11kV ID Switchgear Panels for Secondary Sub-stations
Items Required
SL No Description of Documents/Details Required
PART-I / Manufacturing Co & Factory Related
1 Company profile Owner name, Location of factory, Total Factory Area, Total built-up area, Department buildings/Functional areas, Last five years business turn-over (Qty & Value)
2 Organization profile Organization Chart, Details of Total Manpower, Break-up of man power into Top management & Administration, Technical Managers, Design Engineers, Production Engineers, Skilled workers, semi-skilled workers, QA/QC staff, Sales & marketing, IT staff.
3 Product Profile: Main Product intended to supply, product accreditations (if any), sources of technology, technical collaborations, and Rated Production capacities, Last five years production & sales data, main customers
4 Experience: No of years in business in general. No of years of manufacturing experience of the specific product being proposed for pre-qualification. Qualifications and experience of technical staff including design, production & testing.
5 Machinery used List of main machinery used in the current production line of proposed product, with details of manufacturer name, country of origin, when installed.
6
Lab & Testing Facilities- List of testing equipment, List of type tests/special tests/routine tests the laboratory can carry-out on the finished product, list of testing equipment used for quality verification of raw-materials /out-sourced components, accreditations of laboratory (if any) by Authorized International Accreditation bodies.
7
Manufacturing Process Quality procedure for selection of raw materials or components, Main Production process flow chart, details of main manufacturing process , welding and sheet cutting process, painting process, assembly work, testing of sub-assemblies, testing of finished product, etc
8 Quality control - QA/QC Methods & procedures being followed, check-lists used at each stage of production, details of in-process quality checks/testing methods, rates of rejections etc
9 FAT Tests- Details of in-process testing plan documents, product test & inspection procedures, routine tests, visual inspection, and their acceptance criteria, the documents used to record the FAT tests results of the proposed product.
PART-II / Product Related - General
1 An Application in the form of letter Addressed to Director, Electricity Network Affairs
2
Duly filled-in Pre-qualification Questionnaire for the specific product only (Note: Do not propose range of products or multiple products in one application. If you need to obtain pre-qualification for more than one product, submit separate applications for each individual product)
3 Details of Sales history to Utility companies in GCC and other Countries (details should include names of clients, quantities supplied, date of supply, Capacity/Type/ratings of Panels.
4 Details of Product testimonials/Performance reports/Approvals (if any) received from any Utility Companies in GCC and Other Countries.
5 Copy of Valid ISO 9001: 2000 Certificate (not older than 3-Years from the date of issue).
Electricity Network Planning Department Material Standards & Specification Section
EP-MS-P7/F5 Issue: 0 06-02-2011 Page 2 of 2
Check List of Documents Required For Pre-Qualification of
11kV ID Switchgear Panels for Secondary Sub-stations
Items Required
SL No Description of Documents/Details Required
PART-II / Product Related - Technical
1 Statement of Compliance/Deviations from manufacturer against each clause (up to the sub-sub clause level) of Kahramaa Specification # ED-02-082 ver-3/2008 (Latest Issue). (Note: Remarks like 'Refer our catalogue, noted or other indirect references are not acceptable.)
2
Copies of Type Test & Special test Reports covering Di-electric Tests, Short Circuit test, Internal arc tests (IAC-AFLR, 25kA@1 sec), temperature rise test, Type tests of Earth Switches, issued from Independent reputed International testing laboratories (like KEMA/ASTA). (Notes: Each test report should contain full text of the document, partial reports are not acceptable. The test reports shall not be older than 10-years from the date of Issue.
3
Technical Data Sheets of all types of panels (Transformer feeder, incomer/outgoing feeders, bus-section, directional) Ratings & parameter details, Operational features & procedures, Electrical & mechanical interlocks details, Bus-bar Earthing Procedures, Product Catalogues, etc
4
Technical Data Sheets, Product Catalogues, and sourcing Details of all components, covering CB truck, Vacuum bottle, CTs, VT, Earth Switches, CVDs, Protection Relays & Test blocks, Indicating Instruments, LV control Switches, Live Phase Indicators & Phase comparator sockets, Phase comparator Instrument, Bus-bar coupling kits, etc
5
General Arrangement Drawing(s) of each type of panel (Transformer feeder, incomer/outgoing feeders, bus-section, directional) clearly indicating all dimensions, all components & accessories, preferably in A3 Size (Note: The drawings should include all 3-views, dimensions, important sectional views, parts list, ratings & standards, materials used. Simple sketches are not acceptable)
6 Separate Schematic Diagrams of Power (SLD), Protection, Control & Indication circuits, of each type of panel, mentioning all components & accessories, and its symbols, ratings and parts list.
7 Instruction Manuals of Installation, Operation & Maintenance