CONSTRUCTION AND CONSTRUCTION AND ENGINEERING SUPPORT ENGINEERING SUPPORT SERVICES DEPARTMENTSERVICES DEPARTMENT
INTRODUCTION
3
C&ESS Department is responsible to provide Civil construction, Field Gathering lines & Mechanical fabrication services to Drilling, Production, Process, Store & other client Departments.
Two Division:1- Civil Engineering2- Mechanical Engineering
1. Pre-Drilling Civil Works. 2. Metalled Roads, Field Roads & Right of Ways3. Field Camps, Boundary Walls & Fencing4. Ware Houses, Workshops, Storage sheds etc.5. Dispensaries6. Water Supply Systems, Water & Sewage Treatment Plants7. Laying of Gathering Lines8. Fabrication and installation of Well Head Assemblies.9. Installations for Pig Launching Assemblies10. Fabrication and repair of Oil Storage Tanks and Caravans.11. Maintenance of baseline field machinery.
Functions Functions
4
5
Cost estimates are based on MES Schedule of Rates.
Engineering Works Procedure:• Cost estimate and AFE approvals.• Tender documents preparation and contract administration.• Departmental works utilizing available resources.• Procurement of material & services as per PPRA & PEC.
Working MethodologyWorking Methodology
CIVIL ENGINEERINGCIVIL ENGINEERINGCivil Engineering consists of Three sections1.Engineering Operations North
• Engineering Field Party No. 2• Engineering Field Party No. 3
2.Engineering Operations South• Engineering Field No. 1• Engineering Field No. 4• Engineering Field No. 5
3.Contracts & Consultancy Services
6
Mechanical Engineering consists of two sections1.Equipment and Field Machinery
• Workshop and Transport Section• Base Workshop, I-9, Islamabad• Base Workshop, KBW, Karachi
2.Fabrication and Pipeline• Field Gathering Construction Party No. 1• Field Gathering Constuction Party No. 2
MECHANICAL ENGINEERINGMECHANICAL ENGINEERING
Party Location District Province
EFP-1 Uch Dera Bugti Baluchistan
EFP-2 Kot Adu Muzaffar Garh Punjab
EFP-3 Fateh Jang Attock Punjab
EFP-4 Qadirpur Ghotki Sindh
EFP-5 Hyderabad Hyderabad Sindh
FGCP-1 Multan Multan Punjab
FGCP-2 Hyderabad Hyderabad Sindh
Present Locations of EFPs and FGCPsPresent Locations of EFPs and FGCPs
7
8
ENGG.WORKS DETAILENGG.WORKS DETAILPre Drilling Engineering Works
Description 2011-12 2012-13 2013-14 2014-15 2015-16
Completed 20 22 22 24 28In progress - - - - 9In Tender process
- - - 2
9
ENGG.WORKS DETAILENGG.WORKS DETAILCivil Works for Work Over Jobs
Description 2011-12 2012-13 2013-14 2014-15 2015-16
Completed 8 7 5 14 16In progress - - - - 2In Tender process
- - - - 3
10
Works carried out by EFP-I Works carried out by EFP-I During Last 05 Years
PDEW Work Over Job at Field Development WorksS.No. Name of Project Remarks S.No. Name of Project Remarks S.No. Name of Project Remarks
1 Nashpa#4 Completed 1 Kal#2 Complete. 1 Permanent Fencing at Nashpa#1. Completed.
2 Nashpa#5 Completed 2 Kal#3 Complete. 2 Permanent Fencing at Nashpa#2. Completed.
3 Nashpa#6 Completed 3 Missa Kiswal#3 Complete. 3 Permanent Fencing at Nashpa#4. Completed.
4 Nashpa#7 Completed 4 Chak Naurang#5A Complete. 4 Well operator and security guard room at Nashpa#4. Completed.
5 Mela#4 Completed 5 Chak Naurang South#1 5 PCC hardstanding at stock material at Nashpa. Completed.
6 Mela#5 in progress 6 Rajian#1 in progress 6 F.C. accomodation at Nashpa. Completed.
7 Chanda#4 in progress 7 Rajian#4A Complete. 7 Internal Road at Nashpa. Completed.
8 Shawa#1 Completed 8 Rajian#2 in progress 8 RCC Boundary wall at Nashpa. Completed.
9 Naurang Shah#1 Completed 9 Field development works at Nashpa. Completed.
10 Kurrum#1 Completed 10 Hardstanding for extension of existing filling gantry. Completed.
11 Shaikhanwala#1 Completed 11 RCC Water storage tank at Nashpa. Completed.
12 Surqamar#1 Completed 12 Temporary camps construction for LPG plant extension at Nashpa Completed.
13 Khawaja#1 (Re-entry) Completed 13 Fencing and watch towers at plant extension area at Nashpa. Completed.
14 Kohat#1 Completed 14 API pit/Skimmer tank at Nashpa. in progress
11
Works carried out by EFP-I Works carried out by EFP-I During Last 05 Years
15 Jabbi#1 Completed 15 Pre-casted wall at LPG plant area at Nashpa. Completed.
16 Jand#1 Completed 16 Double gate, road blocker and hydraulic barrier at Nashpa. Completed.
17 Jand#2 Completed 17 Dyke walls and flooring around crude storage tanks at Nashpa. Completed.
18 Dakhni Deep #5. Completed 18 Admin building at Nashpa. Completed.
19 Dakhni#7 Completed 19 02 class rooms with veranda for Govt. Primary School at Awaji Banada, Nashpa. Completed.
20 Dakhni#8 Completed 20 One way road and parking shed at Nashpa. in progress
21 Dakhni#12 Completed 21 Infra structure works at Chanda. Completed.
22 Ajuwala#1 Completed 22 Internal road at Mela. Completed.
23 Soghari#1 Completed 23 TST of internal roads at Chanda. Completed.
24 Soghari#2 Completed 24 Production office building at Dakhni. Completed.
25 Chak Naurang# X-1 Completed 25 Plice Check Post at Dakhni well #3. Completed.
26 Rajian#6 Completed 26 Metalled road (7Km) from Social welfare dispensary to Dakhni #6. Completed.
27 Rajian#7 Completed 27 RCC Hardstanding for Logistic work shop area at Kot Sarang. Completed.
12
Works carried out by EFP-II Works carried out by EFP-II During Last 05 Years
PDEW Work Over Job at Field Development WorksS.No. Name of Project Remarks S.No. Name of Project Remarks S.No. Name of Project Remarks
1 Kup#1 Completed 1 Bahu#5 Completed. 1
Construction of metal road, boundry wall & cement concrete stone paving, additional work for annaxe at R.O Multan
Completed
2 Kalchas#1 Completed 2 Bahu#7 Completed. 2Construction of hard standing(flooring) at kot addu field store
Completed
3 Bahu#5 Completed 3 Punjpir Completed. 3 Repair of fencing at Bahu-5,6,7,8 Completed
4 Bahu#6 Completed 4 Pre-drilling civil work at Barkat wala(Heto) Completed
5 Bahu#7 Completed 5 Water supply scheme for locals at kalchas Completed
6 Bahu#8 Completed 6 Evaporation pond at SS Well no 1 Completed
7 Sohni wala No-1 Completed 7 Construction of officer rest house Annexe at R.O Multan Completed
8 Dhodak Deep #2 A Completed 8 Renovation of banglow A-1 officer rest house kotaddu field Completed
9 Dhodak Deep #1 Completed 9Construction of engine driver room at kotaddu log field,hard standing and roof treatment of Masjid
Completed
10 Muhammad test well No-1(multan north -1) Completed 10
Blasting/removing of crocked mountain along approach road near chapper DDK field.
Completed
11 DDk Rubly x-1 in progress 11 Repair and mantenence of store shed at kotaddu field. Completed
13
Works carried out by EFP-II Works carried out by EFP-II During Last 05 Years
PDEW Work Over Job at Field Development WorksS.No. Name of Project Remarks S.No. Name of Project Remarks S.No. Name of Project Remarks
12 Renovation/partition of banglow B-2 at log field kotaddu Completed
13Urgent construction of security post,rooms for BMP one at mari top dera bugti.
Completed
14 Tuff tiles at nandpur/punjpeer dehydration plant Completed
15 Boundry wall at ss-1 nandpur Completed
16 Re construction of boundry wall at RO-Multan Completed
17 Const of metal road shujabaad canal at ss-1 nandpur Completed
18 Distemper/weather shield paint officer & camp building(EFP_2) Completed
19 Tiles flooring for staff transit camp at RO-multan Completed
20 Dismentling of punjpeer Completed
21 Comst of hardstanding around admin building efp-2 kotaddu Completed
22 Const of washroom at bahu-2 Completed
23 Re-habitation of admin block log-field kotaddu Completed
24 Civil work of const of masjid at dhodak colony multan Completed
25 Renovation work of staff and officer transit camp at RO- multan Completed
26Bahu well no 4 bahu gas field develment at bahu well no 4 hydraulic work
Completed
14
Works carried out by EFP-III Works carried out by EFP-III During Last 05 Years
PDEW Work Over Job at Field Development WorksS.No. Name of Project Remarks S.No. Name of Project Remarks S.No. Name of Project Remarks
1 Nashpa#4 Completed 1 Kal#2 Complete. 1 Permanent Fencing at Nashpa#1. Completed.
2 Nashpa#5 Completed 2 Kal#3 Complete. 2 Permanent Fencing at Nashpa#2. Completed.
3 Nashpa#6 Completed 3 Missa Kiswal#3 Complete. 3 Permanent Fencing at Nashpa#4. Completed.
4 Nashpa#7 Completed 4 Chak Naurang#5A Complete. 4 Well operator and security guard room at Nashpa#4. Completed.
5 Mela#4 Completed 5 Chak Naurang South#1 5 PCC hardstanding at stock material at Nashpa. Completed.
6 Mela#5 in progress 6 Rajian#1 Completed. 6 F.C. accomodation at Nashpa. Completed.
7 Chanda#4 in progress 7 Rajian#4A Completed 7 Internal Road at Nashpa. Completed.
8 Shawa#1 Completed 8 Rajian#2 in progress 8 RCC Boundary wall at Nashpa. Completed.
9 Naurang Shah#1 Completed 9 Field development works at Nashpa. Completed.
10 Kurrum#1 Completed 10 Hardstanding for extension of existing filling gantry. Completed.
11 Shaikhanwala#1 Completed 11 RCC Water storage tank at Nashpa. Completed.
12 Surqamar#1 Completed 12 Temporary camps construction for LPG plant extension at Nashpa Completed.
13 Khawaja#1 (Re-entry) Completed 13 Fencing and watch towers at plant extension area at Nashpa. Completed.
14 Kohat#1 Completed 14 API pit/Skimmer tank at Nashpa. in progress
15
Works carried out by EFP-III Works carried out by EFP-III During Last 05 Years
PDEW Work Over Job at Field Development WorksS.No. Name of Project Remarks S.No. Name of Project Remarks S.No. Name of Project Remarks
15 Jabbi#1 Completed 15 Pre-casted wall at LPG plant area at Nashpa. Completed.
16 Jand#1 Completed 16 Double gate, road blocker and hydraulic barrier at Nashpa. Completed.
17 Jand#2 Completed 17 Dyke walls and flooring around crude storage tanks at Nashpa. Completed.
18 Dakhni Deep #5. Completed 18 Admin building at Nashpa. Completed.
19 Dakhni#7 Completed 1902 class rooms with veranda for Govt. Primary School at Awaji Banada, Nashpa.
Completed.
20 Dakhni#8 Completed 20 One way road and parking shed at Nashpa. in progress
21 Dakhni#12 Completed 21 Infra structure works at Chanda. Completed.
22 Ajuwala#1 Completed 22 Internal road at Mela. Completed.
23 Soghari#1 Completed 23 TST of internal roads at Chanda. Completed.
24 Soghari#2 Completed 24 Production office building at Dakhni. Completed.
25 Chak Naurang# X-1 Completed 25 Plice Check Post at Dakhni well #3. Completed.
26 Rajian#6 Completed 26 Metalled road (7Km) from Social welfare dispensary to Dakhni #6. Completed.
27 Rajian#7 Completed 27 RCC Hardstanding for Logistic work shop area at Kot Sarang. Completed.
16
Works carried out by EFP-III Works carried out by EFP-III During Last 05 Years
PDEW Work Over Job at Field Development WorksS.No. Name of Project Remarks S.No. Name of Project Remarks S.No. Name of Project Remarks
28 Rajian#8 Completed 28 Crude storage tanks foundation and dyke walls at Rajian#5. Completed.
29 Rajian#9 Completed 29 Extension in social welfare dispansary at Rajian. Completed.
30 Govt. Rural Dispansary, at Dina, Jehlum. Completed.
31Repair/maintenance of road from Mohri Rajgan to Chak Treda at Jehlum.
Completed.
32 Repair of main road to Rajian Oil Field. Completed.
33 Hard standing around weigh bridge and RCC culvert at Mela. Completed.
34 Cosndtruction of weigh bridge foundation at Mela. Completed.
35 Cosndtruction of weigh bridge foundation at Nashpa Completed.
36 Cosndtruction of weigh bridge foundation at Rajian. Completed.
37 New waste pit with skimmer tank at Kal. Completed.
38 Repair/upgradation of road from Shakardra to Kharapa More, Kohat. Completed.
39 Worshop shed at Dakhni. Completed.
40 Store shed at Dakhni. in progress
17
Works carried out by EFP-III Works carried out by EFP-III During Last 05 Years
PDEW Work Over Job at Field Development WorksS.No. Name of Project Remarks S.No. Name of Project Remarks S.No. Name of Project Remarks
41 New residential rooms at Rajian. in progress
42 Const. of civil works for utilization of weigh bridge at Rajian. in progress
43 Improvement of existing Tarally Bridge Road at Chanda. in progress
44 Supply of utility water at Nashpa Plant for year 2014. in progress
45 Supply of utility water at Nashpa Plant for year 2015. Completed.
46Construction of dyke wall and PCC hardstanding for crude storage tanks at Mela.
Completed.
47
Construction of RCC hard standing for installation of 20000 BPD Capacity new Separation Battery at Nashpa
Completed.
48 Construction of internal Road at chanda plant Completed.
49 Repair of (0.8 km)Road at Ratta Mohara Rajian oil field. Completed.
50 Modification of New store shed at dakhni Plant. Completed.
18
Works carried out by EFP-III Works carried out by EFP-III During Last 05 Years
PDEW Work Over Job at Field Development WorksS.No. Name of Project Remarks S.No. Name of Project Remarks S.No. Name of Project Remarks
51
Construction of One Rcc under ground water reservior at water source Mela # 01
Completed.
52Construction of well Operator and security Guard Rooms at Nashpa well # 03.
Completed.
53Construction of Foundation for Proplane Bullet at Chanda Plant
Completed.
54 Concrete Flooring at Chanda Plant Completed.
55 New Dehydration Plant at Nashpa Completed.
56 Construction of Room for Mechanical at Chanda Plant Completed.
57Civil Works for Re-installation of TOC at Sheikhan Plant
Completed.
58 Construction of Building of Mela Dehydration Plant Completed.
19
Works carried out by EFP-III Works carried out by EFP-III During Last 05 Years
PDEW Work Over Job at Field Development WorksS.No. Name of Project Remarks S.No. Name of Project Remarks S.No. Name of Project Remarks
59
Construction of Boundary Wall & Provision of steel Stairs for WatchTower at Sheikhan
Completed.
60 Laying of Water Line at Village Nandrakka Completed.
61 Compressor Foundation at Sadqal Completed.
62Renovation of MD Office and Entrance Lobby at Head Office
Completed.
63 Renovation of OGTI Room at Islamabad Completed.
64Improvement of Water Supply Scheme (Social Welfare) Kal Oil Field
Completed.
65
Laying of Sand Cushion / Supply & Installation of Geomembrane at Chak Naurang
Completed.
66 Re-surfacing / Wide laying of Access Road at Rajian#5 Completed.
67 Hardstanding at Chak Naurang Yard Completed.
68 Construction of Block at Govt. High School Rajian Completed.
20
Works carried out by EFP-III Works carried out by EFP-III During Last 05 Years
PDEW Work Over Job at Field Development WorksS.No. Name of Project Remarks S.No. Name of Project Remarks S.No. Name of Project Remarks
69 RCC Approach Road Action yard to Main Gate Completed.
70Construction of 02 Rooms for Store Office at Chak Naurang
Completed.
71 Rising of Boundary Wall at Dakhni Completed.
72Construction of Woven Mesh Fencing & Watch Tower at Chak Naurang Logistic Base
Completed.
73 Construction of Boundary Wall at I-9 Base Store Completed.
74Construction of Civil Works for Installation of LPG/DPR Unit at Dakhni
Completed.
75 Civil Work for Installation of Bullet at Dakhni Plant Completed.
76 Civil Works for Well Head at Dakhni#2 Completed.
77 Repair of Retaining Wall Inside Dakhni Plant Completed.
78 Store Shed at Dakhni Plant Completed.
21
Works carried out by EFP-III Works carried out by EFP-III During Last 05 Years
PDEW Work Over Job at Field Development WorksS.No. Name of Project Remarks S.No. Name of Project Remarks S.No. Name of Project Remarks
79Earth Filling RCC Road PCC Hardstanding at Dakhni Plant
Completed.
80Bathroom with Open Space & Boundary Wall Officers Camp EFP-III
Completed.
81 Semi-covered Shed at I-9 Base Store Completed.
82 08 Number Living Rooms at Dakhni Colony Completed.
83Glazed Tiles for Corridores & Stairs Masood Mansion, F-8 Markaz, Islamabad
Completed.
84 Repair of Bhal Syedan Road under Social Welfare Completed.
22
Works carried out by EFP-IV Works carried out by EFP-IV During Last 05 Years
PDEW Work Over Job at Field Development WorksS.No. Name of Project Remarks S.No. Name of Project Remarks S.No. Name of Project Remarks
1 PDCW well Badar # 02 Completed 1 Work Over Job QP#21 Completed 1 Rasing of Boundary Wall at
QP PlantCompleted.
2 HRL#3 Completed 2 Work Over Job QP#32 Completed 2 Wire Mesh Fencing QP # 37 Completed.
3 HRL#4 Completed 3 Work Over QP #11 Completed 3
Approach Road /ROWs from Eastern Pig Launcher station to QP Gas Field
Completed.
4 HRL#5 Completed 4 Hard Standing Cable Tranches QP Plant
Completed.
5 HRL#6 Completed 5 Repair of Fencing at QP plant
in progress
6 HRL#7 Completed 6Hard Standing and Parking Shed in front of Admin Block QP Plant
Completed.
7 HRL#8 Completed 7 Refencing of QP # 30 Completed.
8 HRL#9 Completed 8 Raised Platform at well QP# 17 Completed.
9 HRL#10 Completed 9 Construction of Office Chowkidar Room and Store Shed at Maru#01 Completed.
10 HRL#11 Completed 10 Relocation of 50MMSCED De Hydration at QP PEL Plant Completed.
11 PDCW QP # 48 Completed 11 Raising & repair of approach roads of well sites Completed.
23
Works carried out by EFP-IV Works carried out by EFP-IV During Last 05 Years
PDEW Work Over Job at Field Development WorksS.No. Name of Project Remarks S.No. Name of Project Remarks S.No. Name of Project Remarks
12 PDCW ERW QP # 47 Completed 12 Flood Fighting Arrangment
of OGDCL Bund.Carried out yearly.
13 PDCW Sara # 04 Completed 13 Repair & Reconstruction of QP Internal Road Completed.
14 PDCW QP 49-A Completed 14 Well Head Assemblies of Maru 1,2,3 Reti # 01 Completed.
15 PDCW QP#46 Completed 15 Raised Platform QP#36 Completed.
16 Civil Work related to stacking of Rig N#03 Completed 16 Permanent Fencing QP33 Completed
.
17 PDCW QP#45 Completed 17 Repair of Works QP#24 Completed.
18 PDCW HRL#06 Completed 18 Completed.
19 PDCW Hadra (Raja#01) Completed 19 Completed
.
20 PDCW QP#35 Completed 20 Repair of Fencing at QP#23& 27 Completed.
21 PDCW QP#44 Completed 21 Relocation Pirkoh Commpressor QP Plant Completed.
22 PDCW Maru South # 01 Completed 22 Fencing of QP # 40 Completed.
23 PDEW QP#42 (ERW-03) Completed 23 Raising/Strengthning of OGDCL Bund. in progress
24
Works carried out by EFP-IV Works carried out by EFP-IV During Last 05 Years
PDEW Work Over Job at Field Development WorksS.No. Name of Project Remarks S.No. Name of Project Remarks S.No. Name of Project Remarks
24 Reti#2 Completed
25 Ismail#1 Completed
26 Thal East#1 Completed
27 ThalEast#3 In progress
28 Thal West #1Completed
25
Works carried out by EFP-V Works carried out by EFP-V During Last 05 Years
PDEW Work Over Job at Field Development WorksS.No. Name of Project Remarks S.No. Name of Project Remarks S.No. Name of Project Remarks
1 Dhacharapur#2. Completed 1 Sona#8 Completed 1 Const. of admin building , warehouse & Sec. Office Building C-I Kunnar Sindh Completed
2 Saand#01 Completed 2 Thora#4 Completed 2 Const. of foundation for de-hydration plant at Bobi Completed
3 Aradin#1 Completed 3 Tando Alam#20 Completed 3 Const. Up-gradation and widening of Kunner-Pasaki Road Distt. Hyderabad, Sindh Completed
4 Pasaki#1 Completed 4 Tando Alam#16-A Completed 4 Field development civil works at Dacharapur # 2 distt Hyderabad Sindh Completed
5 Pasaki#9 Completed 5 Nim West#1 Completed 5 Const. of Water tank for drinking purpose Tando Alam Oil Complex Sidh Hyderabad Completed
6 Bobi#10 Completed 6 Lashari Center #5 Completed 6 Const. of Ploice post at Sinjhoro Completed
7 Tando Qaiser#1 Completed 7 Moolan North#1 Completed 7 Const. of Workshop Office, MP.E&I workshop etc. Kunnar C-2 Completed
8 Jakhro West#1 Completed 8 Tando Alam#20 Completed 8 Const. of Well Head Assembly works for 09 wells at Sinjhoro in progress
9 Patafi#1/Hanif Saddiqi#1 Completed 9 Lashari#5 Completed 9 Const. of remaining civil works at rangers
camp at TOC Hyderabad Sindh Completed
10 Kunner Deep#9 Completed 10 Kunner#2 Completed 10 Const. of Mosque at Daru Plant at Hyderabad Sindh Completed
11 Manna#1 Completed 11 Thora East#1 Completed 11 Const. of social welfare dispensary at Bobi plant sanghar Sindh Completed
12 Chak Dim 5 #2 Completed 12 Tando Alam#17. Completed
13 Chak 25 C#1 Completed 13 Chak 66 North East #1 Completed
14 Pasaki Deep #4 Completed 14 Kunner #2 Completed
15 Saand #2 Completed 15 Thora East#1 Completed
16 Palli Deep#1 Completed 16 Thora#6 Completed
17 Kunner#9 Completed 17 Lashari#3 Completed 18 Jarwar#1 Completed 18 Kunner #4 Completed
26
Works carried out by EFP-V Works carried out by EFP-V During Last 05 Years
PDEW Work Over Job at Field Development WorksS.No. Name of Project Remarks S.No. Name of Project Remarks S.No. Name of Project Remarks
19 Pasaki Deep#5 Completed 19 Kunner#8 Completed
20 Pasaki #10 Completed 20 Pasakhi#7 Completed
21 Chak 3 Dim#3 Completed 21 Kunner#5 Completed
22 Kunner Deep#10 Completed 22 Aradin#1 Completed
23 Sinjhoro#X-1 Completed 23 Dars Deep#1 Completed
24 Buzdar North #2 Completed 24 Chak 2 #3 Completed
25 Tando Allah Yar East#1. Completed 25 Sono#4 Completed
26 Suleman#2 Completed 26 Chak 2 #2 Completed
27 Bitrism West#2 Completed 27 Tando Alam#17. Completed
28 Bachani#1 Completed 28 Tando Alam #18 Completed
29 Kunner #10. Completed 29 Thora Deep#1 Completed
30 Kunner Deep#11. Completed 30 Thora#3 Completed
31 Pasakhi Deep #6. Completed 31 Thora#4 Completed
32 Khewari E.L.(X-1) Completed 32 Kunner#6 Completed
33 Kunner #11 Completed 33 Nim West #1 Completed
34 Palli#2 Completed 34 Thora East #1 Completed
35 Soomro#1 (Daru Deep#1) Completed 35 Pasakhi North#1 Completed
36 Dachrapur#3 Completed 36 Pali Deep#1 in progress 37 Gundanwari#1 in progress
E&FM Section an integral part of C&ESS Department is committed:
• To Plan, co-ordinate & execute repair & maintenance of all field machinery & equipment of the C&ESS Department
• To provide feed back services to EFPs for smooth functioning of their field workshops & water supply.
• To plan & co-ordinate major overhauling of the machinery/equipment at Base workshops.• To plan & co-ordinate for smooth water supply to fields & Rigs sites.
05 Numbers Field Workshops under the administrative control of respective Party Chiefs:EFP-1EFP-IIEFP-IIIEFP-IVEFP-V02 Nos Base Workshops:I-9 Base Workshops at Islamabad.Karachi Base Workshop, its administrative control lies with RC Karachi.
27
WORKSHOPS:
E&FM Section
During Last 03 Years• PERMANENT WORKS• (Majority works done through tender after approval of Engineering Works Procedure-2013)• • 1- COMPLETED WORKS 40• • 2- UNDER CONSTRUCTION WORKS 32 • • 3- WORKS IN TENDERING STAGE 104.• (Bid documents, Tech. Evaluation, Fin. Evaluation, • Competent authority approval, Contract agreement • & Work order stage)• 4- ANNULED / CLOSED CASES/ RETENDERED- 41• • TOTAL WORKS 217• • • PREDRILLING ENGINEERING WORKS • (PDEWs done through tender after approval of Engineering Works Procedure-2013)• • 5. Tendered & awarded PDEWs 115• 6. TOTAL PDEWs tendered & awarded of work - 115• • 7. TOTAL PERMANENT & PDEWs 332
• 28
Works Processed by Contract Section
# JOBS FGCP-I FGCP-II TOTAL
QTY CostMillion Rs
QTY CostMillion Rs
QTY CostMillion Rs
1 Laying of Oil & Gas Pipeline 4”, 6”, 8”, 10”, 16”, 26”, 30” (& Retrival)
273 KM 750 257 KM 861.877 530 KM’s
1612
2 Installation of well head facility 37 Nos 55 25 Nos 24.69 62 Nos 117
3 Crude storage Tanks 3000, 5000, 6000, 12000, 20000 BBLS
06 Nos 8.2 17 Nos 29.75 23 Nos 38
4 Fab / Renovation of living caravans 28 Nos 20 -- -- 28 Nos 20
5 Installation of CO2 removal plant / glycol unit / tie-in of compressor
-- -- 03 Nos 17.812 03 Nos 17.812
6 ATA’s 06 Nos 34 09 Nos 3.962 15 Nos 38
7 Installation of separation batteries (HP/MP/LP) 12 Nos80
14 Nos90
26 Nos170
8 Misc Pipeline repair, installation of knock out vessels, gathering headers, steel structures, pipe supports
200 Nos 76 Nos 276 Nos
TotalRs 2013 Million
# JOBS QTY Cost Rs(Million)
1 Installation of Flow line 56 KM’s 424
2 Well Head Assembly 10 Nos 15
3 Repair of Storage Tank 06 Nos 32
4 Relocation of Flare stack 01 Job 1.5
5 Repair / Renovation of Living Caravans 05 Nos 4.0
Total 476.5
During Last 03 Years• PERMANENT WORKS• (Majority works done through tender after approval of Engineering Works Procedure-2013)• • 1- COMPLETED WORKS 40• • 2- UNDER CONSTRUCTION WORKS 32 • • 3- WORKS IN TENDERING STAGE 104.• (Bid documents, Tech. Evaluation, Fin. Evaluation, • Competent authority approval, Contract agreement • & Work order stage)• 4- ANNULED / CLOSED CASES/ RETENDERED- 41• • TOTAL WORKS 217• • • PREDRILLING ENGINEERING WORKS • (PDEWs done through tender after approval of Engineering Works Procedure-2013)• • 5. Tendered & awarded PDEWs 115• 6. TOTAL PDEWs tendered & awarded of work - 115• • 7. TOTAL PERMANENT & PDEWs 332
• 31
Works Processed by Contract Section
STATE OF FIELD MACHINERY / EQUIPMENT
32
Bulldozers = 18 NoMotor Graders = 10 NoShovel Loaders = 08 NoRoad Rollers = 08 NoFarm Tractors = 12 NoFork Lifter = 05 NoWater Drilling Rigs = 02 NoGenerators = 24 NoWelding Plants = 21 NoPrime movers with trailers = 08 NoDumpers = 21 NoWater Bouzers = 25 NoTrucks = 18 NoDouble cabin Pickups = 08 NoGaso Pumps = 54 NoMisc Water pumps = 57 NoCrane Mounted Trucks = 05 NoLight Trucks 4x2 = 12 No Total = 316 No
IssuesIssuesS. No Issues Solution
1. Identification of locations and land acquisition.
Timely identification & un-conditional acquisition of land to start civil works.
2. Approval of AFEs. Quick approval for timely remittance of funds for execution of works.
3. Shortage of equipment base.
Strengthen equipment base by induction of new machines and through hiring where possible.
4. Shortage of qualified engineers and supervisory staff.
Induction of Engineers/Techs. When the situation permits.
5. Lack of motivation. Transparent career planning of engineers.
6. Financial discipline in field parties.
Monthly audit of field imprest.
33
Supply of water to Production sites = 08.93 million gallons monthlySupply of water to Process & Plants = 76.11 million gallons monthly
Supply of water to Drilling sites = 19.22 million gallons monthly
Total water supplied for one month =104.26 million gallons
Water Supply SectionWater Supply Section
34
35
Vehicle Repaired at I-9 &KBW Base WorkshopVehicle Repaired at I-9 &KBW Base WorkshopS. No. Period Service Minor
RepairMajor Repair
Engine Overhauling
1 2011 – 2012 1177 1279 37 05
2 2012 –2013 982 1082 18 05
3 2013 – 2014 929 1036 18 06
4 2014 – 2015 971 1102 17 02
5 2015 - 2016 849 889 13 03
Total 4908 5388 103 21