Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
|
WECC JSIS Meeting
Heng (Kevin) Chen and Lin Zhang, EPG
Yanfeng Gong and Qiushi Wang, AEP
May 17, 2018
|
▪ Acknowledgment: This material is based upon work supported by the Department ofEnergy under Award Number DE-OE0000850.
▪ Disclaimer: This report was prepared as an account of work sponsored by an agencyof the United States Government. Neither the United States Government nor anyagency thereof, nor any of their employees, makes any warranty, express or implied,or assumes any legal liability or responsibility for the accuracy, completeness, orusefulness of any information, apparatus, product, or process disclosed, orrepresents that its use would not infringe privately owned rights. Reference hereinto any specific commercial product, process, or service by trade name, trademark,manufacturer, or otherwise does not necessarily constitute or imply itsendorsement, recommendation, or favoring by the United States Government or anyagency thereof. The views and opinions of authors expressed herein do notnecessarily state or reflect those of the United States Government or any agencythereof.
© Electric Power Group 2018. All rights reserved1
| 2
▪ Project Introduction
▪ Background
▪ Technical Merit
▪ Technical Approach
▪ Research and System Design
▪ Testing
– Preliminary Simulation Studies
– AEP PMU Deployment and PSCAD Simulation Studies
– 1 Hour Field PMU Data
▪ Current Status & Next Steps
▪ Q&A
© Electric Power Group 2018. All rights reserved
|
▪ DOE/OE and DOE/NETL
– Phil Overholt, Program Manager and Alicia Dalton-Tingler, Project Officer
▪ American Electric Power (AEP) – Sub-recipient
– Project Manager / Alternate – Carlos Casablanca / Yanfeng Gong
▪ Professor Anjan Bose (Washington State University)
– Technical Advisor
▪ Electric Power Group, LLC
– Principal Investigators – Kevin Chen, Lin Zhang
– Key Project Personnel – Ken Martin, Simon Mo, Tingyang Zhang, Neeraj Nayak, Joshua Chynoweth
© Electric Power Group 2018. All rights reserved 3
|
▪ Billions of dollars on transmission and distribution assets
▪ Key substation assets include transformers, circuit breakers,instrument transformers (CTs, PTs, CCVTs) and IntelligentElectronic Device (Relays, PMU, DFRs)
▪ Synchrophasor measurement systems have been widelyinstalled in the North American power grids over the lastdecade
▪ Data from such assets can be used for asset health monitoringand take proactive steps to prevent equipment failure
▪ Proper functioning of substation assets is critical for powersystem operations, reliability and personnel safety
© Electric Power Group 2018. All rights reserved 4
|
▪ Monitor the status and health of substation equipment
▪ Provide early warning indications for potential malfunctioning equipment
▪ Proactively replacement and repair before equipment is damaged
▪ Reduce utility’s forced outage of equipment
▪ Reduce utility’s operating and maintenance costs
Example of failing CCVT in a substation
Example of CCVT voltage signals at Dominion
© Electric Power Group 2018. All rights reserved 5
|
Data from substation will be provided by utility partners▪
Leverage existing synchrophasor technology▪
Research new algorithms in this project▪
Validate at cost share partner substation locations▪
Adapt for general commercial use at other utilities▪
Central Processing: Data sent from substations to central site▪
© Electric Power Group 2018. All rights reserved 6
Provided by Utility Host Provided by EPG
Individual CT/PT timestamped sample
value or phasor
Three PhaseVoltage and Current
Waveform (1, 2, …, m)
Task 3.3
Relay/PMUPost Processing for list of bad measurement
Substation Model (CIM)
Data Recording
SynchrophasorTask 3.2
Pseudo-Synchrophasor
Task 3.1
Alarming to Identify failing Equipment
Visualization DisplaySLSE Engine
DataNXT
Utility Customized One-line Diagram
Task 3.2
Signal Mapping to Substation Model Substation
Network Model Integration
Synchrophasor Data Gateway
One-Line Diagram Kit
EPG component
To be developed
From utility host
Customized One-Line Diagram Integration
Phasor Converter
|
▪ Local Processing at substations: Results sent to asset monitoring center
© Electric Power Group 2018. All rights reserved 7
Provided by Utility Host Provided by EPG
Physical Box In Substation – Hardened PC
Software in Data Center
Individual CT/PT timestamped sample
value or phasor
Three PhaseVoltage and Current
Waveform (1, 2, …, m)
Phasor Convertor
Relay/PMU
Substation Model (CIM)
Data Recording
Synchrophasor
Visualization DisplaySLSE Engine
Substation DataNXT
Utility Customized One-line Diagram
Signal Mapping to Substation Model Substation
Network Model Integration
Synchrophasor Data Gateway
One-Line Diagram Kit
EPG component
To be developed
From utility host
Customized One-Line Diagram Integration
Data Center DataNXT
Post Processing for list of bad measurement
Alarming to Identify failing Equipment
Post Processing for list of bad measurement
Alarming to Identify failing Equipment
|
# SOPO Tasks and Subtasks Planned Timeline
1.0 Project Management and Planning March – April 2017
2.0 Planning, Research, Design, and Specification April 2017 – March 2019
2.1 Overall Project Management April 2017 – March 2019
2.2 Research and Scoping Study March – June 2017
2.3 Functional Design and Design Specifications March – July 2017
3.0 Development, Testing, and Demonstration July 2017 – August 2018
3.1 Pseudo-Synchrophasor Data July – December 2017
3.2 Field Synchrophasor Data December 2017 – March 2018
3.3 Sampled Data from Instrument Transformers April – August 2018
4.0 Deployment and Demonstration at Host Utility September 2018 – March 2019
4.1 Product Documentation September – October 2018
4.2 Installation and Integration at Host Utility October – November 2018
4.3 Site Acceptance Testing November – December 2018
4.4 Demonstration at Host Utility January – February 2019
4.5 Training February – March 2019
5.0 Marketing and Outreach September 2018 – March 2019
5.1 Market Research September – December 2018
5.2 Commercialization Plan January – March 2019
5.3 Outreach September 2018 – March 2019
8
* Requested 1 year project extension according to new PMU deployment schedule at 765kV Vassell substation
© Electric Power Group 2018. All rights reserved
|© Electric Power Group 2018. All rights reserved9
|© Electric Power Group 2018. All rights reserved 10
Cause of Failure / Failure Modes
CT PT CVT/CCVT
•Loose Connections or Corroded Connections•Shorting of Winding Turns•Turns to Ground Shorting•Open CT secondary•Insulation
•Erosion of insulation, Insulation Failure•Voids in Insulation –Increased moisture content, Partial Discharge – increased dielectric losses•Aging of CT and wiring insulation, Oil Leaks•High Insulation power factor of internal insulation
•Magnetic core saturation
•Ferroresonance•Switching Transients•PT Saturation
•Insulation Failure•High Stress Voltage Difference across some of the windings•Shorting of Adjacent Windings due to insulation failure•Deterioration of Insulations
•Transient Overvoltage's & Lightning surges•Loose Connections
•Failure of one or more capacitor elements in HV stack – Overvoltage and Stress on each capacitor•Failure of one or more capacitor elements in LV grounding stack – decrease in secondary voltage•Failure of intermediate voltage transformer or series reactor – change in phase angle and/or voltage•Failure of Ferroresonance suppression circuit –waveform distortion, changes in phase angle and/or voltage•Multiple element failure can cause explosion –Staff Safety Issues•Failure of filter circuit or spark gaps used for harmonics & transient voltage reduction –causes increased stress on components•External Flashover, failure of other components – expansion membrane, gasket seal•Low oil conditioned due to oil leak – capacitor failure
|
Raw PMU Data•
LSE Data•
Redundant PMUs•
Other Phases•
DFR Data*•
Available Input - Data
Minimal false positive•
Minimal false negative•
Maximize prediction time•
Within Computing •
Constraints
Desired Output – Flag Asset Fail
© Electric Power Group 2018. All rights reserved 11
|© Electric Power Group 2018. All rights reserved12
Data-Driven Statistical
Detection Flag
SLSE Flag
Cross-check AlarmYes
Data-Driven Statistical
Detection Flag
SLSE Flag
Timer Threshold 3
Timer Threshold 1
No
Alert Alert
Timer Threshold 2
Alarm
Timer Threshold 4
Alarm
SLSE and data• -driven statistical
detection flags are cross checked
for consistence
Two different user• -defined timers
are used to track these flags
|© Electric Power Group 2018. All rights reserved13
DataNXT
Asset Monitoring
ServiceSLSE Service
One-Line Diagram Kit
Grafana
InfluxDB
Measurements
|© Electric Power Group 2018. All rights reserved14
|
▪ A typical breaker-and-a-half schema 500 kV substation configuration:– Full observability of current injection and flow
– Breaker currents are as measurement inputs, as well as bus and line voltages
© Electric Power Group 2018. All rights reserved 15
4730
900
902
4598
4724
4588
4586
4731
4728
47324594
V1, I1
V2, I2
V3, I3V4, I4
V5, I5V6, I6
PMU Current Measurement
Breaker Open
Breaker Closed
911910
923
916
919901
|
▪ A 1% noise to the original signal is added as anomaly to the raw measurement V2 voltage magnitude:
© Electric Power Group 2018. All rights reserved 16
Comparison of raw and estimated VM for V2
Substation equipment status alarm:
The alarm points to the PT feeding the voltage signal.
|
▪ Breaker 4598, 4588 and 4728 are open.▪ A 30 degree offset to the original signal is added as anomaly to the raw
measurement V4 voltage angle:
17
Comparison of raw and estimated voltage angles for V4:
Raw voltage magnitude data and its derivative over 5 time increments:
© Electric Power Group 2018. All rights reserved
|© Electric Power Group 2018. All rights reserved18
|
▪ 3 new PMUs deployed at West Campus
▪ 3 PMUs planned at Vassell by Sept 2018
▪ Mainly to get breaker current signals
© Electric Power Group 2018. All rights reserved19
|
Vassell Set • 1: CCVT 8 ScenariosWest Campus Set • 1: CCVT 10 Scenarios
© Electric Power Group 2018. All rights reserved20
|
• Vassell Set 2: CT 20 Scenarios• West Campus Set 2: CT 22 Scenarios
© Electric Power Group 2018. All rights reserved21
|
22
▪ The variance is calculated one phase at a time with 3 moving windows
▪ Main window
▪ Delayed Window
▪ Variance Window – Centered data
▪ Square the centered data
▪ Moving average of Squared data
▪ Moving threshold is obtained based on a scaling factor
© Electric Power Group 2018. All rights reserved
|
23
© Electric Power Group 2018. All rights reserved
|
1C - CCVT 711 - 1 capacitor fails first at 5 s, 2nd capacitor fails after 30sec, in phase A
© Electric Power Group 2018. All rights reserved24
|25 25
4A - Normal Operation, one CT turn-to-turn shortage occurs at 10sec in phase A
© Electric Power Group 2018. All rights reserved
|26 26
11B - A single phase-to-ground bus fault on bus 1 phase A at 10sec, fault duration is 0.06 s, open D1, C1, B1 at t = 10.05s, reclose at t=10.55s.
© Electric Power Group 2018. All rights reserved
|
Control chart is a graph or chart with limit lines. There are basically three kinds of
control lines:
• the upper control limit (UCL),
• the central line, and
• the lower control limit (LCL).
The UCL and LCL are calculated based on a 20σ
1. Identifying the maximum and minimum values in 1-second time window.
2. Calculating 1-second the data change range=maximum- minimum.
3. Comparing the 1-second change range with upper control limit (UCL).
© Electric Power Group 2018. All rights reserved 27
|
1A, graph of voltage data CCVT 711 - 1 capacitor fails (short circuit) in phase A at 10 s
© Electric Power Group 2018. All rights reserved28
|
1C - CCVT 711 - 1 capacitor fails first at 5 s, 2nd capacitor fails after 30sec, in phase A
© Electric Power Group 2018. All rights reserved29
|
30
• Current State Estimator: Estimate the breaker current. In this model, all the nodesand breakers at the same voltage level inside the substation construct a zero-impedance power system, and the measurement function can be established byapplying KCL. For each branch current, it is a function with respect to two breakercurrents if it is a breaker-and-a-half schema. For each breaker current, it is afunction with respect to itself.
• Voltage State Estimator: Estimate the bus voltage from the voltage measurementsat all the nodes comprising this bus. This is essentially a weighted average and isformulated here as a zero-impedance voltage state estimator. The states are thevoltage of each bus, and the measurements are the voltage phasor measurementsat the nodes belonging to the bus.
© Electric Power Group 2018. All rights reserved
|31 31
Voltage Level Separation
500kV 345kV 230kV...
Estimate Current States
Bad Data
Estimate Breaker States
Yes
No
Build the Topology for this
voltage level
Estimate Voltage States
Generate Substation States
Estimate Current States
Bad Data
Estimate Breaker States
No
Build the Topology for this
voltage level
Estimate Voltage States
Estimate Current States
Bad Data
Estimate Breaker States
No
Build the Topology for this
voltage level
Estimate Voltage States
Abandon
Yes
Abandon
Yes
Abandon
Estimate Current States
Estimate Current States
Estimate Current States
...
© Electric Power Group 2018. All rights reserved
|32 32
A substation model of Vassell Substation is created in XML format. The signals of the measurements are also mapped:
Examples of the mapping for different types of measurements are shown below:Voltage:
Breaker Current:
© Electric Power Group 2018. All rights reserved
|
1B, graph of voltage data CCVT 711 - 5 capacitor fails (short circuit) in phase A at 10 s
SLSE successfully detected the anomaly caused by CCVT 711 failure
© Electric Power Group 2018. All rights reserved33
|
1B, CCVT 711 - simulation of temporarily short circuit CCVT secondary at 10 s, (FSC taken out at 0.25 s) clearing around 7 cycles on phase A
SLSE successfully bypassed the anomaly caused by the system fault and did not false alarm for CCVT 711 anomaly
© Electric Power Group 2018. All rights reserved34
|© Electric Power Group 2018. All rights reserved35
|
Normal operation data without equipment failure nor system event• Each voltage and current signal is tested independently• Didn’t have false alarm based on the setting
© Electric Power Group 2018. All rights reserved36
|
Validated the accuracy of the SLSE algorithms:• The SLSE didn’t alarm on any anomalies, which is as expected. • The SLSE results are also very close to and following the variations of the raw signals
3 Phase voltage signals:
© Electric Power Group 2018. All rights reserved37
|© Electric Power Group 2018. All rights reserved38
3 Phase breaker current signals:
|
▪ Working with AEP to establish filed synchrophasor connection to EPG
▪ System integration testing with SLSE and data-driven algorithms
▪ AEP setting up central location VM environment to test on-site
▪ Appreciate if any other utilities can contribute to an equipment failure “data library”
▪ Interested in this project for host demonstration? Still not too late to join!
© Electric Power Group 2018. All rights reserved 39
# SOPO Tasks and Subtasks Planned Timeline
3.0 Development, Testing, and Demonstration July 2017 – August 2018
3.1 Pseudo-Synchrophasor Data July – December 2017
3.2 Field Synchrophasor Data December 2017 – March 2018
3.3 Sampled Data from Instrument Transformers April – August 2018
|
1) NASPI Technical Report, “Diagnosing Equipment Health and Mis-operations with PMU data”,May 2015
2) Bogdan Kasztenny and Ian Stevens, “Monitoring Ageing CCVTs – Practical Solutions withModern Relays to Avoid Catastrophic Failures”, March 2007
3) David Shipp and Thomas Dionise, IEEE Tutorial, “ Switching Transients, Transformer Failures,Practical Solutions”, Feb 2016
4) L. Sevov, J. Cardenas and Y. Sun, "CT Failure Detection For Differential ProtectionApplications," 2008 61st Annual Conference for Protective Relay Engineers, College Station, TX,2008, pp. 498-511. doi:10.1109/CPRE.2008.4515076
5) Deepak Rampersad, “Investigation into current transformer failures within Eskom distribution”,December 2010
6) Darren Spoor and Jian Guo Zhu, Monitoring current transformer secondary circuits to forewarnof catastrophic insulation faults
7) D. Costello, "Open-circuited CT misoperation and investigation," 2014 67th Annual Conferencefor Protective Relay Engineers, College Station, TX, 2014, pp. 383-392,doi:10.1109/CPRE.2014.6799015
© Electric Power Group 2018. All rights reserved40
|© Electric Power Group 2018. All rights reserved41
[1] Transmission & Distribution Committee - IEEE Power & Energy Society, “Electric Signatures of Power Equipment Failures,” 2015.
[2] M. Al Karim, M. Chenine, K. Zhu, and L. Nordstrom, “Synchrophasor-based data mining for power system fault analysis,” IEEE PES
Innov. Smart Grid Technol. Conf. Eur., pp. 1–8, 2012.
[3] H. Jiang, X. Dai, D. W. Gao, J. J. Zhang, Y. Zhang, and E. Muljadi, “Spatial-Temporal Synchrophasor Data Characterization and Analytics in
Smart Grid Fault Detection, Identification, and Impact Causal Analysis,” IEEE Trans. Smart Grid, vol. 7, no. 5, pp. 2525–2536, 2016.
[4] H. Jiang, J. J. Zhang, W. Gao, and Z. Wu, “Fault detection, identification, and location in smart grid based on data-driven computational
methods,” IEEE Trans. Smart Grid, vol. 5, no. 6, pp. 2947–2956, 2014.
[5] J. M. Lim and C. L. Demarco, “Model-free voltage stability assessments via singular value analysis of PMU data,” Proc. IREP Symp. Bulk
Power Syst. Dyn. Control - IX Optim. Secur. Control Emerg. Power Grid, IREP 2013, 2013.
[6] R. Meier et al., “Power system data management and analysis using synchrophasor data,” 2014 IEEE Conf. Technol. Sustain., pp. 225–
231, 2014.
[7] A. Silverstein, “Diagnosing Equipment Health and Mis-operations with PMU Data,” 2015.
[8] Xiaodong Liang and S. A. Wallace, “Processing synchrophasor data using a feature selection procedure,” in 2016 IEEE PES Asia-Pacific
Power and Energy Engineering Conference (APPEEC), 2016, pp. 273–277.
[9] K. D. Jones, A. Pal, and J. S. Thorp, “Methodology for Performing Synchrophasor Data Conditioning and Validation,” IEEE Trans. Power
Syst., vol. 30, no. 3, pp. 1121–1130, 2015.
[10] N. Dahal, R. L. King, and V. Madani, “Online dimension reduction of synchrophasor data,” Proc. IEEE Power Eng. Soc. Transm. Distrib.
Conf., pp. 1–7, 2012.
[11] J. Ning and W. Gao, “Multi-feature extraction for power system disturbances by wavelet transform and fractal analysis,” IEEE PES Gen.
Meet. PES 2010, pp. 1–7, 2010.
[12] J. Patel, “Real time big data mining,” The State University of New Jersey, 2016.
|© Electric Power Group 2018. All rights reserved43
|© Electric Power Group 2018. All rights reserved44
Open Circuit in CT secondary due to Wiring damage
High frequency transients observed 8 minutes before CT failure (partial discharge in insulation)
Normal Operation – No failure Reference: [G]
Reference: [F]
|© Electric Power Group 2018. All rights reserved45
Ferroresonance –
Opening Breaker
Switching
Transients
Loose Connection
at PT feeding the
PMU
Blown fuse on
One Phase of PT
Internal
Primary
Winding Issue
Reference: [A]
Reference: [A]
Reference: [C]
|© Electric Power Group 2018. All rights reserved46
Loose Fuse Connections in CCVT Safety SwitchCapacitor Failure in C phase
A - Phase CCVT Issue
Reference: [A]
Reference: [A]
Reference: [B]
|
Prepare/Smooth Data
Extract Feature
Classify and Quantify Feature
Perform pattern recognition, comparison, etc.
Flag data, record data, execute other
algorithms
Take Action
PMU/LSE Data
No
Yes
1
2
3
4
5
Note: Some algorithms may perform more
than one process in a single step.
© Electric Power Group 2018. All rights reserved 47
|© Electric Power Group 2018. All rights reserved48