Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
• The 2014 Sales Surtax Program made significant progress ‐ BUT
• Capital investment needs are ongoing not a point in time
• Two focal points –• Reduce backlog• Preventive not just reactive maintenance!
Why is This Important?• Connection to learning
• Facilities and educational technology matter to teaching and learning
• Improve reliability of building systems• Preserving our assets – changing the paradigm
• Fixing only failures is at the expense of preserving the good
• Replacing/repairing at failure significantly more expensive than preventive maintenance
• Investment in the community• Since 2015 – almost $200 million has been locally invested in construction
Approach - Overview• 2014 resources first, then renewal
• Some overlap, some differences• Data‐driven approach
• Security• Educational Technology• Facilities• Classrooms• Athletics• Playgrounds
• Prioritized safety, security, learning environment and asset preservation
Approach – Revenue• 2014 Sales Surtax
• Projecting about $67 million over the $198 million program target (about 90% of 2019 revenues) – through Feb. 2021
• Allocated $37 million through ICOC/School Board• $25 million – facility renewal• $2 million – educational technology• $10 million ‐ security
• About $30 million left to allocate• Considered this first in allocating to eligible work in each group• Ready to recommend $18 million in projects to ICOC in August• Remaining $12 million
• Buffer against revenue decline or increased project costs
• Additional resources may be available as all projects conclude• Estimating $3‐5 million• Planning smaller projects at schools with resources remaining
Approach – Revenue
• Renewal• Projecting roughly $40 million per year to BPS
• Total revenue $281 million• $36 million to charter schools• $245 million to BPS
• Unpredictable variables• COVID effect on sales surtax revenue• Sales surtax revenue apportioned based on BPS and charter school enrollment
Approach – Overview
• Plan based on $40 million per year revenue to BPS• Proposed program totals $221 million with $19 million unallocated
• Implementation planned by year• More revenue – move faster• Less revenue – move slower
• Design work can proceed to have shovel‐ready projects
• More elements can be funded with 2014 sales surtax if resources are available
Approach – Security
• Started with security assessment• Evaluated elements that can be done with 2014 sales surtax• Several Priority 1 elements programmed with current surtax
• Priority 2 and 3 capital and technology elements• Sustainable with current operating staff and budgets
• Prioritized within the 6 year time frame based on consultant’s recommendations, District Security input
Approach – Educational Technology
• Provided estimated targets to educational technology for current surtax and renewal
• Educational technology team provided recommended use of funds by school and a few District‐wide projects
Approach – Facilities
• Facility renewal approach relied heavily on facility assessment data• Recommended action time frame to prioritize
• Roof renewal was most significant need• Combined multi‐year projects into earliest year
• Then focused on classroom renewal• Prioritized based on component condition assessment• Prioritized based on priority school status
• Then paint• Interior and exterior at every school
Approach – Facilities
• Then electrical • Then HVAC ‐ input from facility assessment, project mangers, plant operations team• Moved as much HVAC as possible to current surtax
• Then water and sewer• Then other infrastructure needs• Adjusted cost estimates to reflect full costs, local conditions
• Leaves about 10% unallocated
Review Sales Surtax Renewal PlanFinancial Summary Summary by Group
Summarized by FacilityFacility Renewal Detail Workshop Book – Pages 4‐22
Recommended Allocation*
Roof Renewal 66,657,851$ 30.14%Educational Technology 34,823,768$ 15.75%Security 27,616,610$ 12.49%Classroom Renewal 23,419,221$ 10.59%Electrical Renewal 21,269,926$ 9.62%HVAC Renewal 16,056,717$ 7.26%Water and Sewer System Renewal 11,053,667$ 5.00%Paint ‐ Interior & Exterior 9,000,000$ 4.07%Athletic Facility Renewal 3,150,000$ 1.42%Playground Renewal 2,560,000$ 1.16%Building System Renewal 1,808,111$ 0.82%Structural Pavilion Renewal 1,275,000$ 0.58%Safety ‐ Gym Bleachers Renewal 1,120,000$ 0.51%Safety ‐ Stadium Bleachers 800,000$ 0.36%Auditorium Renewal 373,657$ 0.17%Pool Equipment Room Renewal 150,000$ 0.07%
Grand Total 221,134,527$ 100.00%
*Renewal Funds Only
Facility Assessment Summary
• Assessment reported direct costs
• Factored up to account for all project costs• Roof x 1.5• Electrical x 1.5• Plumbing x 3
• Some items – “study to evaluate” – does not reflect cost to fix
Discipline/Priority1 ‐ Currently Critical (1
Year)2 ‐ Potentially Critical
(2 Years)3 ‐ Necessary ‐ Not Yet
Critical (3 ‐ 5 Years)4 ‐ Recommended (6 ‐
11 Years)Grand Total
ADA Assessement Items 783,553$ 282,851$ 12,470$ 1,078,874$ Architectural 30,090,812$ 52,874,791$ 112,091,602$ 119,526,177$ 314,583,382$ Civil 1,047,955$ 1,977,359$ 10,580,274$ 6,562,697$ 20,168,285$ Communications 156,687$ 195,269$ 8,669,451$ 9,021,407$ Electrical 5,497,164$ 7,645,939$ 76,035,616$ 11,590,547$ 100,769,267$ Fire Protection 225,196$ 150,771$ 42,312$ 162,230$ 580,509$ Mechanical 7,463,029$ 1,913,053$ 27,962,300$ 22,589,012$ 59,927,394$ Plumbing 894,971$ 1,266,852$ 3,982,297$ 2,084,282$ 8,228,401$ Safety and Security 118,411$ 1,377,440$ 7,927,769$ 11,997,131$ 21,420,751$ Structural 678,664$ 2,625,764$ 1,828,179$ 318,037$ 5,450,643$
Grand Total 46,016,202$ 70,772,209$ 240,928,467$ 183,512,034$ 541,228,913$
Source ‐ State of Our Schools ‐ 21st Century School Fund; U.S. Green Building Council (USGBC), The Center for Green Schools; National Council on School Facilities (NCSF) ‐ 2016
Industry Standards*• Current Replacement Value (CRV) All Facilities –Over $2 Billion• 3% of CRV annual maintenance and operation
• $60 million• 2% of CRV annual facility renewal
• $40 million• 1% of CRV annual as needed alterations
• $20 million• 1% of CRV annual reduction of deferred maintenance
• $20 million
*Goal is to move closer to industry standards with time
RealitySurtax Impact
• $28 million per year facility renewal
• $6 million per year educational technology
• $6 million per year security
Capital Only FY 21
• $7.4 million facility renewal
• $5.2 million educational technology
• $2 million security
Sales surtax is has been highly impactful towards maintaining our facilities infrastructure and investing in security and technology
Next Steps
• Board feedback on content of plan• ICOC review and feedback August 19
• Recommend allocation percentages for School Board Policy development (update or replace Policy 6180.02)
• Initiate Policy development/modification process• Procurement solicitations:
• Roof renewal design/design build projects• Security project
• Start planning & design for summer 2021 projects