Upload
lytuyen
View
242
Download
3
Embed Size (px)
Citation preview
Kapilas Cement Manufacturing Works
(A Unit of OCL India Limited)
Dalmia Bharat Group Co.
KCW1.70 MTPA
Fourth largest cement group in India
with 27 Million Tons of installed
cement capacity 186 MW of captive
power capacity
3 plants in 2 states serving 4 states
27 MnT
14 plants in 9 states serving 21 states
Pan India Footprint Of Dalmia Cement
Kapilas Cement Manufacturing Works 2
KCMW AT A GLANCE
Kapilas Cement Manufacturing Works 3
➢ Kapilas Cement Manufacturing Works (here-in-after referred to as KCMW), a Dalmia Bharat GroupCompany, is operating a Cement Grinding Unit having installed capacity of 1.35 MTPA, later up-gradedto 1.7 MTPA, situated at the border of Cuttack and Jajpur Districts in Odisha.
➢ Cement Plant commissioned on 28th March, 2008.
➢ A Solar PV Power Plant of 2.5 MW capacity commissioned on 28th March, 2014.
➢ Certified for Integrated Management System of ISO 9001,14001 & 18001 ( Quality , Environment & OHSAS ) and Energy Management System ISO 50001 by TUV .
➢ Presently operating a LOESCHE VRM (LM 56.3+3 CS) with 1.70 MTPA capacity for Clinker and Slaggrinding separately.
➢ Predominantly manufacture Portland Slag Cement (PSC) and catering to the coastal belt as well assouthern, northern & central part of Odisha with 100% road dispatches.
Process Flow Diagram
Kapilas Cement Manufacturing Works 4
Cement Silos
2 x 7,500 t
Roto Packers2 X 180 tph
8 Nos, 90 tph Truck loaders
Dispatch to Customers
Gypsum Stockpile 2 x 2,500
t
C VRM
4 Compartmen
t Silo
Slag Stock Pile 2
x 12,500 t
Coal Stockpile
1 x 4,000 t
Clinker Silo 25,000 t
Clinker from
Wagon Tippler
Coal crushe
r
To HAG & Coal Mill
Paddle Mixer
Bag House
MAJOR PLANT & MACHINERY
Kapilas Cement Manufacturing Works 5
CVRM
LM 56. 3+3 C/S
COAL MILL
Alstom BRM 85 (10)
WAGON TIPPLER
LARSEN & TOUBRO LIMITED
HAG
Singhania- 2 x
15 M Kcal/Hr
RECLAIMER
Side Scraper Reclaimer
ROTO PACKER
16 SRPE Enexco Technologies India Ltd
TRUCK LOADER
ENTL 2000-T (12 M)
TRUCK TIPPLER60 Tons Hydraulic Truck Unloader
6
CERTIFICATIONS
Kapilas Cement Manufacturing Works
6ISO 9001: 2008 ISO 14001: 2004 EN ISO 50001: 2011
6
OSHAS 18001: 2007ISO 9001: 2008 ISO 14001: 2004 EN ISO 50001: 2011ISO 9001: 2008 ISO 14001: 2004 EN ISO 50001: 2011
Certification for IMS (QMS, EMS & OHSAS) and Energy Mgt System ISO 50001 from TUV NORD
EnMs & IMS POLICY
Kapilas Cement Manufacturing Works 7
EnMs Policy IMS Policy
8
Awards & Accolades
Kapilas Cement Manufacturing Works
8
8
State Safety Award in the year 2009 & 2012 and International safety AwardNational Energy
Conservation Award
9
Awards & Accolades
Kapilas Cement Manufacturing Works
9
09
Pollution Control Appreciation Award 2016 by OSPCB
Living Legend Award 2016
Green Homes Platinum Award from IGBC
10Kapilas Cement Manufacturing Works 10
SPECIFIC ENERGY CONSUMPTION
105.81 101.42
77.6971.02 65.96
0
20
40
60
80
100
120
14-15 15-16 16-17 17-18 Benchmark
SPECIFIC THERMAL ENERGY CONSUMPTION Kcal/Kg OF CEMENT
32.88%
44.45 42.88 39.935.6 33.0
0
10
20
30
40
50
2014-15 2015-16 2016-17 2017-18 Benchmark
SPECIFIC POWER CONSUMPTION (KWH/TON) ON CEMENT
19.91%
Goal 33 SPC
Goal 65.9 SHC
11Kapilas Cement Manufacturing Works 11
Roadmap To Achieve Target SEC ( KWH/T)
ENERGY CONSERVATION PROJECT IMPLIMENTED
Kapilas Cement Manufacturing Works 12
No of Project Completed
Cost Saving Achieved
Electrical Energy Saved
Thermal Energy Saved
Project With Nil Investment
Investment Made61.77
Million
41 Nos
60.59 Million
9.80 MkWh
44947 MKcal
23 Nos
13
ENCON Actions : Without Investment
Kapilas Cement Manufacturing Works 13
No Title of Project Year
Annual
Electrical
Saving
(Million kWh)
Annual
Electrical
Cost Saving
(Rs million)
Annual Thermal SavingTotal Annual
Savings (Rs
million)Quantity
Unit of
Measuremen
t
1 Stopping of Auxiliary bag filter fan of feeding section during slag transport 2014-2015 0.176 1.056 0 1.056
2 HAG is to be stopped during CCR grinding 2014-2015 0 0 2250000 kilocalorie 1.6698
3 After rain water harvesting, stop all pump for pumping water from ground
for about 10 months.
2014-2015 0.1 0.6 0 0.6
4 Stopping P&V , panel fans while plant stoppage 2014-2015 0.0168 0.1008 0 0.1008
5 Aux bag filter purging off delay time increases from 15 sec. to 30 sec. 2014-2015 0.0384 0.23 0 0.23
6 CVRM main drive motor starting delay time reduced from 15 min to 7 min. 2014-2015 0.27 1.62 0 1.62
7 Ventury removal from Coal Mill ID Fan 2016-2017 0.0405 0.243 0 0.243
8 Reduced power consumption during CVRM mill heat-up & cooling time 2016-2017 0.0054 0.0324 0 0.0324
14
ENCON Actions : Without Investment
Kapilas Cement Manufacturing Works 14
No Title of Project Year
Annual Electrical
Saving (Million kWh)
Annual
Electrical
Cost Saving
(Rs million)
Annual Thermal SavingTotal Annual
Savings (Rs
million)Quantity
Unit of
Measuremen
t
9 Both Packer bag cleaning blower stop when respective radial/tangential
belt not running
2015-2016 0.198 1.188 0 1.188
10 Switching of 2 nos of transformer of solar power plant during night hrs 2016-2017 0.0292 0.18 0 0.18
11 Replacement of 531BC3 and 531BC4 motor from 45 KW to 37 Kw 2016-2017 0.034363 0.206 0 0.206
12 Replacement of 491BC3 motor from 45 KW to 37 KW 2016-2017 0.011781 0.07 0 0.07
13 To stop the Compressor of Packing plant and utilize compressor of CVRM 2016-2017 0.27 0.243 0 0.243
14 Cooling tower fan to be stopped and Temperature sensor installed to
reduce running hour of fan.
2016-2017 0.021 0.126 0 0.126
15 Packer Interlock logic modified for reduction of idle running 2016-2017 0.216 1.296 0 1.296
16 Installation of belt starvation switch and development of logic to minimize
idle run of belt conveyor
2016-2017 0.027 0.162 0 0.162
15
ENCON Actions : Without Investment
Kapilas Cement Manufacturing Works 15
No Title of Project Year
Annual Electrical
Saving (Million kWh)
Annual
Electrical
Cost Saving
(Rs million)
Annual Thermal SavingTotal Annual
Savings (Rs
million)Quantity
Unit of
Measuremen
t
17 Packing House Compressor & MC Silo compressor to be connected with
Bag House compressor
2016-2017 0.11 0.66 0 0.66
18 Reduction of False air Across the system limited to 12% On going process
0 0 44947 MKcal 36.97
19 Master roller sealing arrangement for restriction of false air 2016-2017 0 0
20 Reduction on coal mill residue on 90 Micron 2016-2017 0 0
21 Reduction in mill inside water spray 2016-2017 0 0
22 Slag to be stored in shed in rainy season & to be stored in outside shed in summer season for reduction in heat consumption
On going process
0 0
23 Removal of damper of ID fan motor 2017-2018 0.405 UnderObservation
Under
Observation
ENCON Actions : With Investment
Kapilas Cement Manufacturing Works
No Title of Project Year
Annual Electrical
Saving (Million
kWh)
Annual
Electrical
Cost
Saving (Rs
million)
Annual Thermal
Saving
Annual
Thermal
Cost
Saving (Rs
million)
Total
Annual
Savings
(Rs
million)
Investmen
t Made
(Rs
million)
Payback
(Yrs)Quantity
Unit of
Measure
ment
1 To reduce the minimum coal firing to below 1.5 tph 2014-2015 0 0 240 ton 0 0.67 0.8 1.19
2 By installing VFD for stacker belt conveyor 2014-2015 0.06 0.36 0 0 0.36 0.45 1.25
3 To Stop 591FNB air slid fan by modifying bag filter discharge
chute
2015-2016 0.033 0.198 0 0 0.198 0.025 0.126
4 Classifier bottom bearing cooling arrangement modification 2015-2016 2.599 15.59 0 0 15.59 0.15 0.01
5 Cooling tower one no of pump stop by modify CVRM
motor O/L water direct discharge to Tower
2015-2016 0.222 1.332 0 0 1.332 0.075 0.56
6 Three nos of 50KVA lighting energy saving device installation 2015-2016 0.41975 2.518 0 0 2.518 0.45 0.18
7 Installation of VFD for L21BC1 2015-2016 0.0352 0.212 0 0 0.212 0.35 1.65
8 Installation of new GRR under buy back scheme with better
speed regulation
2015-2016 0.675 4.05 0 0 4.05 0.8 0.2
9 Installation of VFD for coal conveying blower 1 2016-2017 0.0288 0.175 0 0 0.175 0.2 1.14
10 Installation of VFD for coal conveying blower 2 2016-2017 0.0288 0.175 0 0 0.175 0.2 1.14
16
17
ENCON Actions : With Investment
Kapilas Cement Manufacturing Works 17
No Title of Project Year
Annual
Electrical
Saving
(Million
kWh)
Annual
Electrical
Cost
Saving (Rs
million)
Annual Thermal
Saving
Annual
Thermal
Cost
Saving (Rs
million)
Total
Annual
Savings
(Rs
million)
Investmen
t Made (Rs
million)
Payback
(yrs)Quantity
Unit of
Measure
ment
11 Replacement of 300 nos of 70watt HPSV lamp with 32watt LED
lamp
2016-2017 0.04161 0.25 0 0 0.25 0.393 1.57
12 Up-gradation of mill classifier and replacement of new design tire and liner along with Optimisation of Mill
2016-2017 2.7 16.2 0 0 16.2 46 2.84
13 Installation of VFD for Packing plant bag filter fan 1 and 2 2016-2017 0.432 2.6 0 0 2.6 0.9 0.4
14 Installation of SPRS FOR 2500KW ID fan motor 2016-2017 2.025 12.15 0 0 12.15 8.6 0.7
15 Star feeder up-gradation 2017-2018 0.405 2.43 0 0 2.43 1.0 0.41
15 Replacement of existing pump by Grundfos Energy efficient
pump as per pump energy audit
2016-2017 0.088 0.528 0 0 1.6 1.036 0.65
16 Multi-compartment slag bin extraction air slide sized changed
from 300 mm to 400 mm (To increase the TPH & power
reduction).
2016-2017 0.014 0.084 0 0 0.084 0.35 4.1
17 Packer Bin to packer hopper- Single discharge to be modified
to double discharge
2016-2017 0 0
18 Blower Installation at Packing Plant for body cleaning purpose
& reduction in compress air consumption
2016-2017 0 0
Kapilas Cement Manufacturing Works
ENERGY CONSERVATION INITIATIVES
No Title of Project YearAnnual Electrical Saving
(kWh)Annual Thermal Saving
(Ton/year)
1 Switching of Colony transformer and providing separate supply 2017-2018 43800 0
2 Replacement of 400 nos of 70watt HPSV lamp with 32 watt LED lamp 2017-2018 55480 0
3 Installation of VFD for 531FN1 and 531FN2 2017-2018 54000 0
4 Replacement of L21BC4 motor from 200KW to 160KW 2017-2018 23563 0
5 Replacement of scrapper motor from 75KW to 55KW 2017-2018 26509 0
6 replacement of 511BC2 from 110KW to 90KW 2017-2018 17673 0
7 Replacement of L21BC2 from 55KW to 37KW 2017-2018 43200 0
9 Installation of VFD for mill feed circuit bag filter fans 2017-2018 67500 0
10 Uniform distribution of temperature at mill inlet by providing baffle plate 2017-2018 0 0
11 Replacement of existing RAL by 400x400mm against 300X300mm. 2017-2018 32400 0
12 Drag link feeder to be replaced by 25 TPH Weigh Feeder 2017-2018 28350 0
13 FRB Blade installation in cooling tower fan 2017-2018 8910 0
14 Coal mill BH compress air line to be automated by providing solenoid valve 2017-2018 27000 0
TOTAL 428385
18
19Kapilas Cement Manufacturing Works 19
Approach For Energy Conservation Initiatives towardsExcellence
Core Committee Team
Daily Monitoring
Energy Conservation Monthly Review Meeting
Analyzing & Brain Storming to evolve Energyimprovement projects
Action Plan & Implementation
Achieving Goals
Rewards
20Kapilas Cement Manufacturing Works 20
Core Committee Team-Energy Cell
Unit Head
Tech Head
Raw Material Handling
CVRM, Coal Mill, HAG
Packing Plant
Utility & Compressors
Solar Plant
Total Nos of Project Proposed :- 63Total Nos of Project Accepted :- 55Nos of Project Executed :- 41Nos of Project WIP :- 14
21Kapilas Cement Manufacturing Works 21
Daily EnCon, Production, EHS Discuission meeting
22
ENCON Methodology: Energy Levers
Kapilas Cement Manufacturing Works
VRM POWER OPTIMIZATION
1. Dam ring
2. False air
3. Feed size control
4. Separator efficiency Power factor
& efficient silo management to avoid peak hour
usage
Fans & blowers efficient running
1. As required convert delta to
star connection of motor
Compressor power minimization
1. Stopping auxillary
compressor
Equipment idle run minimization
1. Stop interlocks
2. starvation stop
3. Shop stoppage power
Solar power
22
69.56, 69%
14.01, 14%
10.14, 10%
4.63, 5%
1.66, 2%
Effective use of Energy Levers in 2017-18
VRM & Process Optimization
VFD Installation & poweroptimization
Motor load study & optimaztion
Compressor power minimazation
Equipment Idle running
23
ENCON Methodology: Power reports
Kapilas Cement Manufacturing Works 23
DAILY PERFORMANCE REPORT OF 2.5 MW PV SOLAR POWER PLANT
DATE: 3-Apr-17 MONTH: April
SL NO PARTICULARS UNIT TODAY MTD YTD
A COMMITTED:
1 SOLAR IRRADIATION kwh/m2/d 6.17 6.17 6.17
2 NET GENERATION KWH 11387 34161 34161
3 PLANT LOAD FACTOR % 19.0% 19.0% 19.0%
4 PERFORMANCE RATIO % 69.1% 69.1% 69.12%
B ACHIEVED:
1 GENERATION DETAILS
1.1 AT INVERTER OUTPUT- 1A KWH 3241 8889 8889
1.2 AT INVERTER OUTPUT- 1B KWH 3291 9142 9142
1.3 AT INVERTER OUTPUT- 2A KWH 3228 8864 8864
1.4 AT INVERTER OUTPUT- 2B KWH 3266 8953 8953
1.5 TOTAL- INVERTER GENERATION KWH 13026 35848 35848
2 GROSS GENERATION KWH 12883 35456 35456
3 AUXILLIARY CONS. (Net of Import) KWH 72 210 210
4 IMPORT FROM GRID (FOR AUX. CONS.) KWH 10 90 90
5 ACTUAL GENERATION/ INJECTION TO GRID (ELIGIBLE FOR REC) KWH 12740 35050 35050
6 CAPTIVE CONSUMPTION KWH 12740 35050 35050
7 PASSED ON TO GRID KWH 0 0 0
8 REC APPROVED BY NLDC NOS 0
9 DIFFERENCE- COMMITTED VS ACTUAL KWH 1353 889 889
10 PERFORMANCE RATIO % 81.3% 78.4% 78.5%
C OPERATING PARAMETERS:
1 SOLAR IRRADIATION kwh/m2/d 5.87 5.58 5.58
2 PLANT LOAD FACTOR % 21.2% 19.5% 19.5%
3 AMBIENT TEMP- MAXM 0C 36.75 36.75 36.75
4 AMBIENT TEMP- MIN 0C 23.28 23.28 23.28
5 MODULE TEMPERATURE 0C 44.26 47.70 47.70
6 OPERATING TIME HRS 11.30 34.60 34.60
7 DOWNTIME:
7.1 GRID FAILURE HRS 0 0 0.00
7.2 INVERTER MALFUNCTIONING HRS 0.00
7.3 OTHER REASONS HRS 0.00
7.4 TOTAL DOWNTIME HRS 0 0 0.00
28-Jun-16 Jun-16
CESU POWER CONSUMPTION kWh -4237 -193201
OPEN ACCESS POWER AVAILED kWh 181237 4637161
SOLAR POWER CONSUMPTION kWh 10600 276750
TOTAL UNIT AVAILED AT KCMW FROM CESU (OA+GRID) kWh 177000 4443960
DG POWER CONSUMPTION kWh 0
TOTAL POWER CONSUMPTION AT KCMW(OA+SOLAR+GRID) kWh 187600 4720710
Power Cons.in KCW (Without Distribution Loss) kWh 190379 4749145
MAXIMUM DEMAND (MD) MD 9360 9792
Distribution Loss kWh -2779 -28435
Distribution Loss % -1.5 -0.6
Total Power drawn kWh 187600 4720707
Power Consumed With Distribution Loss
STACKER RECLAIMER
STACKER & RECLAIMER kWh
WAGON TIPPLER kWh 542 14212
TRUCK TIPPLER kWh 0
CLINKER SILO FEEDING kWh 638 5440
CVRM-IV
CVRM MAIN DRIVE kWh 103467 2649520
BAG FILTER FAN kWh 38440 956044
CVRM CLASSIFIER kWh 5075 116734
CVRM Aux. as per Loesche kWh 2090 51326
CVRM AUX-1 kWh 2123 50229
CVRM AUX-2 kWh 1675 43636
CVRM COMPRESSOR -1 kWh 2454 65233
CVRM COMPRESSOR -2 kWh 2779 67238
HOPPER FEEDING BELTS kWh 6079 148119
WATER SUPPLY kWh 1569 38533
SILO FEEDING kWh 3356 37252
LIGHTING kWh 0 0
HAG kWh 2838 76493
Total Power consumed for CVRM kWh 173124 4320010
COAL MILL
COAL MILL MAINDRIVE kWh 808 19806
COAL MILL FAN kWh 325 12406
COAL MILL AUX. kWh 91 1994
RAW COAL HOPPER FILLING kWh 0 0
Total Power consumed for COAL MILL 1224 34207
INTERMIXING (MULTICOMPARTMENT)
SILO FEEDING & INTERMIXING kWh 0 50490
PACKING HOUSE
ROTOPACKER -1 kWh 4117 83940
ROTOPACKER -2 kWh 3242 74406
LIGHTING kWh 0 9023
COMPRESSORS & BAGFILTERS ETC. kWh 0
Total Power consumed for PACKING HOUSE kWh 7359 167369
SERVICESkWh 0
GARAGE , STREET LIGHT,STORE AND CANTEEN kWh 515 14469COLONY LIGHTING kWh 1375 37326
FACTORY LIGHTING (DG) kWh 0PLANT OUTSIDE kWh 281 10761
WATER SUPPLY AND PLANT LIGHTING kWh 3723 86076Total Power consumption for SERVICES kWh 5893 148631
TOTAL POWER CONSUMED IN KCW 187600 4720707TOTAL PSC PRODUCTION t 3944.90 103802.60
CEMENT VRM PRODN (PSC) t 1737 45886CEMENT VRM PRODN (CCR) t 0 17994
CEMENT VRM PRODN (SLAG) t 0 27026CEMENT VRM PRODN (DSP) t 2208 16296
TOTAL MATERIAL GROUND (CVRM) t 3945 107202COAL MILL PRODUCTION t 58 1812
PSC PRODUCTION (INTERMIXING) t 0 41621PSC PACKING (DESPATCH) t 4478 102091
CEMENT VRM (PSC) hrs 8.68 227.23CEMENT VRM (CCR) hrs 0.00 83.06
CEMENT VRM (SLAG) hrs 0.00 140.77CEMENT VRM (DSP) hrs 13.67 93.89
TOTAL RUNNING HRS.OF CVRM hrs 22.35 544.95COAL MILL hrs 5.98 130.44
INTERMIXING hrs 0.00 197.91PSC PACKING (DESPATCH) hrs 0.00 0.00
CVRM-IVCVRM MAIN DRIVE kWh/ton 26.23 24.72
BAG FILTER FAN kWh/ton 9.74 8.92CVRM CLASSIFIER kWh/ton 1.29 1.09
CVRM Aux. as per Loesche kWh/ton 0.53 0.48CVRM AUX-1 kWh/ton 0.54 0.47CVRM AUX-2 kWh/ton 0.42 0.41
CVRM COMPRESSOR -1 kWh/ton 0.62 0.61CVRM COMPRESSOR -2 kWh/ton 0.70 0.63HOPPER FEEDING BELTS kWh/ton 1.54 1.38
WATER SUPPLY kWh/ton 0.40 0.36SILO FEEDING INTG kWh/ton 0.85 0.35
LIGHTING kWh/ton 0.00 0.00WAGON TIPPLER kWh/ton 0.14 0.13
HAG kWh/ton 0.72 0.71CLINKER SILO FEEDING kWh/ton 0.16 0.05
Total Power consumed for CVRM kWh/ton 43.89 40.30
COAL MILLCOAL MILL MAINDRIVE kWh/ton 13.93 10.93
COAL MILL FAN kWh/ton 5.61 6.84COAL MILL AUX. kWh/ton 1.6 1.10
RAW COAL HOPPER FILLING kWh/ton 0.0 0.00Total Power consumed for COAL MILL kWh/ton 21.10 18.87
INTERMIXING (MULTICOMPARTMENT)(A) SILO FEEDING & INTERMIXING kWh/ton 0.00 1.21
PACKING HOUSETotal Power consumed for PACKING HOUSE kWh/ton 1.64 1.64
CEMENT VRM PRODN (PSC) kWh/ton 39.0 39.57CEMENT VRM PRODN (CCR) kWh/ton 0.0 36.9
CEMENT VRM PRODN (SLAG) kWh/ton 0.0 41.6CEMENT VRM PRODN (DSP) kWh/ton 48.29 46.04
( B )POWER FOR PRODUCTION. kWh/ton 44.20 40.62( C )POWER FOR PACKING kWh/ton 1.64 1.64
POWER CONSUMED ON CEMENT (A+B+C) kWh/ton 45.84 43.47
24
ENCON Methodology: Idle Running Hr Monitoring
Kapilas Cement Manufacturing Works 24
Idle Hour Counter On main PLC screen
25
ENCON Methodology: Digitization in Monitoring
Kapilas Cement Manufacturing Works 25
Ewatch system access from Computer
Ewatch system access from Mobile
Innovative Project: 1
Kapilas Cement Manufacturing Works
❖ Project: Mill up gradation by replacing the original Classifier of LSKS 92 CS model with latest Vortex based LSVS 97 CS Classifier with modified bigger dia tires & flat liners of Sinter cast and subsequent Mill optimization measures.
❖ Objective: Reduction of Specific Power Consumption & increase in Mill Output.
26
✓ Scope: KCMW was equiped with Loesche Mill LM 56. 3+3 C/s Millwith LSKS 92 CS model classifier
✓ Action taken :
1. Replaced the old design classifier with latest vortex classifier LSVS97 CS alongwith bigger diameter tire & flast table liner.
2. Replaced old GRR with new one along with SPRS installation
3. Damring & louvrering optimization.
4. Reduction of False air across the mill.
5. Water spray nozzle angle change.
Benefits :▪ Sp power on cement reduced by 2.5 kWh /Ton
▪ Annual Electrical Cost Saving Rs. 18.85 Million
▪ Mill output increased from 210 TPH to 252 TPH
Innovative Project: 2
Kapilas Cement Manufacturing Works
❖ Project: CVRM main bag filter capacity 750000 m3/hr inlet Damper removal.
❖ Objective: Power saving
27
✓ Scope: CVRM main bag filter fan is operated with inletmotorized damper, the pressure drop across the damper is45 MMWC.
✓Action taken :
▪ Removed damper & provided transition piece forelimination of any pressure drop.
Benefits :▪ Saved 105 KW by removal of damper.
▪ Sp power on cement reduced by 0.3 kWh/Ton
▪ Annual Electrical Cost Saving Rs. 2.26 million
Innovative Project: 3
Kapilas Cement Manufacturing Works
❖ Project: Increase in KW & RPM of Mill Feed star feeder
❖ Objective: Reduction of idle running & Power saving due to star feeder tripping.
28
✓ Scope: CVRM is equipped with two star feeders for mill feed.Star feeder tripping was on an average 48 times/Month with anaverage stoppage of 9.43 hrs/ month
✓Action taken :
▪ Replaced old starfeeder geared motor of 7.5 KW & 8 RPMwith higher capacity geared motor of 11KW & 12 RPM
Benefits :▪ Sp power on cement reduced by 0.325 kWh/Ton
▪ Annual Electrical Cost Saving Rs. 2.45 million
▪ Stoppage frequency reduced to 8times/Month, i.e. 2 hrs/Month
Innovative Project: 4
Kapilas Cement Manufacturing Works
❖ Project: Providing compress air line to various location for stopping auxiliary compressor & running the
whole plant with one main BH compressor.
❖ Objective: Reduction of specific power consumption.
29
✓ Scope: For plant operation we were running one Main BHcompressor with 3 nos of auxillary compressor
✓Action taken :
▪ Provided compress air line to different locationsin CoalMill & Packing House and stopped all auxillarycompressors
Benefits :▪ Sp power on cement reduced by 0.32kwh/Ton
▪ Annual Electrical Cost Saving Rs. 2.41 million
Month CVRM Prod(Mt)
Power Consumed By
B/H Compressor
(KWH)
Sp.Power CVRM
Prod. (KWH/T)Dispatch (Mt)
Power Consumed
By P/H Compressor
(KWH)
Sp.Power for
Packing (KWH/T)
Nov'16 80610.4 68879 0.85 85803 22979 0.27
Dec'16 110530.8 91083 0.82 109034 19440 0.18
Total 191141.2 159962 0.84 194837 42419 0.22
1.05 KWH/T
Month CVRM Prod(Mt)
Power Consumed By
B/H Compressor
(KWH)
Sp.Power CVRM
Prod. (KWH/T)Dispatch (Mt)
Power Consumed
By P/H Compressor
(KWH)
Sp.Power for
Packing (KWH/T)
Jan'17 (Ti l l 27th) 111547.6 99290 0.89 112200 13193 0.12
1.01 KWH/T
KWH/T 0.05
Rs/KWH 6.00
Rs/T 0.28
Rs/Yr 365789
Power Cost
Cost Saved/T of Cement Production & Dispatch
Cost Saved for 13 LMt Production & Dispatch
Before Modification
After Modification
For 1 Mt of Production & Dispatch, Sp. Power required
For 1 Mt of Production & Dispatch, Sp. Power required
Power Saved/T of Cement Production & Dispatch
Innovative Project: 5
Kapilas Cement Manufacturing Works
❖ Project: Conducted Motor load study and undertook replacement of under loaded motors across the plant.
❖ Objective: Reduction of specific power consumption.
30
✓ Scope: During project time belt conveyor was
designed for higher capacity with higher KWMotor.
✓Action taken :
▪ Studied the motor running load & replaced withsuitable lower KW motor as available in plant
Benefits :▪ Sp power on cement reduced by 0.7kWh/Ton
▪ Annual Electrical Cost Saving Rs. 5.28 million
511 BC-1 Current Reading with 110 KW motor
SL No Date Current KW=Current*415*0.8/1000, PF=0.8
1 11.04.2017 115 66.127762 11.04.2017 117 67.277808
3 12.04.2017 118 67.813656
4 12.05.2017 116 66.702784
5 13.05.2017 110 63.252646 13.05.2017 118 67.852832
7 15.05.2017 112 64.365504
8 15.05.2017 118 67.813656
9 24.05.2017 114 65.51488810 25.05.2017 110 63.25264
11 26.05.2017 115 66.12776
Total 726.101Avg 66.009
511 BC-1 Current Reading With 90 KW Motor1 29.05.2017 98 56.352352
2 30.05.2017 96 55.202304
3 31.05.2017 99 56.927376
4 01.06.2017 97 55.7773285 01.06.2017 96 55.202304
6 02.06.2017 100 57.5024
7 02.06.2017 96 55.202304
8 03.06.2017 97 55.777328
9 05.06.2017 99 56.927376
Total 336.389Avg 56.065
Average KW saving in 511 BC1= 66 KW - 56 KW=10 KWKWH Saving/hr= 10 KWHAverage running Hour /day= 8 hrsTotal running hour in a year considering 320 days=8X320= 2560 HrsTotal Energy saving will be= 2560*11=25600 unitsCost saving in terms of energy @ Rs6/- per unit=25600*6= Rs 153600/-
Renewable Energy Usage From 2.5MW Solar PV Power Plant
Kapilas Cement Manufacturing Works 31
Initiatives taken to optimize Generation despite degradation of Modules as committed by OEM:
✓ Tilting solar module two times in a year with trials at different angle on every season.
✓ Cleaning entire solar modules in 4 cycles in a months for summer and winter season instead of 2 Cycles suggested by OEM.
✓ Regularly checking VOC of solar modules on every month and replacing faulty modules.
✓ Condition monitoring of transformer, HT and LT switch gear and all the repairs or rectification done in the evening hrs with out effecting plant performance . Thus 100% up-keep achived in last year.
✓ Cleaning and replacing air filters of Inverter as regular interval and also arrangement done for better cooling . Thus increased efficiency of inverters.
✓ Planting tress like water melon, pineapple, aloe-verra for cooling of solar modules during summer season.
✓ Water spraying system arrangement done for one inverter on top of the module for cooling purpose.
✓ Switching of power transformer of solar power plant from 06.00PM to 06.00AM . Thus saving 80Kwh everyday.
3330 3302 3278
1123
3250
3765 3823 3866
1285
0
500
1000
1500
2000
2500
3000
3500
4000
4500
2014-15 2015-16 2016-17 2017-18 Benchmark
Solar Power Utilization
Committed Generation in MWH Actual Generation in MWH
9/2/2017 32Kapilas Cement Manufacturing Works
Clean Energy Solutions (Solar study lamps) & Clean cooking Households (Fuel efficient stove) distributed to nearby village
to promote use of renewable Energy
Renewable Energy Usage Continues…..
32
33
Carbon Foot Print Reduction
Kapilas Cement Manufacturing Works
❖ Initiatives to reduce carbon emission :
1. Reduction of thermal energy (Kcal/Kg) by process optimization
2. Installation of 2.5 MW solar PV power plant to utilize renewableenergy and Reduction of total KWH consumption through variousinitiatives.
3. Improving clinker factor by higher addition of slag for cementupto70% & Reduction of Fuel oil consumption by improvingreliability
33
28393.3
43553.9 41748.2
26166.2
0
10000
20000
30000
40000
50000
2013-14 2014-15 2015-16 2016-17
Scope 1. Direct Co2 Emission in Ton
48232
52079
45837
420004300044000450004600047000480004900050000510005200053000
2014-15 2015-16 2016-17
Scope 2. Indirect Co2 Emission in Ton by purchase of electricity
524594488774
446412404901
0
100000
200000
300000
400000
500000
600000
2013-14 2014-15 2015-16 2016-17
Co2 Emission in Ton
34
Carbon Foot Print Reduction
Kapilas Cement Manufacturing Works
❖ Initiatives to reduce carbon emission :
▪ Increase in use of B F Slag %
▪ Journey started with 43.5% in year 2013 to 70% in Year 2017
34
43.5
54.9
64.566.1 69.1
0
10
20
30
40
50
60
70
80
2013-14 2014-15 2015-16 2016-17 2017-18 (4M)
% Usage of Slag
450895396988
352584 332898
0
100000
200000
300000
400000
500000
2013-14 2014-15 2015-16 2016-17
Scope 3. Indirect Co2 Emission in Ton by Cement Grinding
612
579
395
322
Net CO2 Emission in Kg/T of Cement (2016-17 estimated)
Global Average
Indian Average
Dalmia Bharat Group Average
KCMWAverage
Carbon Footprint Scenario in cement sector
Green Supply Chain
Kapilas Cement Manufacturing Works
Best Practices1. Office order issued for procurement of material considering Energy
Efficiency2. Procurement of Energy efficient motor Only, calculating the landed
cost considering the energy efficiency.3. Requesting Quotation/ Offers from various suppliers, energy
efficiency criteria must be mentioned on the quotation request from.4. Idle Running of Equipment, wastage of water, air, fuel etc will impact
performance rating of contractor & the unit will impose penalty on observing such incidence.
35
36
Water Positive Plant
Kapilas Cement Manufacturing Works 36
0.0330.029
0.0250.027
0.0220.02
0
0.005
0.01
0.015
0.02
0.025
0.03
0.035
2012-13 2013-14 2014-15 2015-16 2016-17 2017-18
Specific water consumption KL/Ton
Particulars Earlier Present Annual
Rain water harvesting capacity (KL) 85,467 1,03,767 1,03,767
Direct use of Rain water (KL) Thru WTP-For 3 months- estimated
23,600
STP Treated Water Consumption Pattern (KL/Day) – Used for Horticulture & Dust Suppression
70 100 1200
Rain water harvesting Structures developed - outside Plant
14,607 30,107 30,107
Total-1,58,674Fresh Water Consumption Pattern (KL/DAY)
Actual Target Annual Target
1 Process Water Consumption 71 90 26,250
2Sanitation-Plant, Colony & Truck Parking
261 200 73,000
3 Horticulture 0 0 0
4 Dust Suppression 1 0 0
5 Solar PV Cleaning 1 5 1700
6 Drinking- RO & Truck Parking 12 10 3650
Total Fresh Water Cons (KL/DAY) 346 305 1,04,600
100% treated STP water being used for Dust suppression & Horticulture. Targeted to achieve 150% Water positive status by this year, i.e. Dec-17
❖ Systematic green belt development initiative :▪ Total 105435 nos of survived saplings till Date out of 126865 saplings
planted inside plant premises. Survival rate is around 83%.▪ 33% of total acquired area is developed as a green belt▪ 150 types of different species is planted through out the plant area.▪ Quick growing forest tree plantation initiative along boundary line
having wood value & dust prevention potential.▪ Landscaping garden development at around 16 acre area for
beautification.
22,696 22,226
20,003
14,424
18,838 18,448
16,602
11,972
-
5,000
10,000
15,000
20,000
25,000
2014-15 1015-16 2016-17 2017-18 (4M)
PLANTED SAPLINGS PLANTED SAPLINGS (SURVIVED)
24,378 28,476
36,892
15,591
-
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
2014-15 1015-16 2016-17 2017-18 (4M)
PLANTED SAPLINGS (Out side Plant Premises)
Valuables Trees with Big Trunks,
71.80%
Flowers, 10%
Fruits, 1.20%
Meditional, 2%
Ornamental, 15%
DEVELOPMENT OF GREEN BELT
Greenbelt Development Initiative
Kapilas Cement Manufacturing Works 37
❖ Systematic green belt development initiative :
▪ Organic farming vegetable cultivation through out 43560 Sq Ft area.▪ Canteen waste ,other agriculture & garden waste are used to prepare vermin compost
along with cow dung- received from distributed cows to near by villagers. This eliminatesthe hazard of chemical fertiliser usage. Also ground water contamination is prevented.
▪ Development of green house & Poly house around 360 Sq Mtr for seedling development▪ 10000 nos of pineapple planted below solar panel for solar panel effective cooling.
Greenbelt Development Initiative
Kapilas Cement Manufacturing Works 38
Plant LandscapeTotal Plant Area:- 347 Acre
Plantation Area:- 114 Acre (33%)
Greenbelt Development InitiativeRaw material Storage yardCCR Side Area
Colony area Arial View of the plantNear Packing House area
Greenbelt Development InitiativePlant Canteen Front AreaCCR Front Area
Colony Gate AreaColony Area
42Kapilas Cement Manufacturing Works 42