25 MW Biomass Plant China_CDM

Embed Size (px)

Citation preview

  • 8/13/2019 25 MW Biomass Plant China_CDM

    1/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 1

    CLEAN DEVELOPMENT MECHANISM

    PROJECT DESIGN DOCUMENT FORM (CDM-PDD)Version 03 - in effect as of: 28 July 2006

    CONTENTS

    A. General description of project activity

    B. Application of a baseline and monitoring methodology

    C. Duration of the project activity / crediting period

    D. Environmental impacts

    E. Stakeholders comments

    Annexes

    Annex 1: Contact information on participants in the project activity

    Annex 2: Information regarding public funding

    Annex 3: Baselineinformation

    Annex 4: Monitoring plan

  • 8/13/2019 25 MW Biomass Plant China_CDM

    2/72

  • 8/13/2019 25 MW Biomass Plant China_CDM

    3/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 3

    Figure 1 Shanxian 1*25MW Biomass Direct Burning Power Plant Overview

    The electricity produced by the project activity is supplied to the public Shandong provincial power grid

    which is part of the North China grid system. The electricity from the project will be a must-run

    electricity source of the Shandong Grid. The project will replace the power generated by coal-fired power

    plants. Therefore, the electricity supply from the proposed biomass power plant is an alternative to the

    construction of a power plant based on coal with the same capacity. The heat generated in this biomass

    power plant may in the future be utilized as well, after the local heating system has been established. Notethat no emission reductions from the heating component, if any, of the project will be claimed in this

    PDD.

    The proposed project will reduce the greenhouse gas emissions from biomass caused by natural decay and

    uncontrolled burning, and also will reduce greenhouse gas emissions related to the burning of fossil fuel

    for power production.

    Currently about 700 million tonnes straw are produced in China as residues of agricultural production, but

    only a very small percentage of this is properly utilized. The common method of direct burning for

    heating and cooking by the local farmers results in heavy air pollution and very low level of heating

    efficiency. The remainder of the biomass resource is normally dumped in an uncontrolled manner andoccasionally burned in the open air. Shanxian is one the richest biomass resource towns in China and

    most of the agricultural resources are just dumped and not utilized in a proper way.

    The Shanxian Biomass Power Plant is the first demonstration project involving power generation using

    biomass in the P.R. of China. The Chinese new Renewable Energy Law encourages the development of

    power plants using to compensate shortages in energy supply and in order to reduce the severe

    environmental pollution. Especially the constructions of biomass power plants in regions that are rich in

    biomass are encouraged. The local farmers can benefit by supplying straw as fuel for the biomass power

    plants. This will assist the domestic economic development, contribute to reducing poverty, and

    simultaneously decrease the air pollution, by reducing emissions of local pollutants resulting from the

    uncontrolled burning of cotton as well as the burning of coal in coal-fired based power plants.

  • 8/13/2019 25 MW Biomass Plant China_CDM

    4/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 4

    This project is a national pilot project for renewable resource utilization and new Danish technology forthe core boiler system will be introduced to the PRC. The project developer will introduce the new

    Danish boiler technology and is able to benefit from the Danish engineering expertise that will be used in

    this biomass power plant project. Hence, this sustainable energy project will serve as an example and

    could possibly lead to other similar projects in the PRC and will contribute to China's sustainable

    development.

    The project contributes to China's goal of a 15% share of renewable energy in total power generation by

    2020. More specifically, this project:

    Reduces the power generation burden based on coal fired plants which often result in heavy airpollution

    Promotes the national Chinese sustainable development policy

    Creates direct and indirect income-generating and employment opportunities in the area where thisproject is located

    Is constructed as the pilot project of renewable resource utilization and will be a demonstrationproject for any others project developers working on biomass utilization in a sustainable manner

    Ensures that clean and highly efficient technology will be transferred and applied in Chinese localplant

    Avoids an uncontrolled management of biomass resources and optimizes the usage of naturalresources

    A.3. Project participants:

    Please listproject participants and Party(ies) involved and provide contact information in Annex 1.Information shall be in indicated using the following tabular format.

    Name of Party involved (*)

    ((host) indicates a host

    Party)

    Private and/or public

    entity(ies)

    project participants (*)

    (as applicable)

    Kindly indicate if

    the Party involved

    wishes to be

    considered as

    project participant

    (Yes/No)

    China (host) National Bio Energy Co.,Ltd No

    DenmarkDanish Ministry of Foreign

    AffairsYes

    (*) In accordance with the CDM modalities and procedures, at the time of making the CDM-PDD public

    at the stage of validation, a Party involved may or may not have provided its approval. At the time ofrequesting registration, the approval by the Party(ies) involved is required.

    Note: When the PDD is filled in support of a proposed new methodology (form CDM-NM), at least

    the host Party(ies) and any known project participant (e.g. those proposing a new methodology) shall

    be identified.

    >>

    Host Country:

    People's Republic of China, which has ratified the Kyoto Protocol to the United Nations Framework

    Convention on Climate Change in September 2002.

  • 8/13/2019 25 MW Biomass Plant China_CDM

    5/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 5

    Project Participants:

    National Bio Energy Co.,Ltd(NBE), was established in 2005 with a registered capital of 500 million

    RMB. It is a shareholding company. The main shareholders are Shenzhen State Power Science &

    Technology Development Co., Ltd (55% of registered capital) and Dragon Power Co., Ltd. (45%). The

    biggest investor in the majority shareholder is the State Grid Corporation of China. NBE is one of the

    most pilot biomass power companies in China and has started the planning and implementation of the first

    few biomass power plants in China since 2004.

    Danish Ministry of Foreign Affairs(DANIDA). DANIDA is one of the public entities in Denmark

    involved in the procurement of CERs through CDM projects and ERUs through JI projects to help

    Denmark, as an Annex 1 Country, to achieve its targets under the Kyoto Protocol. DANIDA has also

    made available a facility to assist the preparation of CDM documentation in China through the Danish

    CDM Project Development Facility in China (www.cdmasia.org/danida.html)

    CDM consultants

    COWI Consulting (Beijing) Co., Ltdis a daughter company of COWI A/S with the headquarters

    located in Denmark. COWI has been helping Chinese clients to develop CDM projects. COWI A/S has

    worked with carbon trading since 1995 and has contributed actively to emission reduction through

    industrial energy efficiency improvement and renewable energy utilization.

    A.4. Technical description of the project activity:

    A.4.1. Location of the project activity:

    >>

    A.4.1.1. Host Party(ies):

    >>

    People's .Republic of.China

    A.4.1.2. Region/State/Province etc.:

    >>

    Shandong Province

    A.4.1.3. City/Town/Community etc:

    >>

    Shanxian

    A.4.1.4. Detail of physical location, including information allowing the unique

    identification of this project activity (maximum one page):

    >>

    The project is located in the economical developing region which is 3km to the east of the Shanxian

    downtown area, and the postal code of this plant is 274300 and the longitude is 11636 and the latitude is

    344912. The total area for the power plant is approximately 100mu (Around 6667 m2). The project is

  • 8/13/2019 25 MW Biomass Plant China_CDM

    6/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 6

    located in a flat area nearby the main roads; therefore the transportation is very convenient. The main

    transportation of the straw from the field to the collection stations is by carriage. The straw originatesfrom the local Shanxian farmers. Shanxian is a designated poverty county at the provincial level. The

    intermediate-trader agency has not been established yet. At this stage, farmers have to deliver the biomass

    residues directly to the collection points by themselves.

    The project location was chosen considering the main local wind direction in Shanxian, the future

    enlargement of workshops, and the need to comply with the EIA (Environmental Impact Assessment)

    requirements. There is no large enterprise or natural scenic site located in the near area. On the opposite

    side of the power plant, an area of 50 mu (33333 m2) has been allocated for the ashes from the plant. It is

    estimated that approximately 3 to 5 percentage of the biomass amount will turn into ashes depending on

    the different types of biomass. Consequently, the annual production of ashes from this power plant will be

    around 4000 tonnes to 6600 tonnes. The power plant staff will pack the ash from the incineration and

    deliver it back to the farmers who will use it as fertilizer.The project is located in Southwest of Shandong province, which is located in Northern China. The

    climate in Shanxian is mild and the area is situated in the warm temperate zone, with a semi-humid

    continental climate. The annual precipitation is around 650mm and the annual average temperature is

    13.9oC. There is no possibility of natural disasters such as flooding, earthquake etc happening in the

    project site area according to the long term analysis.

    A.4.2. Category(ies) of project activity:

    >>

    Sectoral Scope: Energy Industries (renewable / non-renewable sources)

    Category: Renewable electricity in grid connected applications

    A.4.3. Technology to be employed by the project activity:

    >>

    This project was approved by National Development and Reformation Commission on 20/09/2004 and

    put into trial operation on 02/10/2006. At the moment of the writing of this version of the PDD, the

    project is in full operation.

    The project entails the establishment of a biomass fired power plant with a rated capacity of 25MWe and

    a maximum capacity of 30MWe. The estimated annual electricity generation is 150Gwh. Approximately

    15% of the power generated will be utilized on the site itself (10% for boiler operation and 5% for

    others). Supply to the power grid therefore equals 127.5Gwh annually.

    The system consists of single extraction steam turbine, with a 1*130t/h vibrating chain type high-temperature, high-pressure boiler, and steam circulation by forced-air cooling. As soon as the heating

    network is established in the town, the heating supply will also be prepared, however the heating supply

    component is not considered part of this project activity.

    The biomass power plant will be connected to the public electric transmission grid, and electricity will be

    used as a must-run resource. The power price for the purchases by the local power company has not

    finally been agreed yet.

  • 8/13/2019 25 MW Biomass Plant China_CDM

    7/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 7

    The main fuel supply is cotton straw, paddy hull, and peanut shell (it is anticipated that paddy hull andpeanut hull will only account for a small percentage of total fuel supply) which are bought from local

    farmers directly. In the project region cotton straw is considered to be abundant resources. The biomass

    resources are only utilized to a very limited degree at the present time. Most of the farmers utilize cotton

    straw as fuel for cooking. The percentage of biomass that is already utilized is approximately 10% from

    the total available biomass resources, according to the project developer's investigations. The majority of

    the biomass amount is left on the field to decay naturally.

    The plant is designed to handle wood chips as well as corn straw, paddy hull and peanut shell, mainly

    including bark, branch, and firewood residue. The biofuel will be cut into pieces of a maximum length of

    3.937in and transported to the plant from the individual collection points. There are eight collection

    points constructed for supplying the biofuel to the plant according to the biomass resources in Shanxian.

    Inside of each individual collection point, there are three major components: the primary storage cabin,the cutting facility plant and secondary storage cabin from where the cut biomass will be transported to

    the power plant.

    The transportation of the biofuel would be sub-contracted with a local logistics firm by the project entity.

    All the trucks utilized for the biofuel transportation are dedicated vehicles belonging to the power plant.

    Different types of biofuel would be transported separately when delivering from collection points to the

    plant site. The total storage capacity of all the 8 collection points is 80,000 tonnes.

    Even though the plant has been put in operational in November, 2006, the cotton collection by the power

    plant staff and storage was already initiated in April, 2006. This is due to the fact that the cotton

    collection season starts late November. The total storage amount was approximately 50,000 tonnes before

    the first firing of the power plant.

    At the plant the fuel is unloaded in a receiver bunker and from there the handling is automatically

    controlled. First, the fuel is stored in a large storage building which can accommodate approximately a

    biomass amount for 5-7 days of burning, and from there it is automatically reclaimed and transported to

    two small buffer silos in the boiler building. The buffer silos will control the feeding of the boiler. The

    burning system will be a vibrating water-cooled grate. The boiler is a three-pass steam boiler designed to

    generate steam at 540oC and 92 Bar. The air pre-heating will be done with hot feed water which will be

    reheated in a flue gas cooler and returned to the feed water tank. By doing this an outlet temperature of

    130oC and a boiler efficiency around 90% will be achievable under optimal operation condition. The flue

    gas cleaning will be by a fabric filter for particles. Due to low content of sulphur in the flue gas, no

    scrubber is needed in this project.

    The boiler is designed in Denmark according to EN rules. This design has then been adjusted to follow

    the Chinese GB rules meaning certain materials have been changed and the strength and thickness of

    some pipes have been changed. Also the set-up regarding safety valves has been changed. All these

    changes are only related to safety requirements from the authorities. All functional design is as designed

    and earlier installed in Europe.

    Using straw as fuel mainly causes massive problems with fouling (build up of slag in the boiler). Based

    on the Danish experience there is no way to avoid this and therefore the design of the boiler has taken this

    into consideration. As the specific measures are part of the patent and expertise the supplier do not wish

    to detail this explanation but as the Danish technology partner has build several straw fired power plants

  • 8/13/2019 25 MW Biomass Plant China_CDM

    8/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 8

    in Europe (Ely in UK, Sanguesa in Spain, Maribo, Masnedoe and Rudkoebing in Denmark) following the

    same principles they do not expect problems with fouling.

    Chlorine can also cause heavy corrosion in the outlet of the boiler (where the flue gas is cold). This

    problem has also been severe on some of the references in Europe. In the newest designs the problem has

    however been solved by the combination of the flue gas cooler and air preheater.

    The fuel handling system is based on handling systems for wood chips as have been installed on

    numerous Scandinavian power plants. The boiler system is based on design from the Danish company

    BWE and is similar to what has been installed on a number of straw fired and wood fired power plants in

    Europe. The turbine and generator will be supplied by Chinese suppliers and so will all the auxiliary

    equipment.

    A.4.4.Estimated amount of emission reductions over the chosen crediting period:

    Please indicate the chosen crediting period and provide the total estimation of emission

    reductions as well as annual estimates for the chosen crediting period. Information on theemission reductions shall be indicated using the following tabular format.

    Years Annual estimation of emission reductions

    in tonnes of CO2e

    15/05/2007 79,439

    2008 127,102

    2009 127,102

    2010 127,102

    2011 127,102

    2012 127,102

    2013 127,102

    15/05/2014 47,663

    Total estimated reductions

    (tonnes of CO2e) 889,716

    Total number of crediting years 7

    Annual average over the crediting period of

    estimated reductions (tonnes of CO2e)

    127,102

    A.4.5. Public funding of the project activity:

    >>

    There is no public funding from Annex I countries for the construction of the Shanxian biomass powerplant project. The only public funding from the Annex I countries is for the preparation of the PDD,

    which is financed by the Danish Ministry of Foreign Affairs.No existing official development assistance (ODA) from Annex I countries is involved in the proposed project.

  • 8/13/2019 25 MW Biomass Plant China_CDM

    9/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 9

    SECTION B. Application of a baseline and monitoring methodology:

    B.1. Title and reference of the approved baseline and monitoring methodology applied to the

    project activity:

    >>

    ACM0006" Consolidated Baseline Methodology for grid-connected electricity generation from biomass

    residues" (Version 04, EB27), in conjunction with "Consolidated monitoring methodology for grid-

    connected electricity generation from biomass residues".

    ACM0006 refers to the ACM 0002 "Consolidated baseline methodology for grid-connected electricity

    generation from renewable sources"(Version 06, 19/05/2006) and the latest version of the "Tool for the

    demonstration and assessment of additionality". More information about the methodology can be found onthe website: http://cdm.unfccc.int/methodologies/approved.

    B.2. Justification of the choice of the methodology and why it is applicable to the project

    activity:

    >>

    There are generally four project activities included in this methodology application area which are

    followings:

    The installation of a new biomass power plant at a site where currently no power generation

    occurs (Greenfield power projects);

    The installation of a new biomass power generation unit, which is operated next to existing power

    generation capacity fired with either fossil fuels or the same type of biomass residue as in theproject plant (Power capacity expansion projects);

    The improvement of energy efficiency of an existing power generation plant (Energy efficiency

    improvement projects);

    The replacement of fossil fuels by biomass in an existing power plant (Fuel switch projects).

    As previously described, the Project is mainly based on two complementary activities as following:

    The collection and acted as biomass resources for power generation

    The generation and supplying of electricity to the regional grid system, thus displacing a certainamount of fossil fuels used for electricity generation.

    Therefore, this Shanxian Biomass power plant project obviously belongs to the Greenfield PowerProjects which listed in the first of the four activities.

    The methodology ACM0006 allows for development of projects falling under 4 conditions:

    Condition 1: No other biomass types than biomass residues (Defined as biomass that is a by-product, residue or waste stream from agriculture, forestry and related industries), as defined

    above, are used in the project plant and these biomass residues are the predominant fuel used in

    the project plant;

    Condition 2: For projects that use biomass residues from a production process, theimplementation of the project should not result in an increase of the processing capacity of raw

    input or in other substantial changes in process;

    Condition 3: The biomass used by project facility should not be stored for more than one year;

  • 8/13/2019 25 MW Biomass Plant China_CDM

    10/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 10

    Condition 4: No significant energy quantities, except from transportation of the biomass, are

    required to prepare the biomass residues for fuel combustion.

    The situations of proposed Shanxian biomass direct burning power plant are as following:

    The biomass which will be utilized in the proposed power plant are mostly from the dumped oruncontrolled burning in the field, and the biomass straws are utilized as the predominant fuel

    supplying for the power plant. Therefore, this is fulfilling the condition 1;

    The biomass residues of bark, branch, and firewood residue are waste from wood processing, theimplementation of the proposed project would not result an increase of the processing capacity of

    raw input or in other substantial changes in wood processing. Other biomass residues (cotton straw,

    paddy hull, peanut shell) are directly from the agriculture, not from production process. Therefore it

    fulfils the condition 2;

    Since there would be a professional logistics company responsible for the biomass transportation,and mainly based on the requirements of moisture and ash contents, the storage time of the biomass

    residues will not be over 1 year, therefore , it fulfils the condition 3;

    There is not significant energy quantities, except from transportation of the biomass are required toprepare the biomass residues for fuel combustion, which also fulfils the condition 4.

    Based on the above analysis, it can be conclude that the project therefore fulfils all the conditions as

    defined above, hence ACM0006 was thought to be the most appropriate methodology for this project.

    In this case a baseline methodology for electricity and or thermal energy displaced shall be an approved

    one used which is ACM 0006 as explained before, including the ACM 0002 "Consolidated Methodology

    for Grid-Connected Power Generation from Renewable Sources".

    The proposed project can meet the applicability criteria of the baseline methodology (ACM0002),

    therefore, the methodology is applicable to the proposed project.

    The proposed project is a grid-connected zero-emission renewable power generation activity frombiomass source;

    The proposed project is not an activity that involves switching from fossil fuels to renewableenergy at the proposed project site.

    The power grid (the North China Power Grid) which the proposed project is to be connected to isclearly identified and information on the characteristics of this grid is publicly available.

    The additionality of the proposed project can be verified using Tools for the demonstration andassessment of additionality requested by the baseline methodology (ACM0002).

    B.3. Description of how the sources and gases included in the project boundary:

  • 8/13/2019 25 MW Biomass Plant China_CDM

    11/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 11

    Overview on emissions sources included in or excluded from the project boundarySource Gas Justification / Explanation

    CO2 Included Main emission source

    CH4 Excluded Excluded for simplification as per the methodology applied.

    This is conservative.

    Grid electricity

    generation

    N2O Excluded Excluded for simplification as per the methodology applied.

    This is conservative.

    CO2 Excluded It is assumed that CO2 emissions from surplus biomass

    residues do not lead to changes of carbon pools in the

    LULUCF sector.

    CH4 Included Project participants decide to include this emission source,since the case B1 has been identified as the most likely

    baseline scenario.

    Baseline Uncontrolled

    burning or decay of

    surplus biomass

    N2O Excluded Excluded for simplification as per the methodology applied.

    This is conservative. Note also that emissions from natural

    decay of biomass are not included in GHG inventories as

    anthropogenic sources.

    CO2 Included An important emission source.

    CH4 Excluded Excluded for simplification as per the methodology applied.

    This emission source is assumed to be very small.

    On-site fossil fuel

    consumption due to

    the project activity

    (stationary or

    mobile)

    N2O Excluded Excluded for simplification as per the methodology applied.This emission source is assumed to be very small.

    CO2 Included An important emission source.

    CH4 Excluded Excluded for simplification as per the methodology applied.

    This emission source is assumed to be very small.

    Off-site

    transportation of

    biomass

    N2O Excluded Excluded for simplification as per the methodology applied.

    This emission source is assumed to be very small.

    CO2 Excluded It is assumed that CO2 emissions from surplus biomass do not

    lead to changes of carbon pools in the LULUCF sector.

    CH4 Included This emission source must be included because CH4 emissions

    from uncontrolled burning or decay of biomass in the baselinescenario are included.

    Combustion of

    biomass for

    electricity and / or

    heat generation

    N2O Excluded Excluded for simplification as per the methodology applied.

    This emission source is assumed to be very small.

    CO2 Excluded It is assumed that CO2 emissions from surplus biomass do not

    lead to changes of carbon pools in the LULUCF sector.

    CH4 Excluded Excluded for simplification. Since biomass is stored for not

    longer than one year, this emission source is assumed to be

    small.

    ProjectActivity

    Biomass storage

    N2O Excluded Excluded for simplification. This emission source is assumed

    to be very small.

  • 8/13/2019 25 MW Biomass Plant China_CDM

    12/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 12

    B.4. Description of how thebaseline scenariois identified and description of the identified baseline

    scenario:>>

    The methodology will be applied using Green Field Power Projectactivity and all the four conditions

    listed under the ACM 0006 are fulfilled.

    Based on the ACM0006, realistic and credible alternatives should be separately determined regarding:

    How Power would be generated in the absence of the CDM project activity;

    What would happen to the Biomass in the absence of the project activity;

    In case of cogeneration projects: how the Heat would be generated in the absence of the projectactivity.

    Baseline Scenario

    P1 The proposed project activity not undertaken as a CDM project activity;

    P2 The proposed project activity (installation of a power plant), fired with the same type of biomass but

    with a lower efficiency of electrical generation (e.g. an efficiency that is common practice in the relevant

    industry sector);

    P3 The generation of power in an existing plant, on-site or nearby the project site, using only fossil fuels;

    P4 The generation of power in existing and/or new grid-connected power plants;

    P5 The continuation of power generation in an existing power plant, fired with the same type of biomass

    as (co-)fired in the project activity, and implementation of the project activity, not undertaken as a CDM

    project activity, at the end of the lifetime of the existing plant;

    P6 The continuation of power generation in an existing power plant, fired with the same type of biomass

    as (co-)fired in the project activity and, at the end of the lifetime of the existing plant, replacement of thatplant by a similar new plant.

    It can be found that in proposed Shanxian biomass direct burning project:

    P2 The proposed project is the first biomass direct burning power plant in Shandong province, therefore

    there is no other power plant fired with the same type of biomass but with a lower efficiency of electrical

    generation, so P2 is not suitable alternative;

    P3 There is no existing plant onsite or nearby the project site only using fossil fuels generating power

    currently, so P3 is not suitable alternative;

    P5 There is no continuation of power generation in an existing power plant, fired with same type of

    biomass as in the project activity, and implementation of the project activity not undertaken as a CDM

    project activity at the end of the lifetime of the exiting plant, so P5 is not suitable alternative;P6 There is no replacement of the existing power plant at the end of the lifetime, by a similar new plant,

    the existing power plant would continue generate power, fired with the same type of biomass as fired in

    the project activity, so P6 is not suitable alternative.

    First, during the identification of the baseline scenario for power generation, the realistic and credible

    alternative was chosen as P1: The proposed project activity not undertaken as a CDM project

    activity; andP4: The generation of power in a new grid connected power plant.

    For the use of biomass, the realistic and credible alternative(s) may include, inter alia:

  • 8/13/2019 25 MW Biomass Plant China_CDM

    13/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 13

    B1 The biomass residues are dumped or left to decay under mainly aerobic conditions. This applies, for

    example, to dumping and decay of biomass residues on fields.B2 The biomass residues are dumped or left to decay under clearly anaerobic conditions. This applies, for

    example, to deep landfills with more than 5 meters. This does not apply to biomass residues that are

    stock-piled or left to decay on fields.

    B3 The biomass residues are burnt in an uncontrolled manner without utilizing it for energy purposes.

    B4 The biomass residues are used for heat and/or electricity generation at the project site;

    B5 The biomass residues are used for power generation, including cogeneration, in other existing or new

    gird-connected power plants;

    B6 The biomass residues are used for heat generation in other existing or new boilers at other sites

    B7 The biomass residues are used for other energy purposes, such as the generation of biofuels

    B8 The biomass residues are used for non-energy purposes, e.g. as fertilizer or as feedstock in processes.

    According to the Biomass Supply / Demand Investigation Report in Shanxian County carried out byShandong Electric Power Engineering Consulting Institute in March 2007, the proposed project utilizes

    biomass residues from agriculture, mainly including cotton straw, paddy hull, and peanut hull; and also

    by-product from wood processing, including bark, branch, and firewood residue. Similar analysis would

    be done for the biomass alternatives as power generation for the proposed Shanxian project:

    B1 This is the scenario that happens around the site of the proposed project, a certain number of surplus

    biomass residues would be dumped or left to decay Thus B1 is the suitable alternative;

    B2 There is no landfill around the site of the proposed project, hence, the unused biomass residues are

    impossible dumped or left to decay under clearly anaerobic conditions. So B2 is not suitable alternative;

    B3 This is the scenario that happens around the site of the proposed project, a certain number of surplus

    biomass residues would be burned uncontrolled outside without utilization it for energy purpose,

    therefore B3 is the suitable alternative;

    B4 The proposed project is the first biomass generation project in China 2. Therefore biomass is not usedfor heat or power generation currently, so B4 is not suitable alternative;

    B5 The proposed project is the first biomass generation project in China. So B5 is not suitable alternative;

    B6 There is no biomass boiler using biomass residues as fuel close to proposed project. Considering the

    cost of biomass transpiration, other existing or new boilers at other places will not use these surplus

    biomass residues. So B6 is not suitable alternative;

    B7 There is no other energy generation project that has needs to the surplus biomass residues consumed

    by the proposed project., so B7 is not suitable alternative;

    B8 There is only a little amount of biomass residue that has been used as fertilizer around the project site,

    however, biomass residues used by the proposed project will not impropriate the biomass as fertilizer,

    since the biomass consumption of the proposed project is from the local surplus biomass residues of the

    area., so B8 is not suitable alternative.

    In conclusion, for the use of biomass, the realistic and credible was chosen as B1 and B3: The biomass

    residues are dumped or left to decay under mainly aerobic conditions and burnt in an uncontrolled

    manner without utilizing it for energy purposes. According to the biomass resource investigation study

    done by National Bio Energy Co.,Ltd. and local authority, the current biomass utilization structure will

    not change after the proposed project operation.

    2http://www.most.gov.cn/dfkjgznew/200510/t20051018_25472.htm

  • 8/13/2019 25 MW Biomass Plant China_CDM

    14/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 14

    If the proposed project activity is the cogeneration of power and heat, project participants shall define the

    most plausible baseline scenario for the generation of heat. For heat generation, realistic and crediblealternative(s) may include, inter alia:

    H1 The proposed project activity not undertaken as a CDM project activity

    H2 The proposed project activity (installation of a cogeneration power plant), fired with the same type of

    biomass but with a different efficiency of heat generation (e.g. an efficiency that is common practice in

    the relevant industry sector)

    H3 The generation of heat in an existing cogeneration plant, on-site or nearby the project site, using only

    fossil fuels

    H4 The generation of heat in boilers using the same type of biomass residues

    H5 The continuation of heat generation in an existing cogeneration plant, fired with the same type of

    biomass as in the project activity, and implementation of the project activity, not undertaken as a CDM

    project activity, at the end of the lifetime of the existing plant

    H6 The generation of heat in boilers using fossil fuelsH7 The use of heat from external sources, such as district heat

    H8 Other heat generation technologies (e.g. heat pumps or solar energy)

    The heating part in the proposed project is not considered in the emission reduction calculation based on

    the conservative principle.

    Therefore, we could find that Scenario 2 which is listed in ACM 0006 Table 1: Combinations of project

    types and baseline scenarios applicable to this methodology, is the right scenario for this project. It

    is described like following:

    The project activity involves the installation of a new power plant at a site where currently nopower generation occurs;

    The power generated by the project plant is fed into grid and would in the absence of the projectactivity be purchased from the grid;

    The biomass would be in the absence of the project activity be dumped or left decay or burned inan uncontrolled manner without utilizing for energy purposes;

    Baseline ScenarioScenario Project Type

    Power Generation Use of biomass Heat Generation

    2 Power Greenfield

    Project

    P4 B1, B3 No Heat now

    Table 1 Identification of Scenario combined with Power, use of biomass and heat generation method for

    Shanxian 1*25MW biomass power plant

    B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below those that

    would have occurred in the absence of the registered CDMproject activity (assessment and

    demonstration of additionality):

    >>

    Approved Tool for the Demonstration and Assessment of Additionality applied in ACM0002 is used to

    demonstrate and assess the additionality of the proposed project in the following steps:

    Step 0 Preliminary screening based on the starting date of the project activity

    The crediting period of the proposed project will not start before the registration of the project activity

    because the starting date of project does not fall between 01/01/2000 and the date of registration as CDM

    project.

  • 8/13/2019 25 MW Biomass Plant China_CDM

    15/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 15

    Step 1 Identification of alternatives to the project activity consistent with current laws andregulations

    Four alternatives are selected as the power generation options in the following table, and the analysis of

    these alternatives whether consistent with current laws and regulations are shown as well.

    Sub Step 1a. Define alternatives to the project activity

    Alternatives to power generation:

    1. Construction of a coal

    firing plant with the same

    power generation capacityequivalent to the proposed

    project activity

    Based on this scenario assumed, the dominating newly installed

    power generation is coming from the thermal firing plants which

    are the normal project behaviour at present time in North ChinaPower Grid system. From the new addition power capacity from

    2002 to 2004 which are the most present statistics, the new

    addition power generation is over 90% from thermal plants.

    Furthermore, it is not possible to build the power plant with the

    same scale under the current Chinese existing new power

    addition regulatory framework. Since it is not allowed to build

    the coal firing power plant smaller than 135MW under the

    current Chinese legislations.

    Therefore, the alternative fossil fuel power plant building with

    the same power generation capacity is not possible to happen

    under the current Chinese laws and legislations for power plants.

    2. Supply of equivalent

    annual power output by the

    Grid where the proposed

    project is connected to

    There is power addition annually from 2002 to 2004 in North

    China Grid Network; therefore it is mostly from the thermal

    generation. The alternative is a feasible scenario to be selected as

    the baseline for the proposed project.

    3. The proposed project

    activity not undertaken as a

    CDM project activity

    The IRR of project is too low if there is no income from CERs.

    So this alternative is not applicable.

    Alternatives to biomass usage:

    The proposed project utilizes the current dumped biomass straws for power generation. According to the

    identified baseline scenario will the biomass utilized in the proposed power plant alternatively be used inan uncontrolled way such as dumped and left to decay or burned in open air.

    Sub Step 1b. Enforcement of applicable laws and regulations:

    For the scenario 1, it will not occur under the current applicable laws and regulations in force. Detailed

    reference is the China Power Yearbook 2003, 2004 and 2005 and relative rules for the new establishing

    power plants.

    Scenario 2 is clearly consistent with the prevailing laws and regulations, since there in the North China

    Grid is a demand for new power addition to ensure the growing industrial and commercial purposes in

    this area.

  • 8/13/2019 25 MW Biomass Plant China_CDM

    16/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 16

    Step 2 Investment analysis

    According to the identified Additionality Assessment Tool for the proposed project, this step has todetermine whether it is financially less attractive than other alternatives without the revenues deriving

    from CERs payment.

    Sub Step 2a Determine appropriate analysis method

    The three analysis methods suggested by Tool for the demonstration and assessment of additionality are:

    Option I simple cost

    analysis

    Since there are both revenues of power price and CERs

    payment, this option is not appropriate to calculate.

    Option II investment

    comparison analysis

    This option is only applicable to the case where the

    alternative baseline scenario is similar to the proposed

    project, so that the comparative analysis can be

    conducted. However, the proposed baseline scenario is theNorth China Grid which is not similar to the suggested

    project.

    Option III benchmark

    analysis

    When both benchmark IRR and total investment IRR of

    proposed project are available, this method can be used.

    Sub Step 2b Apply benchmark analysis

    Chinese power industry very commonly use 8% as the financial benchmark rate of return (after tax) of the

    total investment and this is also used in the feasibility study report. This threshold value of project

    financial assessment is based on the Interim Rules on Economic Assessment of Electric Engineering

    Retrofit Projects.

    Sub Step 2c Calculation and comparison of financial indicators

    Power generation capacity 25MW

    Annual power net output 127.5GWh

    Project lifetime Total 22 years including 1 year

    construction time

    Total project investment 294,184,100 RMB

    Tariff RMB 0.66 Yuan/KWh (excluding VAT)

    Biomass purchasing price 300 RMB/tonne

    Annual Operating hours 6000 hours/year

    Tax 33% income taxEmission reduction crediting period 21 Years

    Expected CERs price 8 Euro/tCO2eqor above

    NPV (Total investment, discount

    factor = 8%) million RMB

    IRR (Total investment,

    benchmark = 8% )

    With CERs revenue 58.5 mill RMB 11.0

    Without CER revenues -41.3 mill. RMB 5.6

  • 8/13/2019 25 MW Biomass Plant China_CDM

    17/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 17

    Data input for financial sensitivity analysis:

    Capacity 25 MW

    Operation hours 6,000 hours/year

    Own consumption 15%

    Total production 127,500 MWh/year

    Tariff 0.410 RMB/kWh

    Tariff Subsidy 0.250 RMB/kWhIncome from power sale 84,150,000 RMB/year

    CERs from power 125,275 CERs

    Unused biomass basel. 4,939 CERs

    Total project emissions 3,111 CERs

    CER per year 127,102 CERs

    Price per CER 8.00 Euro/tons

    Exchange rate 10.00 RMB/Euro

    Income from CERs 10,168,186 RMB/year

    Biomass demand 132,000 tons/year Dry Biomass Residue 119,315 tons/year

    Biomass price 300 RMB/tons

    Expense from purchase 39,600,000 RMB/year

    Staff and maintenance 5% of investment

    Other O&M 14,709,205

    Total Investment 294,184,100 RMB/year

    Biomass Consumption 22 tonnes/hour

    Emission Factor 0.983 tons CO2/MWh

    The above table shows the critical financial benchmark indicators and compares the situations with and

    without CER revenues. It is clear that the proposed project faces great financial barriers. Therefore, CDM

    revenues are necessary to make the proposed project financially viable for investors.

    Sub Step 2d Sensitivity analysis

    The sensitivity analysis is conducted in order to measure the influence on the IRR and NPV due to the

    changes of key financial parameters such as biomass purchasing price, power generation connected to

  • 8/13/2019 25 MW Biomass Plant China_CDM

    18/72

  • 8/13/2019 25 MW Biomass Plant China_CDM

    19/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 19

    On the other hand then the above figure shows clearly that CER revenues will make the proposed project

    attractive compare with the usual rate of return (8%).

    Step 3 Barrier analysis

    Sub Step 3a Identify barriers that would prevent the implementation of type of the proposed

    project activity

    Investment barriers:

    Cost disadvantages compared to coal-fired power plants

    China is an enormous country with an abundant amount of biomass resources. However, until recently

    there has been no development of biomass power plants in China. In comparison with coal-fired power

    plants in China, the costs of building a biomass plant with same power generation capacity are muchhigher.

    Uncertainties in the green electric price policy in China.

    The kWhe price is the most important and critical parameter if biomass technology in the scale of 5 to 30

    MWe has to be made viable. Although currently, the Chinese central government is encouraging the

    renewable energy utilization, the price list and transparent supervising system/mechanisms for any

    renewable energy laws or regulations for this green power generated from biomass power plants are not

    clear at the moment. The price for power wheeled into local or regional grid network is largely

    determined by the local commodities office.

    Risk of a new technology

    Furthermore, the high risks associated with this brand new technology implementation in China would in

    large scale influence the investment return payment. Especially for the first demonstration project in a

    national scope, there are even higher financial risks for the project developers. With reference to the same

    unit investment cost for coal firing power plants the investment return over time for the build of a

    biomass power plant of the same scale has a much longer investment return time.

    Technology barriers:

    To decide whether a biomass power plant is successful or not mainly depends on the availability ofbiomass materials. For the main reason that biomass source availability is highly subject to seasonal

    fluctuations due to the vagaries of the natural environment. Although, the project developer National

    Bio Energy Co., Ltd estimated the amount of the available bio fuel to be sufficient, in the long term

    continuous supply of sufficient quantities of biomass fuels is not assured over the life time of theplant. It is obvious that the viability of the biomass power plant is much less certain than that of fossil

    fuel plants, which could enjoy an assured and regulated supply of fuels;

    Biomass resources are widely dispersed in small quantities at the project site. Therefore, thecollection and transportation of large amounts of biomass materials to the project site or the closest

    collection point becomes a constraint. Apart from this, then it is also expected that the expenses for

    collection and transportation will increase due to increased labour and transportation costs;

    Another major problem is the storage of biomass. Unlike the normal thermal power plant, a biomassfiring plant has to consume much larger quantities of fuel, which is rather difficult to ensure during

    the operation period of the plants lifetime. The characteristics of biomass fuels change quickly

    within a short period of time. The most critical parameter is the calorific value decrease due to the

    volatility and deterioration of biomass, which affects the performance of the power plant equipment.

  • 8/13/2019 25 MW Biomass Plant China_CDM

    20/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 20

    For this reason, biomass material can not be stored for long periods. Fuels that enter the plants

    premises must be consumed on a first-come first-burn basis. It is not possible to stock biomassmaterials seasonally. In addition, the low bulk density (weight per unit volume) makes it difficult to

    handle and store biomass materials;

    The biomass price in the local market will continuously fluctuate because of seasonable variations,which results in very unstable expenditures for operation and power generation The biomass

    purchasing price is crucial for a sustainable operation process since approximately 70% to 80% of the

    estimated total operation cost come from purchasing bio fuel;

    Biomass power generation is a relatively new technology compared to the common technology forfossil fuel power plants, and at this stage no biomass power plants have been in operation in China.

    Therefore, the effects from combusting biomass during the plant life cycle is not known;

    The biomass power conversion efficiency is low compared to the efficiency of fossil fuel energyconversion;

    Due to the relatively small capacity of the plant, any change in the electricity tariff structure willgreatly affect the plant's financial performance.

    Barrier of the first of its kind type

    When the project was initiated, no other biomass power plant of this size had been constructed in China.

    Therefore, the project experienced a first of its kind barrier. This barrier contains some overlap with the

    technological barrier and commercial and financial barrier mentioned above.

    Sub Step 3b Show that the identified barriers would not prevent the implementation of at least one

    of the alternatives except the proposed

    The coal fired power technology is well developed, fully commercialised, is a mature technology, and is

    in fact the dominant technology. China is one of the countries with very rich coal resources, hence the

    previous technology and investment barriers of the proposed project activity will not be applicable to the

    coal fired power plants. Therefore, the identified barriers do not apply to at least one of the alternatives to

    the project scenario.

    Step 4 Common practice analyses

    The main purpose of this analysis is to compare the proposed project activity with the current common

    practice and to analyze whether the proposed project is not common practice in China.

    Sub Step 4a Analyze other activities similar to the proposed project

    There is no other biomass power plant or biomass cogeneration power plant built in China. The Shanxianproject will function as a full scale test project for biomass generation in China. The technology used in

    the proposed project has not been used in China before, thus the project would introduce new technology

    to China and thereby promote the utilisation of renewable resources.

    It can be concluded that the proposed project is not common practice in China but a "first of its kind"

    project.

    Sub Step 4b Discuss any similar options that are occurring

    As already described in the statement above, currently there are no similar projects or proposed projects

    in China.

    Step 5 Impact of CDM registration

  • 8/13/2019 25 MW Biomass Plant China_CDM

    21/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 21

    Biomass power generation and cogeneration technology is a new energy utilization method in China. The

    successful implementation of this new project activity will depend on overcoming financial andtechnological challenges. The new technology will be introduced in cooperation with the Danish

    company BWE and other experienced Scandinavian companies. As for the CDM registration, it will be

    submitted in cooperation with the Danish Consulting Company COWI who will also monitor the

    technical and financial performance of this proposed project.

    Danish experts of the biomass boiler from BWE and other experienced Scandinavian companies would

    help to transfer the advanced biomass technology into the Chinese market, and speed-up transfer of

    technology to the local market. This involves necessary training in project development, plant operation,

    maintenance and biomass resource supplying chain. The CDM revenues will contribute to overcome the

    barriers mentioned above through reducing the financial and commercial risks of, and increasing the

    financial and commercial return to the project.

    B.6. Emission reductions:

    >>

    B.6.1. Explanation of methodological choices:

    Emission Reduction

    As described in the accompanying baseline methodology, the emission from grid electricity generation is

    considered for the baseline.

    yER =ERelectricity,y+ BE biomass,y- PEy- Ly

    where:

    ERelectricity,y are the emission reductions due to displacement of electricity of heat during the year y in tons

    of CO2;BE biomass,y are the baseline emissions due to natural decay of biomass during the year y in tons of CO2equivalents;

    PEy are the project emissions during the year y in tons of CO 2

    Ly are the leakage emissions during the year y in tons of CO 2

    Project emissions

    It includes:

    CO2 emissions from transportation of biomass to the project site (PETy),

    CO2emissions from on-site consumption of fossil fuels due to the project activity (PEFF y) and,where this emission source is included in the project boundary and relevant,

    CH4emissions from the combustion of biomass (PEBiomass,CH4,y)

  • 8/13/2019 25 MW Biomass Plant China_CDM

    22/72

  • 8/13/2019 25 MW Biomass Plant China_CDM

    23/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 23

    ygirdyPJyEC EFECPE ,,, = PEEC,yare the CO2emissions during the year ydue to electricity consumption at project site that

    is attributable to project activity

    ECPJ,y:Onsite electricity consumption attributable

    to project activity during the year y,

    EFgrid,y: CO2emission factor for grid electricity

    during the year y.

    =

    i

    iyi

    CHCHBiomass

    NCVBF

    EFPE

    ,

    44,

    PEBiomass,CH4: Project emissions from the power

    plant(tCO2/year)

    EFCH4:Biomass methane emission factor(tCH4/TJ)

    BFi,y:Biomass type I utilized in power plant

    (tonnes/year)

    NCVi:Net Calorific Value of type I biomass

    (TJ/tonnes)

    Emission reductions due to displacement of electricity

    yyelectricityyyelectricit EFEGER ,, =

    Where:

    ERelectricity,y are the emission reductions due to displacement of electricity during the year y in tons ofCO2,

    EGy is the net quantity of increased electricity generation as a result of the project activity (incremental to

    baseline generation) during the year y in MWh,

    EFelectricity,y is the CO2emission factor for the electricity displaced due to the project activity during

    the year y in tonsCO2/MWh.

    Step 1: Determination of EFelectricity,y

    The project activity displaces electricity from other grid-connected sources (P4). Apart from co-firing

    fossil fuels in the project plant, where relevant, electricity is not generated with fossil fuels at the project

    site. The emission factor for the displacement of electricity should correspond to the grid emission factor

    (EFelectricity,y = EFgrid,y) and EFgrid,y shall be calculated as a combined margin (CM) consisting of

    operating margin (OM) and building margin (BM) factors, following the guidance in the sectionBaselines in the Consolidated baseline methodology for grid-connected electricity generation from

    renewable sources (ACM0002), because the power generation capacity of this proposed biomass power

    plant is of more than 15 MW.

    Sub step1a Calculation of Operating Margin Emission factor EFOM,yCalculation of OM emission factor should be based on one of the following four methods:

    (a) Simple OM, or

    (b) Simple adjusted OM, or

    (c) Dispatch Data Analysis OM, or

    (d) Average OM.

  • 8/13/2019 25 MW Biomass Plant China_CDM

    24/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 24

    The method (c) If the dispatch data is available, method (c) should be the first methodological choice.This method requires the dispatch order of each power plant and the dispatched electricity generation of

    all the power plants in the power grid during every operation hour period. And it truly depicts the

    substitution relation between proposed CDM project activity and the operation of baseline grid, and also

    the corresponding emission reduction. This method requires the detailed operation and dispatch data of

    power plants in the grid. Because of the institutional reform of separating the plant operation from the

    grid operation in China, there is no publicly available information for the grids and power plants at all

    levels. As the North China Grid is a very large regional grid covering several provinces, it would

    certainly be difficult and costly to obtain the hourly dispatch data. Therefore, the method (c) is not

    applicable.

    The method (b), simple adjusted OM, requires the annual load duration curve of the power grid and the

    load data of every hour data during the whole year on the basis of the time order. Based on the samereason stated in the above paragraph, the necessary data for the method (b) are difficult to obtain, so the

    method (b) is not applicable.

    The method (d), average OM, is used when low-cost/must run resources constitute more than 50% of total

    amount of power generation in the grid. According to the data from NDRC, the total installed capacity of

    the North China Grid in 2004 is 96983.3MW, in which coal-fired installed capacity is 93594.9MW,

    accounting for 96.5%. Therefore, the North China Grid generation system is dominated by coal-fired

    power, and this fact will not change for the next many years. So the method (d) is not applicable.

    Installed capacity and electricity supply on North China Grid, 2000-2004

    Year Installed capacity (%) Electricity supplied (%)

    Thermal Hydro Nuclear Others Total Thermal Hydro Nuclear Others Total

    2000 95 5 0 0 100 99 1 0 0 100

    2001 95 5 0 0 100 99 1 0 0 100

    2002 96 4 0 0 100 99 1 0 0 100

    2003 96 4 0 0 100 99 1 0 0 100

    2004 97 3 0 0 100 99 1 0 0 100

    Source: Calculated on basis of data in China Electric Power Yearbook, several years.

    The Simple OM method (a) is used when low-cost/must run resources constitute less than 50% of total

    amount of power generation in:(1) Average of the five most recent years, or

    (2) Based on long-term normal for hydroelectricity production.

    Low operating cost and must run resources typically include hydro, geothermal, wind, low-cost biomass,

    nuclear and solar generation. If coal is obviously used as must-run, it should also be included in this list,

    i.e. excluded from the set of plants. From the description of method (d), the share of the low cost/must run

    resources in the North China Grid from 2001, 2002 and 2004 are 4.55%, 4.24%, and 3.49% from the data

    of NDRC, which meets the requirements of method(a). Therefore, it is reasonable to select the method (a)

    to calculate the OM emission factor.

    Therefore, method (a) is applicable for the proposed project.

  • 8/13/2019 25 MW Biomass Plant China_CDM

    25/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 25

    =

    =

    j

    yj

    ji

    iCOiyji

    j

    yj

    ji

    jiyji

    ysimpleOM

    GEN

    OXIDEFNCVF

    GEN

    COEFFEF

    ,

    ,

    ,2,,

    ,

    ,

    ,,,

    ,,

    Fi,j,y: is the amount of fuel I consumed by relevantpower sources j in year y. The index j runs over all

    power sources including imports, but excludes low

    and must run power plants in the connected grid

    system selected in the proposed project activity.

    COEFi,j,y: is the CO2 emission coefficient of fuel I,

    taking into account the carbon content of fuels used

    by relevant power sources j and the percentage

    osidation of the fuel I in year y

    GENj,y: is the electricity delivered to the grid by

    source j in year y

    NCVi:Net Calorific Value of type I of fuel utilized

    (TJ per mass)OXIDi: IPCC 2006 default values of oxidation factor

    of type I fuel utilized

    EFCO2,i: CO2 emission factor per unit of energy of the

    fuel i(tCO2/TJ)

    For the reason that project monitoring is using ex ante method, power data from the past recent three

    years are necessary to obtain from the China electric yearbook 2003, 2004 and 2005 which are statistics

    for power situation from 2002 to 2004. From the fuel consumption from relevant sources in North China

    Grid and the electricity generation by these sources, the average emissions from 2002 to 2004 could be

    obtained. These are divided by the total amount of energy generated, to give the emission rate per MWh.

    Based on the China National Development and Reformation Commission Climate Change Office Notice

    of Chinese Regional Grid Emission Factor, the simple OM emission factor of North China Grid is

    calculated as 1.0585 tCO2/MWh, to see Annex 3 for details.

    Sub Step 1b Calculation of Building Margin Emission Factor EFBM,yAccording to ACM0002, the BM calculation is defined as generation weighted average emissions factor

    of a sample of power plants. However, the data of individual power plant generation and fuel

    consumption is not available in China at present time.

    ACM0002 provides two options for sample group m:

    (1) The five power plants that have been built most recently, or(2) The power plants capacity additions in the electricity system that comprise 20% of the system

    generation (in MWh) and that have been built most recently.

    The one with larger annual generation should be used.

    Due to the reason that the information of the North China Grid on the five power plants built most

    recently is not available. Therefore, the most recently built 20% of the system generation of the new

    power plants capacity addition will be chosen as the sample group m to calculate BM.Based on the DNV

  • 8/13/2019 25 MW Biomass Plant China_CDM

    26/72

  • 8/13/2019 25 MW Biomass Plant China_CDM

    27/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 27

    %20,

    ,

    j yj

    j nyj

    CAP

    CAP

    yThermalEF , is the emission factor of fuel-fired power with Best Practiced Commercialized Technology

    (BPCT). It can be calculated as following equation:

    AdvGASGASAdvOILOILAdvCOALCOALThermal EFEFEFEF ,,, *** ++=

    =

    ji

    jiyji

    jCOALi

    jiyji

    COALCOEFF

    COEFF

    ,

    ,,,

    ,

    ,,,

    *

    =

    ji

    jiyji

    jOILi

    jiyji

    OilCOEFF

    COEFF

    ,

    ,,,

    ,,,,

    *

    =

    ji

    jiyji

    jGASi

    jiyji

    GASCOEFF

    COEFF

    ,

    ,,,

    ,

    ,,,

    *

    Fi,j,yis the amount of fuel I consumed by relevant power sources j province in year ytce;

    COEFi,j,yis the CO2 emission coefficient of fuel I, taking into account the carbon content of fuels used by

    relevant power sources j province and the percentage oxidation of the fuel I in year y.

    EFCOAL,AdvEFOIL,Advand EFGAS,Advis the emission factor of COAL, OIL, GAS-fired power with BestPracticed Commercialized Technology. These variables can be calculated as following table:

    Variables Power

    Supplying

    Efficiency

    Fuel

    combustion

    factortc/TjOxidation

    Rate

    Emission

    Factor

    A B C D=3.6/A/100

    0*B*C*44/1

    2

    Coal-fire

    power plant

    EFCOAL,Adv 36.53% 25.8 0.98 0.9136

    Gas-fire

    power plant

    EFGAS,Adv 45.87% 15.3 0.995 0.4381

    Oil-fire

    power plant

    EFOIL,Adv 45.87% 21.1 0.99 0.6011

    In addition, there is an assumption in this substitute calculation method: the average annual operational

    hours of non fuel-fired power plants are same as those of fuel-fired power plants. But the fact in China is,

    except nuclear power, the former is much less than the latter. Therefore, this substitute calculation method

    is conservative.

  • 8/13/2019 25 MW Biomass Plant China_CDM

    28/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 28

    Based on the China National Development and Reformation Commission Climate Change Office Noticeof Chinese Regional Grid Emission Factor, the average BM emission factor of North China Grid is

    calculated as 0.9066 tCO2/MWh, see Annex 3 for details.

    Sub Step 1c Calculation of Baseline Emission Factor EFyThe baseline emission factor is calculated as a Combined Margin, using a weighted average of the

    Operating Margin and Building Margin.

    ( )MWhtCO

    EFEFEFEFEFyBMyOMyBMBMyOMOMy

    2

    ,,,,

    983.02

    9066.01.0585

    5.05.0

    =+

    =

    +=

    The detailed calculation is in Annex 3.

    It is noticed that the data used for calculation of combined margin is shown in Annex 3 and section D.

    The main source of data is from NDRC. The default values utilized for the calculations of calorific values

    of fuel types and fuel oxidation rate are from the IPCC GHG Gas Inventory Reference Manual 2006.

    The baseline scenario for the proposed project is that electricity would have been generated, and the

    electricity demand met, by the operation of grid connected thermal power plants and by the addition of

    new fossil fuel based power generating. In the proposed project scenario the same power demand is met

    with the project power generation. Because the project uses a renewable source to produce electricity, and

    there are no additional emissions from the proposed project activity.

    Step 2: Determination of EGy

    According to the scenario identified for this proposed project as showed before, EGy corresponds to the

    net quantity of electricity generation in the project plant (EGy= EGproject plant,y), which is the same amount

    as the power fed into the grid by the proposed project activity. The plant own consumption and electricity

    imported from grid are already taken into the calculation of this parameter.

    Baseline emissions

    This methodology assumes that the biomass would have been burned in an uncontrolled manner for both

    baseline scenarios, natural decay or uncontrolled burning. The baseline emissions are calculated by

    multiplying the quantity of biomass that would not be used in the absence of the project activity with the

    net calorific value and an appropriate emission factor as following:

    BEBiomass,y= iCHburningiyiCH iEFNCVBFGWP ,44 ,,

    There is no evident indication that large portion of the biomass resource would be reduced in the

    foreseeable future, the selected methodology uses the baseline emission as unused biomass open air

    burning which equals to the amount of biomass consumed in the proposed power plant. The baseline

    emission calculation is considered to be conservative because the methane emission from the natural

    decay processing of those equivalent biomass residues would cause greater GHG effect than CO2

    emissions GHG effect from open air burning process.

    The more detailed calculation of baseline emission of unused biomass residues is in Annex 3.

    Leakage Estimation

  • 8/13/2019 25 MW Biomass Plant China_CDM

    29/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 29

    Based on the ACM0006, the following two alternatives are shown to estimate the leakage of the proposed

    project: L1:Showing the current natural

    decay or open air burning

    biomass will continue to be

    uncontrolled dumping without

    proposed project performance

    L2:Demonstrate the amount ofbiomass surplus is far more than

    the project biomass demand

    amount

    Alternative 1:

    Demonstrate

    that the

    biomass

    consumption

    of power

    plant will not

    result in

    increased

    fossil fuel

    consumption

    elsewhere.

    L3:Showing the biomasssuppliers can not sell all their

    biomass to the project plant

    Ly=0

    Alternative 2: If it is not possible to demonstrate that the

    biomass consumption in the proposed project will not

    result in an increased usage of more carbon intensive

    fuels then the leakage emissions must be measured and

    deducted from the net project emission reductions.

    k

    iykPJLECOy

    NCVBFEFL = ,,,2 (tCO2)

    The leakage emissions during the year y

    equals to the CO2emission coefficient per

    energy unit of the most carbon intensive fuel

    utilized in the county multiply by the amount

    of type k biomass used as fuel in the project

    plant during the year y and multiply by the

    Net Calorific Value of biomass type k( per

    volume or mass).

    Based on the ACM0006, L2: Demonstrate the amount of biomass surplus is far more than the project

    biomass demand amount, is chosen in the proposed project for demonstration that the quantity of

    available biomass residue of type k in the region is at least 25% larger than the quantity of available

    residues of type k that are utilized.

    Surplus of biomass in the region

    Type of

    biomass

    residue

    Biomass that

    can be

    supplied

    (tonne)

    Biomass

    used by the

    plant

    (tonne)

    Biomass used

    for fertilizing,

    forage and

    cooking etc.

    (tonne)

    Biomass

    surplus

    (tonne)

    Surplus

    percentage (%)

    A B C D=A-B-C E=D/(B+C)*100%

    Bark 241,000 76,434 10,000 154,566 179%

    Cotton stalk 780,000 19,964 188,000 572,036 275%

    Paddy hull 82,000 16,170 20,000 45,830 127%

    Peanut shell 135,000 11,905 32,000 91,095 207%

    Branch 143,000 2,890 56,000 84,110 143%

    Firewood

    residue156,000 52,988 20,700 82,312 112%

    The quantity of biomass that can be supplied, and biomass that is used for fertilizing, forage and cooking

    etc. are from the Biomass Supply / Demand Investigation Report in Shanxian County. As is listed in the

  • 8/13/2019 25 MW Biomass Plant China_CDM

    30/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 30

    above table, the quantities of available biomass of type k (k = cotton straw, paddy hull, peanut shell, bark,

    branch, firewood residue) in the region were all over 100% larger than the quantity of available residuesof type k that were utilized.

    The conclusion is that the proposed power plant will not influence the present biomass utilisation and

    therefore not create any leakage

    It is at the same time anticipated that the current utilisation of residues will drop over the power plants life

    time due to increase income level for the local farmers and inhabitants around the plant.

    Project emission reduction estimation

    Total baseline emissions

    (+)

    Total project

    emissions (-)

    Project Emission

    Reduction( =)

    Unused biomass baselineemission

    GHG emission frombiomass combustion in

    the power plant

    GHG emission from

    fossil fuel combustion

    in the boiler

    Electricity generation

    baseline emission

    GHG emission from

    biomass transportation

    Total baselineemissions - Total

    project emissions

    The detailed calculations of combined emission factor, project emissions, baseline emissions, leakages are

    showed in Annex 3.

    B.6.2. Data and parameters that are available at validation:

    Data / Parameter: GWPCH4

    Data unit: tCO2e/tCH4Description: Global Warming Potential for CH4

    Source of data used: IPCC 2006 default value

    Value applied: 21 for the first commitment period.

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    Any comment: Shall be updated according to any future COP/MOP decisions.

    Data / Parameter: EFOM

    Data unit: tCO2/MWh

    Description: Operating Margin Emission factor

    Source of data used: China National Development and Reformation Commission Climate Change

    Office Notice of Chinese Regional Grid Emission Factor.

    Value applied: 1.0585

    Justification of the

  • 8/13/2019 25 MW Biomass Plant China_CDM

    31/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 31

    choice of data or

    description ofmeasurement methods

    and procedures actually

    applied :

    Any comment: Shall be updated according to DNA's official data updating.

    Data / Parameter: EFBM

    Data unit: tCO2/MWh

    Description: Building Margin Emission Factor

    Source of data used: China National Development and Reformation Commission Climate Change

    Office Notice of Chinese Regional Grid Emission Factor.

    Value applied: 0.9066

    Justification of thechoice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    Any comment: Shall be updated according to DNA's official data updating.

    Data / Parameter: NCVcotton

    Data unit: GJ/tonne

    Description: Net Calorific Value of type i biomass utilized in power plant

    Source of data used: China Energy Statistical Yearbook 2005 p. 366Value applied: 15.89

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    Value for cotton is used. Because cotton will constitute the majority of bio-fuel

    delivered to the plant based on feasibility study report.

    Any comment: Shall be updated according to China Energy Statistical Yearbook new version.

    Data / Parameter: NCVwheat

    Data unit: GJ/tonne

    Description: Net Calorific Value of type i biomass utilized in power plant

    Source of data used: China Energy Statistical Yearbook 2005 p. 366

    Value applied: 14.635

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    The Value for wheat straw is utilized from the China Energy Statistical

    Yearbook 2005. Since wheat straw could be utilized in the plant operation.

    Any comment: Shall be updated according to China Energy Statistical Yearbook new version.

  • 8/13/2019 25 MW Biomass Plant China_CDM

    32/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 32

    Data / Parameter: NCVpaddy,rice

    Data unit: GJ/tonneDescription: Net Calorific Value of type i biomass utilized in power plant

    Source of data used: China Energy Statistical Yearbook 2005 p. 366

    Value applied: 12.545

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    The Value for paddy rice straw is utilized from the China Energy Statistical

    Yearbook 2005. Since paddy rice could be utilized in the plant operation

    according to feasibility study report.

    Any comment: Shall be updated according to China Energy Statistical Yearbook new version.

    Data / Parameter: NCVmaize,

    Data unit: GJ/tonne

    Description: Net Calorific Value of type i biomass utilized in power plant

    Source of data used: China Energy Statistical Yearbook 2005 p. 366

    Value applied: 15.472

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    Maize straw might be utilized in the proposed project activity according to

    feasibility study report.

    Any comment: Shall be updated according to China Energy Statistical Yearbook new version.

    Data / Parameter: EFCH4,i

    Data unit: KgCH4/TJ

    Description: Methane emission from biomass combusted in power plant

    Source of data used: IPCC 2006 default value

    Value applied: 30 for the first commitment period.

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    Any comment: IPCC value from the latest version published will be utilized

    Data / Parameter: EFburning,CH4,k,y

    Data unit: KgCH4/TJ

    Description: CH4emission factor for uncontrolled burning of the biomass residue type k

    during the year y

    Source of data used: IPCC 2006 default value

    Value applied: 300 for the first commitment period.

    Justification of the

    choice of data or

  • 8/13/2019 25 MW Biomass Plant China_CDM

    33/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 33

    description of

    measurement methodsand procedures actually

    applied :

    Any comment: IPCC value from the latest version published will be utilized

    Data / Parameter: EFkm,co2

    Data unit: kg CO2/km

    Description: Average CO2emission factor for transportation of biomass with trucks

    Source of data used: IPCC 2006 default value from the Moderate Control index for the US heavy

    Duty Diesel Vehicle

    Value applied: 1.011 for the first commitment period.

    Justification of thechoice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    Any comment: IPCC value from the latest version published will be utilized

    Data / Parameter: EFco2,FF,i

    Data unit: tCO2/tonne

    Description: CO2emission factor for the fossil fuel type i combusted in plant

    Source of data used: Latest version of China Energy StatisticsValue applied:

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    Any comment: This parameter is not taken into consideration. Because for the onsite fuel

    consumption calculation the Net Calorific Value and carbon content are utilized

    instead, furthermore for biomass transportation emission calculation the

    Emission Factor per kilometre is utilized instead. Detailed calculation in Annex

    3.

    Data / Parameter: EFco2,LE

    Data unit: tCO2/tonne

    Description: CO2emission factor of the most carbon intensive fuel J in the calculation of CM

    with the ACM0002

    Source of data used: Latest version of China Energy Statistics

    Value applied:

    Justification of the

    choice of data or

    description of

    Local or national data should be preferred. Default values from the China

    Energy Statistics or IPCC 2006 will be used alternatively and should be chosen

    in a most conservative manner. Otherwise, this parameter is not taken into the

  • 8/13/2019 25 MW Biomass Plant China_CDM

    34/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 34

    measurement methods

    and procedures actuallyapplied :

    leakage calculation.

    Any comment: Minimal of two years after last issuance of CERs whenever the leakage exist.

    Data / Parameter: Net Calorific Value (NCVi) of fossil fuel combusted in plant

    Data unit: TJ/tonne

    Description: Net Calorific Value (NCVi) of fossil fuel combusted in plant

    Source of data used: Feasibility Study page 16

    Value applied: 0.04187

    Justification of the

    choice of data or

    description of

    measurement methodsand procedures actually

    applied :

    The value for Diesel is used. But other values will be applied if other fuels are

    used.

    Any comment: The project entity appointed a third party laboratory under the supervision of

    Shandong Power Design Institution for the power plant.

    Data / Parameter: Fossil fuel carbon content (diesel)

    Data unit: tC/TJ

    Description: Fossil fuel carbon content (diesel)

    Source of data used: IPCC 2006 default value

    Value applied: 20.2 for the first commitment period.

    Justification of thechoice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    Any comment: IPCC value from the latest version published will be utilized

    Data / Parameter: Oxidation Rate

    Data unit:

    Description: Oxidation Rate

    Source of data used: IPCC 1996 default value

    Value applied: 0.99 for the first commitment period.

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    Any comment:

    Data / Parameter: Moisture Content

    Data unit:

  • 8/13/2019 25 MW Biomass Plant China_CDM

    35/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 35

    Description: Biomass moisture content

    Source of data used: Project feasibility study report P15Value applied: 0.0961 for the first commitment period.

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    Any comment: The moisture content of the biomass residues are taken into consideration in all

    the calculations of Proposed Project emission reduction.

    Data / Parameter: CO2/C Factor

    Data unit:Description: CO2/C Factor

    Source of data used: IPCC 2006 default value

    Value applied: 3.67

    Justification of the

    choice of data or

    description of

    measurement methods

    and procedures actually

    applied :

    44/12=3.67

    based on molecule and atom weight of carbon and carbon dioxide.

    Any comment:

    Data / Parameter: Quantity of cotton residues that are utilized in the defined geographical region

    Data unit: Tonnes

    Description: Quantity of cotton residues that are utilized (eg for energy generation or as

    feedstock and all kinds of losts, etc) in the defined geographical region

    (1,346,000 tonnes in section B.6)

    Source of data used: Surveys or statistics and project feasibility study report

    Measurement

    procedures (if any):

    Monitoring frequency: Annually

    QA/QC procedures:

    Any comment: This parameter is applicable since approach L2 is utilized to rule out leakage.

    Data / Parameter: Quantity of cotton biomass residues in the region

    Data unit: Tonnes

    Description: Quantity of cotton residues in the region (2,236,000 tonnes in section B.6)

    Source of data used: Surveys or statistics and project feasibility study report

    Measurement

    procedures (if any):

    Monitoring frequency: Annually

    QA/QC procedures:

    Any comment: This parameter is applicable since approach L2 is utilized to rule out leakage.

  • 8/13/2019 25 MW Biomass Plant China_CDM

    36/72

    PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.

    CDM Executive Board

    page 36

    B.6.3. Ex-ante calculation of emission reductions:

    >>

    As described in the baseline information in Annex 3, the following greenhouse gas emissions are

    considered for the project activity:

    1) Methane emissions from biomass utilized in the power plant2) Biomass transportation emissions from collection points to power plant site3) Carbon dioxide emissions from electricity consumption at the power plant4) Emission from start-up/auxiliary fuel combustion in the boiler of the power plant onsite

    The above project emissions are calculated using the algorithms provided in the baseline methodology.

    An illustration of calculation methods is given in the following context.

    yBiomassCHCHyECycoyy PEGWPPEPEFFPETPE ,44,,2 +++= (tCO2/year)

    The total Project emissionsPEyare sum of project emissions from biomass combustion, transportationemissions, power consumption onsite and auxiliary fuel utilization in boiler as listed in the above

    equation. The detailed calculation explanation is demonstrated individually in the following sector.

    Project emission from biomass combustion

    It is estimated that approximately 22tonnes biomass residues will be combusted in the boiler per hour, and

    annual combustion amount reaches around 132,000 tonnes with 9.61% moisture content. Therefore the

    annual dry biomass combustion amount is 119,315 tonnes with a Net Calorific Value of 15.89 GJ/tonne

    for the mix fuel. Therefore, the assumed biomass combustion in the proposed power plant will result in

    the methane emissions of 1636 tCO2annually.

    Methane emission factor is chosen same of wood/wood waste as biomass residues combustion in

    industrial stoker boiler is 30 Kg/TJ as IPCC 2006 default value. Moreover, the proposed technology ismuch more efficient than stoker boiler, the correction of the methane emission factor was set at 1.37,

    which is the lowest from the ones proposed by the baseline methodology.

    Project emission from transportation process

    There is around 5-7 days storage capacity for biomass in the power plant, and 8 collection points surround

    the power plant. The collection sites are chosen based on a balance between distance and resource

    availability. The distance from the collection points to the power plant varies from 6 km to 35km. The

    transportation of biomass from collection point to power plant ended up in the direct emission from the

    combustion of fuel in trucks.

    In order to calculate the CO2-emissions from the transportation of bio-fuel the longest return trip is

    chosen as the simplest and most conservative estimation. Thus 2*35 km is used as the averagetransportation distance. The truck load will roughly be 5 to 8 tonnes. The smallest truck load is selected

    since it takes more