102
ENVIRONMENTAL CLEARANCE APPLICATION “Building Stone Quarry” of Sri Ashok S Banakar Sri Ashok S Banakar, C/o Sai Traders, P B Road, Haveri-581110. Over an extent of 1-20 Acres under (Government Land) Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka.

“Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

ENVIRONMENTAL CLEARANCE APPLICATION

“Building Stone Quarry” of

Sri Ashok S Banakar

Sri Ashok S Banakar,

C/o Sai Traders,

P B Road,

Haveri-581110.

Over an extent of 1-20 Acres under (Government Land)

Sy No. 75,

Kajjari village,

Ranebennur Taluk

Haveri District,

Karnataka.

Page 2: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 1

Contents

1. FORM 1 ........................................................................................................................... 3

(I) Basic Information ............................................................................................................ 3

(II) Activity ........................................................................................................................ 4

(III) Environmental Sensitivity ......................................................................................... 11

(IV) Proposed Terms of Reference for EIA studies .......................................................... 12

2. PRE-FEASIBILITY REPORT .............................................................................................. 15

2.1 Executive Summary ............................................................................................... 15

2.2 Introduction of the project/ Background information ......................................... 15

2.3 Project Description ................................................................................................ 16

2.4 Site Analysis ........................................................................................................... 18

2.5 Planning Brief ........................................................................................................ 20

2.6 Proposed Infrastructure ........................................................................................ 21

2.7 Rehabilitation and Resettlement (R & R) Plan ...................................................... 22

2.8 Project Schedule & Cost Estimates ....................................................................... 23

2.9 Analysis of proposal(Final Recommendation) ...................................................... 24

3. ENVIRONMENTAL MANAGEMENT PLAN ...................................................................... 25

3.1 Introduction........................................................................................................... 25

3.2 Estimation of reserves ........................................................................................... 25

3.3 Project Description ................................................................................................ 26

3.4 Baseline Environment ........................................................................................... 28

3.4.1 Land environment ............................................................................................. 28

3.4.2 Geomorphology and Soils .................................................................................. 29

3.4.3 Noise and vibrations .......................................................................................... 30

3.4.4 Air Quality .......................................................................................................... 30

3.4.5 Climatic conditions ............................................................................................ 30

3.4.6 Socio-Economic environment ............................................................................ 30

3.5 Environmental Management Plan ........................................................................ 31

3.5.1 Introduction ....................................................................................................... 31

3.5.2 Environmental Impact Statement & Control measures .................................... 31

3.5.2.1 Climate ........................................................................................................... 31

3.5.2.2 Air Environment ............................................................................................. 31

3.5.2.2.1 Dust Control ................................................................................................... 32

3.5.2.3 Noise Environment ........................................................................................ 32

3.5.2.4 Water Environment ....................................................................................... 33

3.5.2.5 Storm Water Management ............................................................................ 33

3.5.2.6 Land Restoration/Reclamation ...................................................................... 34

3.5.2.6.1 Reclamation Schedule .................................................................................... 34

3.5.2.6.2 Back-filling/Dumping of Overburden ............................................................. 35

3.5.2.6.3 Preparation of Quarry Benches for Afforestation ......................................... 35

3.5.2.7 Maintenance of Roads ................................................................................... 35

3.5.2.8 Topsoil Management ..................................................................................... 35

3.5.2.9 Plantation ....................................................................................................... 35

3.5.2.9.1 Plantation Species .......................................................................................... 36

3.5.2.9.2 Nursery ........................................................................................................... 36

3.5.2.9.3 Planting Methodology ................................................................................... 37

3.5.2.9.4 Stabilizing Planting: ........................................................................................ 37

Page 3: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 2

3.5.2.9.5 Plantation Schedule: ...................................................................................... 37

3.5.2.9.6 Provision of Green Belt along the affected area ........................................... 38

3.5.2.10 Control on Soil Erosion ................................................................................... 38

3.5.2.11 Management of Socio Economic status ........................................................ 38

3.5.2.12 Disaster Management Plan ............................................................................ 38

3.5.2.13 Occupational Safety and Health: ................................................................... 38

3.6 Environmental Monitoring .................................................................................... 39

3.7 Environmental Management Cell ......................................................................... 39

3.8 Conclusions............................................................................................................ 40

Table 2-1 Details of production and waste .......................................................................... 17

Table 2-2 Land use details .................................................................................................... 19

Table 3-1 Category wise Geological and Mineable reserves calculation for Block ............. 26

Page 4: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 5: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 6: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 7: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 8: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 9: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 10: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 11: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 12: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 13: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 14: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 15: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 16: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 17: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 15

2. PRE-FEASIBILITY REPORT

2.1 Executive Summary

The proposed project is Building stone quarry having lease area of 1.607 ha and falls

under Category- “A” as per EIA Notification 2006 and its amendments of the Ministry

of Environment and Forests, New Delhi due to the applicability of general condition.

The project site is 1.47 kms from the Ranebennur Wildlife Sanctuary.

Department of Mines and Geology, Haveri has Notified the area in the name of Sri. Sri

Ashok S Bankar, Stone Crushers to an extent of 1-20 Acres in Sy No. 75, Kajjaari

Village, Ranrbennur Taluk , Haveri District , Karnataka. The sketch showing the

demarcated area to be granted under Quarrying Lease, is enclosed as Plate No.2.

Copy of Notification is herewith attached in the Quarrying Plan.

2.2 Introduction of the project/ Background information

i) Identification of project and project proponent. In case of mining project, a copy of

mining lease/ letter of intent should be given:

Identification of project:

Extent: 1-20 Acres

“Building Stone Quarry” Of

Sri Ashok S Banakar,

at Sy No: 75, Kajjaari Village, Bengaluru Taluk, Bengaluru District, Karnataka.

Project proponent

Sri Ashok S Banakar,

C/o Sai Traders,

P B Road,

Haveri-581110,

Karnataka

Karnataka. It is a Building Stone Quarry, and copy of Notification from Department

of Mines & Geology is enclosed.

ii) Brief description of nature of the project:

It is a Building Stone Quarry. It is a project of 1-20 Acres with average production of

capacity of – 20,000 TPA.

iii) Need for the project and its importance to the country and or region:

Although, the project is small it plays important role in the development of the region

and country as Building Stone.

Page 18: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 16

iv) Demand- Supply Gap:

There is a good demand for Building Stone.

v) Imports vs. Indigenous production:

Not applicable.

vi) Export Possibility:

Not applicable.

vii) Domestic/ export Markets:

Domestic market –Bengaluru, etc.

viii) Employment Generation (Direct and Indirect) due to the project.

About 18 people will get direct employment and equal number will get indirect

Employment.

2.3 Project Description

i) Type of project including interlinked and interdependent projects, if any:

It is only Quarry and there will not be any interlinked and interdependent projects.

ii) Location (map showing general location, specific location, and project boundary &

project site layout) with coordinates:

Location of the project issued by the Department of Mines & Geology and

Toposheet on 1:50,000 scale is enclosed. In the quarry plan.

iii) Details of alternate sites, considered and the basis of selecting the proposed site,

particularly the environmental considerations gone into should, be highlighted:

Building Stone quarry is site specific.

iv) Size or magnitude of operation:

It is only a small scale Building Stone quarrying with capacity of – 20,000 TPA.

Year wise development for next five years:

Page 19: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 17

The Building Stone deposit is a Flat Ridges which is sloping gently SE and is well

exposed in the entire area. The deposit is wide enough for opening along the

strike. An open cast Other than fully Mechanised method will be adopted to

operate the area. Since, the annual production is 20,000 TPA; the Open cast

method will be followed during the plan period. The Tonnages of saleable stone and

intercalated waste during the plan period is as given below:

Table 2-1 Details of production and waste

Year Saleable Building stone 95%

Waste 5%

1 20,000 1053

2 20,000 1053

3 20,000 1053

4 20,000 1053

5 20,000 1053

Total 1,00,000 5,263

Proposed method of quarrying: Quarrying will be carried out by open cast semi

mechanization method by using compressor operated jack-hammer drills, truck dumpers

etc. As the rock is exposed the open cast quarrying will be sufficient.

v) Project description with process details (a schematic diagram/ flow chart showing

the project layout, components of the project etc. should be given):

It is only a Building Stone quarrying no processing is involved, the details of quarrying

is detailed in quarrying plan.

vi) Raw material required along with estimated quantity, likely source, marketing area

of final product/s, Mode of transport of raw material and finished product:

No raw materials required. Broken Building Stone rock will be transported by

tippers/trucks.

vii) Resource optimization /recycling and reuse envisaged in the project, if any, should

be briefly outlined:

No recycling and reuse of material is envisaged.

viii) Availability of water its source, Energy /power requirement and source should be

given:

Water will be availed from nearby bore wells. No energy /power requirement.

Page 20: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 18

ix) Quantity of wastes to be generated (liquid and solid) and scheme for their

Management /disposal :

No wastes to be generated (liquid and solid). The waste material is dumped in the

waste dump yard as shown in Quarrying plan.

x) Schematic representations of the feasibility drawing which give information of EIA

purpose:

2.4 Site Analysis

i) Connectivity:

Page 21: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 19

The granted area is easily workable in all seasonal conditions. The area is 1.60 Km

NE of Budapanahalli Village. The land is Government land consisting mainly of

Building Stone. All facilities such as, post and telegraph office, Hospital, Police

Station, Schools and Colleges are available at Ranebeenur.

ii) Land Form, Land use and Land ownership:

Land is a Government Land. The entire area is nonagricultural barren land.

iii) Topography(along with map):

A view at a Topo sheet No. 48 N/10 following topo graphic features can be observed

(Topo map enclosed).

• The applied area is waste land.

• The terrain is Flat Ridges and has a gentle slope towards SE direction.

• No major roads pass through the applied area.

• No human settlements within or in the vicinity of the applied area. The

nearest village is at a distance 1.60 Km.

• The general elevation of the area is between 624 and 628m above MSL.

The nallahs flow in the SE direction and act as channels during rainy

season.

iv) Existing land use pattern (agriculture, non-agriculture, forest, water bodies

(including area under CRZ)), shortest distances from the periphery of the project

to periphery of the forests, national park, wild life sanctuary, eco sensitive areas,

water bodies(distance from, the HFL of the river), CRZ, In case of notified industrial

area, a copy of the Gazette notification should be given:

Land use and break up is given as follows:

About 0-31 land will be used for quarrying in the plan period. The present land use

pattern and proposed after 5 years are given bellow. Statutory buildings will be away

from the lease area

Table 2-2 Land use details

Present Land use Propsed Area in Acres

Mine workings 0-31

Roads -

Waste dumps --

Infrastructure --

Page 22: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 20

Mineral Storage --

Safety Zone 0-29

Unexplored area --

Total 1-20

v) Existing Infrastructure:

Within the site - Nil.

vi) Climatic data from secondary sources:

The climate is tropical. The peak summer will be in the month of May. The highest

temperature of 35°C was recorded in this area during the month of May and the

lowest of 23°C was recorded in the month of December.

vii) Social Infrastructure available

Nil.

2.5 Planning Brief

i) Planning Concept (type of industries, facilities, transportation etc) Town and

country Planning/ Development authority classification.

It’s a quarrying project and its material will be used in Aggregate Manufacturing

Industry’s crushers for primary, secondary and tertiary crushing. The area

characterized with prominent sheet rock exposures and it is planned to work this

deposit by adopting semi-mechanized opencast quarrying method. Ultimate pit slope

of 450 shall be maintained. During the plan period production and development

details as furnished in quarry plan. At the end of the conceptual period afforestation

will be done all along the approach road. Barbed wire fence will be established all

around the lease area, safety bunds, fencing shall be constructed as per the directions

and guide lines of DMG and DGMS.

ii) Population Projection

The man power required for quarry operations include quarry manager, engineer,

skilled, semi-skilled, un – skilled labourers etc., As for the socio-economic is

concerned from the quarry activity nearby villagers shall get direct and indirect

employment. The proposed quarry activities shall bring positive change in the villages

Page 23: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 21

as the quarry proponent shall provide socio-economic activities in the region. Total of

16 persons will be employed.

iii) Land use planning (breakup along with green belt etc.)

Enclosed in the quarry plan

iv) Assessment of Infrastructure Demand (Physical & Social)

The existing road network will be sufficient to meet the proposed production capacity.

Only approach road formulated to reach the quarry. However, required infrastructure

for transport within the quarry area will be further strengthened and improved. No

new routes or alternations are required in this regard.

v) Amenities/ Facilities

Security guard house and a weigh bridge is proposed within 1-20 Acres. Lessee

proposes to employ about 18 or more persons directly and around 40 or more

number of persons indirectly. This employment has a positive impact on socio

economic conditions of the nearby villages as most of the work force will be from the

nearby areas. Local persons will be hired for meeting the requirement of quarrying

operations like water sprinkling, trucks loading, plantation, establishment of garland

drains, gully checks etc. drinking water, rest shelter and first aid will provided to

workers at quarry site.

2.6 Proposed Infrastructure

i) Industrial Area(Processing Area)

Nil

ii) Residential Area (Non Processing Area)

Nil

iii) Green Belt

About 75 saplings will be planted every year, along approach road.

Page 24: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 22

iv) Social Infrastructure Connectivity (Traffic and Transportation Road/Rail/Metro

/Water ways etc):

The granted area is easily workable in all seasonal conditions. The area is at 1.6 Km

from Budapanahalli Village.

v) Drinking Water Management (Source & Supply of water):

Bore well water using a tanker.

vi) Sewerage System:

Sewage generation is minimal-Septic tank.

vii) Industrial Waste Management:

Not applicable.

viii) Solid Waste Management:

There is small quantity of soil cover in the quarry lease area the same will be used for

afforestation purpose (Ref. Plate No. 6 of Quarry Plan). Intercalated waste is produced

may be of defective material along the emplacements of pegmatite/epidote veins and

deformed material along the fractures. It is estimated that 5% of entire will account

for intercalated waste, which shall be used for maintenance of haulage/approach

roads and used as foundation filling material for minor building constructions. No toxic

of hazardous elements are reported in the waste & hence, no effect on the

surface/ground water.

ix) Power Requirement & Supply /source:

There will not be any requirement of power supply to the project site. The quarry

activities are envisaged to be carried out only during day time. All the equipment shall

be operated with diesel as motive power.

2.7 Rehabilitation and Resettlement (R & R) Plan

Opencast quarrying operations will alter the topography of the area by way of

excavation and formulating pit. As there is no dump proposal within the Quarry Lease

area issues of water pollution, silting of agricultural lands, air pollution etc., will be

very minimal even though proper preventive measures will be implemented to

Page 25: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 23

maintain the natural condition of surrounding environment. The primary objectives of

reclamation are to restore the affected area to the original state as near as possible.

Various reclamation proposals planned during the plan period as well, rest of the

quarry period such as broad working pit with safe angle of slope, establishment of

effective drainage system, prevention of erosion and excessive run off and

afforestation.

As the quarry area is concerned, so far none of the quarry area is matured or

completely exhausted. Hence, the measures like drainage system and afforestation

works etc., shall be taken up.

2.8 Project Schedule & Cost Estimates

i) Likely date of start of construction and likely date of completion(Time schedule for

the project to be given):

Quarrying will start within a month after getting EC clearance.

ii) Estimated project cost along with analysis in terms of economic viability of the

project:

Estimated project cost is 200 lakhs (including the cost of machinery and additional

preliminary works and working capital etc). It is economically viable as it is quarrying

of the Building Stone.

The return on the investment is by way of sale of mineral (Building Stone). All the

Building Stone will be supplied to crushers. Required machineries will be procured or

shall be hired on contract basis. The proposed annual production of building stone is

48,397tonnes. The major components required to the project are:

Cost of the project

Means of financing

Cost of production

Tax burden and flows

Profitability

1. Cost of the project

The cost of the project consists of the following major components:

a) Land and site development

b) Building and civil works

Page 26: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 24

c) Machinery

d) Processing charges and consultancy charges for preparation of quarry plan,

EMP reports etc.,

e) Margin money for working capital

2. Cost of production

The average proposed production of building stone during the first five years is around

20,000 tonnes per annum. The cost of production includes the following parameters.

Parameters:-

1. Minable reserves - 81,344 Tonnes

2. Nature of ore - Building Stone

3. Production of building stone - 20,000 tonnes per annum

Table 2-3 Production cost for the building stone material for the project

Saleable Building

stone (95%) in Tons

Cost of production

per ton Including Royalty

Total Cost of production in

Rupees

Market price

per Sq.m.

Market price

for the

production in

Rupees

I year 20,000

200

40,00,000

300

60,00,000

II Year 20,000 40,00,000 60,00,000

III Year 20,000 40,00,000 60,00,000 IV Year 20,000 40,00,000 60,00,000 V Year 20,000 40,00,000 60,00,000

Total 1,00,000 200 200,00,000 300 300,00,000

*The details mentioned above is just for the project assessment.

2.9 Analysis of proposal(Final Recommendation)

i) Financial and social benefits with special emphasis on the benefit to the local

people including tribal population, if any, in the area.

Quarrying activity improves the economic status of the village people working in the

area. Overall improvement will be expected in local area.

The building stone quarry with proposed annual production of 20,000 tonnes. The

financial estimates reveal good rate of returns. The project is economically viable. The

estimates have also taken into consideration the occupational health expenses,

environmental protective measures, social welfare activities, etc.

Page 27: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 25

3. ENVIRONMENTAL MANAGEMENT PLAN

3.1 Introduction

Sri Ashok S Bankar, has Applied for quarry lease for extracting of Building stone in Sy

No. 75, Kajjaari Village, Ranrbennur Taluk, Haveri District, Karnataka over an extent of

1-20 Acres for production capacity of 20,000 TPA (aggregate).

Department of Mines and Geology, Haveri has Notified the area in the name of Sri

Ashok S Bankar , to an extent of 1-20 Acres in Sy No.75, Kajjaari Village, Ranrbennur

Taluk , Haveri District , Karnataka. The sketch showing the demarcated area to be

granted under Quarrying Lease, is enclosed as Plate No.2.

Copy of Notification is herewith attached in the Quarrying Plan.

As per the statuary obligation this project needs Environmental Clearance from SEIAA

Karnataka for Quarrying. Accordingly submitting 1) Form- I, 2) Pre-Feasibility Report,

3) Quarry Plan approved by District Mines and Geology, 4) Land documents, 5)

Notification, 6) Statutory Clearances, 7) Survey of India Toposheet duly marking the

project site. To the State Level Environment Assessment Authority of Karnataka

constituted by MoEFCC, GoI for issuing Environment Clearance as per EIA September

14, 216 Notification.

The Environmental Management Plan report has been prepared for the

documentation of environmental impact from the activity and significant measures to

mitigate the impact.

This Environmental Management Plan report has been prepared for submission to

State Level Environmental Appraisal Committee/State Level Environmental Impact

Assessment Authority constituted by MOEF for obtaining Environmental Clearance.

3.2 Estimation of reserves

The reserves are estimated considering, one block of 1-20 acres at the west. The

norms of Reserve estimation are of counting squares of sectional areas marked on the

cross sections. About 1,62,806 Tons of ‘Geological Reserves’ are estimated in block. In

order to meet the various statutory requirement some part of the lease area cannot

be excavated i.e 7.5mtrs safety zone area along the Mining Lease boundary & after

deducting the quantity of Non Mineable area, the Quarry able / Mineable reserves

estimated are 81,344 Tons in block. The details of reserve estimation is as follows:

Page 28: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 26

Table 3-1 Category wise Geological and Mineable reserves calculation for Block

Cross Section with Ref. to plan

Sectional Area of Granitic

Strike influence in m

Volume of granitic gneiss in M3

Rec. % Age. 95%

Insitu Reserves in Metric Ts @ 2.5 M3

Wastage of granitic gneiss in metric Ts @2.5 M3 per ton

Proved / Measured Reserves (111)

A-A’ 388 50 19,400 95 46,075 2425

B-B’ 458 50 22,900 95 54,388 2863

C-C’ 525 50 26,250 95 62,344 3281

Total 1,371 50 68,550 95 1,62,806 8569

Probable / Measured Reserves (121 & 122)

A-A’ 194 50 9700 95 23,038 1213

B-B’ 229 50 11,450 95 27,194 1431

C-C’ 262 50 13,100 95 31,113 1638

Total 685 50 34,250 95 81,344 4281

Inferred Mineral Resources (333)

A-A’ 194 50 9700 95 23,038 1213

B-B’ 229 50 11,450 95 27,194 1431

C-C’ 262 50 13,100 95 31,113 1638

Total 685 50 34,250 95 81,344 4281

3.3 Project Description

Year wise development for next five years: The Building Stone deposit is a Flat

Ridges which is sloping gently SE and is well exposed in the entire area. The

deposit is wide enough for opening along the strike. An open cast Other than fully

Mechanised method will be adopted to operate the area. Since, the annual

production is 20,000 TPA; the Open cast method will be followed during the plan

period.

The Tonnages of saleable stone and intercalated waste during the plan period is as

given below:

Table 3-2 Details of production and waste

Year Saleable Building stone 95%

Waste 5%

1 20,000 1053

2 20,000 1053

3 20,000 1053

4 20,000 1053

5 20,000 1053

Total 1,00,000 5,263

Page 29: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 27

Proposed method of quarrying: Quarrying will be carried out by open cast semi

mechanization method by using compressor operated jack-hammer drills, truck

dumpers etc. As the rock is exposed the open cast quarrying will be sufficient.

Extent of mechanization: The Method of mining shall continue to be Other than fully

mechanized method. There will be no changes in the proposed method of mining and

deployment of machinery.

The following machines are proposed to be hired and used in the mines.

Table 3-3 List of Machineries Type Nos.

Excavator 1

Tippers 2

Compressors 1

Water Tanker 1

Jeep 1

Drilling: Depending upon the requirement of the size of lumps, to dislodge the same,

drilling will be done in a single row by jack hammer. Drilled holes will be filled by the

Cracking agent, where next day the lumps gets dislodge by the main rock mass.

Loading: Loading will be done with the help of excavators and loaders.

Hauling and Transport: Transportation will be done by using trucks and tractors etc.,

the waste and the other over burden will be transported to the waste dumping yard

by using trucks/ tractors. The lumps are kept at the stack yard earmarked. The

materials will be transported to the destination by hired trucks.

Disposal of Rejects and Waste: About 3,947 Tons of mineral is being treated as waste

in this area for first five year. The waste material is stacked in the waste dump yard

and if required will be sent to road construction works. This material can be utilized till

the quarrying operations are over. When the dump reaches optimum height, suitable

greenery will be grown on this dump to stabilize them.

Page 30: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 28

Table 3-4 Employment Potential

1. Permite Mines Manager 01

2. Blaster 01

3. Supervisor 01

4. Excavator & Tipper Operator 03

5. Driller & Driller Helper 02

6. Face Workers 09

7. Watch & Ward 01

Total 18

3.4 Baseline Environment

3.4.1 Land environment

The terrain consists of hilly ridge and gentle slope towards North Western & North

Eastern side. The elevation difference of this mound is 624-628m above MSL.

Land is a Government Land. The entire area is a hillock where earlier worked pits

cover almost 60% of the site.

Proponent will take necessary steps to keep the area under disturbance to the

minimum at any stage of quarrying operations. This shall be achieved by ensuring

reclamation of the excavated area concurrently with the quarrying activities by

reducing the gap between the first damage (due to quarrying and other activities) and

the first repair (reclamation) to the minimum. The first step will be a successful

reclamation programme, which is to decide the post-reclamation land use. In the case

of the present quarrying area, it would be appropriate to convert the quarrying out

area into a water-body with shady-surroundings due to the following reasons:

As the quarry has a long life due to the vast size of the Building Stone

deposit, rejects generated during the quarrying need to be systematically

dumped and stabilized. Therefore, back filling and restoration of quarried-

out area to pre-quarrying land use before abandoning is not feasible.

With the above scenario, the post reclamation land use of water body,

peripheral tree belt and patches of grass shall blend into the surrounding

plantation set-up. The reclamation plan shall include working of following

areas:

Inside quarry,

External Dumps,

Roads, structures etc.

The disturbed land will be fully reclaimed before abandoning the quarry. To

depict the total land use within the quarry area due to the proposed

activities, stage plans have been prepared at five yearly intervals. The land

Page 31: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 29

uses at different stages of the quarry are shown in the Plates of quarrying

plan, up to 5 years of quarrying operations.

The green belt around the quarrying area in the form of strengthening the

plantation growth shall be carried out systematically and continued. The

Building Stone nature is such that quarry bench reclamation may not be

started before exhausting the Building Stone deposit.

The total green belt area shall be divided all-round the lease boundary. The

reclamation process shall take about one year for grading, soil spreading,

stabilization and another three years for landscaping and plantation

stabilization. The area will be reclaimed in stages and be fully reclaimed

after five years of completion of quarrying excavation.

The details of the utilization proposed area for the next five years as follows:

Table 3-5 Land use details

Present Land use Propsed Area in Acres

Mine workings 0-31

Roads -

Waste dumps --

Infrastructure --

Mineral Storage --

Safety Zone 0-29

Unexplored area --

Total 1-20

3.4.2 Geomorphology and Soils

Physiographically the district can be divided into rocky upland, plateau & flat topped hills at an general elevation of about 900amsl with its major part sloping towards south and south east forming pediplains interspersed with hills all along the western part. The pediplains form the major part of the district underlain by granites and gneisses with the highest elevation of 850 to 950 m.amsl. Major part of the pediplain constitute low relief area having matured dissected rolling topography with erosional land slope covered by a layer of red loamy soil of varied thickness. Major part of the pediplains is dissected by streamlets flowing in southern direction. 3.2 Soils: The soils of the districts can be broadly grouped into red loamy soil and lateritic soil. Red loamy soils generally occur on hilly to undulating land slope on granite and gneissic terrain. It is mainly seen in the eastern and southern parts of Bangalore north and south taluks Laterite soils occur on undulating terrain forming plain to gently sloping topography of peninsular gneissic region. It is mainly covered in Anekal taluk and western parts of Bangalore North and south taluks. Hydrogeology & Water quality Ground water occurrence, movement and recharge to aquifers are controlled by degree of weathering, fracture pattern, geomorphological setup and rainfall. Granites and Gneisses of peninsular gneissic group constitute major aquifers in the urban district. Ground water occurs in phreatic conditions in the weathered zone and under semi confined to confined conditions in fractured and jointed rock formations (Fig-3). Laterites of Tertiary age occur as isolated patches capping crystalline rocks in Bangalore north taluk and ground water occur in phreatic condition. Alluvium of 20m thick, which occur along

Page 32: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 30

the river courses, though of limited thickness and aerial extent possess substantial ground water potential. Ground water quality Ground water quality for the district has been arrived at based on hydro chemical data of NHS wells and exploration bore wells. Ground water in the district shows wide variations in its chemical composition. The shallow and deep groundwater is alkaline with pH value ranging from 7.8 to 8.5. Total hardness varies from 100 to 600 ppm. Flouride content in general is less than 1 ppm. Major part of the district is having fresh water with EC ranging from 250 to 2000 micromhos/cm at 25˚ C. In Anekal taluk EC varies from 1000 to 2000 micromhos /cm at 25˚c except for small part in the centre of Anekal taluk where salinity is more with EC> 2000 micromhos /cm at 25˚ c. In Bangalore North and south taluks larger part of the taluks are having fresh ground water with EC ranging from 500 to 1000 micromhos /cm at 25˚c. Isolated patch in NE corner of Bangalore north taluk and centre of Bangalore south taluk shows EC in the range 2000 to 3000 micromhos /cm at 25˚ c. Larger part of Anekal taluk, isolated patches in the eastern part of Bangalore north, southwest and eastern part of Bangalore south taluk is having Chloride in the range of 250 to 1000 mg/l.

3.4.3 Noise and vibrations

There are some noise from neighboring quarrying activities. Steps will be taken to

minimize the noise to prevent noise pollution. Vibrations and noises are minor while

quarrying as open cast mining is carried out for the proposed project. However,

Necessary steps will be taken to minimize the vibrations and to check noise.

3.4.4 Air Quality

The air is clear and healthy as there are no industries and natural clear air is available to the quarry workers.

3.4.5 Climatic conditions

For studying the rainfall pattern 10 years actual rainfall from 1996-2005 is considered. As per the data, normal annual rainfall Bangalore urban district received is 831mm. During the year 2005, Bangalore urban district received actual rainfall of 1342.7 mm in 69 rainy days. Of the total rainfall, contribution from southwestern monsoon is 54.18% and 26.53% is from northeastern monsoon. In addition to this, Premonsoon showers contribute significant rainfall of 18.53%. A perusal of the departures of actual rainfall from respective normal reveals that the Premonsoon season rainfall is highly variable. In case of 8 monsoon season, the rainfall is either normal or above normal in most years. Post monsoon rainfall is also highly variable on annual basis. Typical monsoonal climate prevails in the district with major contribution of rainfall during southwest monsoon. In general, pre-humid to semi arid climatic conditions prevail in the district. Average temperature is 23.1˚C.

3.4.6 Socio-Economic environment

The people of this area are farmers and agricultural laborers. They are engaged in

cultivation. This quarry will provide employment to some extent to the local people,

thus improving socioeconomic conditions.

Page 33: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 31

3.5 Environmental Management Plan

3.5.1 Introduction

Mineral deposits are exploited for the sustained development of the country. But this

economic activity is likely to cause some adverse impact on the environment and

ecosystem of the area. Therefore, it is obligatory on the part of the lessee to

implement suitable control measures to mitigate the adverse impact of the various

quarrying operations. After analyzing and study of the quarry, it is found that the

quarry activity certainly will have little effects on the different environmental

parameters as is evidenced in the earlier chapter. It is possible to control the

deterioration of environment due to quarry activity by adopting and monitoring few

fixed practices as described in detail in this chapter.

3.5.2 Environmental Impact Statement & Control measures

3.5.2.1 Climate

Typical monsoonal climate prevails in the district with major contribution of rainfall

during southwest monsoon. In general, pre-humid to semi arid climatic conditions

prevail in the district. Average temperature is 23.1˚C..

3.5.2.2 Air Environment

The sources of air pollution in the region will be due to quarrying and the related

transportation activities. The meteorology of the area becomes an important

parameter in environmental issues in the mining settlements. Suitable measures to

protect the inhabitants and environment against the dust and fumes emanating from

vehicular movements are required to be taken. The dust generated is from the mine

haul roads and drilling/cutting/loading sites. It is proposed to take up mitigative

measures in the form of sprinkling water in the sensitive areas and also create green

belt along lease boundary to act as a dust barrier. The gaseous pollutants namely SO2

& NOx are below detection level. As stated earlier the gaseous pollutants in and

around the quarry are well within the permissible limits There is no likelihood of the

concentrations exceeding the standards as there is no dust emanating from the

drilling & wire saw cutting units. There is no other factory or beneficiation unit in the

lease area. However, gaseous pollutants will be monitored as per the requirement.

The future quarrying operations are not expected to raise the concentration of the

pollutants beyond prescribed limits, as the production capacity and equipment shall

remain the same as at present. However, the following measures would be adopted to

mitigate the SPM levels in ambient air.

Dust particles, which are normally generated during quarrying operations, on

becoming air borne lead to increase in SPM levels in the ambient air. Another source

of dust generation is the transport of the material by trucks. Adequate control

measures shall be taken up during quarrying operations as well as transportation.

The control measures are:

Page 34: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 32

• Dust suppression by water injection while drilling.

• Using sharp teeth for excavators would reduce dust generation.

• Dust suppression by water spraying with tankers and sprinkling system

would be adopted on roads used for transportation.

• Afforestation around the quarry to filter out the dust and preventing it

from reaching the residential areas would be undertaken.

For dust suppression on the haul roads, sprinkling system along the permanent

portions of the haul road will be adopted. In addition to the control measures adopted

during quarrying and transport operations, reclamation of dumps and quarried out

areas would be done with minimum gap between dumping/excavation and

reclamation to fix the loose material and prevent dust getting airborne.

3.5.2.2.1 Dust Control

The dust generated from loading and transport operations will be controlled by water

spraying. For these purposes water tanker fitted with sprayer will be used at haul

road, etc. Sprinkling water on the roads by tanker will be practiced. The water tankers

to be deployed for dust suppression. The water availability is adequate & the applicant

will provide structures for ground water recharging in their field to replenish the

aquifer. The number of trips of tankers supplied to the mine measures the quantity of

water supplied. The number of trips is recorded in a logbook every day, which will be

duly certified by the in-charge so as to have control on the trips of water utilization.

Further the green belt proposed all-round the Quarry lease boundary will act as a dust

filter and arrest the spread of air borne dust on to the nearby agricultural lands and

villages. The office complex is also suggested to be surrounded by green belt, to arrest

the spread of dust to the other locations.

3.5.2.3 Noise Environment

The haulage vehicles shall be maintained with proper lubrication, fitting of effective

silencers and maintenance to reduce the noise. The proposed green belt around the

lease area will help in reducing the noise level.

The deployment of the machines for excavation, transport, dumping and other

auxiliary operations has adverse impact on the noise levels within the lease area.

However, in the proposed area, the noise level will remain the same as of the pre-

quarrying stage. Additionally, due to the large distances of the quarrying area to

habitation areas, there is negligible impact of the noise levels. However, the

following measures are being taken to reduce the impact to the minimum.

Green belt around the periphery of the quarry to attenuate noise.

Tree would be planted on the side of the approach road to the quarry area.

Proper maintenance of noise generating machinery including the transport

vehicles.

Provision of silencers to reduce noise generated by machines.

Page 35: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 33

Table 3-6 Permissible Noise Exposure for different period of time

Duration per day (Hours) Sound level dBA.

16 80

8 85

4 90

2 95

1 100

1/2 105

1/4 110

1/8 115

3.5.2.4 Water Environment

It is proposed to use water for sprinkling over the roads for suppression of dust during

summer. The major source of water pollution in open cast quarrying is the surface

run-off carrying the fine silt. The problem is prevalent mostly in rainy season. For this

control measures by way of providing check-dams along the boundary of the project

site outside the lease area will be initiated and will be strengthened further and the

lessee will also take up erection of retention walls along the dump toes, slopes & take

up afforestation on the side of these retention walls to minimize the flow of silt.

Drains should be constructed to channelize the water in loose soil areas to prevent

erosion.

3.5.2.5 Storm Water Management

Check dams will be constructed to contain the surface run-off of the silt and

sediments from the lease area during heavy rainy season. Garland drain around the

quarry will be made to divert the water from working areas.

The major cause of surface water pollution during the opencast quarrying activities of

this quarry is the wash-off from the excavated areas and dumps. The program to

prevent water pollution shall focus on controlling wash-off from these areas. Control

measures have been proposed to check not only the wash off from the excavated

areas and soil erosion but also uncontrolled flow of quarry water into the natural

drainage.

These measures are briefly discussed in the following paragraphs:

A water gradient of about 1 in 21 shall be kept at every bench towards the inside of the bench to prevent formation of gully in the bench slopes and the soil being carried away by storm water.

Bunds will be erected on the outer edges of the dumps to prevent formation of erosion gullies along the dump slopes. Chutes shall be constructed by being local stone or masonry to guide the water from the dumps and prevent uncontrolled descent of water along dump slopes thus causing soil erosion.

The worked out quarry benches and dump slopes would be stabilized by planting appropriate shrub/grass species.

Loose material final slopes will be planted by making contour trenches at 2-m interval to check soil erosion due to rain.

Page 36: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 34

Garland drains will be provided around the excavations, dumps and along roads to divert storm water from broken areas into the quarry sump where the water percolates into the ground due to porosity of building stone material.

During monsoon, the probability of water flowing into the working benches increases. Garland drains will be provided around the excavations to prevent storm water from catchments area coming in contact with freshly excavated areas. Making garland drain and diverting the water into the natural drainage channels shall prevent the inflow of rainwater into quarrying benches. Water from the garland drains shall be taken to settling pits to settle suspended solids before release into surface drainage.

All water channels/drains carrying rainwater from the quarry will be provided with check dams and settling pits to arrest the suspended solids, if required. With no major water body in the vicinity and the afore proposed management measures, there will be very marginal effect due to the operation of this quarry, if any, on the surface water quality as well as quantity in the catchments.

There are no wells or springs in the quarrying area. Since there is no scope of ground water sources drying up or any chance of harmful chemicals leaching from the quarry or dump, there is no chance of pollution or depletion of ground water. Hence, no control measures are necessary. Moreover, as explained in previous chapter quarrying could lead to enhanced recharge a positive impact.

3.5.2.6 Land Restoration/Reclamation

Land restoration or reclamation of the area is very essential in any mining industry.

Proper measures adopted during restoration will control most of the adverse

environmental impacts of Quarry and also improve the aesthetic beauty of the area.

Due to the Quarry activities in this area the profile of the ground will change due to

formation of pits. At the end of the Quarry operations, the top soil/mineral rejects will

be utilized for back filling wherever suitable and rehabilitated.

3.5.2.6.1 Reclamation Schedule

Green belt formation has been started all along the boundary and roads. All these

areas that do not fall within quarrying related activity have been covered under green

belt. The green belt is strengthened every year by additional plantation in the

intermediate open patches. Starting from the northern portion, the green belt shall be

extended towards southern directions along the east and west QL boundaries. The

average width of the green belt shall be about 7.5 m in the north and about 7.5 m on

the eastern and western flanks. The well-developed belt shall add to aesthetic value.

The annual green belt coverage shall be about 0.02 acres with more emphasis on

strengthening the green belt.

The reclamation of dump shall be taken up in the future. The availability of areas for

reclamation shall increase continuously, with the advance of quarrying and part of the

quarry and dumps reaching their final positions. Any area achieving the final position

shall be immediately taken up to reclamation.

Page 37: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 35

The steps of reclamation of dump shall include:

1. The steep areas of the final dumps shall be graded. It is proposed to keep

the final slope to the natural angle of repose of the dumped material.

2. The retaining will built all along the dump toe shall be strengthened.

3. After grading of the final terraces, soil shall be spread uniformly over the

area forming a thickness of 0.25 to 0.50 m.

4. The soil while spreading, shall be mixed with fertilizer, watered and planted

with grass and shrubs for stabilization and binding the soil.

5. Along with sowing of grass for stabilization of the soil, pits shall be dug and

trees planted.

The complete procedure from preparing an area for reclamation, plantation and

stabilization is expected to take about four years. The annual reclamation shall be at

an average rate of 0.05 acre per year until ultimate pit of the quarry is achieved.

3.5.2.6.2 Back-filling/Dumping of Overburden

For reclamation of benches, the overburden/rejects from quarrying shall be backfilled

on the benches. A layer of about 0.5 m of the overburden shall be laid on each bench.

This loose material will help in easy penetration by the roots in the initial years of

plant growth.

3.5.2.6.3 Preparation of Quarry Benches for Afforestation

The quarry benches available for afforestation will be provided with a parapet (of local

stone) of about 30-cm height at the edge of each bench. A 10 cm layer of topsoil shall

be spread over the benches with a base layer of rejects thickness of about 0.2 m thick.

The areas will be roughly leveled manually and divided into plots of different sizes and

shapes depending upon the location.

3.5.2.7 Maintenance of Roads

The roads constructed during quarrying shall be kept in good condition during the

reclamation/afforestation period until the quarry is fully reclaimed and abandoned.

The material required for planting trees such as saplings, manure, water etc. can be

transported to the site by trucks/tractor-trailers/pipeline.

3.5.2.8 Topsoil Management

The top soil in the quarrying lease area will be used for afforestation. The overburden

is the mixture of stone fragments with soil. This is conductive for agriculture.

3.5.2.9 Plantation

Plantation shall be done to prevent emission of dust from the quarry area. The aim of

plantation of dumps and quarried out areas is to stabilize the land to protect it from

rain and wind erosion, as the working areas contain broken material and fine particles.

The plantation scheme shall broadly cover the following areas:

• Green belt formation around the quarry

• Plantation along roads

Page 38: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 36

• Reclamation of dumps

• Reclamation of quarried out areas

Apart from the green belt plantations for controlling fugitive emissions and noise, the

plantation shall create an aesthetically pleasing site.

3.5.2.9.1 Plantation Species

The plantation species have been considered keeping in view the following:

Adaptation to the Geo-climatic conditions of the area. A mix of round, spreading,

oblong and conical canopies, different heights ranging from 4 m to 20 m and

preferably evergreen trees is selected. The species that have history of good survival

and growth under similar site conditions shall be planted. The species proposed to be

planted are given in table.

Table 3-7 Species proposed to be planted

Sl.No. Tree Species Common Name

1 Azadirachta Indicia Neam

2 Alhizzia sp Siris

3 Dalhergia Sissoo Sisham

4 Cassia sp Amaltas

5 Pongamia pinnata Karnj

The above species have been recommended by the Central Pollution Control Board in

its guidelines for green belt formation and are adaptable to the geo-climatic

conditions of the area.

Plantation by direct seeding synchronous with the onset of rains for the green belt

shall be started. This will involve preparation of local site with regard to water

harvesting, soil and water conservation measures and weeding. It will give the initial

advantage of time, saving by eliminating nursery, sapling transport and planting. It has

the advantage of improving the form of the tree and its rooting pattern. The

plantation is generally done using saplings procured from forest department

nurseries.

3.5.2.9.2 Nursery

Success of afforestation measures at site will depend on investigation of soil selection

of suitable species and a good planting stock. For this reason, the saplings for

plantation are brought from the nearby forest nurseries. The sapling requirement is

met from the forest department. The saplings brought from the forest nurseries are

directly transported to planting sites.

Afforestation will be carried out in accordance with a timetable drawn up for sowing

and plantation depending upon the afforestation requirements and species to be

planted with regular guidance of authorities.

Page 39: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 37

3.5.2.9.3 Planting Methodology

The plantation site is prepared by digging the required number of pits. 30 cm diameter

pits are dug at 3m interval up to a depth of 50 cm wherever possible. The healthy

nursery raised saplings put in polythene containers are transported to the plantation

sites in baskets. Planting is done soon after the first monsoon showers. After planting

the saplings, the pits are refilled with soil mixed with 4 to 5 kg of FYM and 80 to

100gm of phosphate fertilizer. The soil around the plant is pressed with feet. The

level of the refilled soil is kept about 5 cm below ground for water harvesting. The

filled pit is mulched with dead leaves, vegetation or straw to minimize the evaporation

losses. Watering is continued after plantation during dry spells. Watering is done

manually. A water trolley supplies water in the plantation area.

Cleaning and weeding is done twice during first and once during the following

seasons. Planted area is inspected regularly and mortality rate assessed for each

species. Fresh saplings are planted to replace the dead and decaying plants.

The method adopted for fruit trees is same as given above. Manure, chemical

fertilizer and insecticide are used more liberally, that is twice as much as for other

trees. The frequency of weeding and cleaning is also increased to three in the first

season and two in the subsequent seasons.

Nothing is more discouraging to a tree seedling than being eaten. Thus, protection

from grazing animals is essential. For the protection of saplings in open areas, barbed

wire or fencing along with deputation of security personnel shall be made.

3.5.2.9.4 Stabilizing Planting:

Construction of check dams is necessary for preventing the downward movement of

solids, stabilization of planted vegetation and improving the water regime. The check

dams will be constructed liberally and at appropriate places. The width of check

dams will be 1.5 times more than the height and the wall of check dam. It shall be

raised from the base ground level. The upper side of the check dam shall be

vegetated by putting appropriate shrubs/plants.

3.5.2.9.5 Plantation Schedule:

Keeping the master plan at abandoning stage in mind, the stage-wise plantation shall

be done. Schedule of plantation of the total area in and around the quarry will be

planted to be carried out in the manner given in Table.

Table 3-8 Schedule of Plantation

Year No. of Plants Total Green Belt Reclamation

1 75 75

2 75 150

3 75 225

4 75 300

5 75 375

Page 40: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 38

3.5.2.9.6 Provision of Green Belt along the affected area

Development of the Greenbelt around the project site. The major pollutant is

generation of dust. This is an effective way to check pollutants and their dispersion

into surrounding areas. The degree of pollution attenuation by a green belt depends

on its height and width, foliage surface area and density. The main objective of green

belt is as follows:

1. Mitigation of impacts due to fugitive emissions caused by vehicles

2. Attenuation of noise levels

3. Ecological restoration

4. Creation of aesthetic environment

3.5.2.10 Control on Soil Erosion

The only source of soil erosion is from soil dumps. Since there is no solid

waste/overburden there will not be any effect and hence chances of soil erosion is

negligible.

3.5.2.11 Management of Socio Economic status

The mining activity will improve the economic status of the people in the region.

Continued Quarrying activities, will benefit the local people due to provision of more

infrastructural facilities provided by the mining industry, as mining industry boosts up

the local market, which will invite people from different places to install their ancillary

units. Thus the population density may have some effect over traditional life style of

the local people, and it may create scarcity of the essential commodities thus creating

rise in prices. Adequate facility for drinking water, health, education, recreation and

employment is provided to the workers and shall be continued.

3.5.2.12 Disaster Management Plan

Disaster Management Plan is envisaged with a goal to prevent hazards and accidents

at work places by careful design, operation, maintenance and inspection of the

Quarrying machineries & equipment. All the quarry activities will be in accordance

with the approved Quarrying plan and directives of Directorate General of Mines

Safety. All the eligible employees will be sent to refresher courses from time to time

on safety issues. The control measures will be adopted to take care of

hazards/disasters that may occur during quarry operation.

Safety awareness through competitions, posters & organizing safety weeks

every year

Firefighting & first aid provisions will be provided in mines office & quarry

lease area.

All safety appliances to be made available to all the staff.

Proper maintenance of haulage roads

3.5.2.13 Occupational Safety and Health:

Occupational safety and health is very closely related to productivity and good

employer-employee relationship. The main factors of occupational health in quarries

Page 41: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 39

are fugitive dust and noise. Safety of employees during blasting operation and

maintenance of quarrying equipment and handling of explosive materials will be taken

care of as per the Quarrying Act. To avoid any adverse effects on the health of the

workers due to dust, heat, noise and vibration, sufficient measures have been

provided in the quarry project. These include:

Provision of wet drilling.

Provision of rest shelters for quarry workers.

Provision of personal protection devices to the workers.

Dust suppression on haul road.

First aid facilities in the quarry area.

3.6 Environmental Monitoring

The Monitoring of pollutant in quarry will be as follows:

Air monitoring

Water quality monitoring

Noise monitoring

Soil testing.

Air-Monitoring

Work zone ambient air monitoring in quarry area is conducted once in a month from

the operations like Excavation, Loading, Transportation (Haul road), etc.

Water Monitoring

Water samples are collected once in 3 months from the nearby village bore wells and

analyzed. Additionally, water levels in these wells shall also be monitored regularly.

Noise

Noise measurement of quarry equipment is done once in six months. Noise

measurement will be taken before and after overhaul Noise levels at the lease

boundary shall be monitored quarterly.

Soil Sampling:

Soil samples will be tested before plantation, vegetation of the area. These areas shall

be monitored every six months thereafter.

3.7 Environmental Management Cell

The proponent has created a cell consisting of officers from various disciplines to co-

ordinate the activities concerned with the management and implementation of the

environmental control measures. The environmental management cell undertakes

monitoring of pollution levels by measuring ambient air quality, water quality, noise

levels etc., by appointing external agencies.

The Environmental Management Cell co-ordinates with all the related activities such

as collection of statistics for health of workers and population of the region,

Page 42: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 40

reclamation, afforestation and green belt development. The activities of

environmental management cell are co-ordinate by the management itself.

Budget for Environmental Management Plan

After an in depth study of the Environmental Management Plan, the project

proponent may make estimates of expenditure on annual basis for the

implementation of different environmental protection programme.

The details of investment for procuring the equipment for successful environmental

parameters and implementation of control measures are given approximately in

below table.

Table 3-9 Budgetary provisions for Environmental Management plan:

Sl. No.

Activity Proposed Quantity

Unit Price (in Rs.)

Capital Cost (Rs.)

Recurring Cost/Yr.(Rs)

1 Afforestation/Green belt development

75 Saplings/yr 500/sapling * - 37,500-00

2 Compound Wall 369 m * 0.2 * 1.2 = 88.56 m3

4000/m3 3,54,240-00 -

3 Drains 140 100/m 14,000-00 -

4 Dust screen 160*10 100 m3 1,60,000-00

5 Water for Drinking, Dust suppression, & Plantation

2 KLD 200/ m3 - 1,00,000-00

6 Periodic Medical Checkup & PPE supplies

Frequency : Quarterly

18,000/quarter - 72,000-00

7 Environmental Monitoring

Frequency : Quarterly

12,500/quarter**

- 50,000-00

8 Fire protection Annual 50,000/annum - 50,000-00

9 Check dams*** 2 Nos. 25,000 each 50,000-00 10,000-00

10 Miscellaneous costs Annual 50,000/annum - 50,000-00

Total 5,78,240-00 3,69,500-00

* Including transportation & plantation cost

** Including transportation charges

*** 3 at North

3.8 Conclusions

This investigation has been taken up to assess the quality and quantity of Building

Stone available in the area granted. The quarrying tests so far made reveals that the

material is good in quality and has good demand in local and foreign market. This

quarry works is far away from the neighboring villages and not have any effect on the

local environment.

Suggestions/Recommendations

Page 43: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The

Environmental Clearance Application

Building Stone Quarry in Sy No. 75, Kajjari village, Ranebennur Taluk Haveri District, Karnataka

Sri Ashok S Bankar 41

The Building Stone is very hard, compact and massive in nature. It is fine to medium

grained. The material is having good market both local, it is recommended to develop

the quarry systematically by using modern methods and machinery. Production will be

stepped up gradually. This quarry will improve the status of the local people by

providing them a better living.

Even though there is no perceptible impact from the quarry activity on the

environment of the region, it is imperative that mitigative measures have got to be

implemented on full scale for creating environmental balance and maintain the

ecology of the region. The following suggestions/recommendations are to be given

merit in this regard.

As no control over wind can be exercised, the frequency of the dust

suppression measures like constant watering of the haul roads shall be

practiced.

Afforestation as envisaged in the Quarrying plan is to be carried out so that it

not only enhances the green canopy but also stop the spread of dust particles

and air borne pollutants.

Surface water conservation measures and groundwater recharge be given high

priority.

Environmental Monitoring-Financial Implications

After an in depth study of the Environmental Management Plan, the project

proponent may make estimates of expenditure on annual basis for the

implementation of different environmental protection programme.

Page 44: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 45: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 46: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 47: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 48: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 49: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 50: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 51: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 52: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 53: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 54: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 55: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 56: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 57: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 58: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 59: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 60: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 61: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 62: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 63: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 64: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 65: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 66: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 67: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 68: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 69: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 70: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 71: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 72: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 73: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 74: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 75: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 76: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 77: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 78: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 79: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 80: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 81: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 82: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 83: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 84: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 85: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 86: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 87: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 88: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 89: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 90: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 91: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 92: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 93: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 94: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 95: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 96: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 97: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 98: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 99: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 100: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 101: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The
Page 102: “Building Stone Quarry” of Sri Ashok S Banakar · 2017. 7. 31. · ENV IRONMENTAL MANAGEMENT PLAN ... Sri Ashok S Bankar 15 2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The