- P14315 UPDAS DETAILED DESIGN REVIEW INTRO/AGENDA CART
DESIGN/LAYOUT CONNECTIONS LAYOUT ENCLOSURE LAYOUT WIRING DIAGRAMS
POWER CONSUMPTION PLC PROGRAMING TIMING CALCULATIONS ANALYSIS
SOFTWARE BUDGET ANALYSIS BILL OF MATERIALS MSD II SCHEDULING
- Slide 2
- UPDAS CART DESIGN/LAYOUT 404 product not found
- Slide 3
- SENSORS LISTED Sensor TypeManufacturerPart NumberQuantityUse
Gage Pressure TransducerOMEGA ENGINEERINGPX359-200GI1 Measures
Discharge Pump Pressure Vacuum Pressure Transducer OMEGA
ENGINEERINGPX459-015GI1Measures Suction Pump Pressure
FlowmeterYOKOGAWA USAXF005C2 Measures Pump Suction/Discharge Flow
Stick-On ThermocoupleOMEGA ENGINEERINGSA1-T-SC9 (5 in Use. 4 as
Spare) Measures Various External Temperatures Probe
ThermocoupleOMEGA ENGINEERINGTMQSS-062U-63 Measures
Ambient/Discharge Fluid/Internal Enclosure Temperatures Level
SensorOMEGA ENGINEERINGLVH-2003 Checks for Empty/Low/Overflow Water
Levels
- Slide 4
- CONNECTION LAYOUTS
- Slide 5
- ENCLOSURE LAYOUT
- Slide 6
- SYSTEM OVERVIEW The schematic and system overview drawings are
available here (pdf) and here (orcad)here
- Slide 7
- MAIN ENCLOSURE
- Slide 8
- E-STOP ENCLOSURE
- Slide 9
- POWER SUPPLY ENCLOSURE
- Slide 10
- POWER CONSUMPTION
- Slide 11
- PLC PROGRAM FLOWCHART
- Slide 12
- PLC MEMORY LAYOUT Ladder logic requires address referencing The
memory layout will show the allocation for all addresses
(variables) used in the PLC program Full details here (pdf) and
here (Excel)here
- Slide 13
- PLC GUI Used for initial setup and for starting sampling All
screens available here (pdf) and here (Cscape project)here Sample
user input screenPost-setup screen
- Slide 14
- FAULT CODES The means of communicating failure events to the
analysis program o Examples: Out-of-bounds measurements Loss of
communications User-initiated stops The full list is available here
(pdf)here Number of Values from VFD: 5 VFD Delay (ms): 8 Safety
Factor (ms): 2 Minimum Time per Sample (sec): 0.042 Maximum Sample
Rate (Hz): 23.8 Timing Calculations
- Slide 15
- ANALYSIS SOFTWARE (EXCEL) Load.csv filesCalculate needed values
Hydrodynamic Power Efficiency Slip Generate graphs Pump Degradation
Flow Curve All measured values over time
- Slide 16
- TEST PLAN Adjusted to better follow the MSD format Available
here (pdf)here
- Slide 17
- BUDGETING ANALYSIS Budget Analysis can be found here.
(pdf)here
- Slide 18
- BILL OF MATERIALS Bill of materials can be found here.
(pdf)here
- Slide 19
- MSD II SCHEDULING Jan. 13, 2014: World ends. Jan. 14, 2014: ???
May 23, 2014: Profit.
- Slide 20
- FINAL QUESTIONS? Questions? Comments? Thoughts of great
concern?
- Slide 21
- THANK YOU FOR YOUR TIME! The POWER of UPDAS