22
Infrastructure Projects 1 Crossrail Programme James Greatbanks – Designated Project Engineer NR Crossrail Traction Power Supply Upgrade [email protected] Modelling & Electrification

7_James Greatbanks Presentation [Compatibility Mode]

  • Upload
    buique

  • View
    221

  • Download
    2

Embed Size (px)

Citation preview

Page 1: 7_James Greatbanks Presentation [Compatibility Mode]

Infrastructure Projects

1

Crossrail Programme

James Greatbanks – Designated Project EngineerNR Crossrail Traction Power Supply Upgrade

[email protected]

Modelling &

Electrification

Page 2: 7_James Greatbanks Presentation [Compatibility Mode]

2

Crossrail

• Network Rail delivering £2.3bn enhancements:

– 28 station upgrades

– Electrification and power supply upgrade

– Signalling and telecom renewals

– Grade separation and junction improvements

• New journey opportunities and 10% increase in rail capacity

• Up to 24 tph, each train 200m carrying up to 1500 passengers

• £14.9bn contributing £42bn in benefits

Page 3: 7_James Greatbanks Presentation [Compatibility Mode]

3

Electrification and PSU

• 85 stkm Series 1 OLE

• 2 x 400kV supply points

• Autotransformer feeding: Stratford to Shenfield (30km) & Paddington to Maidenhead (40km)

• £200m KENSAL GREEN400kV Supply Point

PUDDING MILL LANE400kV Supply Point

Maidenhead MPATS

Slough ATSHayes SATS

West EalingATS

WestbourneParkATS

StepneyGreenSATS Plumstead ATS

Ilford SATS

Gidea Park SATS

Shenfield MPATS

Page 4: 7_James Greatbanks Presentation [Compatibility Mode]

4

Electrification Modelling• Supply point loads

• Equipment loading

• Voltage profile

• Rail voltage

• Induced voltage

• Stray current

• Conducted interference

• Radiated emissions

• Train performance

• Earth potential rise

• Earth leakage

• Electrolytic corrosion

• Thermal loads

• Resonance

• Screening

• Staging / phasing

• Import and export

• Failure modes

Page 5: 7_James Greatbanks Presentation [Compatibility Mode]

5

Project Lifecycle

GRIP – Governance for Railway Investment Projects

Staging Commissioning

Hazard Management

RatingsTimetable / Outputs

System Design

Page 6: 7_James Greatbanks Presentation [Compatibility Mode]

6

System Design

TimetableRoute

Standards + Policy400kV Grid

System Design

Options:- E&B Design

- HV Equipment-OLE Sectioning

-Telecoms-Signalling

Outline DesignAIP

Detailed Design

System DesignRolling Stock

Page 7: 7_James Greatbanks Presentation [Compatibility Mode]

7

System Design - Timetable

Page 8: 7_James Greatbanks Presentation [Compatibility Mode]

8

System Design - Demand

Kensal Green Supply Point

0.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

90.0

100.0

00:0

0:00

01:0

0:00

02:0

0:00

03:0

0:00

04:0

0:00

05:0

0:00

06:0

0:00

07:0

0:00

08:0

0:00

09:0

0:00

10:0

0:00

11:0

0:00

12:0

0:00

13:0

0:00

14:0

0:00

15:0

0:00

16:0

0:00

17:0

0:00

18:0

0:00

19:0

0:00

20:0

0:00

21:0

0:00

22:0

0:00

23:0

0:00

Time of Day

Half H

our A

vera

ge Loa

d (M

VA)

30 MVA

67MVA65MVA

Page 9: 7_James Greatbanks Presentation [Compatibility Mode]

9

System Design – Train Voltage

Page 10: 7_James Greatbanks Presentation [Compatibility Mode]

10

System Design – Short Circuit

Kensal Green ATFS

Page 11: 7_James Greatbanks Presentation [Compatibility Mode]

11

System Design – Rail Voltage

Page 12: 7_James Greatbanks Presentation [Compatibility Mode]

12

System Design – Rail Voltage

Page 13: 7_James Greatbanks Presentation [Compatibility Mode]

13

System Design – S&T Circuits

Page 14: 7_James Greatbanks Presentation [Compatibility Mode]

14

AC/DC: South East Section

2km

Parallel AC and DC lines

New station

Engineering Connection

• Stray 50Hz

• Induced 50Hz

• Bridge bonding

• Stray DC / corrosion

Page 15: 7_James Greatbanks Presentation [Compatibility Mode]

15

AC/DC: Conclusions

• Corrosion Rates [ATS earth mat, OLE foundations, bridge foundations]: 3000 – 10000 years

• Negligible 50Hz

• No requirement for screening conductor on NKL

• No requirement for VLDs

• No insulation in OLE masts

• Isolation transformer at Abbey Wood station

• One new rectifier

• Measurments

Page 16: 7_James Greatbanks Presentation [Compatibility Mode]

16

Hazard Specific Modelling

• Inductive and conductive coupling to third parties

–London Underground

–DLR

–Heathrow baggage and air side services tunnels

• ATF cables

• Mark 3B OLE

• Reed track circuits

• Depot bonding

• Harmonic Resonance

Page 17: 7_James Greatbanks Presentation [Compatibility Mode]

17

Third Parties

•Joint Crossrail Ltd / Network Rail study•Multi-frequency coupling•Tailored to ‘victim’ equipment

Page 18: 7_James Greatbanks Presentation [Compatibility Mode]

18

Third Parties

Page 19: 7_James Greatbanks Presentation [Compatibility Mode]

19

Third Parties

Page 20: 7_James Greatbanks Presentation [Compatibility Mode]

20

ATF Cable

• Crossrail ATF is 12% cable

• Δ system design / outline design

• Earthing ATF cable at both ends

• ATF cable and S&T separation

0

1

2

3

4

5

6

0 5 10 15 20 25 30 35 40

Distance from Paddington (km)

ATF

/ S&

T Se

para

tion

(m)

Page 21: 7_James Greatbanks Presentation [Compatibility Mode]

21

ATF Cable

Page 22: 7_James Greatbanks Presentation [Compatibility Mode]

22

Summary

• System Design as early as possible

• Change is inevitable, so build in allowances

• Change to scheme outputs = big impact

• Modelling required throughout the project lifecycle

• Engage sensitive third parties

• Use system boundaries rather than contract boundaries

• Limited number of suppliers

• Shortage of resource

• Modelling £ < Testing £££