Upload
khangminh22
View
1
Download
0
Embed Size (px)
Citation preview
Taking the Lead and Challenging the FutureTaking the Lead and Challenging the FutureTogetherTogether
Guidance Notes of GoodGuidance Notes of GoodContracting PracticeContracting Practice
ScoffoldingScoffolding
Offshore Offshore Contractors’Contractors’ AssociationAssociation
58 Queens Road58 Queens Road
Aberdeen AB15 4YEAberdeen AB15 4YE
TTelephone: 01224 elephone: 01224 326070326070
email: [email protected] email: [email protected]
www.oca-online.co.uk www.oca-online.co.uk
COPYRIGHT © 2002 OCACOPYRIGHT © 2002 OCA COPYRIGHT © 2002 OCACOPYRIGHT © 2002 OCA
INDEXINDEX
1. 1. IntInt rodurodu ction ction …………………………………………………………..………………………..………... ... 33
2. 2. RespResp onsionsi bilitibiliti es es …………………………………………………………………………………………. . 44
2.1 2.1 InitInit iator iator of of access access requiremrequirem ent ent .………….……………...……...……..4…..4
2.2 2.2 Scaffolding Scaffolding ForemForem an an …………………………………………….……….. ….……….. 44
2.3 2.3 Scaffold Scaffold / A/ Access ccess platplat form form user user …………….……….…………….……….55
2.4 2.4 Project Project Support Support (onshore & (onshore & offshore) offshore) …..…………..………….. ….. 55
3. 3. Risk Risk AssessmAssessm ent ent …………………………………………………………………… ……………… 77
3.1 3.1 InIn trodtrod uctiucti on on … … ……………………………………………………………… ……………… 77
3.2 3.2 ManMan ual ual HH andand lingling …………………………………………………………. ………………. 99
3.3 3.3 Raising Raising and and Lowering Lowering of of Materials Materials ……………………………1………100
4. 4. Fall Fall Arrest Arrest EqEq uipuip menmen t t ………………………………………………………...….. ………...….. 1212
4.1 4.1 InspInsp ection ection and use and use of of Fall Fall ArreArrest st EquEqu ipment ……ipment ……... ... 1212
4.2 4.2 Working Working at at HH eigheigh t t ………………………………………………………….. ………….. 1313
4.3 4.3 NNASC ASC GuidGuid ance ance NNote ote SG4:00 SG4:00 …………………………………………… … 1515
4.4 4.4 RescuRescu e e Plan Plan ……………………………………………………………………….….1……….….166
5. 5. ConvenConven tiontion al al Scaffolding Scaffolding …………………………………………….………….….………….1717
5.1 5.1 Scaffolding Scaffolding TuTu be…………………………………be……………………………………. …. 1717
5.2 5.2 Scaffold Scaffold Board Board …………………………………………………………………. ……………. 1818
5.3 5.3 FitFit ting ting : : DouDou ble ble CoupCoup ler ler …………………………………………………. ………. 1818
5.4 5.4 FitFit ting ting : : Single Single CoupCoup ler ler ……………………………………………………... ……... 1919
5.5 5.5 FitFit tintin g g : : Swivel Swivel CoupCoup ler ler ………………………………………………….. ……….. 1919
5.6 5.6 FitFit ting ting : : Sleeve Sleeve CoupCoup ler ler …………………………………………………….. …….. 2020
5.7 5.7 FitFit tintin g g : : Base Base PlatPlat e e ………………………………………….…………… .…………… 2020
5.8 5.8 FitFit ting ting : : Gravlock Gravlock ………………………………………………………… ……………… 2121
5.9 5.9 FittinFittin g g : : Band Band & & Plate Plate ……………………………………………...………...……. 2. 211
5.10 5.10 TimTim ber ber Pole Pole LadLad der der ……………………………………………………… …………… 2222
5.11 5.11 LighLigh tweightweigh t t PlatPlat form form StaginStagin gs gs …………………………………………. . 2222
5.15.12 2 Ladder / UnLadder / Un it it (Lattice ) (Lattice ) Beams …Beams ………………………………. ………. 2323
5.13 5.13 TypeType s s of of Scaffold Scaffold StructStruct ure ……ure ………………………………………………. . 2424
COPYRIGHT © 2002 OCA
5.14 Desi gned Scaffold Struct ures ………………………. 29
5.15 Scaffolds Requiring Design En gineering Inp ut ……29
5.16 Ladd er Access ……………………………………….. 30
5.17 Life Duratio n of Erected Scaffold ………………….. 36
6. Oth er Access Systems …………………………..………... 37
6.1 Syste m Scaffold ……………………………………… 37
6.2 Alumini um/ GRP Tower Systems ………………….. 38
6.3 Mechanical Elevated Work Platforms
(mechanica l mobile plant) …………...……………...40
6.4 Rope Access …………………………………………. 40
7. Mater ial Storag e …………………………………..………. 41
7.1 Insp ection & Storage of Scaffold Material ………….41
7.2 Insp ection Details : Scaffold Fittin g ……………….. 42
7.3 In spect ion Deta ils : Scaffold Board ……...………….42
7.4 Insp ection Details : Scaffold Tub e ………………….43
7.5 Insp ection Details : Pole Ladder …………………… 43
7.6 Illus trat ion of Rack Capa city ……………………….. 44
7.7 Tube & Fit ting Self Weight s…………………………45
8. Inspect ion & Taggin g ………………………….………… 46
8.1 Insp ection / Taggin g ………………………………..46
8.2 In spect ion Tags ...…………………………...……….48
9. Oversid e Working ……………………………..…………. 49
9.1 Rest rictio ns ………………………………………….. 49
9.2 Manning …………………………………….……….. 49
10. Comp etence & Trai ning ………………………………….. 50
11. Legisla tion and Referen ces ………………………………. 51
12. Cont ribu tors ………………………………………………. 54
COPYRIGHT © 2002 OCA
COPYRIGHT © 2002 OCA
Bill AbbottThe Rigblast Group Lt d
Steve Black Salamis (Marine & Industrial) L td
Joe Bogan
SGB Powerchem
Keith McMillan
Cape Industrial Services L td
Graham Morrison
H ealth and Safety E xecutive
Doug Sheal
Salamis (Marine & Industrial) L td
Robin McKenzie
The Rigblast Group L td
Gail AmeyOffshore Contractors A ssociation
COPYRIGHT © 2002 OCA
1. INTRODUCTION
Member companies of the Offshore Contractors Association (OCA) provide
scaffolding access services to the Offshore Oil and Gas industry.
Over the years various means of access have been introduced into the
offshore oil and gas industry, including system scaffolding, aluminium
scaffolding and roped access. This document is intended as guidance for
member companies, their clients and contractors as to the various types of
access available. Advice as to the appropriateness of particular access
systems should be sought from those member companies of OCA, which
provide access services.
Scope
This guidance is intended for the users and providers of temporary access
systems on oil and gas installations operating on the United Kingdom
Continental Shelf. Additional risk assessment may be required for floating
installations.
Objectives
To provide guidance on types of temporary access available to companies
requiring access to work faces, which do not have permanent access.
To provide guidance on health and safety issues arising from the provision
and use of temporary access systems, such as risk assessment, manual
handling and overside working.
To list relevant legislation and other sources of information.
COPYRIGHT © 2002 OCA
2. RESPONSIBILITIES
The following is a broad set of responsibilities for the key positions in any
scaffolding / access environment . It is recommended that they be used as
the basis for the development of local rules that more specifically define the
key interfaces and responsibilities at a specific location.
2.1 Initiator of access requirement
For every scaffold / access platform erected there will be an initiator , who
will request the scaffold in order to comp lete a scope of work or service. The
initiator therefore has a number of responsibilities to fulfil to assist in the safe
and efficient erection of any access structure:
• Formally notify the Scaffolding Foreman of access requirement.
• Accurately define the scope of the access requirements, to assist thescaffolding contractor in ensuring that the structure is ‘fit for
purpose’ on erection.
• Ensure that reasonable timescales are provided to allow sufficient pretask planning and risk assessment to be carried out by the Scaffolding
Foreman.
2.2 Scaffolding Foreman
The Scaffolding Foreman / Chargehand will be the central focus for all
access activities. This ensures that one central point is utilised to co-or dinate
all aspects of access management, reducing risk and increasing efficiency.
The following responsibilities ensue:
⇒ Arrange appropriate Permit to Work compliance at all times.
⇒ Co-ordinate the completion of task risk assessments and toolbox
talks to relay information and instructions to the working party.
⇒ Ensure that any potential conflicts of activities are addressed during
the pre job planning.
⇒ Request Design Engineer assistance if access requirements are not
within the parameters of BS5973 or the company’s Technical
Manual.
⇒ Ensure that sufficient materials are readily available to complete
workscopes.
⇒ Allocate personnel to the task ensuring competencies and numbers
are sufficient to complete tasks safely.
⇒ Handover completed scaffold structure to initiator / end user.
⇒ Ensure that a competent person is available to conduct statutory 7-
day inspections and to maintain the inspection tags and scaffold
COPYRIGHT © 2002 OCA
This recent Directive is expected to be incorporated into UK law by
2004 by amending the regulations to describe a preferred hierarchy
of access systems as between scaffolding, ladders and rope access
and the arrangements for their use. Compliance with the minimum
requirements is designed to ensure a better standard of health and
safety for workers in the use of work equipment provided for
temporary work at a height.
10. Oth er Applicable Regulation s include:
⇒ Control of Substances Hazardous to Health Regulations
1994 (COSHH ). These require employers to protect
workers’ hearing form exposure to noise at work.
⇒ Noise at Work Regulations 1989 (NAWR). These require
employers to protect workers’ hearing from exposure to
noise at work.
⇒ Electricity at Work Regulations 1989 (EAWR). These
require employers, employees and self-employed workers to
prevent risks of injury from electrical equipment and
systems.
11. Step Change in Safety Task Risk Assessment Guide.
This document gives comprehensive guidelines of the completion of
task risk assessment.
12. CONTRIBUTORS
COPYRIGHT © 2002 OCA
5. The Reporting of Injuries, Diseases and Dangerou s
Occurrences Regulations 1995 (RIDDO R)
These require employers to notify certain injuries, diseases and
dangerous events.
6. The Manual H andling Operation s Regulations 1992
These require employers to assess and control the risks to their
employees from manual handling. The employer should avoid the
need for hazardous manual handling, assess the risks of injury from
manual handling that can not be avoided and reduce the risks of
injury, as far as reasonable practicable.
7. Lifting Operations and Lifting Equ ipment Regulations 1998
(LOLER)
LOLER require that where the scaffolding is erected using lifting
equipment the equipment is strong and stable enough for the
particular use and marked to indicate safe working loads, positioned
and installed to minimise any risks, used safely ie the work is
planned, organised and performed by competent people and subject
to ongoing thorough examination and inspection by competent
people.
8. Offshore Installations (Safety Case) Regulations 1992
The primary purpose of these Regulations is to reduce risks to the
offshore workforce from major accident hazards, It also requires
arrangements to be in place for the verification of safety critical
elements and to show that risks are as low as reasonably practicable
(ALARP). Where scaffolding offshore is left in place for any length
of time, for example, the effects of increased congestion in
increasing blast overpressures may need to be considered.
9. Temp orary Work Act H eight Directive 2001
COPYRIGHT © 2002 OCA
⇒ Make adequate provisions available (labour) for the safe dismantle of
access structures.
⇒ Follow local rules relating to ‘adverse weather’ policy.
2.3 Scaffold / Access platform user
To ensure that th e scaffolding / access platform is maintained to as safe a
standard as practical, the user has these key responsibilities:
⇒ Conduct a task risk assessment (TRA) for the activities to be carried
out o n th e scaffolding structure.
⇒ Identify and manage any conflicting activities that occur when using the
scaffolding / access structure.
⇒ Ensure that t he scaffold is ‘fit for purp ose’ for the intended workscope.
Any alterations to t he structure should b e requested to t he scaffolding
foreman.
⇒ Notify the scaffolding foreman of any changes to the scaffold due to
weather, damage or collision.
⇒ Maintain a high level of housekeeping / tidiness whilst working on the
access platform and when leaving the worksite unattended.
⇒ Formally notify the scaffold foreman when work on scaffold has
ceased, ensuring the access platform is left in an acceptable condition.
2.4 Project Support (onshore & offshore)
Project support function provides technical support to the scaffolding
foreman to carry out their duties. Responsibilities include: -
⇒ Providing a Safe System of Work, in conjunction with the client.
⇒ Ensuring that the quality of the equipment supplied for erecting the
scaffold / access structures meets the relevant standards.
⇒ Providing the Scaffold Foreman with suitably trained and competent
personnel to complete the workscopes safely.
⇒ Providing access to competent design engineers.
COPYRIGHT © 2002 OCA
Flowchart of Key Responsibilities.
Initiator Requests
Scaffold access
Scaffold foreman
Surveysworkscope
Scaffold Register &Inspection Tag
maintained
Request designdrawing from Design
Engineer
Does scaffoldrequire a design?
(I.e. outwith theparameters of
BS5973 orTechnical Manual)
RequisitionMaterials
Scaffold inspectedby a competent
person
Erect Scaffold
Handover to enduser
StatutoryInspection
Job complete,
scaffold foremannotified to
dismantle scaffold
No
Yes
Develop a designdrawing
Initiator Requests
Scaffold access
Scaffold foreman
Surveysworkscope
Scaffold Register &Inspection Tag
maintained
Request designdrawing from Design
Engineer
Does scaffoldrequire a design?
(I.e. outwith theparameters of
BS5973 orTechnical Manual)
RequisitionMaterials
Scaffold inspectedby a competent
person
Erect Scaffold
Handover to enduser
StatutoryInspection
Job complete,
scaffold foremannotified to
dismantle scaffold
No
Yes
Develop a designdrawing
COPYRIGHT © 2002 OCA
OCA Revision of Offshore Scaffold Guidance Regulations
1. H ealth and Safety at Work etc. Act 1974 (H SW Act)
This act covers nearly all the safety regulations in Great Britain both
onshore and offshore (see below). The Act places general duties on
employers to ensure, so far as is reasonable practicable, the health
and safety of their employees and others who may be affected by
their undertaking (HSW Act sections 2 and 3). Th ese general duties
are supported by the specific requirements of the supporting
Regulations.
2. Application Outs ide Great Britain Order 2001 (AOGBO)
This order is an amendment of the earlier Order that applies most of
the regulations made under the HSW Act to offshore installations,
pipeline works and connected activities in the territorial waters
outside the mainland of Great Britain. As well as these general
regulations, there are also some offshore-specific regulations made
under the Act.
3. Management of H ealth and Safety at Work Regulations 1999
(MH SWR)
These contain general duties to carry out risk assessment, undertake
appropriate health surveillance and arrange appropriate information
and training for employees.
4. Provision and Use of Work Equ ipment Regulations 1998
(PUWER)
PUWER contains general duties covering the selection of suitable
work equipment and its maintenance and information, training and
instruct ion for workers. The equipment to which PUWER applies is
wide, covering mobile equipment such as scaffolding as well as fixed
plant. PUWER also cover the control of hazards such as instability
and contact with dangerous parts of machinery and hot and cold
surfaces.
COPYRIGHT © 2002 OCA
requisite skills, knowledge and understanding to enable them to perform
their work tasks to an appropriate standard, and also ensures that those skills
are maintained and enhanced.
A competency process ensures that:
♦ Competent persons are employed
♦ Evidence of competency can be provided to the client
♦ Evidence of competency can be provided to the regulatory
authorities
♦ Training needs are identified and appropriate training programmes
implemented
It is acknowledged that, whilst training imparts knowledge, the employee
must be given the opportunity to put this knowledge into practice, in order
to develop the requisite skills and achieve the standard required in the work
place.
Failure by management to provide a safe system of work, and failure by
employees to adhere to procedure, may result in serious injury.
It is recommended that employers have in place procedures for the erection
and dismantling of scaffold structures. Section 11 of this guidance contains
further references to legislation, standards and codes of practice relating to
access.
It is recommended that scaffolders hold a recognised qualification, which
demonstrates the level of skills and competence attained, through training
and examination. The Construction Industry Training Board, CITB, is the
lead body in the provision of scaffold training. The Engineering
Construction Industry Training Board (ECITB) is also a recognised body,
which provide scaffolding qualifications based on continuous assessment and
competency. It is further recommended that employers have in place a
programme of continuous assessment, in order to demonstrate t hat skills are
maintained and training needs identified.
Recommended Training
11. LEGISLATION & REFE REN CES
Scaffolder (CITB) Basic & Advanced
Inspector (CITB) Advance or Inspectors
Scaffolder
Helper
(In-house) Scaffold Awareness, Compon ent Ident ification
Manual Handling, Material Quality, etc.
COPYRIGHT © 2002 OCA
3. RISK ASSESSME NT
3.1 Introduction
A scaffolding activity risk assessment together with a task based risk
assessment must be carried out prior to the erection or dismantling of a
scaffold and must involve the persons carrying out the task. (See Risk
Assessment Flow Chart).
The control room via the permit to work system must ensure that all hazards
in the area of the task location are clearly identified and communicated to
the persons carrying out the t ask.
The success of a Task Risk Assessment will depend on the method of
communication to the workforce. Those carrying out the task must be fully
aware and thoroughly understand, the hazards and the precautions put in
place. Open two-way dialogue should take place at a meeting prior to
starting the task, these meetings are referred to as toolbox talks.
The toolbox talk should fulfil four functions:
1. Give everyone involved in the task a thorough understanding of the
activity details involved in the task, both their own and that of
others. The potential hazards should be identified for each stage of
the task.
The control measures to be put in place to mitigate the hazards and
the individual actions and responsibilities at various stages of the
task should be established for each specific project.
2. Provide the opportunity for those involved in the task to identify
any further hazards and control measures which may have been
overlooked in the initial assessment.
3. Reach agreement of the whole work team on whether or not to
proceed with the task. If agreement cannot be reached, THE JOB
SHOULD NOT BE STARTED.
4. Make clear to all involved that should conditions or personnel
change or assumptions made when planning the job prove false,
they should re-assess the situation and, if in any doubt, THE JOB
SHOULD BE STOPPED.
For these reasons a toolbox talk should be held at or near the worksite, and
should include all people involved in the work and those who may be
affected by it.
COPYRIGHT © 2002 OCA
When new team members join the team, the same communication should be
given to them.
Once the team is satisfied that all hazards have been identified and that
suitable controls have been put in place to reduce the risk to an acceptable
level, they can then undertake the task.
Risk Assessment Flow Chart
Break tasks into component parts to
identify activities to be assessed
Identify who hazards could affect
Using risk ratings – determine level
of risk
Is risk significant?
Identify and evaluatecurrent control measures
Identify any hazards
Is significant risk already
adequately controlled?
Is significant risk already
adequate ly controlled?
Review/ revise existing control m easures
or identify/ implement new preventative
and protective measures
Evaluate controls
Is risk now acceptable?Is risk now acceptable?
Implement controls
Record findings of risk assessment
and set d ate for review
Monitor and review
yes
yes no
no
noyes
Break tasks into component parts to
identify activities to be assessed
Identify who hazards could affect
Using risk ratings – determine level
of risk
Is risk significant?
Identify and evaluatecurrent control measures
Identify any hazards
Is significant risk already
adequately controlled?
Is significant risk already
adequate ly controlled?
Review/ revise existing control m easures
or identify/ implement new preventative
and protective measures
Evaluate controls
Is risk now acceptable?Is risk now acceptable?
Implement controls
Record findings of risk assessment
and set d ate for review
Monitor and review
yes
yes no
no
noyes
COPYRIGHT © 2002 OCA
The guidance below has been developed to act as a checklist of activities that
require to be considered and/ or actioned when working overside:-
• Valid Permit to work is available for the task in hand
• Task specific risk assessments are conducted for each individualoverside job. “Take 5 principles” are encouraged as the mechanism to
address any changes to the workscope.
• Stand-by vessel is available at all times when working overside.
• Radio contact is maintained with the stand-by vessel at all times.
• Fall arrest system is in place including training to the scaffoldingoperatives, rescue arrangements for working overside to be detailed on
a rescue plan.
• Twin chamber, self-inflating lifejackets are worn at all times whenworking overside.
• Any overside scaffold that is outwith the parameters of BS 5973 and/ orcompany technical manuals, is designed by a competent design
engineer.
• Weather restrictions are advised by the standby vessel captain.
Overside working during the hours of darkness will only be undertaken in
EXTREME emergency situations and with a suitable & sufficient task risk
assessment in place.
9.2 Manning
Recommended minimum manning for overside scaffolding works:-
• Two competent scaffolders overside
• One competent scaffolder providing materials for overside workers.
• One competent radio operator. (Must have valid training on the radiocommunication equipment on board)
10. COMPETE NCE & TRAININ G
A competency and training process ensures that employees have the
COPYRIGHT © 2002 OCA
9.1 Restrictions
COPYRIGHT © 2002 OCA
3.2 Manual Handling
The manual handling of scaffold components on offshore oil and gas
installations is commonplace because of restricted access for mechanical
handling aids. In practice, this results in scaffold components being man-
handled from storage racks to worksites, often at different levels on the
installation and often, at outside locations, in inclement weather e.g. high
winds. Manual Handling risks can be reduced by the use of lightweight
system scaffold, where feasible (see section 6). The manual handling
operations regulations apply to all employers in respect of their employees at
work and others who may be affected. Manual handling operations are
defined as the transporting or supporting of any load, including the lifting,
putting down, pushing, pulling, carrying or moving by hand or bodily force.
The scaffolding service provider shall, so far as is reasonably practical, avoid
the need for his employees to undertake any manual handling operations at
work, which involve a risk of personal injury.
Risk assessment shall identify whether mechanical handling aids (e.g. crane)
can be used. Where mechanical handling aids cannot be used, the employer
shall:
a) Make a suitable and sufficient assessment of the manual handling
operations to be un dertaken
b) Take appropriate steps to reduce the risk of injury to those
employees arising out of manual handling operations
c) Take appropriate steps to provide those employees who are
undertaking any manual handling operations general indications,
and, where it is reasonably practical to do so, precise information on:
• The task to be carried out
• The weight of each load/ component
Attention to the ergonomic design of th e workplace is an important factor in
controlling the risks associated with manual handling.
Appropriate manual handling training should be provided for all personnel
involved in the erection/ dismantling of scaffold structures. The training
should address:
4 How to recognise harmful manual handling
4 Appropriate systems of work
4 Use of mechanical aids
4 Good handling techniques