Upload
buibao
View
231
Download
5
Embed Size (px)
Citation preview
OCL Bengal Cement Works(A Unit of OCL India Limited)
Dalmia Bharat Group Co.
Rich Heritage
Bengal Cement Works
The Group was established in 1939 and has a rich heritage of 75+ years of serving India
Dalmia advertisement on 15th August 1947
Re-published on 60th independence day by Times Of India
Cement
Sugar
Refractories
Power
9/2/2017 2
Bengal Cement Works
Pan India Footprint Of Dalmia CementFourth largest cement group in
India with 27 Million Tons of
installed cement capacity 186 MW
of captive power capacity
BCW1.35 MTPA
OBCW AT A GLANCE
Kapilas Cement Manufacturing Works 4
➢OCL Bengal cement Works (here-in-after referred to as OBCW), a Dalmia Bharat GroupCompany, is operating a Cement Grinding Unit having Installed capacity of 1.35 MTPA,now being upgraded to 1.75 MTPA situated at West Midnapur district in West Bengal .
➢Cement Plant commissioned on 27th March, 2014
➢A Solar PV Power Plant of 5.5 MW capacity commissioned on 30th March 2016
➢Certified for Integrated Management System of ISO 9001,14001 & 18001 ( Quality ,Environment & OHSAS ) .
➢Presently operating a FLS OK MILL (42.4) for both PSC & PPC in inter-grinding mode .
➢Predominantly manufacture PSC & PPC and catering to the entire pockets of West Begalwith 100% road despatches.
5
CERTIFICATIONS
Bengal Cement Works
5
Our Focus area IMS CERTIFIED UNIT
ISO 9001: 2008 ISO 14001: 2004 OSHAS 18001: 2007
9/2/20175
EXCELLENT ENERGY EFFICIENT UNIT AWARD IN 2016
CERTIFICATE OF MERIT FOR ENERGY EXCELLENCE FROM BEE IN 2016
CERTIFICATE OF TWO STAR RATING IN 2016
Process Flow Diagram
Bengal Cement Works
Truck Despatch
Bulker
Despatch
Wagon Tippler
Truck Tippler
Clinker Silo
Cement Silo
Raw material hopper
Stacker & reclaimer
CVRM
HAGCoal mill
Coal hopper
Bag House
Roto Packers
Clinker
Gypsum/slag
Coal Fly ash bulker
Fly ash Silo
9/2/2017 6
7Bengal Cement Works 9/2/20179
51.443.27
38.94 36
0
10
20
30
40
50
60
2014-15 2015-16 2016-17 2017-18
SPECIFIC ENERGY (KWH/T) FOR PSC
10%
17%
44.7
33.4430.01 28
0
10
20
30
40
50
2014-15 2015-16 2016-17 2017-18
SPECIFIC ENERGY (KWH/T) FOR PPC
BENCHMARK
10%
15%
Benchmark: Where We Are ..Where To Go…
BENCHMARK
27
85.581.5 78
59
20
40
60
80
2014-15 2015-16 2016-17 2017-18
Kcal/Kg for PSC
4037
28.6 26.5
0
10
20
30
40
50
2014-15 2015-16 2016-17 2017-18
KCal/Kg for PPC
28%
4%
28%
23%
Bengal Cement Works
Roadmap To Achieve Target SEC ( KWH/T)
50
.5
39
.5
36
.0
-6.9
-2.8
-0.7-0.2 -0.1 -0.3 -0.1 -1.2
-0.6 -0.8-0.3
-0.6
30
35
40
45
50
55
60
201
4-1
5
thro
ug
hp
ut
enh
ance
me
nt
by
ca
pa
city u
tilis
atio
n &
optim
izatio
n
cvrm
op
tim
iza
tion
pow
er
facto
r im
pro
ve
men
t
cvrm
ba
g h
ou
se
pu
rgin
g in
DP
mo
de
160
KW
com
pre
sso
r re
pla
ce
me
nt
by 9
0 K
w
optim
izin
g c
om
pre
sse
d a
ir u
sa
ge
equ
ipm
ent
idlin
g m
inim
ization
201
5-1
6
cvrm
op
tim
isa
tion
auxili
ary
po
wer
redu
ctio
n b
y r
aw
ma
teri
al cir
cuit o
ptim
ization
cvrm
fa
n e
ffic
ien
cy e
nh
an
ce
me
nt
&fa
lse a
ir r
ed
uctio
n
co
al m
ill T
PH
en
han
ce
men
t
packin
g p
lan
t p
ow
er
red
uction
201
6-1
7-1
8 Q
1
SEC(KWH/T)
9Bengal Cement Works
ENCON Project with
investments
9/2/2017 16
10
ENCON Actions : without investment
Bengal Cement Works
SN ENCON actions with out investment YearAnnual
Million KWHSaving
Annual INRsaving
(Million)
1 Reduction of compressed air consumption in CVRM Bag house 2014-15 0.104 0.800
2 Reduction in running hour of Slag feeding group Bag filter fans 2014-15 0.050 0.370
3 Reduction of CVRM main drive SPC through Dam ring height adjustment from 192 to 150 mm 2015-16 2.000 15.400
4 Running of CVRM Bag house in DP mode 2015-16 0.144 1.110
5 Reduction of Packing plant SPC by replacing 160 KW compressor by 90 KW 2015-16 0.100 0.780
6 Reducing idle running of Material handling circuit drives through installation of belt starvation switches 2015-16 0.003 0.020
7 Reduction of WTP Cooling Tower fan power consumption through interlock with temperature sensor 2015-16 0.028 0.210
8 Reduction of Compressor power consumption by optimizing loading/unloading set point 2015-16 0.180 1.390
9 PLC interlock modification for process optimization ( Save 15 no of trippings) 2015-16 0.013 0.100
TOTAL 2.620 20.170
9/2/20179
SN ENCON actions with investment YearAnnual
Million KWHsaving
AnnualMINRSaving
1 Gear box radial bearing maintenance & CVRM optimization to run on minimum power mode 2016-17 0.46 3.93
2 CVRM ID fan cone gap correction from 33 mm to 12 mm 2016-17 0.052 0.44
3 Felt seal installation at CVRM dynamic separator seal gap 2016-17 0.03 0.26
4Nozzle ring area increment by removal of three nozzle blocks ( from 4.87m2 to 5.4 m2 )( reduction in nozzle ring velocity from 48 m/s to 40 m/s)
2016-17 0.1 0.92
5 Dam ring reduction by 6 mm( from 122 mm to 116 mm ) 2016-17 0.03 0.32
6Reduction of false air at mill reject chute flap & belt, mill inlet ducts , mill feed chute ,Separator outlet flage & Bag house chamber doors. ( from 18.4 % to 14 %)
2016-17 0.09 0.76
7 Coal mill grinding media regradation & pattern change ( from coarse to fine) 2016-17 0.09 0.79
8 Stop Auxiliary bag filter fan through tapping in main bag filter fan in each packer 2016-17 0.06 0.52
9Packer 1 & 2 bucket elevator group starting interlock modified to avoid group idle running during shift starting
2016-17 0.003 0.026
10Packer 1 & 2 belt bucket elevator & CVRM reject elevtor motor connection change from delta to star
2016-17 0.02 0.18
TOTAL 0.94 8.15
ENCON Actions : without investment
Bengal Cement Works
12Bengal Cement Works
ENCON Project with
investments
9/2/2017 212
13
ENCON Actions: with investment
Bengal Cement Works
SN ENCON actions with investment Year
AnnualMillion KWH
saving in year of installation
AnnualMINRSaving
Investment(MINR)
Payback period
1 Power factor improvement by installing 1500KVAR HT capacitor installation 2015-16 0.500 3.860 1.250 3 M
2Reducing power consumption of HAG fuel firing blower through VFD installation
2015-16 0.030 0.230 0.040 2 M
3 Reduction of Packing plant SPC by replacing 90 KW compressor by 45 KW 2016-17 0.195 1.500 0.900 6 M
4Reducing power consumption of packing plant bag filter Fan by VFD installation
2015-16 0.130 1.000 1.680 1.25 Y
5 Reducing power consumption of CVRM bag filter Fan by VFD installation 2016-17 0.026 0.200 0.050 3 M
6 Solar power generation unit 5.5 MW 2016-17 6.000 46.200 277.200 6 Y
7Installation of plant logistic automation system to improve operational efficiency of packing plant.
2015-16 0.200 1.550 2.500 1.6 Y
8Installation of VFD in 641 FN1 & 642FN1 ( 75*2 kw) Silo bin aeration blower 611BL2 ,packing plant compressor & 611FN1 Silo 1 bag filter fan.
2016-17 0.12 0.99 1.35 1.4 Y
9Installation of VVFD in reject bucket elevator bag filter fan , reject circuit bag filter fan & raw material feeding belts bag filter fan
2016-17 0.092 0.790.8
1 Y
TOTAL 7.3 56.32 285.77 1.25 Y
9/2/2017 10
SN ENCON actions with investment
Annual thermal saving (
MKCal/year)
AnnualMillion KWH
saving Status/Remarks
1Partial blocking of left most duct of CVRM hot air inlet
4052 -By uniform temp distribution heat saving is around 3KCal/Kg
2 Trimming of CVRM ID fan impeller - 0.58 Approx 80KW/Hr saving is estimated
3 CVRM ID Fan inlet duct area enlargement - 0.4 Approx 55 KW/Hr is estimated
4Reduction of system pressure of CVRM circuit by 25 mmwc through several maitenance activity
- 0.14 Around 25 KW/Hr is achieved
5 False air reduction from 14% to 10% - 0.20Reduction from 14% to 11.6% is achieved. By reducing upto 10% 15kw/hr saving is estimated
6Reduction of plant lighting power consumption by replacing HPSV light with LED base light - 0.13 In progress
7 9 no of VFD installation at various section - 0.12 In progress
TOTAL 4052 1.57
Bengal Cement Works
ENCON Actions: For 2017-18
15
ENCON Methodology: ENCON Approach
Bengal Cement Works
MANAGE MEASURE PROTECT
Unit Head
Energy cell
Energy cell head with cross functional team
Daily energy monitoring at
PD
Weekly energy monitoring by
energy cell
Monthly energy meeting
Scope identification
Action plan generation&
execution
Quantification , analysis &
record
9/2/201711
16
ENCON Methodology: Energy Levers
Bengal Cement Works
VRM POWER OPTIMIZATION
1. Dam ring
2. False air
3. Feed size control
4. Separator efficiency Power factor
& efficient silo management to avoid peak hour
usage
Fans & blowers efficient running
Compressor power minimization
Equipment idle run minimization
1. Stop interlocks
2. starvation stop
3. Shop stoppage power
Solar power
31%
5%
12%31%
11%10%
Effective use of Energy Levers in 2016-17
VRM optimization
Equipment idle running
Compressor powerminimizationFan & blower efficientrunningThermal energy saving
others
9/2/2017 12
17
ENCON Methodology: Power reports
Bengal Cement Works
Daily Energy report with real time data captureCCR operation screen with Total KWH & KWH/T display for main drives.
Column12500 kvA
Trafo for
Wagon Tippler
540kW Cement
Mill Separator
Fan for 561MD2
2500 kVA
Trafo Feeder
-1 for CCR
4150 kW
BagHouse Fan
561FN1
CCR Main
Incomer
2500 kVA
Tafo Feeder-
2 for CCR
6500kW Cement
Mill Main Drive
for 561MD1
Solar
Power
Feeder
400kW Coal
Mill Main Drive
for L41MD1
2500kVA Trafo
Feeder for
Packing Plant
Spare
Trafo
Feeder-1
Spare
Trafo
Feeder-2
400kW Belt
Conveyor Feeder
for 491BC3
MRSS
Outgoing
Feeder-1
MRSS
Outgoing
Feeder-2
18-08-2016 00:02 3139752 918607 8161475 25502312 98944160 5979773 56517248 2E+06 1552036 7368597 22 10 174219 99351864 0
18-08-2016 01:02 3139876 918637 8161882 25503988 98950672 5980121 56520604 2E+06 1552268 7368969 22 10 174219 99358432 0
18-08-2016 02:02 3140001 918670 8162287 25505650 98957104 5980504 56523928 2E+06 1552422 7369341 22 10 174219 99364912 0
18-08-2016 03:02 3140126 918703 8162695 25507300 98963344 5980817 56527292 2E+06 1552422 7369711 22 10 174219 99371208 0
18-08-2016 04:02 3140253 918736 8163105 25508956 98969656 5981199 56530656 2E+06 1552422 7370084 22 10 174219 99377576 0
18-08-2016 05:02 3140378 918769 8163514 25510632 98975904 5981554 56533972 2E+06 1552422 7370441 22 10 174219 99383864 0
18-08-2016 06:02 3140472 918802 8163903 25512324 98982016 5981820 56537324 2E+06 1552422 7370780 22 10 174219 99390024 0
18-08-2016 07:02 3140560 918835 8164277 25514018 98987872 5982181 56540648 2E+06 1552422 7371014 22 10 174219 99395928 0
18-08-2016 08:02 3140652 918867 8164649 25515704 98993328 5982517 56543872 2E+06 1552422 7371288 22 10 174219 99401424 0
18-08-2016 09:02 3140816 918899 8165090 25517392 98998520 5982794 56547104 2E+06 1552462 7371545 22 10 174219 99406664 0
18-08-2016 10:02 3140934 918930 8165547 25519004 99002424 5983055 56549888 2E+06 1552693 7371823 22 10 174219 99410592 0
18-08-2016 11:02 3141020 918961 8166006 25520676 99006216 5983394 56553036 2E+06 1552926 7372062 22 10 174219 99414416 0
18-08-2016 12:02 3141158 918992 8166460 25522364 99009136 5983739 56556208 2E+06 1553156 7372329 22 10 174219 99417360 0
18-08-2016 13:02 3141297 919023 8166825 25524048 99012592 5984151 56559360 2E+06 1553384 7372614 22 10 174219 99420848 0
18-08-2016 14:02 3141380 919053 8167190 25525728 99017112 5984543 56562532 2E+06 1553608 7372890 22 10 174219 99425400 0
18-08-2016 15:02 3141464 919084 8167555 25527404 99021352 5984936 56565752 2E+06 1553608 7373204 22 10 174219 99429672 0
18-08-2016 16:02 3141574 919115 8167920 25529074 99025680 5985349 56568952 2E+06 1553608 7373560 22 10 174219 99434032 0
18-08-2016 17:02 3141734 919146 8168284 25530684 99030672 5985712 56572040 2E+06 1553608 7373898 22 10 174219 99439064 0
18-08-2016 18:02 3141840 919149 8168360 25530032 99031208 5985971 56572040 2E+06 1553608 7374225 22 10 174219 99439608 0
18-08-2016 19:02 3141903 919149 8168433 25530032 99031800 5986170 56572040 2E+06 1553608 7374473 22 10 174219 99440200 0
18-08-2016 20:02 3142046 919149 8168513 25530032 99032496 5986281 56572040 2E+06 1553608 7374836 22 10 174219 99440912 0
18-08-2016 21:02 3142186 919149 8168601 25530032 99033232 5986389 56572040 2E+06 1553608 7375220 22 10 174219 99441640 0
18-08-2016 22:02 3142505 919149 8168682 25530032 99034240 5986549 56572040 2E+06 1553608 7375594 22 10 174295 99442664 0
18-08-2016 23:02 3142571 919149 8168761 25530032 99034904 5986698 56572040 2E+06 1553608 7375954 22 10 174295 99443328 0
19-08-2016 00:01 3142676 919149 8168903 25530032 99035616 5986794 56572040 2E+06 1553608 7376318 22 10 174295 99444048 0
Total Consumption 2924 542 7428 27720 91456 7021 54792 18624 1572 7721 0 0 76 92184 0
Dalmia Cements - Active Energy Report
9/2/201713
18
ENCON Methodology: Power reports
Bengal Cement Works
Date 06-08-2016
FTD MTD
TOTAL UNIT AVAILED AT OBCW FROM WBSEDCL kWh 169806.2 559274.3
SOLAR POWER CONSUMPTION kWh 14300.0 68379.0
TOTAL POWER CONSUMPTION AT BCW kWh 184106.2 627653.3
Distribution Loss % 0.8% 0.95%
Raw material handling with stacker(MCC 3)kWh 1982.0 12412.0
CLINKER SILO FEEDING(491BC3) kWh 2573.0 9312.0
Total Reclaimer and hopper feeding circuit(MCC 4)kWh 2137.0 7130.0
CVRM-IV
CVRM MAIN DRIVE kWh 107864.0 333048.0
BAG FILTER FAN kWh 40594.0 133354.0
CVRM CLASSIFIER kWh 1251.0 3430.0
CVRM Aux. as per FLS(MCC 5 INCLUDES HYDRAULIC,HAG)kWh 6172.0 22797.0
CVRM AUX(CEMENT TRANSPORT+CEMENT SILO BUCKET ELEVATOR)kWh 2376.0 11795.0
CVRM COMPRESSOR(70% TOTAL UNIT OF COMPRESSOR)kWh 2511.0 15100.0
LIGHTING kWh 3479.0 22113.0
MILL WATER SUPPLY MCC2 KWh 1424.0 6322.0
Total Power consumed for CVRM kWh 160768.0 519524.0
CVRM UNITS 167460.0 548378.0
Power consumed for PSC KWh 167460.0 503493.0
Power consumed for PPC KWh 0.0 44885.0
COAL MILL
COAL MILL MAINDRIVE kWh 3085.0 9298.0
PSC COAL GRINDING kWh 3085.0 9298.0
PPC COAL GRINDING kWh 0.0 0.0
COAL MILL AUX Incl FAN(MCC 6) kWh 1245.0 4388.0
PSC COAL MILL AUXILLARY kWh 1245.0 4388.0
PPC COAL MILL AUXILLARY kWh 0.0 0.0
Total Power consumed for COAL MILL 4330.0 13686.0
Packing plant
Packing Plant kWh 2660.0 14022.0
Packing Compressor kWh 2001.0 10014.0
Lighting kWh
Total Power consumed for PACKING HOUSE kWh 4661.0 24036.0
SERVICES
PROJECT WORK kWh 0.0 0.0
Lighting kWh 1199.0 7139.0
LIGHTING AND AUXILLARY UNITS and water supplykWh 1199.0 7139.0
Total Power consumption for SERVICES kWh 1199.0 7139.0
182553.0 621674.0
Specific Power Date 06-08-2016
FTD MTD
TOTAL POWER CONSUMED IN OBCW 182553.0 621674.0
CVRM RUN HRS - PSC hrs 22.5 64.5
CVRM RUN HRS - PPC hrs 0.0 5.8
CVRM - RUN Total hrs 22.5 70.3
PSC PRODN ton 4947.4 12926.6
PPC PRODN ton 0.0 1184.8
PRODN - TOTAL ton 4947.4 14111.4
COAL MILL RUN HRS PSC hrs 12.2 36.9
COAL MILL RUN HRS PPC hrs 0.0 0.0
COAL PRODN ton 47.9 157.4
Cement Despatch ton 2384.5 15621.4
Total Reclaimer and hopper feeding circuit(MCC 4)kwh/t 0.4 0.5
Material handling with stacker kwh/t 0.4 0.9
Clinker feeding kwh/t 0.5 0.7
CVRM MAIN DRIVE kwh/t 21.8 23.6
BAG FILTER FAN kwh/t 8.2 9.5
CVRM CLASSIFIER kwh/t 0.3 0.2
CVRM Aux. as per FLS kwh/t 1.2 1.6
CVRM AUX kwh/t 0.5 0.8
CVRM COMPRESSOR kwh/t 0.5 1.1
WATER SUPPLY and lighting kwh/t 0.2 0.5
Total Power consumed for CVRM (Grinding Power)kwh/t 32.5 36.8
Total Power consumed for PSC grinding of CVRM kwh/t 33.8
Total Power consumed for PPC grinding of CVRM kwh/t 0.0
Total Power consumed up to Grinding stagekwh/t 33.8 38.9
COAL MILL MAINDRIVE kwh/t 64.4 59.1
COAL MILL AUX Incl FAN kwh/t 26.0 27.9
Total Power consumed for COAL MILL kwh/t 90.4 87.0
Packing Plant kwh/t 1.1 0.9
Packing Compressor kwh/t 0.8 0.6
Total Power consumed for PACKING HOUSE kwh/t 2.0 1.5
SERVICES Lighting kwh/t 0.2 0.5
WORK SHOP kwh/t 2.0 1.5
Total Power consumption for SERVICES kwh/t 0.2 0.5
Power for cement grinding kwh/t 35.0 40.2
Packing power kwh/t 2.0 1.6
Plant lighting and auxillaries WITH WATER SUPPLYkwh/t 1.0 2.0
power on cement kwh/t 37.99 43.8
Specific Power
Daily powerreport format
9/2/201714
❖ Innovative Project (without investment):
1. CVRM dam ring height & internal air circulation optimization
2. Minimization of compressor power consumption
3. Power saving by minimization of idle running
❖ Innovative Project (with investment)
1. RFID system installation to increase packing plant through put
2. Power factor improvement by installing 1500KVAR HT capacitor
3. VFD installation at packing plant bag filter fans & HAG fuel firing blower0.9500.9600.9700.9800.9901.0001.010
Power Factor
Innovative Project executed & presented last year
Bengal Cement Works
Innovative Project (without investment): 1
Bengal Cement Works
✓ Scope: Due to in apropriate mixing length after HAG outlet duct & recirculation air duct joint, the inlet air through three ducts were having nonuniform heat distribution . The left most duct was carrying most of the heat content. This uniformity was leading non uniforming drying of material & higher specific heat requirement.
❖ Project : Baffle plate installation at Mill inlet duct to distribute uniform heat content to mill through all ducts
❖ Objective: To save thermal energy consumption by effective utilization of supplied heat inside mill
9/2/2017 20
✓Action taken :To resolve the non-uniform temperature distributionat CVRM inlet duct ,a modification with baffles platefixing ( 300 mm width) before the left most duct &between the left & middle duct is done on month ofNovember & it was further remodified to optimize inMar’17.
320 Deg C
133 Deg C
126 Deg C
Innovative Project (without investment): 1
Bengal Cement Works
❖ Projec: Baffle plate installation at Mill inlet duct to distribute uniform heat content to mill through all ducts
❖ Objective: To save thermal energy consumption by effective utilization of supplied heat inside mill
9/2/201721
Heat contribution by VRM inlet ducts ( Kcal)
Before modification After modification
10.09.2016 10.11.2016 04.04.2017 25.05.2017
Temp (
Deg C)
% of
total
heat
content
to mill
Temp
( Deg
C)
% of
total
heat
content
to mill
Temp (
Deg C)
% of
total
heat
content
to mill
Temp
( Deg
C)
% of total
heat
content to
mill
315 49.60% 258 43.80% 280.6 34.30% 287 33.90%
133 26.80% 138 31.50% 190.1 35.80% 190 40.10%
126 23.60% 118 24.70% 135.6 29.90% 140 25.90%
79.566.8
59.349
10.94 10.6111.6
9.1
0
2
4
6
8
10
12
14
0
20
40
60
80
100
FY'17 MARCH APRIL MAY
PSC heat cons(Kcal/Kg) vs Slag moisture%
Heat slag moisture %
Benefits :▪ Energy saved : 1100 T coal
▪ Energy saved : 7 Kcal/Kg cement
▪ Money saved: 5 Million INR
22
Innovative Project : 2
Bengal Cement Works
✓ scope :
▪ coal mill ( equipped with 1st generation staticseperator) was initially designed for :
Feed size of 80% retention at 8mm & ground
product of 15 % retention at 90 Micron sieve.
▪ Operational scenario was
Feed size of 40 % retention at 8 mm & ground
product required of 5% retention at 90 Micron
sieve.
▪ The supplier recommended media pattern wasnot efficient as it was too coarse for the feed &obtained TPH of coal mill was only 3.8 -4 TPHleading to SEC of around 0.7 KWH/T of cement.
❖ Project : coal mill productivity enhancement through grinding media optimization
❖ Objective : To save power consumption by coal mill runhour reduction
9/2/201721
✓ Action taken :
▪ Media pattern optimized to fine pattern
▪ 70 mm media was removed , 60 mm media
proportion reduced & 20 mm media is included.
0.0%
6.4%
12.2%12.7%
22.3%26.4%
20.0%
7.1%
14.2%15.0% 20.8% 20.8% 22%
0.0%
5.0%
10.0%
15.0%
20.0%
25.0%
30.0%
70 60 50 40 30 25 20
MEDIA PATTERN
Ball size ( mm)
9/2/2017 23Bengal Cement Works
0.60.5
0.50.6
0.70.8
0.70.65
0.4
0.0
0.2
0.4
0.6
0.8
1.0
Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16
Coal mill main drive KWH/T Cement
3.8 4.4 4.4
4.1 4.0 4.0 3.9 4.0
5.5
- .0
1.0
2.0
3.0
4.0
5.0
6.0
April'16 May'16 JUNE'16 JULY'16 AUG'16 SEP'16 OCT'16 Nov'16 Dec'16
Coal mill TPH
Benefits :▪ Energy saved : 92000 KWH in 2016-17
▪ Energy saved : 0.3 KWH/T
▪ Money saved: 0.79 Million INR
Innovative Project : 2
Innovative Project ( without investment ): 3
Bengal Cement Works
✓ Scope: Each packer is facilitated with two bag filters of 46000m3/hr & 23000 m3/hr. wheteher as per flow
measurement it was analysed that @ 17 m/s velocity , the circuit dedustiong volume requiremet is only 32000 m3/hr, canbe managed by running a single fan of 75 KW.
✓Action taken :
▪ An inhouse modified tapping is provided from the small bagfilter to larger one . the dedusting duct at designatedsources kept unaltered.
▪ The dedusting fan ( 37 KW, 23000M3/HR) is stopped. & through the suction of the remaining bigger fan ( 75 KW, 46000M3/HR) the whole dedusting purposed is successfully resolved.
▪ saving of around 15 Kw/Hr for two packer each i.e 30 KWH .
❖ Project : Elimination of Auxiliary bag filter fan through tapping in main bag filter fan in each packer
❖ Objective : To save the power consumption for two dedusting fan with successfull dedusting of the circuit
Benefits :▪ Energy saved : 60000 KWH in 2016-17
▪ Energy saved : 0.2 KWH/T
▪ Money saved: 0.52 Million INR
9/2/201724
Innovative Project (without investment): 3
Bengal Cement Works
❖ Project : Elimination of Auxiliary bag filter fan through tapping in main bag filter fan in each packer
❖ Objective : To save the power consumption for two dedusting fan with successfull dedusting of the circuit
9/2/2017 25
26Bengal Cement Works
Renewable
energy
9/2/2017 267
Own
consumption
Solar Module, Poly Crystalline Rating: 310 WattNos of module: 17760Total Output: 5.5 MWp
Inverter
Photovoltaic Inverter Rating: 648 KW/ 406 Volts
TransformerRating: 2500 MVA Volts: 11KV / 415 VoltsNos of Tx.: 2
HT BreakerRating: 800 AmpVolts: 12KVNos of Breaker: 2
Solar Panel
System Monitoring
Renewable Energy Usage :
Bengal Cement Works 27
5.5 MWp solar power plant is commissioned on April’16 to utilize non conventional renewable energy & reduction ofcarbon di oxide emission.
9/2/2017
1910991
11256009
0
2000000
4000000
6000000
8000000
10000000
12000000
14000000
KW
H
Solar Grid
15%
85%
11%
15%
0%
5%
10%
15%
20%
FY17 FY18
SOLAR POWER UTILISATION
28Bengal Cement Works
Water
consumption
reduction
9/2/201733
29
Reduction in process Water consumption :
Bengal Cement Works
0.17
0.08
0.07
0.00
0.02
0.04
0.06
0.08
0.10
0.12
0.14
0.16
0.18
2014-15 2015-16 2016-17
Water consumption KL/T
9/2/201734
Zero water spray for PSC
water spray for PPC is only 2 % of total feed.
30
Carbon
foot print
Bengal Cement Works 9/2/2017 30
31
Carbon Footprint Reduction
Bengal Cement Works
❖ Initiatives to reduce carbon footprint :
▪ Installation of 5.5 MWp solar power plant to utilize renewable energy
▪ Reduction of total KWH consumption through various initiatives.
▪ Reduction of thermal energy (Kcal/Kg) by process optimization
▪ Improving clinker factor by higher addition of slag/fly ash to cement.
▪ Reduction of internal vehicle fuel consumption by commissioningwagon tippler & use of battery driven vehicles.
▪ Reduction of Fuel oil consumption by improving reliability
0.40.29
0.25 0.220
0.00.10.20.30.4
CO2 emission (T/T of Cement)
0.2620.221
0.180 0.169
2014-15 2015-16 2016-17 2017-18
Scope 3: Indirect emissions from recieved clinker
0.067
0.0470.041 0.038
2014-15 2015-16 2016-17 2017-18
Scope 2: Indirect CO2 emission from purchased electricity
0.047
0.026 0.0250.020
2014-15 2015-16 2016-17 2017-18
Scope 1 : Direct CO2 emissions
9/2/201731
TARGET
50.14
63.15 63.16 64.06
0
20
40
60
80
2014-15 2015-16 2016-17 2017-18
Slag % in PSC
33.21
34.89 34.83 34.86
3232.5
3333.5
3434.5
3535.5
2014-15 2015-16 2016-17 2017-18
Fly ash % in PPC
32Bengal Cement Works
Going
green
9/2/201735
38%
15%7%
6%
31%
3% valuable trees withbig trunk
flower
fruits
medicinal
ornamental
PLANNED DEVELOPEMENT OF GREEN BELT
8701
11423
14378
3031
0
2000
4000
6000
8000
10000
12000
14000
16000
2014-15 2015-16 2016-17 2017-18(4M)
PLANTED SAPLINGS ( SURVIVED)
❖ Systematic green belt development initiative :▪ Total 37500 nos of survived saplings till FY 2017-18 . Survival
rate is around 85%.▪ 25% of total acquired area is developed as a green belt▪ 126 types of different species is planted through out the plant
area.▪ Quick growing forest tree plantation initiative along boundary
line having wood value & dust prevention potential.▪ Landscaping garden development at around 3 acre area for
beautification
Greenbelt Development Initiative
Green house for seedling development
❖ Systematic green belt development initiative :
▪ Organic farming vegetable cultivation through out 4500 Sq Ft area.▪ Canteen waste ,other agriculture & garden waste are used to prepare
vermin compost along with cow dung- received from distributed cows tonear by villagers. This eliminates the hazard of chemical fertiliser usage.Also ground water contamination is prevented.
▪ Development of green house round 300 Sq Mt for seedling development▪ Plantation of saplings around 2000 nos with medicine value
Greenbelt Development Initiative
35Bengal Cement Works 9/2/201738