: Test Run
Figure 1 Project Approach
8/8/2019 Biomass Power Generation Plant Installation Project Report
3/30
[3]
GOALS AND OBJECTIVES
BUSINESS GOALS AND OBJECTIVES
The business goals and objectives for this project will focus on production of bio-
diesel from Jatropha which:
Is an additive in commercial and industrial diesel Is cheaper than diesel Is environment friendly Has lower flash point than diesel Has higher lubricity hence increasing engine life Does not require engine modification
PROJECT GOALS AND OBJECTIVES
Project goals and objectives include:
Define planning requirements of the system by 10/08/2010. Define user needs in terms of inputs and outputs by 12/08/2010. Conduct user and stakeholder meetings along the PLC. Complete erection of a 500 liter/day capacity bio-diesel production unit by
16/02/2011.
Complete commissioning of the unit by 05/03/2011. Complete system acceptance and user documentation by 20/03/2011. Achieve Project closure by 01/04/2011.
8/8/2019 Biomass Power Generation Plant Installation Project Report
4/30
[4]
STRATEGIC FIT ANALYSIS
VALUE CHAIN ANALYSIS
Figure 2 - Porter's Value Chain
1. The Inbound Logistics of the RM into the production unit will be outsourced toprivate transporters.
2. The production operations of the bio-diesel will be the core competency of thecompany. It will include full-time employees and contract labors.
3. The Outbound Logistics of bio-diesel from the production unit to the OMCs willbe outsourced to private transporters.
4. Marketing & Sales of bio-diesel is limited to OMCs.
SWOT ANALYSIS
STRENGTHS
Suitable soil & climate Man power availability Waste land availability
WEAKNESS
Reluctant attitude of farmers Only 30% oil yield RM availability
OPPORTUNITIES
Subsidies Priority sector Attraction to green technology 0% excise duty & EPCG
THREATS
Alternative fuels Uncompleted legal environment Low R&D funding Not efficiently developed
business structure
Higher competitiveness of bio-fuels from other regions
8/8/2019 Biomass Power Generation Plant Installation Project Report
5/30
[5]
PROJECT WBS AND LRC MATRIX
TAG LEGEND
WPI WORK PACKAGE DONE INTERNALLY
WPC WORK PACKAGE SUB-CONTRACTED
TASK ID TASK DESCRIPTION TAG RAVI PAWAN VISHAL
1.1 FEASIBILITY STUDY
1.1.1 RM AVAILABILITY
1.1.1.1 LOCAL SUPPLIERS
1.1.1.1.1 COST WPI C1 R C1
1.1.1.1.2 QUALITY WPI C1 R C1
1.1.1.1.3 TRANSPORT WPI C1 R C11.1.1.2 NON-LOCAL SUPPLIERS
1.1.1.2.1 COST WPI C1 C1 R
1.1.1.2.2 QUALITY WPI C1 C1 R
1.1.1.2.3 TRANSPORT WPI C1 C1 R
1.1.1.2.4 LEAD-TIME WPI C1 C1 R
1.1.1.3 SELF
1.1.1.3.1 COST WPI R C1 C1
1.1.1.3.2 LAND AVAILABILITY WPI R C1 C1
1.1.1.3.3 WATER AVAILABILITY WPI R C1 C1
1.1.2 CAPITAL AVAILABILITY
1.1.2.1 KHADI BHANDAR
1.1.2.1.1 INTEREST RATE WPI R C1 C1
1.1.2.1.2 LOAN PERIOD WPI R C1 C1
1.1.2.1.3 LOAN AMOUNT WPI R C1 C1
1.1.2.1.4 COLLATERAL WPI R C1 C1
1.1.2.2 IDBI
1.1.2.2.1 INTEREST RATE WPI C1 C1 R
1.1.2.2.2 LOAN PERIOD WPI C1 C1 R
1.1.2.2.3 LOAN AMOUNT WPI C1 C1 R1.1.2.2.4 COLLATERAL WPI C1 C1 R
1.1.2.3 SSI FINANCE
1.1.2.3.1 INTEREST RATE WPI C1 R C1
1.1.2.3.2 LOAN PERIOD WPI C1 R C1
1.1.2.3.3 LOAN AMOUNT WPI C1 R C1
1.1.2.3.4 COLLATERAL WPI C1 R C1
1.1.3 LAND AVAILABILITY
1.1.3.1 PLANTATION LOCATION
8/8/2019 Biomass Power Generation Plant Installation Project Report
6/30
[6]
1.1.3.1.1 LEASE OR BUY WPI R C1 C1
1.1.3.1.2 WATER AVAILABILITY WPI R C1 C1
1.1.3.2 PROCESSING UNIT LOC.
1.1.3.2.1 POLLUTION WPI R C1 C1
1.1.3.2.2 ROAD CONNECTIVITY WPI R C1 C1
1.1.3.2.3 LEASE OR BUY WPI R C1 C1
1.1.4 POWER AVAILABILITY
1.1.4.1 EXISTING LINES
1.1.4.1.1 TRANSCO PERMISSION WPI C1 C1 R
1.1.4.1.2 COST/kWh WPI C1 C1 R
1.1.4.1.3 TRANSFORMER WPI C1 C1 R
1.1.4.2 NEW LINES
1.1.4.2.1 TRANSCO PERMISSION WPI C1 C1 R
1.1.4.2.2 COST/kWh WPI C1 C1 R
1.1.4.2.3 No. OF POLES WPI C1 C1 R1.1.4.2.4 WIRING LENGTH WPI C1 C1 R
1.1.4.2.5 TRANSFORMER WPI C1 C1 R
1.1.5 MANPOWER AVAILABILITY
1.1.5.1 FOR PLANTATION
1.1.5.1.1 No. OF MEN WPI C1 R C1
1.1.5.1.2 No. OF WOMEN WPI C1 R C1
1.1.5.2 FOR PROCESSING UNIT
1.1.5.2.1 SKILLED WPI C1 R C1
1.1.5.2.2 UNSKILLED WPI C1 R C1
1.2 LISCENSING & REG.
1.2.1 SINGLE WINDOW @ DIC
1.2.1.1 NAME OF FIRM WPI R A A
1.2.1.2 TYPE OF FIRM WPI R C1 C1
1.2.1.3 OUTPUT WPI R C1 C1
1.2.2 MRO PERMISSION WPI R C2 C2
1.2.3 POLLUTION PERMISSION
1.2.3.1 LAND INSPECTION WPI R C2 N1.2.3.2 DISTANCE CALCULATION WPI R C2 N
1.2.4 SARPANCH WILLING LETTER WPI R C2 N
1.3 FINANCE AND BUDGETING
1.3.1 FIXED COST
1.3.1.1 LAND WPI C1 C1 R
1.3.1.2 BUILDING WPI C1 C1 R
1.3.1.3 MACHINERY WPI C1 C1 R
1.3.1.4 PLANT WPI C1 C1 R
1.3.1.5 VEHICLES WPI C1 C1 R
1.3.2 VARIABLE COST
8/8/2019 Biomass Power Generation Plant Installation Project Report
7/30
[7]
1.3.2.1 RAW MATERIAL WPI C1 R C1
1.3.2.2 POWER WPI C1 R C1
1.3.2.3 WAGES WPI C1 R C1
1.3.2.4 ADMIN WPI C1 R C1
1.4 LAND ACQUISITION
1.4.1 FOR PLANTATION
1.4.1.1 PURCHASING
1.4.1.1.1 NEGOTIATE WPI R C1 C1
1.4.1.1.2 PAYMENT & REG. WPI R C1 C1
1.4.1.2 DEVELOPING
1.4.1.2.1 LEVELLING WPC R C1 C1
1.4.1.2.2 PLOUGHING WPC R C1 C1
1.4.1.2.3 SOWING WPC R C1 C1
1.4.1.2.4 TREATING WPC R C1 C1
1.4.2 FOR PROCESSING UNIT1.4.2.1 PURCHASING
1.4.2.1.1 NEGOTIATE WPI R C1 C1
1.4.2.1.2 PAYMENT & REG. WPI R C1 C1
1.4.2.2 DEVELOPING
1.4.2.2.1 LEVELLING WPC R C1 C1
1.4.2.2.2 LAYOUT PLANNING WPI R C1 C1
1.4.2.2.3 FENCING WPC R C1 C1
1.5 PLANT ERECTION
1.5.1 CIVIL WORKS
1.5.1.1 ADMIN BUILDING WPC C1 R C1
1.5.1.2 FABRICATION WPC C1 R C1
1.5.1.3 FOUNDATION WPC C1 R C1
1.5.2 ELECTRICAL
1.5.2.1 TRANSFORMERS WPC C1 C1 R
1.5.2.2 WIRING WPC C1 C1 R
1.5.2.3 EARTHING WPC C1 C1 R
1.5.2.4 SUB-STATION WPC C1 C1 R
1.5.2.5 GRID CONNECTION WPC C1 C1 R
1.5.2.6 MACHINERY CONNECTION WPC C1 C1 R1.5.2.7 ILLUMINATION WPC C1 C1 R
1.5.2.8 GENERATOR SETUP WPC C1 C1 R
1.5.3 MECHANICAL
1.5.3.1 RMH
1.5.3.1.1 RM PROCESSING WPC R C1 C1
1.5.3.1.2 BELT CONVEYORS WPC R C1 C1
1.5.3.1.3 STORAGE BUNKERS WPC R C1 C1
1.5.3.2 FAT EXTRACTOR
1.5.3.2.1 PIPING WPC C1 R C1
1.5.3.2.2 VESSEL WPC C1 R C1
8/8/2019 Biomass Power Generation Plant Installation Project Report
8/30
[8]
1.5.3.2.3 COMPRESSOR WPC C1 R C1
1.5.3.3 CATALYZER
1.5.3.3.1 PIPING WPC R C1 C1
1.5.3.3.2 VESSEL WPC R C1 C1
1.5.3.3.3 CATALYZER PUMP WPC R C1 C1
1.5.3.4 EXTRACTOR
1.5.3.4.1 INPUT PIPING WPC C1 C1 R
1.5.3.4.2 REACTOR VESSEL WPC C1 C1 R
1.5.3.4.3 EXTRACTION SYSTEM WPC C1 C1 R
1.5.4 INSTRUMENTATION
1.5.4.1 PLC FOR THERMOCOUPLES WPC C1 C1 R
1.5.4.2 PLC FOR COMPRESSORS WPC C1 C1 R1.5.4.3 PLC FOR FEED CHEMICALS WPC C1 C1 R
1.5.4.4 PLC FOR RMH WPC C1 C1 R
1.5.4.5 PLC FOR VALVES WPC C1 C1 R
1.5.5 PILOT TEST WPI C1 C1 R
1.5.6 IT
1.5.6.1 SYSTEM INSTALLATION WPC C1 R C1
1.5.6.2 OS & SOFTWARE WPC C1 R C1
1.5.6.3 ERP WPC C1 R C1
1.5.6.4 NETWORKING WPC C1 R C1
1.5.6.5 FIREWALL WPC C1 R C1
1.6 MARKTING & DISTRIBUTION
1.6.1 MARKET RESEARCH WPI R C1 C1
1.6.2 SWOT & 4Ps WPI C1 R C1
1.6.3 STP WPI C1 C1 R
1.6.4 LOGISTICS
1.6.4.1 INTERNAL
1.6.4.1.1 No. OF VEHICLES PURCHASED WPI R C1 C1
1.6.4.1.2 No. OF VEHICLES LEASED WPI C1 R C1
1.6.4.2 EXTERNAL1.6.4.2.1 TRANSPORTERS WPI R C1 C1
1.6.4.2.2 3PLs WPI C1 C1 R
8/8/2019 Biomass Power Generation Plant Installation Project Report
9/30
[9]
WORK PACKAGE TIME, COST BUDGETING AND SCHEDULING
8/8/2019 Biomass Power Generation Plant Installation Project Report
10/30
[10]
8/8/2019 Biomass Power Generation Plant Installation Project Report
11/30
[11]
8/8/2019 Biomass Power Generation Plant Installation Project Report
12/30
[12]
8/8/2019 Biomass Power Generation Plant Installation Project Report
13/30
[13]
8/8/2019 Biomass Power Generation Plant Installation Project Report
14/30
[14]
8/8/2019 Biomass Power Generation Plant Installation Project Report
15/30
[15]
WORK PACKAGE SEQUENCING
Figure 3 - PERT
8/8/2019 Biomass Power Generation Plant Installation Project Report
16/30
[16]
FINANCIAL PLANNING
Construction Period 7 months
Source of Finance 30% equity
70% debt
Tax Holidays 3 years
Bank Interest 13.5%
Discount Cash Flow 13.5%
WORKING CAPITAL
INITIAL INVESTMENT COST
S.No. COST ITEM TOTAL COST (Rs.)
1. Land 2,450,000
2. Building & Civil Cost 985,0003. Plant & Machinery 1,455,000
4. Over Heads 38,900
5. Working Capital 919,780
TOTAL COST 5,848,680
8/8/2019 Biomass Power Generation Plant Installation Project Report
17/30
[17]
PRODUCTION COSTS
COST OBJECT (per Kg) PRICE (Rs.)
Seed
Collection & Oil Extraction
Cake Produced
Trans-esterification
Glycerin
Overheads
Cost/Kg
--------------------------------------------------------------
Cost/L
16.40
2.48
(-) 2.23
8.77
(-) 3.80
1.35
22.97
-----------
19.52
Selling Price of bio-diesel = Rs. 32/L
BEP = 468,644 units
- 100% Capacity Utilization (Optimistic), BEP after 468 days.- 70% Capacity Utilization (Pessimistic), BEP after 669 days.
8/8/2019 Biomass Power Generation Plant Installation Project Report
18/30
[18]
FACILITY AND LOCATION PLANNING
PROPOSED LOCATION
PROPOSED FACILITY LAYOUT
8/8/2019 Biomass Power Generation Plant Installation Project Report
19/30
[19]
RISK ANALYSIS & MANAGEMENT
INITIAL PROJECT RISK ASSESSMENT
Risk Risk LevelL/M/HLikelihood of
EventMitigation Strategy
Project Size
Person Hours H: Over 20,000 Certainty Assigned Project Manager, engagedconsultant, comprehensive project
management approach and
communications plan
Estimated Project Schedule H: Over 7 months Certainty Created comprehensive projecttimeline with frequent baseline
reviews
Team Size at Peak H: Over 15 members Certainty Comprehensive communicationsplan, frequent meetings, tight
project management oversightProject Definition
Narrow Knowledge Level of
Users
M: Knowledgeable of
user area only
Likely Assigned Project Manager(s) toassess global implications
Available documentation
clouds establishment of
baseline
M: More than 75%
complete/current
Likely Balance of information to begathered by consultant
Project Scope Creep L: Scope generally
defined, subject to
revision
Unlikely Scope intially defined in project plan,
reviewed monthly by three groups
(Project Manager and Steering
Committee) to prevent undetected
scope creep
Consultant Project
Deliverables unclear
L: Well defined Unlikely Included in project plan, subject toamendment
Vendor Project Deliverables M: Estimated, not clearly
defined
Somewhat
likelyIncluded in project plan, subject to
amendment
Cost Estimates Unrealistic L: Thoroughly predicted
using proven practices to
15% margin of error
Unlikely Included in project plan, subject toamendment as new details regarding
project scope are revealed
Timeline Estimates
Unrealistic
M: Timeline assumes no
derailment
Somewhat
likelyTimeline reviewed monthly by three
groups (Project Manager and
Steering Committee) to prevent
undetected timeline departures
Number of Team Members
Unknowledgeable of Business
L: Team well versed in
business operations
impacted by technology
Unlikely Project Manager and consultant toidentify knowledge gaps and provide
training, as necessary
Project Leadership
Steering Committee
existence
L: Identified and
enthusiastic
Unlikely Frequently seek feedback to ensurecontinued support
Absence of Commitment
Level/Attitude of
Management
L: Understands value &
supports project
Unlikely Frequently seek feedback to ensure
continued support
Absence of Mid-Management
Commitment
L: Most understand value
& support project
Unlikely Frequently seek feedback to ensurecontinued support
8/8/2019 Biomass Power Generation Plant Installation Project Report
20/30
[20]
Risk Risk LevelL/M/H
Likelihood of
EventMitigation Strategy
Project Staffing
Project Team Availability M: Distributed team
makes availability
questionable
Somewhat
likelyContinuous review of project
momentum by all levels. Consultant
to identify any impacts caused by
unavailability. If necessary, increase
committmment by participants to full
time status
Physical Location of Team
prevents effective
management
L: Team works in
complete co-ordination
Unlikely Use of comprehensiveCommunications Plan
Project Teams Shared Work
Experience creates poor
working relationship
M: Some have worked
together before
Somewhat
likelyComprehensive Communications Plan
Weak User Participation on
Project Team
L: Users are part-time
team members
Unlikely User Group Participants coordinatedby full time employee
Project ManagementProcurement
Methodology Used foreign to
team
L: Procurement
Methodology familiar to
team
Unlikely N/A
Change Management
Procedures undefined
L: Well-defined Unlikely N/A
Quality Management
Procedures unclear
L: Well-defined and
accepted
Unlikely N/A
Software Vendor (ERP)
Number of Times Team Has
Done Prior Work with Vendor
Creates Foreign Relationship
H: Never Certainty A comprehensive vendor evaluationand selection process (incorporated
into Project Plan) will be employed to
predict and define the relationshipbetween the department and the
vendor
Teams Lack of Knowledge of
Package
M: Conceptual
understanding
Somewhat
likelyComprehensive vendor evaluation
and selection process incorporated
into Project Plan will assist the team
in better understanding the package
offering(s)
Poor Functional Match of
Package to Initial System
Requirements
L: Minimal customization
required
Unlikely Although a package has not yet been
selected, the Consultant has
compared the initial requirementswith available functionality and
determined that a functional match to
the initial requirements is very likely.
Vendor selection will be based, in
part, on how well the proposed
application matches defined
functional specifications.
Teams Involvement in
Package Selection Impacts
Success of Implementation
L: High involvement in
selection
Unlikely Comprehensive vendor evaluationand selection process incorporated
into Project Plan
8/8/2019 Biomass Power Generation Plant Installation Project Report
21/30
[21]
SENSITIVITY ANALYSIS
SP (%) VC (%) BEP BEP (%)
0 0 468644.2 0
-1 0 480977 2.631579
-5 0 537562.5 14.70588
-7 0 571160.2 21.875
-10 0 630245.7 34.48276
-12 0 676930.6 44.44444
-15 0 761546.9 62.5
-20 0 961953.9 105.2632
-25 0 1305509 178.5714
0 1 476090.8 1.588955
0 3 491717.1 4.923325
0 5 508404 8.484006
0 7 526263.3 12.29485
0 10 555535.7 18.54103
0 12 576929.5 23.10606
0 15 612299 30.65327
-1 1 488823.9 4.305964
-5 3 568141.9 21.23096
-7 5 631334.2 34.71503
-10 7 739066.9 57.70319
-12 10 874503.6 86.60287
-15 12 1095751 133.8129
-20 15 1855546 295.9391
8/8/2019 Biomass Power Generation Plant Installation Project Report
22/30
[22]
0
20
40
60
80
100
120
140
160
180
200
-30 -25 -20 -15 -10 -5 0
SP vs BEP
SENSITIVITY TO SP
0
5
10
15
20
25
30
35
0 2 4 6 8 10 12 14 16
VC vs BEP
SENSITIVITY TO VC
8/8/2019 Biomass Power Generation Plant Installation Project Report
23/30
[23]
PROJECT CONTROL
Once a project is running it is important that the project manager keeps control. This is
achieved by regular reporting of issues, risks, progress and constant checking of thebusiness case to ensure that the expected benefits will be delivered and are still valid. All
proposed changes should be assessed, logged and appropriate action taken.
CHANGE MANAGEMENT
The information contained within the Project Plan will likely change as the project
progresses. While change is both certain and required, it is important to note that
any changes to the Project Plan will impact at least one of three critical success
factors: Available Time, Available Resources (Financial, Personnel), or Project Quality.
The decision by which to make modifications to the Project Plan (including project
scope and resources) should be coordinated using the following process:
Step 1: As soon as a change which impacts project scope, schedule, staffing or
spending is identified, the Project Manager will document the issue.
Step 2: The Project Manager will review the change and determine the
associated impact to the project and will forward the issue, along witha recommendation, to the Steering Committee for review and
decision.
Step 3: Upon receipt, the Steering Committee should reach a consensus
opinion on whether to approve, reject or modify the request based
upon the information contained within the project website, the
Project Managers recommendation and their own judgment. Should
the Steering Committee be unable to reach consensus on the
approval or denial of a change, the issue will be forwarded to the
Project Sponsor, with a written summation of the issue, for ultimate
resolution.
Step 4: If required under the decision matrix or due to a lack of consensus,
the Project Sponsor shall review the issue(s) and render a final
decision on the approval or denial of a change.
Step 5: Following an approval or denial (by the Steering Committee or Project
Sponsor), the Project Manager will notify the original requestor of the
action taken. There is no appeal process.
8/8/2019 Biomass Power Generation Plant Installation Project Report
24/30
[24]
ASSESS ORGANIZATIONAL CULTURE
The Project Organizational Culture will be assessed along the following dimensions:
Positive work environment:- Openness to new ideas,- Employees feeling valued as individuals,- Open discussion with superiors encouraged etc.
Management leadership: this includes factors such as- Clear goals set and responsibilities delegated,- Employees have input in decision making,- Incentives offered to work on new ideas,- High-risk high-return projects encouraged etc.
Results orientation: this includes factors such as- Employees are pressured to finish work,- Correct procedures more important than correct results etc.
8/8/2019 Biomass Power Generation Plant Installation Project Report
25/30
[25]
ORGANIZATIONAL DESIGN
ORGANIZATION STRUCTURE
SPONSOR
STEERING COMMITTEE
PROJECT
MANAGER
WORK
PACKAGE
MANAGER
WORK
PACKAGE
MANAGER
SUBJECT
MATTER
EXPERTS
SITE
EMPLOYEES
SUB
CONTRACTORS
8/8/2019 Biomass Power Generation Plant Installation Project Report
26/30
[26]
PROJECT TEAM AND ADMINISTRATION POLICIES
Role Scope Of Administration Participant(s)
ProjectSponsor
Ultimate decision-maker and tie-breaker Provide project oversight and guidance Review/approve some project elements
XYZ Ltd.
Steering
Committee
Commits department resources Approves major funding and resource
allocation strategies, and significant
changes to funding/resource allocation
Resolves conflicts and issues Provides direction to the Project Manager Review project deliverables
Mr. A
Mr. B
Mr. C
Mr. D
Project
Manager
Manages project in accordance to theproject plan
Serves as liaison to the Steering Committee Receive guidance from Steering Committee Supervises consultants Supervise vendor(s) Provide overall project direction Direct/lead team members toward project
objectives
Handle problem resolution Manages the project budget
Mr. Ravi Jain
Project
Participants
Understand the user needs and businessprocesses of their area
Act as consumer advocate in representingtheir area
Communicate project goals, status andprogress throughout the project to
personnel in their area
Review and approve project deliverables Creates or helps create work products Coordinates participation of work groups,
individuals and stakeholders
Provide knowledge and recommendations Helps identify and remove project barriers Assure quality of products that will meet
the project goals and objectives
Identify risks and issues and help inresolutions
Mr. Pawan Akella
Mr. Vishal Chandra
Mr. B.K.Dheeraj
Mr. Krishna Chandra
Mr. Gautam Kumar
Subject
Matter
Experts
Lend expertise and guidance as needed Mr. Srinivas ReddyMr. Teja Manik
8/8/2019 Biomass Power Generation Plant Installation Project Report
27/30
[27]
COMMUNICATIONS PLANNING
AUDIENCE
Project Sponsor Steering Committee Project Manager User Group Participants Subject Matter Experts Secondary Stakeholders
COMMUNICATION METHODOLOGY
The communications methodology utilizes three directions for effective
communication:
Top-Down It is absolutely crucial that all participants in this project sense the
executive support and guidance for this effort. The executive leadership of
the organization needs to speak with a unified, enthusiastic voice about the
project and what it holds for everyone involved. This will be 'hands-on'
change management, if it is to be successful. Not only will the executivesneed to speak directly to all levels of the organization, they will also need to
listen directly to all levels of the organization, as well.
The transition from the project management practices of today to the
practices envisioned for tomorrow will be driven by a sure and convinced
leadership focused on a vision and guided by clearly defined, strategic,
measurable goals.
Bottom-Up To ensure the buy-in and confidence of the personnel involved in
bringing the proposed changes to reality, it will be important to communicate
the way in which the solutions were created. If the perception in the
organization is that only the Steering Committee created the proposed
changes, resistance is likely to occur. However, if it is understood that all
participants were consulted, acceptance seems more promising.
8/8/2019 Biomass Power Generation Plant Installation Project Report
28/30
[28]
Middle-Out Full support at all levels, where the changes will have to be
implemented, is important to sustainable improvement. At this level (as with
all levels), there must be an effort to find and communicate the specific
benefits of the changes. People need a personal stake in the success of the
project management practices.
PMIS
The following is a list of communication channels that are established for this
project:
Monthly Status Reports
The Project Manager shall provide monthly written status reports to the
Steering Committee. The reports shall include the following information
tracked against the Project Plan:
- Summary of tasks completed in previous month- Summary of tasks scheduled for completion in the next month- Summary of issue status and resolutionsMonthly Steering Committee Meeting
These status meetings are held at least once per month and are coordinated
by the Project Manager. Every member of the Steering Committee
participates in the meeting. The Project Manager sends the status report to
each member of the team prior to the meeting time so everyone can review
it in advance.
Bi-Monthly Project Team Status Meeting
These status meetings are held every other month. Every member of the
Project Team will be invited to participate in the meeting. Project Manager
sends the status report to each member of the team prior to the meeting so
everyone can review it in advance.
Website Use
User Group Participants and Subject Matter Experts may be updated monthly
at the discretion of the Project Manager. Information will be posted to the
projects website.
8/8/2019 Biomass Power Generation Plant Installation Project Report
29/30
[29]
STAKEHOLDER MANAGEMENT
ANALYSIS
1=None, 2=Minimal, 3=Average, and 4=Significant
STAKEHOLDER LEVEL OF
INTEREST
LEVEL OF
INFLUENCE
LEVEL OF
IMPACT
LEVEL OF
SUPPORT
TOTAL
SPONSOR 4 4 4 4 16
STEERING COMMITTEE 4 4 4 4 16
RAVI JAIN 4 3 3 4 14
PAWAN AKELLA 3 2 2 3 10
VISHAL 3 2 2 3 10
SUB-CONTRACTOR 3 1 1 2 8SUPPLIERS 1 1 3 3 8
SARPANCH 1 1 3 2 7
VILLAGERS 1 1 2 2 6
CUSTOMERS 3 2 1 2 8
FARMERS 2 1 2 2 7
MEDIA 1 1 2 2 6
MANAGEMENT
There are two tools and techniques used:
1. Communication methods - Communication methods are listed in thecommunication management plan.
2. Issues log
Issue
No.
Type Date
raised
Description Action
Required/Notes
Raised
by
Issue
Owner
Status Priority Closed
Date
Closure
Comments
001
002
003
004
005
8/8/2019 Biomass Power Generation Plant Installation Project Report
30/30
REFERENCES
PMBOK Project Management Body of Knowledge Hand Book Microsoft Project Help Notes Project Management A Systems Approach, Harold Kerzner Class Notes http://www.onprojectmanagement.files.wordpress.com
http://www.onprojectmanagement.files.wordpress.com/http://www.onprojectmanagement.files.wordpress.com/http://www.onprojectmanagement.files.wordpress.com/