Comox Valley Quarterly Public Meeting
September 16, 2014
• K’ómoks First Nation
2
Acknowledgement of Traditional Lands
Approvals
• Treasury Board
• Cabinet
Project Agreement
• Commercial Close
• Financial Close
Construction Underway
• Groundbreaking
• Site Administration
• Excavation
• Concrete
• Steel
Since May 27, 2014
3
• Location: 101 Lerwick Road, Courtenay
o 39,826 m2
o 153 beds
o $331.7 million
o Comox Strathcona Regional Hospital District 40%
4
Comox Valley Hospital
Webcam 11:52 a.m. September 16, 2014
4
• Location: Next to existing hospital (375 - 2nd Avenue)
o 22,316 m2
o 95 beds
o $274.5 million
o Comox Strathcona Regional Hospital District 40%
5
Campbell River Hospital
Webcam 11:55 a.m. September 16, 2014
5
Project Coordinator
Campbell River Site
(EA to CPO)
Monique Hebert
Chief Project Officer
Tom Sparrow
Technical Team
Lead: Kerry Beauchamp
Equipment Lead: Catherine Brooks
Clinical Team Lead: Norma Jones
IMIT Team Lead: Steve Carter
Smart Technologies
Team Lead: David Leadbetter
Financial Team Lead: Bill Boomer
Communication Team
Sr Project Coordinator
Comox Valley Hospital
Jennifer Singer
6
Island Health Project Team
7
Tandem Health Partners
Working Group Structure
COVER
8
9
Business
Case &
Design
Concept
Construction
Issue
RFQ
Issue RFP
Negotiate
Maintenance
3 years
5 months
to 2 years
Design
Concept
Plan
Contract Term
30 years
2 to 4
months We are here
10
Progress – Design & Construction Phase
Design
• Detail Design Review
• Clinical User Consultation
• Mockup Spaces
• Guidance
• Aboriginal Working Group
• Public Advisory Committee
Construction
• Excavation - Underway
• Foundation Work – Underway
Where we are going
11
Comox Valley – Level 0
12
Comox Valley – Level 1
Cardiopulmonary
Diagnostics 13
Comox Valley – Level 2
14
Comox Valley – Level 3
15
Comox Valley – Level 4
TES
T
TES
T
16
Mockups
Sink
Paper Towel
Sharps
Soap
17
Mockup – Operating Room
18
Community Engagement & Consultation
Quarterly Public Meetings
Newsletters
Website
Webcams
Public Patient
Advisory Committee
(in recruitment)
Art Committee
(Terms of Reference in development)
Aboriginal Working Group
School Advisory
Committee
19
Public-Patient Advisory Committee
Expression of Interest – September 16
First Intake - Interviews – mid October
First Committee Meeting - end October
20
Education and Training
• Inter-agency Discussions – March 13, 2014
• North Island Employment Foundations Society, North Vancouver Island Aboriginal Training Society, Industry Training Authority, North Island College, SD72, SD71, Vancouver Island Construction Association, Island Health
Industry Training Authority
• Dialogue on Trades/Apprenticeships Opportunities – September 9, 2014
Community Benefits - Opportunities
21
Business and Industry
• Chambers of Commerce – Industry Speed Dating Sessions
• Campbell River: May 27, 2013 (Workshop: May 16)
• Comox Valley: May 28, 2013 (Workshop: May 16)
• Follow up Sessions (Planning in Progress)
Tender / Bid Opportunities
• Prequalification
• Work Packages
Community Benefits - Opportunities
22
Work Packages and Awards
Work Packages and Awards
25
Community Benefits
26
• Construction began – July 7th
Construction fencing installation Erosion & sediment control Temporary access road Groundbreaking – August 7th Install Site Trailers – In Progress Bulk excavation continues Erect cranes – end of September
Construction – September, October
Wheel Wash Facility
27
28
Construction – Excavation
29
30
Construction cont’d.
Project Schedule
Design and Construction of New Facilities July 2014 – April 2017
Service Commencement – Project Completion April 30, 2017
Commissioning and Transition Period Summer – Fall 2017
Move-In Late Fall 2017
31
What we have been hearing
• Traffic Concerns
32
What we have been hearing
• Dust Control
33
What we have been hearing
• Dead Trees
34
For more information and updates, visit our website:
http://nihp.viha.ca/
North Island Hospitals Project Website
35
Thank You!!
Questions?