Upload
informa-australia
View
683
Download
0
Embed Size (px)
DESCRIPTION
Graeme Robertson, Head of Operations – UK, Sulzer Dowding & Mills delivered this presentation at the 2013 Gas Turbines conference. The event is designed as a platform for discussion on the latest technologies & developments in gas power generation. For more information on the annual event, please visit the conference website: http://www.informa.com.au/gasturbinesconference
Citation preview
Sulzer Turbo Services
GasTurbine Conference , Brisbane, October 2013
Graeme Robertson – Head of Operations UK
Sulzer Dowding & Mills
| slide 2
Sulzer Turbo ServicesLARGE HV MACHINE REPAIR OPTIONS
Repair to coil lead
Cutting coils out of circuit
Splicing in a coil side
Replace a failed coil [s] / bars
Complete rewind
| slide 3
Sulzer Turbo ServicesFACTORS TO BE CONSIDERED
Machine Specific
Secondary damage, core
loss or impact
Impregnation system
Type of winding
Age of winding
General Factors
Physical size & access
Impact on other operations
Production loss and outage cost
/ Budget Availability
| slide 4
Sulzer Turbo ServicesREPAIR TO COIL LEAD OR CONNECTIONS - 1
Simplest repair option if only one coil leg or connection is affected
Damage to adjacent coils increases the risk of repair escalating
Likely that secondary arc flash damage will be evident
Global VPI makes this process more difficult
| slide 5
Sulzer Turbo Services2.5MVA, 2 MW, 8 Pole, 11KV
Global VPI Impregnation
Lead Arc Flash Damage
| slide 6
Sulzer Turbo ServicesCUTTING COILS OUT OF CIRCUIT - 2
Will affect machine performance
Likelihood of reduced output
Excitation current will change
Out of circuit coils need to be isolated and insulated to prevent circulating
currents
Minimise air gap harmonics to minimise, noise, vibration, increased losses
In all cases Stator core requires to be fit for service as a result of failure
| slide 7
Sulzer Turbo Services12 MW 4 Pole 11KV Compressor Motor
Stator Winding Earth Fault
Damage to sidewall insulation
Failed with multiple failed coils and earths
| slide 8
Sulzer Turbo ServicesORIGINAL COIL CIRCUIT
| slide 9
Sulzer Turbo Services
Coils reduced from 72 to 66
1 coil splice repair
STAR connected with 2 parallel circuits.
Coils / Phase parallel path 12 to 11
10% increase in gap density
Rating reduced from 12MW to 9MW
Minimal outage time available, required for production
CUTTING COILS OUT OF CIRCUIT
| slide 10
Sulzer Turbo ServicesREDESIGNED COIL CIRCUIT
| slide 11
Sulzer Turbo ServicesREDESIGN MODIFICATIONS TO CONNECTION RING
Connections of coils taken out of circuit
New Coil to Coil Connections@ Conn Ring
| slide 12
Sulzer Turbo ServicesMODIFICATION TO NON CONNECTION END COIL
Cut Coil Knuckle@ Non Conn End
Cut Coil Isolated & Insulated
| slide 13
Sulzer Turbo ServicesSPLICE IN COIL SIDE - 3
Straight forward with top coil side, can be achieved on bottoms legs
Must maintain strand continuity
Must maintain strand, turn & ground insulation levels
Must maintain coil bracing, coil to coil, coil to support arm
Must not restrict airflow – staggered scarfing
| slide 14
Sulzer Turbo Services
Slot Cleaning is critical
Care taken to avoid damage to adjacent coils
SPLICE IN COIL SIDE
Lift Centre strip packing
Vacuum to remove all debris before, repacking and wedging
| slide 15
Sulzer Turbo ServicesSTAGES OF SPLICING IN COIL
| slide 16
Sulzer Turbo Services
No change in performance
Easier with half bars, diamond coil requires care / process
Must lift all coils in coil pitch [Diamond]
More coils lifted for WAVE winding
Depends upon condition of original winding, evolute / nose stress
Very difficult for global VPI windings, hard coil cells, prone to cracking
during removal
REPLACE A FAILED COIL / BARS - 4
| slide 17
Sulzer Turbo Services120 MW 2 Pole 13.8KV Gen
Connections un-brazed to allow bar testing and subsequent removal
Stator bar being jacked out of slot
| slide 18
Sulzer Turbo Services120 MW 2 Pole 13.8KV Gen
| slide 19
Sulzer Turbo Services
Secondary Epoxy Injected
Replace Failed Coil
| slide 20
Sulzer Turbo Services120 MW 2 Pole 13.8KV Gen
Significant number of top bars [25] which had to be removed
Finished stator with bracing and blocking all restored, new connection caps fitted
| slide 21
Sulzer Turbo ServicesREPLACE FAILED COIL
Stator bar being jacked out of slot, note the use of multi point jacking, the fit of coil and VPI system meant that the coil had to be drilled and tapped to facilitate removal without damage to core
| slide 22
Sulzer Turbo Services
Performance maintained or Increased
If possible engineer out the previous failure mechanism – [ increase
interturn or sidewall insulation]
Restores Winding & Bracing system to new condition
Winding is a ‘consumable’ of a Motor or Generator, has a life span, which is
determined by loading / cycling / starts /environmental conditions /
maintenance procedures
New Windings will obviously extend the machine expected lifespan
FULL STATOR REWIND - 5
Sulzer Dowding & Mills 2013 <Copyright © Sulzer> | slide 23
Sulzer Dowding & MillsProduction Platform – Generation Problems
Sulzer Dowding & Mills 2013 <Copyright © Sulzer> | slide 24
Sulzer Dowding & MillsOverview
Total generation capacity of 35MW
GT 4 was to be returned to Service after period of inactivity, this was a 15MW, 6.6kv, 4 pole Generator driven by an Avon Engine
Provided critical power for Sea Water Injection Pump motors
Platform required SWI Pump Motors running to support production
Module Roof was not watertight !
Generator Anti-Condensation Heaters were defective !
Sulzer Dowding & Mills 2013 <Copyright © Sulzer> | slide 25
Sulzer Dowding & MillsBringing back to service…
Pre-commission checks identified very low IR and no PI.
1000v DC Test IR value 0.2MΩ & breaking down after 4 minutes
As our engineers were being mobilised to site, platform staff spun the turbine generator for a period of 4 hours unexcited to determine if dampness / condensation was the issue.
Retest did not show any difference in the IR or PI levels
Complete winding was wet with an earth fault present
Sulzer Dowding & Mills 2013 <Copyright © Sulzer> | slide 26
Sulzer Dowding & MillsInvestigating the problem
Our Service Engineers then carried out a methodical check:
opened alternator for internal inspection of rotor / stator for any evidence of ingress of contamination
cables and all connections from the cubicle to the alternator terminal box, removed all clamps / post connections
disconnected the star point / split phase connections
split low reading phase coils to form 2 halves for inspection & test
continue to split until defective coil or coils were located
identify the defective area / coil section
Sulzer Dowding & Mills 2013 <Copyright © Sulzer> | slide 27
Sulzer Dowding & MillsThe Defective Coil
The defective coil was identified by a process of elimination, and located at 4 o'clock position when viewed from DE, fault was specific to one diamond coil.
The stator winding had 66 coils connected in 2 parallel circuits
The winding had 5 & 6 coil groups
We proposed an in-situ repair potentially saving 16 weeks on time scale and circa £700k on rewind costs
A primary objective was to minimise outage time to get SWI pumps operating ASAP.
Sulzer Dowding & Mills 2013 <Copyright © Sulzer> | slide 28
Sulzer Dowding & MillsThe Turbo Generator
Generator with end covers partially removedto expose Stator Winding
Sulzer Dowding & Mills 2013 <Copyright © Sulzer> | slide 29
Sulzer Dowding & MillsSource of the Problem
Generator Stator Coils ready for splitting to locate defective coil
Sulzer Dowding & Mills 2013 <Copyright © Sulzer> | slide 30
Sulzer Dowding & MillsWinding Modification
4 pole 3 Phase Generator
66 Slots & 66 Coils
2 Parallel Circuit Star
12 Coil Groups 5 coils & 6 Coils
2 Coil Groups in each parallel path 1 with 5 coils the other with 6 coils
Failed coil 2nd in 6 coil group
Sulzer Dowding & Mills 2013 <Copyright © Sulzer> | slide 31
Sulzer Dowding & MillsWinding Modification
4 pole 3 Phase Generator
66 Slots & 60 Coils
2 Parallel Circuit Star
12 Coil Groups all 5 coils
Sulzer Dowding & Mills 2013 <Copyright © Sulzer> | slide 32
Sulzer Dowding & MillsOur Solution..
We calculated what would be the effect of cutting out 6 coils, 2 per phase, on the performance of the Generator
It was necessary to take 2 coils from each phase, to prevent circulating currents and kept the winding balanced
We assessed that a maximum 10 % loss of output would result in changes
Results were relayed to Client who approved the process and methodology of repair.
Sulzer Dowding & Mills 2013 <Copyright © Sulzer> | slide 33
Sulzer Dowding & MillsThe Completion..
Work was completed in 14 Days utilising 24 hr working :-
The generator was part dismantled, rotor remained in position An environmental habitat was erected around the stator Stator winding configuration was changed and reconnected,
the defective coil and 5 other coils removed from circuit. Stoving heaters were applied to dry the rest of winding The stator winding was cleaned, dried, and spray varnished The machine was fully built and prepared for test
Generator returned to service with slow increase of load from 2 MW to 7MW over a shift and then up to 13.8MW
Machine was handed back to client after successful commissioning test, with some alterations to protection relays and AVR settings.
Sulzer Dowding & Mills 2013 <Copyright © Sulzer> | slide 34
Sulzer Dowding & MillsConclusion
Drilling Program was at risk due to lack of generation capacity
Failure to complete the ‘well work-over’ in time put the complete well at risk, including future oil revenues
Failure to provide power for the SWI Motors would result in loss of oil production
Generator Repair saved 16 Weeks of down time and circa £700k
Generator operating satisfactorily 15months later
Sister 15MW generator rewound this year
Scheduled to return 2014 to rewind this generator
| slide 35
Sulzer Turbo ServicesBEST PRACTICES – SITE WORKING
LOCAL SITE CONDITIONS REQUIRE
Simple enclosure to create clean room
Controlled environment with some or all of:-
Air Conditioning De-humidifiers Heaters Work platforms Positive pressure Air Filtration Lighting Power outlets Tool storage
MITIGATING FACTORS
Remote Locations
Temperature & Humidity
Effects of high altitude
Hazardous Atmospheres
Noxious fumes
Political Situation (Risk)
| slide 36
Sulzer Turbo ServicesBEST PRACTICES - STATOR WORKS
Stator core fit for 20-30 years
Fit of coil in slot
Resistance between coil & stator core
Tightness of wedging / size and position of ripple springs
Stress grading tape in correct position
Blocking & bracing of coil in endwinding
Continuity of sub-conductors
Insulation integrity / quality of coil / bar
| slide 37
Sulzer Turbo Services
ConductingMiddle Strip
Bottom Coil Side
Wedge Top Packing
Top Coil Side
BEST PRACTICES – STATOR SLOT FILL
Conducting Vetronite
| slide 38
Sulzer Turbo ServicesBEST PRACTICES - STATOR CORE
Test by power flux test or El-Cid method
Ensure tightness of lamination packs and cleanliness
Condition of air vents and security of duct spacers
| slide 39
Sulzer Turbo Services
For tight fitting wedges max length 8”
Staggered under wedge packing
BEST PRACTICES – STATOR WEDGING
| slide 40
Sulzer Turbo Services
Insulation Scarf Joint
Good scarfing of joints and staggering of scarfs
Avoid local build ups of insulation which would restrict air flow paths
BEST PRACTICES – STATOR SCARFING
| slide 41
Sulzer Turbo Services
Maintain end winding blocking & bracing, maintain coil spacing
Ensure adequate clearances;
between coils
between connections
and to earth
Ensure adequate separation between phase coils
6.6kV 5.5mm 0.22”
11.0kV 8.0mm 0.32”
13.8kV 10.0mm 0.40”
BEST PRACTICES – STATOR BRACING / BLOCKING
| slide 42
Sulzer Turbo Services
Winding Tests
DC resistance
Insulation resistance
Polarisation Index
Voltage withstand AC or DC
Tan Delta
Partial Discharge
BEST PRACTICES – STATOR TESTING
| slide 43
Sulzer Turbo ServicesBEST PRACTICES – ROTOR REWINDING ON SITE
Two Options
New Rotor Copper
Utilising Original Copper
Removal of old insulation Validate forging Renew all slot, end-winding and under retaining ring insulation Reinsulate and rewind Maintain all symmetry of blocking & bracing Refit all fan blades and auxiliaries in original position Balance weights all accurately recorded and refitted Minor trim balancing may be required
| slide 44
Sulzer Turbo ServicesBEST PRACTICES – ROTOR REWINDING ON SITE
When rewinding Rotor >100MW we would recommend high speed balancing which usually cannot be achieved on site.
Similarly when fitting new retaining rings, we would also recommend high speed balancing to ensure the correct balance condition at speed and also to ensure settlement of the rings
| slide 45
Sulzer Turbo ServicesHIGH SPEED BALANCING FACILITY
Sulzer Dowding & Mills 2013 <Copyright © Sulzer> | slide 46
Sulzer Dowding & MillsQuestions ?
Thank you for your attention,