Upload
terje-saebo
View
53
Download
0
Embed Size (px)
Citation preview
Project Assurance
Terje M. SæbøPartner, Considium Consulting Group
Make sure your projects deliver as expected
Project Assurance:- building the organization's capability to identify and resolve issuesto improve predictability and results in project execution.
• Lack of accountability and ownership for project goals and milestones in project team
• Weak alignment and interaction between project and organisation, customer, partners, suppliers and within sub-projects
• Do not look ahead and/or reacts to slow or to weak to remove barriers or to exploit opportunities
• Reporting process is backward looking and characterized by explaining deviations
• Steering and learning are separate processes
– Too little learning between project managers causes same problems in several projects
• Project Execution Models too complex, bureaucratic and detailed
– Based on control paradigm, fear of failing
– Kills accountability, speed, flexibility and use of professional knowledge
• Projects in trouble get “management help” that does not add value, but adds to the burden
– Extra reviews and reporting, audits, task forces
• Steering comities overlaps established management structures – who takes the required decisions?
Why do projects struggle to meet result expectations
Project Status Reporting: Explaining past and status
FuturePast
Activities
“It’s like being in a courtroom where you are judged on past actions and events”(quote from a Project Manager)
ResultsWhyareyoubehind?
Project Assurance– from reporting and explanations to steering and actions/decisions
Future
ProjectGoals
Past
Results
Whatdoesittaketoachievemilestonesandgoals?
Activities
Purpose:To make sure the project(s) have control and will be successful
Deviations,risks&opportunities
Actions&decisions
Mile-stone
Mile-stone
Mile-stone
Both large projects & portfolios
Focusonresultsonprojectandportfoliolevel• Willtheportfoliodeliverasexpected?• Willtheprojectsdeliverasexpected?• Dependencies&prioritieswithinportfolio• Participants:ProjectManagers,PortfolioManager,
Linemanagement
Focusonresult&milestonesonworkpackage/sub-projectlevel• Willyoudeliveryourworkpackage’scriticalmilestonesandgoals?• Dependencies&prioritieswithintheproject• Participants:ProjectManagementTeam
ProjectAssuranceofProjects&Portfolio
Portfoliox
ProjectAssurancesub-projects/workpackages,
responsibilityareas
ProjectA ProjectB ProjectB
Comment:Portfoliomanageristhepersonresponsiblefortheportfolioresults.Insomeorganisations calledprogrammanagerorareamanager.
ProjectExecution
Two main elements
1. Steering platform• Setclearandcommittedgoals• DefinetheCriticalMilestonesasateameffort• Values&GroundRules
ProjectExecution
2. Project Assurance Meeting• Resultevaluationfuturecriticalmilestones&goals• Dynamicevaluationofrisks&opportunities• Getfeedbackandadvicefrommanagementand
colleagues• Actionsanddecisionstoresolvecriticalissues&
exploitopportunities
Project Dashboard – Project X (tailored for each client)
Goalachievement
Contribution forecast
Currentcontractvalue
Current LDexposure
LDcap[MNOK/%]
Risks[MNOK]
Opportunities[MNOK]
PotentialVORcontr.[MNOK]
Contingency[MNOK]
Deviation/Barrier/Opportunity Consequence Have done Will do/decisions needed Resp Due Date
Keyissuesthatneedstobeaddressed:
Keyfigures
Contribution:Target
Contribution:StretchTarget
OnTimeDelivery Quality Project
teamCustomerrelations
YES, will achieve goalYES, will achieve goal but currently behind or major risks presentNO, Will not achieve goal, decision required
Visual project managementEach project creates a critical milestone schedule
• Foreachnewproject:ProjectManagementteamdefineupcomingcriticalmilestones
• The milestone schedule is established as a joint effort by the Project Management team to build commitment and accountability
• The milestones are selected based on criticality, depending on contract, scope and customer
• Schedule should be updated every 6-12 months – depending on project need
Milestoneschedule Illustration
www.considium.no
<Project>, Critical Milestones (month, year)
Eng
inee
ring
Sup
ply
chai
n M
ater
ials
and
su
bcon
tract
ors
Man
u-
fact
urin
g
Milestone)E1)dd-mm-yy)
Ok) dd-mm-yy)
Milestone)E2)dd-mm-yy)
Ok) dd-mm-yy)
Milestone)S1)29-09-11)
Ok) dd-mm-yy)
Milestone)S2)dd-mm-yy)
dd-mm-yy)
MS)S4)dd-mm-yy)
dd-mm-yy)
MS)M1)dd-mm-yy)
dd-mm-yy)
MS)S3)dd-mm-yy)
Ok dd-mm-yy)
Start)Manufact.)dd-mm-yy)
dd-mm-yy)
MS)M3)dd-mm-yy)
dd-mm-yy)
Complete(dd-mm-yy)
dd-mm-yy)
MS)E3)dd-mm-yy)
dd-mm-yy)
MS)E4)dd-mm-yy)
dd-mm-yy)
Descrip@on)Pl.)date)
Forecast)
Be prepared and know your situation and outlook
Preparation
ProjectAssuranceMeeting
What are the key issues I need advice or decision on to achieve agreed results?What do I need to get out of the meeting?
Milestoneschedule
Progress&costreports
Projectgoals
Situationalassessment(engageyourteam)
Resultandrisk&opportunityevaluation.Proposeactions&
decisions www.considium.no
<Project>, Critical Milestones (month, year)
Eng
inee
ring
Sup
ply
chai
n M
ater
ials
and
su
bcon
tract
ors
Man
u-
fact
urin
g
Milestone)E1)dd-mm-yy)
Ok) dd-mm-yy)
Milestone)E2)dd-mm-yy)
Ok) dd-mm-yy)
Milestone)S1)29-09-11)
Ok) dd-mm-yy)
Milestone)S2)dd-mm-yy)
dd-mm-yy)
MS)S4)dd-mm-yy)
dd-mm-yy)
MS)M1)dd-mm-yy)
dd-mm-yy)
MS)S3)dd-mm-yy)
Ok dd-mm-yy)
Start)Manufact.)dd-mm-yy)
dd-mm-yy)
MS)M3)dd-mm-yy)
dd-mm-yy)
Complete(dd-mm-yy)
dd-mm-yy)
MS)E3)dd-mm-yy)
dd-mm-yy)
MS)E4)dd-mm-yy)
dd-mm-yy)
Descrip@on)Pl.)date)
Forecast)
www.considium.no
Project Dashboard - <project name> Goal%achievement%
Current%contract%value%
Current%LD%exposure%[MNOK]%
LD%cap%[MNOK/%]%
Risks%[MNOK]%
Opportuni@es%[MNOK]%
Poten@al%VOR%contr.%[MNOK]%
Con@ngency%[MNOK]%
7.7# 7.7#
Deviation/Risk/Opportunity Have done Will do/decisions needed Resp Due Date
Top%issues%that%need%to%be%addressed:%
Key%figures%
Contribu@on:%Forecast%
Contribu@on:%Stretch%Target%
Contract%Delivery%
Current%Delivery% Quality% HSE% Customer%
rela@ons%
[MNOK/%]# [MNK/%]# dd.mm.yy# dd.mm.yy# Customer#Acceptance# Zero#Accidents# Sa>sfied#
customer#
YES, will achieve goal
YES, will achieve goal but currently behind or major risks present NO, Will not achieve goal, decision required
The Project Assurance Meeting– early warning of bad news is second best to good
– milestones and/or results will NOT be achieved as agreed or not within time• What do you intend to do about it – and what decisions need to be taken?• What risks and opportunities do you see ahead – and what actions do these
require?• Do we as a team agree with the situation assessment?• Do you need help? How can the team contribute to find new solutions?
YES
NO
Will you achieve your results and milestones within time?
– milestones and results will be achieved within time• What risks and opportunities do you see ahead – and what actions do these
require?• Do we as a team agree with the situation assessment and the mitigating actions? If
not, put it on the table
Strict agenda stimulates feedback, learning and decisions
CheckoutYes/No PresentationofDashboardandfeedback Agendaitemsanddecisions
CheckoutYESorNO – "Willyouachieveyourresultsandmilestoneswithintime?"
• Write up answers on whiteboard
The goal of the meeting is to use the teams collective knowledge to make the required decisions that will turn a NO into a YES
• If YES, focus on risk
Eachprojectgoesthroughcriticalmilestonesanddashboardwithproposedactions/decisions(10min.)
Feedback and advice from the other participants
• Agree/disagree with assessment & proposed actions
• Suggestions on what to do (not questions)
• Take quick decisions
Issuesthatrequireamorethoroughdiscussionbeforedecisioniswrittenup
Prioritizeandgothroughtheagendapointstomakesuretherequireddecisionsaretaken
Summarizekeyactionsanddecisions
Evaluatemeeting
1 2 3
1
2
3
Issuefromprojectx
Crossprojectissue
www.considium.no
Project Dashboard - <project name> Goal%achievement%
Current%contract%value%
Current%LD%exposure%[MNOK]%
LD%cap%[MNOK/%]%
Risks%[MNOK]%
Opportuni@es%[MNOK]%
Poten@al%VOR%contr.%[MNOK]%
Con@ngency%[MNOK]%
7.7# 7.7#
Deviation/Risk/Opportunity Have done Will do/decisions needed Resp Due Date
Top%issues%that%need%to%be%addressed:%
Key%figures%
Contribu@on:%Forecast%
Contribu@on:%Stretch%Target%
Contract%Delivery%
Current%Delivery% Quality% HSE% Customer%
rela@ons%
[MNOK/%]# [MNK/%]# dd.mm.yy# dd.mm.yy# Customer#Acceptance# Zero#Accidents# Sa>sfied#
customer#
YES, will achieve goal
YES, will achieve goal but currently behind or major risks present NO, Will not achieve goal, decision required
www.considium.no
The Project Assurance Meeting
– milestones and/or results will NOT be achieved as agreed or not within time!• What do you intend to do about it – and what decisions need to be taken?!• What risks and opportunities do you see ahead – and what actions do these
require?!• Do we as a team agree with the situation assessment?!• Do you need help? How can the team contribute to find new solutions?
YES
NO
Will you achieve your results and milestones within time?
– milestones and results will be achieved within time!• What risks and opportunities do you see ahead – and what actions do these
require?!• Do we as a team agree with the situation assessment and the mitigating actions? If
not, put it on the table
Why are you behind?Why did/didn’t you …?
What does it take to get back on track?What might we do?
Future
DefensivenessBlamingCover your backFrustration
ProactivityInitiativeResponsibilityMotivation
Results&MilestonesRisks&PossibilitiesActions&Decisions
ActivitiesProblemsExplanations
Create forward focus by asking the right questions
Past
• During the project assurance meeting the leader must avoid taking the responsibility and initiative away from his team-members.
• Follow-up meetings are often focused on what the manager considers as necessary actions – while the team-members who actually should be followed up, are given the role as listeners.
• The consequence is that the delegated responsibility has been withdrawn.
• The persons who are followed up must act as a chairman during their own presentation and ensure that necessary decisions are taken!
Keep responsibility where it belongs
Meeting rules
Do Don’t
Specifytheproblemtobesolved Submittostorytelling andproblemexplanation
Makecommitmentswithcriticalstakeholders ontheirpartinresolvingtheproblem
Makesuperficialpreparations/establish unclearprerequisites
Haveatleastonesuggestedway toresolvetheproblem Justpresenttheproblemoronlyaskingquestions
Demonstrateproblemsolvingbehaviorandwhatittakestoresolvetheissue Sit onthebalconyarguingwhytheproblemisinsolvable
• As project manager you need to have full attention on your project– Make sure the project deliver as promised– Transparent and open about deviations, risks & opportunities as early as possible
• As a business manager you are accountable to the overall success of the business– Make sure WE AS A TEAM deliver as promised– Help your colleagues to succeed by providing feedback and suggestions to resolve issues– Compensate for losses or overspending in other projects
• So…– Think both unit and unity– Challenge yourself and the others– Invite the others to challenge you
Like race horses, project managers need to wear blinders..... but, not all the time. You are also a business manager
Project Assurance is about moving from reporting to steering
Project Assurance is about making sure the project will be successfulü Improved predictability of execution and results
- early warning, early actions/decisionsü Increased accountability and commitment to project goalsü Increased commercial focus in Project Management Teamü Better handling of dependencies between Work Packages (on project
level) and between projects (on portfolio level)
ü Improved alignment and interaction between projects and line organization
ü Clear identification of bottlenecks in organizational setup and processes
Monthly meetings the main arena for Project Assurance• The Project Assurance meeting is a decision meeting,
not a status meeting
• Project Managers report on goal and achievement (not status) and related critical issues
• Projects Managers come prepared with proposed required actions and decisions to:
• Handle deviations• Remove barriers• Exploit opportunities
• Meeting provides feedback, support and makes decisions – Focus on what it takes to achieve goals
Project Assurance to ensure forward looking... ... by focusing on future milestones/goals
Will you achieve your results and
milestones within time?
Yes
NoFuture
ProjectGoals
Past
Results
Activities
Deviations,risks&opportunities
Actions&decisions
M1 M2 M15