Page 1 CHAPTER NO. 8 STONE MASONRY DESCRIPTION OF ITEM NO 1: Random, rubble masonry (uncoursed), foundation and plinth. a) Dry Masonry Detail Unit Rate (British System) per Qty Rate Per Unit (Rs) Material Quarried Stone 100 Cft 300.00 Per % Cft Headers or through stones Note: Special size of stone for headers average size = 20x1.5'x8"x10" (457x200x250mm) 20 Nos. 20 Nos 15.00 Each Total Contractor's Profit & Overh ### Percent Total Labour Mason 2.00 Nos 300.00 Per Day Unskilled Coolies 3.00 Nos 140.00 Per Day Total Sundries ### Percent Total Contractor's Profit & Overh ### Percent Total Labour Rate for 100 Cft Rs. ### Say Labour Rate P/ Cum Rs. 475.55 Say Composite Rate for 100 Cft Rs. ### Say Composite Rate P/ Cum Rs. 729.85 Say

33788151 Rate Analsis Chapter No 8 Stone Masonary

Embed Size (px)

Citation preview

Page 1: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 1

CHAPTER NO. 8

STONE MASONRYDESCRIPTION OF ITEM NO 1: Random, rubble masonry (uncoursed), in

foundation and plinth.a) Dry Masonry

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Headers or through stonesNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00

Total 600.00 Contractor's Profit & Overhead 20.00 Percent 120.00 Total 720.00

Labour

Mason 2.00 Nos 300.00 Per Day 600.00 Unskilled Coolies 3.00 Nos 140.00 Per Day 420.00

Total 1,020.00 Sundries 10.00 Percent 102.00 Total 1,122.00

Contractor's Profit & Overhead 20.00 Percent 224.40 Total 1,346.40

Labour Rate for 100 Cft Rs. 1,346.40 Say 1,346.40 Labour Rate P/ Cum Rs. 475.55 Say 475.55

Composite Rate for 100 Cft Rs. 2,066.40 Say 2,066.40 Composite Rate P/ Cum Rs. 729.85 Say 729.85

Page 2: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 2

Item No. 1 b) In Mud Mortar

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Headers or through stonesNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Good earth 45 Cft 150.00 %Cft 67.50

Total 667.50 Contractor's Profit & Overhead 20.00 Percent 133.50 Total 801.00

Labour

Mason 2.50 Nos 300.00 Per Day 750.00 Unskilled Coolies 3.50 Nos 140.00 Per Day 490.00 Bahishti 0.25 No 160.00 Per Day 40.00

Total 1,280.00 Sundries 10.00 Percent 128.00 Total 1,408.00

Contractor's Profit & Overhead 20.00 Percent 281.60 Total 1,689.60

Labour Rate for 100 Cft Rs. 1,689.60 Say 1,689.60 Labour Rate P/ Cum Rs. 596.77 Say 596.75

Composite Rate for 100 Cft Rs. 2,490.60 Say 2,490.60 Composite Rate P/ Cum Rs. 879.68 Say 879.70

Page 3: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 3

Item No. 1 c) In Lime Mortar, Ratio (1 Lime 2 Sand).

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headersNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Lime Slaked (Ground) 224 Kg 2.00 Per Kg. 448.00 Sand 30 Cft 350.00 Per %Cft 105.00

Total 1,153.00 Contractor's Profit & Overhead 20.00 Percent 230.60 Total 1,383.60

Labour

Mason 4.00 Nos 300.00 Per Day 1,200.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.50 No 160.00 Per Day 80.00

Total 1,980.00 Sundries 10.00 Percent 198.00 Total 2,178.00

Contractor's Profit & Overhead 20.00 Percent 435.60 Total 2,613.60

Labour Rate for 100 Cft Rs. 2,613.60 Say 2,613.60 Labour Rate P/ Cum Rs. 923.12 Say 923.10

Composite Rate for 100 Cft Rs. 3,997.20 Say 3,997.20 Composite Rate P/ Cum Rs. 1,411.81 Say 1,411.80

Page 4: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 4

Item No. 1 d) In Cement Sand Mortari) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headersNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Cement 9 Bag 230.00 P. Bag 2,070.00 Sand 33.75 Cft 350.00 Per %Cft 118.13

Total 2,788.13 Contractor's Profit & Overhead 20.00 Percent 557.63 Total 3,345.75

Labour

Mason 4.00 Nos 300.00 Per Day 1,200.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.50 No 160.00 Per Day 80.00

Total 1,980.00 Sundries 10.00 Percent 198.00 Total 2,178.00

Contractor's Profit & Overhead 20.00 Percent 435.60 Total 2,613.60

Labour Rate for 100 Cft Rs. 2,613.60 Say 2,613.60 Labour Rate P/ Cum Rs. 923.12 Say 923.10

Composite Rate for 100 Cft Rs. 5,959.35 Say 5,959.35 Composite Rate P/ Cum Rs. 2,104.84 Say 2,104.85

Page 5: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 5

Item No. 1 d) In Cement Sand Mortarii) Ratio ( 1:4 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headersNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Cement 7.20 Bag 230.00 Each 1,656.00 Sand 36.0 Cft 350.00 Per % Cft 126.00

Total 2,382.00 Contractor's Profit & Overhead 20.00 Percent 476.40 Total 2,858.40

Labour

Mason 4.00 Nos 300.00 Per Day 1,200.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.50 No 160.00 Per Day 80.00

Total 1,980.00 Sundries 10.00 Percent 198.00 Total 2,178.00

Contractor's Profit & Overhead 20.00 Percent 435.60 Total 2,613.60

Labour Rate for 100 Cft Rs. 2,613.60 Say 2,613.60 Labour Rate P/ Cum Rs. 923.12 Say 923.10

Composite Rate for 100 Cft Rs. 5,472.00 Say 5,472.00 Composite Rate P/ Cum Rs. 1,932.71 Say 1,932.70

Page 6: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 6

Item No. 1 d) In Cement Sand Mortariii) Ratio ( 1:6 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headersNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Cement 5.14 Bag 230.00 Each 1,182.20 Sand 38.57 Cft 350.00 Per%Cft 135.00

Total 1,917.19 Contractor's Profit & Overhead 20.00 Percent 383.44 Total 2,300.63

Labour

Mason 4.00 Nos 300.00 Per Day 1,200.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.50 No 160.00 Per Day 80.00

Total 1,980.00 Sundries 10.00 Percent 198.00 Total 2,178.00

Contractor's Profit & Overhead 20.00 Percent 435.60 Total 2,613.60

Labour Rate for 100 Cft Rs. 2,613.60 Say 2,613.60 Labour Rate P/ Cum Rs. 923.12 Say 923.10

Composite Rate for 100 Cft Rs. 4,914.23 Say 4,914.25 Composite Rate P/ Cum Rs. 1,735.71 Say 1,735.70

Page 7: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 7

Item No. 1 d) In Cement Sand Mortariv) Ratio ( 1:8 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headersNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Cement 4 Bag 230.00 Each 920.00 Sand 40 Cft 350.00 Per%Cft 140.00

Total 1,660.00 Contractor's Profit & Overhead 20.00 Percent 332.00 Total 1,992.00

Labour

Mason 4.00 Nos 300.00 Per Day 1,200.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.50 No 160.00 Per Day 80.00

Total 1,980.00 Sundries 10.00 Percent 198.00 Total 2,178.00

Contractor's Profit & Overhead 20.00 Percent 435.60 Total 2,613.60

Labour Rate for 100 Cft Rs. 2,613.60 Say 2,613.60 Labour Rate P/ Cum Rs. 923.12 Say 923.10

Composite Rate for 100 Cft Rs. 4,605.60 Say 4,605.60 Composite Rate P/ Cum Rs. 1,626.70 Say 1,626.70

Page 8: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 8

DESCRIPTION OF ITEM NO 2: Coursed Rubble Masonry hammer dressed,foundation and plinth.

a) Dry Masonry

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Headers or through stonesNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00

Total 600.00 Contractor's Profit & Overhead 20.00 Percent 120.00 Total 720.00

Labour

Mason 3.00 Nos 300.00 Per Day 900.00 Unskilled Coolies 3.00 Nos 140.00 Per Day 420.00

Total 1,320.00 Sundries 10.00 Percent 132.00 Total 1,452.00

Contractor's Profit & Overhead 20.00 Percent 290.40 Total 1,742.40

Labour Rate for 100 Cft Rs. 1,742.40 Say 1,742.40 Labour Rate P/ Cum Rs. 615.42 Say 615.40

Composite Rate for 100 Cft Rs. 2,462.40 Say 2,462.40 Composite Rate P/ Cum Rs. 869.72 Say 869.70

Page 9: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 9

Item No. 2 b) In Mud Mortar

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Headers or through stonesNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Good earth 45 Cft 150.00 Per% Cft 67.50

Total 667.50 Contractor's Profit & Overhead 20.00 Percent 133.50 Total 801.00

Labour

Mason 4.00 Nos 300.00 Per Day 1,200.00 Unskilled Coolies 4.00 Nos 140.00 Per Day 560.00 Bahishti 0.50 No 160.00 Per Day 80.00

Total 1,840.00 Sundries 10.00 Percent 184.00 Total 2,024.00

Contractor's Profit & Overhead 20.00 Percent 404.80 Total 2,428.80

Labour Rate for 100 Cft Rs. 2,428.80 Say 2,428.80 Labour Rate P/ Cum Rs. 857.85 Say 857.85

Composite Rate for 100 Cft Rs. 3,229.80 Say 3,229.80 Composite Rate P/ Cum Rs. 1,140.77 Say 1,140.75

Page 10: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 10

Item No. 2 c) In Lime Sand Mortar. (Ratio 1:2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headers 20 Nos 15.00 Each 300.00 Lime Slaked (Ground) 5.33/ 199 Kg 2.00 Per Per Kg. 398.00 Sand 26.67 Cft 350.00 Per%Cft 93.35

Total 1,091.35 Contractor's Profit & Overhead 20.00 Percent 218.27 Total 1,309.61

Labour

Mason 4.75 Nos 300.00 Per Day 1,425.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,245.00 Sundries 10.00 Percent 224.50 Total 2,469.50

Contractor's Profit & Overhead 20.00 Percent 493.90 Total 2,963.40

Labour Rate for 100 Cft Rs. 2,963.40 Say 2,963.40 Labour Rate P/ Cum Rs. 1,046.67 Say 1,046.65

Composite Rate for 100 Cft Rs. 4,273.01 Say 4,273.00 Composite Rate P/ Cum Rs. 1,509.22 Say 1,509.20

Page 11: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 11

Item No. 2 d) In Cement Sand Mortari) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stone Note: Special size of stone for headersaverage size = 35x1.5'x8"x10"(457x200x250mm) 35 Nos. 35 Nos 15.00 Each 525.00 Cement 8 Bag 230.00 Each 1,840.00 Sand 30 Cft 350.00 Per%Cft 105.00

Total 2,770.00 Contractor's Profit & Overhead 20.00 Percent 554.00 Total 3,324.00

Labour

Mason 4.75 Nos 300.00 Per Day 1,425.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,245.00 Sundries 10.00 Percent 224.50 Total 2,469.50

Contractor's Profit & Overhead 20.00 Percent 493.90 Total 2,963.40

Labour Rate for 100 Cft Rs. 2,963.40 Say 2,963.40 Labour Rate P/ Cum Rs. 1,046.67 Say 1,046.65

Composite Rate for 100 Cft Rs. 6,287.40 Say 6,287.40 Composite Rate P/ Cum Rs. 2,220.71 Say 2,220.70

Page 12: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 12

Item No. 2 d) In Cement Sand Mortarii) Ratio ( 1:4 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone including wastage 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stone Note: Special size of stone for headersaverage size = 35x1.5'x8"x10"(450x200x250mm) 35 Nos. 35 Nos 15.00 Each 525.00 Cement 6.40 Bag 230.00 Each 1,472.00 Sand 32 Cft 350.00 Per%Cft 112.00

Total 2,409.00 Contractor's Profit & Overhead 20.00 Percent 481.80 Total 2,890.80

Labour

Mason 4.75 Nos 300.00 Per Day 1,425.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,245.00 Sundries 10.00 Percent 224.50 Total 2,469.50

Contractor's Profit & Overhead 20.00 Percent 493.90 Total 2,963.40

Labour Rate for 100 Cft Rs. 2,963.40 Say 2,963.40 Labour Rate P/ Cum Rs. 1,046.68 Say 1,046.70

Composite Rate for 100 Cft Rs. 5,854.20 Say 5,854.20 Composite Rate P/ Cum Rs. 2,067.70 Say 2,067.70

Page 13: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 13

Item No. 2 d) In Cement Sand Mortariii) Ratio ( 1:6 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stone Note: Special size of stone for headersaverage size = 35x1.5'x8"x10"(450x200x250mm) 35 Nos. 35 Nos 15.00 Each 525.00 Cement 4.57 Bag 230.00 Each 1,051.10 Sand 34.20 Cft 350.00 Per%Cft 119.70

Total 1,995.80 Contractor's Profit & Overhead 20.00 Percent 399.16 Total 2,394.96

Labour

Mason 4.75 Nos 300.00 Per Day 1,425.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,245.00 Sundries 10.00 Percent 224.50 Total 2,469.50

Contractor's Profit & Overhead 20.00 Percent 493.90 Total 2,963.40

Labour Rate for 100 Cft Rs. 2,963.40 Say 2,963.40 Labour Rate P/ Cum Rs. 1,046.67 Say 1,046.65

Composite Rate for 100 Cft Rs. 5,358.36 Say 5,358.35 Composite Rate P/ Cum Rs. 1,892.57 Say 1,892.55

Page 14: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 14

Item No. 2 d) In Cement Sand Mortariv) Ratio ( 1:8 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stoneNote: Special size of stone for headersaverage size = 35x1.5'x8"x10"(457x200x250mm) 35 Nos. 35 Nos 15.00 Each 525.00 Cement 3.56 Bag 230.00 Each 818.80 Sand 35.60 Cft 350.00 Per%Cft 124.60

Total 1,768.40 Contractor's Profit & Overhead 20.00 Percent 353.68 Total 2,122.08

Labour

Mason 4.75 Nos 300.00 Per Day 1,425.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,245.00 Sundries 10.00 Percent 224.50 Total 2,469.50

Contractor's Profit & Overhead 20.00 Percent 493.90 Total 2,963.40

Labour Rate for 100 Cft Rs. 2,963.40 Say 2,963.40 Labour Rate P/ Cum Rs. 1,046.67 Say 1,046.65

Composite Rate for 100 Cft Rs. 5,085.48 Say 5,085.50 Composite Rate P/ Cum Rs. 1,796.19 Say 1,796.20

Page 15: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 15

DESCRIPTION OF ITEM NO 3: Random Rubble Masonry (uncoursed) in groundfloor or 20'(6 M) height,building/other than building.

a) Dry Masonry

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Headers or through stonesNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00

Total 600.00 Contractor's Profit & Overhead 20.00 Percent 120.00 Total 720.00

Labour

Mason 2.50 Nos 300.00 Per Day 750.00 Unskilled Coolies 3.00 Nos 140.00 Per Day 420.00

Total 1,170.00 Sundries 10.00 Percent 117.00 Total 1,287.00

Contractor's Profit & Overhead 20.00 Percent 257.40 Total 1,544.40

Labour Rate for 100 Cft Rs. 1,544.40 Say 1,544.40 Labour Rate P/ Cum Rs. 545.48 Say 545.50

Composite Rate for 100 Cft Rs. 2,264.40 Say 2,264.40 Composite Rate P/ Cum Rs. 799.79 Say 799.80

Page 16: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 16

Item No. 3 b) In Mud Mortar

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Headers or through stonesNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Good earth 45 Cft 150.00 Per % Cft 67.50

Total 667.50 Contractor's Profit & Overhead 20.00 Percent 133.50 Total 801.00

Labour

Mason 3.00 Nos 300.00 Per Day 900.00 Unskilled Coolies 4.00 Nos 140.00 Per Day 560.00 Bahishti 0.50 No 160.00 Per Day 80.00

Total 1,540.00 Sundries 10.00 Percent 154.00 Total 1,694.00

Contractor's Profit & Overhead 20.00 Percent 338.80 Total 2,032.80

Labour Rate for 100 Cft Rs. 2,032.80 Say 2,032.80 Labour Rate P/ Cum Rs. 717.99 Say 718.00

Composite Rate for 100 Cft Rs. 2,833.80 Say 2,833.80 Composite Rate P/ Cum Rs. 1,000.90 Say 1,000.90

Page 17: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 17

Item No. 3 c) In Lime Sand Mortar. (Ratio 1:2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headersNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Lime Slaked (Ground) 224 Kg 2.00 Per Per Kg. 448.00 Sand 30 Cft 350.00 Per % Cft 105.00

Total 1,153.00 Contractor's Profit & Overhead 20.00 Percent 230.60 Total 1,383.60

Labour

Mason 4.50 Nos 300.00 Per Day 1,350.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,170.00 Sundries 10.00 Percent 217.00 Total 2,387.00

Contractor's Profit & Overhead 20.00 Percent 477.40 Total 2,864.40

Labour Rate for 100 Cft Rs. 2,864.40 Say 2,864.40 Labour Rate P/ Cum Rs. 1,011.71 Say 1,011.70

Composite Rate for 100 Cft Rs. 4,248.00 Say 4,248.00 Composite Rate P/ Cum Rs. 1,500.39 Say 1,500.40

Page 18: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 18

Item No. 3 d) In Cement Sand Mortari) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headersNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Cement 9 Bag 230.00 Each 2,070.00 Sand 33.75 Cft 350.00 Per % Cft 118.13

Total 2,788.13 Contractor's Profit & Overhead 20.00 Percent 557.63 Total 3,345.75

Labour

Mason 4.50 Nos 300.00 Per Day 1,350.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,170.00 Sundries 10.00 Percent 217.00 Total 2,387.00

Contractor's Profit & Overhead 20.00 Percent 477.40 Total 2,864.40

Labour Rate for 100 Cft Rs. 2,864.40 Say 2,864.40 Labour Rate P/ Cum Rs. 1,011.71 Say 1,011.70

Composite Rate for 100 Cft Rs. 6,210.15 Say 6,210.15 Composite Rate P/ Cum Rs. 2,193.42 Say 2,193.45

Page 19: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 19

Item No. 3 d) In Cement Sand Mortarii) Ratio ( 1:4 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stone Note: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Cement 7.2 Bag 230.00 Each 1,656.00 Sand 36 Cft 350.00 Per % Cft 126.00

Total 2,382.00 Contractor's Profit & Overhead 20.00 Percent 476.40 Total 2,858.40

Labour

Mason 4.50 Nos 300.00 Per Day 1,350.00 Unskilled Coolies 5 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,170.00 Sundries 10.00 Percent 217.00 Total 2,387.00

Contractor's Profit & Overhead 20.00 Percent 477.40 Total 2,864.40

Labour Rate for 100 Cft Rs. 2,864.40 Say 2,864.40 Labour Rate P/ Cum Rs. 1,011.71 Say 1,011.70

Composite Rate for 100 Cft Rs. 5,722.80 Say 5,722.80 Composite Rate P/ Cum Rs. 2,021.29 Say 2,021.30

Page 20: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 20

Item No. 3 d) In Cement Sand Mortariii) Ratio ( 1:6 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100.00 Cft 300.00 Per % Cft 300.00

Through Stone or bond stone Note: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Cement 5.14 Bag 230.00 Each 1,182.20 Sand 38.57 Cft 350.00 Per % Cft 135.00

Total 1,917.19 Contractor's Profit & Overhead 20.00 Percent 383.44 Total 2,300.63

Labour

Mason 4.50 Nos 300.00 Per Day 1,350.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,170.00 Sundries 10.00 Percent 217.00 Total 2,387.00

Contractor's Profit & Overhead 20.00 Percent 477.40 Total 2,864.40

Labour Rate for 100 Cft Rs. 2,864.40 Say 2,864.40 Labour Rate P/ Cum Rs. 1,011.71 Say 1,011.70

Composite Rate for 100 Cft Rs. 5,165.04 Say 5,165.05 Composite Rate P/ Cum Rs. 1,824.29 Say 1,824.30

Page 21: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 21

Item No. 3 d) In Cement Sand Mortariv) Ratio ( 1:8 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stoneNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250) 20 Nos. 20 Nos 15.00 Each 300.00 Cement 4 Bag 230.00 Each 920.00 Sand 40 Cft 350.00 Per % Cft 140.00

Total 1,660.00 Contractor's Profit & Overhead 20.00 Percent 332.00 Total 1,992.00

Labour

Mason 4.50 Nos 300.00 Per Day 1,350.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,170.00 Sundries 10.00 Percent 217.00 Total 2,387.00

Contractor's Profit & Overhead 20.00 Percent 477.40 Total 2,864.40

Labour Rate for 100 Cft Rs. 2,864.40 Say 2,864.40 Labour Rate P/ Cum Rs. 1,011.71 Say 1,011.70

Composite Rate for 100 Cft Rs. 4,856.40 Say 4,856.40 Composite Rate P/ Cum Rs. 1,715.28 Say 1,715.30

Page 22: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 22

DESCRIPTION OF ITEM NO 4: Coursed Rubble Masonry hammer dressed inground floor or 20' (6 M) height, building otherthan building.

a) Dry Masonry

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Headers or through stonesNote: Special size of stone for headersaverage size = 20x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00

Total 600.00 Contractor's Profit & Overhead 20.00 Percent 120.00 Total 720.00

Labour

Mason 3.50 Nos 300.00 Per Day 1,050.00 Unskilled Coolies 3.50 Nos 140.00 Per Day 490.00

Total 1,540.00 Sundries 10.00 Percent 154.00 Total 1,694.00

Contractor's Profit & Overhead 20.00 Percent 338.80 Total 2,032.80

Labour Rate for 100 Cft Rs. 2,032.80 Say 2,032.80 Labour Rate P/ Cum Rs. 717.99 Say 718.00

Composite Rate for 100 Cft Rs. 2,752.80 Say 2,752.80 Composite Rate P/ Cum Rs. 972.29 Say 972.30

Page 23: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 23

Item No. 4 b) In Mud Mortar

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Headers or through stonesNote: Special size of stone for headersaverage size = 30x1.5'x8"x10"(457x200x250mm) 20 Nos. 20 Nos 15.00 Each 300.00 Good earth 43 Cft 150.00 Per % Cft 64.50

Total 664.50 Contractor's Profit & Overhead 20.00 Percent 132.90 Total 797.40

Labour

Mason 5.00 Nos 300.00 Per Day 1,500.00 Unskilled Coolies 5.00 Nos 140.00 Per Day 700.00 Bahishti 0.50 No 160.00 Per Day 80.00

Total 2,280.00 Sundries 10.00 Percent 228.00 Total 2,508.00

Contractor's Profit & Overhead 20.00 Percent 501.60 Total 3,009.60

Labour Rate for 100 Cft Rs. 3,009.60 Say 3,009.60 Labour Rate P/ Cum Rs. 1,063.00 Say 1,063.00

Composite Rate for 100 Cft Rs. 3,807.00 Say 3,807.00 Composite Rate P/ Cum Rs. 1,344.63 Say 1,344.65

Page 24: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 24

Item No. 4 c) In Lime Sand Mortar. (Ratio 1:2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone including wastage 100 Cft 300.00 Per % Cft 300.00

Through Stone or headers 20 Nos 15.00 Each 300.00 Lime Slaked (Ground) 5.33 Mds(19 9)Kg 2.00 Per Per Kg. 398.00 Sand 26.67 Cft 350.00 Per % Cft 93.35

Total 1,091.35 Contractor's Profit & Overhead 20.00 Percent 218.27 Total 1,309.61

Labour

Mason 5.50 Nos 300.00 Per Day 1,650.00 Unskilled Coolies 5.50 Nos 140.00 Per Day 770.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,540.00 Sundries 10.00 Percent 254.00 Total 2,794.00

Contractor's Profit & Overhead 20.00 Percent 558.80 Total 3,352.80

Labour Rate for 100 Cft Rs. 3,352.80 Say 3,352.80 Labour Rate P/ Cum Rs. 1,184.21 Say 1,184.20

Composite Rate for 100 Cft Rs. 4,662.42 Say 4,662.40 Composite Rate P/ Cum Rs. 1,646.76 Say 1,646.75

Page 25: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 25

Item No. 4 d) In Cement Sand Mortari) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or headersNote: Special size of stone for headersaverage size = 35x1.5'x8"x10"(457x200x250) 35 Nos. 35 Nos 15.00 Each 525.00 Cement 8 Bag 230.00 Each 1,840.00 Sand 30 Cft 350.00 Per % Cft 105.00

Total 2,770.00 Contractor's Profit & Overhead 20.00 Percent 554.00 Total 3,324.00

Labour

Mason 5.50 Nos 300.00 Per Day 1,650.00 Unskilled Coolies 5.50 Nos 140.00 Per Day 770.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,540.00 Sundries 10.00 Percent 254.00 Total 2,794.00

Contractor's Profit & Overhead 20.00 Percent 558.80 Total 3,352.80

Labour Rate for 100 Cft Rs. 3,352.80 Say 3,352.80 Labour Rate P/ Cum Rs. 1,184.21 Say 1,184.20

Composite Rate for 100 Cft Rs. 6,676.80 Say 6,676.80 Composite Rate P/ Cum Rs. 2,358.25 Say 2,358.25

Page 26: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 26

Item No. 4 d) In Cement Sand Mortarii) Ratio ( 1:4 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stone Note: Special size of stone for headersaverage size = 35x1.5'x8"x10"(457x200x250mm) 35 Nos. 35 Nos 15.00 Each 525.00 Cement 6 Bag 230.00 Each 1,472.00 Sand 32 Cft 350.00 Per % Cft 112.00

Total 2,409.00 Contractor's Profit & Overhead 20.00 Percent 481.80 Total 2,890.80

Labour

Mason 5.50 Nos 300.00 Per Day 1,650.00 Unskilled Coolies 5.50 Nos 140.00 Per Day 770.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,540.00 Sundries 10.00 Percent 254.00 Total 2,794.00

Contractor's Profit & Overhead 20.00 Percent 558.80 Total 3,352.80

Labour Rate for 100 Cft Rs. 3,352.80 Say 3,352.80 Labour Rate P/ Cum Rs. 1,184.21 Say 1,184.20

Composite Rate for 100 Cft Rs. 6,243.60 Say 6,243.60 Composite Rate P/ Cum Rs. 2,205.24 Say 2,205.25

Page 27: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 27

Item No. 4 d) In Cement Sand Mortariii) Ratio ( 1:6 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stone Note: Special size of stone for headersaverage size = 35x1.5'x8"x10"(457x200x250mm) 35 Nos. 35 Nos 15.00 Each 525.00 Cement 4.57 Bag 230.00 Each 1,051.10 Sand 34.20 Cft 350.00 Per % Cft 119.70

Total 1,995.80 Contractor's Profit & Overhead 20.00 Percent 399.16 Total 2,394.96

Labour

Mason 5.50 Nos 300.00 Per Day 1,650.00 Unskilled Coolies 5.50 Nos 140.00 Per Day 770.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,540.00 Sundries 10.00 Percent 254.00 Total 2,794.00

Contractor's Profit & Overhead 20.00 Percent 558.80 Total 3,352.80

Labour Rate for 100 Cft Rs. 3,352.80 Say 3,352.80 Labour Rate P/ Cum Rs. 1,184.21 Say 1,184.20

Composite Rate for 100 Cft Rs. 5,747.76 Say 5,747.75 Composite Rate P/ Cum Rs. 2,030.11 Say 2,030.10

Page 28: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 28

Item No. 4 d) In Cement Sand Mortariv) Ratio ( 1:8 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 100 Cft 300.00 Per % Cft 300.00

Through Stone or bond stoneNote: Special size of stone for headersaverage size = 35x1.5'x8"x10"(457x200x250mm) 35 Nos. 35 Nos 15.00 Each 525.00 Cement 3.56 Bag 230.00 Each 818.80 Sand 35.60 Cft 350.00 Per % Cft 124.60

Total 1,768.40 Contractor's Profit & Overhead 20.00 Percent 353.68 Total 2,122.08

Labour

Mason 5.50 Nos 300.00 Per Day 1,650.00 Unskilled Coolies 5.50 Nos 140.00 Per Day 770.00 Bahishti 0.75 No 160.00 Per Day 120.00

Total 2,540.00 Sundries 10.00 Percent 254.00 Total 2,794.00

Contractor's Profit & Overhead 20.00 Percent 558.80 Total 3,352.80

Labour Rate for 100 Cft Rs. 3,352.80 Say 3,352.80 Labour Rate P/ Cum Rs. 1,184.21 Say 1,184.20

Composite Rate for 100 Cft Rs. 5,474.88 Say 5,474.90 Composite Rate P/ Cum Rs. 1,933.73 Say 1,933.75

Page 29: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 29

DESCRIPTION OF ITEM NO 5: Ashlar block in course or scabbled masonry(including dressing etc.) in ground floor or 20' (6 M) height, Building other than building.

a) In Lime Sand. (Ratio 1:2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 200 Cft 300.00 Per % Cft 600.00 Lime Slaked (Ground) 4Md (149.30 Kg) 2.00 Per Kg. 298.60 Sand 20 Cft 3.50 Cft 70.00 Charcoal 30Lb (13.61 Kg) 4.00 Per Kg. 54.44 Steel 3.3Lb (1.50 Kg) 17.00 Per Kg. 25.50

Total 1,048.54 Contractor's Profit & Overhead 20.00 Percent 209.71 Total 1,258.25

Labour

Mason 17.00 Nos 300.00 Per Day 5,100.00 Unskilled Coolies 10.00 Nos 140.00 Per Day 1,400.00 Bahishti 1.00 No 160.00 Per Day 160.00 Blacksmith 1.00 No 170.00 Per Day 170.00 Bellow-man 1.00 No 75.00 Per Day 75.00

Total 6,905.00 Sundries 10.00 Percent 690.50 Total 7,595.50

Contractor's Profit & Overhead 20.00 Percent 1,519.10 Total 9,114.60

Labour Rate for 100 Cft Rs. 9,114.60 Say 9,114.60 Labour Rate P/ Cum Rs. 3,219.28 Say 3,219.30

Composite Rate for 100 Cft Rs. ### Say ###Composite Rate P/ Cum Rs. 3,663.68 Say 3,663.70

Page 30: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 30

Item No. 5 b) In Cement Sand Mortari) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 200 Cft 300.00 Per % Cft 600.00 Cement 6 Bag 230.00 Each 1,380.00 Sand 22.50 Cft 3.50 Cft 78.75 Charcoal 30Lb (13.61 Kg) 4.00 Per Kg. 54.44 Steel 3.3Lb (1.50 Kg) 17.00 Per Kg. 25.50

Total 2,138.69 Contractor's Profit & Overhead 20.00 Percent 427.74 Total 2,566.43

Labour

Mason 17.00 Nos 300.00 Per Day 5,100.00 Unskilled Coolies 10.00 Nos 140.00 Per Day 1,400.00 Bahishti 1.00 No 160.00 Per Day 160.00 Blacksmith 1.00 No 170.00 Per Day 170.00 Bellow-man 1.00 No 75.00 Per Day 75.00

Total 6,905.00 Sundries 10.00 Percent 690.50 Total 7,595.50

Contractor's Profit & Overhead 20.00 Percent 1,519.10 Total 9,114.60

Labour Rate for 100 Cft Rs. 9,114.60 Say 9,114.60 Labour Rate P/ Cum Rs. 3,219.28 Say 3,219.30

Composite Rate for 100 Cft Rs. ### Say ###Composite Rate P/ Cum Rs. 4,125.75 Say 4,125.75

Page 31: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 31

Item No. 5 b) In Cement Sand Mortarii) Ratio ( 1:4 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 200 Cft 300.00 Per % Cft 600.00 Cement 4.80 Bag 230.00 Each 1,104.00 Sand 24 Cft 350.00 % Cft 84.00 Charcoal 30Lb (13.61 Kg) 4.00 Per Per Kg. 54.44 Steel 3.3Lb (1.50 Kg) 17.00 Per Per Kg. 25.50

Total 1,867.94 Contractor's Profit & Overhead 20.00 Percent 373.59 Total 2,241.53

Labour

Mason 17.00 Nos 300.00 Per Day 5,100.00 Unskilled Coolies 10.00 Nos 140.00 Per Day 1,400.00 Bahishti 1.00 No 160.00 Per Day 160.00 Blacksmith 1.00 No 170.00 Per Day 170.00 Bellow-man 1.00 No 75.00 Per Day 75.00

Total 6,905.00 Sundries 10.00 Percent 690.50 Total 7,595.50

Contractor's Profit & Overhead 20.00 Percent 1,519.10 Total 9,114.60

Labour Rate for 100 Cft Rs. 9,114.60 Say 9,114.60 Labour Rate P/ Cum Rs. 3,219.28 Say 3,219.30

Composite Rate for 100 Cft Rs. ### Say ###Composite Rate P/ Cum Rs. 4,010.98 Say 4,011.00

Page 32: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 32

Item No. 5 b) In Cement Sand Mortariii) Ratio ( 1:6 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 200 Cft 300.00 Per % Cft 600.00 Cement 3.44 Bag 230.00 Each 791.20 Sand 25.70 Cft 3.50 Cft 89.95 Charcoal 30Lb (13.61 Kg) 4.00 Per Per Kg. 54.44 Steel 3.3Lb (1.50 Kg) 17.00 Per Per Kg. 25.50

Total 1,561.09 Contractor's Profit & Overhead 20.00 Percent 312.22 Total 1,873.31

Labour

Mason 17.00 Nos 300.00 Per Day 5,100.00 Unskilled Coolies 10.00 Nos 140.00 Per Day 1,400.00 Bahishti 1.00 No 160.00 Per Day 160.00 Blacksmith 1.00 No 170.00 Per Day 170.00 Bellow-man 1.00 No 75.00 Per Day 75.00

Total 6,905.00 Sundries 10.00 Percent 690.50 Total 7,595.50

Contractor's Profit & Overhead 20.00 Percent 1,519.10 Total 9,114.60

Labour Rate for 100 Cft Rs. 9,114.60 Say 9,114.60 Labour Rate P/ Cum Rs. 3,219.28 Say 3,219.30

Composite Rate for 100 Cft Rs. ### Say ###Composite Rate P/ Cum Rs. 3,880.93 Say 3,880.95

Page 33: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 33

DESCRIPTION OF ITEM NO 6: Ashlar fine masonry (including dressing etc.) inground floor or 20' (6 M) height, Building otherthan building.

a) In Lime Sand Mortar. (Ratio 1:2)

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 250 Cft 300.00 Per % Cft 750.00 Lime Slaked (Ground) 2Md (74.65 Kg) 2.00 Per Per Kg. 149.30 Sand 10 Cft 3.50 Cft 35.00 Charcoal 0.73Md(27.2 5)Kg 4.00 Per Per Kg. 109.00 Steel 4Lb (1.82 Kg) 17.00 Per Per Kg. 30.94

Total 1,074.24 Contractor's Profit & Overhead 20.00 Percent 214.85 Total 1,289.09

Labour

Mason 40.00 Nos 300.00 Per Day 12,000.00 Unskilled Coolies 8.00 Nos 140.00 Per Day 1,120.00 Bahishti 1.00 No 160.00 Per Day 160.00 Blacksmith 1.50 No 170.00 Per Day 255.00 Bellow-man 1.50 No 75.00 Per Day 112.50

Total ###Sundries 10.00 Percent 1,364.75 Total ###

Contractor's Profit & Overhead 20.00 Percent 3,002.45 Total ###

Labour Rate Per 100 Cft Rs. ### Say ###Labour Rate P/ Cum Rs. 6,362.79 Say 6,362.80

Composite Rate Per 100 Cft Rs. ### Say ###Composite Rate P/ Cum Rs. 6,818.10 Say 6,818.10

Page 34: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 34

Item No. 6 b) In Cement Sand Mortari) Ratio ( 1:3 )

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 250 Cft 300.00 Per % Cft 750.00 Cement 3 Bag 230.00 Each 690.00 Sand 11.25 Cft 3.50 Per % Cft 39.38 Charcoal 0.73Md (27.25 Kg) 4.00 Per Per Kg. 109.00 Steel 4Lb (1.82 Kg) 17.00 Per Per Kg. 30.94

Total 1,619.32 Contractor's Profit & Overhead 20.00 Percent 323.86 Total 1,943.18

Labour

Mason 40.00 Nos 300.00 Per Day 12,000.00 Unskilled Coolies 8.00 Nos 140.00 Per Day 1,120.00 Bahishti 1.00 No 160.00 Per Day 160.00 Blacksmith 1.50 No 170.00 Per Day 255.00 Bellow-man 1.50 No 75.00 Per Day 112.50

Total ###Sundries 10.00 Percent 1,364.75 Total ###

Contractor's Profit & Overhead 20.00 Percent 3,002.45 Total ###

Labour Rate for 100 Cft Rs. ### Say ###Labour Rate P/ Cum Rs. 6,362.79 Say 6,362.80

Composite Rate for 100 Cft Rs. ### Say ###Composite Rate P/ Cum Rs. 7,049.13 Say 7,049.15

Page 35: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 35

Item No. 6 b) In Cement Sand Mortarii) Ratio 1:4

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 250 Cft 300.00 Per % Cft 750.00 Cement 2.40 Bag 230.00 Each 552.00 Sand 12 Cft 3.50 Per % Cft 42.00 Charcoal 60Lb (27.22 Kg) 4.00 Per Per Kg. 108.88 Steel 4Lb (1.82 Kg) 17.00 Per Per Kg. 30.94

Total 1,483.82 Contractor's Profit & Overhead 20.00 Percent 296.76 Total 1,780.58

Labour

Mason 40.00 Nos 300.00 Per Day 12,000.00 Unskilled Coolies 8.00 Nos 140.00 Per Day 1,120.00 Bahishti 1.00 No 160.00 Per Day 160.00 Blacksmith 1.50 No 170.00 Per Day 255.00 Bellow-man 1.50 No 75.00 Per Day 112.50

Total ###Sundries 10.00 Percent 1,364.75 Total ###

Contractor's Profit & Overhead 20.00 Percent 3,002.45 Total ###

Labour Rate for 100 Cft Rs. ### Say ###Labour Rate P/ Cum Rs. 6,362.79 Say 6,362.80

Composite Rate for 100 Cft Rs. ### Say ###Composite Rate P/ Cum Rs. 6,991.69 Say 6,991.70

Page 36: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 36

Item No. 6 b) In Cement Sand Mortariii) Ratio 1:6

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Quarried Stone 250 Cft 300.00 Per % Cft 750.00 Cement 1.73 Bag 230.00 Each 397.90 Sand 13 Cft 350.00 Per % Cft 45.50 Charcoal 60Lb (27.22 Kg) 4.00 Per Per Kg. 108.88 Steel 4Lb (1.82 Kg) 17.00 Per Per Kg. 30.94

Total 1,333.22 Contractor's Profit & Overhead 20.00 Percent 266.64 Total 1,599.86

Labour

Mason 40.00 Nos 300.00 Per Day 12,000.00 Unskilled Coolies 8.00 Nos 140.00 Per Day 1,120.00 Bahishti 1.00 No 160.00 Per Day 160.00 Blacksmith 1.50 No 170.00 Per Day 255.00 Bellow-man 1.50 No 75.00 Per Day 112.50

Total ###Sundries 10.00 Percent 1,364.75 Total ###

Contractor's Profit & Overhead 20.00 Percent 3,002.45 Total ###

Labour Rate for 100 Cft Rs. ### Say ###Labour Rate P/ Cum Rs. 6,362.79 Say 6,362.80

Composite Rate for 100 Cft Rs. ### Say ###Composite Rate P/ Cum Rs. 6,927.87 Say 6,927.85

Page 37: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 37

DESCRIPTION OF ITEM NO 7: Extra labour on items 3,4,5 and 6 for work in.

i) First Floor

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Cft.

Mason 0.40 No 300.00 Per Day 120.00 Unskilled Coolies 1.35 No 140.00 Per Day 189.00

Total 309.00 Sundries 10.00 Percent 30.90 Total 339.90

Contractor's Profit & Overhead 20.00 Percent 67.98 Total 407.88

Labour Rate for 100 Cft Rs. 326.31 Say 326.30

Labour Rate P/ Cum Rs. 115.25 Say 115.25

Page 38: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 38

Item No. 7 ii) Second Floor

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Cft.

Mason 1.20 No 300.00 Per Day 360.00 Unskilled Coolies 2.60 Nos 140.00 Per Day 364.00

Total 724.00 Sundries 10.00 Percent 72.40 Total 796.40

Contractor's Profit & Overhead 20.00 Percent 159.28 Total for 125 Cft. 955.68 Rate for 100 Cft. 764.54

Labour Rate for 100 Cft Rs. 764.54 Say 764.55

Labour Rate P/ Cum Rs. 270.04 Say 270.05

Page 39: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 39

Item No. 7 iii) Third Floor

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Cft.

Mason 2 Nos 300.00 Per Day 600.00 Unskilled Coolies 3.90 Nos 140.00 Per Day 546.00

Total 1,146.00 Sundries 10.00 Percent 114.60 Total 1,260.60

Contractor's Profit & Overhead 20.00 Percent 252.12 Total for 125 Cft. 1,512.72 Rate for 100 Cft. 1,210.18

Labour Rate for 100 Cft Rs. 1,210.18 Say 1,210.20

Labour Rate P/ Cum Rs. 427.43 Say 427.45

Item No. 7 iv) Fourth Floor

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Cft.

Mason 3.60 Nos 300.00 Per Day 1,080.00 Unskilled Coolies 5.60 Nos 140.00 Per Day 784.00

Total 1,864.00 Sundries 10.00 Percent 186.40 Total 2,050.40

Contractor's Profit & Overhead 20.00 Percent 410.08 Total for 125 Cft. 2,460.48 Rate for 100 Cft. 1,968.38

Labour Rate for 100 Cft Rs. 1,968.38 Say 1,968.40

Labour Rate P/ Cum Rs. 695.23 Say 695.25

Page 40: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 40

DESCRIPTION OF ITEM NO 8: Extra labour on items 3,4,5 and 6 above for every5ft (1.5 M) additional height building other thanbuilding part thereof.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Cft.

Mason 0.50 No 300.00 Per Day 150.00 Unskilled Coolies 1 No 140.00 Per Day 140.00

Total 290.00 Sundries 10.00 Percent 29.00 Total 319.00

Contractor's Profit & Overhead 20.00 Percent 63.80 Totalfor 125 Cft. 382.80 Rate for 100 Cft. 306.24

Labour Rate for 100 Cft Rs. 306.24 Say 306.25

Labour Rate P/ Cum Rs. 108.16 Say 108.15

Page 41: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 41

DESCRIPTION OF ITEM NO 9: Extra labour for arch work in stone masonryincluding centering and de-centering, etc.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material

Kikar wood = 3.75 Cft to be used for60 times 3.75/60 = 0.06 Cft 0.06 Cft 250.00 Per Cft 15.00 Earth 2.00 Cft 150.00 % Cft 3.00

18.00 Contractor's Profit & Overhead 20.00 Percent 3.60 Total for 33.8 Cft 21.60 Total for 100 Cft 19.8 x 100 63.91

33.8Labour

Mason 1.50 Nos 300.00 Per Day 450.00 Unskilled Coolies 1.50 Nos 140.00 Per Day 210.00

Total 660.00 Sundries 10.00 Percent 66.00 Total 726.00

Contractor's Profit & Overhead 20.00 Percent 145.20 Total 871.20 Total (i+ii) 935.12

Labour Rate for 100 Cft Rs. 935.12 Say 935.10

Labour Rate P/ Cum Rs. 330.28 Say 330.30

Semi circular opening 15'x1.5'x1.5' = 33.8 Cft

Page 42: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 42

DESCRIPTION OF ITEM NO 10: Extra labour for :-

a) Coping and caps etc

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Material for 125 Cft.

Stone 12" (300mm) and above 30 Cft 300.00 Per % Cft 90.00 Steel 0.75Lb (0.34 Kg) 17.00 Per Kg. 5.78 Charcoal 10Lb (4.54 Kg) 4.00 Per Kg. 18.16

Total 113.94 Contractor's Profit & Overhead 20.00 Percent 22.79 Total 136.73

Labour

Mason 18.00 Nos 300.00 Per Day 5,400.00

Total 5,400.00 Sundries 10.00 Percent 540.00 Total 5,940.00

Contractor's Profit & Overhead 20.00 Percent 1,188.00 Total for 125 Cft. 7,128.00 Rate for 100 Cft. 5,702.40

Extra Rate Per 100 Cft Rs. 5,702.40 Say 5,702.40

Extra Rate P/ Cum Rs. 2,014.09 Say 2,014.10

Page 43: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 43

Item No. 10 b) Cornice and string course

Detail Unit Rate (British System) per 100 Rft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Rft

Mason 18 Nos 300.00 Per Day 5,400.00

Total 5,400.00 Sundries 10.00 Percent 540.00 Total 5,940.00

Contractor's Profit & Overhead 20.00 Percent 1,188.00 Total for 125 Rft 7,128.00 Rate for 100 Rft 5,702.40

Labour Rate for 100 Rft Rs. 5,702.40 Say 5,702.40

Labour Rate P/ LM. Rs. 187.04 Say 187.05

Page 44: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 44

DESCRIPTION OF ITEM NO 11: Dressing Stones

a) Hammer Dressed

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Sft

Mason 5 Nos 300.00 Per Day 1,500.00 Unskilled Coolies 2.50 Nos 140.00 Per Day 350.00

Total 1,850.00 Sundries 10.00 Percent 185.00 Total 2,035.00

Contractor's Profit & Overhead 20.00 Percent 407.00 Total for 125 Sft 2,442.00 Rate for 100 Sft. 1,953.60

Labour Rate for 100 Sft Rs. 1,953.60 Say 1,953.60

Labour Rate P/ Sq.m Rs. 210.21 Say 210.20

Item No. 11 b) Rough tooled dressed

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Sft

Mason 10 Nos 300.00 Per Day 3,000.00 Unskilled Coolies 4 Nos 140.00 Per Day 560.00

Total 3,560.00 Sundries 10.00 Percent 356.00 Total 3,916.00

Contractor's Profit & Overhead 20.00 Percent 783.20 Total for 125 Sft 4,699.20 Rate for 100 Sft 3,759.36

Labour Rate for 100 Sft Rs. 3,759.36 Say 3,759.35 Labour Rate P/ Sq.m Rs. 404.51 Say 404.50

Page 45: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 45

Item No. 11 c) Chisel dressed

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Sft

Mason 12 Nos 300.00 Per Day 3,600.00 Unskilled Coolies 5 Nos 140.00 Per Day 700.00

Total 4,300.00 Sundries 10.00 Percent 430.00 Total 4,730.00

Contractor's Profit & Overhead 20.00 Percent 946.00 Total for 125 Sft 5,676.00 Rate for 100 Sft 4,540.80

Labour Rate for 100 Sft Rs. 4,540.80 Say 4,540.80

Labour Rate P/ Sq.m Rs. 488.59 Say 488.60

Item No. 11 d) Fine dressed

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit (Rs) Amount (Rs)

Labour for 125 Sft

Mason 28 Nos 300.00 Per Day 8,400.00 Unskilled Coolies 5 Nos 140.00 Per Day 700.00 Blacksmith 1 No 170.00 Per Day 170.00

Total 9,270.00 Sundries 10.00 Percent 927.00 Total ###

Contractor's Profit & Overhead 20.00 Percent 2,039.40 Total for 125 Sft ###Rate for 100 Sft 9,789.12

Labour Rate for 100 Sft Rs. 9,789.12 Say 9,789.10 Labour Rate P/ Sq.m Rs. 1,053.31 Say 1,053.30

Page 46: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 46

DESCRIPTION OF ITEM NO 12: Dhajji walling 5"x5" (125x125mm) thickdeodar framing with stone laid in 1:6 cementsand mortar and (1:4) cement sand plaster onboth sides.

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit (Rs) Amount (Rs)

Rate Analysis for 234 Sft

a) Detail of Woodi) Top bottom

12x12ii) Vertical post 4" (100mm) apart

6x13'x5/12x5/12 = 13.55 Cftiii) Horizontal Pieces

3x18'x5/12x¼ = 5.62 Cftiv) Diagonl Strutts

31.67 Cft

38.00 CftThis wood can be used 10 time hencewood for our operation would be = 38/10 3.80 Cft

b) Stone (Quarried) 1x18x13x5/12 = 98.00 Cft

66.00 CftTherefore stone required = 66 x 2 112 Cft

Material

Wood as above 2nd Class 3.80 Cft 300.00 Cft 1,140.00 Spikes ¾" (20mm) 0.333 Kg. 30.00 Per Kg. 9.99 Wire nail 4" (100mm) 0.333 Kg. 45.00 Per Kg. 14.99 Wood preservative 0.304 Ltr 625.00 Per Litre 190.00 Stone quarried 112.00 Cft 300.00 Per % Cft 336.00 Cement for 1:6 ratio for laying 3.00 Bag 230.00 Per Bag 690.00 Cement for plastering ½" thick bothside (1:4) 3.40 Bag 230.00 Per Bag 782.00

2x18'x5x5 = 6.25 Cft

20x6x5/12x1/6 = 6.25 Cft

Wastage 20% = 6.33

Deduct Scantling = 32.00 Cft

Page 47: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 47

Item No. 12

Detail Unit Rate (British System) per 100 Sft

Qty Rate Per Unit (Rs) Amount (Rs)

Sand 40 Cft 350.00 % Cft 140.00 Steel 3Lb (1.36 Kg) 17.00 Per Kg. 23.12 Coal 0.5Md (18.66 Kg) 4.00 Per Kg. 74.64

Total 3,400.74 Contractor's Profit & Overhead 20.00 Percent 680.15 Total 4,080.88

Labour

Carpenters for wood work 4.00 Nos 300.00 Per Day 1,200.00 UnsKilled Coolies 2.00 Nos 140.00 Per Day 280.00 Masons for dressing of stones includinglaying 10.00 Nos 300.00 Per Day 3,000.00 Unskilled Coolies for laying 5.00 Nos 140.00 Per Day 700.00 Masson for plaster 3.00 Nos 300.00 Per Day 900.00 Unskilled Coolies 3.00 Nos 140.00 Per Day 420.00 Blacksmith 0.50 No 170.00 Per Day 85.00 Bellow-man 0.50 No 75.00 Per Day 37.50

Total 6,622.50 Sundries 10.00 Percent 662.25 Total 7,284.75

Contractor's Profit & Overhead 20.00 Percent 1,456.95 Total for 234 Sft 8,741.70 Rate for 100 Sft 3,735.77

Labour Rate for 100 Sft Rs. 3,735.77 Say 3,735.75 Labour Rate P/ Sqm Rs. 401.97 Say 401.95

Composite Rate for 100 Sft Rs. 5,479.74 Say 5,479.75 Composite Rate P/ Sqm Rs. 589.62 Say 589.60

Page 48: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 48

DESCRIPTION OF ITEM NO 13: Providing and fixing stone blocks from 2 Cft to 6Cft (0.06 to 017 M³) each, including lift upto20' (6 M).

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Rate Analysis for 4 Cft

Material

Hand dressed stone average 4 Cft 1 No 70.00 Each 70.00 Cement 0.06 Bag 230.00 Bag 14.03 Sand 0.30 Cft. 350.00 % Cft 1.05

Total 85.08 Contractor's Profit & Overhead 20.00 Percent 17.02 Total 102.10

Labour

Mason 0.25 No 300.00 Per Day 75.00 Unskilled Coolies 2.00 Nos 140.00 Per Day 280.00 Blacksmith 0.12 No 170.00 Per Day 20.40

Total 375.40 Sundries 10.00 Percent 37.54 Total 412.94

Contractor's Profit & Overhead 20.00 Percent 82.59 Total for 4 Cft 495.53 Rate for Per Cft 123.88

Labour Rate Per Cft Rs. 123.88 Say 123.90 Labour Rate P/ Cum Rs. 4,375.43 Say 4,375.45

Composite Rate Per Cft Rs. 149.41 Say 149.40 Composite Rate P/ Cum Rs. 5,277.02 Say 5,277.00

Page 49: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 49

DESCRIPTION OF ITEM NO 14: Providing and fixing stone blocks under 2 Cft(0.05 M³) each, including lift upto 20 Cft (6 M).

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit (Rs) Amount (Rs)

Hand dressed stone average (2 Cft) 1 No 35.00 Each 35.00 Cement 0.03 Bag 230.00 Bag 6.90 Sand 0.17 Cft. 350.00 % Cft 0.60

Total 42.50 Contractor's Profit & Overhead 20.00 Percent 8.50 Total 51.00 51.00

2.00 25.50

Mason 0.05 No 300.00 Per Day 15.00 Unskilled Coolies 0.25 No 140.00 Per Day 35.00 Blacksmith 0.03 No 170.00 Per Day 5.10

Total 55.10 Sundries 10.00 Percent 5.51 Total 60.61

Contractor's Profit & Overhead 20.00 Percent 12.12 Total 72.73

Labour Rate Per Cft Rs. 72.73 Say 72.75 Labour Rate P/ Cum Rs. 2,568.89 Say 2,568.90

Composite Rate Per Cft Rs. 98.23 Say 98.25 Composite Rate P/ Cum Rs. 3,469.62 Say 3,469.65

Material Rate Analysis for 2 Cft

Labour Rate Analysis for 1 Cft

Page 50: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 50

Amount (Rs)

Page 51: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 51

Amount (Rs)

Page 52: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 52

Amount (Rs)

Page 53: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 53

Amount (Rs)

Page 54: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 54

Amount (Rs)

Page 55: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 55

Amount (Rs)

Page 56: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 56

Amount (Rs)

Page 57: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 57

Amount (Rs)

Page 58: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 58

Amount (Rs)

Page 59: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 59

Amount (Rs)

Page 60: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 60

Amount (Rs)

Page 61: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 61

Amount (Rs)

Page 62: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 62

Amount (Rs)

Page 63: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 63

Amount (Rs)

Page 64: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 64

floor or 20'(6 M) height,building/other than building.

Amount (Rs)

Page 65: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 65

Amount (Rs)

Page 66: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 66

Amount (Rs)

Page 67: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 67

Amount (Rs)

Page 68: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 68

Amount (Rs)

Page 69: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 69

Amount (Rs)

Page 70: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 70

Amount (Rs)

Page 71: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 71

Amount (Rs)

Page 72: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 72

Amount (Rs)

Page 73: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 73

Amount (Rs)

Page 74: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 74

Amount (Rs)

Page 75: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 75

Amount (Rs)

Page 76: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 76

Amount (Rs)

Page 77: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 77

Amount (Rs)

Page 78: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 78

Amount (Rs)

Page 79: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 79

Amount (Rs)

Page 80: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 80

Amount (Rs)

Page 81: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 81

Amount (Rs)

Page 82: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 82

Amount (Rs)

Page 83: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 83

Amount (Rs)

Page 84: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 84

Amount (Rs)

Page 85: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 85

Amount (Rs)

Page 86: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 86

Amount (Rs)

Page 87: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 87

Amount (Rs)

Page 88: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 88

Amount (Rs)

Amount (Rs)

Page 89: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 89

Amount (Rs)

Page 90: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 90

Amount (Rs)

Page 91: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 91

Amount (Rs)

Page 92: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 92

Amount (Rs)

Page 93: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 93

Amount (Rs)

Amount (Rs)

Page 94: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 94

Amount (Rs)

Amount (Rs)

Page 95: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 95

Amount (Rs)

Page 96: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 96

Amount (Rs)

Page 97: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 97

Amount (Rs)

Page 98: 33788151 Rate Analsis Chapter No 8 Stone Masonary

Page 98

Amount (Rs)