Cicatih mini hydro site visit report

Embed Size (px)

DESCRIPTION

cicatih mini hydro project situated in sukabumi district, Indonesia, along cicatih river

Citation preview

Page 1: Cicatih mini hydro site visit report
Page 2: Cicatih mini hydro site visit report

A1-Intake access from district road A2-Access to proposed

Yard/Storage area

Page 3: Cicatih mini hydro site visit report

Drawing CCT01

Page 4: Cicatih mini hydro site visit report

A3-Backfilling at right hand side waterway A4-Disposal area 4

Page 5: Cicatih mini hydro site visit report

B1- soil at river areaB2- Piling needed at left

side waterway

Page 6: Cicatih mini hydro site visit report

B3-Outcrop Rock in main river D1-Access to proposed site office

Page 7: Cicatih mini hydro site visit report

Figure 1:Airport location, Jakarta and site at Cimanggu

Page 8: Cicatih mini hydro site visit report

D2-CIBURUG the nearest facilitated town D3-Yard storage area

Page 9: Cicatih mini hydro site visit report

D4-Proposed laydown area

D5- Existing waterways to be widen

Page 10: Cicatih mini hydro site visit report

D6-Electricity supply for construction tap point

E1-Adidas factory at Cikembar

Page 11: Cicatih mini hydro site visit report

E2-Kampong residential area near proposed site E3-CUBURUG town

Page 12: Cicatih mini hydro site visit report

E4-Jakarta to Ciawi tol hiway

F1-possssible landslide in rainy season

Page 13: Cicatih mini hydro site visit report

F2-Possible shear at headpond area

F3-Bad rock at waterway

Page 14: Cicatih mini hydro site visit report

F4-Hydrological condition, rainfall2 ,800mm per year

F5-Rainfall 2,800mm per year

Page 15: Cicatih mini hydro site visit report

Figure2- Indonesia hydro consult

Page 16: Cicatih mini hydro site visit report

I1-Feed in point to PLN I2-Site is nearby to

village resident having access to electric power

Page 17: Cicatih mini hydro site visit report

Figure J1-Hydrology regime

Page 18: Cicatih mini hydro site visit report

J1-Rock in river

J2-Existing weir to be upgrade

Page 19: Cicatih mini hydro site visit report

J3-waterway to be upgrade

J4- sandtrap area near to main river for ease of silt disposal

Page 20: Cicatih mini hydro site visit report

J5-Headpond area 26m above powerhouse J6- Existing Waterway to be

widen to 9 m

Page 21: Cicatih mini hydro site visit report

J7-water discharge channel

J8-Penstock location at high level 26m above powerhouse downstream

Page 22: Cicatih mini hydro site visit report

Feed in point to PLN 1.2km from powerhouse