Bronx Community College Work In Progress Formally beginning in January 2020, projects that are funded and entering the Work In Progress stage, as agreed by CUCF and BCC, and all projects in construction will be required to have a poster documenting: The Project Name Anticipated Date of Completion Key Partners, Sponsors or Contractors Key Contact Information Permit Information as required The posters will be displayed: at the project location on the college website – A&F /Work In Progress In the Campus Service Center – digital board This PowerPoint will be updated with all project signage. Contractors will be required to provide a digital version of the mandated signage for inclusion.

WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

Bronx Community College – Work In Progress

• Formally beginning in January 2020, projects that are funded and entering the Work In Progress stage, as agreed by CUCF and BCC, and all projects in construction will be required to have a poster documenting:• The Project Name• Anticipated Date of Completion • Key Partners, Sponsors or Contractors• Key Contact Information • Permit Information as required

• The posters will be displayed:• at the project location • on the college website – A&F /Work In Progress• In the Campus Service Center – digital board

• This PowerPoint will be updated with all project signage.• Contractors will be required to provide a digital version of the

mandated signage for inclusion.

Page 2: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

AG Bridge Replacement

General Contractor:ProCon Group, Inc.2351 Hylan BoulevardStaten Island, New York 10306

Architect:Superstructures32 Avenue of The Americas New York, NY 10013

Reconstruction of the bridge

Construction Manager: DASNY 515 Broadway Albany, NY 12207

Fall 2019

Page 3: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Fire Alarm Upgrade – Phase I

General Contractor:Siemens 8 Fernwood Road Florham Park, NJ 07932

Architect:Siemens 8 Fernwood Road Florham Park, NJ 07932

Fire Alarm Upgrade in Meister Hall, Gould Memorial Library, Carl PolowczykHall, New Hall

Construction Manager:CUNY FPCMBCC

Spring 2020

Page 4: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

MER Re-piping

General Contractor:ACS Systems Associates, INC. 160 W. Lincoln AveMount Vernon, NY 10550

Partners:New York Power Authority CUNY FPCMBCC

Replace all MTHW piping to steam generators and heat exchangers in

18 buildings

Construction Manager:LIRO ENGINEERS, INC.3 Aerial WaySyosset, New York 11791

Fall 2019

Page 5: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Utility Upgrade Phase IV

General Contractor:Stalco Construction, Inc.1316 Motor Parkway Islandia, New York 11749

Partners:New York Power Authority CUNY FPCMBCC

Utility and Mechanical Upgrades at East and Southwest Campus,

Building a new Electrical Service Building. Construction Manager:LIRO ENGINEERS, INC.3 Aerial WaySyosset, New York 11791

Spring 2020

Page 6: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Utility Upgrade Phase V

General Contractor:A.K.S. International Inc. 37-04 19th Avenue Astoria, NY 11105

Partners:New York Power Authority CUNYBCC

Electrical Infrastructure Upgrade Construction Manager:LIRO ENGINEERS, INC.3 Aerial WaySyosset, New York 11791

Fall 2022

Page 7: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

RBSC Roof & Façade Rehabilitation

General Contractor:Imperium Construction Inc.338 Scholes Street, Brooklyn, NY

Architect:Urbahn Architects9 WEST 37TH ST, 6TH FLNEW YORK, NY 10018

Restoration of the Exterior Building Envelope

Construction Manager: DASNY 515 Broadway Albany, NY 12207

Fall 2020

Page 8: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Colston and Community Local Law 11

General Contractor: A1 Contraction Services2468 N Jerusalem Rd Bellmore NY 11710

Architect:Superstructures32 Avenue of The Americas New York, NY 10013

Local Law 11, NYC requires buildings over 6 stories have their exterior walls inspected every 5-years . This project implements the recommendations from that inspection.

Construction Manager:DASNY 515 Broadway Albany, NY 12207

Summer 2020

Page 9: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Gould Memorial Library – Rotunda Egress Stair

General Contractor: M&J Electrical Contractors 23-24 Steinway StreetAstoria NY 11105

Architect:EASTON ARCHITECTS, LLP 20 W 44TH STREET, SUITE 604 NEW YORK, NY 10036

To provide rear egress stairs from the Rotunda Construction Manager:DASNY 515 Broadway Albany, NY 12207

Fall 2020

Page 10: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Gould Memorial Library Roof and Dome Restoration

General Contractor: Nicholson & Galloway, INC261 Glen Head RDGlen Head, NY 11545

Architect:Beyer Blinder BelleArchitects & Planners LLP120 Broadway, 20th FloorNew York, NY 10271

New copper cladding dome roof, cupola and new roof drains

Construction Manager: TDX330 Seventh Ave, 5th Floor New York, NY 10001

Spring 2021

Page 11: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Automotive/Fuel Technology (CUNY 2020)

General Contractor:Constructomics, LLC 40 Broad Street, 4th Floor New York, New York 10004

Architect:Graf & Lewent Architects LLP90-30 161st Street Jamaica, NY 11432

Renovation of Patterson Garage for Automotive Technology Program and Meister Hall 2nd FL sustainable fuel and product development lab

Construction Manager:DASNY 515 Broadway Albany, NY 12207

Fall 2020

Page 12: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Snow Hall Elevator

Architect:CURTIS+ GINSBERG Architects LLC 299 Broadway, Suite 1107 New York, NY 10007

Install New Elevator

Construction Manager:DASNY 515 Broadway Albany, NY 12207

Spring 2021

Page 13: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Bronx Express

General Contractor: TBD

Architect:Dattner Architects D.P.C. 1385 Broadway, 15th Floor New York NY 10018

Renovation of Former Library in Meister for use as a One-Stop Student Center for Enrollment Management: Admission, Registration, Financial Aid, Bursar

Construction Manager: TDX330 Seventh Ave, 5th Floor New York, NY 10001

Spring 2022

Page 14: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Fire Alarm Upgrade – Phase II

General Contractor:TBD

Architect:Siemens 8 Fernwood Road Florham Park, NJ 07932

Fire Alarm - 12 Bldgs: (Nichols, Bliss, Alumni, Gould, Guggenheim, Philosophy, Loew, Colston, Community, Havemeyer Lab & Annex, Language and Butler Halls)

Construction Manager:CUNY FPCM BCC

TBD

Page 15: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Meister Hall – Lighting Upgrade

O’Brian and Gere Partners:DCASNew York Power Authority CUNY FPCMBCC

Redesign lighting layouts and upgrade to LED source technology for energy efficiency and visual performance

TBD

Page 16: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Meister Hall Lab STEM Resource Center

General Contractor:TBD

Architect:Graf & Lewent Architects LLP90-30 161st Street Jamaica, NY 11432

Construction Manager:DASNY 515 Broadway Albany, NY 12207

TBD

Page 17: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Ohio Field Track Restoration

Architect:SARATOGA ASSOCIATES4 Congress Park Centre, 21 Congress St Suite 201, Saratoga Springs NY 12866

Replace existing track, baseball and soccer field

Construction Manager:DASNY 515 Broadway Albany, NY 12207

In Design

Page 18: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Loew Hall Accessibility and Elevator

Architect:Graf & Lewent Architects LLP90-30 161st Street Jamaica, NY 11432

Installation of new fully accessible elevator and main entrance vestibule door

In Design

Page 19: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

New Hall Plaza and Façade Rehabilitation

General Contractor:TBD

Architect:AHUJA PARTNERSHIP ARCHITECTS 200 Varick Street, Suite 512New York, NY 10014

Replacement of plaza roofing system, façade repairs and provide ADA access to front entrance

Construction Manager:DASNY 515 Broadway Albany, NY 12207

In Design

Page 20: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Bliss Hall ADA Restrooms and Entrance Ramp

General Contractor:

Architect:H2M Architects & Engineers31 Penn Plaza/132 West 31st Street, Suite 604 New York, New York 10001

To provide access to the Building and Restroom

Construction Manager:DASNY 515 Broadway Albany, NY 12207

In Design

Page 21: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Alumni Gymnasium Locker Room Restrooms

General Contractor:Architect:H2M Architects & Engineers31 Penn Plaza/132 West 31st Street, Suite 604 New York, New York 10001

Upgrading both male and female toilets and shower room

Construction Manager:DASNY 515 Broadway Albany, NY 12207

In Design

Page 22: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Nichols Hall – Entrance Ramp

General Contractor: TBD

Architect:LI·SALTZMAN ARCHITECTS, P.C. 50 BROADWAY 33RD FLR, NY, NY 10004

ADA accessibility to main entrance Construction Manager:

In Design

Page 23: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

NL Library Flooring Replacement

Contractor:GP Flooring32 Marway CircleGates, NY 14624

Bronx Community College

Replacement of Cork Flooring in Main Reading Room

Winter 2019 -2020

Page 24: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Meister 5th FL - MLT New Lockers

Vendor:Young Equipment

Bronx Community College

Installation of 3 sets of lockers

Spring 2020

Page 25: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Entrance Door Mats

Vendor:Knight Marketing Corporation of NY

Bronx Community College

New entrance door mats Campus Wide

June 2020

Page 26: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Gould Hall – Outdoor Fitness Center

Spring – Fall 2020

Page 27: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Havemeyer Bathroom Upgrade

Bronx Community College

Renovate Women's and Men's Public Restroom

Fall 2020

Page 28: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

BUILDING INTENSIVE CLEAN – Bliss Hall

Building Intensive Clean Programs customize and prioritize a more focused cleaning and repair effort that also provides critical remedial work specific to a building and in partnership with the building occupants.

Summer 2020

Page 29: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

BUILDING INTENSIVE CLEAN–GREENHOUSE

Gardening Club will provide seedlings and support

PPS Laborers will clean debris and Carpentry shop will rebuild planting tables

To clean and restore basic use of greenhouse

Summer 2020

Page 30: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Campus Wide Elevator Remediation

General Contractor:Slade Elevator

Bronx Community College

Meister Hall, Colston Hall, Roscoe Brown, Loew Hall, North Hall, CPH, Community Hall, Children’s Center

Spring 2020

Page 31: WORK IN PROGRESS - Bronx Community College · 2020-02-14 · Bronx Community College –Work In Progress •Formally beginning in January 2020, projects that are funded and entering

To report a concern or unsafe condition at the worksite call 311 or Public Safety at 718-289-5911

ANTICIPATED COMPLETION:

For Additional Information: 718-289-5905

WORK IN PROGRESS

DASNYDORMATORY AUTHORITY STATE NEW YORK

Nichols Elevator Restoration

Bronx Community College

Refurbishment of existing elevator

Summer 2020