Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Building Trust. Engineering Success.
Vertical Lined Barrier System: Case Study: Four Hills Landfill
Presented by Ryan L. Clay, E.I.T.
Senior Project Engineer
Sanborn, Head & Associates, Inc.
1
Presentation Outline
1. History of vertical lined barriers
2. Case Study: Four Hills Landfill a. The dilemma
b. Initial solution
c. Constructability issues
d. Diagnosing the problem
e. Designing new solution
f. Constructing the barrier
3. Questions
2
History: what and why?
http://www.dewindonepasstrenching.com/wp-content/uploads/2012/06/HDPE_Barrier_Walls.jpg
3
http://www.ce.utexas.edu/prof/zornberg/pdfs/BC/Zornberg_Christopher_2007.pdf
4
Uses at Landfills
http://www.ce.utexas.edu/prof/zornberg/pdfs/BC/Zornberg_Christopher_2007.pdf
5
Bristol Landfill in Bristol, Virginia - The first abandoned open-pit quarry excavation to be lined and backfilled with municipal solid waste.
http://geosyntheticsmagazine.com/articles/0410_f1_backfill.html
6
http://www.tensarinternational.com/Applications/Landfill-Construction/Landfill-Liner-Support#
7
Case Study – Nashua, NH
8
YOU
ARE
HERE
Four Hills Landfill – Nashua, NH
9
Closed Unlined Landfill
Closed Unlined
C&D Landfill
Active Lined
Landfill
LFGTE Facility operated by
PPL Renewable Energy Compost
Facility
10
The dilemma
Landfill was designed/constructed with liner system extending within a 500-foot setback to structures not owned by the City.
City sought a waiver but was denied.
Cannot place any MSW within 500-foot setback.
Plan needed to optimize airspace.
11
Airspace
12
Separation
13
Initial Solution
14
Discovered Problem
15
Investigation
16
Lateral deviation
17
http://www.bloggs74.com/artwork/food-art/
18
Now what?
What’s done is done. City decides it’s not cost effective to recover lost airspace.
How do we move forward?
Can we get back on track?
Goal = Limit future loss of airspace.
Need a new plan.
19
20
Maybe there’s another way
City expresses frustration with constructing the soil wall.
City suggests a retaining wall.
New design must be:
a) Hydraulic barrier;
b) Equal to or less expensive than constructing soil wall; and
c) Safe and simple to construct.
21
Building Blocks
22
Cheap
Interlocking
Easy to transport
Design
23
NON-WOVEN GEOTEXTILE
NON-WOVEN GEOTEXTILE
SMOOTH HDPE GEOMEMBRANE
Profile
24
25
26
Stability – Scenario 1
27
Stability – Scenario 2
28
Design Recommendation
29
Construction
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
Questions?
Thank you!
Ryan L Clay, E.I.T
Senior Project Engineer
Sanborn, Head & Associates, Inc.
52