Upload
ngokhue
View
215
Download
1
Embed Size (px)
Citation preview
(A) HALF-YEARLY COMPLIANCE OF STIPULATED ENVIRONMENTAL CONDITIONS/ SAFEGUARDS IN THE ENVIRONMENTAL CLEARANCE REF. LETTER NO. SEIAA/HR/2013/1251 DATED 25.11.2013 FOR “COMMERCIAL COLONY” PROJECT IN THE REVENUE ESTATE OF VILLAGE SIHI, SEC-83, GURGAON HARYANA BY M/S INFORMATION TV PVT. LTD
Sl. No. Conditions Status of Compliance
PART A - SPECIFIC CONDITIONS: Construction Phase:-
I “Consent for Establishment” shall be obtained
from Haryana State Pollution Control Board
Under Air and Water act and a copy shall be
submitted to the SEIAA, Haryana before the
start of any construction work at site.
Agreed. “Consent to Establishment” has
been obtained Vide letter no
2821214GUSOCTE569514 Dated
18/02/2014 from the Haryana State
Pollution Control Board under Air and
Water act. Copy of CTE is enclosed as
Annexure –I.
II A first aid room as proposed in the project
report shall be provided in both during
construction and operation phase of the
project.
Agreed. First aid room will be provided
in both during construction and
operation phase of the project.
III Adequate drinking water and sanitary facilities
should be provided for construction workers at
the site. Provision should be made for mobile
toilets. Open defecation by the labors is strictly
prohibited. The safe disposal of waste water
and solid wastes generated during the
construction phase should be ensured.
Agreed. Adequate drinking water and
sanitary facilities will be provided for
construction workers at the site.
Provision will be made for mobile
toilets. The safe disposal of waste water
and solid wastes generated during the
construction phase will be ensured.
IV All the top soil excavated during construction
activities should be stored for use in
horticulture/landscape development within the
project site.
Agreed, Separate stock piles will be
maintain and all the top soil excavated
during construction activities will be
store and utilized in horticulture/
landscape developments within the
project site. The remaining excavated
soil will be utilized in re-filling of
foundation, road works, rising of site
level etc.
V The project proponent shall ensure that the
building material required during construction
phase is properly stored within the project area
and disposal of construction waste should not
create any adverse effect on the neighboring
communities and should be disposed of after
taking necessary precautions for general safety
and health aspects of people, only in approved
sites with the approval of competent authority.
Agreed: The project proponent will
ensure that the building material
required during construction phase is
properly stored within the project area
and disposal of construction waste
should not create any adverse effect on
the neighboring communities and should
be disposed of after taking necessary
precautions for general safety and health
aspects of people, only in approved sites
with the approval of competent
authority.
VI Construction spoils, including bituminous
material and other hazardous materials, must
not be allowed to contaminate watercourses
and the dump sites for such material must be
secured so that they should not leach into the
ground water and any hazardous waste
generated during construction phase, should be
disposed off as per applicable rules and norms
with necessary approval of the Haryana State
Pollution Control Board.
Agreed, Construction spoils including
bituminous material and other hazardous
materials will not allow contaminating
water courses and the dump sites for
such material will be secure so that they
should not leach into the ground water.
Materials are being disposed off as per
applicable rules and norms with
necessary approval of the Haryana State
Pollution Control Board.
VII The diesel generator sets to be used during
construction phase should be ultra-low sulphur
diesel type and should conform to
Environment (Protection) Rules prescribed for
air and noise emission standards.
Agreed. During construction phase DG
sets will be used for office lighting and
site lighting. DG sets will be acoustic
enclosed. It will be running on ultra-low
sulphur diesel only with the provision of
air and noise emission standards as per
EPA Rules, 1986.
Results of the environmental monitoring
carried out at the site are enclosed as
Annexure – II.
VIII The diesel required for operating DG sets shall
be stored in underground tanks and if required,
clearance from Chief Controller of Explosives
shall be taken.
Agreed. The diesel required for
operating DG set will be stored in
HDPE Drums and log books will be
managed adequately.
IX Ambient noise levels should conform to
residential standards both during day and
night. Incremental pollution loads on the
ambient air and noise quality should be within
3month period. Latest Corporate Environment
Policy should be submitted to SEIAA within 3
months of issuance of this letter. Closely
monitored during construction phase.
Adequate measures should be taken to reduce
ambient air and noise level during construction
phase, so as to conform to the stipulated
residential standards.
Agreed, ambient noise levels are
being conformed to standards both
during day and night.
The silent type DG set with acoustic
enclosures will be installed at project
site and office.
Low sulphur fuel will be used
Exhaust will be conforming to the
provisions of Environment
(Protection) Rules prescribed for air
and noise emission standards.
All vehicles entering to the site will be
with valid PUC certificate.
All machinery used at the site will be
new and periodic maintenance of the
machinery insured.
Results of the environmental
monitoring carried out at the site are
enclosed as Annexure – II.
Shelter belt will be provided to reduce
the noise level within the site.
X Fly ash should be used as building material in Agreed, Fly ash based material/
the construction as per the provisions of Fly
Ash Notification of September, 1999 and
amended as on 27th August, 2003
products will be used as per the
provisions of fly ash notification of
September, 1999 and as amended on
27th August, 2003.
XI Storm water control and its re-use as per
CGWB and BIS standards for various
applications should be ensured.
Agreed. Storm water control and its
reuse will be maintained as per Central
Ground Water Board and BIS standards
for various applications.
XII Water demand during construction should be
reduced by use of premixed concrete, curing
agents and other best practices .
Water demand during construction will
be reduced by the practice of using
premixed concrete, curing agents and
other best practices.
XIII In view of severe constrains in water supply
augmentation in the region and sustainability
of water resources, the developer will submit
the NOC from CGWA specifying water
extraction quantities and assurance from
HUDA / utility provider indicating source of
water supply and quantity of water with details
of intended use of water potable and non
potable. Assurance is required for both
construction and operation stages separately. It
shall be submitted to the SEIAA/ R.O. MoEF,
Chandigarh before the start of construction.
Ground water will not be extracted for
the purpose of construction as well as
for operation phase of the project.
Application has been filed to HUDA for
fresh water. Acknowledgement copy of
the same is enclosed as Annexure-III
XIV Roof should meet prescriptive requirement as
per Energy Conservation Building Code by
using appropriate thermal insulation material.
Agreed, Roof will meet the prescriptive
requirement as per Energy Conservation
Building Code by using appropriate
thermal insulation material.
XV Opaque wall should meet prescriptive
requirement as per Energy Conservation
Building Code which is proposed to be
Agreed: Opaque wall will meet
prescriptive requirement as per Energy
Conservation Building Code.
mandatory for all air conditioned spaces while
it is desirable for non-air-conditioned spaces
by use of appropriate thermal insulation
material to fulfill requirement.
XVI The approval of the competent authority shall
be obtained for structural safety of the building
on account of earthquake, adequacy of
firefighting equipments, etc. as per National
Building Code including protection measures
from lightening etc. If any forestland is
involved in the proposed site, clearance under
Forest Conservation Act shall be taken from
the competent Authority.
Agreed, The approval of competent
authority will be taken for structural
safety of the building due to earthquake,
adequacy of firefighting equipments etc.
as per National Building Code including
protection measures from lightening etc.
Project site does not fall in Forest area.
NOC from Divisional Forest Officer is
enclosed as Annexure-IV.
XVII Overexploited groundwater and impending
severe shortage of water supply in the region
requires the developer to redraw the water and
energy conservation plan. Developer shall
reduce the overall footprint of the proposed
development. Project proponent shall
incorporate water efficiency / Saving measures
as well as water reuse/ recycling within 3
months before the start of construction to the
SEIAA Haryana and RO, MOEF, GOI,
Chandigarh.
Agreed, No ground water extraction will
take place. However treated water for
construction will be supplied by HUDA.
To reduce the demand in operation
phase treated water from STP will be
used for horticulture, flushing, cooling,
rest will be used in nearby construction
site. As well as efficient fixture will be
used to minimize the water demand for
domestic purpose.
XVIII The project proponent as stated in proposal
shall construct 04 nos rain water harvesting
pits for recharging the ground water within the
project premises. Rain Water harvesting pits
shall be designed to make provisions for silting
chamber and removal of floating matter before
entering harvesting pit. Maintenance budget
Agreed, 13 rain water harvesting pits
will be provided for recharging the
ground water within the project
premises. To remove silt and floating
matter, desilting chamber will be
proposed with rain water harvesting pits.
Care will be taken that contaminated
and persons responsible for maintenance must
be provided. Care shall also be taken that
contaminated water do not enter any RWH pit.
water will not be entered in any of RWH
pits.
XIX The Project Proponent shall provide for
adequate fire safety measures and equipments
as required by Haryana Fire Service Act, 2009
and instructions issued by the local
Authority/Directorate of fire from time to time.
Further the project proponent shall take
necessary permission regarding fire safety
scheme/NOC from competent authority as
required.
Agreed: The Project Proponent will
provide for adequate fire safety
measures and equipments as required by
Haryana Fire Service Act, 2009 and
instructions issued by the local
Authority/Directorate of fire from time
to time. Further the project proponent
will take necessary permission regarding
fire safety scheme/NOC from competent
authority as required.
XX The project proponent shall obtain assurance
from the DHBVN for supply of 3397 KVA of
power supply before the start of construction.
In no case project will be operational solely on
generators without any power supply from any
external power utility.
Agreed, The project proponent will
obtain assurance from the DHBVN for
supply of 3397 KVA of power supply
before the start of construction. In no
case project will be operational solely
on generators without any power supply
from any external power utility.
XXI Detail calculation of power load and ultimate
power load of the project shall be submitted to
DHBVN under intimation to SEIAA, Haryana
before the start of construction. Provision shall
be made for electrical infrastructure in the
Project area.
Agreed, Detail calculation of power load
and ultimate power load of the project
has been submitted to DHBVN under
intimation to SEIAA, Haryana before
the start of construction. Provision will
be made for electrical infrastructure in
the Project area.
XXII The Project proponent shall not raise any
construction in the natural land depression/
Nallah/ Water course and shall ensure that the
natural flow from the Nallah/ Water course is
Agreed, the project site does not contain
any natural land depression nallah/
water course as well as no natural flow
will be obstructed by the project.
not obstructed.
XXIII The project proponent shall keep the plinth
level of the building blocks sufficiently above
the level of the approach road as per prescribed
bye laws. Levels of the other areas in the
Projects shall also be kept suitably so as to
avoid flooding.
Agreed, The plinth level of the building
block will be above the level of the
approach road as per the prescribed bye
laws. Levels will be suitably
maintained to avoid flooding.
XXIV Construction shall be carried out so that
density of population does not exceed norms
approved by Director General Town and
Country Department Haryana.
Agreed, population density will be as
per the approved building plan by
Director General Town and Country
Department, Haryana.
XXV The Project proponent shall submit an affidavit
with the declaration that ground water will not
be used for construction and only treated water
should be used for construction.
Agreed, Ground water will not be used
for the construction activity. An
affidavit with the declaration that
ground water will not be used for
construction has already been submitted
to SEIAA, Haryana.
XXVI The project proponent shall not cut any
existing tree and project landscaping plan
should be modified to include those trees in
green area.
There is no need to cut the trees, Only
small bushes clearing will be required
for construction activity.
XXVII The project proponent shall ensure that ECBC
norms for composite climate zone are met. In
Particular building envelope, HVAC service
water heating, pumping, lighting and electrical
infrastructure must meet ECBC norms.
Agreed, ECBC norms for composite
climate zone, water heating, pumping,
lighting and electrical infrastructure will
be followed.
XXVIII The project proponent shall provide 3m high
barricade around the project area, dust screen
for every floor above the ground, proper
sprinkling and covering of stored material to
restrict dust and air pollution during
Agreed: The project proponent will
provide 3m high barricade around the
project area, dust screen for every floor
above the ground, proper sprinkling and
covering of stored material to restrict
construction. dust and air pollution during
construction.
XXIX The project proponent shall construct a
sedimentation basin in the lower level of the
project site to trap pollutant and other wastes
during rains.
Agreed: The project proponent will
construct a sedimentation basin in the
lower level of the project site to trap
pollutant and other wastes during rains.
XXX The project proponent shall provide proper
Rasta of proper width and proper strength for
each project before the start of construction.
Agreed: The project proponent will
provide proper Rasta of proper width
and proper strength for each project
before the start of construction.
XXXI The project proponent shall ensure that the U-
value of the glass is less than 3.177 and
maximum solar heat gain co-efficient is 0.25
for vertical fenestration.
Agreed: The project proponent shall
ensure that the U-value of the glass is
less than 3.177 and maximum solar heat
gain co-efficient is 0.25 for vertical
fenestration.
XXXII The project proponent shall adequately control
construction dusts like silica dust, non-silica
dust, wood dust. Such dusts shall not spread
outside project premises. Project Proponent
shall provide respiratory protective equipment
to all construction workers.
Agreed: The project proponent will
adequately control construction dusts
like silica dust, non-silica dust, and
wood dust. Such dusts will not spread
outside project premises. Project
Proponent will provide respiratory
protective equipment to all construction
workers.
XXXIII The project proponent shall provide one refuse
area till 24 meter as per National Building
Code.
Agreed, one refuse area till 24 meter as
per National Building Code will be
provided.
XXXIV The project proponent shall provide fire
control room and fire officers for building
above 30 meter as per national building Code.
Agreed: The project proponent will
provide fire control room and fire
officers for building above 30 meter as
per national building Code.
XXXV The project proponent shall obtain permission Agreed, Permission from Mines and
of Mines and Geology Department for
excavation of soil before the start of
construction.
Geology Department for excavation of
soil will be obtained for construction.
XXXVI The project proponent shall seek specific prior
approval from concerned local
Authority/HUDA regarding provision of storm
drainage and sewerage system including their
integration with external services of HUDA/
Local authorities beside other required services
before taking up any construction activity.
Agreed: The project proponent will seek
specific prior approval from concerned
local Authority/HUDA regarding
provision of storm drainage and
sewerage system including their
integration with external services of
HUDA/ Local authorities beside other
required services before taking up any
construction activity.
XXXV
III
The site for solid waste management plant be
earmarked on the layout plan and the detailed
project for setting up the solid waste
management plant shall be submitted to the
Authority within one month.
Agreed: The site for solid waste
management plant is earmarked on the
layout plan.
XXXVI
III
Vertical fenestration shall not exceed 40% of
total wall area.
Agreed: Vertical fenestration will not be
exceeding 40% of total wall area.
XXXIX The project proponent shall discharge excess
of treated waste water/storm water in the
public drainage system and shall seek
permission of HUDA before the start of
construction.
Agreed: The project proponent will
discharge excess of treated waste
water/storm water in the public drainage
system and shall seek permission of
HUDA before the start of construction.
XXXX The project proponent shall revise the water
calculation for service apartments @135 lpcd
instead of @111 lpcd and shall also submit
revised water balance diagram before the start
of construction. Sewerage and STP capacity
shall also be revised accordingly.
Agreed: The project proponent has
revised the water calculation for service
apartments and already submitted to the
SEIAA.
PART A- SPECIFIC CONDITIONS : Operation Phase
a “Consent to operate” shall be obtained from
Haryana State Pollution Control Board under
Air and Water Act and a copy shall be
submitted to the SEIAA, Haryana.
Agreed: “Consent to operate” will be
obtained from Haryana State Pollution
Control Board under Air and Water Act
and a copy shall be submitted to the
SEIAA, Haryana.
b The Sewage Treatment Plant (STP) shall be
installed for the treatment of the sewage to the
prescribed standards including odour and
treated effluent will be recycled to achieve
zero exit discharge. The installation of STP
should be certified by an independent expert
and a report in this regard should be submitted
to the SEIAA, Haryana before the project is
commissioned for operation. Tertiary
treatment of waste water is mandatory.
Discharge of treated sewage shall conform to
the norms and standards of HSPCB,
Panchkula. Project proponent shall implement
such STP technology which does not require
filter backwash.
Agreed, The Sewage Treatment Plant
(STP) will be installed for the treatment
of the sewage to be prescribed standards
including odour and treated effluent will
be recycled and used for flushing,
cooling, and rest will be used in nearby
construction site. Report of installation
of STP has been submitted to the
SEIAA, Haryana before the project is
commissioned for operation.
c Separation of the grey and black water should
be done by the use of dual plumbing line.
Treatment of 100% grey water by
decentralized treatment should be done
ensuring that the recirculated water should
have BOD maximum upto 10 mg/litre and the
recycled water will be used for flushing,
gardening and DG set cooling etc.
Agreed, Grey and black water will be
separated by the use of dual plumbing
line. Agreed, recycled water will be used
for flushing, gardening, cooling and rest
will be used for nearby construction site.
water balance diagram is enclosed as
Annexure- V
d For disinfection of the treated waste water
ultra violet radiation or ozonization process
Agreed, for disinfection of the treated
waste water ultra violet radiation process
should be used. will be used.
e Diesel Power generating sets proposed as
source of backup power for lifts, common area
illumination and for domestic use should be of
enclosed type and conform to rules made
under the Environment (Protection) Act, 1986.
The location of the DG sets should be in the
basement as promised by the project
proponent with appropriate stack height i.e.
above the roof level as per the CPCB norms.
The diesel used for DG sets should be of ultra
low sulphur diesel (0.05% sulphur), instead of
low sulphur diesel.
Agreed. DG set will be acoustic
enclosed & conform to rules made under
the Environment (Protection) Act, 1986.
The diesel used for DG sets will be of
ultra-low sulphur contents (maximum up
to 0.05%).
f Ambient Noise Level should be controlled to
ensure that it does not exceed the prescribed
standards both within and at the boundary of
the proposed commercial complex.
Agreed. The Ambient noise level will be
controlled such that it will not exceed
the prescribed standards both within and
at the boundary of the project.
g The project proponent as stated in the proposal
shall maintain at least 31.67% as green cover
area for tree plantation especially all around
the periphery of the project and on the road
sides preferably with local species which can
provide protection against noise and
suspended particulates matter. The open
spaces inside the project should be preferably
landscaped and covered with vegetation/grass,
Herbs& shrubs Only local available plant
species shall be used.
Agreed. The project proponent will
maintaining at least 20% as green cover
area for tree plantation especially all
around the periphery of the project and
on the road sides preferably with local
species so as to provide protection
against particulates and noise. The open
spaces inside the plot will be preferably
landscape and covered with
vegetation/glass. Landscape Plan is
attached as Annexure-.VI
h The project proponent shall strive to
minimize water in irrigation of landscape by
minimizing grass area, using native variety,
Agreed. To reduce the fresh water
demand for landscaping treated water
from STP will be used. Xeriscaping and
xeriscaping and mulching, utilizing efficient
irrigation system, scheduling irrigation only
after checking evapotranspiration data.
mulching technology will be adopted to
reduce the landscaping demand. .
i Rain water harvesting for roof runoff and
surface runoff, as per plan submitted should be
implemented. Before recharging the surface
runoff, pretreatment through sedimentation
tanks must be done to remove suspended
matter, oil and grease. The bore well for rain
water recharging shall be kept at least 5 m
above the highest ground water table. Care
shall be taken that contaminated water do not
enter any RWH pit. The project proponent
shall avoid rain water harvesting of first 10
minutes of rain fall. Roof top of the building
shall be without any toxic material or paint
which can contaminate rain water. Wire mess
and filters should be used wherever required.
Rainwater harvesting as per plan for roof
run-off and surface run-off will be
implemented. Suspended matter, oil and
grease will be removed by treatment
before recharging with surface run-off.
The bore well for recharge will be kept
at least 5 mts. above the highest ground
water table. Rain water Harvesting Plan
is enclosed as Annexure- VII
j The ground water level and its quality should
be monitored regularly in consultation with
Central Ground Water Authority.
Agreed. If required ground water level
and its quality will be monitored
regularly in consultation with Central
Ground Water Authority.
k There should be no traffic congestion near the
entry and exist points from the roads adjoining
the proposed project site. Parking should be
fully internalized and no public space should
be utilized.
Agreed. Parking will be completely
internalized and no public space will be
utilized. Care will be taken to ensure that
there will be no traffic congestion at the
entry and exit points.
l A report on the energy conservation measures
conforming to energy conservation norms
finalize by Bureau of Energy Efficiency
should be prepared incorporating details about
Report on energy conservation measure
conforming to energy conservation
norms finalized by BEE which will
include details of building materials and
building materials & technology; R & U
factors etc. and submit to the SEIAA, Haryana
in three months time.
technology, R & U factors etc has been
submitted to the SEIAA, Haryana within
three months time.
m Energy conservation measures like installation
of LED for lighting the areas outside the
building should be integral part of the project
design and should be in place before project
commissioning. Use of solar panels must be
adapted to the maximum energy conservation.
Agreed. CFL light will be used in
common areas like lift, corridors, and
staircase and service areas. CFLs will be
properly collected and disposed off/sent
for recycling as per the prevailing
guidelines/rules of the regulatory
authority to avoid mercury
contamination. Use of solar panels will
be adapted to the maximum extent
possible for energy conservation.
n The project proponent shall use zero ozone
depleting potential material in insulation,
refrigeration, air-conditioning and adhesive.
Project proponent shall also provide halon free
fire suppression system
Agreed: The project proponent will use
zero ozone depleting potential material
in insulation, refrigeration, air-
conditioning and adhesive. Project
proponent will also provide halon free
fire suppression system
o The solid waste generated should be properly
collected and segregated as per the
requirement of the MSW Rules, 2000 and as
amended from time to time. The bio-
degradable waste should be treated by
appropriate technology at the site ear-marked
within the project area and dry/inert solid
waste should be disposed off to the approved
sites for land filling after recovering recyclable
material.
Agreed: The solid waste generated will
be properly collected and segregated as
per the requirement of the MSW Rules,
2000 and as amended from time to time.
The bio-degradable waste should be
treated by appropriate technology at the
site ear-marked within the project area
and dry/inert solid waste should be
disposed off to the approved. Solid
waste management plan is enclosed as
Annexure-VIII
p The provision of the solar water heating Agreed. Provision of the solar water
system shall be as per norms specified by
HAREDA and shall be made operational in
each building block.
heating system will be as per norms
specified by HAREDA and will be made
operational in open spaces and signages.
q The traffic plan and the parking plan proposed
by the PP should be adhered to meticulously
with further scope of additional parking for
future requirement. There should be no traffic
congestion near the entry and exit points from
the roads adjoining the proposed project site.
Parking should be fully internalized and no
public space should be used.
Agreed. The traffic plan and the parking
plan will be adhered with further scope
of additional parking for future
requirement. Parking will be fully
internalized and no public space will be
used. Traffic circulation plan is
enclosed as Annexure-IX.
r The project shall be operationalized only once
HUDA will provide domestic water supply
system in the area.
Agreed, Project will be operationalized
once HUDA will provide domestic water
supply system in the area.
s Operation and maintenance of STP, solid
waste management and electrical
infrastructure pollution control measures shall
be ensured even after the completion of sale.
Operation and maintenance of STP,
solid waste management and electrical
infrastructure will be maintained by the
Environment Management Cell.
t Different type of wastes should be disposed
off as per provisions of municipal solid waste,
biomedical waste, hazardous waste, e waste,
batteries & plastic rules made under
Environment Protection Act, 1986.particularly
E-waste and battery waste shall be disposed of
as per existing E-waste Management rules
2011 and batteries Management rules 2001.
The project proponent should maintain a
collection center for E-waste and it should be
disposed of to only registered and authorized
dismantler/ recycler.
Agreed: Different type of wastes will be
disposed off as per provisions of
municipal solid waste, biomedical waste,
hazardous waste, e waste, batteries &
plastic rules made under Environment
Protection Act, 1986particularly E-waste
and battery waste will be disposed of as
per existing E-waste Management rules
2011 and batteries Management rules
2001. The project proponent will
maintain a collection Centre for E-waste
and it should be disposed of to only
registered and authorized dismantler/
recycler. Soild waste management plan
has been enclosed as Annexure-VIII
U. Standards for discharge of environment
pollutants as enshrined in various schedule of
rule 3 of Environment Protection Rule 1986
shall be strictly complied with.
Agreed, all the required standard
discharge will be followed for discharge
of environment pollutants as enshrined
in various schedule of rule 3 of
Environment Protection Rule 1986.
v The project proponent shall make provision
for guard pond and other provision for safety
against failure in the operation of wastewater
treatment facilities. The project proponent
shall also identify acceptable outfall for treated
effluents.
Agreed: The project proponent will
make provision for guard pond and other
provision for safety against failure in the
operation of wastewater treatment
facilities. The project proponent shall
also identify acceptable outfall for
treated effluents.
w. The project proponent shall ensure that the
stack height of DG sets is as per the CPCB
prescribed limits. Noise and emission level of
DG sets greater than 800KVA shall be as per
CPCB latestet standards for high capacity DG
sets.
Agreed: The project proponent will
ensure that the stack height of DG sets
is as per the CPCB prescribed limits.
Noise and emission level of DG sets
greater than 800KVA shall be as per
CPCB latest standards for high capacity
DG sets.
x All electric supply exceeding 100amp, 3 phase
shall maintain the power factor between 0.98
lag to 1 at the point of connection
Agreed: All electric supply exceeding
100amp, 3 phase will maintain the
power factor between 0.98 lag to 1 at the
point of connection
y The project proponent shall minimize heat
island effect through shading and reflective or
pervious surface instead of hard surface.
Agreed: The project proponent will
minimize heat island effect through
shading and reflective or pervious
surface instead of hard surface.
z The project proponent shall use only treated
water instead of fresh water for HVAC and
Agreed:
DG cooling. The project proponent shall also
use evaporative cooling technology and
double stage cooling system for HVAC in
order to reduce water consumption . further
temperature, relative humidity during summer
and winter seasons should be kept at optimal
level. Variable speed drive, best C0-efficient
of Performance, as well as optimal integrated
point load value and minimum outside fresh
air supply may be resorted for conservation of
power and water. Coil type cooling Dg Sets
shall be used for saving cooling water
consumption for water cooled Dg sets.
aa The project proponent shall ensure that the
transformer is constructed with high quality
grain oriented, low loss silicon steel and virgin
electrolyte grade copper.
The project proponent shall obtain
manufacturer’s certificate also for that.
Agreed: The project proponent will
ensure that the transformer is
constructed with high quality grain
oriented, low loss silicon steel and virgin
electrolyte grade copper.
The project proponent shall obtain
manufacturer’s certificate also for that.
ab Water supply shall be metered among different
users of utilities.
Agreed: Water supply will be metered
among different users of utilities.
ac The project proponent shall ensure that exit
velocity from the stack should be sufficiently
high. Stack shall be designed in such a way
that there is no stack down-water under any
meteorological conditions.
Agreed: The project proponent will
ensure that exit velocity from the stack
should be sufficiently high. Stack will be
designed in such a way that there is no
stack down-water under any
meteorological conditions.
ad The project proponent shall provide water
sprinkling system in the project area to
suppress the dust in addition to the already
Agreed: The project proponent will
provide water sprinkling system in the
project area to suppress the dust in
suggested mitigation measures in the Air
Environment Chapter of EMP
addition to the already suggested
mitigation measures in the Air
Environment Chapter of EMP.
Environment management Plan is
enclosed as Annexure-X.
PART-B GENERAL CONDITIONS
I The Project proponent shall ensure the
commitments made in Form-1, Form-1A,
EIA/EMP and other documents submitted to
the SEIAA for the protection of environment
and proposed environmental safeguards are
complied with in letter and spirit. In case of
contradiction between two or more documents
on any points, the most environmentally
friendly commitment on the point shall be
taken as commitment by project proponent.
Agreed: All safeguards mentioned in the
application will be implemented during
the construction phase and will be
implemented to the maximum possible
extent.
II Six monthly compliance reports should be
submitted to the Haryana State Pollution
Control Board and Regional Office, MOEF,
GOI, Northern Region, Chandigarh and a copy
to the SEIAA, Haryana
Agreed. Six monthly compliance reports
is being submitted to Haryana State
Pollution Control Board and Regional
Office, MOEF, GOI, Northern Region,
Chandigarh and a copy to the Regulatory
Authority of Haryana.
II STP outlet after stabilization and stack
emission shall be monitored monthly. Other
environmental parameters and green belt shall
be monitored on quarterly basis. After every
3(three) months, the project proponent shall
conduct environmental audit and shall take
corrective measures, if required, without any
delay.
Agreed: STP outlet after stabilization
and stack emission shall be monitored
monthly. Other environmental
parameters and green belt shall be
monitored on quarterly basis. After
every 3(three) months, the project
proponent shall conduct environmental
audit and shall take corrective measures,
if required, without any delay.
IV The SEIAA, Haryana reserves the right to add
additional safeguard measure subsequently, if
found necessary. Environmental Clearance
granted will be revoked if it is found that false
information has been given for getting
approval of this project. SEIAA reserves the
right to revoke the clearance if conditions
stipulated are not implemented to the 10
satisfaction of SEIAA/MoEF.
Agreed, The SEIAA Haryana reserves
the right to add additional safeguard
measure subsequently, if found
necessary.
V The Project proponent shall not violate any
judicial orders/ pronouncements issued by any
Court/Tribunal.
Agreed: There will be no violation of
any judicial order/ pronouncements
issued by the Hon’ble Supreme
Court/High Courts.
VI All other statutory clearances such as the
approvals for storage of diesel from Chief
Controller of Explosives, Fire Department,
Civil Aviation Department, Forest
Conservation Act, 1980 and Wildlife
(Protection) Act, 1972, PLPA, 1900, Forest
Act, 1927 etc. shall be obtained, as applicable
by project proponents from the respective
authorities prior to construction of the project
Agreed, all the required applicable
clearance will be taken from the
respective authority.
VII The project proponent should inform the
public that the project has been accorded
Environment Clearance by the SEIAA and
copies of the clearance letter are available with
the Haryana State Pollution Control Board &
SEIAA. This should be advertised within 7
days from the date of issue of the clearance
letter at least in two local newspaper that are
Agreed:
widely circulated in the region and the copy of
the same should be forwarded to SEIAA,
Haryana. A copy of Environment Clearance
conditions shall also be put on project
proponent web site for public awareness.
VIII Under the provision of Environment
(Protection) Act, 1986 legal action shall be
initiated against the project proponent if it was
found that construction of the project has been
started before obtaining prior environment
clearance.
Agreed, already environment clearance
vide letter no. SEIAA/HR/2012/492 has
been obtained. Copy of the same is
attached as Annexure-XI.
IX Any appeal against this Environment
Clearance shall lie with the National Green
Tribunal, if preferred, within a period of 30
days as prescribed under Section 16 of the
National Green Tribunal Act, 2010.
Not applicable.
X The project proponent shall put in place
Corporate Environment Policy as mentioned
in MoEF, GOI OM No. J-11013/41/2006-IA II
(I) dated 26.4.2012 within 3 month periods.
Latest Corporate Environment Policy should
be submitted to SEIAA within 3months of
issuance of this letter.
Agreed, Corporate Environment Responsibility as mentioned in MOEF, GOI OM No. J-11013/41/2006-IA II (I) dated 26.4.2012 will be justified.
That the safe and hygienic working
conditions will provide for the workers
during construction.
That the drinking water and sanitary
facilities of the type of mobile sulabh
shauchalayas has been provided during
construction phase.
First aid facilities will be maintained at
readily accessible place where necessary
appliances including sterilized cotton,
wool, etc. have been available.
Routine inspection, cleaning and
maintenance of the site will be occurred.
The corporate social responsibility is
enclosed as Annexure-XI
XI The fund ear marked for environment
protection measures should be kept in separate
account and should not be diverted for other
purposes and year wise expenditure shall be
reported to the SEIAA/ RO MoEF GoI under
rules prescribed for Environment Audit.
Agreed, The fund earmarked for
environment protection measures will be
kept in separate account and will not be
diverted for other purposes and year
wise expenditure will be reported to the
SEIAA/ RO MoEF GoI under rules
prescribed for Environment Audit.
XII The project proponent shall ensure the
compliance of Forest Department, Haryana
Notification no. S.O.121/PA2/1900/S.4/97
dated 28.11.1997.
Agreed: The project proponent will
ensure the compliance of Forest
Department, Haryana Notification no.
S.O.121/PA2/1900/S.4/97 dated
28.11.1997.
XIII The project proponent shall ensure that no
vehicle during construction/operation phase
enter the project premises without valid
‘Pollution Under Control’ certificate from
competent Authority.
Agreed: The project proponent will
ensure that no vehicle during
construction/operation phase enter the
project premises without valid ‘Pollution
Under Control’ certificate from
competent Authority.
XIV The project proponent shall seek prior
clearance from the forest department for
access to the commercial complex from
Highway.
Agreed: The project proponent will seek
prior clearance from the forest
department for access to the commercial
complex from Highway.
XV The project proponent is responsible for
compliance of all conditions on Environmental
Clearance letter and project proponent cannot
absolve himself/herself of the responsibility by
shifting it to any contractor engaged by project
Agreed: The project proponent is
responsible for compliance of all
conditions on Environmental Clearance
letter and project proponent cannot
absolve himself/herself of the
proponent. responsibility by shifting it to any
contractor engaged by project proponent.
XVI The project proponent shall seek fresh
Environmental clearance if at any stage there
is change in the planning of the proposed
project.
Agreed: The project proponent will seek
fresh Environmental clearance if at any
stage there is change in the planning of
the project.
XVII Besides the developer/applicant, the
responsibility to ensure the compliance of
Environmental Safeguards/ conditions
imposed in the Environmental Clearance letter
shall also lie on the licensee/licenses in whose
name/names the license/CLU has been granted
by the Town & Country Planning Department,
Haryana.
Agreed: Besides the developer/applicant,
the responsibility to ensure the
compliance of Environmental
Safeguards/ conditions imposed in the
Environmental Clearance letter shall
also lie on the licensee/licenses in whose
name/names the license/CLU has been
granted by the Town & Country
Planning Department, Haryana.
(B) COMPLIANCE TO ENVIRONMENTAL IMPACT ASSESSMENT GUIDANCE MANUAL 2010 OF MoEF
S. No. Points as per EIA Guidance Manual Status of Compliance
A. Air Environment
1. Wind erosion is a serious problem in areas
where the ground is virtually bare and devoid
of vegetation. Vegetation methods are found to
be most effective in the form of windbreaks
and shelterbelts.
Windbreaks and shelterbelts will be
provided to reduce wind erosion during
the construction phase.
2. Sprinkling of water and fine spray from
nozzles to suppress the dust.
Water sprinkling will be provided during
the construction phase.
S. No. Points as per EIA Guidance Manual Status of Compliance
3. On-Road-Inspection should be done for black
smoke generating machinery.
All the machineries will be use at site
having highest standard and of reputed
make and will comply with emission &
noise standards.
4. Promotion of use of cleaner fuel should be
done.
Ultra low sulphur diesel (ULSD) (sulphur
content less than 0.05%) will be used for
running of DG sets, vehicles and
construction machineries.
5. All DG sets should comply emission norms
notified by MoEF.
The DG sets will be installed such a way
that it will comply with the emission
norms notified by MoEF.
6. Vehicles having pollution under control
certificate may be allowed to ply.
It is ensured that all the vehicles used for
construction activities will have valid
Pollution under Check (PUC) certificates.
The vehicles without valid Pollution under
Check (PUC) certificate will be permit at
project site.
7. Use of covering sheet to prevent dust
dispersion at buildings and infrastructure sites,
which are being constructed.
Covering sheet will be use to prevent dust
dispersion during the construction phase.
8. Use of covering sheets should be done for
trucks to prevent dust dispersion from the
trucks, implemented by district offices.
Covering sheets will be used on trucks to
prevent dust dispersion from the trucks.
9. Paving is a more permanent solution to dust
control, suitable for longer duration projects.
High cost is the major drawback to paving.
During construction, access roads will be
covered with gravels to prevent dust
emission.
S. No. Points as per EIA Guidance Manual Status of Compliance
10. Reducing the speed of a vehicle to 20 kmph
can reduce emissions by a large extent. Speed
bumps are commonly used to ensure speed
reduction. In cases where speed reduction
cannot effectively reduce fugitive dust, it may
be necessary to divert traffic to nearby paved
areas.
Speed of the vehicles will be restricted by
erecting speed bumps at regular intervals
at project site and proper signage will be
provided for guided vehicular movement
and speed restrictions.
11. Material storages/ warehouses-Care should be
taken to keep all material storages adequately
covered and contained so that they are not
exposed to situations where winds on site
could lead to dust/ particulate emissions.
Fabrics and plastics for covering piles of soils
and debris is an effective means to reduce
fugitive dust.
Construction material will be stored in
storage yard.
B. Noise Environment
Setting up the barriers: National Building Code
2005 suggests that design solutions such as
barrier blocks should be used to reduce
external LA10 noise levels to at least 60-
70dB(A) at any point 1.0 m from any inward
looking façade.
The site will be enclosed with barricade
wall around the project boundary.
The DG will be installed within factory
made acoustic enclosure which conforms
to the permissible noise standards notified
by MOEF.
C. Water Environment
1. Curing water should be sprayed on concrete
structures; free flow of water should not be
allowed for curing.
STP treated water will be sprayed on
concrete structures.
S. No. Points as per EIA Guidance Manual Status of Compliance
2. After liberal curing on the first day, all
concrete structures should be painted with
curing chemical to save water. This will stop
daily water curing hence save water.
STP treated water will be used for curing.
3. Concrete structures should be covered with
thick cloth/gunny bags and then water should
be sprayed on them. This would avoid water
rebound and will ensure sustained and
complete curing.
Water will be sprayed on concrete
structures which will be covered with
thick cloth/gunny bags.
4. Ponds should be made using cement and sand
mortar to avoid water flowing away from the
flat surface while curing
Ponds will be made using cement and
sand mortar to avoid water flowing away
from the flat surface while curing.
5. Water ponding should be done on all sunken
slabs; this would also highlight the importance
of having an impervious formwork.
Agreed. Water ponding will be done on
all sunken slabs; this would also highlight
the importance of having an impervious
formwork.
(C) COMPLIANCE TO NGT ORDER DATED 10.04.2015 RELATED TO
CONSTRUCTION
S. No. NGT Order dated 10.04.2015 Status of Compliance
1. Every builder or owner shall put tarpaulin on
scaffolding around the area of construction and
the building. No person including builder,
owner can be permitted to store any
construction material particularly sand on any
part of the street, roads in any colony.
Tarpaulin covers will be provided around
the area of construction, wherever
required. No construction materials such
as cement, sand and aggregates will be
stored at site.
S. No. NGT Order dated 10.04.2015 Status of Compliance
2. The construction material of any kind that is
stored in the site will be fully covered in all
respects so that it does not disperse in the Air
in any form.
Construction material on site will be fully
covered.
3. All the construction material and debris shall
be carried in the trucks or other vehicles which
are fully covered and protected so as to ensure
that the construction debris or the construction
material does not get dispersed into the air or
atmosphere, in any form whatsoever.
The trucks carrying construction materials
and debris will be suitably covered by
tarpaulin and plastic sheets.
4. The dust emissions from the construction site
should be completely controlled and all
precautions taken in that behalf.
All necessary precautions will be adopted
to control the dust emissions. Water
sprinkling at site has been done.
5. The vehicles carrying construction material
and construction debris of any kind should be
cleaned before it is permitted to ply on the road
after unloading of such material.
Vehicles carrying construction material
and construction debris will be cleaned
before it will be permitted to ply on the
road after unloading of such material.
6. Every worker working on the construction site
and involved in loading, unloading and
carriage of construction material and
construction debris shall be provided with
mask to prevent inhalation of dust particles.
All safety measures will be taken.
7. Every owner and or builder shall be under
obligation to provide all medical help,
investigation and treatment to the workers
involved in the construction of building and
carry of construction material and debris
relatable to dust emission.
First aid facility will be provided at the
construction site.
S. No. NGT Order dated 10.04.2015 Status of Compliance
8. It shall be the responsibility of every builder to
transport construction material and debris
waste to construction site, dumping site or any
other place in accordance with rules and in
terms of this order.
Construction material and debris waste
will be disposed off to construction site,
dumping site or any other place in
accordance with rules and in terms of this
order.
9. All to take appropriate measures and to ensure
that the terms and conditions of the earlier
order and these orders should strictly comply
with by fixing sprinklers, creations of green air
barriers.
Regular sprinkling of water will be carried
out at site.
10. Compulsory use of wet jet in grinding and
stone cutting.
Wet jet in grinding and stone cutting will
be used.
11. Wind breaking walls around construction site. Wind breaking walls will be provided
around the construction site.
12. All the builders who are building commercial,
residential complexes which are covered under
the EIA Notification of 2006 shall provide
green belt around the building that they
construct. All Authorities shall ensure that such
green belts are in existence prior to issuance of
occupancy certificate.
Green area will be developed as per
approved building plan.