STADIUM SUPPLIES
• Stadium and Precinct supplies complete• Precinct lighting due for completion mid April• Gas Turbine - Operational (Test runs conducted
regularly)• Fettes Rd nearing completion, risk of cable damage
minimised• Gelvandale Training venue electricity supply
complete
2010 PREPAREDNESS
• Telecomms– Communication conducted by means of 2-way radio,
cellphone, Telkom.– Repeaters for Radio serviced regularly, back up generation
for Repeater sites
• IT Support– Contingency plan in place, system upgraded– Back up generation available for IT Network (UPS, standby
generator)
2010 PREPAREDNESS Cont.
• Communications– Radio comms between System Operations and Disaster
Management and Eskom Control (ELS)– Telkom– Cell phones
• Security– Contingency plans in place (Security NMBM, Eskom)– Securing of major substations (listing)
2010 PREPAREDNESS Cont:
• Disaster Management– In place (Fire Services Building), contingency plan in place– Electricity & Energy not part of DM, will however attend
de-briefing sessions on daily basis due to 24hr System Operations Centre
– Key personnel identified
• Personnel– All personnel to be available during exclusive period– Persons to be despatched to key sites (eg Substations, etc)
on match days– Roster in place for exclusive period