Upload
others
View
10
Download
0
Embed Size (px)
Citation preview
Application for Environmental Clearance
of
GROUP HOUSING
At
Khasra nos. 533/1 & 533/2
Village Chandanhaula, Tehsil Hauz Khas, New Delhi
Developed by
Wellworth Realtech LLP
1497, Bhardwaj Bhawan, Wzir Nagar,
Kotla, Mubarak Pur, New Delhi-110003
Prepared By:
M/s PERFACT ENVIRO SOLUTIONS PVT. LTD.
(NABET Registered wide list of accredited consultants organizations/ Rev 72/ January,
2019 at S.No.-117)
505, 5th Floor, NN Mall, Mangalam Palace, Sector-3, Rohini, New-Delhi-85
Phone: 011-49281360
WELLWORTH RE,AI_,TECH LLP1497, Bhardwai Bhawan, Wazir Nagar, Kotla Mubarakpur, New-Delhi
Ph. : 246337 34, 246337 44,
The Member Secretary,
lnfrastructure & Miscellaneous Projects & CRZ Committee (lnfra 2)
Ministry of Environment, Forests & Climate Change
Govt. of lndia,
lndira Paryavaran Bhawan
Jor Bagh Road,
New Delhi-110003
Dated: 30-0L-2019
Sub: Environmental Clearance of "Group Housing" at village Chandanhaula (La! Dora area)Tehsil Hauz Khas, New Delhi being developed by Wellworth Realtech LLP.
Dear sir,
We are developing a "Group Housing" Project at village Chandanhaula (Lal Dora area) Tehsil
Hauz Khas, New Delhi, being developed by Wellworth Realtech LLP. The total plot area of theproject is 10871 m'12.68 Acres) & Built-up area of the project is 42253.97 m2.
As the built-up area of the Project is less than L,50,000 sqm thus, the project falls under
Category'B'schedule 8(a) of EIA notification dated 14th Sep,2006 and its subsequent
amendments. However, tenure of Delhi Committee got completed, hence we are submittingthe application in MoEF&CC.
Thus, we are hereby enclosing the following documents-:
L. Form l& lA
2. Brief Summary
3. Environment Management Plan
We request you to kindly initiate the process of Environmental Clearance at the earliest.
Thanking you,
Yours faithfully,
For M/s Wellworth Realtech LLP
(Authorized Signatory)
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
2
TABLE OF CONTENTS
FORM 1 & 1A ............................................................................................................. 4
CONCEPTUAL PLAN .................................................................................................. 43
INTRODUCTION .............................................................................................................................. 44
ACTIVITIES/ AMENITIES .................................................................................................................... 44
SITE LOCATION ............................................................................................................................... 44
TYPE OF PROJECT ............................................................................................................................ 44
PROJECT DETAILS ............................................................................................................................ 44
POPULATION DETAILS ...................................................................................................................... 45
WATER MANAGEMENT .................................................................................................................... 46
RAIN WATER COLLECTION DETAILS ..................................................................................................... 46
POWER REQUIREMENT& BACK-UP ..................................................................................................... 46
SOLID & HAZARDOUS WASTE MANAGEMENT ...................................................................................... 47
PARKING MANAGEMENT .................................................................................................................. 47
GREEN AREA DEVELOPMENT ............................................................................................................. 47
ENVIRONMENT REPORT ........................................................................................... 48
EXECUTIVE SUMMARY OF THE PROJECT .................................................................................... 50
3.1.1 Activities: ............................................................................................................................... 50
3.1.2 Description & Details of Project: ............................................................................................ 50
INTRODUCTION OF THE BACKGROUND INFORMATION ............................................................ 51
3.2.1 Brief Description of the Nature of the Project: ...................................................................... 51
PROJECT DESCRIPTION ............................................................................................................... 51
3.3.1 Land Use and Ownership of the site land .............................................................................. 51
3.3.2 Location of the project with connectivity .............................................................................. 52
RESOURCES ................................................................................................................................... 55
3.4.1 Water Resource Management............................................................................................... 55
Water Balance ................................................................................................................................... 56
3.4.2 Energy Resource Management .............................................................................................. 57
3.4.3 Air Quality at Site ................................................................................................................... 57
3.4.4 Noise Quality at Site .............................................................................................................. 57
SITE ANALYSIS ............................................................................................................................ 58
3.5.1 Eco-sensitive areas with distance from project location ....................................................... 58
3.5.2 Centrally Protected Monuments Under Delhi Circle .............................................................. 59
3.5.3 Annual Windrose Diagram .................................................................................................... 62
3.5.4 Social Infrastructure available ............................................................................................... 63
PROPOSED INFRASTRUCTURE .................................................................................................... 63
3.6.1 Types of Buildings & Activities Proposed ............................................................................... 63
ENVIRONMENT MANAGEMENT PLAN ....................................................................................... 63
3.7.1 ENVIRONMENT MANAGEMENT DURING CONSTRUCTION ................................................... 64
3.7.2 ENVIRONMENT MANAGEMENT DURING OPERATION .......................................................... 66
ANTICIPITATED IMPACT & MITIGATION MEASURES .................................................................. 78
3.8.1 DURING CONSTRUCTION PHASE ............................................................................................ 78
3.8.2 DURING OPERATION PHASE .................................................................................................. 80
ENVIRONMENT MONITORING PLAN .......................................................................................... 81
RISK ASSESSMENT .................................................................................................... 82
RISK ASSESSMENT ...................................................................................................................... 83
4.1.1 HAZARD IDENTIFICATION ...................................................................................................... 83
4.1.2 VULNERABILITY ANALYSES ..................................................................................................... 83
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
3
4.1.3 RISK ANALYSIS ........................................................................................................................ 83
4.1.4 ONSITE EMERGENCY PLAN .................................................................................................... 85
4.1.5 Offsite Emergency Plan .......................................................................................................... 92
4.1.6 Security plan .......................................................................................................................... 92
EVACUATION PLAN .................................................................................................................... 93
CERTIFICATE OF THE CONSULTANT .......................................................................... 95
LAND PAPERS ........................................................................................................... 96
AIR DISPERSION REPORT .......................................................................................... 97
TEST REPORT ............................................................................................................ 98
TOPOGRAPHICAL MAP ............................................................................................. 99
LAYOUT PLAN/LANDSCAPE PLAN ....................................................................... 100
SURVEY PLAN ..................................................................................................... 101
STORM WATER PLAN ......................................................................................... 102
DUAL PLUMBING PLAN ...................................................................................... 103
PARKING PLAN ................................................................................................... 104
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
4
FORM 1 & 1A
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
5
FORM 1
I. Basic Information
S.No. Item Details
1. Name of the project/s “Group Housing”
2. S. No. in the schedule 8 (a)
3.
Proposed capacity/ area/length/
tonnage to be handled/ command
area/ lease area/ number of wells
to be drilled
Total plot area- 10871.05 m2 (1.0871 ha)
Total Built-up area- 42253.97 m2
Net planned area- 9971.25 m2
4. New/ Expansion/Modernization New
5. Existing Capacity/ Area etc. Not applicable
6. Category of Project i.e. ‘A’ or ‘B’
The project falls under Category ‘B’ of EIA
Notification, 2006. However, since the tenure
of SEAC, Delhi has been completed. Hence, the
application is being applied to MoEF & CC.
7. Does it attract the general
condition? If yes, please specify. Not Applicable
8. Does it attract the specific
condition? If yes, please specify. Not Applicable
9.
Location 533/1 & 533/2 Village
Chandanhola, Tehsil Hauz Khas, New Delhi
Plot/ Survey/ Khasra No. Khasra No.- 533/1 & 533/2
Village Chandanhaula
Tehsil Hauz Khas
District South West Delhi
State Delhi
10. Nearest railway station/ airport
along with distance in kms.
Railway Station: Tughlaqabad Railway Station- 11.60 km NE Airport Safdarjung Airport- 13.35 km NNE
11.
Nearest Town, city, District
Headquarters along with distance
in kms.
The project is in Delhi itself.
12.
Village Panchayats, Zilla Parishad,
Municipal Corporation, Local body
(complete postal addresses with
telephone nos. to be given)
Municipal Corporation of South Delhi
South Zone, Sector 9, RK Puram, New Delhi,
Delhi 110022
13. Name of the applicant Wellworth Realtech LLP
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
6
14. Registered Address 1497, Bhardwaj Bhawan, Wzir Nagar,
Kotla, Mubarak Pur, New Delhi-110003
15. Address for correspondence: 1497, Bhardwaj Bhawan, Wzir Nagar,
Kotla, Mubarak Pur, New Delhi-110003
Name Sumit Gupta
Designation (Owner/Partner/CEO) Designated Partner
Address 1497, Bhardwaj Bhawan, Wzir Nagar,
Kotla, Mubarak Pur, New Delhi-
Pin Code 110003
E-mail [email protected]
Telephone No. 9818623231
Fax no. -
16.
Details of Alternative Sites
examined, if any. Location of these
sites should be shown on a
toposheet.
No alternative site has been examined.
17. Interlinked Projects No, it is not an interlinked project
18.
Whether separate application of
interlinked project has been
submitted?
Not Applicable
19. If yes, date of submission Not Applicable
20. If no, reason Not Applicable
21.
Whether the proposal involves
approval/clearance under: if yes,
details of the same and their status
to be given.
(a) The Forest (Conservation) Act,
1980?
(b) The Wildlife (Protection) Act,
1972?
(c) The C.R.Z. Notification, 1991?
Not Applicable
Not Applicable
Not Applicable
22.
Whether there is any Government
Order/ Policy relevant/ relating to
the site?
Not Applicable
23. Forest land involved (hectares) No
24.
Whether there is any litigation
pending against the project and/ or
land in which the project is propose
to be set up?
(a) Name of the Court
No
Not applicable
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
7
(b) Case No.
(c) Orders/ directions of the
Court, if any and its
relevance with the
proposed project.
Not applicable
Not applicable
II. Activity
1. Construction, operation or decommissioning of the Project involving actions,
which will cause physical changes in the locality (topography, land use, changes
in water bodies, etc.)
S.No. Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
1.1 Permanent or temporary
change in land use, land cover
or topography including
increase in intensity of land use
(with respect to local land use
plan)
Yes As per the Master plan of Delhi (2021),
land use of the site is for urban
development. The land use and land cover
will change to group housing.
1.2 Clearance of existing land,
vegetation and buildings?
Yes Presently, the land has total 161 no. of
trees out of which 81 nos. are required to
be cut or transplanted in order to develop
the roads, basement, and buildings of the
Group Housing Colony. However, mostly
trees are young trees and permission
required is only for 6 number of trees,
which will be cut/ transplanted only after
obtaining the Tree Cutting/ transplanting
permission from Forest department &
remaining 80 no of trees shall be retained
the site.
1.3
Creation of new land uses?
Yes As per Master plan of Delhi (2021), land use
of the site is for urban development and
the land will be developed into a Group
Housing.
1.4 Pre-construction investigations
e.g. bore houses, soil testing?
Yes Pre-construction Geo-technical
investigation will be done.
1.5 Construction works? Yes Construction shall be done as per
Sanctioned Building plans & Master plan of
Delhi.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
8
1.6 Demolition works? Yes One two floor small building and one
temporary structure exist at site, which will
be demolished.
1.7 Temporary sites used for
construction works or housing
of construction workers?
No Approx. 150 workers during construction
phase will be hired from nearby areas and
hence there will be no need of providing
housing. Only temporary shelters will be
provided.
1.8 Above ground buildings,
structures or earthworks
including linear structures, cut
and fill or excavations
Yes Above ground, the building shall be
elevated upto maximum height of 78 m.
Soil excavation will be done for foundation
& 2 level basements.
1.9 Underground works including
mining or tunnelling?
No Not applicable
1.10 Reclamation works? No No reclamation work will be done.
1.11 Dredging? No Not applicable
1.12 Offshore structures? No Not applicable
1.13 Production and manufacturing
processes?
No It is a Group Housing; hence no production
or manufacturing processes shall be carried
out.
1.14 Facilities for storage of goods
or materials?
Yes During Construction Phase:
• Separate raw material yard shall be
made within the project site.
• Cement shall be separately stored
under cover in bales.
• Sand shall be stacked nearby under
tarpaulin cover.
• Bricks and steel shall be laid in open.
During Operation Phase:
As the project is Group Housing, the raw
material will be food, stationary & other
household items which will be stored in
respective dwelling units only.
1.15 Facilities for treatment or
disposal of solid waste or liquid
effluents?
Yes During Construction phase:
Approx. 150 labourers shall work during
the construction phase and hence the solid
waste generation shall be 23 kg/day, which
shall be disposed off at municipal solid
waste site.
Construction debris will be used in levelling
& backfilling purposes to the extent
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
9
possible & rest will be sent to the
construction & demolition facility.
Excavated soil generated for providing
foundation will be used for levelling and
back filling purposes. Top soil will be
preserved and shall be reused for
landscaping to the extent possible.
Mobile toilets shall be provided at site for
labourers which shall be regularly cleaned.
During Operation Phase:
Approx. 153 Tons/ annum of solid waste
shall be generated from the project out of
which the biodegradable waste will be 92
Tons/annum which shall be treated in
organic waste converter and converted to
manure. 61 Tons/annum of Non-
Biodegradable waste will be given to
approved recycler.
The total waste water generation in the
project shall be 112 KLD which will be
treated in STP of 135 KLD based in MBBR
technology.
Details of water management are given in
Environment Report.
1.16 Facilities for long term housing
of operational workers?
No During Construction phase:
The workers during construction phase
shall be hired from nearby areas and hence
there is no need of providing long term
housing. Only temporary shelters will be
provided.
During Operation Phase:
As this is a Group Housing, staff like
maintenance staff will be from the nearby
areas. Servant units shall be provided
attached with few dwelling units which
may be used for accommodation of
owner’s servant.
1.17
New road, rail or sea traffic
during construction or
operation?
No No new road, rail or sea traffic is proposed.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
10
1.18
New road, rail, air, waterborne
or other transport
infrastructure including new or
altered routes and stations,
ports, airports etc.?
No No new road, rail or sea traffic is proposed.
The transportation measures already
existing near site are as follows:
Nearest Railway Station: Tughlaqabad Railway Station : 11.60 Km NE Nearest Highway: NH -236 – 4.55 Km NW Nearest Airport: Indira Gandhi International Airport -13.02 Km NW
1.19 Closure or diversion of existing
transport routes or
infrastructure leading to
changes in traffic movements?
No No closure or diversion of existing
transport routes or infrastructure leading
to changes in traffic movements will be
made.
1.20 New or diverted transmission
lines or pipelines?
No No such closure or diversion of
transmission lines is required.
1.21 Impoundment, damming,
culverting, realignment or
other changes to the hydrology
of watercourses or aquifers?
No No impoundment, damming, culverting,
realignment or other changes to the
hydrology of surface water courses is
required.
1.22 Stream crossings? No No stream crossing.
1.23 Abstraction or transfers of
water from ground or surface
waters?
No No ground water abstraction is proposed.
Abstraction of water if required will be
done only after getting permission from
CGWA.
1.24 Changes in water bodies or the
land surface affecting drainage
or run-off?
Yes There is no such water body existing near
the site & hence there will be no change in
any water bodies but, the vacant uneven
land surface will be developed into a
levelled group housing with a proper
drainage network & rain water harvesting
pits which will lead to ground water
recharge & effective drainage.
1.25 Transport of personnel or
materials for construction,
operation or
decommissioning?
Yes During Construction phase:
Materials during construction phase shall
be transported by truck, trolley etc. cars &
two wheelers will be used for
transportation of personnel.
During Operation Phase:
Car, two-wheeler, etc. will be used.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
11
1.26 Long-term dismantling or
decommissioning or
restoration works?
No Not Applicable
1.27 Ongoing activity during
decommissioning which could
have an impact on the
environment?
No Not Applicable
1.28 Influx of people to an area in
either temporarily or
permanently?
No During Construction phase:
Temporary influx of people in the form of
labours is envisaged. Approx. 150 no. of
local labours shall be employed.
During Operation Phase:
As this is a Group Housing, 887 residents,
40 no. of staff & 100 nos. visitors are
envisaged.
1.29 Introduction of alien species? No Not Applicable
1.30 Loss of native species or
genetic diversity?
No No tree
1.31 Any other actions? No Not Applicable
2. Use of Natural resources for construction or operation of the Project (such as
land, water, materials or energy, especially any resources which are non-
renewable or in short supply):
S.No. Information/checklist
confirmation
Yes
/No
Details thereof (with approximate
quantities /rates, wherever possible) with
source of information data
2.1 Land especially undeveloped
or agricultural land (ha)
Yes 10871.05 m2 of undeveloped land will be
developed into Group Housing. 2.2 Water (expected source &
competing users) unit: KLD
Yes Source & Quantity During Construction
phase:
Water during construction phase shall be
arranged on temporary basis. For
construction activities, water shall be taken
from treated water from nearby DJB STP.
Source & Quantity During Operation
Phase:
The ultimate source of water will be DJB.
Total water requirement details are given
below:
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
12
Total Water Requirement
152 KLD
Fresh Water Requirement
83 KLD
Treated Water Reuse
69 KLD
Detail water management & water balance
are given in Environment Report.
2.3 Minerals (MT) No Not applicable
2.4 Construction material – stone,
aggregates, sand / soil
(expected source – MT)
Yes The major materials required for
construction of the project will be steel,
tiles, glass, cement, agate, bricks, flooring
tiles / stones, sanitary and hardware items,
electrical fittings, etc.
2.5 Forests and timber (source –
MT)
Yes Plywood for doors & windows shall be used
which shall be procured from local market.
2.6 Energy including electricity
and fuels (source, competing
users) Unit: fuel (MT), energy
(MW)
Yes Source of Electricity – BSES
Total Electrical load – 3400 KW
D.G. sets for power back up- 3 x 1010 KVA
2.7 Any other natural resources
(use appropriate standard
units)
No Not applicable
3. Use, storage, transport, handling or production of substances or materials, which
could be harmful to human health or the environment or raise concerns about actual
or perceived risks to human health.
S. No. Information/Checklist
confirmation
Yes
/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
3.1 Use of substances or materials,
which are hazardous (as per
MSIHC rules) to human health
or the environment (flora,
fauna, and water supplies)
Yes No storage of hazardous substances (as
per MSIHC RULES) will be done.
3.2 Changes in occurrence of
disease or affect disease vectors
(e.g. insect or water borne
diseases)
No Suitable drainage and waste management
measures will be adopted in both the
construction and operational phase which
will restrict stagnation of water or
accumulation of water. This will
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
13
effectively restrict the reproduction and
growth of disease vectors.
3.3 Affect the welfare of people e.g.
by changing living conditions?
Yes During Construction phase:
Employment opportunities provided due
to the project will lead to better quality of
life & will also set a standard for future
developments in the area. This project will
provide employment to about 150 local
labours during construction phase.
During Operation Phase:
As it is Group Housing, there shall be
several services which will generate direct
& indirect employment for the people of
nearby area in the form of security guards,
cleaning & maintenance staff, gardener,
staff for club, etc.
3.4 Vulnerable groups of people
who could be affected by the
project e.g. hospital patients,
children, the elderly etc.,
No No vulnerable group of people will be
affected by the project.
3.5 Any other causes No None
4. Production of solid wastes during construction or operation or decommissioning
(MT/month)
S.No. Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
4.1 Spoil, overburden or mine
wastes.
No Not applicable
4.2 Municipal waste (domestic
and or commercial wastes)
Yes During Construction phase:
Solid waste during construction phase will
be 23 kg/day which shall be disposed off
at municipal solid waste site.
During Operation Phase:
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
14
Approx. 153 Tons/annum of solid waste
shall be generated from the project
during operational phase.
Detailed Solid Waste Management is
given in Environment Report.
4.3 Hazardous wastes (as per
Hazardous Waste
Management Rules)
Yes During Construction phase:
Used oil whenever generated from the
DG sets shall be kept in leak proof
containers in an isolated area and shall
be sent to approved recycler.
During Operation Phase:
Used oil generated from DG sets will be
carefully stored in HDPE drums in
isolated covered facility. The used oil will
be sold to vendors authorized by Central
Pollution Control Board for the
treatment of the same.
Suitable care will be taken so that
spills/leaks of used oil from storage could
be avoided.
4.4 Other industrial process
wastes
No Not Applicable
4.5 Surplus product No Not applicable
4.6 Sewage sludge or other
sludge from effluent
treatment
Yes About 8-10 Kg/day of dried sludge will be
generated from STP within colony during
operation phase and this sludge will be
passed through filter press where it will
be dewatered/ dried to form a cake and
then will be used as manure in green
areas. The unused sludge shall be given to
farmers or nursery.
4.7 Construction or demolition
wastes
No During construction phase:
Construction waste shall be shall be used
for flooring & Back filling in roads etc.
During operation phase:
No C & D waste is envisaged during
operation phase.
4.8 Redundant machinery or
equipment
No Not applicable
4.9 Contaminated soils or other
materials
No Not applicable
4.10 Agricultural wastes
No Not applicable
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
15
4.11 Other solid wastes
Yes During Construction phase:
No E-waste shall be generated.
During Operation Phase: A small
quantity of E-Waste shall be generated. It
shall be given to approved recycler of
SPCB. Battery waste generated from
inverters & UPS which shall be disposed
off as per the Batteries (Management &
Handling) Rules, 2001.
5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)
S.No. Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
5.1 Emissions from combustion
of fossil fuels from
stationary or mobile
sources
Yes During Construction phase:
DG sets of capacities 62.5 KVA shall be
bought and shall be installed
acoustically enclosed with adequate
stack height
During Operation Phase:
The only source of air emission will be
emissions from combustion of fuel of 3
x 1010 KVA capacities. Hence, to avoid
the emissions, stack height of 6 m above
roof level for the D.G. Set shall be
provided. The DG set shall meet all the
norms prescribed by CPCB.
5.2 Emissions from production
processes
No Not applicable
5.3 Emissions from materials
handling including storage
or transport
Yes Dust shall be generated during
construction, from the movement of
transport vehicles & other construction
activities. The effect will be restricted to
construction phase only.
Water sprinklers shall be used for dust
suppression.
Material will be transported under
covered vehicles & will be stored under
Tarpaulin cover. Other dust mitigation
measures shall be taken to mitigate the
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
16
emissions from construction activities
which are given in detail in EMP report.
5.4 Emissions from
construction activities
including plant and
equipment
Yes Ready Mix Concrete (RMC) shall be used
to minimize the emission impacts from
the project. Dust & emissions are still
likely to be generated during
construction activities which shall be
reduced by sprinkling of water in a
specific time interval & timely
maintenance schedule for machinery.
Also, the machines shall be shut down
during idle period.
5.5 Dust or odours from
handling of materials
including construction
materials, sewage and
waste
Yes During loading & unloading of
construction material dust is likely to be
generated during construction phase.
Water shall be sprinkled and tarpaulin
cover shall be provided over stored raw
material to reduce dust emission.
Mobile Toilets during construction
phase shall be provided & shall be
cleaned regularly.
5.6 Emissions from incineration
of waste.
No Not applicable.
5.7 Emissions from burning of
waste in open air (e.g. slash
materials, construction
debris).
No Open burning of biomass/ other
material will be prohibited.
5.8 Emissions from any other
sources.
No None
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
17
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No. Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities/rates, wherever possible) with
source of information data with source of
information data
6.1 From operation of equipment
e.g. engines, ventilation
plant, crushers
No During Construction phase:
DG sets of capacities 62.5 KVA shall be
installed acoustically enclosed. The
equipment such as mixer machines,
bulldozers, cranes, compactors &
excavators shall be used which will be of
highest standard of reputed make and
adhere to international standards. Hence
an insignificant impact due to construction
machinery is envisaged.
Apart from this, the construction activities
shall be restricted to daytime only and
timely maintenance of machinery will be
ensured.
During Operation Phase:
Source of noise in the operational phase will
be D.G. Set of 3 x 1010 KVA. The D.G. Set
shall be kept in acoustically treated room
with anti-vibration pads and will be used
during Power failure only. They may
generate noise level maximum upto 75 dB
(A).
6.2 From industrial or similar
processes
No Not applicable
6.3 From construction or
demolition
Yes Due to the various construction activities,
there will be short-term noise impacts in
the immediate vicinity of the project site.
These shall be restricted to day time only. It
has been estimated that during the
construction period the average noise level
is 70-75 dB (A) during peak construction
hours.
Barricading of site shall be done in order to
reduce noise impacts outside the project
boundary.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
18
6.4 From blasting or piling No No blasting or piling will be done.
6.5 From construction or
operational traffic
Yes Some amount of noise (70 – 75 dB (A)) will
be generated from vehicular movement in
the construction and operational phase.
Barricading/ Boundary development/
Plantation around the boundary wall shall
be done to reduce noise from traffic.
6.6 From lighting or cooling
systems
No Not Applicable
6.7 From any other sources No None
7. Risks of contamination of land or water from releases of pollutants into the
ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S. No. Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
7.1 From handling, storage, use
or spillage of hazardous
materials
Yes Diesel will be stored within the site for
operation of DG set.
The hazardous waste generated will be
Used oil only and it will be stored in
HDPE drums and kept in covered rooms
under lock and key and will be sold to
authorized vendors only. Special care
will be taken to prevent leakages and
spills.
7.2 From discharge of sewage or
other effluents to water or
the land (expected mode and
place of discharge)
Yes During operational phase STP of 135
KLD will be installed for treating 112 KLD
waste water out of which 69 KLD will be
reused in flushing, gardening, & misc.
purpose. Excess treated water of 32 KLD
shall be discharge to sewer line.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
19
7.3 By deposition of pollutants
emitted to air into the land or
into water
Yes The only source of air emission will be
DG sets & vehicular emissions. The DG
sets adhering to CPCB standards will be
installed with adequate stack height.
The emission from DG sets will be
dispersed in the air & will not create any
contamination to land or water.
Vehicles with valid PUC certificates shall
be allowed in the project premises.
Residents shall be guided to keep their
vehicles checked for pollution control.
7.4 From any other sources No None
7.5 Is there a risk of long-term
build-up of pollutants in the
environment from these
sources?
No Not applicable
8. Risk of accidents during construction or operation of the Project, which could
affect human health or the environment.
S. No. Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
8.1 From explosions, spillages,
fires etc. from storage,
handling, use or production
of hazardous substances
No During Construction Phase:
All appropriate measures shall be taken
to avoid accidents.
During Operational Phase:
Proper Disaster management &
firefighting system will be installed in
the proposed complex.
8.2 From any other causes No During Construction Phase:
All the labours shall be provided with
suitable personal protective equipment
(PPE) as required under the health &
safety norms. Training and awareness
about the safety norms shall be
provided to all supervisors and labours
involved in construction activity
8.3 Could the project be
affected by natural
disasters causing
environmental damage
Yes The area under study falls in Seismic
zone-IV, according to the Indian
Standard Seismic Zoning Map. There
may be possibilities that the project may
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
20
(e.g. floods, earthquakes,
landslides, cloudburst etc.)?
get affected due to earthquake,
flooding, etc. type of natural disasters.
Suitable seismic coefficients in
horizontal and vertical directions
respectively, will be adopted while
designing the structure to provide
sufficient strength to the structures to
withstand the earthquakes.
Flooding can occur only due to excess
rain in the area for which such drainage
system shall be designed & developed
that no flooding situation takes place.
Risk assessment is given as Enclosure IV.
9. Factors which should be considered (such as consequential development) which could
lead to environmental effects or the potential for cumulative impacts with other existing
or planned activities in the locality.
S. No. Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
9.1 Lead to development of
supporting facilities, ancillary
development or development
stimulated by the project
which could have impact on
the environment e.g.
• Supporting
infrastructure (roads,
power supply, waste or
waste water treatment,
etc.)
• Housing development
• Extractive industries
• Supply industries
• Other
No
No
No
No
No
No
The project area is already developed
area.
Not Applicable
Not Applicable
Not Applicable
Not Applicable
9.2 Lead to after-use of the site,
which could have an impact
on the environment.
No Not Applicable
9.3 Set a precedent for later
developments
Yes It will attract people to develop
organized group housings & planned
development of area.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
21
9.4 Have cumulative effects due
to proximity to other existing
or planned projects with
similar effects
No No impact
III. Environmental Sensitivity
S. No Areas Name/ Identity
Aerial distance (within 15 km.) from Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value
Asola Wild Life Sanctuary
1.87 Km SEE
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests
Water Bodies Drain near Project Site Sharpur Nala Pond near Junapur Rohar Nala Pond near Aya Nagar Shamsi Talab Ghitorni Lake Bhuriya Nala Neela Hauz Jauhar Nala Kaunsat Nala Dhulainti Nala Bhawaro Nala Hauz Khas Tank Suraj Kund Li Nala Badkal Lake Forest Forest near Aya Nagar Extension Rajokari Protective Forest Jahanpanah City Protective Forest Fairly Dence Forest near Hamdard Nagar Forest near Hauz Khas
0.06 Km SWW 1.01 Km SSW 2.84 Km W 4.61 Km S 5.22 Km NWW 5.25 Km NNW 5.27 Km NWW 5.44 Km SEE 7.15 Km NNW 7.27 Km S 7.30 Km SSW 8.58 Km SSW 9.14 Km SW 9.72 Km NNE 9.78 Km NEE 10.02 Km SW 10.17 Km SE 6.88 Km W 7.20 Km NW 7.89 Km NE 8.24 Km NE 8.98 Km NNE
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
22
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration
Asola Wild Life Sanctuary
1.87 Km SEE
4 Inland, coastal, marine or underground waters
None None
5 State, National boundaries
Haryana Boundary 6.18 Km SSW
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas
Roads Main Chhatarpur Road NH -236 NH-8 NH-2 Railway Station Chhatarpur Metro Station Saket Metro Station Tughalaqabad Rly. Station Okhla Railway Station Airport IGI Airport Delhi Safdarjung Airport
0.02 Km E 4.55 Km NW 9.83 Km NW 12.22 Km NE 4.69 Km NNW 6.35 Km NNE 11.60 Km NE 13.01 Km NE 13.02 Km NW 13.35 Km NNE
7 Defence installations
Arjangarh Air Force Station 4.45 Km SSW
8 Densely populated or built-up area Fatehpur Beri 0.52 Km SSW
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities)
Hospital Hospital near Fatehpur Beri Hospital near Sat Bari Poultary Farm Hospital near Junapur Post Office Post Office near Fatehpur Beri Post Office near Asola Post Office neari Junapur Place of Worship Temple near Chandan Haula Mosque near Chandan Haula Temple near Fatehpur Beri Schools Thana Pal Ka Jila Katihar Sali Pur Gaon Sarkari School Chandanhaula Nagar Nigam Prathmik Vidyalay ChandanHaula R.C.C.E. Public School near Mehrauli, Main Chhatarpur Rd. Chandan Haula Banks Punjab Nation Bank, Asola Canara Bank, Asola
0.64 Km SE 2.02 Km NNE 2.68 Km W 0.83 Km SSW 1.13 Km SSE 2.91 Km NWW 0.29 Km N 0.33 Km NNE 0.47 Km SSW 0.27 Km NWW 0.34 Km NNE 0.39 Km NNE 0.04 Km SSW 0.38 Km SSW
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
23
State Bank of India-Customer Service Point near Church Fatehpur Beri
0.85 Km SSW
10. Areas containing important, high quality or scarce resources (Ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals)
ASI Monument given in EMP report.
11 Areas already subjected to pollution or environmental damage. (Those where existing legal environmental standards are exceeded)
Okhla Industrial Area
11.50 Km NE
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (Earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)
Area falls in seismic zone IV
WE,LLWORTH RE],ALTE,CH LLP1497, Bhardwai llhawan, Wazir Nagar, Kotla Mubarakpur, New-Delhi
I'h. : 246337 34, 246337 44,
To Whom !t Mav Concern
We authorize M/s Perfact Enviro Solutions Pvt. Ltd., 5th Floor, NN Mall, Mangalam
Palace, Sector-3, Rohini, New Delhi-110085. One of the approved consultants ofMinistry of Environment & Forest, Govt. of lndia listed on MoEF&CC website forgetting Environmental Clearance for our project "Group Housing" at Khasra no.
53311. & 53312 Village Chandanhaula, Tehsil Hauz Khas, New Delhi being developed
by M/s Wellworth Realtech. LLP.
For M/s Wellworth Realtech LLP.
Authorisecj Slgnatory
Date:17.01.2019
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
25
FORM 1A
CHECK LIST OF ENVIRONMENTAL IMPACTS
(Project proponents are required to provide full information and wherever necessary attach
explanatory notes with the Form and submit along with proposed environmental
management plan & monitoring programme)
I. LAND ENVIRONMENT
(Attach panoramic view of the project site and the vicinity)
1.1 Will the existing landuse get
significantly altered from the
project that is not consistent with
the surroundings? (Proposed
landuse must conform to the
approved Master Plan /
Development Plan of the area.
Change of landuse if any and the
statutory approval from the
competent authority be
submitted).
Attach Maps of
(i) Site location
(ii) Surrounding features of the
proposed site (within 500 meters)
(iii) The site (indicating levels &
contours) to appropriate scales. If
not available attach only
conceptual plans.
As per Master plan of Delhi (2021) land Use of the
site is for urban development and the land will be
developed into a Group housing.
The site location shown on Google Map is given in
Environment Report.
Map showing vicinity around the site is given in
Environment Report.
Site plan is enclosed as Enclosure 10.
1.2 List out all the major project
requirements in terms of the
Land area,
Built up area
Water consumption
Power requirement
Connectivity
Community facilities
Parking needs etc.
Total plot area – 10871.05 m2 (1.0871 ha)
42253.97 m2
152KLD
3400 KW
Main Chhatarpur Road-0.02 Km E
Commercial Building & Club
Parking Requirement- 421 ECS (including parking
for EWS & Visitors)
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
26
Parking Provision- 440 ECS
1.3 What are the likely impacts of the
proposed activity on the existing
facilities adjacent to the
proposed site?
(Such as open spaces, community
facilities, details of the existing
landuse, and disturbance to the
local ecology).
The entire project influenced area will be
developed as per the provision of Master Pan,
thus no induced development is foreseen due to
the proposed project.
Also, the proposed development shall be carried
out as per the defined building by-laws; hence no
impact is envisaged due to proposed
development.
Construction phase as well as operation Phase of
the project, will generate direct and indirect
employment opportunities for a large section of
society. The employment will have positive
impact thereby increasing the quality of life.
1.4 Will there be any significant land
disturbance resulting in erosion,
subsidence & instability?
(Details of soil type, slope
analysis, vulnerability to
subsidence, seismicity etc. may
be given).
No such significant land disturbance will result.
However, care will be taken so that no erosion,
subsidence & instability takes place.
Soil Type: Silt Loam
Slope Analysis:
The project area possesses fairly plain terrain.
Erosion / Subsidence:
Proper greening & paving of area will be done to
avoid any soil erosion problem and subsidence.
Seismicity:
The area under study falls in Seismic zone-IV
according to the Indian Standard Seismic Map.
Suitable seismic coefficients in horizontal and
vertical directions respectively, will be adopted
while designing the structure.
1.5 Will the proposal involve
alteration of natural drainage
systems?
(Give details on a contour map
showing the natural drainage
near the proposed project site)
The proposed project will be developed into an
organized Group Housing with drainage network
& rain water recharge pits. The drainage of the
will be proper as 03 nos. of rain water pits will lead
to Ground water recharging. However, the
proposal does not involve any alteration of the
natural drainage system of the area in a broader
aspect.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
27
1.6 What are the quantities of
earthwork involved in the
construction activity cutting,
filling, reclamation etc.
(Give details of the quantities of
earthwork involved, transport of
fill materials from outside the site
etc.)
During construction phase, Total 51040 cu. m. of
soil will be excavated in order to provide 2 level of
basement & foundation. The excavated soil will be
properly stacked within the project site. The
excavated top soil will be preserved separately
and will be used for landscaping purpose only.
1.7 Give details regarding water
supply, waste handling etc.
during the construction period.
Water Supply: During construction phase
water for construction purpose will be sourced
through tanker suppliers (treated water from DJB)
and domestic water from labour will be sourced
from tanker supply.
Waste Generation / Handling:
Soil excavated will be reused for backfilling and
the fertile top soil will be reused for horticulture
purpose.
cement residual from concrete mixer plants will
be properly collected and reused in construction
site.
For construction labour, proper sanitary facilities
& wash areas will be constructed which includes
mobile toilets and good hygienic conditions will
be maintained. Mobile toilets shall be regularly
cleaned by the vendor. Municipal solid waste
from laborers shall be disposed off at designated
site.
Used oil shall be stored separately in leak proof
containers & shall be given to authorized vendors.
1.8 Will the low-lying areas &
wetlands get altered?
(Provide details of how low lying
and wetlands are getting
modified from the proposed
activity)
No low lying and wetlands area are present in and
around the project site.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
28
1.9 Whether construction debris &
waste during construction cause
health hazard? (Give quantities of
various types of wastes
generated during construction
including the construction labour
and the means of disposal)
The construction waste generated from the
project will be common in nature and will not
cause any health hazard to associate and nearby
population. The construction debris will be used
for land levelling /back filling. Waste concrete will
be reused as aggregate in construction process.
The rest of the construction debris shall be sent to
C & D facility.
Mobile toilets & drinking water for construction
labour shall be provided.
2. WATER ENVIRONMENT
2.1 Give the total quantity of
water requirement for the
proposed project with the
breakup of requirements
for various uses.
How will the water
requirement met?
State the sources &
quantities and furnish a
water balance statement.
The total quantity of water requirement shall be 152
KLD and 83 KLD of the fresh water requirement shall
be met by DJB .
Domestic : 78 KLD
Flushing : 46 KLD
DG Cooling : 15 KLD
Gardening : 3 KLD
Swimming Pool: 5 KLD
Misc. : 5 KLD
Total Water Requirement : 152 KLD
Fresh water : 83 KLD
Treated Water Reuse : 69 KLD
Total Waste Water Discharge : 112 KLD
2.2 What is the capacity
(dependable flow or yield)
of the proposed source of
water?
DJB will supply water to the project and it is a
dependable source of water.
2.3 What is the quality of water
required, in case, the
supply is not from a
municipal source? (Provide
physical, chemical,
biological characteristics
with class of water quality)
In case DJB supply is not made or the supply made is
inadequate then the water complying with IS – 10500
shall be arranged.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
29
2.4 How much of the water
requirement can be met
from the recycling of
treated wastewater?
(Give the details of
quantities, sources and
usage)
Total treated water of 101 KLD shall be generated from
the S.T.P out of which 69 KLD shall be reused in
flushing, gardening, DG cooling & misc. purposes
within the project premises. Approx. 46% of total
water requirement will be met by recycled water.
2.5 Will there be diversion of
water from other users?
(Please assess the impacts
of the project on other
existing uses and quantities
of consumption)
There will not be any substantial effect on water
demand of this region as the development will be done
as per the development plan of the area.
2.6 What is the incremental
pollution load from
wastewater generated
from the proposed
activity?
(Give details of the
quantities and composition
of wastewater generated
from the proposed activity)
The total waste water generation from the project will
be 112 KLD which will be treated in in-house S.T.P of
capacity 135 KLD. 69 KLD treated water will be reused
for flushing, gardening, DG cooling & misc. purposes.
Approx. 68 % of treated water will be recycled for use.
Excess treated water of 32 KLD shall be discharged in
sewer.
2.7 Give details of the water
requirements met from
water harvesting? Furnish
details of the facilities
created.
3 no. of rain water harvesting structures shall be
provided at site. (Details of Rain water structure are
given in Environment Report).
2.8 What would be the impact
of the land use changes
occurring due to the
proposed project on the
runoff characteristics
(quantitative as well as
qualitative) of the area in
the post construction
phase on a long-term
basis?
Would it aggravate the
problems of flooding or
water logging in any way?
After the construction of the complex, the rain water
will be properly channelized to the RWH network &
will be recharged to the ground.
No, it will not aggravate the problem of flooding or
water logging in any way, rather will reduce the same.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
30
2.9 What are the impacts of
the proposal on the ground
water?
(Will there be tapping of
ground water; give the
details of ground water
table, recharging capacity,
and approvals obtained
from competent authority,
if any)
Groundwater recharging is proposed through rain
water harvesting, so, there will be positive impact on
ground water levels.
2.10 What
precautions/measures are
taken to prevent the run-
off from construction
activities polluting land &
aquifers?
(Give details of quantities
and the measures taken to
avoid the adverse impacts)
During the construction phase, runoff from the
construction site will not be allowed into the roadside.
It will be collected in tanks & used for sprinkling,
curing, etc.
2.11 How is the storm water
from within the site
managed?
(State the provisions made
to avoid flooding of the
area, details of the
drainage facilities provided
along with a site layout
indication contour levels)
During construction phase
Adequate measures will be taken to channelize storm
water and the same will be collected in a tank and it
will be reused for sprinkling, curing etc.
During operation phase
Storm water will be channelized to 3 no. of rainwater
harvesting pits proposed within the complex & will
recharge the ground water.
2.12 Will the deployment of
construction labourers
particularly in the peak
period lead to unsanitary
conditions around the
project site (Justify with
proper explanation)
Mobile toilets will be provided for labourers during
construction period which shall be cleaned regularly.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
31
2.13 What on-site facilities are
provided for the collection,
treatment & safe disposal
of sewage?
(Give details of the
quantities of wastewater
generation, treatment
capacities with technology
& facilities for recycling and
disposal)
During construction phase
Total water requirement during construction phase
will be 15 KLD out of which 7 KLD of water will be
required by labourers for domestic & flushing
purposes and 8 KLD for construction purpose. Mobile
toilets shall be provided at the site which shall be
cleaned regularly.
During operation phase, 112 KLD of waste water will
be treated in the proposed S.T.P. of 135 KLD capacity
based on MBBR technology. Approx. 68 % of treated
water will be reused. Excess treated water of 32 KLD
shall be discharged to sewer.
2.14 Give details of dual
plumbing system if treated
waste used is used for
flushing of toilets or any
other use.
Dual Plumbing line will be provided in the colony for
reuse of treated water.
3. VEGETATION
3.1 Is there any threat of the
project to the biodiversity?
(Give a description of the
local ecosystem with its
unique features, if any)
Core Zone:
Presently, the land has total 161 no. of trees out of
which 81 nos. are required to be cut/ transplanted in
order to develop the roads, basement, and buildings
of the Group Housing Colony. However, mostly trees
are young trees and permission required is only for 6
number of trees, which will be cut/ transplanted only
after obtaining the Tree Cutting/ transplanting
permission from Forest department & remaining 80
no of trees shall be retained the site.
Buffer Zone: The following species were found in
the buffer zone.
3.2 Will the construction
involve extensive clearing
or modification of
vegetation?
(Provide a detailed account
of the trees & vegetation
affected by the project)
Presently, the land has total 161 no. of trees out of
which 81 nos. are required to be cut/ transplanted in
order to develop the roads, basement, and buildings
of the Group Housing Colony. However, mostly trees
are young trees and permission required is only for 6
number of trees, which will be cut/ transplanted only
after obtaining the Tree Cutting/ transplanting
permission from Forest department & remaining 80
no of trees shall be retained the site.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
32
Details given in EMP report.
3.3 What are the measures
proposed to be taken to
minimize the likely impacts
on important site features?
(Give details of proposal
for tree plantation,
landscaping, creation of
water bodies etc along
with a layout plan to an
appropriate scale)
There will not be any kind of impact of this project on
site features.
The Shelter belt for the proposed project has been
planned to provide a clean, healthy and beautiful
green environment for the people to live in within the
proposed project site.
To minimize the impact, the provision of plantation
area of 3331.69 m2 area (33.41% of net plot area),
with lawns, ornamental plants and trees shall be
provided.
4. FAUNA
4.1 Is there likely to be any
displacement of fauna-
both terrestrial and
aquatic or creation of
barriers for their
movement? Provide the
details.
Core Zone & Buffer Zone:
There will not be any type of displacement or any other
effect on the local fauna due to proposed project
activities.
4.2 Any direct or indirect
impacts on the avifauna of
the area? Provide details.
Avifaunal species like crow, parrot, jungle babbler,
myna, red vented bulbul & pigeon were seen at the site
during site visit, since, the proposed site has total 161
no. of trees out of which 81 nos. are required to be cut/
transplanted in order to develop the roads, basement,
and buildings of the Group Housing Colony. However,
mostly trees are young trees and permission required is
only for 6 number of trees, which will be cut/
transplanted only after obtaining the Tree Cutting/
transplanting permission from Forest department &
remaining 80 no of trees shall be retained the site.
However, proper landscaping has been planned to
provide a clean, healthy and beautiful green
environment for the population.
Common native variety of trees and ornamental
flowering species will be planted in the green space
which will attract avifauna & hence will have direct
positive impact on the local avifauna & this will provide
shelter to local birds.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
33
4.3 Prescribe measures such
as corridors, fish ladders
etc. to mitigate adverse
impacts on fauna.
Not applicable
5. AIR ENVIRONMENT
5.1 Will the project increase
atmospheric concentration of
gases & result in heat islands?
(Give details of background
air quality levels with
predicted values based on
dispersion models taking into
account the increased traffic
generation as a result of the
proposed constructions)
The main source of air emissions in the project are
traffic that will increase due to the project and the
DG sets used for the project.
Increased traffic generation of vehicles due to
project will not cause significant increase in
atmospheric concentration of gases and do not
result in heat island formation.
Tree plantation in the complex will be provided such
that the impact of air pollution shall be minimized.
D.G. set of capacity 3 x 1010 KVA will be installed in
the complex which will be operated during power
cut only & which will be bought as per CPCB norms.
The DG sets will be provided with sufficiently high
stack for better dispersion of the flue gases.
The Air Dispersion Report is enclosed as Annexure
7.
5.2 What are the impacts on
generation of dust, smoke,
odorous fumes or other
hazardous gases? Give details
in relation to all the
meteorological parameters.
During construction phase sprinkling will be done so
no dust and odour will be generated at site. The only
source of dust generation at the site during the
operation phase is the traffic movement. However,
regular cleaning of dust from roads shall be taken
care of. No dust generating activities shall be
promoted in the Group Housing, If required,
sprinkling shall be done.
Smoke will be generated from the operation of DG
sets. DG sets shall be bought as per CPCB norms and
shall be maintained properly to keep the emissions
within the prescribed standards. Proper emission
standards will be maintained as per CPCB
guidelines. The basement & STP of the complex shall
be kept properly ventilated to avoid any form of
odorous fumes or accumulation of any hazardous
gases.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
34
The Meteorological parameters are given below:-
Temperature 33°C
Humidity 49%
Wind Speed 10 km/hr
5.3 Will the proposal create
shortage of parking space for
vehicles? Furnish details of
the present level of transport
infrastructure and measures
proposed for improvement
including the traffic
management at the entry &
exit to the project site.
The optimum parking provision is proposed in the
basements, stilt area & surface area. Hence there
will be no shortage of parking space for vehicles.
Total parking provision within the project will be
440 ECS which includes parking for residents,
reserved parking for EWS residents & additional
parking space for the visitors.
5.4 Provide details of the
movement patterns with
internal roads, bicycle tracks,
pedestrian pathways,
footpaths etc., with areas
under each category.
A proper route shall be provided for the traffic
movement as well as pedestrian movement. The
project drive ways will be developed 9m wide or
even wider where majorly one-way movement will
be followed.
5.5 Will there be significant
increase in traffic noise &
vibrations? Give details of the
sources and the measures
proposed for mitigation of the
above.
During operation phase
Since it is a residential project, movement of
vehicles like car, three wheelers, two wheelers will
be there in the colony. One-way traffic movement
will mitigate the traffic conjunction & honking
noises in the colony. Shelter belt shall be developed
within the complex that will further mitigate the
traffic noise.
Though vibrations are not anticipated by the
movement of light vehicles like, cars & two/ three
wheelers, however, the foundation shall be made
very hard and paved with rubber flooring to
minimize the vibration, also all necessary measures
will be adopted during designing that there will not
be any cause of vibrations during the traffic density.
5.6 What will be the impact of DG
sets & other equipment on
noise levels & vibration in &
ambient air quality around
the project site? Provide
details.
There would be slight impact of DG sets on noise
levels, vibration and in ambient air quality around
the project site.
All the DG Sets of the proposed project will be
acoustically enclosed and be kept in acoustically
treated room.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
35
Stack height as per C.P.C.B. norms to reduce the
impact on air quality around the project site will be
provided.
The noise from DG sets will meet the desired
standard as per C.P.C.B. guidelines. Low Sulphur fuel
will be used to run these DG sets.
Vibration pads will be used to run these DG sets to
minimize the vibration effect.
6. AESTHETICS
6.1 Will the proposed constructions in any way result in the obstruction of a view, scenic amenity or landscapes? Are these considerations considered by the proponents?
Presently the land does not have any scenic amenity or beauty. Construction of the colony will increase the beauty of the area by having proper landscaping. Yes, all considerations have been taken by the proponents.
6.2 Will there be any adverse impacts from new constructions on the existing structures? What are the considerations taken into account?
No existing structure at site, however, there are a few trees and bushes exist at site which will be cut taking prior permission. Also, green area will be developed within the proposed project. Hence, no adverse effects are foreseen.
6.3 Whether there are any local considerations of urban form & urban design influencing the design criteria? They may be explicitly spelt out. Are there any anthropological or archaeological sites or artifacts nearby? State if any other significant features in the vicinity of the proposed site have been considered.
There are no typical urban form & urban design
influencing the design criteria.
There are no Anthropological Site near the project.
Details of archaeological sites are given in EMP
report.
All significant features have been considered.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
36
7. SOCIO-ECONOMIC ASPECTS
7.1 Will the proposal result in any
changes to the demographic
structure of local population?
Provide the details.
The proposed project is a Group Housing & thus
there will be influx of population in the form of
residents, staffs & visitors. Thus, there will be some
change in the demographic structure of the area.
7.2 Give details of the existing
social infrastructure around
the proposed project.
Hospital Hospital near Fatehpur Beri Hospital near Sat Bari Poultary Farm Hospital near Junapur Post Office Post Office near Fatehpur Beri Post Office near Asola Post Office neari Junapur Place of Worship Temple near Chandan Haula Mosque near Chandan Haula Temple near Fatehpur Beri Schools Thana Pal Ka Jila Katihar Sali Pur Gaon Sarkari School Chandanhaula Nagar Nigam Prathmik Vidyalay ChandanHaula R.C.C.E. Public School near Mehrauli, Main Chhatarpur Rd. Chandan Haula Banks Punjab Nation Bank, Asola Canara Bank, Asola State Bank of India-Customer Service Point near Church Fatehpur Beri
0.64 Km SE 2.02 Km NNE 2.68 Km W 0.83 Km SSW 1.13 Km SSE 2.91 Km NWW 0.29 Km N 0.33 Km NNE 0.47 Km SSW 0.27 Km NWW 0.34 Km NNE 0.39 Km NNE 0.04 Km SSW 0.38 Km SSW 0.85 Km SSW
7.3 Will the project cause adverse
effects on local communities,
disturbance to sacred sites or
other cultural values? What
are the safeguards proposed?
The proposed colony will be constructed within the
designated site as per the defined building by-laws
of government authority. There is no sacred site or
cultural heritage site within vicinity of proposed
project; hence no adverse impacts are envisaged.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
37
8. BUILDING MATERIALS
8.1 May involve the use of building materials with high-embodied energy. Are the construction materials produced with energy efficient processes? (Give details of energy conservation measures in the selection of building materials and their energy efficiency
The major materials required for construction of the project are steel, cement, bricks, flooring tiles/ stones, sanitary and hardware items, electrical fittings, etc. Energy efficient building material are being used.
8.2 Transport and handling of materials during construction may result in pollution, noise & public nuisance. What measures are taken to minimize the impacts?
Yes, transportation and handling of material results in air & noise pollution.
The air & noise pollution will be minimized by
covering material by tarpaulin and ensuring PUC
certificate of vehicles and good condition of
silencers. Sprinkling shall be done on the site.
Detailed measures of air & noise pollution control
during construction phase are given in the EMP
report.
8.3 Are recycled materials used in roads and structures? State the extent of savings achieved?
Yes, Following Recyclable waste will be used in
roads
• Cement jute bags, plastic bags etc. will be
used in roads
• Construction debris like Concrete will be
recycled and will be used in parking area and road
area.
• Sub Stratum removed during foundation
& excavation will be used for plot filling & making
pathways.
• Brick work wastage will be used for
pavements and parking area.
• Cut Tiles & chips will be used in creating
pathways in the landscape area & rest will be sent
to the construction & demolition facility.
• No recycled materials used in structures.
However, fly-ash mixed cement, concrete shall be
used.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
38
8.4 Give details of the methods of collection, segregation & disposal of the garbage generated during the operation phases of the project.
Collection: The different colour coded bins shall
be placed at different location within the group
housing colony. The bins will be emptied into the
main bins of the colony
Segregation: The solid waste will be segregated
at individual house levels or at the garbage room.
Disposal: From the main bins, service provider
will collect organic waste 92 Tons/annum
(Consisting of kitchen waste, wood, leaves and
branches etc) from green bins shall be treated by
using organic waste converter and converted to
manure. 46 Tons/annum recyclable waste
(Paper, Glass, Metals etc) will be given to
authorized recycler & 15 Tons/annum of plastic
waste shall be given to the authorized recycler.
9. ENERGY CONSERVATION
9.1 Give details of the power requirements, source of supply, backup source etc. What is the energy consumption assumed per square foot of built-up area? How have you tried to minimize energy consumption?
Power Requirement – 3400 KW Source of Power: BSES Back-up Source: Power back up is proposed by using D.G. Sets of capacity 3 x 1010 KVA To minimize energy consumption following measures shall be adopted: LED, Solar panel, energy efficient lifts, energy efficient motors and pumps shall be used to conserve the electrical energy. During power failure D.G. Sets will start automatically. Fuel consumption for DG sets has been calculated to be 480 lt/hr (when in operation) of Ultra Low Sulphur Diesel. They will be having efficiencies as per the latest CPCB norms. D.G. Sets have to be installed in acoustically enclosed room and fitted with silencer. All cables shall be debated to avoid heating during use. This also indirectly reduces losses and imposes reliability. Consumption of non-renewable fuel shall be minimized. Solar panels shall be installed in the complex.
9.2 What type of and capacity of power back-up do you plan to provide?
DG Sets: 3 x 1010 KVA
Fuel: Ultra Low sulphur diesel.
Solar backup details: -
• Solar energy by installing Solar Photovoltaic
panels will be generated.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
39
9.3 What are the characteristics of the glass you plan to use? Provide specifications of its characteristics related to both short wave and long wave radiation?
Plain glass (single glazed) will be used in the
complex.
Specification of plain single glazed Glass is given below: ‘R’ Values (in Sq m. Deg C/ Watt): 0.14 ‘U’ Values (in Watts/ Sq m. Deg C): 7.1 Solar Heat Gain Co-efficient: 0.82
9.4 What passive solar architectural features are being used in the building? Illustrate the applications made in the proposed project.
Shading devices and fenestration have been
adequately designed to cut off, summer sun and to
let in winter sun.
Landscaping shall be done so that wind direction will
be favourably altered.
The architectural features will be such that max day
light provision will be provided.
9.5 Does the layout of streets & buildings maximize the potential for solar energy devices? Have you considered the use of street lighting, emergency lighting and solar hot water systems for use in the building? Substantiate with details.
Yes, the layouts of blocks are designed to maximize
the potential for use of solar lighting per day
devices.
Solar energy by installing Solar Photovoltaic panels
will be generated.
9.6. Is shading effectively used to reduce cooling/heating loads? What principles have been used to maximize the shading of Walls on the East and the West and the Roof? How much energy saving has been effected?
Use external shading devices over openings, such as
wider eaves, window awnings and deep verandas or
pergolas with louvres set to the correct angle, will be
made.
Shading devices and fenestration have been
adequately designed to cut off, summer sun and to
let in winter sun.
9.7 Do the structures use energy-efficient space conditioning, lighting and mechanical systems? Provide technical details.
Provide details of the transformers and motor efficiencies, lighting intensity and air-conditioning load assumptions?
Space conditioning will be provided as per norms of
National Building Code – Part 8; Building Services
Section 3–Mechanical Ventilation.
As it is a Group housing with no in built provision for
space cooling, Energy efficiency in lighting and
mechanical systems will be achieved by following
measures:
• Purchase of energy efficient appliances
• Constant monitoring of energy consumption
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
40
Are you using CFC and HCFC free chillers? Provide specifications
• Adjusting the settings and illumination levels
to ensure minimum energy used for desired
comfort levels
• Installing programmable on/off timers and
sensors for low occupancy areas
• Uses of incandescent lamp and halogen
lamps have been avoided and energy
efficient LED shall be used for all common
area.
Lighting intensity will be done as per the National
Building Code Guidelines. As the building is
residential, we are not providing any air-
conditioning or chillers. Energy efficient motors will
be used only to lift water to overhead water tanks,
STP and for firefighting systems.
Motors: As per IS-2165, energy efficient motors
shall be used.
• Motors upto 1 HP shall be having energy
efficiency upto 80%,
• Motors upto 10 HP shall be having energy
efficiency upto 80-90%
• Motors above 10 HP shall be having energy
efficiency upto 90-95%,
Transformers: As per Bureau of Energy Efficiency,
high efficiency (4-5 Star rating) transformers shall be
used.
Lux Level in the residential area: 10 W/sqm
Lux Level in the commercial area: 15 W/sqm
This is a Group Housing hence, no centralized HVAC
shall be provided. Hence, no use of CFC and HCFC
free chillers.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
41
9.8 What are the likely effects of the building activity in altering the micro-climates? Provide a self-assessment on the likely impacts of the proposed construction on creation of heat island & inversion effects?
Predominant wind direction is from West to East,
there will be free flow of wind.
Building orientation is done in such a way that all the
blocks will have good natural cross ventilation.
Energy efficient construction material will be used to
achieve desirable thermal comfort. As the proposed
project involves construction of building which are
heat absorbing thus to counter the heat absorbing
effect facade of low U & R Value and proper
plantation will be provided.
Plantation will be done to reduce heat island effect
near pedestrian circulation area, passive and active
open space to enhance human comfort within the
development and the neighbourhood.
9.9 What are the thermal characteristics of the building envelope? (a) roof; (b) external walls; and (c) fenestration? Give details of the material used and the U-values or the R values of the individual components.
S. No
BUILDING MATERIAL PROPOSED WITH U & R VALUES
‘R’ Values (in Sq m. Deg C/ Watts )
‘U’ Values (in Watts/ Sq m. Deg C)
Solar Heat Gain Factor
1. Wall Brick & ACC Blocks wall (230 mm thick), both side thick sand cement plaster (12-18mm) with insulation.
2.28 0.44 0.011
2. Roof 200 mm RCC slab with mud phuska & clay tiles with 75 mm insulation.
2.04 0.49 0.01
9.10 What precautions & safety measures are proposed against fire hazards? Furnish details of emergency plans.
NBC 2016 Guidelines for Group Housing colony shall
be followed.
9.11 If you are using glass as wall material provides details and specifications including emissive and thermal characteristics.
No, glass is not being used as wall material. Only
Plain openable glass windows shall be provided
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
42
9.12 What is the rate of air infiltration into the building? Provide details of how you are mitigating the effects of infiltration.
The air inflow and outflow shall be maintained as per
norms.
Guideline will be provided to individual plot owner
to maintain proper ventilation in the kitchen and
toilet.
*Proper Inflow and outflow of air shall be
maintained and proper dilution shall be provided by
using air exhaust to maintain air quality.
9.13 To what extent the non-conventional energy technologies are utilized in the overall energy consumption? Provide details of the renewable energy technologies used.
Solar energy will be used inside the colony by
installing Solar Photovoltaic panel.
1% of total energy will be saved by using Solar
power generation.
10. ENVIRONMENT MANAGEMENT PLAN
10.1 The Environment Management Plan would consist of all mitigation measures for each item wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire.
Environment Management Plan is given as ENCLOSURE -3
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
43
CONCEPTUAL PLAN
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
44
CONCEPTUAL PLAN
Introduction A “Group Housing” is proposed at village Chandanhaula, Lal Dora area, Hauz Khas, New
Delhi which by Wellworth Realtech LLP. The land was purchased from M/s Amit
Landscappers Pvt Ltd by M/s Wellworth Realtech Pvt ltd (now known as M/s Wellworth
Realtech LLP). As per the Master plan of Delhi (2021), land use of the site is for urban
development.
Activities/ Amenities • Dwelling Units
• EWS
• Servant Units
• Club & community building
• Commercial building
Site Location The project site is located at village chandanhaula (Lal Dora area) Tehsil Hauz Khas, New
Delhi. The location of the project site is shown in Environment Report.
Type of Project The project “Group Housing” is proposed to be developed on a total plot area of 10871
m2 (1.0871 ha). The built-up area of the project will be 42253.97 m2 which is less than
1, 50,000 m2. Hence, it falls under category 8 (a) of EIA Notification, 2006.
Project Details
The total plot area of the project will be 10871 m2 (1.0871 ha), out of which net planned
area is 9971.25 sqm and 899.75 sqm will be deducted under road widening. 3320.44 m2
shall be utilized as ground coverage. Total FAR proposed for project will be 22910.85 m2.
The NON-FAR will be 6583.0 m2, total basement area will be 12760.16 m2 & the built-up
area of the project will be 42253.97 m2. Total 2 nos. of main towers are proposed and
maximum no. of floors will be G+16. The maximum height of the building will be 78.0 m.
Project details are given in Table below:
Table 2-1: Project Details
S.No. Description Unit Details
1. Project Cost Crore 106
2. Total Plot Area sqm 10871 (1.0871ha)
Area under road widening sqm 899.75
Net planned area sqm 9971.25
3. Ground Coverage (Permissible) (33%) sqm 3320.44
4. Ground Coverage (Achieved) (17 %) sqm 1701.09
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
45
5. Total FAR (Permissible) (200%) sqm 19942.6
6. FAR proposed
FAR – main Dwelling Unit sqm 19912.79
FAR – EWS unit sqm 2998.06
Total FAR Proposed (A) sqm 22910.85
7. NON-FAR AREA
Area for swatch delhi block and ward cabin
sqm 46
Stilt Area sqm 3615.74
Area under swimming pool sqm 100
Proposed for community sqm 399.89
Balcony area sqm 2421.33
Total Non-FAR (B) sqm 6583.0
8. Basement Area
Basement Level -1 sqm 6380.08
Basement Level-2 sqm 6380.08
Total basement Area (C) sqm 12760.16 9. Built-up Area (A+B+C) sqm 42253.97
10. Green Area (33% of the net plot area) sqm 3331.69
11. No. of Floors No. G+16
12. No. of Towers/Block No. 2
13. No. of Basement (level) Level 2
14. Maximum Height of Building m 78.0
15. No. of DU No. 115
16. No of EWS No. 82
17. No of Servant unit No. 44
18. Total Population No. 1027
19. Total Solid Waste Generation Ton/Annum 153
20. Total Water Requirement KLD 152
21. Total Waste Water Generation KLD 112
22. STP Capacity KLD 135
23. Rain water Harvesting No. 3
24. Total Power Load KW 3400
25. DG Sets KVA 3 x 1010 KVA
26. Parking Required ECS 421
27. Parking Provided ECS 440
Population Details During Construction Phase- 150 Nos. of local labour will be employed for the
construction of the project.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
46
During Operation Phase- the total population of the project has been estimated to be 1027 persons including residents, staff, visitors.
The population details are given in Table below.
Table 2-2: Estimation of Population
Population of Residential
Dwelling Units (DU) 115 4.5 Person/DU 518
EWS 82 4.5 Person/EWS 369
Total Residents 887
Staff 40
Visitors 100
TOTAL POPULATION 1027
Water Management Water Requirement
During construction phase- Total 15 KLD of water will be required out of which 5 KLD of
treated water will be arranged on temporary basis for construction activities, which will
be sourced through nearby STP and 10 KLD of water will be required for labours for
domestic & flushing purposes which will be sourced through tankers. Mobile toilets shall
be provided at site for labourers which shall be regularly cleaned.
During operation phase- Total 152 KLD water requirement will be met through supply
to be arranged by DJB. The amount of waste water generated will be 112 KLD from the
project which will be treated in STP of 135 KLD Capacity.
The total water management has been given in Environment Report.
Rain water collection Details The main source of ground water recharging in the study area is rainwater, which
infiltrates into the ground through various lithological units present in the study area.
Total 3 no. of Rain Water Harvesting structures shall be provided in the project site to
recharge the ground. Details are given in Environment Report.
Power Requirement& Back-up During Construction Phase- DG sets of 3 x 1010 KVA will be used for construction works.
During Operation Phase- The total power requirement of the project will be 3400 KW
which will be met by BSES. In case of power failure, power backup will be provided
through DG sets of 3 x 1010 KVA. Stack height of 6 m above roof level will be maintained.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
47
Solid & Hazardous Waste Management During Construction Phase- Approx. 51040 cum of soil will be excavated due to
excavation of 2 levels basement & foundation. Total 23 kg/day of waste will be
generated from labourers. One two floor small building and one temporary structure
exist at site, which will be demolished. Construction & Demolition waste debris
generated from site shall be used in backfilling & levelling purposes & rest shall be
disposed off to C & D facility. Recyclable material of construction phase like aluminium,
steel, wood pieces, cement bags, plastic containers, cartons, glass etc. will be sold to
recyclers.
During operation phase- Total 153 Ton/annum solid waste will be generated from the
project. 92 Ton/annum of bio-degradable waste generated will be treated in organic
waste convertor proposed within the site, 61 Ton/annum of Non- Biodegradable waste
shall be given to approved recycler and 15 Ton/annum of Plastic waste shall be given to
approved recycler.
0.08 kilo ltrs/annum used oil shall be generated which will be sent to approved vendor.
E-waste generated will also be given to approved vendor.
Battery waste shall be generated from inverters & UPS. It will be properly managed as
per Batteries (Management and Handling) Rules 2001.
Parking Management During construction phase- Proper parking provisions for trucks and other construction
vehicles shall be made. Proper spaces for loading and unloading shall be defined.
During operation phase- Total parking requirement will be 421 ECS. Provision of 440
ECS will be provided. Details are given in Environment Report.
Green Area Development At present, the land has total 161 no. of trees out of which 81 nos. are required to be cut/
transplanted in order to develop the roads, basement, and buildings of the Group
Housing Colony. However, mostly trees are young trees and permission required is only
for 6 number of trees, which will be cut/ transplanted only after obtaining the Tree
Cutting/ transplanting permission from Forest department & remaining 80 no of trees
shall be retained the site. Development of Group Housing includes development of a
plantation area including big foliage trees, herbs, shrubs and grasses in the form of
Green Belt, Periphery plantation, Avenue plantation and lawns within the site. Total
plantation area for the project will be approx. 3331.69 m2, i.e.33 % of the net plot area.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
48
ENVIRONMENT REPORT
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
49
ENVIRONMENT REPORT Application for Environmental Clearance
Of
GROUP HOUSING
At
Khasra nos. 533/1 & 533/2
Village Chandanhaula, Tehsil Hauz Khas, New Delhi
Developed by
Wellworth Realtech LLP
1497, Bhardwaj Bhawan, Wzir Nagar,
Kotla, Mubarak Pur, New Delhi-110003
Prepared By:
M/s PERFACT ENVIRO SOLUTIONS PVT. LTD.
(NABET Registered wide list of accredited consultants organizations/ Rev 72/ January,
2019 at S.No.-117)
505, 5th Floor, NN Mall, Mangalam Palace, Sector-3, Rohini, New-Delhi-85
Phone: 011-49281360
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
50
EXECUTIVE SUMMARY OF THE PROJECT
3.1.1 Activities:
The project is a “Group Housing” is proposed at village Chandanhaula ( Lal Dora area,
Hauz Khas, New Delhi which by Wellworth Realtech LLP. The land was purchased from
M/s Amit Landscappers Pvt Ltd by M/s Wellworth Realtech Pvt ltd (now known as M/s
Wellworth Realtech LLP). As per the Master plan of Delhi (2021), land use of the site is
for urban development. Project includes Dwelling Units, EWS, Servant units, Club &
Commercial building.
3.1.2 Description & Details of Project:
The total plot area of the project will be 10871 m2 (1.0871 ha), out of which net planned
area is 9971.25 sqm and 899.75 sqm will be deducted under road widening. 3320.44 m2
shall be utilized as ground coverage. Total FAR proposed for project will be 22910.85 m2.
The NON-FAR will be 6583.0 m2, total basement area will be 12760.16 m2 & the built-up
area of the project will be 42253.97 m2. Total 2 nos. of main towers are proposed and
maximum no. of floors will be G+16. The maximum height of the building will be 78.0 m.
Project details are given in Table below.
Table 3-1: Project Details
S.No. Description Unit Details
1. Project Cost Crore 106
2. Total Plot Area sqm 10871 (1.0871ha)
Area under road widening sqm 899.75
Net planned area sqm 9971.25
3. Ground Coverage (Permissible) (33%) sqm 3320.44
4. Ground Coverage (Achieved) (17 %) sqm 1701.09
5. Total FAR (Permissible) (200%) sqm 19942.6
6. FAR proposed
FAR – main Dwelling Unit sqm 19912.79
FAR – EWS unit sqm 2998.06
Total FAR Proposed (A) sqm 22910.85
7. NON-FAR AREA
Area for swatch delhi block and ward cabin
sqm 46
Stilt Area sqm 3615.74
Area under swimming pool sqm 100
Proposed for community sqm 399.89
Balcony area sqm 2421.33
Total Non-FAR (B) sqm 6583.0
8. Basement Area
Basement Level -1 sqm 6380.08
Basement Level-2 sqm 6380.08
Total basement Area (C) sqm 12760.16
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
51
9. Built-up Area (A+B+C) sqm 42253.97
10. Green Area (33% of the net plot area) sqm 3331.69
11. No. of Floors No. G+16
12. No. of Towers/Block No. 2
13. No. of Basement (level) Level 2
14. Maximum Height of Building m 78.0
15. No. of DU No. 115
16. No of EWS No. 82
17. No of Servant unit No. 44
18. Total Population No. 1027
19. Total Solid Waste Generation Ton/Annum 153
20. Total Water Requirement KLD 152
21. Total Waste Water Generation KLD 112
22. STP Capacity KLD 135
23. Rain water Harvesting No. 3
24. Total Power Load KW 3400
25. DG Sets KVA 3 x 1010 KVA
26. Parking Required ECS 421
27. Parking Provided ECS 440
INTRODUCTION OF THE BACKGROUND INFORMATION
3.2.1 Brief Description of the Nature of the Project:
The project is a “Group Housing” is proposed at village Chandanhaula ( Lal Dora area,
Hauz Khas, New Delhi which by Wellworth Realtech LLP. The project will provide a
better living to the people along with amenities, the activities in the proposed project
are:
Sr. No. Activities No.
1 No. of Dwelling Units 115
2 No. of EWS 82
3 Servant Unit 44
PROJECT DESCRIPTION
3.3.1 Land Use and Ownership of the site land
The land was purchased from M/s Amit Landscappers Pvt Ltd by M/s Wellworth Realtech
Pvt ltd (now known as M/s Wellworth Realtech LLP). As per the Master plan of Delhi
(2021), land use of the site is for urban development. The land use and land cover will
change to group housing.
Presently, the land has total 161 no. of trees out of which 81 nos. are required to be cut/
transplanted in order to develop the roads, basement, and buildings of the Group
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
52
Housing Colony. However, mostly trees are young trees and permission required is only
for 6 number of trees, which will be cut/ transplanted only after obtaining the Tree
Cutting/ transplanting permission from Forest department & remaining 80 no of trees
shall be retained the site.
The land use proposed at the site is given in Table below & Figure below.
Table 3-2: Land use proposed for the project Site
Land Use Area (sqm) Percentage
Ground Coverage 1701.09 17.05%
Green Area 3331.69 33.41%
Road & Open area 4938.47
49.54%
Net Planned Area 9971.25 100.00%
Land use Diagram:-
3.3.2 Location of the project with connectivity Details of connectivity are shown in Table below.
Table 3-3- Site Connectivity
S.No. Accessibility Description Distance & Direction
1. Highway/ Road Main Chhatarpur Road NH -236 NH-8 NH-2
0.02 Km E 4.55 Km NW 9.83 Km NW 12.22 Km NE
17.05%
33.41%
49.54%
Land use Diagram
Ground Coverage
Green Area
Road & Open area (inclu)
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
53
2. Railway Station Chhatarpur Metro Station Saket Metro Station Tughalaqabad Rly. Station Okhla Railway Station
4.69 Km NNW 6.35 Km NNE 11.60 Km NE 13.01 Km NE
3. Airport IGI Airport Delhi Safdarjung Airport
13.02 Km NW 13.35 Km NNE
3.3.2.1 Geographical Information of Site
Latitude Longitude Elevation
28°27'54.19"N 77°11'6.97"E 264 m
3.3.2.2 Map on Google
Location map is shown in Figure 1.
Figure 1: Location Map
3.3.2.3 Topographical Map
Topographical map is shown in Figure 2.
Figure 2 : Topographical Map
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
54
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
55
3.3.2.4 Layout Plan
The layout plan is given in figure 3.
Figure 3: Layout Plan
Resources
3.4.1 Water Resource Management
3.4.1.1 Present Quality
The present quality of the water environment has been accessed and Test reports is
enclosed as Annexure - 13.
3.4.1.2 Water Requirement
During construction phase, for construction activities, treated water will be arranged on
temporary basis which will be sourced through nearby STP. Drinking water for labourers
will be sourced through the tankers.
Total water requirement during construction phase will be 15 KLD, out of which 8 KLD
shall be used by labours for domestic & flushing purposes and 7 KLD of water will be
used for construction activities. Waste water will be generated from the labours which
will be disposed to Mobile toilets and will be regularly cleaned.
During operation phase, fresh water will be met through DJB.
The total water requirement has been shown in the Table below:
Table 3-4: Water Requirement
S.No. Particulars Population Factor in LPCD
TOTAL requirement (KLD) Waste Water (KLD)
Total (KLD)
Domestic (KLD)
Flushing (KLD)
Total (KLD)
N
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
56
Water Balance
1. Domestic
Resident 887 135 120 76 44
Staff 40 45 2 1 1
Visitors 100 15 2 1 1
Sub Total 1027 124 KLD
78 KLD 46 KLD
2. Waste Water
62 KLD 46 KLD 112 KLD
3. Gardening @ 5ltr/sqm 3 Nil
4. Swimming Pool
5 Nil
5. DG Cooling 15 Nil
6. Misc. 5 4
Total 152 KLD 112 KLD
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
57
3.4.1.3 Source of Water
The water will be resourced through Municipal Supply/ DJB.
3.4.1.4 Disposal
Total quantity of wastewater generation from the complex will be 112 KLD. The
generated sewage will be treated in in-house sewage Treatment Plants of total capacity
135 KLD. Total 69 KLD of treated water will be utilized to the extent possible for flushing,
gardening & miscellaneous purposes & the rest 32 KLD excess treated water shall be
discharged to sewer line of the area.
3.4.2 Energy Resource Management
3.4.2.1 During Construction
DG sets of 62.5 KVA shall be used for Power supply during the construction phase.
3.4.2.2 During Operation
During operation phase 3400 KW of electric load from BSES shall be supplied to the
Colony. Power backup for common utilities shall be provided by DG set of 3 x 1010 KVA.
3.4.2.3 Conservation
Following are the measures adopted to conserve the energy:
• We shall provide LED lights for common areas, street lighting & basement
lighting.
• Solar power shall be generated by installing Solar Photovoltaic panel.
• Energy Efficient (VVVF Non-gear) lifts shall be used.
• Energy Efficient/ load sharing DG sets shall be used.
• The motors used by pumps proposed in the project shall be energy efficient
complying with the ECBC norms.
3.4.3 Air Quality at Site
The present quality of the air has been accessed and Test reports are enclosed as
Annexure-13.
3.4.4 Noise Quality at Site
The present Noise quality has been accessed and Test reports are enclosed as
Annexure-13.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
58
SITE ANALYSIS
3.5.1 Eco-sensitive areas with distance from project location1 The eco sensitive zones with distance from the project location are given in Table below:
Table 3-5: Eco sensitive sites around the project site
S. No Areas Name/ Identity
Aerial distance (within 15 km.) from Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value
Asola Wild Life Sanctuary
1.87 Km SEE
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests
Water Bodies Drain near Project Site Sharpur Nala Pond near Junapur Rohar Nala Pond near Aya Nagar Shamsi Talab Ghitorni Lake Bhuriya Nala Neela Hauz Jauhar Nala Kaunsat Nala Dhulainti Nala Bhawaro Nala Hauz Khas Tank Suraj Kund Li Nala Badkal Lake Forest Forest near Aya Nagar Extension Rajokari Protective Forest Jahanpanah City Protective Forest Fairly Dence Forest near Hamdard Nagar Forest near Hauz Khas
0.06 Km SWW 1.01 Km SSW 2.84 Km W 4.61 Km S 5.22 Km NWW 5.25 Km NNW 5.27 Km NWW 5.44 Km SEE 7.15 Km NNW 7.27 Km S 7.30 Km SSW 8.58 Km SSW 9.14 Km SW 9.72 Km NNE 9.78 Km NEE 10.02 Km SW 10.17 Km SE 6.88 Km W 7.20 Km NW 7.89 Km NE 8.24 Km NE 8.98 Km NNE
1 As per Topographical Map and Google Earth
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
59
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration
Asola Wild Life Sanctuary
1.87 Km SEE
3.5.2 Centrally Protected Monuments Under Delhi Circle2
Name of Monuments Locality District
Distance & Direction
Mosque known by the name of ShamsiTallab together with both platform entrance gates.
Mehrauli Village South 5.33 Km NNW
HauzShamsi, with central red stone pavilion situated at Mehrauli in field Nos. 1574-81, 1588-97, 1614, 1623 & 1624, owner Government
Mehrauli South
5.41 Km NNW
Jahaz Mahal in Mehrauli Mehrauli Village South 5.45 Km NNW
Mandi Mosque Lado Sarai Village South 5.49 Km N
Moti Masjid Mehrauli Village South 5.98 Km NNW
Old Palace of Bahadur Shah II alias Lal Mahal in Mehrauli
Mehrauli Village South 5.99 Km NNW
Tomb and Mosque of MaulanaJamaliKamali Mehrauli South 6.01 Km N
Area between Balban Khan's Tomb &JamliKamali
Lado Sarai South 6.02 Km N
Rajon-ki-Bain with Mosque and Chatri Lado Sarai Village South 6.10 Km NNW
Old Baoli known as Diving Wall in Mouza locally known as (Gandak-ki-baoli), Mehrauli
Mehrauli South 6.17 Km NNW
Unknown tomb said to be of Azim Khan Lado Sarai Village South
6.28 Km NNE
Badaun Gates, Lado Sarai Village South 6.29 Km NNE
Tomb of Adham Khan (Rest House) Mehrauli South 6.40 Km NNW
The Qutab Archaeological area as now fenced in, including the Mosque, Iron Pillar, Minar of Qutbud-din, unfinished Minar, all colonnades, screen arches, tomb of Altamash, college, buildings of Alaud-Din, Tomb of Imam Zamin and all carved stones in the above area with gardens, paths and water channels, and all
Mehrauli Village South
6.55 Km NNW
2 As per Archaeological Survey of India
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
60
gateways including the Alai-Darwaza , also all graves in the above area
Iron Pillar, Hindu remains Mehrauli (Qutb Complex)
South 6.60 Km NNW
Ramp and gateways of Rai Pithora's Fort, Adchini
Adchini South 7.15 Km NNE
Walls of Lal Kot and Rai Pithora's fort from Sohan Gate to Adham Khan's tomb including the ditch where there is an outer wall
Mehrauli South 7.26 Km NNW
Khirkee Masjid Khirki Village near Malviya Nagar
South 8.04 Km NNE
Satpula-III –216 Khirki Village near Malviya Nagar
South 8.21 Km NNE
Tomb of Usuf-Quttal situated at Khirki Khirki Village near Malviya Nagar
South 8.26 Km NNE
Begumpuri Masjid Begumpur South 8.42 Km NNE
Bastion, where a wall of Jahan panah meets the wall of Rai Pithora’s fort, Adchini
Adchini South 8.55 Km NNE
Wall of Rai Pithora's Fort and Jahan panah at the point where they meet together
Hauz Rani Village South 8.55 Km NNE
Bijay Mandal, neighbouring domes, buildings and dalan to north of Begumpur
Malviya Nagar South 8.57 Km NNE
Group of monuments at Sarai Shahji Malviya Nagar South 8.67 Km NNE
Lal Gumbad, Chirag Delhi Chirag Delhi South 8.71 Km NNE
Tomb of Sheikh Kaburuddin also known as RakabwalaGumbad in field no.84 min. situated at sarai Shah 31 property of ThoksShahpur and Adhehini
Malviya Nagar South
8.72 Km NNE
Tomb of GhiyasuddinTughlakabad. walls and bastions, gates and cause way including the tomb of Dad Khan
Tughlaqabad South East
8.83 Km NE
Tomb of Sultan Ghari
MalikpurKothi opposite Vasant Kunj
South 8.85 Km NNW
Tomb of Bahlol Lodi Chirag Delhi South 9.05 Km NNE
Walls, gateways bastions and internal buildings of both inner and outer citadels of Tughlakabad Fort
Tughlaqabad South East
9.10 Km NE
Nai-ka-kot in Tughlaqabad Tughlaqabad
South East 9.11 Km NE
Walls, gate and bastions of Adilabad (Mohammadabad) and causeway leading there to from Tughlakabad.
Tughlaqabad South East
9.15 Km NEE
ChorMinar No. 289 Vol III HauzKhas South 9.33 Km NNE
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
61
Idgah of Kharehra HauzKhas Enclave South 9.42 Km NNE
TohfewalaGumbad
Humayunpur Village (HauzKhas), ShahpurJat
South
9.62 Km NNE
HauzKhas:- Group of Building at HauzKhas consisting of the following i. The tomb of Ferozshah ii. Domed Building to the west of No.1 iii. Dalan between 1&2 iv. Domed Building & its court to the south of No. 3, v. Dalans and all ruined Buildings to the north of no. 1 and existing upto No.10 vi. Five Chhatris to the East of No. 1& No.5 vii. Old Gate to the north of No.6 viii. Three Chhatris to the north-west of No.7 ix. Ruined courtyard and its Dalans with the Domed building to the north-west to the No.8 x. Old wall running east from No.4 xi. 2.23 Acres of land surrounding the above monuments and bouded on the North by house of Chhange and Mehra Chand sons of Hansram and house of Udairam, son of Kushla South Ghairmumkan Rasta East By village site belonging to village community. Others West By field no. 185 & 186.
HauzKhas South
9.75 Km NNE
Bara Khamba-285 HauzKhas South 9.82 Km NNE
Sakri Gumti-284
HauzKhas Enclave near Green Park
South 9.86 Km NNE
ChotiGumti HauzKhas South 9.88 Km NNE
Biwi or Dadi-ka-Gumbad-281 HauzKhas South 9.91 Km NNE
Bandi or PotikaGumbad III-280 HauzKhas South 9.92 Km NNE
Ruined line of walls, bastions & gateways of siriKh. No. 88, 265 &447 pf village ShahpurJat
ShahpurJat Village
South 9.95 Km NNE
Nili Mosque HauzKhas Enclave South
9.99 Km NE
Biran-Ka-Gumbad-282 HauzKhas South 10.13 KM NNE
Bagh-i-AlamGumbad with a Mosque
Humayunpur Village (HauzKhas)
South 10.14 Km NNE
Kali Gumti HauzKhas South 10.20 NNE
Munda Gumbad, Munirka Munirka South 10.64 Km NNW
Baoli, Munirka Munirka South 10.79 Km NNW
Wazir Pur-ki-Gumbad, Munirka 312 Munirka South
10.84 Km NNW
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
62
Tin BurjiWalaGumbad, MommadPur Village Mohammad Pur Village
South 11.18 Km N
Moth-ki-Masjid Behind South Extension-II
South 11.26 Km NNE
Tomb of Bhura Khan KotlaMubrakpur Village
South 12.34 Km NNE
Mosque attached to Mubarak shah Tomb
KotlaMubrakpur Village
South 12.38 Km NNE
Ashokan Rock Edict at Bahapur East of Kailash
South East 12.38 Km NNE
Tombs of Bade-Khan, and MubarakpurKotla, Kotla
KotlaMubrakpur Village
South 12.40 Km NNE
Tombs of Chote Khan, Mubarakpur, Kotla KotlaMubrakpur Village
South 12.40 Km NNE
Tomb of Mubarik Shah in Mubarikpur, Kotla KotlaMubrakpur Village
South 12.44 Km NNE
Bara Pulah bridge near Nizammudin Nizamuddin
South East 14.72 Km NNE
Tomb of Khan-i-Khana Nizamuddin
South East 14.89 Km NNE
The Grave of Jahanara Begum Nizamuddin
South East 14.98 Km NNE
Tomb of Amir Khusro Nizamuddin
South East 14.99 Km NNE
Tomb of NizamuddinOlia Nizamuddin
South East 15.00 Km NNE
The Grave of Mirza Jahangir Nizamuddin
South East 15.00 Km NNE
3.5.3 Annual Windrose Diagram The Wind Rose Diagram of Annual Average (2002-2013) is given in figure below:
Figure 3: Annual Windrose
(source- IMD, Safdurjung)
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
63
3.5.4 Social Infrastructure available
The social infrastructure available at site is given in Table below
Table 3-6: Social Infrastructure near the project site
Areas occupied by sensitive man-
made land uses (hospitals,
schools
, places of worship, community
facilities)
Hospital Hospital near Fatehpur Beri Hospital near Sat Bari Poultary Farm Hospital near Junapur Post Office Post Office near Fatehpur Beri Post Office near Asola Post Office neari Junapur Place of Worship Temple near Chandan Haula Mosque near Chandan Haula Temple near Fatehpur Beri Schools Thana Pal Ka Jila Katihar Sali Pur Gaon Sarkari School Chandanhaula Nagar Nigam Prathmik Vidyalay ChandanHaula R.C.C.E. Public School near Mehrauli, Main Chhatarpur Rd. Chandan Haula Banks Punjab Nation Bank, Asola Canara Bank, Asola State Bank of India-Customer Service Point near Church Fatehpur Beri
0.64 Km SE 2.02 Km NNE 2.68 Km W 0.83 Km SSW 1.13 Km SSE 2.91 Km NWW 0.29 Km N 0.33 Km NNE 0.47 Km SSW 0.27 Km NWW 0.34 Km NNE 0.39 Km NNE 0.04 Km SSW 0.38 Km SSW 0.85 Km SSW
PROPOSED INFRASTRUCTURE
3.6.1 Types of Buildings & Activities Proposed
The proposed project is “Group Housing”. Total 2 no. of towers are proposed. The
activities include dwelling units, EWS units, Servant units, Commercial building,
Community Building & Club.
ENVIRONMENT MANAGEMENT PLAN The Environment Management Plan (EMP) is a site-specific plan developed to ensure
that the project is implemented in an environmentally sustainable manner where all
stakeholders including the project proponents, contractors and subcontractors,
including consultants, understand the potential environmental risks arising from the
proposed project and take appropriate actions to properly manage that risk. Adequate
environmental management measures need to be incorporated during the entire
planning, construction and operating stages of the project to minimize any adverse
environmental impact and assure sustainable development of the area.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
64
The EMP presented below should be followed and regular monitoring of relevant
parameters as stated in post project-monitoring schedule shall be carried out. The EMP
is to be proactive in nature and will be upgraded if new facilities or modification of
existing facilities, with environmental concerns, come up at a later stage.
EMP includes four elements:
• Commitment and Policy: Proposed project will strive to provide and implement
the Environmental Management Plan that incorporates all issues related to air,
land and water.
• Planning: This includes identification of environmental impacts, legal
requirements and setting environmental objectives.
• Implementation: This comprises of resources available to the developers,
accountability of contractors, training of operational staff associated with
environmental control facilities and documentation of measures to be taken.
• Measurement and Evaluation: This includes monitoring, corrective actions, and
record keeping.
3.7.1 ENVIRONMENT MANAGEMENT DURING CONSTRUCTION
3.7.1.1 AIR ENVIRONMENT :-
Air quality around the project will be adversely impacted during the construction stage.
Various construction activities especially related to lose material likely to cause
generation of dust that adversely impacts the air quality of the surrounding area of the
project site. To minimize such impact, following measures will be taken:
• Dust mitigation measures shall be taken as per Environment (Protection)
Amendment Rules, 2018.
• Metallic Roads leading to or at construction sites shall be paved and blacktopped.
• No excavation of soil shall be carried out without adequate dust mitigation
measures in place.
• No loose soil or sand or Construction & Demolition Waste or any other
construction material that causes dust shall be left uncovered.
• Wind-breaker around the project site shall be provided.
• Water sprinkling system shall be put in place using spraying Nozzles.
• Sprinkling shall be done every hour by fixed sprinkling system.
• Grinding and cutting of building materials in open area shall be prohibited.
• Construction and Demolition waste shall be stored only within earmarked area
and road side storage of construction material and waste shall be prohibited.
• Only covered vehicles carrying construction material and waste shall be
permitted inside the complex.
• Construction and Demolition Waste processing and disposal site shall be
identified and required dust mitigation measures be notified at the site.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
65
• DG sets shall be installed acoustically enclosed with adequate stack heights.
Tankers will be used for supply of construction water. Maximum Ground Level
Concentration of PM10 due movement of tankers and operation of DG Set shall be
maintained. Detailed AAQ report is discussed in Dispersion report enclosed as Annexure
- 7. Sprinkling will be done at the source of dust anticipated.
3.7.1.2 WATER MANAGEMENT: -
During the construction of the proposed project, the services required like water supply
and sewage facilities shall be arranged on a temporary basis and the same shall be
maintained without any adverse impact on the environment. Following are the
measures required to manage the water environment at site:
• 15 KLD of water is required during construction phase, out of which 8 KLD of water
for labours for domestic & flushing use which shall be sourced through tankers and
7 KLD of water is required for construction purpose which shall be STP treated water
from nearby area/ STP supplied through Tankers.
• Mobile toilets for construction labours shall be provided which shall be cleaned
regularly and hygienic conditions shall be maintained at site.
• Runoff from the construction site shall not be allowed to stand (water logging) or
enter into the roadside or nearby drain. Adequate measures shall be taken to collect
such run off and either reuse or dispose off at the designated location.
3.7.1.3 NOISE ENVIRONMENT: -
During the construction stage, expected noise levels will be in the range of 80-100 dB(A),
which will decrease with increase in distance. To avoid Noise impacts during night time,
majorly all the noise generating construction activities shall be carried out during the
daytime.
There will be some noise generation due to the movement of vehicles carrying
construction materials and as this will be only a temporary phenomenon, it shall be
managed by properly regulating the movement of vehicular traffic so that the ambient
noise quality will not be adversely affected.
To prevent any occupational hazard, ear muffs / ear plugs shall be given to the workers
working around or operating the plant and machinery emitting high noise levels.
Operation of such plant or machinery shall be strictly prohibited during night hours.
Careful planning of machinery operation and scheduling of operations shall be done to
minimize such impact. Furthermore, following measures shall also be adopted:
• All the machinery and equipment shall be regularly maintained to reduce the noise
level.
• DG sets of capacity 62.5 KVA shall be installed acoustically enclosed.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
66
• Barricading of site shall be done in order to reduce noise impacts outside the project
boundary.
3.7.1.4 SOLID WASTE MANAGEMENT: -
During the construction, approx. 51040 cu m of soil shall be excavated to provide the
basements and foundation. This excavated soil will be properly stacked within the site
and will be reused for back filling purposes. The top soil shall be stored at a designated
area and will be used for landscaping purposes during operational phase of the project.
As soon as proposed green area will be ready the top soil will be transferred and seeding
will be done with regular sprinkling.
One two floor small building and one temporary structure exist at site, which will be
demolished. Construction debris like Concrete will be recycled and will be used in lean
concrete, brick work wastage will be used in waterproofing for terrace, toilets etc. Tiles
will be used in creating pathways, in landscape area etc. Rest of the waste shall be sent
to C & D facility. Recyclable materials like aluminium, steel, wood pieces, cement bags,
plastic containers, cartons, glass etc. will be sold to recyclers.
Approximately 23 kg/day of Municipal solid waste shall be generated from temporary
labours which shall be disposed off at Municipal Landfill site.
Used oil whenever generated from the DG sets shall be kept in a secured place and in
leak prof container and shall be sent to approved recycler
3.7.2 ENVIRONMENT MANAGEMENT DURING OPERATION
3.7.2.1 AIR ENVIRONMENT
DG set of 3 x 1010 KVA will be installed as power backup for common utilities during
power failure. Proper stack height of 6 m above roof level will be maintained which will
help in reducing the air pollution.
Table 3-7: DG set & stack Height
D. G. Set. Capacity No. Stack Height (above roof level)
Stack Height (above ground level)
Location of DG sets
1010 KVA 3 6 meters above roof
level
6.0 m + 78 m
= 84 m
Basement
As per the specifications from D.G. Set manufacturer following emissions shall be
maintained, as given in Table below.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
67
Table 3-8: DG Set emission standards
D. G. Set. Capacity
No. PM mg/Nm3
Nox mg/Nm3
HC mg/Nm3
CO mg/Nm3
1010 KVA 3 75 887.5 100 150
3.7.2.2 WATER MANAGEMENT
Total water requirement has been estimated to be 152 KLD for the proposed project,
out of which fresh water requirement will be 83 KLD which will be met by Municipal/
DJB supply. Water shall be used mainly for domestic, swimming pool, flushing,
gardening, DG Cooling, & Misc. purposes.
Total quantity of wastewater generation will be 112 KLD for the proposed project. The
generated sewage will be treated in Sewage Treatment Plants of capacity 135 KLD. 69
KLD of the treated water shall be reused for flushing, gardening, misc. purposes and 32
KLD of excess treated water shall be discharged to sewer.
3.7.2.2.1 WASTEWATER TREATMENT SCHEME OF SEWAGE TREATMENT PLANT:
In the project, the generation of waste water will be about 112 KLD. The generated
sewage will be treated in in-house Sewage Treatment Plants of total 135 KLD capacity.
Table 3-9: RAW SEWAGE CHARACTERISTICS
The Sewage Treatment Plant (STP) can treat the sewage & effluent of the STP can be
reused for Flushing, Gardening & Misc. purposes.
Table 3-10: TREATED SEWAGE CHARACTERISTICS
pH - 6.5-9.0
BOD mg / l <10
COD mg / l <50
TSS mg / l <20
Oil & Grease mg / l NIL
TREATMENT PROCESS:
Flow M3 / day 112 KLD
pH - 7.5 – 8.0
BOD mg / l 200 - 350
COD mg / l 400 - 500
TSS mg / l 100
Oil & Grease mg / l 10
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
68
It is proposed to treat the complete wastewater in a scientific manner through a
properly planned treatment plant. The objective is to stabilize the decomposable
organic matters present in sewage so as to get an effluent and sludge having
characteristics which are within safe limits. To have an efficient treatment system, this
aeration system is proposed consisting of MBBR Technology. The sewerage treatment
plant can be constructed in such a way that it becomes viable by providing Treated water
for reuse and sludge that can be used as for manure for further use.
Following are the benefits of providing the Sewage Treatment Plant in the present
circumstances:
• It is mandatory as per the latest requirements to provide the Sewage Treatment
Plant.
• Reduced net daily fresh water requirements from various sources, by utilizing
the treated water.
• Reduced dependence on the public utilities for water supply and sewerage
systems & hence reduced stress on environment.
• Dried sludge from the Sewage Treatment Plant shall be rich in organic materials
and is an excellent fertilizer for horticultural purposes.
Different Components of the Plant
In the proposed treatment scheme, the following component unit shall be
provided:
➢ Screen chamber
➢ Bar screen /Grit chamber within effluent collection sump.
➢ Submersible type raw effluent re-lift pumps
➢ Equalization tank
➢ MBBR tank/ Aeration tank
➢ Tube settler
➢ Clarified Water, Filtered Water & Soft Water Storage Tanks
➢ Filter feed pump
➢ Tertiary Treatment Units (Filtration, U.V treatment)
➢ Treated Water Supply Pumps
➢ Sludge return pump
➢ Sludge holding tank
➢ Filter Press for solid waste management
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
69
➢ Sludge loading pumps
➢ Sludge drying beds, Centrifuge/Filter Press
PROCESS DESCRIPTION
a) Raw sewage from main sewer line should be collected through gravity pipes into the
screen chamber. This manually cleaned screen should be provided to remove
floating and big size particles which may otherwise choke the pumps and pipe lines.
b) After screening, the waste water should be allowed to pass through a grit chamber
to remove the grit material. The screens and grit chambers shall be accessible so that
they may be manually cleaned from time to time.
c) The screened waste water from the Grit chamber should then pass into the
equalization tank to homogenize the waste water quality and also even out flow
fluctuations and feed waste water of uniform quality at constant rate to subsequent
treatment units. Air mixing should be provided to mix the contents of the
equalization tank. A coarse bubble aeration grid should be provided to mix the
contents of the equalization tank and also to avoid septic conditions in the tank.
From the equalization tank the wastewater will be pumped into an MBBR Tank.
d) The MBBR process uses small plastic carrier elements to provide growth sites for
bacteria attachment in a suspended growth medium. The carrier elements shall
allow a higher biomass concentration to be maintained in the reactor. This shall
increase the biological treatment capacity for the given reactor volume.
e) The carrier elements shall be continuously kept in suspension by the aeration
system. The agitation pattern in the reactor shall be designed to provide an upward
movement of the carriers across the surface of the retention screen which creates a
scrubbing effect to prevent clogging. Combination of fine & coarse bubbles may be
provided to provide oxygen as per detailing.
f) From the MBBR tank mixed liquor shall flow by gravity into the Tube settler. The
solids will settle in the tank. The sludge that settles down shall be transferred to
sludge holding tank via sludge loading pumps, with provision of sludge return to the
bioreactor if necessary.
g) From the tube settler, treated wastewater will be fed by means of filter/softener
feed pump sets to pass through dual media filters, activated carbon filters and
softeners and stored in the filtered water and soft water storage tanks. The activated
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
70
carbon filters shall ensure removal of all coloration and odours present in the treated
effluent.
h) The filtered, clean and odourless water from filtered water tank is then fed through
a variable frequency drive hydro-pneumatic system to the external treated effluent
rings as per the master plan, from where connections are taken to the garden
hydrant system and to each unit for flushing water as per detailing.
i) Excess sludge from the tube settler will be taken periodically into sludge holding
tank. In this tank sludge will be aerated for self-stabilization. Air will be shut off
periodically and superannuate water will be transferred to the aeration tank creating
stabilized sludge. The final sludge shall be de-watered through a centrifuge
mechanism. Sludge loading arrangements shall also be provided for direct disposal
of sludge to sludge tankers / trolleys.
3.7.2.2.2 Hydraulic Flow Diagram of STP based on MBBR Technology
3.7.2.3 Rain Water Harvesting
The main source of ground water recharging in the study area is rainwater, which
infiltrates into the ground through various lithological units present in the study area. 3
nos. of RWH harvesting structures are proposed in the site to recharge the ground water.
The runoff from the rooftop and storm water shall go to the recharge structures.
Scheme for Ground Water Recharging
INCOMIN
G
SEWAGEBAR
SCREEN BAFFLE
WALL
OIL &
GREASE EQUALIZATION
TANK
MBBR-1 MBBR-2 TUBE
SETTLER
CLEAR
WATER
TANK MGF ACF
TREATED
WATER
TANK
TREATED
WATER
USED
UV
FILTER
PRESS
SLUDGE
HOLDING
TANK FINAL
DISPOSAL
TO
EQUALIZATION
TANK
MBBR STP TECHNOLOGY
LEGENDS
Mark Descriptions
Air Line
Sludge Line
Effluent line
Air Blowers
Air Diffusers
Butter Fly Valv
Non Return
Valv
Pump
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
71
The rainwater is diverted from the rooftop using rain water pipes to the surface /
underground drainage network. The entire complex is sub divided for recharging
structures. The rainwater is diverted into the desilting tank to remove inorganic
impurities and the outflow of the desilting tank is taken into the recharge well.
Desilting Tank
The desilting tanks are used to remove silt and other floating impurities from rainwater.
Desilting tank is like an ordinary container having provision for the inflow, outflow and
overflow. Apart from removing silt it holds the excess amount of water till it is soaked
up by the recharge structure. The bottom of tank will have unpaved surface (layers of
coarse sand) to allow standing water to percolate into the soil. The rainwater collected
in these desilting chambers shall be utilized for horticulture.
Recharge well
The recharge well consists of percolation pits with boreholes in the middle of the pit.
UPVC pipe perforated will be lowered in the middle of the boreholes and the pit will be
filled with gravel and pebbles in three layers consisting of boulders, gravel and coarse
sand. The mouth of the UPVC pipe shall be protected to avoid silt getting into it. The
depth of the bore will depend on the soil condition/water strata. The schematic diagram
is enclosed.
It should be therefore concluded that there is no significant impact on surface water
quality & hydrology of the area. The proposed rainwater-harvesting scheme will stabilize
the groundwater table in the area.
3.7.2.4 RAIN WATER HARVESTING CALCULATION: -
Soil Quality : Silt Loam Annual Rain fall : 797 mm Peak Hourly Rain fall : 60 mm/hr Ground Water Level : 25.9- 26.2 m below ground level (As
per Geotechnical Report) No. of Pits : 3 No. Size of each pit : Dia – 1.8 m & Depth- 3 m
Table 3-11: Rain water Harvesting Calculation
S.
No.
Description of
Area
Area
Considered
(Sq. M)
Harvesting
Factor /
Collection
Efficiency
per area
Retention
time capacity
of recharge
tank in 15 min
Total Volume of
Water Available
for Rain Water
Harvesting
(cu. m/15 min)
1. Water Available
from Terraces of
Apartment
1701.09 0.85 15 22
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
72
Rain Water Harvesting pit Diagram:-
5000
BAFFLE WALL
1250
45
0
( 1.5 TO 2 MM )
OIL & GREASE CHAMBER
600 x 600 x 100 M.M.
4 Nos 300x300 M.M
GREASE TRAP
900 x 600 M.M. COVER
22
50
OR STONE SLAB
345
GROUND LEVEL
900 x 600 M.M. COVER
DESSILTING / SETTLING CHAMBER & RECHARGE PIT
PIPE TO SILT TRAP
1250
STRUCTURE DESIGN
OPENINGS
900 x 600 M.M. COVER
INFLOW PIPE
RCC DEFLECTOR
R.C.C. SLAB
COARSE SAND BED
RCC SLAB AS PER
12501250
VARIABLE DEPTH
OPENINGS
50
0
INFLOW PIPE
SCREEN ( 25MM OPENING )
RCC DEFLECTOR
DE- SILTING CHAMBER
600 x 600 x 100 M.M.
150 M.M. THICK
MESH
500 M.M. THICK
OR STONE SLAB
900 x 600 M.M. COVER
12
0
BRICK WORK4 Nos 300x300 M.M
buildings/Plots and
other roof-top
surfaces
2. Paved Surfaces,
Roads & other
Built-up Areas
4938.47 0.7 15 52
3. Lawns, Gardens &
all other Open
Areas
3331.69 0.15 15 7
Net Plot Area 9971.25 81 cu m
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
73
Maintenance Plan: -
1. Rain water harvesting pits should be checked and cleaned before and after rainy
season. Cleaning procedure consist of scrubbing of inner walls and floors. Cover
and ventilate the tank also.
2. Chlorine solution can be used for cleaning purposes followed by through rinsing.
3. Cleaning of filter shall be done before and after rainy season.
4. Cleaning of desilting tank shall be done before and after rainy season.
5. Regular cleaning of oil and grease trap will be done and maintained.
6. Weekly cleaning of the pits shall be done during rainy season.
3.7.2.5 NOISE ENVIRONMENT
The main sources of the noise pollution will be D.G sets. of 3 x 1010 KVA that will be
installed in the project.
3.7.2.5.1 Noise Pollution Control System
DG sets shall be bought & installed acoustically treated and shall meet the norms
prescribed by CPCB. Planting of the trees at the boundary of the project will help in
reducing the level of the noise within the project.
Location of DG sets: Basement
3.7.2.5.2 ACOUSTIC ENCLOSURE / TREATMENT
There are two methods to reduce noise from DG Sets.
1. Acoustic Enclosures [when DG Set is kept outdoor]
2. Acoustic Treatment [when DG Set is kept indoor]
Insulation of air inlet and outlet points The sound travels along with air therefore it is necessary to control the travelling
sound with the help of insulated ducts [2” glass wool pads and perforated sheets] and
louvers at inlet and outlet air points. The ducts have S-type shape to prevent any direct
escape of noise Insulated service door
The maintenance and servicing of D.G. set is done using a suitable service door of 5’ x 7’
size. The door is made of MS sheet and frames fully insulated with 3” thick glass wool
pad followed by perforated aluminium sheets.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
74
Antivibration Pads
Layout Plan of D.G Set Room
3.7.2.6 PARKING MANAGEMENT
Parking Required:
Parking Dwelling Unit (FAR 19912.79 m2) 2 ECS/100 m2 398 ECS
Parking EWS (FAR:2998.06 m2 ) 0.5 ECS/100 m2 15 ECS
community parking (400 m2) 2 ECS/100 m2 8 ECS
Total Parking Provision 421 ECS
Parking Provision:
Parking Provision
Location Total Area
Service Area
Net Parking Area Factor
ECS provided
Basement Area 12760 2807.240 9952.92 32 311
Stilt parking 3615.74 28 129
TOTAL 440 ECS
3.7.2.7 WASTE MANAGEMENT
3.7.2.7.1 MUNICIPAL SOLID WASTE
For 1027 persons around 153 Ton/annum of municipal solid waste will be generated
from the proposed site.
Solid waste will be generated from the project (Biodegradable: 92 Ton/annum, Non-
Biodegradable: 46 Ton/annum & Plastic: 15 Ton/annum).
Battery waste shall be generated from inverters & UPS.
The solid waste categories and disposal method detail is shown is given in Table below:
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
75
Table 3-12: Municipal Waste Management
Type of
Waste
Colours
of Bins
Category Disposal Method Total Waste
(Ton/annum)
Bio-
Degradable
Green Organics
The waste shall be treated
in organic waste
converter and converted
to manure
92
Non-Bio
Degradable
Blue Recyclable Approved Recycler 46
Plastic Blue Recyclable Approved Recycler 15
Total 153 Ton/annum
DETAILS OF ORGANIC WASTE CONVERTER
Tentative details of the Organic Waste Converter are as follows:
MODEL NO. NO. OF OWC
PROVISION
CAPACITY PER
BATCH
POWER DIMENSION (L X W X H)
OWC-60 1 NO. 25 KG/BATCH 4 HP 1.74 M X 1.06 M X 1.1 M
Biodegradable Waste
Batch Capacity Curing Capacity Time Taken No of Batch
92 kg/day 25/batch 100 kg/day Machine Time=
15-20 m
Total Time=1 hr
4 batch/day
• No. of organic waste converter = 1 Nos.
• Volume of waste = 0.184 tons/day or 0.184 m3
• Capacity of curing for 10 days = 1.84 m2
• Space area for curing= 6.13 m2
• Space for organic waste converter= 1.74 m x 1.06 m =1.84 x 1=1.84 m2
• Area required for storage and management of solid waste = 7.97 m2
• Area provided for storage and management of solid waste = 20 m2
3.7.2.7.2 Hazardous waste management: - Hazardous waste is a waste with properties that make it dangerous or potentially
harmful to human health or the environment. The universe of hazardous wastes is large
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
76
and diverse. Hazardous wastes can be liquids, solids, contained gases, or sludge. They
can be the by-products of manufacturing processes or simply discarded commercial
products, like cleaning fluids or pesticides. All hazardous wastes are required to be
treated and disposed off in the prescribed manner.
The main objective is to promote safe management and use of hazardous substances
including hazardous chemicals and hazardous wastes, in order to avoid damage to
health and environment.
Table 3-13: Hazardous & E-Waste Management
Battery waste will be generated from inverters & UPS, which shall be treated as per the
Batteries (Management & Handling) Rules 2001
3.7.2.7.3 PLANTATION
Green belt planning will be done with ecological perspectives for the project taking into
consideration and availability of space and other aspects. This will help in increasing the
aesthetic effect of the environment.
Since tree trunks are devoid of foliage, scrub should form there to give coverage to the
trunks. The trees maintain the regional ecological balance and conform to soil and
hydrological conditions. Indigenous species would be preferred.
Green belt/greenery will be developed along most of the periphery of the project area
as well as along roads. Proposed area under plantation/greenery is 3331.69 m2 (33.41%
of net planned area) with trees, plants, herbs & shrubs and lawns. The trees planted will
be of adequate height.
Trees required –net Plot area/80 = 9971.25/80 = 124 no. of trees
No of trees proposed: 130
Type of Waste Disposal Method Total Waste
Used Oil
(Schedule 5.1)
Waste shall be collected in leak proof containers at
isolated place and then it will be given to approved
vender of CPCB as per Hazardous Waste & other
Wastes (Management & Transboundary
Movement) Rules, 2016
0.08
kiloltr/annum
E-waste
E-Waste shall be collected and given to approved
vender of CPCB as per E-Waste (Management)
Rules, 2016.
0.024
Ton/annum
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
77
Species Proposed: -
Presently, the land has total 86 no. of trees out of which 81 nos. are required to be cut/
transplanted in order to develop the roads, basement, and buildings of the Group
Housing Colony. However, mostly trees are young trees and permission required is only
for 6 number of trees, which will be transplanted only after obtaining the permission
from Forest department.
Details of trees requiring permission to be cut is given below:
SL.NO Botanical Name Common Name
Permission Required Number
1 Alstonia scholaris Devil tree Required Permission 4
2 Ficus benghalensis Banayan tree Required Permission 2
Total 6
3.7.2.7.4 PLANTATION PROGRAMME LAYOUT
Plantation in the project area helps to arrest the particulate matter in the area and
hence attenuate the pollution to a great extent and contribute positively to the
environment. The trees also help in maintenance of regional ecological balance and
S No. Scientific Name Common Name
1. Alstonia scholaris Devil Tree
2. Saraca asoca Ashoka
3. Azadirachta indica Neem
4. Plumeria alba Champa
5. Neolamarckia cadamb Kadam
6. Cassia fistula Amaltas
7. Syzygium cumini Jamun
8. Bauhinia acuminata Dwarf white bauhinia
9. Ficus benjamina Weeping fig
10. Ficus panda Ficus
11. Hibiscus rosa-sinensis China rose
12. Gardenia jasmoides Gardenia
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
78
conform to soil and hydrological conditions. Indigenous species are preferred for the
purpose.
The following characteristics are taken into consideration while selecting plant species
for green belt development and tree plantation.
• They are fast growing and tall trees.
• They are perennial and evergreen.
• They have thick canopy cover
• They have large leaf area index.
ANTICIPITATED IMPACT & MITIGATION MEASURES
3.8.1 DURING CONSTRUCTION PHASE
S.
NO.
Description Impacts Mitigation Measures
1. Air & Noise
Environment
• Dust will be generated
due to Site clearance,
construction activities
and emissions may be
generated due to
vehicles, DG sets and
machinery/equipment
etc.
• Loading and unloading of
construction materials
like, cement, sand,
stones, bricks, etc. will
result in dust generation.
• Procurement and
transport of construction
materials such as sand,
cement etc. will also
result in dust generation.
• Due to demolition of
existing structure.
• Proper Barricading shall be done to
reduce the dust during construction
of buildings. Also, barricading will
cut off some of the noise due to
construction activities.
• Water sprinkling shall be done to
reduce the dust during construction
of buildings.
• Raw material, construction debris
shall be kept covered during storage
as well as during transportation.
• The buildings under construction
shall be kept covered with green
cloth.
• D.G. set of 62.5 KVA shall be
provided with adequate stack
height to avoid emissions.
• No loose soil or sand or
Construction & Demolition Waste or
any other construction material that
causes dust shall be left uncovered. 2. Water
Environment
• Soil runoff from the site
leading to off – site
contamination
(Particularly during rainy
season).
• During construction phase, water
will be provided from the nearby
STP/tanker water supplier.
• Disposal of debris shall not be done
near water resources, rather, C & D
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
79
• Improper disposal of
construction debris
leading to off-site
contamination of water
resources.
• Disposal of domestic
waste water from
temporary labour rest
rooms.
Spillage of oil and grease
from the vehicle and
waste water stream
generated from on-site
activities.
waste shall be disposed off as per
applicable rules.
• The rain water from the
construction site shall be collected
& reused for sprinkling.
• Mobile toilets shall be installed at
the site during construction phase
which will be regularly cleaned by
the agency.
3. Solid Waste • The waste from labour
rest rooms/sheds would
be mainly household
domestic waste
• The solid waste
generated during
construction phase
• Used oil from DG sets.
• Construction and
demolition waste.
• Approx. 23 kg/day municipal solid
waste shall be generated from 150
labours which shall be disposed off
in MSW site.
• The excavated soil of 51040 cum will
be reused for back filling purpose.
The top soil will be preserved
separately and will be used for
landscaping purposes only. The
unused soil shall be sent to landfill
site only identified be Municipal
corporation.
• Construction debris generated from
site shall be used in backfilling &
levelling purposes to the extent
possible. Rest of the waste shall be
sent to C & D facility.
• Used oil whenever generated from
the DG sets shall be kept in an
isolated area and in leak proof
container and sent to approve
recycler.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
80
3.8.2 DURING OPERATION PHASE S. No. Description Impacts Mitigation Measures
1. Air & Noise
Environment
• Running of DG sets of
capacities 3 x 1010 KVA during
power failure will result into
air emissions.
• DG sets shall be provided
with stack height of 6 m
above roof level as per
CPCB norms.
2. Water
Environment
• During the operation phase
abstraction of ground water is
not proposed for project.
Water supply shall be met by
Municipal/ HUDA supply.
• In the proposed colony, water
will be used for domestic use,
flushing, & misc. purposes etc.
Therefore, there will be a
wastewater discharge in the
form of liquid waste and
sewage. and
• Fresh water requirement
shall be reduced by using
STP treated water in the
complex.
• The waste water/ sewage
shall be treated in a STP of
total 135 KLD capacity
based on MBBR
technology.
• The treated water of 112
KLD will be reused in
flushing, miscellaneous &
gardening purposes
• The excess treated water
of 32 KLD will be
discharged to sewer.
• Rain water shall be
recharged into the ground
water by 3 rain water
harvesting pits.
3. Solid Waste • Bio-degradable and recyclable
waste from household
activities.
• Used oil from DG sets and e-
waste.
• E- waste & battery waste
generation.
Bio-degradable waste of
92 Ton/annum shall be
treated in Organic waste
convertor. 61 ton/annum
of recyclable waste will be
given to authorised
recycler.
Used oil will be generated
from the DG sets which
shall be kept in an isolated
area and in leak proof
container and shall be
given to authorised
recycler.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
81
The generated E-waste
shall be given to
Authorized vendor.
Battery waste shall be
treated as per the
Batteries (Handling &
Management) Rules,
2001.
ENVIRONMENT MONITORING PLAN
Monitoring During Construction During Operation
Air & stack :
• Ambient air quality at appropriate
location for PM10,PM2.5,SO2.NOX
• Stack emission for point sources
PM,SO2,NOX,HC & CO.
• Six monthly
• Six monthly
• Six monthly
• Six monthly
Water :
• Water Quality Monitoring for
relevant parameters of IS - 10500
• Six monthly
• Six monthly
Wastewater:
• Waste Water Quality (Treated &
Untreated) for pH, TSS, Oil &
Grease.
• Waste water quality pH, TSS, oil &
Grease. BOD, COD, TKN &
Phosphate.
--
--
• Daily till
stabilization of
STP.
• Weekly till one
month then
monthly
Noise :
• Day & night level Noise Monitoring
• Six monthly
• Six monthly
Soil :
• Soil Monitoring ,Qualitative and
Quantitative testing/analysis to
check the soil fertility , porosity,
texture, water holding capacity etc.
• Six monthly
• Six monthly
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
82
RISK ASSESSMENT
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
83
RISK ASSESSMENT Risk is a potential that a chosen action or activity will lead to a loss of human or property.
Risk assessment is a step for Risk Management. Risk assessment is determination of
qualitative and quantitative value of risk related a situation or hazard.
Hazard is a situation that poses a level of threat to life health or environment.
Risk assessment involves the following:
• Hazard Identification
• Vulnerability Analysis
• Risk Analysis
• Emergency Preparedness Plan
4.1.1 HAZARD IDENTIFICATION
The project is a Group Housing and there may be following types of hazards:
4.1.1.1 Natural hazard:
1. Earthquake
2. Flooding
4.1.1.2 Manmade hazard:
1. Health Injuries
2. Fire & explosion
3. Electrical
4. Mechanical
5. Radiation
6. Thermal
7. Chemical
4.1.2 VULNERABILITY ANALYSES
This is a Group Housing hence residents, staff & visitors will be vulnerable to risks.
4.1.3 RISK ANALYSIS
The risk is likelihood of harmful effect big or small due to hazard, together with severity
of harm suffered. Risk also depends on number of people exposed to hazard.
Risk analysis provides severity of harm from particular type of hazard.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
84
4.1.3.1 Earthquake:
The project will be located at seismic zone IV where earthquake can occur from 4.0-7.0
Ricter scale.
4.1.3.2 Flooding:
The project site will be located in an area where no natural river or drainage exists.
However, flooding can occur due to excess rain.
4.1.3.3 Health Injuries
Health Injuries can occur during Construction Phase & appropriate measures shall be
taken as described below:
1. Safety nets shall be provided at appropriate level and various shafts/ openings will
be kept covered to prevent falls, slips, trips etc.
2. Necessary safety belts, helmets and eye-masks as required will be enforced at site.
3. Adequate guardrails will be provided to the staircases and common areas.
4. Adequate guardrails/ fences will be provided around the water storage spaces to
prevent drowning accidents.
5. Adequate protection/ fence will be provided around the excavated areas.
6. The machinery and the equipments will be regularly tested and maintained with the
specific emphasis against accidents failures.
7. The deployed Safety officers will ensure that the personnel/ labour will be kept at a
safe distance from working machinery to avoid accidents/ injuries due to toxic gases/
chemical/ noise.
8. Moving parts of various parts of machineries/ equipments shall be properly guarded.
9. Required fire extinguishers will be provided at the construction site.
10. Arrangements for clean drinking water will be made.
11. Rest rooms and first aid facilities will be made available for the workers.
4.1.3.4 Fire & Explosion:
Since it is a Group Housing , fire can occur due to electrical spark or gas leakage from
pantry.
Fire is mainly caused in Group housing due to carelessness, short circuits, and
malfunctioning of gas regulator, tube, and such related products.
4.1.3.5 Electrical:
The electrical current can pass to the floor & metals due to inadequate insulation or
accidently.
4.1.3.6 Mechanical:
The mechanical fault can cause the risk & hazard which include the elevators.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
85
4.1.3.7 Radiation:
Due to use of wireless equipment’s there may be electromagnetic radiation.
4.1.3.8 Thermal:
Thermal heat can be generated from the D.G sets and the vehicles in the project.
4.1.3.9 Chemical:
Chemical use in the Group Housing will be limited to cleaning agents & medicines.
4.1.4 ONSITE EMERGENCY PLAN
An onsite emergency is caused by an accident or hazard that takes place within the
project and the effects are confined to the project.
The onsite emergency plan consists of following key elements:
• Planning as per hazard analysis
• Preventive measures
• Emergency response procedure
• Recovery procedure
4.1.4.1 Planning
1. Mapping of hazard vulnerable area shall be done in consultation with
management.
2. There shall be Disaster Management Cell in place
3. The disaster management cell have following members to share the responsibility
I. Site Controller (Administrator of project)
II. Incident Controller (Asstt. Administrator)
III. Personal Manager
IV. Communication Officer
V. Fire Officer
VI. Security Officer
VII. Engineering Incharge
VIII. Fire pump attendant
IX. First Aid Team
4.1.4.2 Preventive Measures
4.1.4.2.1 Earthquake:
Since project will be located at Seismic Zone IV, structural designing will be done as per
National Building Code 2016.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
86
4.1.4.2.2 Flooding:
• Proper designing of drainage system for domestic as well as storm water.
• Rain water harvesting structures will have provision of storage for one hour peak
rainfall.
4.1.4.2.3 Fire:
Reference:
• NBC-2016
FIRE STATIC STORAGE TANK:
Fire storage tank for covering the entire complex shall be provided with fire pumps like
Hydrant Pumps, Jockey Pump, and Pressure Vessel & Diesel engine driver pump is
proposed near the water storage tanks for proposed group housing.
• Accessories:
i) Suction manifold (in fire pump room) fed from two fire water storage tanks.
ii) Delivery manifold (in fire pump room) fed by the pumps as explained above.
iii) An Air vessel shall be provided on delivery manifold of Hydrant system, to
compensate for slight loss of pressure and to provide an Air cushion for counter
acting pressure surges from the system. Separate delivery pipes will be given for
Hydrant system.
FIRE HYDRANT SYSTEMS:
Fire hydrant system shall consist of the following:
i) Each fire hose cabinet shall be provided with
a) One single out let landing valve
b) Two sets of canvas hose pipe with branch pipe
c) One first aid fire hose reel.
d) One firemen’s Axe
e) 2 Nos fire Extinguishers
PORTABLE EXTINGUISHERS & FIRE SAFETY APPLIANCES:
Portable Extinguishers will be located in prominent and easy to reach during fire
emergency.
Type of Extinguishers:
Selection type and capacity of the Extinguishers shall be done as per I.S: 15683.
• Water-CO2 Type
• Dry Chemical Power (DCP) Type
• CO2 Type Extinguishers
• ABC (Power Type) Extinguisher:
Test Demonstration:
At least 1 extinguisher per each type shall be demonstrated at site in simulated fire
conditions.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
87
EXIT SIGNAGE
Exit Signage and evacuation instruction shall be displayed judiciously at prominent
locations.
FACILITY OF FIRE MAN AT MAIN GATE
i) Fire brigade inlet connection to tank.
ii) Fire brigade draw out connection to tank
4.1.4.2.4 Electrical:
i) Planning Stage:
Safety parameters as indicated under Indian Electricity Rules 1956 and ECBC shall be
complied. The following safety measurement is considered.
• Earthing system
• The earthing system shall comply the requirement of IS: 3043, Indian Electricity
rules and other applicable statuary regulations and safety codes in the locality of
installation.
• GI plates earthing system shall be provided.
• One Earth Leakage Breaker sensitivity 30 mA shall be used per phase in all
Distribution Boards
In addition to that, following measures shall be adopted
• There will be colour coding and labelling of high voltage electrical wires.
• Sand bags/ wire bucket shall be placed near the electrical control/panel.
• Installation of electrical equipments shall be properly done like insulation,
guarding and grounding.
• Work practices and handling of the electrical equipments shall be properly
managed.
• Employees and workers shall be trained for awareness of safe work practices
and systems.
• Properly maintained equipments and tools will be used.
• Service of electrical equipments shall be done under the supervision of trained
personnel.
• Temporary connections made for experimental reasons shall be safe and
properly insulated.
• Live electrical terminals shall be shielded.
ii) Operation Stage:
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
88
• Have only licensed electricians install, repair and dismantle jobsite wiring. That
way, everything will be completed according to electrical safety codes, ensuring
greater protection for the workers who will be using the wiring to power tools
and equipment. Bringing in a professional electrician also prevents the injuries
that result when less-qualified individuals attempt electrical jobs that they aren’t
properly trained to do.
• Check each extension cord before use. Ensure that insulation is completely intact
(free from cracks, tears, or abrasion) and that power extension cables haven’t
been knotted, which can cause conductor damage and increase the risk of fire.
• Do a thorough check for electrical wiring before cutting through any wall, floor
or ceiling. Any time that a tool inadvertently makes contact with an unseen
electrical line, the person holding that tool is likely to be shocked or electrocuted.
Always size up the situation before you get started to reduce your risk of injury.
• Inspect power equipments on a regular basis. Look over the tools’ power cords
and plugs for any sign of damage to the insulation, blades, or grounding pin. If
you find signs of excessive wear and tear, take tools out of commission until
they’ve been properly repaired. Maintain awareness during electrical tool use as
well; if a tool starts to overheat, smoke, give off a burning smell, or shock you on
contact, discontinue use immediately.
• Check insulated tools for damage before each use. Once the insulation layer of
an insulated hand tool becomes nicked, cracked or cut, the tool is no longer
effectively insulated – it actually becomes more of an electrical conductor, and
can increase your risk of injury. If a tool has damaged insulation, it is no longer
safe to use – destroy and replace it right away.
Never modify electrical plugs. Under no circumstances should you ever file down
the blades, remove the ground pin, or otherwise modify an electrical plug so that
it will fit into a socket – doing so only increases the likelihood of shock,
electrocution, and fire. Either have a certified electrician change the device’s plug,
or replace outdated two-prong receptacles with grounded outlets that can
accommodate a ground pin.
Keep extension cords in a safe place where they won’t be stepped on or driven
over. The force of a vehicle – or even repeated treading by pedestrians – can
cause an extension cord’s conductor to become misshapen or break, a problems
that can lead to electrical fires. Because it occurs in the core of the cable,
conductor damage isn’t always obvious to the eye, so play it safe from the start
by guarding jobsite extension cords with heavy-duty cord covers.
Ensure that all electrical components stay dry. It’s one of the cardinal rules of
electrical safety: don’t mix electricity and water. Store power tools and cables
above water level when not in use, cover outdoor receptacles, and never use
electrically powered tools in a wet environment.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
89
Use the right extension cord for the job. Before you plug in, make sure that the
wattage rating of the extension cord you’re using is greater than the pull (or
power requirement) of the equipment it’s powering. Using an extension cord to
supply more wattage than it’s rated for can cause conductor strain, overheating,
and possibly even fire.
4.1.4.2.5 Chemicals: This is a Group Housing project no chemical container/tanker shall be allowed inside
the project.
The chemical hazard includes the following:
• Causing fire, explosion.
• Release of harmful /toxic gas or particles.
• Splashing of hot corrosive or toxic liquid.
To prevent chemical hazard following measures shall be taken:
1. Use of safer chemicals as for as possible.
2. Keep material safety Data Sheet (MSDS) of all chemical.
3. Storage of chemical in appropriate container (which is safer for chemical)
4. Storage of chemical at defined place will spillage control system.
5. Proper environment like ventilation, temperature.
6. Use of chemicals by qualified and trained personals.
7. Use of personal protective equipment (PPE) during handing of chemicals.
8. Use of emergency procedures in case of leakage like
a) Fire fighting – for fire
b) Spillage treatment
c) First aid
d) Evacuation of area
For building projects only chemicals used are:
1. Cleaning agent (acid /caustic)
2. Insecticides
Cleaning agents can be treated by water.
Insecticides shall be contained with specified space during sand & cotton and waste shall
be sent to TSDF.
The spray of insecticide shall be done by using gas mask.
4.1.4.2.6 Terrorism: All the preventive measures shall be taken as given in security plan.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
90
4.1.4.2.7 Mechanical:
Mechanical hazards are created by powered operation of equipments or tools.
Mechanical hazards can occur at three locations:
1. Elevators
2. DG set room, Pump & motors room.
3. Vehicular Movement
Following preventive measures shall be taken.
1. Elevators shall be properly maintained with record book of maintenance.
2. Periodic replacement of critical components of elevator/ machine.
3. Proper training to operators of machines.
4. The protective guard will be installed at fan & motors.
5. There will be safe distance demarcation on heavy machines like cranes
(during construction)
6. Sign of danger at the hazard places.
4.1.4.2.8 Radiation:
The radiation hazard can be of two types:
• Ionizing Radiation (nuclear radiation)
• No ionizing radiation (non-nuclear radiation)
In the buildings in a Group Housing, radiation hazard is non ionizing.
The radiation can be prevented in following manner:
1. Shielding of radiation.
2. Safe distance from radiation source.
3. Sign of radiation hazard at vulnerable areas.
4.1.4.2.9 Thermal:
Thermal hazards are objects or substances that transfer energy as heat.
Typical building can have following points of thermal hazard.
• Open flame
• Boiling liquid
• Hot machines/ equipments
The thermal hazard can cause burn of skin, following preventive measures can be
taken:
1. The open flame area like mess shall be restricted.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
91
2. Water heaters shall be properly insulated and safe distance & guard will be
installed.
3. D.G set room will have restricted entry.
4. Operators in the thermal hazard area shall be provided with protective gears
like gloves, goggles etc.
5. For emergency first acid room will be maintained.
4.1.4.3 Emergency Response Procedure
After all the preventive measures for any emergency following infrastructure shall be
provided.
1. Administrative office shall also make an Emergency Control Room.
2. Assembly area shall be demarked for each type of flats.
3. Communication system shall be installed in the project which includes
intercom and public addressing system.
4. Fire alarm shall be installed at vulnerable place.
5. The evacuation plan of each building shall be displayed at each floor of
respective building.
6. The safe zones (at the time of emergency) on map shall be displayed at
different locations.
7. First Aid facility shall be made available at Control room.
In case of emergency following action shall be taken.
1. The emergency shall be declared in case of following:
i) Fire alarm buzzing (Fire hazard)
ii) Vibration/Earthquake feeling (Earthquake)
iii) Water logging in the project above 30 cm (Flood)
iv) Any unusual smell of gas or suffocating feeling (Chemical leakage)
v) Security alarm from main gate. (Security risk/Terrorism)
2. On declaration of emergency communication shall be made to residents for
any type emergency
3. All the resident of the affected area shall be moved to safe zone
4. The control measures shall be done as per the emergency action plan for each
type of hazard.
5. All the members of disaster management cell shall take charge of their
respective duties.
6. Outside help like fire tender, police ambulance etc. shall be called by site
controller or Incident controller.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
92
4.1.4.4 Recovery Procedure
The recovery procedure will depend on the type of emergency. Recovery procedure
shall be followed by engineering section to restore the essential services like electricity,
water, telephone, food items.
4.1.5 Offsite Emergency Plan
If an accident take place in the project and its effect are felt outside the project, the
situation thus created is called an offsite emergency. In this case off site emergency is
not applicable.
4.1.6 Security plan
An ISO 27001 and 27002, which are the international best practice information security
management standards, defining and guiding Information Security Management System
(ISMS) development shall be adopted. These will provide the necessary benchmarking
for individual users to know the type of cover and the responsibilities that are defined
and provided by that institution for its guests. Most importantly, training, to staff needs
to be regularly imparted in dealing with such situations.
1. Manual Checks: At all gates the visitors and guest shall be manually checked
and asked for ID’s.
2. CCTV: At all important location with a remote viewing facility and record back
up. With highest resolution and picture quality. DVR being the back bone, its
recording and replaying capabilities must be considered.
3. Video Door Phone System: VDP equipment with associated telephone wiring
shall be provided for all flats having color view screen.
4. Central Control Room: This will control the security system from inside.
5. Communication Systems: Proper communication system to security staff shall
help them to coordinate better during emergencies.
Training and Security Drills (including Surveillance System)
Disaster planning is the responsibility of all sections of the community. The police, fire
brigade, civil defence, Home Guards, press, clergy, industrial groups, and community
groups must participate in the pre-disaster planning. The community as a whole has the
responsibility to teach first aid to groups in the community that could be utilized in
disaster situations. The disaster may involve the normal communication network itself.
Therefore, two-way radio systems and messenger systems must be included as backups
in the event of a communication-system failure.
Proper training, security drill and evacuation drill shall be conducted in a defined time
period, so as to train the management people, security personnel’s, senior staff and all
other working staff in the Group housing project to take control of all odds what so ever
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
93
come in the way. These trainings shall be conducted for use of weapons and Arms by
some trained agencies for the said trainings. The training shall be done periodically.
Making of Standard Operating Procedures
A standard operating procedure manual shall be prepared, followed and maintained
for all the eventualities due to attack by armed intruders.
Emergency Response Team
The disaster management cell shall act as an emergency response team shall be formed
in the project which will comprise of persons from Internal Control room personnel,
security staff, trainers, Police Control, Army official, Nearest Hospital Management, Fire
officer to take control of any eventuality if comes in the project.
EVACUATION PLAN Standard operating procedures will be formulated and maintained for all eventualities
due to attack by armed intruders.
Evacuation plan includes the evacuation due to
• fire hazard in the project
• Armed Intrusion
• Flood
• Earthquake
During any of the above-mentioned hazards, the evacuation will be as follows:
INFORM CONTROL ROOM
INFORM CONCERNED AGENCY
SUGGEST EVACUATION PLAN
SHIFTING RESIDENTS TO INTERNAL SAFE AREA
FIRST AID
TRANSPORT INJURED TO NEAREST HOSPITAL
TRANSPORT PEOPLE TO SAFE PLACE
CALL NECESSARY HELP
Communication
The communication system is useful for rapid notification to appropriate units and
expeditious implementation of relief procedures. The fire brigade and metro police
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
94
units are linked through a wireless communication network. Additional channels of
communication are now available through personal cell phones. Use of personal cell
phones will not be restricted during disasters.
On-site crowd control and information management
Disasters usually attract crowds consisting of curious bystanders, onlookers,
overenthusiastic volunteers, and self-styled advisers. In general, this hampers rapid
triage and transport. The primary responsibility for crowd management is with the
police. When a call is received at any of the control rooms, the information is passed on
to the local police. The police contingent which arrives on the scene has the primary
responsibility for crowd control.
During construction Phase During Operation Phase
• Safety nets shall be provided at appropriate level and various shafts/ openings would be covered to prevent falls, slips, trips etc.
• Necessary safety belts, helmets and eye-masks as required are enforced at site.
• Adequate guardrails shall be provided to the staircases and common areas.
• Adequate guardrails/ fences shall be provided around the water storage spaces to prevent drowning accidents.
• Adequate protection/ fence shall be provided around the excavated areas.
• The machinery and the equipments shall be regularly tested and maintained with the specific emphasis against accidents failures.
• The deployed Safety officers ensure that the personnel/ labour shall be kept at a safe distance from working machinery to avoid accidents/ injuries due to toxic gases/ chemical/ noise.
• Moving parts of various parts of machineries/ equipments shall be properly guarded.
• Required fire extinguishers shall be provided at the construction site.
• Arrangements for clean drinking water shall be made.
• Rest rooms and first aid facilities shall be made available for the workers.
• Fire Protection system shall be designed as per requirements of National Building Code – 2016.
• The project is located at Seismic Zone IV. Structural designing will be done as per best structural engineering practices complying with all the applicable codes / standards. Also we have received the structural stability certificate.
• Proper designing of drainage system for domestic as well as storm water shall be provided.
• Rain water harvesting structures will have provision of storage.
• Fire Protection system shall be designed as per requirements of National Building Code – 2016
• Proper Fire evacuation system shall be provided.
• Safety parameters as indicated under Indian Electricity Rules 1956 and ECBC shall be complied.
• Elevators shall be properly maintained with record book of maintenance.
• Periodic replacement of critical components of elevator/ machines.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
95
CERTIFICATE OF THE CONSULTANT
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
96
LAND PAPERS
FORM 19
[Refer Rule 32(1) of the LLP Rules, 2009]
CERTIFICATE OF REGISTRATION ON CONVERSION
OF
WELLWORTH REALTECH PRIVATE LIMITED
TO
WELLWORTH REALTECH LLP
LLP Identification Number: AAE-2669
GOVERNMENT OF INDIA
MINISTRY OF CORPORATE AFFAIRS
Registrar ,RoC-Delhi4th Floor , IFCI Tower , 61 , Nehru Place , New Delhi - 110019, Delhi, INDIA
Registrar ,National Capital Territory of Delhi and Haryana
Note: The corresponding form has been approved by DEBASISH BANDOPADYAY,Registrar and thiscertificate has been digitally signed by the Registrar through a system generated digital signature underrule 36(3)(ii) of the Limited Liability Partnership Rules, 2009The digitally signed certificate can be verified at the Ministry website (www.mca.gov.in).
Mailing Address as per record available in Registrar office:WELLWORTH REALTECH LLP1497, Bharadwaj Bhawan, Kotla, MubarakPur,Delhi - 110003,Delhi, INDIA
It is hereby certified that WELLWORTH REALTECH LLP is this day registered pursuant tosection 58(1) of the LLP Act 2008.
Given at Delhi this Twenty Sixth day of June Two Thousand Fifteen.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
97
AIR DISPERSION REPORT
IMPACT PREDICTION OF POINT EMISSION ON AMBIENT AIR QUALITY
For
Group Housing
At Plot no. 533/1 & 533/2 Village
Chandanhola, Tehsil Hauz Khas, New Delhi
Prepared BY: M/s PERFACT ENVIRO SOLUTIONS PVT. LTD. 501 -507 NN MALL, SECTOR 3 ROHINI NEW DELHI – 110085 PH : 011 –49281360
INTRODUCTION The ambient air quality Ground Level Concentration (GLC) of the area near any project is impacted
due to air pollution sources in the project. The air pollution sources are of two types:
• Point Sources – Chimneys/ Stacks/ ducts/ Vents
• Non-Point Sources – Vehicles, machinery, blasting, drilling etc.
The emissions from these sources spread or disperse in the air and cause increase in the pollution
level in ambient air. This causes an increase in Ground Level Concentration (GLC). This increase in GLC
can be predicted for proposed project using Air Dispersion Modelling. In this study, AERMOD
developed by Lakes Environmental Inc. is used to calculate incremental Ground Level concentrations
(GLC) for the proposed sources of air pollution in the current expansion, for Particulate emissions,
Gaseous emissions (NOx & SO2).
METHODOLOGY For Air Dispersion Modelling following methodology shall be used:
Modelling Procedure AERMOD uses Gaussian plume dispersion modelling parameters, the generalised equation is given
below:
𝒄 =𝑸
𝟐𝝅𝒖𝝈𝒚𝝈𝒛𝒆𝒙𝒑 (−
𝟏
𝟐
𝒀𝟐
𝝈𝟐𝒚) {𝒆𝒙𝒑 [−
𝟏
𝟐 (𝒛 − 𝒉𝟐)
𝝈𝟐𝒛] + 𝒆𝒙𝒑 [−
𝟏
𝟐 (𝒛 + 𝒉𝟐)
𝝈𝟐𝒛]}
Where
c = concentration at a given point (g/m3)
Q = emission rate (g/s)
u = wind speed (m/s)
σy = dispersion parameter in the horizontal (lateral) direction (m)
σz = dispersion parameter in the vertical direction (m)
x = direction of the wind (x = 0 at the source; x > 0 downwind).
y = horizontal direction perpendicular to the wind (y = 0 at the center of the plume; positive on your
left when you look downwind).
z = vertical direction (z = 0 at the surface and positive above the surface).
As well as the effective source height h. They all have meters as units.
Plume Rise
Plume rise h has been determined according to Brigg’s formula (CPCB guideline)
h = 21.425 F3 4 for F<55
Us
and
h = 38.71 F3 5 for F>55
Us
F = g VsD2(Ts-Ta)/4Ts
Where
Us = wind speed at stack level (m/s)
Vs = stack gas velocity (m/s)
Ts = stack gas temperature (K)
Ta = ambient temperature (K)
F = Buoyancy flux parameter (m4/s3)
h = Plume rise (m)
D = Diameter of the stack (m)
g = acceleration due to gravity, 9.807 (m/s2)
Extrapolation of Wind Speed Wind speed at stack level is calculated by power law as given below.
Ustack = U10(Stack height/10)p
Where U10 is the wind speed at 10 meter level and p is the power law coefficient (0.07, 0.07, 0.10,
0.15, 0.35 and 0.55 for stability classes A,B,C,D,E and F respectively) as per Irwin for rural areas (USEPA,
1987).
Stability Classification Hourly stability is determined by wind direction fluctuation method as suggested by Slade (1965) and
recommended by CPCB (PROBES/70/1997-1998).
= Wdr/6
, is standard deviation of wind direction fluctuation, Wdr is the overall wind direction fluctuation or
width of the wind direction in degrees. The table for stability classes is given as under.
Stability Class (degree)
A > 22.5
B 22.4 – 17.5
C 17.4 – 12.5
D 12.4 – 7.5
E 7.4 – 3.5
F < 3.5
Dispersion Parameters Dispersion parameters y and z for open country conditions (Briggs, 1974) are used as the project is
located on a flat terrain in a rural area. Atmospheric dispersion coefficients vary with downwind
distance (x) from emission sources for different atmospheric stability conditions. (CPCB –
PROBES/70/1997-98).
Rural Conditions
Meteorological Data Hourly meteorological data project site for period of one season (Dec. 2018) in respect of wind speed,
wind direction, temperature and cloud amount are utilized in this study which were collected by M/s
Perfact Researchers Pvt Ltd. Mean mixing heights for each hour for region are extracted from the IMD
data and AERMOD Upper air estimator data. These data are used in air quality modelling software.
Ambient Air Quality Standards and Background Concentrations Ambient air quality standards promulgated by Central Pollution Control Board (CPCB) for different areas are as follows:
S. No Pollutant
µg/m3
Time Weighted
Average
Concentration in Ambient Air
Industrial, Residential,
Rural and Other Area
Ecologically Sensitive
Area(Notified by Central
Government)
1. Sulphur Dioxide(SO2), Annual*
24 hours**
50
80
20
80
2. Nitrogen
Dioxide(NO2),
Annual*
24 hours**
40
80
30
80
3. Particulate Matter
(size less than 10µm)
or PM10
Annual*
24 hours**
60
100
60
100
4. Particulate Matter
(size less than 2.5µm)
or PM2.5
Annual*
24 hours**
40
60
40
60
Stability Class y z
A 0.22x(1+0.0001x)-.5 0.20x
B 0.16x(1+0.0001x)-.5 0.12x
C 0.11x(1+0.0001x)-.5 0.08x(1+0.0002x).5
D 0.08x(1+0.0001x)-.5 0.06(1+0.0015x).5
E 0.06x(1+0.0001x)-.5 0.03x(1+0.0003x)-1
F 0.04x(1+0.0001x)-.5 0.16x(1+0.0003x)-1
*Annual arithmetic mean of minimum 104 measurements in a year at particular site taken twice a
week 24 hourly at uniform intervals**24 hours monitored values, shall be compiled with 98% of the
time in a year, 2% of the time, they may exceed the limits but not on two consecutive days of the
morning. The above standards are for a sampling period of 24 hours.
Station No.
Location Mean Baseline
Values for PM10 in µg/m3
Mean Baseline
Values for PM2.5 in µg/m3
Mean Baseline
Values for SO2µg/m3
Mean Baseline
Values for NOx
µg/m3
1 Onsite 226.25 133.85 7.65 41.2
2 Shahurpur 200.25 116.85 6.4 34.2
Plan and Frame Work of Computations
Selection of Locations The locations have been selected around project site covering an area of 10 km radius from the centre
of the project site. The entire area has been put on grid network and grid spacing has been taken as
500 m.
Plan of Computation The emission rate, dispersion coefficients and other input data being now available; it was planned to
compute the following:
- The 24-hourly averaged incremental concentration with hourly data.
- The identification of grid point having peak concentration for the incremental values.
- Preparation of isopleths of for various pollutants.
MODEL OUTPUT FILES
AERMOD OUTPUT ISOPLETH FOR PM2.5 DISPERSION
AERMOD OUTPUT ISOPLETH FOR PM10 DISPERSION
AERMOD OUTPUT ISOPLETH FOR NOx DISPERSION
AERMOD OUTPUT ISOPLETH FOR SO2 DISPERSION
RESULT AND DISCUSSIONS
PREDICTED AMBIENT AIR QUALITY FOR IMPACT OF PM2.5 With available ambient air quality data and incremental concentrations computed through
mathematical modelling the following post project ambient air quality has been predicted. The
maximum GLC for PM2.5 modelling will be 0.625 g/m3.
Table Showing Village PM2.5 Dispersion Results:
PREDICTED AMBIENT AIR QUALITY FOR IMPACT OF PM10 With available ambient air quality data and incremental concentrations computed through
mathematical modelling the following post project ambient air quality has been predicted. The
maximum GLC for PM10 modelling will be 1.11 g/m3.
Table Showing Village PM10 Dispersion Results:
PREDICTED AMBIENT AIR QUALITY FOR IMPACT OF NOx With available ambient air quality data and incremental concentrations computed through
mathematical modelling (Gaussian Plume) the following post project ambient air quality has been
predicted. The maximum GLC for NOx modelling will be 2.98 g/m3 which would be on road.
Location Background Concentration
PM2.5 (g/m3)
Predicted Incremental Concentration PM2.5
(g/m3) DG Sets
Post Project Air Quality PM2.5
(g/m3) DG Sets
NAAQS
(g/m3)
Onsite 133.85 0.137 133.987 60
Shahurpur 116.85 0.065 116.915 60
Location Background Concentration
PM10 (g/m3)
Predicted Incremental Concentration PM10
(g/m3)
Post Project Air Quality PM10
(g/m3)
NAAQS
(g/m3)
Onsite 226.25 0.230 226.48 100
Shahurpur 200.25 0.06 200.31 100
Location Background Concentration
NOX (g/m3)
Predicted Incremental Concentration NOX
(g/m3)
Post Project Air Quality
NOX (g/m3)
NAAQS
(g/m3)
Onsite 41.2 0.432 41.632 80
Shahurpur 34.2 0.085 34.285 80
PREDICTED AMBIENT AIR QUALITY FOR IMPACT OF SO2 With available ambient air quality data and incremental concentrations computed through
mathematical modelling (Gaussian Plume) the following post project ambient air quality has been
predicted. The maximum GLC for SO2 modelling will be 0.553 g/m3.
DATA INTERPRETATION From the results generated by AERMOD in form of Isopleth and results of same in table above show
that maximum GLC of PM10/ PM2.5/SO2/NOX after commencement of project does not have a
significant impact on environment/ ambient air quality on sensitive receptors of the project.
Location Background Concentration
SO2 (g/m3)
Predicted Incremental Concentration SO2
(g/m3)
Post Project Air Quality SO2
(g/m3)
NAAQS
(g/m3)
Onsite 7.65 0.065 7.715 80
Shahurpur 6.4 0.04 6.44 80
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
98
TEST REPORT
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
99
TOPOGRAPHICAL MAP
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
100
LAYOUT PLAN/LANDSCAPE PLAN
145.23
43.93
105.93
31.93
TERRACE
TO BE LANDSCAPED
(OPEN TO SKY)
PODIUM LINE
13.6
13.6
23.75 28.75 11.73
3.75
105.93
31.93
8.123
.83
13.6
18.33
TOWER 1
STILT + 16 FLOORS
9.00
(F
IR
E T
EN
DE
R
MO
VE
ME
NT
)
OTHER'S PROPERTY
12.00
(P
ER
MIS
SIB
LE
S
ET
BA
CK
)
9.00
(F
IR
E T
EN
DE
R
MO
VE
ME
NT
)
3000
BASEMENT LINE
BASEMENT LINE
OTHER'S PROPERTY
12.00
(PERM
ISSIBLE SETBACK)
PLO
T B
OU
ND
AR
Y
AR
EA
U
ND
ER
R
OA
D W
ID
EN
IN
G
(835 sq.m
.)
30M
O
FF
SE
T F
RO
M R
OA
D
CE
NT
ER
LIN
E F
OR
F
UT
UR
E
RO
AD
W
ID
EN
IN
G P
UR
PO
SE
IF
RE
QU
IR
ED
OT
HE
R'S
P
RO
PE
RT
Y
15.00
(PERMISSIBLE SETBACK)
12.00
(PERMISSIBLE SETBACK)
GREEN AREA GREEN AREAGREEN AREA
GR
EE
N A
RE
A
GREEN AREA
GREEN AREA
TOWER 2
STILT + 7 FLOORS
SWACCH DELHI
BLOCK
(as per BBL Clause
12.1 &12.2)
AREA: 40.00 SQ.M.
60
M W
ID
E R
OA
D A
S/Z
DP
-J
GREEN AREA
16.21 11.1
9.00
(FIRE TENDER
MOVEMENT)
RAM
P DO
WN
TO B
ASEM
ENT 01
UP RAMP FROM
BASEMENT 01
9.00
(FIRE TENDER
MOVEMENT)
9.00(FIRE TENDERMOVEMENT)
13.03
7.3 7.313
.03
13.03
7.3
13.913.913.9
145.23
43930
31.4
4.656.45
87.08
44.71
148.7515.26 13.02
58.02
12.22 .7 31.38
4.04
57
EN
TR
Y/E
XIT
TO
A
ND
HE
RIA
M
OD
E
TO
B
HA
TI
SETBACK LINE
SETBACK LINE
710.491.292.3215.25
WARD CABIN : 6 SQ.M.
(TEMPORARY)
EXISTING STRUCTURE TO BE
DEMOLISHED
EXISTING STRUCTURE
TO BE DEMOLISHED
6
6
6.24
6.62
7.08
9.79
9.08
PLOT BOUNDARY
PLOT BOUNDARY
SETBACK LINE
BA
SE
ME
NT
LIN
E
HEIGHT 30 M
LVL +3.30 m
HEIGHT 78.00 M
GR
EE
N A
RE
A
COMMUNITY NEEDS AS PER MPD
2021(LATEST AMENDMENTS)
(AT 1ST FLOOR )
CLUB & SOCIETY OFFICE
93.76 SQ.M.
COMMUNITY NEEDS AS PER MPD
2021(LATEST AMENDMENTS)
(AT 1ST FLOOR )
RECREATIONAL HALL
149.53 SQ.M.
COMMUNITY NEEDS AS PER MPD
2021(LATEST AMENDMENTS)
(AT 1ST FLOOR )
COMMUNITY HALL
93.76 SQ.M.
COMMUNITY NEEDS AS PER MPD
2021(LATEST AMENDMENTS)
(AT 1ST FLOOR )
READING ROOM/LIBRARY
62.84 SQ.M.
CHANGING ROOM FOR
SWIMMING POOL
(AT 1ST FLOOR )
99.96 SQ.M.
COVERED SWIMMING
POOL
11.76 m X 8.5 m
(100 sqm COVERED POOL
FREE FROM FAR)
TERRACE
TO BE LANDSCAPED
(OPEN TO SKY)
TERRACE
TO BE LANDSCAPED
(OPEN TO SKY)
7.46
7.11
12
151.23
931
.939
4.8
30
6.77
6.55
6
4.8
151.23
31.93
31.93
SWIMMING POOL
LEVEL+4.45 M
DEVELOPMENT CONTROL
GROUND COVERAGE
REGULATIONS
EXISTING
(IF ANY)
PROPOSED
FAR
HEIGHT (METRE)
PARKING
DENSITY (DU's / Ha.)
FRONT SETBACK (METRE)
REAR SETBACK (METRE)
LEFT SETBACK (METRE)
RIGHT SETBACK (METRE)
GREEN AREA
200
33%
NR
421
200
15
12
50%
12
12
199.70
17.06%
78
440
115.00
15
12
12
12
50.09%
DESCRIPTION
SETBACK LINE
PODIUM LINE
AREA FOR
ROAD WIDENING
COMMUNITY NEEDS AS PER
MPD 2021(latest amendments)
LEGENDS
BASEMENT LINE
MAIN ROAD
PLOT BOUNDARY
EXISTING STRUCTURES
BUILDING LINE
GREEN AREA
FIRE TENDER PATH
N
SCALE:
1:200
OWNER'S
SIGN:
TOWN PLANNER'S
SIGN:
OWNER:
M/S WELLWORTH REALTECH
L.L.P.
NORTH
LAYOUT PLAN OF GROUP HOUSING ON PLOT
BEARING KH. NOS. 533/1 (7-12) & 533/2 (5-6)
SITUATED IN VILLAGE CHANDANHAULA, (LAL
DORA AREA) TEHSIL HAUZ KHAS, NEW DELHI.
PROPOSEDSITE
DERA
BHATTI
ASOLA
SATBARI
JOANPUR
RATEHPUR
CHATTARPUR
CHANDANHAULA
RAJOKRI
RAPASHERA
MEHRAULI
Main C
hhatarppur R
oad
To A
ndheria M
or
V
illa
g
e
R
o
a
d
V
i
l
l
a
g
e
R
o
a
d
A
s
o
la
R
o
a
d
Village Road
SITE FOR
GROUP HOUSING
OTHERS PROPERTY
OTHERS PROPERTY
OTHERS PROPERTY
OTHERS PROPERTY
OTHERS PROPERTY
OTHERS PROPERTY
HINDU
TEMPLE
N
N
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
101
SURVEY PLAN
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
102
STORM WATER PLAN
DOWN TO UPPER
BASEMENT
TOWER 2TOWER 1
40000
PODIUM LINE
105925
31930
8100
23830
13600
18330
90
00
(F
IR
E T
EN
DE
R
MO
VE
ME
NT
)
OTHER'S PROPERTY
12000
(S
ET
BA
CK
)
90
00
(F
IR
E T
EN
DE
R
MO
VE
ME
NT
)
30
00
BASEMENT LINE
BASEMENT LINE
OTHER'S PROPERTY
12000
(SETBACK)
PLO
T B
OU
ND
AR
Y
AR
EA
U
ND
ER
R
OA
D W
ID
EN
IN
G
(835 sq.m
.)
30M
O
FF
SE
T F
RO
M R
OA
D
CE
NT
ER
LIN
E F
OR
F
UT
UR
E
RO
AD
W
ID
EN
IN
G P
UR
PO
SE
IF
RE
QU
IR
ED
OT
HE
R'S
P
RO
PE
RT
Y
15000
(SETBACK)
12000
(SETBACK)
GREEN AREA
GREEN AREA
GREEN AREA
GR
EE
N A
RE
A
GREEN AREA
GREEN AREA
SW
AA
CH
D
EL
HI B
LO
CK
60M
W
ID
E R
OA
D A
S/Z
DP
-J
GREEN AREA
16205 11100
9000
(FIRE TENDER
MOVEMENT)
RAM
P DO
WN
TO B
ASEM
ENT 01
UP RAMP FROM
BASEMENT 01
9000
(FIRE TENDER
MOVEMENT)
9000
(FIRE TENDER
MOVEMENT)
145230
43930
31400
46506450
87085
44715
16177015260
5802
5
12220 700
31380
4040
5700
5
EN
TR
Y/E
XIT
TO
A
ND
HE
RIA
M
OD
E
TO
B
HA
TI
SETBACK LINE
SETBACK LINE
70001048512009000232515250
WARD CABIN
WITH WC: 6 SQ.M.
SITE PLAN
3
MH MH MH MH MH MH
MH
MH
MH
MH
MH MH MH MH MH MH MH
MH
MH
MH
GH GH GH GH GH GH GH GH
GH
GH
GH
GH
GH
GH
GH
GH GH
GH
GH
GH
AT
M
4000
2900
2900
9800
3000
20
00
SWMHSWMHSWMHSWMHSWMHSWMHSWMH
SWMH SWMH SWMH SWMH SWMH SWMH SWMH SWMH
SWMH
SWMH
SWMHSWMH
GTGTGTGTGTGT
GT
GT
GT
GTGTGTGTGTGT
DSILTING CHAMBER
RWH PIT
TO STORM
WATER DRAIN
DSILTING CHAMBER
RWH PIT
TO STORM
WATER DRAIN
DSILTING CHAMBER
RWH PIT
9
9
9
2 1
2 1
2
10
3 5 4
4
5 4
3
6
4
3
2 1
2
1
5
4
3
2
1
5
3 4 5 3 4 5 2 1
9
9
9
9
1
2
1
2
1
2
1
3
4 5
5
4
2
3
3
3
4
5
4
5
6
9 9 9 9 9 9 9 9 9
9
9
9
9
9
9
1 2
2
1 2
2 1
1 2
2
2
10
10
5 4
3
3 5 4
4
1
3
5
4
2
4
3
2
1
5
4
3
2
1
5
5 4
3
5 4
3
2 1 3 5 4
4
4
2 1 3
5 4
1
2
3
4
5
1
2
45
3
1
2
3
4
5
2 1 2 1 3 4 5 3 4 5
6
6
6
6
9 9 9
9
9
9
9
9
1
2
2 1
2
5 4
3
2 1 3 5 4
4
4
3
2
1
5
1
3
5
4
2
3
4
5
1
2
4 5
3
2 1 3 4 5
1
2
3
4
5
6
6
LVL +59.00
LVL +59.00
LVL +59.00
FIRE WATER TANK
CAP: 20 CUM
W.D. 1.5 M
DOM. WATER
TANK
CAP: 10 CUM
W.D. 1.5 M
FLUSHING
WATER
CAP: 20 CUM
W.D. 1.5 M
FIRE WATER TANK
CAP: 20 CUM
W.D. 1.5 M
DOM. WATER
TANK
CAP: 10 CUM
W.D. 1.5 M
FLUSHING
WATER
CAP: 20 CUM
W.D. 1.5 M
FIRE WATER TANK
CAP: 20 CUM
W.D. 1.5 M
DOM. WATER
TANK
CAP: 10 CUM
W.D. 1.5 M
FLUSHING
WATER
CAP: 20 CUM
W.D. 1.5 M
FIRE WATER TANK
CAP: 20 CUM
W.D. 1.5 M
DOM. WATER
TANK
CAP: 10 CUM
W.D. 1.5 M
FLUSHING
WATER
CAP: 20 CUM
W.D. 1.5 M
LVL +59.00
MUMTY
MUMTY
SPACE FOR SOLAR PANEL SPACE FOR SOLAR PANEL
2
1
2
1
2
1
2
1
2
1
2
1
9
9
9
9
9
9
7
8
FIRE WATER
TANK
CAP: 5 CUM
DOM. WATER
TANK
CAP: 15 CUM
OVERFLOW PIPE FROM
FIRE TO DOM. TANK
FLUSHING
WATER
CAP: 5 CUM
LVL +52.45
LVL +52.45
LVL +52.45
LVL +52.45
7 8 7 8
33320
LVL +24.60
SE
C
C
SE
C
C
7455
7105
12000
151230
9000
31930
9000
4800
30000
6765
6550
6000
4800
151230
31930
31930
9000
3193
0
9000
31
93
0
9000
02.
03.
04.
05.
06.
07.
08.
09.
10.
LEGENDS FOR PLUMBING
01. 1
2
3
4
5
6
7
8
9
10
100 Ø SOIL AND VENT PIPE
100 Ø WASTE AND VENT PIPE
75 Ø VENT PIPE
DOMESTIC WATER SUPPLY DN. TAKE
FLUSHING WATER SUPPLY DN. TAKE
HOT WATER SUPPLY DN. TAKE FROM SOLAR PANEL
DOMESTIC WATER SUPPLY RISER TO O.H.T
FLUSHING WATER SUPPLY RISER TO O.H.T
100 Ø RAINWATER PIPE
150 Ø RAINWATER PIPE
DETAIL OF PIPE CONNECTION
* FROM WC TO STACK\MH....100Ø PIPE
* FROM FT TO STACK\GT......100Ø PIPE
* FROM WB TO FD\FT...............40Ø PIPE
* FROM WC WASTE TO FT.......50Ø PIPE
* FROM BT/SH TO FT................65Ø PIPE
* FLOOR TRAP 100 X 100...FT
* FLOOR DRAIN 100 X 65 / 100X 50......FD
* FLOOR CLEAN OUT 100 X 100...........COP
LEGENDS
SYMBOL DESCRIPTION
300 X 300 EARTH PITING CHAMBER
IRRIGATION WATER SUPPLY
DOM. WATER SUPPLY LINE
GARDEN HYDRANTGH
SEWER LINE
STORM WATER PIPES
SWMH
MH
EXTERNAL FIRE HYDRANT LINE
EXTERNAL FIRE HYDRANT
SETBACK LINE
BASEMENT LINE
PLOT LINE
ROAD
N
DRAWING NO. :
OWNER'S SIGN:
ARCHITECT'S SIGN:
OWNER:
M/S WELLWORTH REALTECH
PVT. LTD.
NORTH
DRAWING TITLE
SCALE: 1:200
Main C
hhatarppur R
oad
To A
ndheria M
or
V
illa
g
e
R
o
a
d
V
i
l
l
a
g
e
R
o
a
d
A
s
o
la
R
o
a
d
Village Road
SITE FOR
GROUP HOUSING
OTHERS PROPERTY
OTHERS PROPERTY
OTHERS PROPERTY
OTHERS PROPERTY
OTHERS PROPERTY
OTHERS PROPERTY
PROPOSEDSITE
DERA
BHATTI
ASOLA
SATBARI
JOANPUR
RATEHPUR
CHATTARPUR
CHANDANHAULA
RAJOKRI
RAPASHERA
MEHRAULI
LOCATION PLAN
1
KEY PLAN
2
SITE PLAN
A - 1.0
ROAD AREA DIAGRAM4
PROPOSED BUILDING PLAN FOR CONST.
OF A GROUP HOUSING ON PLOT BEARING
KH. NOS. 533/1 (7-12) & 533/2 (5-6) SITUATED
IN VILLAGE CHANDANHAULA, LAL DORA
AREA, TEHSIL HAUZ KHAS, NEW DELHI.
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
103
DUAL PLUMBING PLAN
Group Housing at Khasra nos. 533/1 & 533/2 Village Chandanhaula, Tehsil Hauz Khas, New Delhi by Wellworth Realtech LLP
Environment Consultant: -M/s Perfact Enviro Solutions Pvt. Ltd.
104
PARKING PLAN