Facilities Services 2700 Judge Fran Jamieson Way Viera, Florida 32940-6601 Campus Capital Needs Sales Surtax Funded Attachment F Estimate Detail Report Condition Code Facility Edgewood Jr./Sr. High 1.52 $634,405 District School Security $106,561 1.00 Perimeter/Entry Fencing and Gates $67,319 Pedestrian Access and Safety (Fencing) 1.00 $67,319 Building Access Security Equipment $39,242 Public Access Control 1.00 $39,242 Educational Technology $120,586 2.00 Technology Building Cabling $10,007 Structured Cabling 4.00 $10,007 Technology Equipment Renewal $110,580 Computer Replacement 3.00 $39,896 Server Replacement 1.00 $23,578 Switch Replacement 1.00 $30,592 Telephone System Replacement 1.00 $16,514 Facility Renewal $407,257 1.44 Cooling and Heating Control System Renewal $134,076 Building Automation System 2.00 $134,076 Roofing System Renewal $144,000 Relocatable Covered Walkways (SREF) 1.00 $144,000 Exterior Building Wall Finish System Renewal $43,368 Expansion / Control Joints 1.00 $2,343 Exterior Finish 2.00 $19,813 Sealants 2.00 $10,335 Soffits 1.00 $6,192 Thermal Condition 2.00 $4,685 Exterior Door/Window/Louver System Renewal $2,807 Main Entry Doors 2.00 $2,807 Building Water and Sanitary Piping System Renewal $33,140 Sanitary Piping 1.00 $23,343 Supply Piping 1.00 $9,797 Water Heating System Renewal $2,449 Water Heaters 2.00 $2,449 Air Supply and Exhaust System Renewal $47,417 Exhaust Fans Art Kiln Room, Locker Rooms, Restrooms, Science 1.00 $47,417 July 22, 2014

Attachment F - Brevard Public Schools · Edgewood Jr./Sr. High 1.52 $634,405 District School Security 1.00 $106,561 ... 53 07 Roofing System Renewal $144,000.00 $144,000.00 ... Cambridge

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Attachment F - Brevard Public Schools · Edgewood Jr./Sr. High 1.52 $634,405 District School Security 1.00 $106,561 ... 53 07 Roofing System Renewal $144,000.00 $144,000.00 ... Cambridge

Facilities Services2700 Judge Fran Jamieson WayViera, Florida 32940-6601

Campus Capital Needs Sales Surtax Funded

Attachment F

Estimate

Detail ReportCondition CodeFacility

Edgewood Jr./Sr. High 1.52 $634,405District School Security $106,5611.00

Perimeter/Entry Fencing and Gates $67,319Pedestrian Access and Safety (Fencing) 1.00 $67,319

Building Access Security Equipment $39,242Public Access Control 1.00 $39,242

Educational Technology $120,5862.00

Technology Building Cabling $10,007Structured Cabling 4.00 $10,007

Technology Equipment Renewal $110,580Computer Replacement 3.00 $39,896Server Replacement 1.00 $23,578Switch Replacement 1.00 $30,592Telephone System Replacement 1.00 $16,514

Facility Renewal $407,2571.44

Cooling and Heating Control System Renewal $134,076Building Automation System 2.00 $134,076

Roofing System Renewal $144,000Relocatable Covered Walkways (SREF) 1.00 $144,000

Exterior Building Wall Finish System Renewal $43,368Expansion / Control Joints 1.00 $2,343Exterior Finish 2.00 $19,813Sealants 2.00 $10,335Soffits 1.00 $6,192Thermal Condition 2.00 $4,685

Exterior Door/Window/Louver System Renewal $2,807Main Entry Doors 2.00 $2,807

Building Water and Sanitary Piping System Renewal $33,140Sanitary Piping 1.00 $23,343Supply Piping 1.00 $9,797

Water Heating System Renewal $2,449Water Heaters 2.00 $2,449

Air Supply and Exhaust System Renewal $47,417Exhaust Fans Art Kiln Room, Locker Rooms, Restrooms, Science 1.00 $47,417

July 22, 2014

Page 2: Attachment F - Brevard Public Schools · Edgewood Jr./Sr. High 1.52 $634,405 District School Security 1.00 $106,561 ... 53 07 Roofing System Renewal $144,000.00 $144,000.00 ... Cambridge

Exhibit B ‐‐ Sales Surtax Summary Form

Edgewood Jr./Sr. High SchoolConstruction Manger Firm Name: Canaveral  

Date: February 15, 2020

DISTRICT SCHOOL SECURITY60 01 Perimeter/Entry Fencing and Gates60 02 Building Access and Security Equipment

EDUCATIONAL TECHNOLOGY65 01 Technology Building Cabling65 02 Technology Equipment Renewal65 03 Classroom Technology Infrastructure (Electrical, HVAC, Data)

FACILITY RENEWAL50 00 Facility Renewal (design and preconstsruction) $178,412.00 ‐$178,412.0051 01 Safety and Building Code Deficiency Corrections51 02 ADA Code Deficiency Correction51 03 Fire Alarm System Renewal52 04 Central Mechanical Plant Renewal $312,389.43 ‐$312,389.4352 05 Cooling and Heating Control System Renewal $442,093.52 $134,076.00 ‐$308,017.5252 06 Air Conditioning and Air Distribution Equipment Renewal $580,500.78 ‐$580,500.7853 07 Roofing System Renewal $144,000.00 $144,000.0053 08 Exterior Building Wall Finish System Renewal $172,438.96 $43,368.00 ‐$129,070.9653 09 Exterior Door/Window/Louver System Renewal $2,807.00 $2,807.0052 10 Building Water and Sanitary Piping System Renewal $33,140.00 $33,140.0052 11 Water Heating System Renewal $2,449.00 $2,449.0054 12 Electrical Supply System (Transformers, Switchgear, Wiring) Renewal $47,417.00 $47,417.0054 13 Electrical Distribution System Renewal $172,314.01 ‐$172,314.0154 14 Electrical Components (Lightning Protection, Intercom, Generator) Renewal*54 15 Interior and Exterior Lighting Equipment Renewal52 16 Air Supply and Exhaust System Renewal55 17 Site Utility Systems (Gas, Electric, Storm, Water, Sanitary) Renewal $304,838.42 ‐$304,838.42

Contingency previously applied  ‐$64,700.00 $64,700.00Reserve for covered walkways $144,000.00 ‐$144,000.00Additional administration and permitting $10,000.00 ‐$10,000.00Sales surtax supplement ‐$1,550,000.00 $1,550,000.00Sales surtax supplement ‐ drainage  ‐$305,000.00 $305,000.00

 

$1,984,575.12 $407,257.00 ‐$1,587,288.00 $9,969.88

BalanceAttachment F Spent & EncumberedGroup/Category Description Proposed Price

Page 3: Attachment F - Brevard Public Schools · Edgewood Jr./Sr. High 1.52 $634,405 District School Security 1.00 $106,561 ... 53 07 Roofing System Renewal $144,000.00 $144,000.00 ... Cambridge

Month Year Revenue Cumulative Security 50% ET 15% Facilities 35% Total

August  2019 $1,294,012 $1,294,012 $647,006 $194,102 $452,904 $1,294,012September 2019 $3,474,204 $4,768,216 $1,737,102 $521,131 $1,215,971 $3,474,204October 2019 $3,440,101 $8,208,317 $1,720,051 $516,015 $1,204,035 $3,440,101November 2019 $4,526,234 $12,734,551 $2,263,117 $678,935 $1,584,182 $4,526,234December 2019 $3,425,373 $16,159,924 $1,712,687 $513,806 $1,198,881 $3,425,373January 2020 $3,477,814 $19,637,738 $1,738,907 $521,672 $1,217,235 $3,477,814February 2020 $5,420,075 $25,057,813 $2,710,038 $813,011 $1,897,026 $5,420,075March  2020 $3,315,493 $28,373,306 $1,657,747 $497,324 $1,160,423 $3,315,493April 2020 $3,355,854 $31,729,160 $1,677,927 $503,378 $1,174,549 $3,355,854May  2020 $5,389,791 $37,118,951 $2,694,896 $808,469 $1,886,427 $5,389,791June 2020 $3,554,107 $40,673,058 $1,777,054 $533,116 $1,243,937 $3,554,107July 2020 $3,574,694 $44,247,752 $1,787,347 $536,204 $1,251,143 $3,574,694August 2020 $4,954,442 $49,202,194 $2,477,221 $743,166 $1,734,055 $4,954,442September 2020 $3,474,204 $52,676,398 $1,737,102 $521,131 $1,215,971 $3,474,204October 2020 $3,440,101 $56,116,499 $1,720,051 $516,015 $1,204,035 $3,440,101November 2020 $4,526,234 $60,642,733 $2,263,117 $678,935 $1,584,182 $4,526,234December 2020 $3,425,373 $64,068,106 $1,712,687 $513,806 $1,198,881 $3,425,373January 2021 $3,477,814 $67,545,920 $1,738,907 $521,672 $1,217,235 $3,477,814February 2021 $5,420,075 $72,965,995 $2,710,038 $813,011 $1,897,026 $5,420,075

Total $72,965,995 $35,835,992 $10,750,797 $25,085,194 $72,965,995Estimated based on prior year receipts

Approved/Requested Allocations: Security ET Facilities Total Original Amount Reduction

Repayment of temporary transfer ‐ security to facilities 9,332,130.58$          9,332,130.58$      Allocation to security previously approved but not used) 280,144.46$              280,144.46$         Building Automation System plan (Board approved September 24, 2019) ‐ under study ‐ defer 200,000$                200,000.00$         Columbia, McAuliffe, Challenger 7 HVAC (Board approved September 24, 2019) 7,000,000$            7,000,000.00$       Board agenda 3/10Computer replacement (Board approved September 24, 2019) 500,000$                500,000.00$         Longleaf Elementary facility renewal ‐ GMP pending ICOC Approved 12/11/2019 250,000$                250,000.00$          Board agenda 3/10Cocoa Beach High facility renewal ‐ GMP pending ICOC Approved 12/11/2019 1,000,000$            1,000,000.00$      Satellite High facility renewal ‐ GMP pending ICOC Approved 12/11/2019 1,200,000$            1,200,000.00$      Mims Elementary facility renewal ‐ supplemental funding ICOC Approved 12/11/2019 1,200,000$            1,200,000.00$       Board agenda 1/28McNair Elementary facility renewal ‐ supplemental funding ICOC Approved 12/11/2019 950,000$                950,000.00$          Board agenda 3/10 $1,000,000 50,000$                   Edgewood Jr./Sr. High facility renewal ‐ supplemental funding ICOC Approved 12/11/2019 1,550,000$            1,550,000.00$       Board agenda 3/10 $1,600,000 50,000$                   Additional allocation Columbia, McAuliffe, Challenger 7 HVAC ICOC Approved 12/11/2019 2,000,000$            2,000,000.00$       Board agenda 3/10Cambridge Elementary facility renewal ‐ supplemental request  ICOC Approved 01/09/2020 700,000$                700,000.00$          Board agenda 1/14Enterprise Elementary facility renewal ‐ supplemental request  ICOC Approved 01/09/2020 650,000$                650,000.00$          Board agenda 1/14Titusville High facility renewal ‐ supplemental request ICOC Approved 01/09/2020 770,000$                770,000.00$          Board agenda 1/14Imperial Estates facility renewal ‐ supplemental request  ICOC Approved 01/09/2020 520,000$                520,000.00$          Board agenda 1/14Astronaut High facility renewal ‐ supplemental request ICOC Approved 01/09/2020 460,000$                460,000.00$          Board agenda 1/28Space Coast Jr./Sr. High facility renewal ‐ supplemental request ICOC Approved 01/09/2020 300,000$                300,000.00$          Board agenda 1/28 $450,000 150,000$                 Suntree Elementary  ICOC Approved 01/09/2020 ‐$                        ‐$                        Board agenda 2/11 $240,000 240,000$                 Manatee Elementary ‐ supplemental request ICOC Approved 01/09/2020 400,000$                400,000.00$          Board agenda 1/28 $460,000 60,000$                   Sunrise Elementary  ICOC Approved 01/09/2020 230,000$                230,000.00$          Board agenda 2/11 $270,000 40,000$                   Gardendale Alternative Learning Center ‐ GMP pending ICOC Approved 01/09/2020 200,000$                200,000.00$         Clearlake Adult Education Center  ICOC Approved 01/09/2020 300,000$                300,000.00$         Cocoa Beach Jr./Sr. High AHU 8.2  ICOC Approved 01/09/2020 200,000$                200,000.00$          Board agenda 1/14Bayside High structural repair ‐ GMP pending ICOC Approved 01/09/2020 400,000$                400,000.00$         Jupiter Elementary ‐ GMP pending ICOC Approved 01/09/2020 100,000$                100,000.00$          Board agenda 3/10Riviera Elementary ‐ GMP pending ICOC Approved 01/09/2020 250,000$                250,000.00$          Board agenda 3/10 $300,000 50,000$                   Palm Bay High (roof top AHUs Building 7 and elevator)  ICOC Approved 01/09/2020 500,000$                500,000.00$          Board agenda 2/11Palm Bay High (3 new chillers) ‐ pending further investigation ICOC Approved 01/09/2020 1,400,000$            1,400,000.00$      

Gardendale (additional allocation) ICOC Approved 2/19/2020 100,000$               Longleaf (additional allocation) ICOC Approved 2/19/2020 200,000$                Board agenda 3/10Satellite High School (additional allocation) ICOC Approved 2/19/2020 200,000$               Cambridge building automation system ICOC Approved 2/19/2020 340,000$                Board agenda 3/10 350,000$                 10,000$                   Riviera (additional allocation) ICOC Approved 2/19/2020 ‐$                        Board agenda 3/10 40,000$                   40,000$                   Jupiter (additional allocation) ICOC Approved 2/19/2020 5,000$                    Board agenda 3/10 40,000$                   35,000$                   Viera High School ‐ supplemental request ICOC Approved 2/19/2020 680,000$                Board agenda 3/10 700,000$                 20,000$                   Creel (security request) ICOC Approved 2/19/2020 400,000$                  Educational technology ‐ computer refreshment ICOC Approved 2/19/2020 1,500,000$           Palm Bay High ‐ defer chiller replacement pending further investigation ICOC Approved 2/19/2020 (1,000,000)$          Building automation system study (defer) ICOC Approved 2/19/2020 (200,000)$             Edgewood drainage ICOC Approved 2/19/2020 305,000$                Board agenda 3/10 $320,000 15,000$                   

Total Allocation 10,012,275$              2,000,000$            23,360,000$          35,372,275$          $760,000

Net Remaining Allocation 25,823,716$              8,750,797$            1,725,194$            37,593,720$         

February 19, 2020 ICOC agendaChanges from prior approved allocation

Projected Revenue over $198 Million Preliminary Recommended Distribution

Updated 02/23/2020

Page 4: Attachment F - Brevard Public Schools · Edgewood Jr./Sr. High 1.52 $634,405 District School Security 1.00 $106,561 ... 53 07 Roofing System Renewal $144,000.00 $144,000.00 ... Cambridge
Page 5: Attachment F - Brevard Public Schools · Edgewood Jr./Sr. High 1.52 $634,405 District School Security 1.00 $106,561 ... 53 07 Roofing System Renewal $144,000.00 $144,000.00 ... Cambridge
Page 6: Attachment F - Brevard Public Schools · Edgewood Jr./Sr. High 1.52 $634,405 District School Security 1.00 $106,561 ... 53 07 Roofing System Renewal $144,000.00 $144,000.00 ... Cambridge
Page 7: Attachment F - Brevard Public Schools · Edgewood Jr./Sr. High 1.52 $634,405 District School Security 1.00 $106,561 ... 53 07 Roofing System Renewal $144,000.00 $144,000.00 ... Cambridge
Page 8: Attachment F - Brevard Public Schools · Edgewood Jr./Sr. High 1.52 $634,405 District School Security 1.00 $106,561 ... 53 07 Roofing System Renewal $144,000.00 $144,000.00 ... Cambridge
Page 9: Attachment F - Brevard Public Schools · Edgewood Jr./Sr. High 1.52 $634,405 District School Security 1.00 $106,561 ... 53 07 Roofing System Renewal $144,000.00 $144,000.00 ... Cambridge
Page 10: Attachment F - Brevard Public Schools · Edgewood Jr./Sr. High 1.52 $634,405 District School Security 1.00 $106,561 ... 53 07 Roofing System Renewal $144,000.00 $144,000.00 ... Cambridge
Page 11: Attachment F - Brevard Public Schools · Edgewood Jr./Sr. High 1.52 $634,405 District School Security 1.00 $106,561 ... 53 07 Roofing System Renewal $144,000.00 $144,000.00 ... Cambridge
Page 12: Attachment F - Brevard Public Schools · Edgewood Jr./Sr. High 1.52 $634,405 District School Security 1.00 $106,561 ... 53 07 Roofing System Renewal $144,000.00 $144,000.00 ... Cambridge
Page 13: Attachment F - Brevard Public Schools · Edgewood Jr./Sr. High 1.52 $634,405 District School Security 1.00 $106,561 ... 53 07 Roofing System Renewal $144,000.00 $144,000.00 ... Cambridge
Page 14: Attachment F - Brevard Public Schools · Edgewood Jr./Sr. High 1.52 $634,405 District School Security 1.00 $106,561 ... 53 07 Roofing System Renewal $144,000.00 $144,000.00 ... Cambridge