APAVE VIET NAM & SOUTHEAST ASIA Project Management Plan If any page(s) of this document is found dirty, deficient, torn or unreadable, please inform to be re-supplied. Code: AVN-CTC-QLDA Date of Issue: 12/03/2009 Issue no.: 01 Page 1/15 PROJECT MANAGEMENT PLAN CODE: AVN-CTC-QLDA PREPARED BY REVIEWED BY APPROVED BY THAI NGUYEN DAN PHUONG LE HUE NGUYEN CONG PHU Specialist of Technical- Operation Division Assistant of Deputy General Director General Director

Xaydung360.Vn_Project Management Plan

Embed Size (px)

Citation preview

Page 1: Xaydung360.Vn_Project Management Plan

APAVE VIET NAM & SOUTHEAST ASIA

Project Management Plan

If any page(s) of this document is found dirty, deficient, torn or unreadable, please inform to be re-supplied.

Code: AVN-CTC-QLDA Date of Issue: 12/03/2009 Issue no.: 01 Page 1/15

PROJECT MANAGEMENT PLAN

CODE: AVN-CTC-QLDA

PREPARED BY REVIEWED BY APPROVED BY

THAI NGUYEN DAN PHUONG LE HUE NGUYEN CONG PHU

Specialist of Technical-

Operation Division

Assistant of Deputy General

Director General Director

Page 2: Xaydung360.Vn_Project Management Plan

APAVE VIET NAM & SOUTHEAST ASIA

Project Management Plan

If any page(s) of this document is found dirty, deficient, torn or unreadable, please inform to be re-supplied.

Code: AVN-CTC-QLDA Date of Issue: 12/03/2009 Issue no.: 01 Page 2/15

AMENDMENT RECORD: in one issue

Revision Date Content

Page 3: Xaydung360.Vn_Project Management Plan

APAVE VIET NAM & SOUTHEAST ASIA

Project Management Plan

If any page(s) of this document is found dirty, deficient, torn or unreadable, please inform to be re-supplied.

Code: AVN-CTC-QLDA Date of Issue: 12/03/2009 Issue no.: 01 Page 3/15

1. Objective

The objective of this document is to inform the Owner the organization plan and the

executive method of APAVE Vietnam and South East Asia’s project management. This is to

obtain/ satisfy the requirements of project and of customers.

2. Scope of application

This document is applied in APAVE Vietnam and South East Asia’s and the parties which

are related to the projects managed by APAVE Vietnam and South East Asia.

3. Reference

Quality Manual of APAVE Vietnam and South East Asia

The current edition of ISO 9001

Decree 12/2009/NĐCP issued on 12/02/2009 about the Construction Management

for Construction works and the current documents

Decree 209/2004/NĐCP issued on 16/12/2004 about the Quality Management for

Construction works

4. Content

4.1 Project Management Principles

APAVE Vietnam and South East Asia manages projects basing on the following principles:

Comply with the Owner's contract,

Comply with the construction law, Decree 12/2009/NĐCP and Decree

209/2004/NĐCP

Apply the management model based on the current ISO 9001

4.2 Project Management Objectives

Project management objectives are determined to satisfy the Owner’s requirements of:

Scope of work

Quality of the construction work

Execution progress of the construction work

Ensure the contract expense

4.3 Project Management Deployment

4.3.1 Presentation of construction project

Name of construction project

Project location

The Owner

The Project Management Consultant

Page 4: Xaydung360.Vn_Project Management Plan

APAVE VIET NAM & SOUTHEAST ASIA

Project Management Plan

If any page(s) of this document is found dirty, deficient, torn or unreadable, please inform to be re-supplied.

Code: AVN-CTC-QLDA Date of Issue: 12/03/2009 Issue no.: 01 Page 4/15

The contractors

Scale of construction project

Structure of construction project

Architecture of construction work

Technical systems

4.3.2 Requirements of the Owner

Quality of construction work

Completion time of construction work

Execution manners

Other requirements

4.3.3 Scope of work

Scope of project management is based on the memorial minutes which is established

between the Owner and APAVE Vietnam and South East Asia

Scope of work usually consists of:

Support the Owner in project execution, from the investment preparation to the

investment execution

Support the Owner in project execution in the investment completion

Technical design/ construction drawing design verification and estimate of

expenditure

Tender planning, tender organization, tender evaluation and tendering result

submission to the Owner

Negotiation organization, submission to the Owner

Management and operation of construction project, consisting of:

- Quality management

- Quantity management

- Schedule management

- Cost management

- Human resources management

- Risk management

- Communication management

- Procurement management

- Labor safety & Environmental hygiene management

Legality verification of the related works in construction phase.

Verification of acceptance documents, as-built quality/ quantity documents

Supporting the Owner in documents/ records establishment and storage

- Legal documents

Page 5: Xaydung360.Vn_Project Management Plan

APAVE VIET NAM & SOUTHEAST ASIA

Project Management Plan

If any page(s) of this document is found dirty, deficient, torn or unreadable, please inform to be re-supplied.

Code: AVN-CTC-QLDA Date of Issue: 12/03/2009 Issue no.: 01 Page 5/15

- Quality documents

- Material documents

- Labor safety documents

4.3.4 Appointment of Project Director and Project Manager

Project Director

Project Director shall be APAVE Deputy General Director, Branch Managers or

Division Managers depending on the project scale

Project Director shall bear the principle responsibility for executing the requirements

in the contract between APAVE Vietnam and South East Asia and the Owner in

project execution

Project Director shall bear responsibilities to the General Director of APAVE Vietnam

and South East Asia in consequences of management, of Project Management

Board operation and in ensuring the project quality to the contract requirements

Project Manager

Project Manager shall be appointed with rights and responsibilities in order to ensure

that he can bring into play the competence of Project Management Board to satisfy

the Owner’s requirements

4.3.5 Project management for construction works

Basing on the scope of work assigned by the Owner, the construction projects managed by

APAVE Vietnam and South East Asia are divided into the following phases:

4.3.5.1 Design phase

The Big Projects Management Board and APAVE branch offices near the sites shall support

in this phase. It consists of the following affairs :

Planning the organization of a designer selection and an evaluation board (if

needed). The invited designers must have appropriate design experiences.

Organizing a designer selection

Negotiating contract with the design consultant

Deploying preliminary design, technical design and construction drawing design

steps

Supervising and controlling the design process

Supporting the Owner in selecting design solutions

Verifying designs and estimating of expenditure

Reviewing verification results and amending

Submitting drawing designs to the Owner

Submitting cost estimate documents to the Owner

Page 6: Xaydung360.Vn_Project Management Plan

APAVE VIET NAM & SOUTHEAST ASIA

Project Management Plan

If any page(s) of this document is found dirty, deficient, torn or unreadable, please inform to be re-supplied.

Code: AVN-CTC-QLDA Date of Issue: 12/03/2009 Issue no.: 01 Page 6/15

References:

Procedure for verifying the structural design of civil and industrial construction works,

AVN-CTC-P01

Procedure for verifying the cost estimate document, APS-CTC-P03

Instruction for checking the calculation and design of foundation of construction

works, AVN-CTC-P01-I01

Instruction for checking the design calculation of reinforced concrete structure,, AVN-

CTC-P01-I02

4.3.5.2 Tender phase

The Big Projects Management Board and APAVE branch offices near the sites shall support

in this phase. It consists of the following affairs :

Planning the organization of a tendering, ensuring that attending contractors must

know and have much experiences in the same construction works.

Supporting the Owner in approving tender plans.

Supporting the Owner in organizing a Tender Evaluation Board, verifying

consultant’s tender evaluation results, selecting the winner.

Supporting the Owner in establishing Tender selection documents and notifying

tendering results

Supporting the Owner in negotiating contract with selected parties

Submitting contracts to the Owner for approval.

References:

Procedure for consultation of tender arrangement for erection & purchasing of material &

equipment, AVN-CTC-P03

4.3.5.3 Construction phase

Project Management in construction phase includes following processes:

Prepraring process

Planning process

Executing process

Supervising process

Closing process

A) Preparing

Understand the requirements of Owner about the scope of work, schedule to put the

buildings into operation, quality requirement and construction method;

Make the general organization diagram of the project.

Page 7: Xaydung360.Vn_Project Management Plan

APAVE VIET NAM & SOUTHEAST ASIA

Project Management Plan

If any page(s) of this document is found dirty, deficient, torn or unreadable, please inform to be re-supplied.

Code: AVN-CTC-QLDA Date of Issue: 12/03/2009 Issue no.: 01 Page 7/15

Project Management Organization Diagram

Project Management Organization Diagram includes Project Director, Project

Manager, Site Secretary, project management team, supervising team, supportive

departments from company's offices and from APAVE group.

Project Management Board shall receive technical support from APAVE France,

APAVE Malaysia, Big Project Department, Technical Operation Department of

APAVE Viet Nam & Southeast Asia.

Besides, branches of APAVE which are near the project site shall support design

verification, consultation to select tender and human resource.

Make total project schedule to be approved by Owner. Construction schedule shall

be made in accordance with the compensation plan, demolishment, re-establishment

and commision requirement of Owner.

Legal requirement, kick-off conditions and requirements of other organization (if any)

Project's budget.

OWNER

PROJECT MANAGEMENT CONSULTANT

APAVE VN & SEA

DESIGN

CONSULTANT

SUPERVISING

CONSULTANT CONSTRUCTOR

QUALITY CONSTRUCTION

CONTROL

STATE DEPARTMENTS

Page 8: Xaydung360.Vn_Project Management Plan

APAVE VIET NAM & SOUTHEAST ASIA

Project Management Plan

If any page(s) of this document is found dirty, deficient, torn or unreadable, please inform to be re-supplied.

Code: AVN-CTC-QLDA Date of Issue: 12/03/2009 Issue no.: 01 Page 8/15

Page 9: Xaydung360.Vn_Project Management Plan

APAVE VIET NAM & SOUTHEAST ASIA

Project Management Plan

If any page(s) of this document is found dirty, deficient, torn or unreadable, please inform to be re-supplied.

Code: AVN-CTC-QLDA Date of Issue: 12/03/2009 Issue no.: 01 Page 9/15

B) Planning

Planning process for project mangement shall be prepared after the contract between

APAVE Vietnam & South East Asia and the Owner is signed.

Construction management plan shall be made prior to the construction phase and shall

be summited to the Owner for approval before use.

Construction management plan shall includes:

Intergrated mangement plan

- Definition, preparation, integration and cooperation small plans to monitor and

control overall project.

- Establishing procedures for project construction cooperation

- Establishing the plan to monitor and control the general situation of the project.

Reference: Procedure for executive cooperation, AVN-PIM-P01

Scope management plan

- Determining the work, items based on the scope of work stated by the Owner

work, items that belong to structural construction

work, items that belong to M/E

work, items that belong to architecture and finishing work

Other works that are relevant to the protect.

- Establishing the Work Breakdown Structure and numbering work, items

- Making the plan to supervise, take and check over the project.

Schedule management plan

- Determining the order of work, items, including strutural construction, M&E,

architecture

- Estimating the resource to carry out the construction work, items

- Estimate the time to conduct construction work, items

- Make the project schedule

- Make the plan to monitor the construction schedule at site

Cost management plan

- Estimation, budget for the project

- Establishing the procedure to check the payment to contractor

- Acheiving the agreement among the participants about the procedures, forms,

receipts, responsibilities as a legal base for payment

- Making statistic list to record all payments in chronologic order

- Achieve the agreement with Contractor about the payment procedure and and

payment plan

Page 10: Xaydung360.Vn_Project Management Plan

APAVE VIET NAM & SOUTHEAST ASIA

Project Management Plan

If any page(s) of this document is found dirty, deficient, torn or unreadable, please inform to be re-supplied.

Code: AVN-CTC-QLDA Date of Issue: 12/03/2009 Issue no.: 01 Page 10/15

Quality management plan

- Establishing standards related to the project and executive methods

- Building quality objectives

- Building management system and quaility assurance system in accordance with

TCVN ISO 9000

Reference: Quality Manual, AVN-QMS-M

Human resource management plan

- making human resource plan, searching human resources and appointing

personels into appropriate positions corresponding to each construction phase

(including structural construction and infrastructure phase, M&E phase and

finishing phase)

- Responsibilities and reporting level of each position

Communication management plan

- Communication methods, communication hierarchy, weekly meeting plans

- Plans to report the construction schedule to the Owner.

Risk management plan

For longterm project, it's necessary to determine risks that might affect the project,

as well as their characteristics, and reaction plan to minimize their impact.

Materials, equipment supply and procurement management plan

- making plan to assure that materials, equipment shall be supplied in time, in

accordance with construction schedule:

plans to supply materials and equipment for structural items

plans to supply materials and equipment for M&E items

plans to supply materials and equipment for architectural items, fishing work.

- Checking the materials' quality to be supplied

- Checking the origine of materials and equipment, quantity and specifications in

conformity with the design requirement, checking the quality certificate of

equipment and materials

- Plans to manage the supply and procurement contracts.

Document management plan

Establishing procedures to control document and records

Reference: Document control procedure, AVN-QMS-P01

Record control procedure, AVN-QMS-P02

Labor safety and environmental hygiene management plan

Establishing methods and procedures to assure labor safety which is based on the

labor safety codes & standards, labor safety decrees

Page 11: Xaydung360.Vn_Project Management Plan

APAVE VIET NAM & SOUTHEAST ASIA

Project Management Plan

If any page(s) of this document is found dirty, deficient, torn or unreadable, please inform to be re-supplied.

Code: AVN-CTC-QLDA Date of Issue: 12/03/2009 Issue no.: 01 Page 11/15

Establishing plans to collect wastes, garbages, keep the construction site dry and

clean.

Reference: Instruction for labor safety and environmental hygiene, AVN-PIM-I03

C) Executing

Control, coordinate the activities of project based on approved plan.

Apply the system’s procedures to ensure the quality of project.

Make the periodical payment report and balance report to the Owner.

Attend with the Owner to explain the balance report.

Human resource management including the human appointment, ability

improvement and member interface ensures that the project is well done;.

Exchange and supply information in time to right object.

Guide the contractor to implement the labour safety and site sanitary mission.

D) Monitoring, supervising and controlling

The construction project monitoring, supervising and controlling processes ensure that

all the execution works are carried out as requirements, all risk problems are identified in

time so that the reparation action will be performed; and the regular monitoring and

measurement can identify all the changes compared with plan.

Project performance situation supervising and controlling:

- The informations about project performance situation shall be collected and

measured. To make the project performance reports, supply the information

about workload, progress, cost, manpower, quality and risk. All the evaluation of

work’s process and tendency will be performed to ameliorate the process

effectively.

- Project management parts will make the project performance report to Project

Manager.

- Monitor all the design changements (if any).

- Verify, reckon up all the complaint of Contractor and report to the Owner.

- If there is any variation, it should be coordinated with design consultancy,

contractor to make the actuality confirming record , reason of the variation and

report to the Owner.

- Monitor, reckon up and synthetize all the contract breachs of Contractor record

including the loss and report to the Owner.

Reference:

Procedure for supervision work of civil and industrial construction, AVN-CTC-P02

Unified technical procedure for construction inspection, APS-CTC-P02.

Instruction for supervising of civil engineering construction, AVN-CTC-P02-I12

Supervising and quantity management:

Page 12: Xaydung360.Vn_Project Management Plan

APAVE VIET NAM & SOUTHEAST ASIA

Project Management Plan

If any page(s) of this document is found dirty, deficient, torn or unreadable, please inform to be re-supplied.

Code: AVN-CTC-QLDA Date of Issue: 12/03/2009 Issue no.: 01 Page 12/15

- Supervise, reckon up and update the work’s quantity in defined period (monthly).

Work’s quantity shall be supervised by items: structure and infrastructure, M&E

and architecture.

- The verification and comparation compare between the actuality and as-built

drawing of each item is used to confirm the finishing quatity and is basis for the

payment to Contractor from the Owner.

- Base on the work structure in planning stage, to identify the variation of quantity

in project performance process.

- Indentify the reason of variations for the approval of the Owner.

- Confirm the variation quantities.

- Make the periodical report about finishing work to the Owner.

The schedule supervising and controlling:

- Supervise and evaluate the execution progress of Contractor and report to the

Owner for approval.

- Supervise, reckon up and update the actual work on site: starting time and

finishing time of each task. Verify and compare the actual progress with the

approved.

- Propose to the Owner, Contractor the specific and in time method to keep the

schedule.

- Modify the schedule if needed.

- Control all the changes of project’s schedule.

- Identify the reason and period of time of the execution delay.

Cost Supervising and controlling:

- Reckon up all payment situation following time progress.

- Control the change of cost, unit cost.

- Consider the influence of the elements to the changes of project budget and

control these changes.

Project quality upervising and controlling:

- Monitor the quality of these items: structure, M&E, and architect.

- Indentify the way to eliminate the reasons which influence to quality.

Reference:

Instruction for checking the construction of reinforced concrete structure at site,

AVN-CTC-P02-I01

Instruction for steel structure construction checking, AVN-CTC-P02-I02

Instruction for external drainage construction checking, AVN-CTC-P02-I03

Instruction for bored pile and wall in trench construction checking, AVN-CTC-

P02-I04

Instruction for testing piles by P.I.T method, AVN-CTC-P02-I05

Page 13: Xaydung360.Vn_Project Management Plan

APAVE VIET NAM & SOUTHEAST ASIA

Project Management Plan

If any page(s) of this document is found dirty, deficient, torn or unreadable, please inform to be re-supplied.

Code: AVN-CTC-QLDA Date of Issue: 12/03/2009 Issue no.: 01 Page 13/15

Instruction for transformer substation insllation checking, AVN-CTC-P02-I06

Instruction for checking the installation of electric equipment, AVN-CTC-P02-I07

Instruction for electric line and cable installation verification, AVN-CTC-P02-I08

Instruction for grounding system verification, AVN-CTC-P02-I09

Instruction for distribution cubicle system installation verification, AVN-CTC-P02- I10

Instruction for electrical installation verification, AVN-CTC-P02-I11

Project management human resource supervising and controlling:

Supervise the members of project management group, supply, feedback and resolve

all problems and coordinate to ensure the quality of project.

Document and record control: control the document and record maintaining works

following procedure.

Risk monitoring and controlling:

Monitor and reckon up all the factors which influence to execution work such as: the

weather, materials supply, equipment installation, electric and water supply…

Materials procurement:

Monitor and manage the material procurement contract; consider and make the

document of materials supply of supplier. Other variation requirement if needed.

Labour safety and environmental hygiene

Check the labour safety work on site following approved methods and procedures.

E) Closing phase

a) Construction closing

Check all commissioning codition

o Modify the errors when preliminarily commissioning

o Check all commissioning records, quality documents, quantity documents

of Contractors.

o Check the as-built documents of Contractors.

o Verify the cost balance of Contractors.

Set up the commissioning board as authorities requirements.

Make the finishing report.

o Submit to the Owner for approval all technical, balance and as-built

documents.

o Verify the project.

o Make the finishing report of project.

o Hand over the project.

Verify, reckon up all maintained documents

o Legal records

o Quality, commissioning records.

Page 14: Xaydung360.Vn_Project Management Plan

APAVE VIET NAM & SOUTHEAST ASIA

Project Management Plan

If any page(s) of this document is found dirty, deficient, torn or unreadable, please inform to be re-supplied.

Code: AVN-CTC-QLDA Date of Issue: 12/03/2009 Issue no.: 01 Page 14/15

o Materials records.

o Labour safety documents.

o Project’s general logs.

o As-built drawings.

Hand over the documents to the Owner, these documents include both type:

hard copy (paper) and soft copy (on CD). In addition, documents should be

kept in accordance with APAVE’s procedures.

b) Project closing

Finish all activities concerning to project.

Update all the operation procedures to make its more conformable and

perfect.

Finish the contract with the Owner.

5. Annex

Reference list of procedures and instructions

1. Quality Manual AVN-QMS-M

2. Document Control Procedure AVN-QMS-P01

3. Record Control Procedure AVN-QMS-P02

4. Procedure for verifying the structural design of civil and industrial

construction works

AVN-CTC-P01

5. Instruction for checking the calculation and design of foundation of

construction works

AVN-CTC-P01-I01

6. Instruction for checking the design calculation of reinforced concrete

structure

AVN-CTC-P01-I02

7. Procedure for supervision work of civil and industrial construction AVN-CTC-P02

8. Instruction for checking the construction of reinforce concrete

structure at site

AVN-CTC-P02-I01

9. Instruction for steel structure construction checking AVN-CTC-P02-I02

10. Instruction for external drainage construction checking AVN-CTC-P02-I03

11. Instruction for bored pile constructionchecking AVN-CTC-P02-I04

12. Instruction for testing piles by PIT method AVN-CTC-P02-I05

13. Instruction for transformer substation installation checking AVN-CTC-P02-I06

14. Installation for checking the installation of eletric equipment AVN-CTC-P02-I07

15. Installation for electric line and cable installation verification AVN-CTC-P02-I08

Page 15: Xaydung360.Vn_Project Management Plan

APAVE VIET NAM & SOUTHEAST ASIA

Project Management Plan

If any page(s) of this document is found dirty, deficient, torn or unreadable, please inform to be re-supplied.

Code: AVN-CTC-QLDA Date of Issue: 12/03/2009 Issue no.: 01 Page 15/15

16. Instruction for grounding system verification AVN-CTC-P02-I09

17. Instruction for distribution cubicle system installation verification AVN-CTC-P02-I10

18. Instruction for electrical installation verification AVN-CTC-P02-I11

19. Procedure for consultation of tender arrangement for erection and

purchasing of materials & equipment

AVN-CTC-P03

20. Unified technical procedure for construction inspection APS-CTC-P02

21. Procedure for verifying the cost estimate document AVN-CTC-P7

22. Procedure for executive cooperation AVN-PIM-I01

23. Instruction for labor safety and environmental hygiene AVN-PIM-I03